Part 6 - Superstrructure (Excluding Roofs)
Part 6 - Superstrructure (Excluding Roofs)
On
13/02/2013
Part 6
Superstructure (excluding roofs)
6.5 Steelwork
6.6 Staircases
Chapter 6.1
6.1
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
CONTENTS
Thermal insulation M9 8
Cladding materials M10 8
Movement joints M11 9
SITEWORK
Sitework standards S1 9
Construction S2 9
Stone masonry S3 11
Damp-proof courses and cavity trays S4 11
Wall ties S5 12
Lintels S6 13
Thermal insulation S7 14
Rendering S8 14
Cold weather working S9 15
Handling and protection S10 15
6.1
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
6.1
proprietary equivalent, at maximum
(b) lateral restraint provided by concrete 300mm intervals. Movement joints are not normally
floors necessary to the inner leaf of cavity walls
Concrete floors, with a minimum 90mm (g) movement joints but consideration should be given to
bearing onto the wall, provide adequate Movement joints should be provided, providing:
restraint. where necessary, and in such a way that • movement joints in rooms with straight
stability is maintained. If no provision unbroken lengths of wall over 6m. This is
Concrete floors running parallel to and is made for both initial and long term unnecessary for fired clay bricks
not built into walls require restraint straps movements, masonry walls may crack. • bed joint reinforcement as an alternative
to provide restraint to the wall (reference to movement joints in areas of risk, eg
should also be made to Chapter 6.4 Vertical movement joints should be
under window openings.
‘Timber and concrete upper floors’ (each provided in the outer leaf to minimise the
section)). risk of major cracking, as shown in the To reduce cracking and to maintain the
following table: level of thermal resistance:
(c) lateral restraint provided by timber • bricks and blocks, or blocks of different
floors Material Joint Normal spacing densities, in a wall should not be mixed
Timber joisted floors can provide adequate width • a joint should be formed where
restraint when joists are carried by (mm) dissimilar materials abut
ordinary hangers to BS EN 845 and Clay brick 16 12m (15m maximum) • the joint should be tied (eg with
connected to the wall with restraint straps. expanded metal in the bed joint) unless
Calcium 10 7.5 to 9m
In buildings of not more than two storeys, silicate the joint is to act as a movement joint.
timber joisted floors can provide adequate brick
Where cracking is likely, walls should be
restraint without strapping when: Concrete 10 6m dry lined or clad (reference should also be
• the minimum bearing onto masonry block and made to Sitework clause 6.1 - S2(g)).
is 90mm (or 75mm onto a timber wall brick
plate), or Any 10 half the above (h) calcium silicate brickwork
• joists are carried by restraint type masonry in spacings and 1.5m Design of calcium silicate brickwork
hangers, as described in BS EN 845-1 a parapet from corners (double should follow the the brick manufacturer’s
with performance equivalent to a wall the frequency) recommendations.
restraint strap at not more than 2m
centres. (i) cladding to framed structures
Allowance should be made for differential
movement between cladding and frame.
The following precautions should be taken • below dpc where there is a high risk of In Scotland, Northern Ireland, the Isle of
to prevent buckling and fracturing of saturation Man and in other places where the
masonry panels: • retaining walls exposure to driving rain is Very Severe,
• flexible movement joints should be • parapets masonry should form a rebate at the
provided at the underside of each • freestanding walls reveals of openings to avoid a straight
horizontal support member • rendered walls through joint where the frame abuts the
• the masonry outer leaf should have at • areas of Severe or Very Severe exposure masonry.
least two-thirds of its width supported to driving rain. Minimum 12mm overlap of
masonry (or render) to frame
securely by the concrete frame or a
Reclaimed bricks should be used only in
metal angle sealant ‘rebated‘ or
accordance with Technical Requirement R3. ‘check‘ reveal
• the inner leaf should be adequately tied 25mm
in areas of Very
severe exposure
to the structural frame. Forked plate (b) rain penetration
ties held in dovetail slots, cast into the Rainwater will penetrate the outer leaf of
sealant
• concrete blocks with a density not less bricks without the brick manufacturer’s (d) admixtures and additives
than 1500kg/m3 or of strength not less written agreement. Calcium chloride should not be used as
than 7.3N/mm2 an admixture to mortar. The contents of
• most types of aerated concrete blocks MORTAR admixtures should be checked to ensure
with render. that they do not contain calcium chloride.
6.1 - D5 Mortar shall be of the mix
In Scotland, all clay bricks used as facings proportions necessary to achieve Admixtures should only be used in
should be frost-resistant (F2,S2 or F2,S1 to adequate strength and durability and be accordance with manufacturers’
BS EN 771). suitable for the type of masonry recommendations/instructions.
If there are doubts about the suitability Items to be taken into account include: Mortars containing an air-entraining
of a facing brick for sites in areas of plasticiser are more resistant to freeze/
exceptionally severe frost exposure (a) geographical location and position thaw damage when set.
classification, written confirmation should within the structure
Recommended mortar mixes for different White cement to BS EN 197 and pigments
be obtained from the brick manufacturer
locations are given in Appendix 6.1-C. to BS 1014 may be used, but pigments
that the brick is suitable for:
should not exceed 10% of the cement
• its geographical location, and
(b) sources of sulfate weight or 3% if carbon black is used.
• its location in the structure.
Ordinary Portland cement mortar can
Further advice concerning admixtures is
This applies particularly to bricks such expand, crumble and deteriorate badly
given in Appendix 6.1-C.
as fletton facings which are moderately if attacked by sulfates. Sufficient soluble
freeze/thaw resistant (F1,S2 or F1,S1). sulfate to cause this problem may be
In addition, follow manufacturers’ contained in clay bricks. Clay bricks with DAMP-PROOF COURSES
recommendations on suitability, including an S1 designation have no limit on their AND CAVITY TRAYS
the choice and use of mortar and the type sulfate content. The problem is most acute
of pointing. when brickwork is saturated for long 6.1 - D6 Damp-proof courses and related
periods; mortar is vulnerable to attack by components shall be provided to prevent
Recessed joints should only be used in moisture rising or entering the building
any soluble sulfates present.
compliance with Clause D5(c).
To reduce the risk, sulfate-resisting Items to be taken into account include:
Bricks that are not frost-resistant (F0,S2 or
Portland cement to BS 4027 should be (a) dpcs
F0,S1 to BS EN 771) may not be acceptable
used: Damp-proof courses should be provided
for use externally, unless completely
• below dpc level when sulfates are in accordance with the Table in Appendix
protected by a cladding which can
present in the ground 6.1-D.
adequately resist the passage of water.
• when clay bricks (F2,S1 and F1,S1 to BS
Good brickwork detailing can limit EN 771) are used, and there is a high At complicated junctions, clear drawings
persistent wetting of brickwork and reduce saturation risk, for example in the should be provided and preformed
the risk of frost attack. following situations: profiles specified. Isometric drawings
-- parapets can sometimes be clearer than the
6.1
For example: -- chimney stacks combination of plan and section/elevation
• paths should drain away from walls to -- retaining walls drawings.
avoid saturating bricks near the ground -- freestanding walls
• sills, copings and the like should have a -- rendered walls (b) cavity trays
weathered upper surface -- areas of Severe or Very Severe Cavity trays should be provided at all
• a coping should be provided for exposure to driving rain. interruptions to the cavity, eg window
all parapet walls, chimneys and and door openings, air bricks, etc, unless
freestanding walls unless clay bricks of (c) joints otherwise protected, eg by overhanging
F2,S1 or F2,S2 classification to BS EN Struck (or weathered) and bucket handle eaves.
771 have been used. Copings should joints are preferable.
A cavity tray should:
have a generous overhang, throatings
Recessed joints should not be used where: • provide an impervious barrier and
at least 40mm clear of the wall and a
• bricks are perforated nearer than 15mm ensure that water drains outwards
continuous, supported dpc underneath
to the face • project at least 25mm beyond the outer
which projects beyond the line of the
• bricks are not frost resistant (if clay F1,S1 face of the cavity closure or, where
wall. Single leaf parapet walls should not
or F1,S2 to BS EN 771), unless the brick a combined cavity tray and lintel is
be rendered on both sides.
manufacturer has agreed in writing for acceptable, give complete protection to
Where there is a risk that brickwork may their use in a particular location the top of the reveal and vertical dpc
be persistently wet, bricks should be • there is no reasonable shelter from where provided
specified that are low in soluble salts (if driving rain (reasonable shelter could • provide drip protection to door and
clay, F2,S2 or F1,S2 to BS EN 771). be from buildings or groups of trees window heads
if these are within 50m and of similar • have an overall minimum upstand from
Note height to the dwelling) the inside face of the outer leaf to the
Only clay bricks designated L by BS EN • the dwelling is built on steep sloping outside of the inner leaf of 140mm
771 have a low limit on their soluble salt ground, facing open countryside or • be shaped to provide at least a 100mm
content. In persistently wet conditions, clay within 8km of a coast or large estuary vertical protection above a point where
bricks of S1 designation may create sulfate • the cavity is to be fully filled with cavity mortar droppings could collect.
attack on the mortar. insulation.
Painted or decorated finishes can trap Jointing is preferable to pointing because
moisture in external brickwork and it leaves the mortar undisturbed.
increase the risk of frost damage, sulfate
attack or other detrimental effects. They
should not be applied to S1 designation
(c) abutment details for brick and block masonry, where (e.g. coastal sites) should be austenitic
Cavity trays should be provided at applicable stainless steel.
abutments of roofs and cavity walls. This
will ensure that any water penetrating into Stone masonry (natural or cast stone) In Scotland, Northern Ireland, the Isle of
the cavity does not enter the enclosed should be designed to meet the Man and areas of Severe or Very Severe
area. This only applies where the roof requirements of BS EN 1996 ‘Design of exposure to driving rain, separate damp-
is over an enclosed area, including an masonry structures’. proof protection should be provided over
attached garage, but does not apply to all lintels in accordance with the guidance
open car ports and open porches. LINTELS for cavity trays given in Clause D6(b).
Where the roof abuts at an angle with 6.1 - D9 Lintels shall safely support the Lintels should be of such a size and be
the wall, preformed stepped cavity trays applied loads located so that the external edge of the
should be provided. Items to be taken into account include: lintel projects beyond, and therefore offers
protection to, the window head.
(a) structural support
preformed
stepped Concrete, steel and reinforced brickwork (c) cold bridging and condensation
cavity trays
are acceptable materials for use as lintels. The BRE Report ‘Thermal insulation:
Timber lintels should not be used, unless: avoiding risks’ discusses aspects of
• they are protected from the weather, insulation relevant to external masonry
and walls. In England and Wales account should
• they do not support masonry or other be taken of Accredited Details.
at least
85mm rigid or brittle materials. The risk of condensation at reveals and
Lintels should be designed in accordance soffits becomes more likely as the wall
either with Technical Requirement R5 or insulation increases. Cold bridge paths
manufacturers’ published data. A lintel should be avoided.
should be provided where frames are not To avoid a cold bridge, the wall insulation
designed to support superimposed loads. should ideally abut the head of the window
(d) parapet details
Lintels should be wide enough to provide frame.
Dpcs below the coping should be
supported over the cavity to prevent adequate support to walling above. Clause D4(b) details methods of preventing
sagging. A dpc should be specified that can Masonry should not overhang the lintel rain penetration which may also be
achieve a good key with the mortar. support by more than 25mm. A lintel required.
should extend beyond the opening at each
end by at least the following lengths:
(d) adequate fire resistance (c) partial cavity insulation SOUND INSULATION
Where steel lintels are used, Partial cavity insulation should be fixed
manufacturers’ recommendations for only against the cavity face of the inner 6.1 - D13 External walls adjacent to
providing adequate fire resistance, leaf. The clear cavity width between partial sound-resisting walls shall be designed
particularly to the lower steel flange, cavity insulation and the outer leaf should to adequately resist flanking sound
should be followed. be at least 50mm nominal. In areas of Very transmission
Severe exposure in England and Wales, a Acceptable levels of sound reduction
THERMAL INSULATION residual cavity of 75mm is required where between dwellings may be achieved by:
the outer leaf is fair faced masonry. • the inner leaf of an external cavity wall
6.1 - D10 External walls shall be
Wall ties should be long enough to allow a having sufficient weight, and
designed to provide the required
50mm embedment in each masonry leaf. • sealing of air paths
standard of thermal insulation
• allowing appropriate spacings between
The insulation value of the wall must meet (d) inner leaf of insulated blockwork openings in external walls.
the requirements of the relevant Building Types of blockwork include:
Regulations. The density of external walls and the
• lightweight aerated concrete
position of openings adjacent to sound-
• lightweight aggregate blocks
Design should avoid cold bridging at resisting walls should be in accordance
• voided blocks with insulation infill
openings and at junctions of external walls with statutory requirements and, where
• blocks faced with insulation material.
with roofs, floors and internal walls. relevant, an assessment which complies
Manufacturers’ recommendations should with Technical Requirement R3.
6.1 - D11 External walls shall be designed be followed and particular note taken of
to ensure the correct use of insulation
materials
the following: CLADDINGS
• a clear 50mm wide cavity should always
be maintained 6.1 - D14 Cladding shall satisfactorily
Items to be taken into account include:
• the blocks should be capable of resist the passage of moisture
(a) acceptable insulation materials
Insulation, or lightweight aerated concrete supporting concentrated loads Items to be taken into account include:
blocks, or blocks with face bonded • the correct type of joist hanger for the (a) battens
insulation, or voided blocks with insulation type and size of block and size of joist Where battens are required, they must be
infill should be used in accordance with: should be used pre-treated with preservative, as described
• an assessment which complies with • long unbroken lengths of blockwork in Chapter 2.3 ‘Timber preservation
Technical Requirement R3, or should be avoided (natural solid timber)’ (each section).
• a British Standard and the relevant Code • precautions should be taken to reduce
of Practice. risk of shrinkage cracking (b) joints
• dry lining should be used where Joints between claddings and adjacent
(b) full cavity insulation shrinkage cracking might be unsightly materials should be detailed to be
In Northern Ireland and the Isle of Man, and to avoid long term pattern staining watertight under the particular exposure
it is not permissible to fill cavities with at mortar joints conditions of the site. Where necessary,
6.1
pumped thermal insulants at the time of • restrictions on chasing for services provision should be made for differential
construction. when using voided blocks should be movement.
noted (reference should be made to
In Scotland, it is not permissible to fill the (c) moisture barriers
Clause D3(e)).
full width of the cavity with any thermal Unless specifically not required for a
insulants at the time of construction. (e) dual insulation proprietary cladding, moisture barriers
Where partial cavity insulation is used should be provided between walls of solid
The type of insulation, its thickness and
in addition to an insulated block inner masonry and any boarding, slating, tiling
the wall construction should be suitable for
leaf (reference should be made to Clause or other similar claddings. The moisture
the exposure of the dwelling in accordance
D11(c)), the whole composite construction barrier may be roofing underfelt or
with Appendix 6.1-A.
should have been assessed in accordance equivalent.
Materials clause 6.1 - M9 sets out the range with Technical Requirement R3.
of acceptable insulation materials and the Vapour barriers such as polyethylene
relevant British Standards. (f) insulated dry linings sheet are not an acceptable moisture
Where an insulated dry lining contains a barrier as they can trap moisture in the
Render on an external leaf of clay bricks combustible insulant, the plasterboard structure.
(F2,S1 or F1,S1 designation bricks to BS EN should be at least 12.5mm thick and
771) in Severe or Very Severe exposures mechanically fixed to the masonry inner For timber framed walls clad with masonry,
is not permitted where the cavity is to be leaf. This is to prevent early collapse of the reference should be made to Chapter 6.2
fully filled with insulation. lining in a fire. ‘External timber framed walls’ for details.
The following design points should be (d) vertical tile or slate cladding
noted: FIRE SAFETY Every tile or slate should be nailed with
• stop ends should be provided to cavity 6.1 - D12 Cavity walls shall adequately two nails. Nails should be aluminium,
trays or combined lintels resist the passage of fire copper or silicon bronze.
• weepholes should be provided at
Cavities should be closed with cavity Bottom edges should be finished with an
450mm (maximum) centres with at least
closers in accordance with statutory under-course and tilting batten.
two per opening
• mortar joints should not be recessed requirements.
(e) timber cladding
• painted finishes on bricks or render are Timber claddings should be pre-treated
not acceptable if they are likely to cause with preservative in accordance with
frost damage or sulfate attack or other Chapter 2.3 ‘Timber preservation (natural
damage. solid timber)’ (each section).
RENDERING • cement for brickwork mortar is sulfate- Undercoats should be allowed to shrink
resisting to BS 4027 and dry out before applying following
6.1 - D15 Rendering, in conjunction • the brick manufacturer has confirmed, coats. When rendering onto dense
with the surface to which it is applied, in writing, that the brick is suitable, concrete blocks, adhesion can be improved
shall satisfactorily resist the passage of taking account of the brickwork detailing by use of proprietary bonding agents or a
moisture and the particular exposure of each spatterdash coat.
Items to be taken into account include: rendered element. If sulfate-resisting
cement is used in the mortar, it should (g) detailing of timber/brick/render
(a) rain penetration Dwellings which incorporate rendered
also be used in spatterdash coats and
External rendered finishes should comply panels between timber boards should have
base coats of the render.
with BS EN 13914 ‘Design, preparation at least one coat of render applied over
and application of external rendering and Care should be taken when specifying the whole wall face before the boards are
internal plastering’ and the guidance given render to walls with full cavity fill. The lack fixed. The second coat may be applied
below. of a ventilated cavity can slow down the between the boards.
rate at which the wall dries out.
It is important to prevent rainwater Rendering and timber can shrink causing
penetrating behind the rendering. Design Rendered finishes should not be used over gaps. Precautions should be taken to
features around openings and at the head fully filled cavity walls if: prevent rain from penetrating the junction
of the rendering should provide shelter, • the outer leaf is built in bricks with S1 as this might cause the render to fail as a
where possible, and help to shed water designation (F2,S1 and F1,S1 to BS EN result of frost damage.
away from the surface below. 771), and
• the site is in an area classed as Severe All exposed timber, except naturally durable
(b) exposed elements or Very Severe exposure to driving rain species, should be treated in accordance with
It is not advisable to render exposed (see Appendix 6.1-A). Chapter 2.3 ‘Timber preservation (natural
parts of a building, such as parapets and solid timber)’ (each section).
chimneys constructed of clay bricks of S1 Rendering may be used on brickwork
designation, without the use of sulfate- with partial cavity insulation provided a Where timber is used on brick or render,
resisting cement. clear cavity width between insulation and it is essential that all cut ends, mortices,
outer leaf of at least 50mm nominal is etc made after treatment are flood coated
(c) movement maintained. with preservative.
Movements can occur at a change in
Large section timbers should be fitted
material. In such cases, the render should (e) mixes
with suitable weather bars, flashings, etc
be either stopped at specially formed The rendering mix should be appropriate
to prevent moisture penetration through
movement joints or, if the expected to the strength of the background. No
joints with adjacent materials.
movement is small, be reinforced by metal render coat should be stronger than the
lathing carried across the joint. If metal background or richer than the preceding Non-ferrous fixings should be used.
lathing is used, three rendering coats coat. The render should be of adequate Aluminium is not suitable when the
should be applied. strength to achieve durability. preservative is Copper/Chromium/Arsenic.
6.1
(d) background Mixes should comply with the (h) proprietary and local rendering
To achieve a good bond, the masonry recommendations of BS EN 13914 ‘Design, systems
backing should be moderately strong preparation and application of external Proprietary rendering finishes should be
and porous to give some suction and a rendering and internal plastering’. When applied in accordance with manufacturers’
mechanical key. Dense masonry with a rendering on bricks that are F1,S1 or recommendations.
smooth surface should not be rendered. F1,S2 to BS EN 771, the Table to Sitework
clause 6.1 - S8(b) should be followed. The Traditional local rendering should comply
Aerated or lightweight aggregate concrete manufacturer of the background masonry with the above guidance, as appropriate,
blocks can be used, as a background, should be consulted regarding particular and with established local practice.
but more care is needed when selecting requirements for the mix or its application.
a rendering mix and surface treatment.
Strong render mixes should not be used. Pigments complying with the requirements PROVISION OF
Roughcast and dry dash finishes that of BS 1014 may be added to the finishing INFORMATION
require a strong mix are not recommended coat up to a limit of 10% of the cement
6.1 - D16 Designs and specifications
for use on aerated or lightweight weight or 3% in the case of carbon black.
shall be produced in a clearly
aggregate blocks. Block manufacturers’ White Portland cement may be used.
understandable format and include all
recommendations should be followed. relevant information
(f) number and thickness of coats
In Scotland, render should be applied only The number of coats should be chosen For external masonry walls, the drawings
to bricks: with regard to the background and the should show:
• which are keyed, or exposure conditions of the site. • wall layout with all dimensions shown
• where a spatterdash coat has been • position and size of openings
For rendering on masonry cavity walls,
applied before the first render • coursing of the bricks and blocks in
one undercoat and one finishing coat is
undercoat. relation to storey heights and opening
acceptable. On metal lathing or on solid
In other areas, render should be applied wall construction, two undercoats and one positions
only to bricks where either: finishing coat are required. • details at all junctions, indicating
• keyed bricks are used, or position of dpcs and cavity trays.
Initial undercoats should not be less than Isometric sketches are recommended
• the joints are raked out at least 15mm
10mm and not more than 15mm thick. Any for complicated junctions
deep.
further undercoat should be thinner than • position and type of lintels
Render may be applied to bricks (if clay
the preceding coat. Finishing coats should • position of restraint straps
F2,S1 or F1,S1 to BS EN 771) only if the
be generally between 6mm and 10mm • details of cavity closers
following conditions are met:
thick. • details at reveals
6.1
applies (see Chapter 1.1 ‘Introduction to the appropriate if there is a risk of vulnerability
to frost. In saturated conditions, sulfate- Other factors may dictate the strength of
Standards and Technical Requirements’).
resisting cement mortar is required for S1 blocks required in certain circumstances,
References to British Standards and Codes designation bricks. eg sulfate-resistance may require blocks of
of Practice include those made under the greater strength.
Construction Products Directive (89/106/ CALCIUM SILICATE BRICKS The maximum loadbearing capacity of the
EEC) and, in particular, appropriate Bricks of compressive strength Class 20 wall should not exceed manufacturers’
European Technical Specifications (to BS EN 771-2) are suitable for most recommendations.
approved by a European Committee for applications. Bricks of strength Class 30
Standardisation (CEN). and declared as freeze/thaw resistant (to (b) have appropriate resistance to
BS EN 771-2) are recommended in areas adverse effects of freeze/thaw and
BRICKS of severe freeze/thaw exposure (see map sulfate attack
in Appendix 6.1-B) or for use where bricks Concrete blocks used in the outer leaf
6.1 - M2 Bricks shall:
may be persistently wet (eg parapets, without protective cladding or render,
(a) be capable of supporting intended chimneys, sills and below dpc). should:
loads
Calcium silicate bricks do not contain • have a compressive strength exceeding
Requirements for the design strength of
significant amounts of soluble sulfates 7.3N/mm2, or
bricks are given in BS EN 1996-1-1. The
and may be suitable where sulfate bearing • have a density exceeding 1500kg/m3, or
brick specified in the design should be
soil and ground water conditions exist. • be made with dense aggregate to BS EN
used. Clay bricks to BS EN 771 with a
Manufacturers’ recommendations should 12620, or
minimum compressive strength of 9N/mm2
be followed. • be lightweight aerated concrete blocks
should be adequate for one and two storey
dwellings and 13N/mm2 for three storey having had their suitability confirmed by
CONCRETE BRICKS the manufacturer.
dwellings.
In concrete bricks there is a direct
relationship between strength and Concrete blocks should not be used below
(b) have appropriate resistance to the
durability, including freeze/thaw resistance. dpc where there are sulfates in the ground,
adverse effects of freeze/thaw and
Most concrete bricks in production have unless suitability is confirmed by the block
sulfate attack
a strength of 20N/mm2 and are durable manufacturer. Sulfates may attack the
in most situations. For copings and sills, cement used in the block. Sulfate-resisting
bricks with a compressive strength of 36N/ cement will be required in the mortar. The
mm2 should be used. proportions will depend on the level of
sulfates in the ground.
(c) have an adequate thermal resistance, DPC MATERIALS Lintels up to 1.2m length which do not
where required need a separate dpc tray should have a
The designer may have specified a 6.1 - M6 Materials for damp-proofing minimum 100mm end bearing and project
particular type and thickness of concrete shall resist adequately the passage of beyond the cavity closer by at least 25mm.
block because of its thermal insulation moisture Normally, other lintels should be long
performance in addition to its strength. Items to be taken into account include: enough to have a minimum 150mm end
Alternative concrete blocks should not be bearing each side of the opening.
(a) dpcs
used without the designer’s acceptance. The following materials are acceptable for Cavity trays may be required over the
use as dpcs: lintels. This should be specified in the
STONE MASONRY • bitumen to BS 6398 design. Reference should be made to
6.1 - M4 Stone masonry shall be capable • polyethylene to BS 6515 (except below Design clause 6.1 - D9(b).
of supporting the intended loads and copings and in parapets)
• proprietary materials assessed in
have appropriate resistance to the
accordance with Technical Requirement
THERMAL INSULATION
adverse effects of freeze/thaw
R3. 6.1 - M9 Insulation materials shall
Stone for masonry should conform to the Dpcs and flexible cavity trays should be of provide the degree of insulation to
requirements of BS EN 771-6. the correct dimensions to suit the detailed comply with the design
design. All retro-fill insulation materials (UF
Cast stone masonry units should comply
with BS EN 771-5 or BS 1217 as appropriate. For complicated junctions, preformed foam, blown mineral fibre and expanded
cavity trays are recommended. Care should polystyrene beads) should be installed by
MORTAR AND RENDERING be taken to order the correct type and installers trained by the assessment holder
shape. and approved jointly by the assessment
6.1 - M5 Mortar and rendering materials holder and the assessing organisation.
shall be of the mix proportions to (b) flashings
achieve adequate strength and durability The following are acceptable as flashings: The installer should be a member of a
to comply with the design • rolled lead sheet (at least Code 4) surveillance scheme acceptable to NHBC.
Items to be taken into account include: complying with BS EN 12588 Insulation materials should be installed in
• aluminium and aluminium alloys accordance with the following:
(a) cement and lime
complying with BS 1470 (0.6mm to • UF foam to BS 5617 installed in
Ordinary Portland cement should be to BS
0.9mm thick) accordance with BS 5618
EN 197. Sulfate-resisting Portland cement
• zinc alloy complying with BS 6561 and • all other insulation materials, whether
should be to BS 4027. Masonry cement
0.6mm thick. for full or partial cavity insulation,
should be to either BS EN 197 or BS EN
insulated blockwork or internal
413. WALL TIES insulation may only be used if
Limes should conform to BS EN 459. 6.1 - M7 Wall ties shall be appropriate assessed in accordance with Technical
for their location and intended use Requirement R3.
(b) sand type
6.1
Sand and aggregate from natural sources Wall ties shall be in accordance with either: The thickness of materials required by the
should conform to BS EN 13139. • BS EN 845, or design and Appendix 6.1-A should be used.
• an assessment in accordance with
(c) mortar type Technical Requirement R3.
Ready-mixed mortars should comply with
CLADDING MATERIALS
BS EN 998. For recommended mortar Ties should be long enough to be 6.1 - M10 Cladding materials shall be
mixes, see Appendix 6.1-C. embedded at least 50mm into each leaf. of the quality, type and dimensions
In England and Wales, wall ties should be required by the design
(d) additives
stainless steel or non-ferrous. In Northern Items to be taken into account include:
Air entraining and set retarding admixtures
Ireland, stainless steel or non-ferrous ties (a) tiles and slates
should comply with BS EN 934.
should be used where the cavity is fully Clay tiles for tile hanging should be to BS
Pigments for colouring mortars should filled with insulation and 75mm wide or 402.
conform to BS EN 12878. more. In Scotland, galvanised ties may be
used. Concrete tiles for tile hanging should be to
(e) render BS 473.
Sand for render should be sharp sand to Where partial cavity insulation is used,
BS EN 13139, preferably from the coarse it should be held in place by retaining Slates for vertical slating should be to BS
end of the grading scale. Sand with devices which may be clipped to the wall 680.
excessive fine material will shrink and ties. These devices should be assessed in
accordance with Technical Requirement R3 (b) timber boarding
crack.
and used only with compatible wall ties. Timber should comply with BS 1186 and be
Reinforcement for render, including angle Class 3 or better.
beads, corner beads, stop beads and
render stops, should be stainless steel or
LINTELS Timber should be a naturally durable
species or pre-treated with preservative.
PVC. 6.1 - M8 Lintels shall be of the type and
Reference should be made to Chapter 2.3
dimensions appropriate to their position
Decorative finishes that contain asbestos ‘Timber preservation (natural solid timber)’
within the structure
are not acceptable. (each section) for guidance on preservative
Steel and concrete lintels should comply treatments.
with BS EN 845-2, ‘Specification for
ancillary components for masonry’. (c) underfelt behind cladding
Type 1F felt to BS 747 is acceptable as an
underfelt behind cladding.
6.1
spirit levels. To keep the wall plumb, do not over-reach
expansion joints in fired clay bricks, are:
• hemp at changes of lift. It is better to wait for the
(c) mortar
• fibreboard next scaffolding lift.
Different types of bricks and blocks need
• cork. different strength mortar mixes. Some
In concrete blockwork, the construction parts of the building, such as below
joint may be a simple vertical joint filled dpc, chimneys and copings, may need a
with mortar and sealed. different mix to the main walling. Make
sure the mix is right for the job.
(g) bonding
A regular bonding pattern should be
maintained. External walls should be
bonded to partitions and party walls, as
required by the design. Either: Where a different size of masonry unit is
• • tooth every alternate course, or needed to ensure correct coursing, small
• • tie with wall ties, expanded metal or units of the same material should be used
equivalent at centres not exceeding to reduce cracking and problems due to
300mm vertically. different thermal insulation properties.
different masonry types
bond where blocks used to adjust coursing
are of the same type
Clean cavities with mortar droppings
removed are particularly important in
exposed areas and where partial cavity fill
is used.
Where cavity insulation is used, mortar
droppings should be cleaned off from the
top edge. Mortar left on the top edge may
transmit dampness to the inner leaf. The
use of a cavity batten will prevent this.
incorrect use of different masonry types
Cavity battens should be wrapped with
flexible material to allow easy withdrawal.
Where the inner leaf of a cavity wall is
being used for thermal insulation and
batten keeps tie where blocks are where a different size of masonry unit is
of a different type
cavity clear of
mortar droppings
used to ensure correct coursing, the unit
should have similar thermal insulation
properties to the masonry used for the
rest of the wall. For example aerated
concrete blocks should not be mixed with
6.1
clay bricks.
6.1
at doorways where the dwelling is to be
T designed to allow access for the disabled.
thickness
not reduced
wall tie
on this side Dpcs should: (c) dpcs to prevent downward flow of
• be laid on a surface, free from water
projections which could puncture or Where dpcs are intended to prevent the
adversely affect the dpc material downward movement of water, joints
• be fully bedded on fresh mortar where should be sealed or welded. Lapped joints,
required by the design, or where the unsealed, are unacceptable.
T
building is over three storeys in height
maximum corbel = T maximum corbel = T • be of correct width Where flashings link with dpcs, rake out
3 3
• not project into the cavity 25mm of mortar below the dpc to allow for
CAVITY WALL SOLID WALL
• not be set back from the edge of the the flashing to be tucked in. It is easiest to
masonry rake out the joints as the work proceeds.
(k) calcium silicate bricks • lap the dpm.
Where calcium silicate bricks are used, the
brick manufacturer’s recommendations dpcs clear of cavity
should be followed.
dpc laps dpm
STONE MASONRY
slight
projection 25mm
6.1 - S3 Stone masonry shall be
mortar raked out flashing wedged in
constructed to an acceptable standard while still green place and pointed up
Where a jointed or permeable sill is used protection to the top of the reveal and A dpm should be provided behind meter
(all sills in Northern Ireland and the Isle vertical dpc where provided. boxes in areas of very severe exposure to
of Man), a dpc should be placed between driving rain.
the sill and the outer leaf, turned up at the
back and ends of the sill.
cavity cavity
tray tray
at least at least
dpc turned up 140mm 100mm rise
at back and total rise in cavity tray
ends of sill in cavity from front
tray of cavity
WALL TIES
stop end
6.1 - S5 Wall ties shall be of the correct
type correctly installed
Items to be taken into account include:
at least 2 weep holes (a) type
per opening, not more
than 450mm apart The type of wall tie specified by the
insulation vertical dpc
designer should be used.
combined lintel
projects at least
Where there is a sill dpc, it should be 25mm beyond (b) position
the outer face
lapped with the reveal dpc. of cavity closure If ties slope down to the inner leaf, if
drips are off-centre or if ties have mortar
If there is no sill dpc, the vertical dpc 25mm min droppings on them, water can cross the
should be continued 150mm below the sill cavity.
level.
The two leaves should be coursed so that
A fillet joint of sealant should not be the wall tie is level or slopes outwards.
considered as a substitute for good
combined lintel
workmanship or dpcs. However, a bead of or cavity tray
mastic should be used around openings.
proceeds. The drip should face downwards. At openings and movement joints, wall ties
Ties should be built-in, not pushed into should be spaced at maximum 300mm
joints. centres vertically even if this means
wall tie built at least
50mm into each leaf cutting cavity insulation to insert the tie. lintel
correct bonding
below supporting
block
225mm
450mm
Lintels and masonry should form openings
of the correct size for the frame of the
window or door.
Concrete floor units or other heavy
900mm
components which bear on lintels should
be positioned carefully to avoid damage or
drip of wall tie placed
centrally in cavity (d) use of partial fill insulation shock load.
Where partial cavity fill insulation is
The lintel toe should:
being used, it should be retained against
• project past the window head
the inner leaf by retaining devices. The
• have a flexible sealing compound
retaining devices should be compatible
between toe and window.
with the wall ties and used in accordance
with an assessment which complies with Brickwork or masonry should not overhang
Technical Requirement R3. the lintel by more than 25mm.
Unless the independent assessment states
otherwise, where partial cavity fill is being
used the wall ties should be spaced more
closely to provide adequate support and
restraint for the 1200mm long boards.
Where one leaf is built in advance of the
Ties should be spaced at 600mm centres
other, the wall ties should project enough
horizontally and in vertical as well as
from the built leaf to bed at least 50mm
horizontal rows, ie not staggered.
into the unbuilt leaf.
LINTELS
overhang overhang
6.1
6.1 - S6 Lintels and beams shall be not more not more
than 25mm than 25mm
installed correctly
flexible sealant
Items to be taken into account include: lintel toe projects between lintel
50mm beyond window head and window
(a) span and placing
wall tie should project Lintels should be the correct size for the STEEL LINTEL
enough to build 50mm
into the unbuilt leaf opening and have the correct bearing at
each end: (b) thermal insulation
Insulation may help to prevent cold bridges
Minimum bearing length (mm) at the heads of openings in external walls.
Span (m) Simple Lintel combined The design should be checked for this
lintel with cavity tray requirement. Insulation should be provided
to the underside of the lintel unless the
Up to 1.2 100 150
manufacturer shows an alternative to
prevent cold bridging.
Over 1.2 150 150
ensured that sulfate-resisting cement Freshly laid mortar and render may fail if it It is cost effective to protect and store
which complies with Appendix 6.1-C is used freezes because the frozen water expands materials properly and maintain good
in the mortar. and forces apart the particles of mortar. quality control during construction.
If water-resisting properties are required, Admixtures which contain calcium chloride (b) handling
Portland cement with a waterproofing should not be used. The unloading of all bricks and blocks,
agent already incorporated may be especially facing bricks, preferably should
The use of air entraining agents in cold
available. Otherwise, a waterproofing be by mechanical means, directly onto a
weather gives better frost resistance to
agent should be used and added to the firm level surface. Bricks that are tipped
set mortar but does not aid the set. The
rendering mix in strict accordance with on delivery or moved about the site in
use of accelerating admixtures and other
manufacturers’ instructions. dumper trucks often have a high degree of
admixtures should not be relied on as an
wastage. Chipped or fractured bricks are
(c) application anti-freeze precaution.
not acceptable for facework.
The number and thickness of coats should
Check what effect additives have on
be in accordance with the design.
setting times. Cold weather slows setting,
as do retarders. If the set is retarded too
much, the next lift might squeeze out the
joints raked out
15mm to give mortar below.
key for 10mm
to 15mm thick
undercoat Brick and blockwork should not be built
nor rendering carried out when the air
temperature is 2°C and falling.
following 2ºC
coats thinner
and weaker
than undercoat 0ºC
render stopped
above dpc
6.1
In Scotland, a spatterdash coat should be frost damage. Covers should be provided
applied before the first render coat if the to form a still air space to insulate the wall.
background is of Scottish common bricks (c) storage
Walling damaged by frost will not regain
and bricks to BS EN 771. Stacks of bricks and blocks should be
strength and should be taken down and
protected from rain, mud splashes, etc by
re-built when conditions improve.
Undercoats should be applied at least 3 covering with waterproof covers. Bricks
days before applying the following coat. and blocks that become excessively wet
cover weighted down
can suffer from:
If coloured pigments are specified,
• staining and efflorescence
batching should be undertaken with care
cover provides • increased drying shrinkage with a
to ensure colour consistency. a still air space
to insulate the greater risk of cracking
wall from frost
(d) cracking and crazing • lack of mortar adhesion to mud stained
Rendering should be free from significant surfaces.
cracking and crazing.
To avoid surface crazing:
• use properly graded sand (fine sand
increases the risk of crazing) Reference should be made to Chapter 1.4
• strong mixes should not be used as the ‘Cold weather working’ for more detailed
finishing coat advice.
• overworking, which causes laitance to be
drawn to the surface, should be avoided
• the finishing coat should be kept damp HANDLING AND
for at least 3 days. In warm dry weather, PROTECTION protection of bricks and blocks
spraying or protection by polyethylene
6.1 - S10 Materials shall be handled, Cement should be stored off the ground
sheet may be needed. Rendering should
stored, used and protected in such a and protected from weather. Sand should
not be carried out during hot weather or
in bright sunshine. way as to ensure that the construction be prevented from spreading and be
shall be neat, clean and undamaged upon protected so that it remains clean.
COLD WEATHER WORKING completion
The work place should be kept clean to
6.1 - S9 Precautions shall be taken to Items to be taken into account include: reduce mortar splashes to a minimum. Any
protect walls and rendering from damage (a) avoidance of damage accidental mortar smears should be lightly
by frost during construction
Fairfaced masonry 1
N/A N/A N/A
6.1
Exposure zones Exposure to wind driven
rain (litres/m² per spell)
Note:
Variations to the exposure shown on
the map can only be made by site-specific
calculations using BS 8104 “Assessing
exposure of walls to wind driven rain”
and the table above.
Appendix 6.1-B
KW
IV
PA
AB
PH
DD
PA
FK
KY
G
EH
ML
KA TD
DG NE
CA DH SR
DL TS
6.1
LA
HG YO
BD
Northern Ireland FY PR BB LS
From the available HX
HU
meteorological data, BLOL HD
WF
the three criteria for L WN
M DN
assessing severe WA S
exposure to frost SK
attack, as set out CH
CW LN
above, do not occur LL
simultaneously in any NG
ST DE
part of Northern Ireland
SY TF
WS LE
PE NR
WV
DY B
CV NN
LD WR IP
HR CB
SA MK
GL SG
NP OX LU CO
HP AL CM
CF HA EN
UB G
SN SL TW RM
SS
BS RG DB
SM BR DA
KT CR
BA ME
TA GU CT
SP RH TN
SO
EX
DT BH PO BN
PL
TQ
TR
The following list identifies the postal areas within which the three criteria for severe exposure to frost attack are met.
Only in a few instances is the whole of the post code district within the area of severe frost exposure.
54
40
28
27
26
25
24
23 23
22 47 22
20 21 84 19
12 19 48 14 55 20 83 18
11 17 47 13 48 19 82 17
10 16 46 12 47 18 81 16 26
9 13 45 11 46 17 77 15 19
8 12 44 10 45 16 76 14 18
7 24 11 43 8 44 15 75 13 17
6 23 9 10 42 7 43 14 74 12 16
5 22 8 9 41 6 28 13 72 7 6
4 21 7 8 40 4 13 27 12 65 8 7 6 5
3 20 2 7 39 3 12 26 11 64 7 5 6 4 4
5 2 15 1 6 37 9 6 2 11 23 8 63 4 3 4 3 3
3 1 13 0 5 8 7 8 4 1 8 8 14 1 62 3 3 2 2 1 1
AA BB BD BL CA CF CH DD DE DG DH DL EH FK G HD HG HR HX IV KA
6.1
57
55 21
54 20
41 16 19 41
40 15 18 40
33 14 41 17 39
32 13 40 16 38
28 12 38 15 37 48
14 27 11 37 11 36 44 25
13 23 26 12 10 36 10 35 40 24
12 22 25 11 44 9 35 9 34 39 17 23
11 21 8 24 10 8 8 34 8 33 33 16 22
10 20 7 23 9 71 7 7 33 7 32 32 15 21
9 12 6 22 8 66 6 6 32 6 31 20 14 20 71
8 10 5 21 7 49 5 5 27 5 30 19 13 19 11
7 9 4 20 6 48 4 4 26 4 26 30 13 12 18 8 22
6 8 3 16 3 47 3 3 25 3 25 11 11 11 17 5 21
5 6 2 15 2 46 2 2 24 2 23 10 10 10 13 16 2 18
3 13 2 1 11 24 1 19 1 1 23 1 22 6 9 6 10 10 1 9 6
KW KY LA LD LL M ML NE NP OL PA PH S SA SK ST SY TD TS YO
partly within
wholly within
Appendix 6.1-C
Mortar mixes
Unless recommended otherwise by the brick manufacturer, the mixes in the table below
should be used for clay bricks.
In the case of concrete or calcium silicate bricks, particular attention should be paid to
manufacturers’ recommendations.
Mortar mixes using ordinary Portland or sulfate-resisting cements where required (see
also Design clauses 6.1- D5(b) and (d)).
Air-entraining plasticiser can be incorporated in the following general use and high durability
6.1
mortars:
1 : 1 : 5½, cement : lime : sand, or
1 : 1 : 4½, cement : lime : sand.
Retarded mortar
Retarded mortar and most pre-mixed mortars can be used over a longer period of time than
site mixed, cement : lime : sand mortars. The timescale of use is defined by the manufacturer,
whose advice should be followed:
• protect retarded mortar against freezing prior to use
• do not use retarded mortar beyond the time for which it is effective
• because of delayed setting, temporary bracing of larger walls, for example gable peaks
and long walls, may be necessary.
Admixtures and additives
Where air-entraining plasticisers or other additives are to be used, follow manufacturers’
instructions:
• do not overdose, ‘more is not better’
• an air entraining agent can help reduce frost damage but it is not an anti-freeze
• do not use unauthorised additives.
Appendix 6.1-D
dpc
at least
150mm
ground
6.1
abutment of all surface. The tray should be lapped over any roof upstand or flashing to ensure
roofs over enclosed water penetrating into the cavity does not enter the enclosed area.
areas and balconies
to walls
At sloping A stepped cavity tray should be provided above the roof surface and linked to
abutments of all any roof upstand or flashing to ensure any water penetrating into the cavity
roofs over enclosed does not enter the enclosed area.
areas to cavity
walls
Doorsteps A dpc should be provided behind a doorstep where it is higher than a wall dpc.
dpm behind
doorstep links
with dpc
level of
wall dpc
doorstep
Sills Where precast concrete or similar sills incorporate joints or are of a permeable
material, a dpc should be provided beneath them for the full length and be
turned up at the back and the end of the sill.
Jambs in cavity The reveal should be protected throughout its width by a continuous dpc. The
width of the dpc should be sufficient to be fixed to, or overlap, the frame and
fully protect the reveal.
For Severe and Very Severe exposure conditions: rebated reveal construction,
with or without closed cavity and dpc.
Appendix 6.1-E
Calcium silicate and concrete bricks contain no significant active soluble salts. Information
on their durability is given in Materials clause 6.1 - M2(b).
Appendix 6.1-F
6.1
6.1
INDEX
A F S
Abutment details 4 Fire resistance 4, 5 Setting out 9
Admixtures and additives 3, 8, 20 Flashings 8 Sound insulation 5
Ancilliary components 22 Frost attack 2, 18 Slates 8
B I Stone masonry 4, 7, 11
Background, rendering 6 Insulation, full fill 5, 16 Storage 15
Blockwork 5 Insulation, partial fill 5, 13 Structural support, lintels 4, 13
Bonding 1, 10 J Sulfate 3
Bricks and blocks 7, 22 Joints 3 T
C L Thermal insulation 5, 8, 14
Calcium silicate bricks 1, 7, 11 Lateral restraint 1 W
Cavity trays 3, 11, 12, Lintels 4, 13 Wall ties 4, 8, 12
13, 21 M Workmanship 16
Cavity walls 5, 9 Mortar 3, 8, 9,
Cement 8 20
Cladding 1, 5, 8 Movement joints 1, 8, 10
Cold bridging 4 O
Cold weather working 15 Openings 10
Condensation 4 P
Corbelling 2, 11 Parapet details 4
D Point loads 1
Damp proof courses 3, 8, 11, Protection 1, 15
13, 21 R
Dry linings 5 Rain penetration 2, 5
Durability 4, 22 Reclaimed bricks 7
E Render 5, 8, 14
6.1
Exposure 2, 18
Chapter 6.2
6.2
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
CONTENTS SCOPE
DESIGN Clause Page This Chapter gives guidance on meeting the Technical
Requirements and recommendations for external walls of
Design standards D1 1 timber framed dwellings, substantially timber framed dwellings
Statutory requirements D2 1 and wall panels (including relevant certification procedures).
Load bearing walls D3 1 This Chapter applies to timber framed walls up to seven
Moisture control and insulation D4 1 storeys high.
Preservative treatment D5 2
Exterior cladding D6 2
Control of fire D7 3
Provision of information D8, D9 3
MATERIALS
Materials standards M1 3
Timber M2 3
Timber preservation M3 4
Sheathing M4 4
Breather membranes M5 4
Cavity barriers and fire-stops M6 4
Holding down devices M7 4
Nails and staples M8 4
Vapour control layers M9 4
Wall ties and fixings M10 4
Wall Insulation M11 4
SITEWORK
Sitework standards S1 4
6.2
Construction S2 4
Breather membranes S3 5
Wall ties S4 6
Insulation S5 6
Vapour control layers S6 6
Cladding S7 6
Control of fire S8 6
Services S9 7
APPENDIX 6.2-A
Certification procedure 7
APPENDIX 6.2-B
Specimen certificate (England, Wales, 7
Northern Ireland and Isle of Man),
APPENDIX 6.2-C
Specimen certificate (Scotland) 8
INDEX 16
6.2
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
DESIGN STANDARDS
not affect the stud spacing or where the MOISTURE CONTROL AND
supported loads are carried by a rim beam
or perimeter joist. INSULATION
6.2 - D1 Design shall meet the Technical
Additional studs may be required at 6.2 - D4 The design shall ensure that
Requirements
openings for fixing wall ties where the structure is adequately protected
Dwellings with a timber frame from the effects of moisture
masonry cladding is used.
superstructure require certification
Items to be taken into account include:
indicating that the design has been Multiple studs should be included to
checked by an NHBC timber frame certifier. support multiple joists and other point (a) provision of dpcs and dpms
See Appendix 6.2-A. loads unless otherwise specified by the Dpcs should be installed below the sole
designer. plates of all ground floor walls, including
Design that follows the guidance below will internal partitions, to protect timber from
be acceptable for external walls of timber The design should avoid narrow, rising damp and residual construction
framed dwellings, substantially timber inaccessible gaps between studs which are moisture.
framed dwellings and wall panels. This difficult to insulate.
Chapter applies to timber framed walls up Dpcs and trays should be fitted at openings
to seven storeys high. where needed to prevent rain penetration.
For guidance on the prevention of fire In Scotland, Northern Ireland, the Isle of
during construction see ‘Fire Prevention Man and other places where the exposure
lintel
on Construction Sites’ jointly published by to driving rain is Severe or Very Severe,
the Construction Federation and the Fire masonry should form a rebate at the
Protection Association (www.thefpa.co.uk) cripple reveals of openings to avoid a straight
stud
and guidance from the UKTFA under the through joint where the frame abuts the
‘Site Safety Strategy’ that presents fire risk masonry.
management publications such as the ‘16
Steps to Fire Safety’ and the ‘Design Guide
to Separation Distances’ (www.uktfa.com). dpc
STATUTORY
REQUIREMENTS
6.2 - D2 Design shall comply with all
relevant statutory requirements
load bearing lintel
Design should be in accordance with supported by cripple studs sealant
relevant Building Regulations and other
statutory requirements.
6.2
LOADBEARING WALLS (b) anchoring the frame JAMB - SHELTERED
Wall panels should be adequately fixed
6.2 - D3 Loadbearing timber framed to the sole plate which in turn should be
walls shall be designed to support and anchored to the substructure to resist all
transfer loads to foundations safely and the lateral and vertical forces acting at
without undue movement these junctions. Typical details are shown rain
(b) wall ties (e) services and relevant specialist subcontractors and/
Wall ties should be: Differential movement should be allowed or suppliers.
• of a type which complies with BS EN 845 for services both within the timber frame
Where proprietary products are to be
and fully permits differential movement envelope or where they pass through it.
used, manufacturers usually have specific
between the timber frame and the Additional guidance is given in Appendix
requirements for fixing and/or assembly
cladding - see Clause D6(c) below 6.2-C or in the case of gas services
of their products. This information should
• fixed to studs, not sheathing publications from the Institution of Gas
also be made available for reference
• spaced at a maximum of 600mm Engineers and Managers (www.igem.org.uk).
on site so that work can be carried out
horizontally and 450mm vertically
satisfactorily in accordance with the design
• spaced at jambs of openings and at CONTROL OF FIRE and specification.
movement joints in masonry a maximum
of 300mm vertically within 225mm of 6.2 - D7 Walls and panels shall resist The fixing schedule should allow for every
the masonry reveal or movement joint. the spread of fire structural connection made on site including
In this case additional studs may be For guidance on the prevention of fire fixing details for framing, wall ties, breather
needed during construction see ‘Fire Prevention membrane, sheathing and vapour control
• spaced within 225mm of the top of a on Construction Sites’ jointly published by layers, and should show as appropriate:
masonry wall the Construction Federation and the Fire • number and spacing of nails and staples
• inclined away from the sheathing so Protection Association (www.thefpa.co.uk) • size and type of nail including material
that the slope is maintained following and guidance from the UKTFA under the and corrosion protection
differential movement. ‘Site Safety Strategy’ that presents fire risk • method of nailing (eg skew, end, etc.).
management publications such as the ‘16
(c) movement between the timber frame Where the wall design relies on
Steps to Fire Safety’ and the ‘Design Guide
wall and other elements. plasterboard to take racking forces those
to Separation Distances’ (www.uktfa.com).
walls should be clearly defined and the
Differential movement
All elements should have adequate fire type and centres of the fixings stated.
During the first two years after erection,
resistance.
the timber frame will reduce in overall Copies of the fixing schedule should be
height as it dries out. The anticipated Service mains should not pass through given to the person doing the job.
amount of shrinkage of the timber frame is separating wall cavities.
given in Appendix 6.2-C. 6.2 - D9 Design of the superstructure
In Scotland services are not permitted shall be checked by an NHBC timber
Movement between the timber frame and within a timber framed separating wall. frame certifier
other parts of the construction will occur at:
• door and window openings Service outlets should not impair the fire The superstructure design should be
• eaves and verges resistance of floors and walls. placed with an NHBC approved timber
• balconies (including Juliet balconies) frame certifier so that a certificate can be
Items to be taken into account include:
• openings for drive-throughs issued in accordance with Appendix 6.2-A.
(a) cavity barriers
• staircases and lift shaft enclosures
6.2
The design should detail the position and
(where they are not timber framed)
• service entries
materials for cavity barriers in accordance MATERIALS STANDARDS
with relevant Building Regulations.
• the interface of the timber frame with 6.2 - M1 All materials shall:
any other construction. Horizontal cavity barriers (except under (a) meet the Technical Requirements
eaves) should be protected with a dpc tray. (b) take account of the design
Appendix 6.2-C provides guidance on the
The tray should have a minimum upstand
anticipated amount of shrinkage of the Materials that comply with the design and
of 100mm. Alternatively polyethylene
timber frame and where it will occur between the guidance below will be acceptable for
encased cavity barriers providing a minimum
other parts of the structure. The extent of external timber framed walls including
upstand of 100mm should be used.
the differential movement increases with the wall panels and dwellings which are
number of storeys. Movement gaps should be Dpcs should be used to cover horizontal substantially timber framed.
filled with suitable materials to take up the and vertical cavity barriers and to shed
expected movement. The manufacturer of the moisture away from the sheathing. Typical Materials should comply with all relevant
material should be consulted on the suitability details are shown in Clause S8. standards, including those listed below.
for the extent of the movement expected. Where no standard exists, Technical
Vertical timber cavity barriers should be Requirement R3 applies (see Chapter
Where the movement gap is expected to protected from penetrating moisture by a 1.1 ‘Introduction to the Standards and
be more than 35mm it should be protected dpc. Technical Requirements’).
by a cover strip.
(b) fire-stops References to British Standards and Codes
All claddings that are fixed direct to the The design should detail the position of Practice include those made under the
timber frame, should have a horizontal and type of fire-stops in accordance with Construction Products Directive (89/106/
movement joint at each floor level. See relevant Building Regulations. EEC) and, in particular, appropriate
Appendix 6.2-C European Technical Specifications
A typical fire-stop detail is shown in
Masonry claddings should not be approved by a European Committee for
Clause S8.
supported by the timber frame. Standardisation (CEN).
• dry graded and marked in accordance of providing adequate resistance to fire INSULATION
with BS 4978. and smoke
6.2 - M11 Insulation materials shall
I-studs should be assessed in accordance Materials specified in statutory provide the degree of insulation to
with Technical Requirement R3. requirements are acceptable. comply with the design and statutory
Other materials may be used if requirements
TIMBER PRESERVATION satisfactorily assessed in accordance with Wall insulation should be of a type that
6.2 - M3 Timber shall be either naturally Technical Requirement R3. ‘breathes’, eg mineral wool (rock or glass).
durable or preservative treated to Other insulation used in walls should be
provide adequate protection against rot HOLDING DOWN DEVICES assessed in accordance with Technical
and insect attack Requirement R3 for use in timber frame
6.2 - M7 Holding down devices shall be
wall panels.
Timber preservation should be in of durable material
accordance with Chapter 2.3 ‘Timber
Holding down devices should be
preservation (natural solid timber)’.
manufactured from: SITEWORK STANDARDS
I-studs manufactured from timber of • austenitic stainless steel to BS EN
10088-1, minimum grade 1.4301 6.2 - S1 All sitework shall:
durability class ‘moderately durable’ or
• galvanised mild steel with zinc coating (a) meet the Technical Requirements
lower should be preservative treated in
to BS EN ISO 1461, minimum coating 940 (b) take account of the design
accordance with Chapter 2.3 ‘Timber
g/m2 on each side. (c) follow established good practice and
preservation (natural solid timber).
workmanship
Sole plate anchors within the internal
SHEATHING envelope should be galvanised mild steel, All relevant information in a form suitable
minimum coating Z275. for the use of site operatives should be
6.2 - M4 Sheathing shall be durable available on site before construction starts
and capable of providing structural All holding down devices should be as including:
resistance to racking detailed in the design. • full set of drawings
The following materials are acceptable: • materials specification
• plywood in accordance with BS EN 636 NAILS AND STAPLES • fixing schedules
and BS EN 13986 table 7 • nailing details
6.2 - M8 Nails and staples shall be • manufacturers’ recommendations
• oriented strand board in accordance
durable and of the correct type to relating to proprietary items.
with BS EN 300 type OSB/3 or 4
provide adequate mechanical fixing
• moisture-resistant chipboard in
accordance with BS EN 312 type P5 or P7. Staples for fixing breather membranes
CONSTRUCTION
• medium board in accordance with BS EN should be austenitic stainless steel or 6.2 - S2 Construction shall ensure that
622-3 type MBH.HLS1 or MBH.HLS2. other material of similar strength and the building is structurally adequate
• impregnated soft board in accordance corrosion resistance.
6.2
If head binders are not provided, joists and Masonry claddings should not be
roof trusses, including girder trusses and supported by the timber frame.
other similar loads, should bear directly
over studs. Individual studs should be not (g) prefabricated chimneys
ledge protected
by breather less than 37mm wide, at maximum 600mm Prefabricated chimneys should either be
membrane
centres, unless other adequate support is supported by:
provided for wall boards and fixings. • the masonry cladding, or
frame set back
12mm maximum • the timber frame, including any roof
from edge of A lintel and cripple studs should be construction supported by the timber
supporting structure
(20mm for 140mm provided to any opening in loadbearing frame.
wide studs) panels except when the opening does
not affect the stud spacing or where the (h) cavities
supported loads are carried by a rim beam A cavity should be provided to reduce
or perimeter joist. the risk of rain penetrating to the frame.
(b) anchoring the frame The following minimum cavity widths,
The frame should be anchored to resist Unless otherwise clearly specified by the measured between the cladding and
both lateral movement and uplift. Care designer, multiple studs should be included sheathing, should be provided:
should be taken to avoid splitting timber to support multiple joists.
plates or damaging the substructure.
Cladding Minimum cavity width
(d) supporting claddings
When shotfiring, care should be taken not Wall ties should be in accordance with the Masonry 50mm nominal
to spall edges of masonry or slabs. When design and fixed to studs. Render on backed 25mm nominal
shotfiring into masonry, solid concrete lathing
blocks with a minimum crushing strength Battens supporting lightweight cladding Vertical tile No vertical cavity
of 7.3N/mm 2should be used, positioned to should be fixed to studs. hanging without required when a breather
receive fixings. underlay membrane is fitted to the
(e) fixing plasterboard sheathing
Plasterboard should be fixed in accordance Other cladding* 15mm
with Chapter 8.2 ‘Wall and ceiling finishes’
(Sitework) unless the design specifies *See Chapter 6.9 ‘Curtain walling and
closer fixing centres cladding’.
dpc
Particular care should be taken at A clear cavity for at least 150mm below
the junction between walls and roofs. dpc should be maintained. Weep holes (eg
Reference should be made to Chapter 8.2 open perpends) should be provided where
‘Wall and ceiling finishes’ (Sitework). necessary to prevent water build up in the
FIXING TO PLATE cavity.
(f) movement between timber frame wall
and other elements BREATHER MEMBRANES
6.2
The timber frame will reduce in overall
height as it dries out. The anticipated 6.2 - S3 Breather membranes shall
amount of shrinkage of the timber frame where required protect the sheathing
and where it will occur between other from dampness
parts of the structure is given in Appendix Special attention should be given to the
6.2-C. following details:
Movement will occur at: • laps, which should be at least 100mm on
• door and window openings horizontal joints and 150mm on vertical
• eaves and verges joints as shown in the following diagram
• balconies (including Juliet balconies) • direction of laps - upper layers should
• openings for drive-throughs be fixed over lower layers to ensure rain
• staircases and lift enclosures (where runs away from the sheathing. Vertical
they are not timber framed) joints should be staggered wherever
• service entries possible
• the interface of the timber frame with • fixing should be at regular intervals to
FIXING TO STUDS any other construction. prevent damage by wind and should
be not more than 600mm centres
The extent of the differential movement horizontally, 300mm centres vertically
increases with the number of storeys. and 150mm centres around openings
Movement gaps should be filled with • marking the stud positions for wall tie
(c) fixing panels
suitable materials to take up the expected fixing
All fixings, including nailed joints and
movement. The manufacturer of the • shedding water away from the lowest
sheathing, should be as scheduled in the
material should be consulted on the timber
design.
suitability for the extent of the movement • use of self extinguishing grade
Wall panels should be securely fixed expected. membrane
together and to floor and roof framing. • use of high performance breather
Where the movement gap is expected to
membrane in areas of Very Severe
Sole plates and head binders should be be more than 35mm it should be protected
exposure to wind driven rain (as
provided to bind the panels together. by a cover strip.
defined in Appendix 6.1-A) (unless the
Joints in sole plates and head binders
All claddings that are fixed directly to the alternatives given in Design Clause D4(c)
should not coincide with those between
timber frame, should have a horizontal are adopted)
panels. Joints in head binders should occur
movement joint at each floor level. See • use of fixings described in Chapter 6.2
over a stud.
Appendix 6.2-C. (Materials).
used. Where vapour control plasterboard ‘Site Safety Strategy’ that presents fire risk
is used joints between sheets should be management publications such as the ‘16
positioned on studs or noggings and the
Steps to Fire Safety’ and the ‘Design Guide
joints should be filled, taped and finished.
to Separation Distances’ (www.uktfa.com)’.
Where polyethylene is used all joints in the
vapour control layer should have at least CAVITY BARRIERS
100mm laps and be located on studs or Cavity barriers should be installed in
WALL TIES noggings. positions detailed by the design and
6.2 - S4 Wall ties shall be correctly relevant Building Regulations.
Vapour control layers should be fixed at
installed
250mm centres to the top and bottom of Cavity barriers should be formed of
• of the type specified in the design the frame, at laps and around openings. materials specified in the design. If no
• fixed to the studs not the sheathing specification is available the advice of the
When cutting vapour control plasterboard
• be sufficiently flexible or of a type that designer should be obtained.
care should be taken not to displace the
fully permits differential movement vapour control material.
• be kept clean and free from mortar Horizontal cavity barriers (except under
droppings Any holes made in a vapour control layer eaves) should be protected with a dpc tray.
• spaced at a maximum of 600mm should be made good. The tray should have a minimum upstand of
horizontally and 450mm vertically 100mm. Alternatively polyethylene encased
The vapour control layer should cover the cavity barriers providing a minimum
• spaced at jambs of openings and at external framed wall area including rails,
movement joints in masonry a maximum upstand of 100mm should be used.
studs, reveals, lintels and sills.
of 300mm vertically within 225mm of
the masonry reveal or movement joint The vapour control layer should lap with
• spaced within 225mm of the top of a the dpc.
masonry wall breather membrane
• inclined away from the sheathing so CLADDING lapped over dpc tray
6.2 - S5 Insulation shall be correctly Horizontal battens, which obstruct the dpc
Vertical timber cavity barriers should be confirming that he has assessed the 2 Bedding of sole plate
protected from moisture by a dpc. structural adequacy of the timber frame bottom member
of wall panel
superstructure for a specific project.
The completed and signed certificate must
be given to the registered builder.
Certifiers must be suitably qualified civil sole plate
dpc
or structural engineers with at least
mortar bed
three years’ experience in timber frame
construction and Chapter 6.2 ‘External
timber framed walls’. The certifier must
not be the designer of the timber frame.
Where the design is four storeys or more
and the floor joists are solid timber the
design is to be submitted to NHBC. The sole plate is laid and levelled on a
FIRE-STOPPING Applications to become a timber frame continuous bed of mortar, prior to the
Fire-stops should be installed in positions certifier should be made to NHBC erection of the wall panels. The bedding
detailed in the design and relevant Building Standards and Technical. should extend the full width of the sole
Regulations. plate. Care is needed to ensure that the
Registered builders bedding is not disturbed during the fixing
Only those materials specified in the
Registered builders should ensure that of the sole plate.
design should be used for fire-stopping.
the completed timber frame certificate is
If details of fire-stop design, location and available on site for inspection by NHBC. 3 Doube sole plate ‘sandwich’
bottom member
materials are not available they should of wall panel
be verified with the designer before
construction commences. Appendix 6.2-B
fire-stop between
battens above
underlay Packing under sole plates
fire-stop below
The finished surface of the substructure sole plate
underlay supporting the timber frame should be permanent
packing
reasonably level. However, where packing under
temporary each stud
is required to ensure the timber frame spacers
or sole plate is level, the following three
alternative options are acceptable.
6.2
The options given are for packing up to
20mm. Packing exceeding 20mm should
be agreed between the timber frame
The lower sole plate is fixed to follow the
manufacturer’s engineer and NHBC.
contours of the supporting structure.
cavity barrier cavity barrier The upper sole plate is fixed on top and
of mineral wool or in wall between 1 Permanent structural packing under
fire-resisting board buildings levelled with temporary spacers inserted
in boxed eaves sole plate
bottom member between the sole plates. Once the first lift
of wall panel construction has been erected permanent
SERVICES packing is inserted under each load point
(e.g. stud or post).
6.2 - S9 Services shall not reduce sole plate
the fire resistance or stability of the Because this method introduces an
dwelling temporary additional sole plate the extra shrinkage
spacer
grout or permanent
should be taken into account. See
Service outlets should not impair the fire packing under Appendix 6.2-C.
resistance of floors and walls. each stud
Appendix 6.2-C
DIFFERENTIAL MOVEMENT
INTRODUCTION
During the first two years after erection the timber frame will reduce in overall height as it dries out. Movement will occur between the timber
frame and other parts of the structure.
This Appendix contains:
• guidance on differential movement of the timber frame, and
• common details for timber frame construction where differential movement will take place.
The sketches show examples of typical interfaces and illustrate general design principles.
In the absence of project specific calculations the gaps shown in the following table, are required:
Notes
6.2
Stud
Sole plate
Structural decking
Movement
Headbinder
Closing gap
Top rail of panel
Stud
COMMON DETAILS
The following sketches show examples of
typical construction details and illustrate
general principles relating to differential
movement.
Further information is available from the
UKTFA document ‘Guidance on detailing
to accommodate differential movement
in timber frame buildings’. This UKTFA
publication includes guidance on: Sill not
built into Sill not
masonry built into
• the interface between a lift shaft and the Allow for masonry Allow for
movement
timber frame movement
6.2
Timber frame
movement
Allow for
movement
Allow for
movement
6.2
Timber frame
movement
Allow for
movement
Timber frame
movement
Allow for
movement
Allow
for
movement
75mm
minimum
6.2
Timber
frame
movement
TIMBER FRAME INTERFACE WITH CONCRETE OR MASONRY STAIRS AND COMMON AREAS
Timber
Transition piece frame
movement
EAVES
(movement gaps in excess of 35mm should be protected by cover strips)
Timber
frame
movement
Allow for
movement
VERGE
Timber
Allow for frame
movement movement
6.2
SERVICES
Timber
frame
Service passing through wall movement
Allow for
movement
DRIVE THROUGH
Timber
frame
movement
Lintel/beam
Lintel/beam
6.2
Ceiling
Ceiling
Allow for
movement
Section A - A
Timber
frame
movement
Allow for
movement
Ceiling Ceiling
Drive through
Drive through
Section B - B
BALCONY ABUTMENTS
(movement gaps in excess of 35mm should be protected by cover strips)
Allow for
movement
Decking
Allow for
movement
Balcony structure
Decking Timber independant of timber frame
frame
movement
Balcony structure
independant of timber frame
Allow for
movement
Gap
Allow for
Timber movement
Allow for
frame
Allow for movement
movement
movement
Slotted
holes Slotted
holes
6.2
Juliet balcony
15mm*
Movement across
floor zone
Allow for
15mm*
15mm*
movement
Cavity
Timber
Allow for
frame
movement
movement
6.2
After movement
As built
75mm
Allow for minimum
movement
Timber
frame
movement
INDEX
A I T
Anchoring frame 1, 5 Information 3 Timber 3
B Insulation 2, 4, 6 Timber cladding 2
Balconies 14 J Timber framing 2
Breather membranes 4, 5 Joints 1 V
C L Vapour control layer 2, 4, 6
Cavities 2, 5 Loadbearing walls 1 Verge 12
Cavity barriers 3, 4, 6 M W
Certification 7 Membranes 2 Wall ties 2, 4, 6
Chimneys 11 Moisture 4 Window reveals 9
Cladding 5, 6, 10, 11, 15 Movement 3, 5 Window heads 10, 11
D N Window sill 11
Damp proof courses 1 Nails 4
Differential movement 7, 8 P
Drive through 13 Panels, fixing 5
E Plasterboard, fixing 5
Eaves 12 Preservative treatment 2, 4
Exterior cladding 2 Packing 7
F Prefabricated chimneys 3, 5
Fire control 3, 6 S
Fire-stops 3, 4, 7 Services 3, 7, 12
Fixings 4, 5 Setting out 4
Flat roof 15 Sheathing 4
H Stairs interface 11
Holding down devices 4 Staples 4
6.2
Structural elements 1
Sole plates 7
Internal walls
Part 6 Superstructure (excluding roofs)
Chapter 6.3
6.3
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
Internal walls
CONTENTS SCOPE
DESIGN Clause Page This Chapter gives guidance on meeting the Technical
Requirements and recommendations for internal walls,
Design standards D1 1 including separating walls and compartment walls.
Statutory requirements D2 1
Loadbearing masonry walls D3 1
Loadbearing timber walls D4 2
Beams and lintels D5 2
Non-loadbearing internal partitions D6 2
Fire resistance D7 2
Movement joints D8 3
Sound insulation D9 3
Damp-proofing D10 4
Fireplaces and flues D11 4
Provision of information D12-D13 4
MATERIALS
Materials standards M1 4
Masonry materials M2 5
Wall ties and related items M3 5
Timber M4-M5 5
Plasterboard M6 5
Proprietary systems M7 5
Damp-proof courses M8 5
Sound insulation materials M9 5
Fire-stopping materials M10 6
Fireplaces and flues M11 6
6.3
SITEWORK
Sitework standards S1 6
Damp-proof courses S2 6
Masonry partitions S3 6
Timber stud partitions S4 7
Proprietary partitions S5 8
Separating walls S6 8
Partitions to rooms containing a WC S7 8
Walls providing fire resistance S8 9
Chimneys, flues and linings S9 9
INDEX 9
6.3
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
Internal walls
6.3
Sleeper walls should be designed and restraint straps equivalent fixings, at maximum 300mm
at 2m centres
constructed as described in Chapter 4.4 to each floor vertical centres.
‘Strip and trench fill foundations’ (each
section). The external wall cavity should be closed
at least 450mm
at the junction with the separating wall
Where necessary, oversite concrete should with a flexible cavity stop, unless the cavity
be protected against sulfate attack by is fully filled with built-in insulation (where
the use of a polyethylene sheet dpm, not permitted).
less than 1200 gauge (0.3mm), (or 1000
Timber joists with a minimum of 90mm
gauge (0.25mm) if assessed in accordance (e) movement joints
bearing normally provide adequate lateral
with Technical Requirement R3) properly For guidance on the design of movement
restraint.
lapped. joints, reference should be made to Clause
Where timber joists are not built into a D8.
Loadbearing walls built off a concrete
masonry wall, restraint should be provided
groundbearing slab are acceptable only if (f) wall ties for cavity separating walls
at 2m centres by means of either:
the concrete forms part of a foundation Normally, the two leaves of a masonry
• restraint type joist hangers to BS EN
which is designed by an Engineer in cavity separating wall should be tied
845-1 with performance equivalent to a
accordance with Technical Requirement together to provide structural stability.
restraint strap, or
R5. The type of tie and spacing should limit
• restraint straps with a cross section of at
least 30mm x 5mm. the sound transmission across the cavity.
Foundation design should take account of
Reference should be made to Clause D9
any site investigation or ground hazards.
Where restraint is required and restraint- for details.
(b) structural elements type hangers are not used, straps should
be: In England and Wales, separating walls may
Bricks and blocks should be selected in be built in accordance with Robust Details
accordance with their intended use. The • at least 300mm long on each joist
• fixed with four fixings to each joist “Resistance to the passage of sound”.
table below gives recommended strengths
of bricks and blocks to be used in buildings • not more than 2m apart.
up to 3 storeys high:
Internal walls
LOADBEARING TIMBER type of tie and spacing should limit sound (b) movement joints
transmission across the cavity. Reference should be made to Clause D8.
WALLS
To limit sound transmission, metal tie (c) method of supporting partition
6.3 - D4 Loadbearing timber internal straps should be: Walls and partitions should be supported
walls shall be designed to support and • not more than 3mm thick by the structural floor, not by a floating
transfer loads to foundations safely and • fixed below ceiling level floor that incorporates a compressible
without undue movement • spaced at least 1.2m apart horizontally. layer, unless the material is specifically
Structural design of loadbearing timber manufactured for that purpose.
Thicker ties, fixed at ceiling level or
walls should be in accordance with BS EN
more closely spaced will increase sound Preferably, masonry partitions should be
1995-1-1
transmission across the cavity. supported on:
Structural timber should be specified • other masonry partitions or walls
according to the strength classes in BS BEAMS AND LINTELS (wherever possible the design of
EN 338, eg C16 or C24. When using the dwellings should be such that first floor
BS 4978 grading rules, the timber species 6.3 - D5 Beams and lintels shall be
masonry partitions are a continuation of
should be in accordance with BS EN 1912 adequate for their purpose those on the ground floor)
or strength class specified. The strength Items to be taken into account include: • concrete floors
classes can then be determined from BS (a) loads and spans • steel or concrete beams.
EN 338 Loads and spans should be either Where steel or concrete beams are to be
Items to be taken into account include: in accordance with manufacturers’ used, it may be necessary to use padstones
recommendations or designed by an at bearings.
(a) provision of foundations
Engineer in accordance with Technical
Foundations should be provided as for
Requirement R5. Masonry partitions should not be
structural masonry walls (see Clause
supported by timber joists or beams,
D3(a)). (b) materials unless they have been designed by an
Concrete or steel lintels are suitable for Engineer in accordance with Technical
(b) structural elements
use in masonry walls. Timber lintels should Requirement R5.
Normally, individual studs, sills and
not be used to support masonry.
headplates should be 38mm x 75mm. The design should make allowance for the
Larger timber section sizes may be Lintels should extend beyond each end of relatively flexible nature of the timber and
required in order to achieve an adequate openings in masonry as follows: the relatively rigid nature of masonry.
level of fire resistance. Studs should be
spaced at maximum 600mm centres. Span [m] Minimum length of bearing Where stud partitions or proprietary
[mm] plasterboard partitions are supported by
A lintel and cripple studs should be Up to 1.2 100 a timber floor, extra noggings or joists
provided to any opening except when should be specified, unless it can be shown
Over 1.2 150
the stud spacing is unaffected. Normally, that the deck can transfer the load without
6.3
multiple studs should be provided to Where structurally necessary, padstones undue movement.
support multiple joists. should be provided under the bearings of
Allowance should be made for the
Where internal walls are made up of lintels and beams. Reference should be
possible deflection of floors at the head
panels, structural continuity should be made to Chapter 6.5 ‘Steelwork support to
of partitions to prevent the partition
maintained, for example by the use of a upper floors and partitions’.
becoming loadbearing.
continuous top binder.
NON-LOADBEARING
INTERNAL PARTITIONS
6.3 - D6 Non-loadbearing partitions
continuous
shall have adequate strength and be
top binder adequately supported floor deflects gap for
when loaded possible
Items to be taken into account include: deflection
Internal walls
Items to be taken into account include: made to Chapter 6.2 ‘External timber methods, where permitted, cannot enter
(a) fire resistance of internal walls framed walls’ for further information. the separating wall cavity.
In houses up to 2 storeys, the following
In masonry cavity separating walls, where
walls should be fire-resisting: MOVEMENT JOINTS the cavity is up to 75mm, flexible wall ties
• loadbearing walls (half-hour minimum)
6.3 - D8 Masonry walls shall, where should be used, such as:
• separating walls (one hour minimum)
necessary, be provided with movement • butterfly type ties, or
• walls between a house and an integral or
joints • ties assessed for the purpose.
attached garage (half-hour minimum).
Movement joints should be provided in Where structural design permits, the
In houses of 3 or more storeys, in addition
straight unbroken lengths of wall as shown omission of ties will enhance sound
to the above, the walls enclosing the
in the following table: insulation.
staircase should have half-hour fire
resistance. Type of brick Joint width Normal spacing
Ties should be spaced 900mm horizontally
or block [mm] and 450mm vertically. Closer spacing
For flats, the following walls should be
Clay brick 16 12m (15m max)
will increase sound transmission. Wider
fire-resisting:
spacing may impair structural stability.
• loadbearing walls within the flat (half- Calcium 10 7.5 to 9m
silicate brick
Rigid ties transmit sound more readily than
hour for up to 2 storeys, one hour for 3
flexible ties.
or more storeys) Concrete 10 6m
• separating walls, compartment walls and block and Chases for services should be kept to a
walls enclosing protected shafts, such as brick minimum and be well filled with mortar.
staircases (normally one hour)
• other walls enclosing hallways within Movement joints in foundations should be (c) flanking transmission
flats, half-hour. continued through the superstructure. The construction of the flanking wall,
including the position of openings in it, will
(b) fire-stopping SOUND INSULATION have an impact on sound transmission.
Fire-resisting walls should be fire-stopped The requirements of statutory regulations
or constructed to resist fire spread: 6.3 - D9 Internal walls shall, where should be followed.
• at their perimeter necessary, have adequate resistance to
• at junctions with other fire-resisting the transmission of sound (d) partitions to rooms containing a WC
walls, floors and roofs Items to be taken into account include: The guidance below applies in Scotland,
• where openings are formed for doors, Northern Ireland and the Isle of Man. In
(a) all separating walls
pipes, etc. England and Wales reference should be
In England and Wales, separating walls
made to statutory requirements.
The following details should be designed may be built in accordance with Robust
carefully: Details Part E “Resistance to the passage PARTITION PERFORMANCE
• the junction between a separating or of sound”. Any partition between a room containing
compartment wall and a pitched roof or For details of separating walls in timber a WC and a living room, dining room, study
6.3
a flat roof frame construction, reference should be or bedroom should have a weighted sound
• where pipes and cables penetrate a fire- made to Chapter 6.2 ‘External timber reduction index of not less than 38dB over
resisting wall (reference should also be framed walls’. the frequency range 100-3150Hz, when
made to Chapter 8.1 ‘Internal services’ tested in accordance with BS EN ISO 140-4.
(Design and Sitework)). To ensure an adequate level of sound This does not apply to a partition between
insulation for masonry separating walls: a WC and a bedroom where the WC forms
The wall dividing an integral or attached • statutory requirements may permit the
garage and the floor above should act an en-suite facility to the bedroom.
building in of joist ends into separating
together to provide adequate resistance to walls. Where permitted there should be The following methods of construction
fire spread. If there is either no ceiling or a mortar joint around the joist perimeter will achieve the performance level stated
no floor to the space above the ceiling to and the face of the joint pointed with above.
the garage, vertical fire separation may be silicone sealant
required. • all joints in the separating wall should be BLOCKWORK PARTITIONS
fully filled with mortar Blocks having a density of not less than
When fire-stopping against timber
• flexible cavity stops should be provided 600kg/m3 finished on both sides with
construction, it is important to specify
at the junction of separating walls with 13mm of plaster are acceptable.
compressible material, such as mineral
wool, to allow timber shrinkage to take external walls Blockwork should be tied in every course
place without affecting the fire-stopping. • avoid any reduction in the thickness of to adjoining walls, with the joints filled
masonry, but where this is unavoidable, solid.
(c) provision of cavity barriers eg to accommodate electrical sockets,
All internal walls of hollow or cavity positions on opposite sides of the For details of bonding and tying, reference
construction, whether fire-resisting or not, separating wall should be staggered. should be made to Sitework clause 6.3 -
should have cavity barriers installed at S3(d).
their perimeter and at junctions with fire- Care should be taken when specifying
resisting floors and walls. dry lining to masonry separating walls. TIMBER STUDWORK
The thickness of plasterboard layers, Timber studwork is acceptable if used
For cavity separating walls of masonry the method of fixing and sealing may be with one of the following combinations of
construction, the top of the wall needs to critical. For fixing details, reference should materials:
be closed for fire resistance. be made to BS 8212.
Timber framed separating walls should (b) cavity separating walls
be specified with cavity barriers of wire Cavity separating walls should be
reinforced mineral wool at junctions with constructed so that any external cavity
floors and ceilings. Reference should be wall insulation placed by blown or pumped
Internal walls
cavity separating
wall FIREPLACES AND FLUES
6.3 - D11 Fireplaces and flues
membranes
and dpcs
See Chapter 6.8 ‘Fireplaces, chimneys and
linked flues’.
two layers one layer of
of 12.5mm 12.5mm protection to
vertical dpm
plasterboard
each side
+
plasterboard
each side
+
PROVISION OF
no insulation 25mm
mineral
wool quilt
INFORMATION
dpm
6.3 - D12 Designs and specifications
shall be produced in a clearly
concrete cavity
fill below dpc understandable format and include all
relevant information
Drawings should give full information,
including:
• wall layout, with all dimensions shown
• position and size of openings and lintels
Dpcs should be included below the • details at junctions, indicating fire-
following: stopping where applicable
5mm plaster
coat on one
one layer of
12mm • non-loadbearing partitions built off an • details of wall constructions and
layer of
9.5mm
panel board
each side in-situ ground slab with a dpm applied to materials, ties and restraints
plasterboard
each side
+
75mm the top of the slab • details of foundations where required.
+ mineral wool
25mm quilt
mineral wool 6.3 - D13 All relevant information shall
quilt
screed on be distributed to appropriate personnel
dpm above
partition on dpc slab
above polyethylene Ensure that design and specification
dpm
information is issued to site supervisors
and relevant specialist subcontractors and/
or suppliers.
Other forms of timber studwork
construction will be acceptable provided Where proprietary components are to be
the criteria given under PARTITION used, manufacturers usually have specific
PERFORMANCE is achieved and requirements for fixing and/or assembly
independent evidence of performance is of their products. This information should
available at the request of NHBC. also be made available for reference
on site so that work can be carried out
6.3
Internal walls
When used in loadbearing partitions, with the manufacturer’s recommendations, For sound-resisting walls (separating
blocks should have the minimum provided those of the masonry walls and walls to WC compartments), the
compressive strength required by manufacturer agree. correct thickness, number of layers of
the design. The table below gives plasterboard sheets and sealing should be
recommended strengths of blocks to be WALL TIES AND RELATED specified (see Design clause 6.3 - D9).
used in specific cases: ITEMS Tapered edge boards should be used where
Height of wall Minimum compressive 6.3 - M3 Walls ties and related items the plasterboard is to be jointed only
strength of block unit shall be of the appropriate type and before decoration.
1 or 2 storeys blocks - 2.9N/mm2 strength and shall have adequate Dry lining systems should comply with
Lowest storey of blocks - 7.3N/mm2 durability BS 8212. Reference should be made to
a 3 storey wall or (unless calculations show Chapter 8.2 ‘Wall and ceiling finishes’ (each
where individual that lower strengths are WALL TIES FOR SEPARATING WALLS
storeys exceed
section) for further details.
suitable) Wall ties should either:
2.7m
• be butterfly type, or
Upper storeys of 3 blocks - 2.9N/mm2 • have been tested to show that PROPRIETARY SYSTEMS
storey wall their design meets with statutory 6.3 - M7 Prefabricated proprietary
requirements. partition systems shall be suitable for
Where buildings are more than 3 storeys their purpose
Wall ties for timber frame separating walls
in height, masonry should be designed in
should be not more than 40mm x 3mm in Proprietary partitions should be specified
accordance with Technical Requirement R5
cross section. in accordance with the manufacturer’s
using the block strength specified by the
recommendations.
designer. HANGERS, STRAPS, ETC
Joist hangers, restraint straps, bond ties,
The maximum loadbearing capacity
etc should be protected against corrosion.
DAMP-PROOF COURSES
of the wall should not exceed the
recommendations of the manufacturer. Ferrous metals with the following levels of 6.3 - M8 Materials for damp-proofing
protection are acceptable: shall adequately resist the passage of
In some partitions to WC compartments
6.3
• post-galvanizing to BS 729, or moisture
and all separating walls, blocks should have • pre-galvanizing to BS 2989. Materials which are acceptable for use as
at least the minimum density required by
Restraint straps for use in masonry dpcs include:
the design in order to achieve the required
construction should have a minimum cross • bitumen to BS 6398
sound insulation.
section of 30mm x 5mm. • polyethylene to BS 6515
Where special blocks/pipes are • proprietary materials assessed in
used for flues, the manufacturer’s accordance with Technical Requirement
recommendations should be checked.
TIMBER R3.
Special materials may be required around 6.3 - M4 Timber shall be of the
appropriate grades and sizes to support Dpcs should be not less than the width of
the blocks/pipes.
the imposed loads the wall or partition.
(b) bricks
Preferably, regularised timber should
Bricks should comply with the relevant
be used for stud partitions. Structural
SOUND INSULATION
British Standards:
• clay bricks should comply with BS EN timber should be specified according to MATERIALS
771-1 the strength classes in BS EN 338, eg C16 6.3 - M9 Materials used for sound
• calcium silicate bricks should comply or C24. When using the BS 4978 grading insulation shall be of a suitable
with BS EN 771-2 rules, the timber species should be thickness and density
• concrete bricks should comply with BS included in accordance with BS EN 1912 or
class strength specified. The strength class Normally, mineral wool quilt should be
EN 771-3.
can then be determined from BS EN 338. used for acoustic insulation in partitions.
When used in a separating wall, bricks The thickness and density should be as
should have at least the minimum density Finger joints should comply with BS EN required by the design.
required by the design. A lighter brick 385 and timber for dry lining with BS 8212.
may not provide a suitable level of sound 6.3 - M5 Timber shall have a suitable
resistance.
moisture content
For bricks suitable for use in chimneys To minimise drying shrinkage, timber
reference should be made to Chapter 6.8 should have a moisture content not
‘Fireplaces, chimneys and flues’. greater than 20%.
(c) mortar Structural softwood for internal use should
A mortar of 1 : 1 : 5½, cement : lime : sand, be dry graded to BS 4978 and marked
with plasticiser is suitable for both internal ‘DRY’ or ‘KD’.
and external walls.
Internal walls
Internal walls
6.3
(g) restraint strapping other and to abutting walls. Noggings
Joists built into masonry walls provide or extra studs should be used, where
adequate lateral restraint. necessary.
Restraint straps may be required by the
incorrect use of different masonry types
design. If so, they should be fitted before
new masonry is built above.
the manufacturer.
Partitions should be fixed at head and base
TIMBER STUD PARTITIONS to noggings or joists.
Internal walls
fixing to
nogging
Fixing and finishing plasterboard partitions TIMBER SEPARATING WALLS
should be in accordance with Chapter 8.2 The design details should be carefully
‘Wall and ceiling finishes’ (Sitework). followed. There should be no gaps in the:
• mineral wool quilt
PROPRIETARY PARTITIONS • plasterboard layers
• fire-stopping.
6.3 - S5 Proprietary partitions
shall be erected in accordance with Services should not penetrate the
manufacturers’ recommendations plasterboard layers. They should be fixed
in front of the plasterboard.
Partitioning should be correctly positioned,
square and plumb. The manufacturer’s PARTITIONS TO ROOMS
recommended construction sequence
fixing to
nogging
should be followed.
CONTAINING A WC
6.3 - S7 Partitions to rooms containing
Timber or other additional fixings should a WC shall provide adequate sound
be provided for radiators, electrical outlets,
insulation, where required by the design
switches and the like.
The guidance below applies in Scotland,
Northern Ireland and the Isle of Man. In
SEPARATING WALLS England and Wales the design should be
6.3 - S6 Construction of separating checked to see how sound insulation is to
walls shall ensure adequate sound be achieved.
PARTITION PARALLEL TO JOIST insulation
A partition between a room containing
fixing to joist MASONRY SEPARATING WALLS a WC and a living room, dining room,
The correct density of block should be study or bedroom (except where the WC
used. Holes, voids, even hairline cracks, is en-suite) should have adequate sound
can significantly reduce the effectiveness insulation.
of a sound-insulating wall.
Most masonry partitions provide adequate
To maintain sound insulation: sound insulation without additional
• fully fill all mortar beds and perpends treatment.
• use only butterfly or other approved wall
Some methods of providing adequate
ties for cavities up to 75mm wide
sound insulation with a timber stud
• space wall ties 900mm minimum
partition are shown below:
horizontally and 450mm minimum
vertically
• stagger the positions of electrical socket
6.3
against ceiling joists or roof trusses. This joist perimeter with silicone sealant as
does not allow for ceiling deflection/ required by the design
movement and can damage the ceiling • chases for services should be well filled
boards. with mortar.
Partitions should not be over-wedged at floor Solid separating walls should be taken
level. This could damage floor boarding. through the inner leaf of a cavity external
Noggings should be provided to support wall using metal ties to provide rigidity.
fittings, such as radiators, wall mounted However, if the same blocks are used for
boilers, sanitary fittings, kitchen units, etc. both walls, tooth bonding is acceptable.
5mm plaster one layer of
coat on one 12mm
layer of panel board
separating wall taken 9.5mm each side
through and tied to inner leaf plasterboard +
dense each side 75mm
block + mineral wool
separating 25mm quilt
wall mineral wool
quilt
nogging
supports
radiator
Where two layers of plasterboard are used,
the joints should be staggered and the
joints in the outer layer properly filled.
lightweight block inner leaf
Proprietary plasterboard partitions usually
need an additional layer of plasterboard
to one or both sides of the partition to
provide adequate sound insulation.
Internal walls
6.3
It is important that a cavity barrier is
provided within boxed eaves. The cavity
barrier should be wire reinforced mineral
wool blanket, at least 50mm thick, nailed
to the rafter and carefully cut to shape to
fully seal the boxed eaves.
Internal walls
INDEX
A J S
Additives 6 Joints 6 Separating walls 1, 2, 3, 5
B Joist hangers 5 Services 7, 9
Beams 7 L Setting out 6, 7
Blockwork 3 Lateral restraint 1 Sound insulation 3, 5
Bonding 1, 6 Lintels 7 Studwork 3
Bricks 5 M Support 2, 7
C Masonry 5, 6, 8 T
Cavity barriers 3 Moisture resistance 4, 5, 6 Timber 5
Cavity walls 1, 3 Mortar 5, 6 Timber stud partitions 7
Chasing 7 Movement joints 1, 2, 3 Timber walls 2, 8
Chimneys 9 P Tying 1, 6
Concrete blocks 5 Partitions 2, 3, 4, 6 W
D Plasterboard 5 Wall ties 1, 2, 5
Damp proofing 4, 6 Precast blocks 5 WCs 3, 8
Durability 5 Proprietary systems 5 Workmanship 6, 7
F R
Fireplaces 4, 6 Restraint straps 5, 7
Fire stopping 3, 6
Fixings 4, 7
Flanking transmission, 3
sound
Flues 4, 6, 9
Foundations 1, 2
6.3
CONTENTS
MATERIALS
Materials standards M1 4
Timber floors M2-M4 4
Joist hangers and restraint straps M5 5
Strutting M6 5
Floor decking M7 5
Sound insulation M8 5
Structural steel in floors M9 5
6.4
SITEWORK
Sitework standards S1 5
Timber floors S2 5
Joist hangers S3-S4 6
Trimmed and trimming joists S5-S6 6-7
Multiple joists S7 7
Strutting of floors S8 8
Notching and drilling S9 9
Restraint strapping S10-S12 9 - 10
Overlapping and butted joists S13 10
Floor decking: general S14-S16 10
Softwood boarding S17 11
Chipboard flooring S18-S19 11
Oriented strand board flooring S20 11
Plywood flooring S21 11
Other floor decking S22 12
Floors between dwellings S23 12
Concrete floors S24-S25 12
In-situ concrete S26 12
Precast concrete S27 12
Fire-stopping S28 13
6.4
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
6.4
imposed when the building is in use. They (b) joist sizes
include the weight of furniture and people. Solid timber joist sizes are given in the
BS EN 1991-1-1 recommends an imposed span tables in BS 8103-3. Where the
loading allowance of 1.5kN/m2 for self tables do not apply or where there are
contained dwellings. concentrated loads, floor joists should be
designed by an Engineer in accordance
Where the design includes communal areas
with Technical Requirement R5.
serving flats or maisonettes, refer to BS EN uprights at
1991-1-1 for recommended imposed loads. end bearing
Regularised timber is recommended for
floor joists. The section sizes in the tables
Information concerning balconies is given
reproduced in Appendix 6.4-A should be
in Chapter 7.1 ‘Flat roofs and balconies’
regularised, or be ALS or CLS to enable
(Design and Sitework).
floors and ceilings to be level.
(b) supporting structure I-joists and metal web joists should
The floor structure should have an be specified in accordance with
adequate bearing on the supporting manufacturers’ instructions.
structure. Timber joists should normally
have a minimum bearing as shown in the (c) joist spacing
table. Joists should not be spaced at centres
Type of timber Minimum bearing [mm]
uprights at
intermediate bearing
greater than 600mm.
joist End support Intermediate When planning joist spacings, a clearance
support of 25mm to 75mm between the first joist
Solid joist on 90 (75) 90 (75) and the wall face should be allowed. This
masonry walls Joists may be supported on joist hangers helps when installing services and fixing
Solid joist on 75 75 or on internal load bearing walls. Where floorboards.
timber wall plate permitted they may be built into the inner
I-joist 90 (45) 90 leaf of an external cavity wall. Where joists (d) support of lightweight partitions
Metal web joist 90 (75) 90 are built into the inner leaf care should be Multiple solid timber joists supporting
taken to ensure air-tightness. Where solid lightweight non-loadbearing partitions
Note timber joists are built into solid external running parallel to the joists should be
Figures in brackets should only be used walls, they should be pre-treated with suitably fixed together (see Sitework
when the joist is not providing restraint to preservative in accordance with Chapter clause 6.4 -S7).
the wall. 2.3 ‘Timber preservation (natural solid
I-joists and metal web joists should either: TRIMMER JOISTS STRUTTING OF FLOOR
• be positioned centrally below a non-
loadbearing partition (if necessary 6.4 - D5 Adequately sized trimmer JOISTS
they can be doubled or tripled up in joists shall be provided around floor 6.4 - D6 Strutting shall be adequate
accordance with the manufacturer’s openings to distribute loads and limit movement
instructions), or Trimmed openings may be needed around within floors.
• support the weight of the non- staircase openings and chimneys. Solid
loadbearing partition by noggings or Herringbone strutting or blocking should
trimmed joists may be supported using
bearers to the two adjacent joists. be provided at the ends of solid joists
either:
Unless designed otherwise the noggings where they:
• joist hangers
should not be less than 38 x 90mm • bear onto steelwork
• notches
at 600mm centres and fixed with • bear onto intermediate walls
• support battens (light loading only)
metal clips.The sole plate of the non- • are supported on joist hangers.
• tusked tenon joints.
loadbearing partition should be fixed to Where solid joists span over 2.5m
the noggings. I-joists and metal web trimmed joists
additional strutting should also be
may be supported using joist hangers. If
specified as follows:
an I-joist is used as a trimmer to support
another I-joist, backer blocks should be Joist span [m] Rows of strutting
provided on both sides of the web of the
Under 2.5 none needed
trimmer.
I - joist 2.5 to 4.5 1 (at centre of span)
Over 4.5 2 (at equal spacing)
following table;
metal web
For metal web joists: required. In buildings of not more than two Flanges of metal web joists should not
• the hanger should be the full depth of storeys where restraint type joist hangers, be notched. Joists can bear directly into
the joist and restrain the top flange or, assessed in accordance with Technical the steel beam if there is at least 75mm
• top flange restraint should be provided Requirement R3 are used or where joists bearing on the bottom flange of the steel
(see Sitework clause 6.4-S4). are built into a wall and bear at least beam. Timber uprights should be provided
90mm on the wall no restraint straps are between the flanges and 38mm x 97mm
A timber upright should be fixed between
required along the joists. noggings should be provided between the
the flanges of metal web joists.
uprights. If the bearing is less than 75mm
Joist hangers should meet with the STRUCTURAL STEELWORK metal web joists can be supported on their
requirements of BS EN 845-1 or be top flange and their bottom flange should
assessed in accordance with Technical
IN FLOORS be fixed to timber blocking supported on
Requirement R3. The manufacturers of 6.4 - D11 Steelwork in floors shall be the inside of the steel beam.
I-joists and metal web joists shouldbe designed by an Engineer
consulted about joist hangers suitable for
Structural steelwork should be in
their range of products.
accordance with Chapter 6.5 ‘Steelwork
If low strength masonry is used, the support to upper floors and partitions’
timber blocking
loading on the top flange of the joist (each section), or should be designed by to support metal
web joists
hanger should not be greater than the an Engineer in accordance with Technical
strength of the supporting masonry. Requirement R5.
6.4 - D8 Adequate end bearings shall be Where steelwork supports solid timber
provided for joists and joist hangers joists, the depth ofthe timber joists should
be such that they can be notched and
The design should detail the type of have 12mm/2mm projections to allow for
support to be used for joists, trimmers and shrinkage of the timber.
trimming joists. at least 12mm projection
6.4
at least 2mm projection
different specification for the ceiling than
that for solid timber joists to achieve the
JOIST SUPPORT AT Structural continuity of the floor should be same fire resistance.
provided by the use of continuous decking
SEPARATING WALLS fixed to joists on both sides of a transverse Ceilings should not be perforated (e.g.
steel joist. for downlighters) unless it can be shown
6.4 - D9 Joists shall be correctly
that the floor construction achieves the
supported at masonry separating walls
Steel sizes should allow adequate bearing required fire resistance.
Joists built into separating walls may for timber joists, where required.
provide lateral support but it can conflict 6.4 - D13 Structural timber shall be
with sound insulation and fire resistance Where steelwork supports I-joists, the located away from heat sources
requirements in England & Wales. joists may bear directly into the steel beam
if there is at least 45mm bearing on the Combustible material should be kept
In Scotland joists should not be built into bottom flange of the steel beam. Noggings away from heat sourcesas described in
separating walls. (38mm x thickness of flange) should be Chapter 6.8 ‘Fireplaces, chimneys and
provided at the top and bottom flanges flues’ (Design and Sitework). In particular,
structural timber should be at least 40mm
RESTRAINT STRAPS of the I-joists. If the bearing is less than
from the outer surface of a masonry
45mm timber blocking should be fixed
6.4 - D10 Adequate restraint strapping to the steel beam to enable the I-joists to chimney or fireplace recess. Floorboards
shall be provided be face fixed using joist hangers to the may be closer than 40mm from the
blocking inside the steel beam. chimney wall.
Restraint straps and/or joist hangers
suitable for taking tensile forces may be
required to tie the walls and upper floors
= at least 40mm
together. Restraint straps at not more than
2m centres should be provided along the
walls that run parallel to the joists.
BS 8103-1 gives details of the connections
between structural elements.
The position and size of restraint straps
should be shown on drawings.
structural timber
Where joists are supported on hangers kept away from
chimney wall
restraint straps along the direction of the
joists at not more than 2m centres are
resistant flooring Type P5 to BS EN 312 also specified so that the strength class
For upper floors, the drawings should can be determined.
throughout the dwelling. Oriented strand show:
board should be Type OSB3 to BS EN300. • direction of floor span and size Finger joints should comply with BS EN
and spacing of joists or concrete 385.
(c) fixing
Adequate support and correct fixings components
Where possible, regularised timber should
should be specified in accordance with • size of trimmers and trimming joists
be used for joists.
the manufacturer’s recommendations. All • position of strutting
butt joints should be supported by joists or • openings in the floor I-joists and metal web joists should be
noggings. Nail length should be 2½ times • supporting walls below assessed in accordance with Technical
the thickness of the decking material. • walls and partitions above Requirement R3.
• positions of restraint straps
Some decking materials require their joints • positions of large service penetrations, 6.4 - M3 Structural timber shall be
to be glued together and glued to joists eg chimneys, SVPs of suitable durability, particularly in
(see Sitework clauses 6.4 - S19 and S20). • position of insulation conditions where it could become damp
• details at all junctions. Timber that is built into solid external
(d) sound insulation
Where the floor decking contributes to walls or embedded should be pre-treated
6.4 - D19 All relevant information shall
the sound insulation of a floor within a with preservative. Reference should be
be distributed to appropriate personnel
dwelling, the thickness of the decking made to Chapter 2.3 ‘Timber preservation
Ensure that design and specification (natural solid timber)’ (each section) for
given in (a) above may not achieve a
information is issued to site supervisors recommended methods of preservative
mass of 15 kg/m2. Alternatively the floor
and relevant specialist subcontractors and/ treatment.
construction may have been tested to
or suppliers.
show adequacy. Any timber treated with preservative and
Where proprietary components are to be cut after treatment should be given two
CONCRETE FLOORS used, manufacturers may have specific liberal applications of a suitable colour
requirements for fixing and/or assembly tinted preservative to the cut surfaces.
6.4 - D15 Concrete floors shall be of their products. This information should
designed to transmit loads to the also be made available for reference 6.4 - M4 Structural timber shall have a
supporting structure without undue on site so that work can be carried out suitable moisture content
movement satisfactorily, in accordance with the Structural softwood for internal use should
Design should be in accordance with design and specification. be dry graded to BS 4978 or BS EN 519
Clause D3. and marked ‘DRY’ or ‘KD’.
6.4
38mm, or be stored on bearers or in racks and be
• solid strutting at least 38mm thick and CONCRETE AND protected.
at least three-quarters the depth of the
joist. REINFORCEMENT
store timber off
Proprietary metal strutting should 6.4 - M10 Concrete shall have ground on bearers
support support
sides of the web if the hanger does not
restrain the top flange of an I-joist. Flanges of I-joists should not be notched.
Solid joist on 90 (75) 90 (75)
masonry walls Where joist hangers are supported on Tabs of the hanger should be bent and
Solid joist on 75 75 lightweight blockwork, the suitability of the nailed to the bottom flange of the I-joist.
timber wall plate hanger should be checked. Joist hangers
I-joist 90 (45) 90 which meet BS EN 845 are stamped on
Metal web joist 90 (75) 90 the base or gusset with the minimum
compressive strength of block for which
Note they are suitable, eg 2.9N/mm2 or 3.6N/
Figures in brackets should only be used mm2. Where hangers are to BS EN 845-1
when the joist is not providing restraint to ensure the supporting masonry is that
the wall. specified in the design.
Bearings should be level. If joists are not Joist hangers should be supported on level
laid level, the floor will be springy and beds and should be tight to the wall.
uneven. Where bearings are uneven, joists
The masonry course to carry the joist
should be levelled using hard packing, eg
hangers should be checked for level and
tiles or slates bedded in mortar. Loose or
height. Hangers should not be cut into the
soft packing should not be used.
walling. tabs on hanger bent over
For further information concerning timber and nailed to flange
Where restraint type joist hangers
framed construction, reference should
are shown in the design do not use
6.4
staircase
trimmer heavy duty hanger
timber to timber hanger
trimming
joists
6.4 - S4 Joists shall be properly cut to
length and fitted to joist hangers
joists levelled from staircase trimmer or trimming joist
Joists should be accurately cut to length
for a tight fit. Solid joists should be
(f) joist spacings notched into the hanger to keep the ceiling
Joist spacing should be as shown on the line level.
drawings. If the joist spacing is not shown,
the designer should provide spacing
details. Do not increase the spacing.
Joists should not be spaced at more than
600mm centres. The decking material to top flange restraint
be used should be taken into account.
(g) clearance from the wall All circular holes in the vertical sides of
When placing joists, a clearance of 25mm joist hangers should be fully nailed.
to 75mm should be allowed between the When joist hangers are used at both ends
first joist and the wall face. This helps of a joist, measuring, marking and cutting
when installing services and fixing floor should be accurate to ensure the joist fits
decking. properly at both ends.
TRIMMED AND TRIMMING Flanges of I-joists should not be notched be fixed to the steel beam to enable the
and should be supported on trimmers I-joists to be face fixed using joist hangers
JOISTS by ‘timber-to-timber’ hangers. Timber to the blocking inside the steel beam.
6.4 - S5 Trimmed and trimming joists blocking should be used to face fix a joist
shall be properly supported to a trimmer joist.
single or double
trimmer as required
by the design
timber blocking
6.4
to support
metal web joists
TIMBER-TO-TIMBER JOIST HANGER
timber upright
NAILED
For lightly loaded trimmed joists, support
nails at approx
battens (plates) may be used. 20mm from top
and bottom
of joist
lightly loaded
trimmed joist
at least 2mm projection
Fixings should be to the Engineer’s should not project beyond the top and (c) joists supported by hangers
specification and should be given a second bottom edges of joists. Solid blocking should be used at all joist
check for tightness just before fixing the bearings of solid timber joists where they
At the end of each run of strutting the last
ceiling. are not built into brickwork or blockwork.
joist should be firmly blocked to the wall.
This includes some forms of timber frame
Toothed plate, split ring and shear
construction. The blocking may be used for
plate connectors should be used in
fixing plasterboard and floor decking.
strict accordance with manufacturers’
recommendations. blocking
SPLIT RING
TOOTHED PLATE herringbone strutting
SHEAR PLATE
should be used with bolts. Check whether solid timber joists. are not built into blockwork
toothed connectors are required between Where metal web joists require strutting it
the timber faces. Ensure that all washers, (d) I-joists and metal web joists
should be in accordance with the following
etc are provided. supported on walls
table:
Bolts should be checked for tightness Noggings should be provided for I-joists
Joist span [m] Rows of bracing and metal web joists at the top flange
(fixing bolts should not be used for
tightening). Make sure that timber is not 4.0 to 8.0 1 (at centre of span) along the wall to support the floor decking.
damaged by over-tightening. Over 8.0 2 (at equal spacing) Noggings at the bottom flange may be
required to support the plasterboard
I-joists can be doubled or tripled up For metal web joists, bracing (strongbacks) ceiling.
in accordance with manufacturer’s should be provided.
recommendations to support a lightweight
partition or to form trimmers. The design
should specify how the joists are fixed
together.
bracing (strongback)
6.4
STRUTTING OF FLOOR
JOISTS
6.4 - S8 Appropriate strutting shall be
provided to joists, where required
solid strutting
Items to be taken into account include:
(a) span of the floor
Strutting should be provided where I-joists
Strutting for solid timber joists should be
bear directly onto the bottom flange of the
provided before laying floor decking as
steel beam. Noggings (38mm x thickness
follows:
of flange) should be provided at the top
Joist span [m] Rows of strutting and bottom flanges of the I-joists. Strutting
is not necessary when an infill timber perimeter nogging
Up to 2.5 none needed
blocking is fixed to the steel beam and
2.5 to 4.5 1 (at centre of span) joists hangers of full depth of the joists are
Over 4.5 2 (at equal spacing) used to face fix the joists to the blocking.
For solid timber joists either herringbone Strutting should be provided where metal
strutting (38mm x 38mm timber) or web joists bear directly on to the bottom
minimum 38mm thick solid strutting flange of the steel beam. Timber uprights
should be used, for not less than three- should be provided between the flanges
quarters the depth of the joist. Strutting and 38mm x 97mm noggings should be
provided between the uprights.
notches on top in a
zone between 0.1
and 0.2 x span
RESTRAINT STRAPPING noggings for I-joists
6.4
accordance with Technical Requirement
R3. (See clause 6.4 -S12 for fixing details).
Where joists run parallel to the wall, straps In buildings of not more than two storeys
should be supported on noggings fixed where joists are supported on walls,
between the three joists adjacent to the restraint straps will not normally be
wall. required at the ends of joists, if there is at
least 90mm bearing (eg if they are built
Solid timber joists should have noggings
into masonry).
at least 100mm between not less than 0.5 times the depth of the
notches and holes
joists if the strap is located on top of the Separate straps should be fitted along the
joists but the full depth if located beneath joists and at centres not more than 2m
the joists. unless the joist hangers are designed to
provide restraint.
I-joists should have solid timber noggings
not less than 0.5 times the depth of the
Special instructions should be obtained I-joists up to a maximum of 150mm, fixed
from the designer when notching and between the webs and located beneath
drilling: the top flange of the I-joists when 30mm joist hanger
• is required in joists deeper than 250mm x 5mm galvanised straps are used. Where
• does not meet the above guidelines, or straps which have been assessed in
• is needed close to heavy loads, such as accordance with Technical Requirement
those from partitions, cisterns, cylinders R3 are used the noggings should be short
and stair trimming. lengths of I-joist or solid timber noggings restraint strap
held tight
against blockwork
If structural strength is impaired by to the full depth of the I-joists.
notching or drilling, the element should be Metal web joists should have solid timber
replaced or correctly repaired. noggings, size 35mm x 97mm, used
beneath the top flange of the metal web
(b) I-joists
joists and twice nailed to the joists.
In I-joists pre-formed holes are provided
in the timber webs for pipes and cables. Straps should be placed at a maximum of
Other holes or notches should not be cut 2m apart and carried over the three joists.
without the approval of the manufacturer. Packing should be provided between the
However, restraint straps can be slotted into wall and the first joist.
webs immediately below the top flange.
OVERLAPPING AND
BUTTED JOISTS
6.4 - S13 Joists shall be properly fixed
at intermediate load bearing walls
Items to be taken into account include:
(a) solid timber joists
Where joists overlap on load bearing
intermediate walls, they should be
nailed together and cut so that they
will not project beyond the supporting
wall by more than 100mm. This is to
prevent the floor decking being pushed
up or the ceiling being cracked when intermediate support for
metal web joists
the cantilevered part of the joist moves
I-joist with restraint strap upwards.
SOFTWOOD BOARDING 6.4 - S19 Chipboard flooring shall be Projecting ends of boards should be cut
securely fixed back to form a butt joint on a joist.
6.4 - S17 Softwood boarding shall be
securely fixed ALL TYPES OF CHIPBOARD To reduce squeaking, tongued and grooved
Chipboard should be supported and joints between boards should be glued and
End (butt) joints should be made on joists the boards should be glued to the joists. A
fixed in accordance with manufacturers’
and staggered, ie the joints of adjacent suitable polyvinyl acetate (PVAC) adhesive
instructions, using either:
boards should not be on the same joist. should be used.
• flat-headed ring shank nails minimum
3mm diameter and of length 2½ times
the thickness of the chipboard, or
• screws, to BS 1210 with a minimum
length of twice the board thickness and
not less than size no. 8.
Edges at room perimeters should be
supported on joists or noggings.
Fixings should be spaced at centres
not more than 300mm apart along the
joist continuously supported edges and the joist or nogging
intermediate supports.
Expansion gaps should be not less than
10mm wide where boards abut a rigid
Board thickness should not be less upstand. For larger areas of boarded floor
than the following for the joist spacings a wider gap may be needed at upstands ORIENTED STRAND BOARD
indicated: and intermediate expansion gaps equal to
2mm per linear metre of floor provided.
FLOORING
Board thickness Maximum joist centres 6.4 - S20 Oriented strand board flooring
[mm] [mm] shall be securely fixed
16 450
Oriented strand board should be laid over
19 600
supports in the direction indicated on the
boards. The stronger axis should be laid at
Boards should be cramped up and either expansion gap at least 10mm right angles to the supporting joists.
double nailed or secret nailed to each joist.
Nails should be of a length 2½ times the All square edges should be supported. All
thickness of the decking and should be short edges should be supported on the
punched well below the surface. centre line of the joist. It is not necessary
6.4
to support the long edges of tongued and
The above thicknesses may not be
grooved boards, except at room perimeters
adequate to achieve a mass for floor
where all board edges should be fully
boarding of 15 kg/m2 for sound insulation
supported.
requirements of floors in England & Wales.
No boards less than two joist spacings long
CHIPBOARD FLOORING should be used.
6.4 - S18 Chipboard flooring shall be of Nails should be flat headed, annular
SQUARE EDGED BOARDS AND BOARDS grooved nails 3mm in diameter.
the type and thickness specified
WITH LOOSE TONGUES
Only moisture-resistant, Type P5 chipboard Boards should be supported on all sides on Expansion gaps should be not less than
to BS EN 312 should be used for flooring. joists or noggings. 10mm wide where boards abut a rigid
This can be recognised by the green stripe upstand. For larger areas of boarded floor
on the chipboard edge and an identifying a wider gap may be needed at upstands
marking. and intermediate expansion gaps equal to
2mm per linear metre of floor provided.
Board thicknesses should be not less
than the following for the joist spacings To reduce squeaking, tongued and grooved
indicated: joints between boards should be glued and
the boards should be glued to the joists. A
Board thickness Maximum joist centres suitable polyvinyl acetate (PVAC) adhesive
[mm] [mm] should be used.
18/20 450
22 600 nogging PLYWOOD FLOORING
The above thicknesses may not be 6.4 - S21 Plywood decking shall be
adequate to achieve a mass for floor securely fixed
decking of 15 kg/m2 for sound insulation Plywood should be laid with the face grain
requirements of floors in England & Wales. at right angles to the supports. All butt
TONGUED AND GROOVED BOARDS
Boards should be laid with long edges at joints and joints with loose tongues should
right angles to joists. be supported on joists or noggings. All
end joints should occur over joists (38mm
Short edges should be supported on joists minimum thickness) or noggings.
or noggings.
Board thickness should be not less CONCRETE FLOORS Beam layout drawings should always be
than the following for the joist spacings followed. Doubled beams usually support
indicated: 6.4 - S24 Concrete upper floors shall be concentrated loads, such as partitions.
constructed/erected in accordance with
Board thickness Maximum joist centres the design. (d) propping of beams and planks during
[mm] [mm] construction
Care should be taken to ensure that
12 450 Where floors rely on structural topping or
concrete floors are reasonably level and
16 600 in-situ make-up sections, propping may
smooth. Particular care should be taken at
be needed until the in-situ concrete has
doorways and junctions.
The above thicknesses may not be reached its design strength.
adequate to achieve a mass for floor 6.4 - S25 Appropriate measures shall be
(e) grouting of joints
decking of 15 kg/m2 for sound insulation taken when concreting or screeding in
Most precast floors rely on a grout to
requirements of floors in England & Wales. cold weather
ensure composite action of the units and
Nails for fixing plywood should be either: Reference should be made to Chapter 1.4 provide adequate strength, as well as fire
• plain wire nails - minimum diameter ‘Cold weatherworking’. and sound resistance.
3.35mm
The manufacturer’s specification should be
-- minimum length 65mm IN-SITU CONCRETE checked for the grout mix.
-- with penetration not less than 40mm,
or 6.4 - S26 Reinforced concrete upper
(f) restraint straps and ties
• annular-ring shank nails - minimum floors shall be constructed in accordance
Restraint straps should be shown on the
diameter 3mm with design details
drawings. They are usually necessary
-- minimum length 50mm All concrete work should be in accordance where the beams run parallel with the wall.
-- penetration not less than 32mm. with Chapter 2.1 ‘Concrete and its
reinforcement’ (each section).
Fixings should be at 150mm centres (max)
around the perimeter and 300mm centres The Builder should not depart from the
(max) on intermediate supports. design without the Engineer’s written
consent.
An expansion gap of at least 1.5 - 2mm at least 450mm straps at not more
should be allowed between each panel. than 2m centres
PRECAST CONCRETE
OTHER FLOOR DECKING 6.4 - S27 Precast concrete upper floors
shall be erected in accordance with
6.4 - S22 Proprietary flooring materials
design details
shall be securely fixed strap tight
to blockwork
precast beam
6.4
them. The partitions should be fixed
through the floor decking into the joist(s)
beneath. In tables 1 and 2, one additional
joist is generally sufficient. Where two
additional joists are needed, the spans
are markedwith an asterisk (eg 1.76*). For
similar lightweight partitions which run
at right-angles to the joists, the maximum
spans in Tables 1 and 2 should be reduced
by 10%. For all other additional loads, joist
sizes should be designed by an Engineer
in accordance with Technical Requirement
R3.
Table 1 - Permissible clear spans for domestic floor joists - strength class C16
Imposed load not exceeding 1.5 kN/m2
Service Class 1 or 2
63 170 3.94* 3.79* 3.45 3.72* 3.58* 3.25 3.26 3.13 2.84
63 195 4.50* 4.33* 3.94 4.25* 4.09* 3.72 3.73 3.58 3.25
63 220 5.06* 4.87* 4.44 4.78* 4.60* 4.18 4.20 4.04 3.66
75 120 2.96* 2.85* 2.59 2.79* 2.69* 2.44 2.45 2.35 2.09
75 145 3.56* 3.43* 3.12 3.37* 3.24* 2.94 2.95 2.84 2.57
75 170 4.16* 4.01* 3.65 3.93* 3.79* 3.44 3.45 3.32 3.01
75 195 4.75* 4.58* 4.17 4.49* 4.33* 3.94 3.95 3.80 3.45
75 220 5.34* 5.15* 4.70 5.05* 4.87* 4.43 4.45 4.28 3.88
ALS/CLS
38 140 2.75* 2.64* 2.39 2.59* 2.49* 2.21 2.24 2.13 1.88
38 184 3.60* 3.46* 3.14 3.39* 3.26* 2.95 2.96 2.84 2.56
38 235 4.58* 4.40* 3.99 4.32* 4.15* 3.76 3.77 3.62 3.27
89 184 4.74* 4.57* 4.17 4.48* 4.32* 3.94 3.95 3.80 3.45
89 235 5.99* 5.78* 5.29 5.68* 5.48* 5.00 5.01 4.83 4.39
* Two additional joists required Normal bearing of 40mm to be doubled
Table 2 - Permissible clear spans for domestic floor joists - strength class C24
Imposed load not exceeding qk = 1.5 kN/m2 or Qk = 0.90 kN
Service Class 1 or 2
6.4
63 170 4.37* 4.21* 3.84 4.13* 3.98* 3.62 3.63 3.49 3.17
63 195 5.00* 4.81* 4.39 4.72* 4.55* 4.14 4.15 4.00 3.62
63 220 5.61* 5.41* 4.94 5.31* 5.12* 4.66 4.68 4.50 4.08
75 120 3.29* 3.17* 2.88 3.11* 2.99* 2.72 2.73 2.62 2.38
75 145 3.96* 3.81* 3.48 3.74* 3.60* 3.28 3.29 3.16 2.87
75 170 4.62* 4.45* 4.06 4.37* 4.21* 3.83 3.85 3.70 3.36
75 195 5.27* 5.08* 4.64 4.99* 4.81* 4.38 4.40 4.23 3.85
75 220 5.92* 5.71* 5.22 5.61* 5.41* 4.93 4.95 4.76 4.33
ALS/CLS
38 140 3.07* 2.95* 2.67 2.89* 2.77* 2.51 2.52 2.42 2.15
38 184 4.01* 3.86* 3.50 3.78* 3.63* 3.29 3.31 3.17 2.87
38 235 5.10* 4.90* 4.46 4.81* 4.62* 4.20 4.21 4.04 3.65
89 184 5.25* 5.07* 4.63 4.98* 4.80* 4.38 4.39 4.23 3.85
89 235 6.64* 6.41* 5.87 6.30* 6.08* 5.56 5.57 5.37 4.89
* Two additional joists required Normal bearing of 40mm to be doubled
INDEX
B J S
Bearings 3, 6, 8, 12 Joist hangers 2, 5, 6, 8 Separating walls 3
Boarding 10, 11 Joist sizes 1 Shrinkage 2
C Joist spacing 1, 4, 6 Sound transmission 4, 5
Chimneys 3 L Span 1, 8
Chipboard 11 Levelling 6 Strength class 1
Clearance 6 Lightweight partitions 1 Structural steel 3, 5, 7
Concrete 4, 5, 12 M Strutting 2, 5, 8
D Masonry partitions 2 Supporting structure 1
Dead loads 1 Metal web joists 7, 8, 9, 10 T
Decking 4, 5, 10, 11 Moisture 4, 5 Timber floors 4, 5
Drilling 9 Multiple joists 7 Timber joists 9, 10
E N Trimming joists 2, 6
End bearings 3 Notching 9
F O
Fire spread 3 Oriented strand board 11
Fire-stopping 13 Overlapping joists 10
Fixings 4 P
Floating floors 12 Plywood 11
Flooring 3 Pre-cast concrete 12
I Proprietary systems 5, 12
Imposed loads 4 R
In-situ concrete 12 Reinforcement 5, 12
I-joists 7, 8, 9, 10 Restraint strapping 3, 5, 9, 12
6.4
Steelwork
Part 6 Superstructure (excluding roofs)
Chapter 6.5
6.5
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
Steelwork
CONTENTS SCOPE
DESIGN Clause Page This Chapter gives guidance on meeting the Technical
Requirements and recommendations for steelwork to support
Design standards D1 1
masonry partitions, timber floors and to trim floor voids.
Structural design D2 1
Padstones D3 1
MATERIALS
Materials standards M1 1
Steelwork M2 1
Padstones M3 1
Connections M4 1
SITEWORK
Sitework standards S1 2
Steelwork S2-S3 2
APPENDIX 6.5-A
Design tables for support of masonry 2
partitions (no floor loads)
Table 1 - Load of partition to be 2
supported
Table 2 - Size of steel beam supporting 2
partition
Table 3 - Size of padstone 3
APPENDIX 6.5-B
6.5
APPENDIX 6.5-C
Connection of beams supporting 5
floors
INDEX 5
6.5
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
Steelwork
DESIGN STANDARDS
(d) steelwork to steelwork connection STEELWORK
Connections between steel beams should
be designed. 6.5 - M2 Steelwork shall be of sufficient
6.5 - D1 Design shall meet the Technical strength and durability
Requirements Where appropriate, steelwork beam-to-beam
connections should be in accordance with Steelwork will be acceptable if it complies
Design that follows the guidance below will with Clause M1 above and is based on:
Appendix 6.5-C.
be acceptable for steelwork supporting
either masonry partitions or floors. Appendix 6.5-C uses bolted connections BS 4 Part 1 Structural steel sections :
(using black bolts) or welding. Connections Specification for hot-rolled
STRUCTURAL DESIGN requiring the use of other forms of sections, or
connection (such as high strength friction
6.5 - D2 Steelwork shall be designed grip bolts) should be designed by an BS 4848 Specification for hot-rolled
to support and transmit loads to the Engineer in accordance with Technical structural steel sections.
supporting structure without undue Requirement R5.
movement or deflection To ensure durability, steelwork should be
(e) durability given a protective coating system. For
Steelwork (including its support and any steelwork which is to be bolted (using black
Steelwork should be given a protective
connections) should be either: bolts) or not connected, an acceptable
coating system to ensure durability. For
• designed by an Engineer in accordance coating system is one coat of high build
details, refer to Sitework clause 6.5-S3.
with Technical Requirement R5, or zinc phosphate primer and one coat of
• where appropriate, detailed according to (f) fire resistance bituminous paint. Where welding is to be
the designs shown in this Chapter. Steelwork should be provided with the carried out, use the protective coating
The designs shown in this Chapter are in level of fire resistance required by Building system specified by the designer.
accordance with BS EN 1993-1-1 using grade Regulations.
S275 steel and therefore meet statutory PADSTONES
requirements. PADSTONES 6.5 - M3 Padstones shall distribute point
It should be noted that the information 6.5 - D3 Padstones shall distribute point loads safely to the supporting structure
given in this Chapter has been prepared loads safely to the supporting structure
Details of padstones are given in Table 3,
primarily to assist builders in providing
Where a steel beam is supported by Appendix 6.5-A and Table 5, Appendix 6.5-B.
proper support to masonry partitions and
masonry, a padstone may be required to For the design of padstones see Design
floors. The designs given will not always be
spread the load over a sufficiently large area section, clause D2.
the most economic and an engineer may be
of the masonry to prevent overstressing.
able to design a smaller section beam for a
particular situation.
A padstone may be necessary (see Table 3, CONNECTIONS
Appendix 6.5-A and Table 5, Appendix 6.5-B
Items to be taken into account include: for sizes). 6.5 - M4 Connections shall be chosen to
be capable of supporting and transmitting
6.5
(a) support of masonry partitions Where the inner leaf is used to provide a the intended loads
Where appropriate, masonry partitions major contribution to the thermal insulation
may be supported by steelwork selected in of a cavity wall, any padstone that is needed Connections should comply with the design.
accordance with Appendix 6.5-A. should have similar thermal properties to the Bolts will be acceptable if they comply with
masonry used for the rest of the inner leaf the design and are based on the relevant
Care should be taken during construction to
or precautions should be taken to prevent British Standards, including:
avoid the problem of out-of-true masonry
being only partly supported by steelwork. cold bridging.
BS 4190 Specification for ISO metric
(b) support of floors black hexagon bolts, screws
Timber floors can be supported by steelwork. MATERIALS STANDARDS and nuts
Steelwork
Items to be taken into account include: If any of the above limitations are not met, steelwork should be designed in accordance with
(a) the section size and grade detailed in Technical Requirement R5.
the design Method of applying tables
When materials are delivered to site, check
that they conform with either: 1 Check that the situation is within all the limitations detailed above.
• the Engineer’s design, or 2 Identify the masonry partition construction and thickness.
• the steelwork sizes given in the 3 Use Table 1 to establish the load per metre run.
Appendices to this Chapter. 4 Check the span of the beam(s).
5 Use Table 2 to determine a suitable steel section size.
(b) bearings 6 Check whether padstones are required - see Table 3.
Bearings for steelwork should be:
• at least 100mm, and (To help in applying the tables, a worked example is given at the end of this Appendix.)
• clean, dry and level.
Padstones may be required in accordance
Table 1 - Load of partition to be supported
with: Type of masonry for supported Maximum masonry density Structural thickness [mm]
• the Engineer’s design, or partition (not more than 2.7m high [kg/m3]
100 90 75
• the guidance given in Table 3, Appendix and plastered both sides)
6.5-A and Table 5, Appendix 6.5-B. Load [kN/m run]
6.5
Steelwork
6.5
outer
padstone If any of the above limitations are not
met, steelwork should be designed by an
inner
Engineer in accordance with Technical
100mm steel beam
padstone Requirement R5.
-opening 3.8m
-min 100mm bearing
at each end
100mm Method of applying tables
Procedure 1 Check that the situation is within all the
1 Using information about the supported wall and Table 1: limitations detailed above.
• load per metre run = 4.2kN/m. 2 Using Figure 1, determine the area
2 Using the load per metre run, the span of the beam and Table 2: supported by the beam(s).
• suitable section size = 178 x 102 x 19 UB (The alternative 152 x 152 x 23 UC is not suitable 3 Check the span of the beam(s).
as it is too wide for the inner padstone/wall.) 4 Use Table 4 to determine a suitable steel
3 Using information about the wall supporting the beam (100mm thick), the walls supported section size.
by the beam (medium density block) and Table 3: 5 Check whether padstones are required
• minimum padstone size = 155mm long by Table 5.
6 If steel beam-to-steel beam connections
= 150 mm deep
are required, use Appendix 6.5-C.
• outer padstone (beam at right angles to wall):
- minimum length = 155mm
(as this is greater than the flange dimension of the steel section obtained in 2 above -
102mm - a padstone is required to distribute the load)
- minimum depth = 150mm
- thickness = 100mm, to match blockwork
(The actual length and depth of a padstone could be greater to suit masonry coursing.)
• inner padstone (beam in line with the wall):
- minimum length = 200mm (see Note 2 to Table 3)
- minimum depth = 150mm
- thickness = 100mm, to match blockwork.
Note
Beam supports should not occur above window or door openings
Steelwork
Figure 1 - Effective areas supported by Table 4 - Size of steel beam supporting floor
steel beams Effective Effective Smallest suitable steel section size
If any area shown as ‘void’ contains a staircase, add 2m2 to the area trimmer span (mm x mm x kg/m)
supported = clear span +
effective area supported by any beam which supports (partially or Universal beam Universal column
(m2) 100mm (m)
fully) that staircase.
0 to 20 0 to 2.0 127 x 76 x 13 152 x 152 x 23
B
0 to 20 2 to 2.5 127 x 76 x 13 152 x 152 x 23
20 to 30 152 x 89 x 16 152 x 152 x 23
0 to 10 2.5 to 3 127 x 76 x 13 152 x 152 x 23
10 to 20 152 x 89 x 16 152 x 152 x 23
A A
20 to 30 178 x 102 x 19 152 x 152 x 23
wall wall
under under
B 0 to 10 3 to 3.5 127 x 76 x 13 152 x 152 x 23
A A 10 to 30 178 x 102 x 19 152 x 152 x 23
30 to 40 203 x 133 x 25 152 x 152 x 30
0 to 10 3.5 to 4 152 x 89 x 16 152 x 152 x 23
Beam Effective area Beam Effective area 10 to 20 178 x 102 x 19 152 x 152 x 23
AA AA +
20 to 30 203 x 102 x 23 152 x 152 x 23
30 to 40 203 x 102 x 30 152 x 152 x 30
BB 40 to 50 see Note 1 152 x 152 x 37
0 to 10 4 to 4.5 203 x 102 x 23 152 x 152 x 23
10 to 20 203 x 133 x 25 152 x 152 x 23
20 to 30 203 x 133 x 30 152 x 152 x 30
30 to 40 see Note 1 152 x 152 x 37
40 to 50 see Note 1 203 x 203 x 46
Note to Table 4
A A A A
B B 1 Beams should be designed by an Engineer in accordance with
void void Technical Requirement R5.
B B
Steelwork
Appendix 6.5-C
INDEX
Connection of beams B M
supporting floors Beams 2, 4 Masonry partitions, support 1, 2
The connection methods shown in this Bearings 2 P
Appendix (determined using Appendix Bolted connections 1 Padstones 1, 3, 4
6.5-B) are suitable for connecting steel C Partitions 2
beams used to support floor loads
Clear span 4 Point loads 1
25mm Coatings 1, 2 S
Cold bridging 1 Section size 2
maximum 170mm
Limitations
Limitations on the use of this method are:
6.5
• neither beam is to support masonry
partitions, and
• both beams have been chosen from
Table 4 of Appendix 6.5-B, and
• beams do not differ in depth by more
than 40mm.
The following connections should be
designed by an Engineer in accordance
with Technical Requirement R5:
• between steel sections which differ in
depth by more than 40mm, or
• between steel sections, one of which
carries floor loads and one of which
carries a masonry partition, or
• between steel sections which have not
been derived using Appendix 6.5-B, or
• between steel sections which both carry
masonry partitions.
Staircases
Part 6 Superstructure (excluding roofs)
Chapter 6.6
6.6
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
Staircases
CONTENTS SCOPE
DESIGN Clause Page This Chapter gives guidance on meeting the Technical
Design standards D1 1 Requirements and recommendations for staircases.
Statutory requirements D2 1
Safe transmission of loads D3 1
Staircase width and headroom D4 1
Design of steps D5 1
Landings D6 2
Handrails D7 2
Guarding D8 2
Fire Precautions D9 2
Lighting D10 2
Provision of information D11-D12 2
MATERIALS
Materials standards M1 3
Staircase units M2 3
Timber and wood-based products M3 3
In-situ and precast concrete M4 3
Fixings M5 3
SITEWORK
Sitework standards S1 3
Location and fixing S2 3
Timber staircases S3-S4 3-4
Concrete staircases S5-S7 4
Steel staircases S8-S9 4
6.6
APPENDIX 6.6-A
Design aid for rise and going 6
INDEX 7
6.6
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
Staircases
DESIGN STANDARDS STAIRCASE WIDTH AND The dimensions of the rise (R) and the
going (G) should usually be related so that
HEADROOM 2R+G is between 550mm and 700mm.
6.6 - D1 Design shall meet the Technical
6.6 - D4 Staircase design shall ensure A design aid giving the relationship
Requirements
adequate provision for: between rise and going is given in
Design that follows the guidance below will
(a) headroom Appendix 6.6-A.
be acceptable for staircases.
The minimum headroom above stairs Further information on staircase design
should be measured vertically from the
STATUTORY pitch line. The clear headroom (h) over
may be found in BS 5395.
REQUIREMENTS the entire length and width of a stairway, (b) consistent rise and going
including landings, should be 2.0m. In each flight of stairs all the steps should
6.6 - D2 Design shall comply with all
relevant statutory requirements have the same rise and going.
landing
SAFE TRANSMISSION OF
h
LOADS unequal rises
do not comply
6.6
centre
vibration under load, given in BS 585 : line
Part 2. DESIGN OF STEPS
The method of fixing flights to the 6.6 - D5 The design of steps shall allow
surrounding structure should be specified. safe use of the staircase g
Staircases
LANDINGS • that handrail ends do not project to should comply with the relevant Building
catch clothing, etc. Regulations.
6.6 - D6 Landings shall be designed to
allow safe use of the staircase Ventilation of staircases serving flats in
GUARDING buildings of three or more storeys should
Landings should be provided at the top comply with BS 5588.
6.6 - D8 Guarding shall be designed to
and bottom of every flight. The width and
prevent accidents by falling
depth of landings should be at least the
same as the width of the stair. Items to be taken into account include: LIGHTING
(a) resistance to loads 6.6 - D10 Lighting shall be provided to
Landings should be properly framed to
Guarding should be: ensure safe use of the staircase
provide full support and secure fixings for
• capable of resisting a horizontal force
flights, nosings, newels, etc. Artificial light sources should be provided
of 0.36kN/m at its minimum required
to all staircases and landings. Within
Where pivot windows are being used, they height
dwellings, lighting to stairs should be
should not obstruct the landing area or • a solid wall or balustrading.
controlled by two way switching.
stair flight when in the open position.
Where guardrails or balustrades are long,
Where the Public Lighting Authority
Generally, door swings should not obstruct the newel posts may not be sufficient to
specify and maintain control of entrance
landings. However, a door may open across transfer horizontal forces to the structure
lighting, their requirements should be
the bottom landing of a flight of private and intermediate posts may be needed.
met. Otherwise, landings and staircases
stairs if the swing is at least 400mm from in common areas to dwellings should be
The method of fixing newels should be
the first tread and the dwelling is not over provided with adequate artificial lighting.
specified (eg through-bolted to joists).
two storeys high. Manual two way switching, controlled by
Any glazing in the guarding should be people using these areas is acceptable.
bottom
landing
toughened or laminated glass, or glass Automatic light sensitive controls may be
blocks. Wired glass is not regarded as safe used, provided lights can also be switched
for this purpose and should not be used. two way manually.
at least
400mm (b) dimensional requirements Reference should be made to Chapter
Guarding should be provided along the 8.1 ‘Internal services’ (Design) for further
full length of the open sides of all stairs details on lighting.
and landings when the drop is more than
600mm at any point. To comply with Where staircases are lit by glazing, any
HANDRAILS relevant Building Regulations, guarding glass below the minimum height of
may be required where a stair abuts an guarding (see Table to Clause D8(b))
6.6 - D7 Handrails shall be designed to
opening window. should be:
provide a safe handhold
• protected by a balustrade or railing, or
A handrail is required to all flights of stairs Guarding is not needed when the rise is • glass (toughened or laminated), or
6.6
that rise over 600mm. less than 600mm and when the stair or • constructed of glass blocks.
landing is not a means of escape.
Where winders are used, Building
Regulations (Northern Ireland) require Balustrading should be designed so that it PROVISION OF
a handrail to be fitted on the side where is not easily climbed by children. INFORMATION
tapered treads have the greater going.
No opening in the balustrade should 6.6 - D11 Designs and specifications
be large enough for a 100mm diameter shall be produced in a clearly
sphere to pass through. understandable format and include all
relevant information
Type of stairs Minimum guarding
height [mm] Usually, staircase drawings and
specifications should show:
flights landings • layout of stairs
Private stairs 900 900 • dimensions covering width, rise and
(England, going, handrail height, etc
Wales, Northern • fixings of stairs, treads, risers, strings,
Ireland
and the Isle of Man)
balustrades, newel posts and handrails,
at least
as appropriate
Private stairs 840 900
25mm
(Scotland)
• the length of time before formwork can
be removed from in-situ concrete stairs
Common stairs 900 1100
• whether precast concrete or steel
staircases can be used immediately
after erection or whether time should be
FIRE PRECAUTIONS allowed to cure grouted connections.
Handrails should be at a height between
6.6 - D9 Staircases shall provide the
900mm (840mm in Scotland) and 6.6 - D12 All relevant information shall
necessary means of escape in case of
1000mm. be distributed to appropriate personnel
fire
Design should ensure: Ensure that design and specification
Timber staircases are acceptable within
• a firm handhold information is issued to site supervisors
a single family dwelling where there are
• that trapping or injuring the hand is and relevant specialist subcontractors and/
no more than four storeys, excluding the
prevented or suppliers.
basement.
• a minimum 25mm clearance at the back
of the handrail Houses of three or more storeys and
• secure fixing flats in buildings of three or more storeys
Staircases
the guidance below will be acceptable for (d) oriented strand board landing
staircases. Oriented strand board should comply with
h
Materials for staircases should comply Type OSB3 of BS EN 300.
with all relevant standards, including those
(e) medium density fibreboard
listed below. Where no standard exists, pitch
Fibre building boards should comply with line
Technical Requirement R3 applies (see
BS 1142 : Part 2.
Chapter 1.1 ‘Introduction to the Standards
and Technical Requirements’). (f) laminated timber
References to British Standards and Codes Glued laminated timber structural (b) overall vertical rise
of Practice include those made under the members should comply with BS 4169. Staircases are normally manufactured off
Construction Products Directive (89/106/ site so the floor-to-floor dimensions should
EEC) and, in particular, appropriate IN-SITU AND PRECAST be accurate. An allowance should be made
European Technical Specifications for floor finishes to structural floors or
approved by a European Committee for
CONCRETE staircase treads.
Standardisation (CEN). 6.6 - M4 Concrete shall be of the
mix proportions to achieve adequate (c) pitch
strength as required by the design Staircases should be accurately located
STAIRCASE UNITS and fixed with the string at the correct
6.6 - M2 Proprietary staircases Reference should be made to Chapter 2.1 angle so all treads are horizontal.
‘Concrete and its reinforcement’ (Design
and associated components shall
and Materials) for guidance on concrete, (d) landings
comply with the design and Technical
reinforcement and additives. Landings, where required, should be
Requirements
properly framed to provide full support
Where proprietary staircases or FIXINGS to and secure fixings for flights, nosings,
associated components are proposed, newels, apron linings, etc.
they should meet the statutory and design 6.6 - M5 Fixings shall be of adequate
requirements for stairs, as detailed in the strength and durability and comply with (e) floor finishes
drawings and/or specification. the design Allowance should be made for stair and
Fixings should be checked for compliance floor finishes to ensure that all risers are
6.6
Manufacturers of staircases and equal.
balustrading, etc should be sent all with the design and whether they are
relevant drawings and other information provided by the supplier, especially for:
to ensure their products meet the design • timber and steel staircases stair
requirements. • newel posts finish
• handrails
Allowance should be made for tolerances • guarding and balustrading. all risers
or actual site dimensions. equal
Staircases
staircases are correctly located and 6.6 - S9 All work shall be carried
levelled out strictly in accordance with
100mm diameter spheres
PRECAST CONSTRUCTION manufacturers’ instructions cannot pass through gaps
When setting out levels, account should Manufacturers’ assembly and erection
be taken of the thickness of finishes to the instructions should be available and
floor or landing, as well as any finish to be followed.
applied to the stair treads. Particular care In concrete staircases, balustrading may be:
is needed at the top and bottom of each HANDRAILS AND • grouted into pre-formed holes or
flight. pockets
BALUSTRADES • bolted or screwed into pre-drilled holes
Precast units should be accurately located
and levelled. 6.6 - S10 A handrail shall be correctly • bolted to brackets cast into the concrete.
located and fixed to provide a safe
handhold Fixing methods for balustrading should
IN-SITU CONSTRUCTION
allow a degree of tolerance. It may be
Shuttering for in-situ concrete elements A handrail should be provided for any flight preferable to take measurements from
or connections should be accurately that rises 600mm or more. The handrail the completed staircase, whether of
constructed to ensure a consistent rise should be fixed between 900mm (840mm in-situ or precast construction, before
and going. in Scotland) and 1000mm vertically above manufacturing the balustrading. This will
the pitch line. ensure that the fixings are positioned
FLOOR FINISHES
For both precast and in-situ staircases, The ends of the handrail should be shaped correctly and allow for variations in the
allowance should be made for the or returned to the wall to prevent clothes surrounding structure.
thickness of finish at the top and bottom catching on projections. Design details on the spacing of bolt
of flights. fixings for balustrades or handrails should
Throughout its whole length the handrail
should be: be followed.
6.6 - S6 Concrete staircases shall be
constructed to provide satisfactory final • fixed securely
performance • continuous
• smooth and unobstructed
Items to be taken into account include: • at least 25mm from any surface.
(a) correct placing of reinforcement to
give the required cover Check that fixing and location are in
Chairs or spacing blocks should be used accordance with the design.
to give the following minimum cover to
reinforcement:
Staircases
dimensions
should be
sufficient to
avoid fracture
PROTECTION OF FINISHED
WORK
6.6 - S12 On completion, staircases
shall be undamaged, fixed properly and
suitable for handover
When stored, staircases should be stacked
on bearers. Wood staircases should be
stored under cover and be fixed in place
only when the building is weathertight.
Staircases, stair treads, nosings,
balustrades and handrails may be protected
with timber strips, plywood or building
paper. Plastic sheeting should not be used
to protect stairs because it gives a slippery
surface which is not safe to walk on.
6.6
treads and
nosings protected
Staircases
Appendix 6.6-A
220
244
210
200
198
243
190
187
180
170
Rise
160
[mm]
150
140
130
120
6.6
110
100
220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380
Going
[mm]
Key
Private stairs - whole of shaded area
Common stairs - hatched area only
Based on Figure 11 in BS 5395 : Part 1.
Staircases
INDEX
B I R
Balusters 3, 4, 5 In-situ concrete 3, 4 Reinforcement 4
C J Rise 1, 3, 6
Chipboard 3 Joinery 4 S
Concrete 3 L Steel staircases 1, 4
Concrete staircases 1, 4, 5 Landings 1, 2, 3 Steps 1
D Lighting 2 Straight flights 1
Differential movement 1 Location 3 Strings 3
Doors 2 M T
Durability 3 Means of escape 2 Timber 3
F Medium density fibreboard 3 Timber staircases 1, 3
Finish 4 Movement 1 Treads 1, 3, 4
Fire precautions 2 N W
Fixings 1, 3, 4, 5 Nosings 3, 4, 5 Width 1, 3
Floor finishes 3, 4 Newel posts 3 Winders 1
Formwork 4 O
G Oriented strand board 3
Going 1, 6 P
Guarding 2 Pitch 1, 3
H Plywood 3
Handrails 2, 3, 4 Precast concrete 3, 4
Headroom 1, 3 Proprietary staircases 1, 3
Protection 5
6.6
Chapter 6.7
6.7
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
CONTENTS SCOPE
DESIGN Clause Page This Chapter gives guidance on meeting the Technical
Requirements and recommendations for doors, windows and
Design standards D1 1 glazing, including where coupled door and window frame
Statutory requirements D2 1 assemblies are contained within a single storey.
Environmental factors D3 1 Coupled door and window frame assemblies which are:
Security D4 1
• one storey or more in height, or
Inservice performance D5 2
Resistance to decay D6 2 • not contained between a structural floor and ceiling
Glazing D7 2 should be designed in accordance with Chapter 6.9 ‘Curtain
Provision of information D8 3 walling and cladding’.
MATERIALS
Materials standards M1 3
Timber doors and windows M2-M4 3
Non-timber doors and windows M5 3
Ironmongery M6 3
Glazing M7 4
SITEWORK
Sitework standards S1 4
Protection against damp S2 4
Location and fixing S3 4
Glazing S4-S5 5
Protection S6 6
INDEX 6
6.7
6.7
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
broken, would permit release of the snib by with visitors, without opening their door,
DESIGN STANDARDS hand or arm entry should be laminated. should be considered in place of opening
limitation devices.
6.7 - D1 Design shall meet the Technical DWELLINGS - with an alternative means
Requirements of escape via a door (c) view outside main entrance door
Design that follows the guidance below Lock(s) should provide initial security There should be a means of giving a wide
will be acceptable for doors, windows, and by use of a latch operable with a key angle view of the area immediately outside
glazing. externally and a handle/thumb turn the main entrance door of individual
release internally. The full deadlocking dwellings. Acceptable ways include:
facility should be engaged and be operable • a through-door viewer
STATUTORY REQUIREMENTS with a key externally and a handle/thumb • clear glazing either to part of the door
6.7 - D2 Design shall comply with all turn release internally. Locks which comply or a convenient window
statutory requirements with BS 8621, meet these requirements. • closed circuit camera and display, which
External handles on multi-point locking is not linked to television sets.
Design should be in accordance with
relevant Building Regulations and other systems should be twin or split spindle to
(d) secondary external access doors
statutory requirements. avoid operating the latch.
The door should be held closed on a latch
Enhanced security can also be achieved and operable by use of a handle both
ENVIRONMENTAL FACTORS by providing the facility to deadlock the internally and externally. A deadlocking
internal/thumb turn when leaving the facility should be operable by use of a
6.7 - D3 Design and selection of doors,
dwelling un-occupied. Locks which comply key both internally and externally. Locks
windows and glazing shall take account with BS 10621, meet these requirements. complying with BS 3621 meet these
of location and planning requirements requirements. Alternatively a thumb turn
Items to be taken into account include: DWELLINGS - opening direct to outside may be used internally in place of key
without an alternative means of escape operation. Locks complying to BS 8621
(a) noise control via a door meet these requirements.
Where noise levels are very high, for example The door should be held closed by use of a
near airports or motorways, it may be latch operable with a key externally and a In addition bolts should be fixed securely
advisable to install sound-insulating windows, handle/thumb turn release internally. The at both top and bottom of the door on the
usually of special design and construction. full deadlocking facility should be engaged internal opening edge.
and be operable with a key externally and Where multi-point locking systems are
(b) planning requirements a handle/thumb turn release internally.
Local planning authorities may impose used bolts may be omitted.
Locks which comply with BS 8621, meet
limitations on the shape, size and choice these requirements. External handles on External sliding doors should be secured
of materials for windows and doors, for multi-point locking systems should be by way of multi-point locking system
example in conservation areas. twin or split spindle to avoid operating the with a minimum of three locking points
latch. incorporating mushroom headed bolts,
(c) climatic conditions
6.7
hookbolts or shoot bolts. Where shoot
Climatic conditions, especially wind speed,
DWELLINGS - opening onto a communual bolts are fitted they should engage into the
together with the required level of window
access without an alternative means of head and sill of the door frame. An anti-lift
performance (eg in relation to air tightness),
escape device should also be fitted so that doors
may govern the size of glass panes and
The door should be held closed either cannot be lifted from their frame from the
opening lights in exposed locations.
on a latch operable with a handle both outside.
internally and externally or a roller bolt
SECURITY so that the door cannot slam shut locking
Connections between door and/or frame
components which can be easily released
6.7 - D4 Doors, door frames, windows the homeowner out without a key. The full
from outside should not be used. This
and locks shall be designed and specified deadlocking facility should be engaged
includes accessible screw connections.
so as to improve their resistance to and be operable with a key externally and
unauthorised entry a handle/thumb turn release internally. (e) fittings for windows
Locks which comply with BS 8621, meet Ironmongery for windows should be
Items to be taken into account include: these requirements. supplied as follows:
(a) locks to main entrance doors of Timber or light steel frame walls, should • hinges and fastenings of opening lights
dwellings (including houses, flats and incorporate one of the following: of windows should be of a type which
maisonettes) • timber sheathing minimum 9mm thick, prevents them from being opened from
or the outside when in the closed position
DWELLINGS - all
• expanded metal. • opening lights on all ground floor
All entrance doors of individual dwellings
windows and others which are readily
should be fitted with one (or more) The material should be the full height accessible from the outside may be
securely fixed lock and keep or multi-point of the door and not less than 600mm fitted with lockable devices which cannot
locking system, which has: measured from the lock(s). be released without a key
• at least 1000 differs, and
• where the windows are required by
• a fixing which, if burst open, would not (b) opening limitation devices to main Building Regulations to have background
pull out without breaking the door or its entrance doors ventilation they may be fitted with
frame, and A securely fixed opening limitation device trickle ventilators or some other
• a hardened steel bolt or inserts to should be fitted to main entrance doors means of providing ventilation which is
prevent sawing, and in houses and the entrance doors of controllable and located to avoid undue
• latch and deadlocking facility. individual flats and maisonettes. draughts. Windows with ‘night vent’
Locking devices fitted to entrance doors In sheltered accommodation opening positions are not accepted as meeting
should permit emergency egress without limitation devices should be not inhibit these recommendations.
the use of a key when the dwelling is emergency access. Alternative methods
occupied. Any glazing which, if open or for residents to identify and communicate
breakdown of the edge seal. (a) classification and use Preservative treatment is required for the
Site glazing may incorporate fully bedded All timber and wood-based materials following:
systems on the top and sides of the should comply with the relevant • external door frames
insulating glass unit but the rebate platform requirements of BS EN 942 as follows: • windows
requires a drained and vented bottom bead. • glazing beads - European • timber surrounds to metal windows
• window casements/sashes - ‘J’ classes • external doors, other than flush doors.
INSULATING GLASS UNITS • all other elements - (see table 1 of
• Insulating glass units should comply with BS EN 942). (b) priming
the requirements of BS EN 1279, be CE Material to be painted should be primed
marked and the subject of a third party In England, Wales, Northern Ireland and before fixing. For further guidance on
certification scheme (e.g. Kitemarking). the Isle of Man, planted stops are not preparing elements for painting, see
permitted on frames to external doors. Chapter 8.5 ‘Painting and decorating’
Insulating glass units should normally (each section).
Storey-height frames should be of a section
have a dual seal, or single seal if of hot appropriate to their height and function.
melt butyl, together with desiccant in at (c) staining
least one long and one short section of External doors should be not less than Material to be stained should have the first
the spacer bar. 42.5mm (44mm nominal) in thickness. coat applied before delivery to site.
Wood windows should comply with the 6.7 - M4 Glazing compounds and timber
BEADS
relevant requirements of BS 644 and have stains shall be compatible
In external situations the bottom bead
a minimum rebate depth of 15mm where Compatibility of glazing, sealants and
should project slightly over the rebate
double glazed units are to be installed. finishes should be checked with relevant
edge, and be bedded to the rebate platform.
Medium density fibreboard for window manufacturers.
PROVISION OF boards should be moisture resistant grade.
INFORMATION NON-TIMBER DOORS AND
(b) drying shrinkage
6.7 - D8 All relevant information shall be To minimise drying shrinkage, the moisture WINDOWS
distributed to appropriate personnel content of joinery, when fixed, should not 6.7 - M5 Doors and windows of materials
exceed the following: other than timber shall be in accordance
Ensure that design and specification
Joinery items Moisture content (%)* with appropriate standards
information is issued to site supervisors
and relevant specialist subcontractors Windows and frames 17 Relevant standards include the following:
and/or suppliers. Internal joinery in: BS 4873 Specification for aluminium
- intermittent heating 15 alloy windows
6.7
BS 7412 Plastics windows made from
(a) meet the Technical Requirements * on delivery, the moisture content should be PVC-U extruded hollow profiles
(b) take account of the design within 2% either side of the values specified.
BS 7413 White PVC-U extruded hollow
Materials that comply with the design and profiles with heat welded
the guidance below will be acceptable for corner joints for plastics
(c) workmanship
windows: materials type A
doors, windows and glazing. All prefabricated items should be
constructed to a good standard of BS 7414 White PVC-U extruded hollow
Joints between door and window frame profiles with heat welded
workmanship, including:
assemblies should be formed with corner joints for plastics
• fit and construction of joints
suitable materials to ensure durability and windows: materials type B.
• construction of finger joints
satisfactory in-service performance.
• glueing and laminating
Third party certification is also required
Materials for doors, windows and glazing • construction of moving parts
for PVC-U windows. Windows which
should comply with all relevant standards, • surface finishes.
are Kitemarked will meet with the
including those listed below. Where no Performance Standard.
Prefabricated components should comply
standard exists, Technical Requirement R3
with the relevant parts of BS 1186 : Part 2.
applies (see Chapter 1.1 ‘Introduction to the Doors and windows to which the above
Standards and Technical Requirements’). (d) surface finish British Standards do not apply should
Any surface finishing defects should be have been assessed in accordance with
References to British Standards and Codes Technical Requirement R3.
of Practice include those made under the such that they would not be apparent with
Construction Products Directive (89/106/ a matt paint finish, whether the surface is
EEC) and, in particular, appropriate to be stained or painted, gloss or matt. IRONMONGERY
European Technical Specifications 6.7 - M6 Ironmongery shall be of the
6.7 - M3 Timber for doors and windows
approved by a European Committee for type and material required by the design
shall be of a naturally durable timber
Standardisation (CEN).
species or preservative treated and Items to be taken into account include:
primed
TIMBER DOORS AND (a) relevant standards
Items to be taken into account include: Ironmongery should be provided
WINDOWS in accordance with the design and
(a) preservation
6.7 - M2 Timber and wood-based specification. For critical functions,
Non-durable timbers used externally
materials shall be of the quality and materials should comply with appropriate
should be treated, see Chapter 2.3 ‘Timber
dimensions required by the design standards, including the following:
preservation (natural solid timber)’ (each
Items to be taken into account include: section) for details.
BS EN Building hardware - single axis Permanent marking of safety glass (including Doors and windows should be installed
1935 hinges - Requirements and test glazed shower/bath screens) is required. correctly so they perform satisfactorily
methods in use.
Glazing materials should be compatible with
BS 3621 Thief resistant lock assembly. Key the required levels of safety and security. The Dpcs should be correctly installed.
egress requirements for critical locations with a high
The dpc should extend approximately
BS 8621 Thief resistant lock assembly. risk of accidental breakage should comply
25mm into the cavity. If a thick block is
Keyless egress with the safety requirements of Approved
used to close the cavity and form the
BS 10621 Thief resistant dual mode lock Document N in England, Wales and the Isle of
reveal, a wider dpc will be required.
assembly Man, Technical Booklet V in Northern Ireland
and BS 6262 in Scotland. Vertical dpcs should extend continuously
BS 4951 Specification for builders’
hardware: lock and latch furniture to the full height of the frame.
(doors)
SITEWORK STANDARDS In Scotland, Northern Ireland and areas of
BS 5872 Specification for locks and Very Severe exposure in England, Wales
latches for doors in buildings 6.7 - S1 All sitework shall: and the Isle of Man, ‘check’ reveals should
BS 6459 Door closers. (a) meet the Technical Requirements be used. Additionally, an appropriate
(b) take account of the design sealant is required between doors and
(b) security (c) follow established good practice and windows and masonry.
Security items for doors and windows are workmanship Minimum 12mm
overlap of masonry
contained in Clause D4. (or render) to frame
Sitework that complies with the design and
(c) door hinges the guidance below will be acceptable for
sealant
The requirements for door hinges are doors, windows and glazing. ’rebated’ or
25mm ’check’ reveal
contained in Clause D5(f). in areas of Very
GLAZING DAMP
6.7 - M7 Glazing shall be as required by Joints between multiple door and window
6.7 - S2 Door and window components
the design frame assemblies should be part of an
shall, where necessary, be adequately
engineered system and formed using
protected against damp
(a) relevant standards suitable materials in accordance with the
Insulating glass units and glazing materials Items to be taken into account include: manufacturer’s recommendations.
should comply with appropriate British
Standards, including the following: (a) priming (b) fixing
Material to be painted should be primed Window frames and linings should be fixed
BS 5516 Code of Practice for patent
before fixing. Material to be stained should solidly, level and plumb and should be either:
glazing have the first coat applied before delivery • secured by door/window cramps, or
to site. Any material delivered untreated
6.7
(c) bay windows Locks should not be fitted in mortices too GLAZING
To prevent sagging and bowing, bay and tightly and keyholes should be aligned and
bow type windows should be adequately locks should turn easily. The clearance 6.7 - S4 Glass and glazing shall be
supported and secured to the structure to between a door handle and a door stop installed upon delivery or shall be
prevent casements becoming twisted. should be at least 25mm. adequately stored and protected until
required
Bay windows should be properly linked to (h) door hinges
dpcs at reveals. Glass and insulating glass units should be
To reduce twisting, doors should be hung
inspected for visual defects and defects
on hinges as follows:
which could lead to premature failure.
Type of door Hinges Often, defects are caused by:
bay windows External 1½ pairs x 100mm • water accumulating between sheets,
adequately
supported
Fire door which may cause surfaces to become
1½ pairs* x 100mm
marked, and
Airing or cylinder 1½ pairs x 75mm • edge damage or scratching.
cupboard
Other internal 1 pair x 75mm 6.7 - S5 Glazing shall be carried out in
* 1 pair where rising butts are used accordance with relevant standards
Items to be taken into account include:
(i) security (a) size of insulating glass units/sheets
(d) cut ends Security items for doors and windows are
Where pre-treated joinery is cut or Sufficient space should be provided
contained in Clause D4. between the glass edge and the frame to
adjusted on site, the affected surfaces
should be re-treated with two flood brush (j) workmanship allow for thermal expansion of the glass.
coats of appropriate preservative. Internal door frames and linings should be A gap of 3mm is recommended, except for
of the correct widths to match the wall or drained systems where at least 5mm is
partition thickness, including finish. required for drainage at the bottom bead.
Insulating glass units should not be cut or
Frames and linings should be blocked off punctured in any way on site.
walls, wherever possible, to allow for full
architraves. When cutting single sheets of glass or
plastics for windows, an allowance should
be made for thermal movement of the
pane, taking into account:
• the material being used, and
• the size of the pane.
full architrave
(e) window boards This allowance is especially important
6.7
The top surface of window boards should when window rebates are shallow, allowing
be flat and level. Boards should be fixed limited tolerance for expansion of the
All timber trim should be:
close to the frame and adequately secured glazing.
• sufficiently wide to mask joints, and
against twist and other movement,
• fixed so as to minimise movement and
particularly any back slope towards the (b) rebates
shrinkage.
frame. Before glazing, rebates should:
Architraves should be: • have been primed (for timber frames),
Medium density fibreboard should be
• parallel to frame and lining arrises • be rigid and true, and
moisture resistant grade.
• accurately mitred or scribed to fit tightly • be of the correct size for the glazing.
(f) hanging doors and opening lights and neatly
Insulating glass units should be properly
Opening lights and door leaves should • fixed with an equal margin to each
protected by the frame from sunlight. The
hang square within the frame or lining frame member
spacer bar of the insulating glass unit
and fit neatly with minimum gaps, • fixed securely together with linings to
should always be below the level of the
subject to the requirements of effective prevent curling.
frame’s sightline.
weatherstripping. Doors to bathrooms and Nails should be punched below the surface
WCs with mechanical ventilation should be Setting and location blocks should be of
of the timber and holes stopped. Nails
hung with a gap at the bottom or be fitted a suitable resilient material. In drained
should not be driven home with the hammer
with a ventilation grille. and ventilated frames the drainage
head. Damage should be avoided where
channels in the rebate should be free
Where a standard flush door is reduced in easing is necessary. Any damage should be
from obstructions that prevent effective
height, the bottom rail should be replaced made good.
drainage. The dimensions of holes and
if necessary. The leading edges of doors slots should be checked to ensure that
(k) finish upon completion of work
should be protected with timber lipping, effective drainage can occur.
Work should be left in a clean state and
where necessary.
brought to an appropriate level of finish
(c) bead glazing
(g) general ironmongery for other trades.
Beads and linings should be used for:
Where required, hinges and other Finishing trades should not be relied upon • all internal glazing
ironmongery should be housed neatly to correct untidy work. • other locations where shock
flush with the surface. absorptionproperties are required.
The full complement of matching screws Beads should be used:
should be provided and properly screwed • where doors or windows are to be
home. finished with water-borne stains
• where fully bedded systems are used to be checked to ensure that they comply PROTECTION
install insulating glass units with the design. The insulating glass
• where glazing takes place on site, the units should carry a CE mark to BS EN 6.7 - S6 Completed work shall be free
bottom bead should be drained and 1279 and have a third party assessment from damage
vented. certificate such as the BSI Kitemark. The Keep internal doors covered with
glass type, gas filling, edge seal type and polyethylene or original wrapping.
Beads should be fixed at not more than
dimensions should be checked against the
150mm centres. Door frames and linings should be
documentation and the insulating glass
unit itself. protected with timber strips or plywood to
(d) glazing compounds
at least 1m above skirting level. Thresholds
All materials should be compatible
(f) doors and windows of materials other and window sills should be covered.
and used in accordance with the
than wood Scaffolding and walkways should be kept
manufacturer’s recommendations.
Where doors and windows of materials away from frames.
Materials from different manufacturers
other than timber are delivered to the
should not be used together unless both Joinery should be protected from paint
site unglazed, the glazing should be
have agreed in writing. splashes and other damage.
carried out in strict accordance with the
(e) insulating glass units manufacturer’s instructions. All temporary coverings should be
Unless factory glazed, insulating glass Appropriate fixing and sealing systems removed after all other work has been
units should be installed in accordance should include: completed, before handover.
with the design. In timber frames where • distance pieces, unless load bearing
solid bedding methods are to be used on tapes are used
site, the bottom bead should be drained • setting blocks
and vented. • location blocks where required
Insulating glass units and any • appropriate beads
accompanying documentation should • glazing compounds, sealants, gaskets
and/or capping.
INDEX
6.7
A G S
Aluminium doors and windows 3 Glazing 2, 3, 5 Secondary external access 1
doors
B Glazing compounds 5
Security 1, 3, 4
Bay windows 4 I
Steel doors and windows 3
C Ironmongery 3, 4
Storage 4
Compatibility 3 L
Strength 2
D Locks 1, 3
T
Door hinges 2, 5 M
Timber doors and windows 3
Drained and vented systems 2 Main entrance doors 1
V
Durability 2 P
Ventilation control 2
E Performance 1, 2
W
Emergency access 2 Preservation 2, 3, 4
Weather resistance 1
Environmental factors 1 Priming 3, 4
Weathertightness 1, 4
Escape windows 1 Protection 4, 5
Wind loads 2
F PVC-U doors and windows 3
Workmanship 3, 4
Finish 5 R
Fire safety 2 Rebates 5
Fixing 4
Flats and maisonettes 1
Fully bedded systems 2
Chapter 6.8
6.8
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
CONTENTS
MATERIALS
Materials standards M1 5
Bricks M2 5
Concrete blocks M3 5
Stone masonry M4 6
Mortar M5 6
Flue liners M6 6
Flue pipes M7 6
6.8
Flue terminals M8 6
Flue blocks for gas appliances M9 6
Twin wall flue systems M10 6
Flashings M11 6
Damp proof course M12 6
SITEWORK
Sitework standards S1 6
Fireplaces and hearths S2 6
Flues S3 7
Chimneys S4 7
Terminals S5 9
Provision of combustion air S6 9
Testing S7 9
APPENDIX 6.8-A
Provision of combustion air 10
APPENDIX 6.8-B
Minimum sizes for flues contained in 10
chimneys
APPENDIX 6.8-C
Typical construction details 11/14
solid non-combustible
material at least 75mm thick
6.8
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
less than
150mm
at least
150mm at least
1.2m
Fireplaces, chimneys andhearth
flues
6.8 - D2 Design shall comply with all below an open fire. FLUE PIPES
relevant statutory requirements The hearth for a freestanding appliance
6.8 - D6 Flue pipes shall be correctly
Design should be in accordance with should have minimum dimensions of
designed to safely connect an appliance
relevant Building Regulations and other 840mm. The following diagram shows the
to a flue
statutory requirements. minimum dimensions from the appliance
to the edge of the hearth. Items to be taken into account include:
6.8
• construction adjacent to hearths recommendations. Appendix 6.8-C gives
and flues some recess dimensions. The diagrams in
• limitations on the type of appliance or Clause S2 show minimum masonry thickness
open fire which can be installed or fuel surrounding the fireplace recess. Recesses
which can be used. are generally lined with a fire back or fire
Where a chimney or flue is provided it bricks.
should be continuous from the hearth or For recess openings up to 500mm x 550mm,
appliance to the outside air. (d) separation from combustible materials
a 200mm diameter flue or square section of
Flue pipes should be separated from
A notice plate containing safety equivalent area can be used. For openings
combustible materials by at least the following:
information about any hearths and flues larger than this the flue size should be 15% of
• 200mm of non-combustible materials, or
should be securely fixed in an unobtrusive the area of the recess opening.
• an airspace at least 4 times the diameter
but obvious position within the home. of the flue pipe, or
WALLS NEAR APPLIANCES • shielded by a non-combustible shield
Solid fuel 6.8 - D5 Walls near appliances and their at least 3 times the diameter of the
hearths shall be located to minimise the flue pipe in width. The shield should be
FIREPLACES AND HEARTHS risk of fire to the building at least 12mm from the combustible
material and the combustible material at
6.8 - D4 Fireplaces and hearths shall be Walls near an appliance or its hearth should least 1.5 times the diameter either side
designed to ensure proper combustion be non-combustible or the appliance should of the flue pipe.
of fuel and to minimise the risk of the be positioned not closer to the wall than
building catching fire in consequence of shown in the following diagrams.
12mm
air space
their use
D
3x
solid non-combustible
Where appliances are not provided, it is material at least 75mm thick
flue pipe
important to construct fireplaces and hearths
at least 4 x D
shield of
to suit the appliance most likely to be fitted. D
D non-combustible
less than material
150mm
Items to be taken into account include: at least
at least
150mm
1.2m
3
hearth
1.5 x D
Combustion air is vital to the safe and
efficient operation of appliances. Solid fuel PLAN PLAN
appliances should have an air supply either REQUIREMENT IN REQUIREMENT
NORTHERN IRELAND ELSEWHERE
directly or indirectly from the external air
(d) chimney cappings The diagram below shows minimum (e) separation from combustible materials
Chimney cappings should be designed projections for the hearth beyond the Single wall flue pipes should be separated
to protect the masonry below. Cappings appliance. from combustible materials by:
should preferably be monolithic slabs, • at least 25mm
weathered, projecting at least 50mm with at least 150mm • a non-combustible sleeve enclosing an
PLAN
a drip to shed water clear of the masonry. at least
150mm
air space of at least 25mm around the
Brick chimneys which do not have this type pipe where it passes through a wall,
of capping should be constructed using floor or roof
frost resistant masonry. • non-combustible casing material with at
appliance least half the fire resistance needed for
All external face brickwork in Scotland should
the wall or floor where passing through a
be constructed using frost resistant bricks.
front compartment wall or compartment floor.
Cappings may be designed as a cover
at least 225mm The 25mm may be measured from the
slab supported on piers to reduce the rain beyond front
outside of the inner pipe in the case of
penetration into the top of the flue. The hearth for back boiler double-walled pipes (see BS 5440).
height of the supporting piers should be
sufficient to allow a total free opening area ALL OTHER GAS APPLIANCES
at least twice the area of the flue outlet. Hearths for other types of appliance CHIMNEYS
CHIMNEY POT should be at least 12mm thick non- 6.8 - D11 Chimneys shall incorporate
flue terminal (chimney pot) combustible material to the same plan flues capable of safely conducting
dimensions as above. In some cases the products of combustion from an
provision of a hearth is not required, for appliance to the external air. The
example if the flame or incandescent structure shall be capable of supporting
purpose-made
chimney material is at least 225mm above the floor. the flue and providing adequate
cappings
50mm
Where a hearth has been provided, its protection to adjacent materials
edges should be marked to provide Chimneys for gas appliances must not
a warning to the home owner and to incorporate an adjustable draught control.
discourage combustible floor finishes such
as carpet from being laid too close to the Items to be taken into account include:
FLUE LINING ACTING
AS FLUE TERMINAL
appliance. A way of achieving this would be (a) masonry chimneys
to provide a change in level. Flues should be of the minimum sizes
(c) separating appliances from given in Appendix 6.8-B.
purpose-made
chimney
cappings combustible materials Masonry chimneys as described for solid
50mm Appliances should not be closer than 75mm fuel are acceptable.
to combustible material. This applies to the
6.8
back, sides and top of the appliance and any Brick or blockwork chimneys for gas
draught-diverter. It does not apply if a 25mm appliances should provide at least the fire
thick non-combustible shield is used or the resistance of any compartment wall or floor
Gas appliance complies with the appropriate of which it forms part or passes through (the
parts of BS 5258 or BS 5386. compartment wall may form the chimney
FIREPLACES AND HEARTHS wall if it is a masonry material).
Flue blocks projecting into the cavity Balanced flues which bridge the cavity of (b) direction
should be protected by providing a an external wall should have a means of As for solid fuel.
vertical dpm. The dpm may be supported preventing moisture crossing the cavity,
by building in a layer of suitable non- for example, a moisture drip collar set in (c) separation from adjacent spaces and
combustible insulation. the centre of the cavity. materials
See Clause D14 (c).
Plaster should not be applied directly to CIRCULAR FLUES
6.8
As for solid fuel flue pipes if the flue gases a projecting capping bedded on a dpc. In
• position and size of chimneys and flues
are likely to exceed a temperature of Scotland frost resistant bricks should be
• position and proximity of combustible
250°C or the temperature is not known. used for all external facing brickwork.
materials
(i) stability • position and details of flue terminals or Reference should also be made to Chapters
As for solid fuel if of masonry construction. outlets 6.1 ‘External masonry walls’ (Materials) and
• position of dpcs and flashings 6.3 ‘Internal walls’ (Materials).
(j) factory-made insulated chimneys • construction details of fireplace
This type of chimney should be designed openings and chimney connections
in accordance with BS 4543 : Part 1 to Part • details of materials to be used
CONCRETE BLOCKS
3 BS EN 1859 and installed in accordance • limitations on the type of appliance or 6.8 - M3 Blocks shall be capable of
with BS 7566 : Part 2 or be assessed in open fire which can be installed or fuel supporting intended loads and have
accordance with Technical Requirement which can be used appropriate resistance to the adverse
R3. An operating life of at least 30 years is • details of tests required on chimneys effects of frost and sulfates
required. Component systems to be BS 715 and flues including who is responsible Blocks should be selected in accordance
installed in accordance with BS 5440. for carrying them out. with BS 6461 Part 1, BS EN 771 or
(k) outlets 6.8 - D17 All relevant information shall satisfactorily assessed in accordance with
See Appendix 6.8-F for positions of flue be distributed to appropriate personnel Technical Requirement R3. Block density
outlets. should be minimum 1500 kg/m3, unless
Ensure that design and specification designed by an Engineer in accordance
All balanced flue terminals should be information is issued to site supervisors with Technical Requirement R5.
positioned to allow free intake of air to the and relevant specialist subcontractors and/
appliance. or suppliers. Reference should also be made to Chapters
6.1 ‘External masonry walls’ (Materials) and
(l) terminals Where proprietary products are to be 6.3 ‘Internal walls’ (Materials).
As for solid fuel if of masonry construction, used, manufacturers usually have specific
requirements for fixing and/or assembly In Scotland, 100mm thick blockwork in
unless otherwise stated in the appliance
of their products. This information should chimney construction should have a
manufacturer’s instructions, which should
also be made available for reference density of at least 1600 kg/m3. Other
be followed.
on site so that work can be carried out suitable masonry specifications for
satisfactorily in accordance with the design Scotland are given in the Building
and specification. Standards (Scotland) Regulations.
could be: FLUE TERMINALS and the guidance below will be acceptable
• liners whose performance is at least for fireplaces, chimneys and flues. Gas
6.8 - M8 Flue terminals shall be suitable
equal to that corresponding to the appliances should be fitted by a Gas Safe
for their purpose
designation T450 N2 S D 3, as described Register (GSR) installer to comply with
Clay flue terminals should comply with the Gas Safety (Installation and Use)
in BS EN 1443: 1999, such as:
or be constructed from materials which Regulations 1998.
-- clay flue liners with rebates or sockets
comply with BS 1181.
for jointing meeting the requirements Good workmanship and effective
for Class A1 N2 or Class A1 N1 as Chimneys serving gas appliances should supervision during construction are
described in BS EN 1457: 1999; or have terminals complying with BS EN 1858. essential to ensure that fireplaces,
-- concrete flue liners meeting the Flue pipes serving gas appliances should chimneys and flues function correctly
requirements for the classification have terminals complying with BS 715. in use.
Type A1, Type A2, Type B1 or Type B2
as described in prEN 1857(e18) January Additional construction details are shown
2001; or
FLUE BLOCKS FOR GAS in Appendix 6.8-C.
-- other products that are independently APPLIANCES
certified as meeting the criteria in a); or 6.8 - M9 Flue blocks for gas appliances FIREPLACES AND
• imperforate clay pipes with sockets
for jointing as described in BS 65: 1991
shall be unaffected by flue gases and HEARTHS
suitable for their purpose
(1997). 6.8 - S2 Fireplaces and hearths shall
Flue blocks for use with gas appliances safely accommodate the appliances for
Liners should be installed in accordance should comply with BS 1289 : Part 1 which they are designed
with their manufacturer’s instructions. (Concrete) or Part 2 (Clay). In situations
Appropriate components should be where the cavity width is reduced by Fireplace recesses should be constructed
selected to produce the flue path without the flue block all insulation and vertical of solid non-combustible material as shown
cutting and to keep joints to a minimum. dpms should be in accordance with below:
Bends and offsets should only be formed manufacturers’ instructions.
with purpose-made components. Liners
need to be placed with the sockets
or rebate ends uppermost to contain
TWIN WALL FLUE SYSTEMS
water and other condensates in the flue. 6.8 - M10 Twin wall flue systems shall be
Caulking can be effected with fire cement suitable for their purpose
or refractory mortar. Spaces between
Twin wall flue systems should comply with
the lining and the surrounding masonry
BS 715 or be assessed in accordance with
should not be filled with ordinary mortar.
Technical Requirement R3.
fireplace surround
Changes of direction of flue liners should
be formed using purpose made fittings.
offset using
pre-fabricated bends
6.8
below. Hearths for freestanding appliances manufacturers’ instructions. Adjustable Each joint should be fully filled and all
should be at least 840mm square. flue draught control units are not surplus material cleared from the inside of
at least 150mm permitted where gas burning appliances each joint as the flue is built.
are installed.
(f) fire hazards
(d) flue pipes Combustible materials close to any brick or
Flue pipes should be fixed ‘socket up’ blockwork chimney should be:
and correctly aligned. Longer flue pipes • at least 200mm from a flue, or
hearth
projection
forming flues from gas appliances should • except in Scotland, 40mm from the face
at least hearth be supported at a maximum of 1.8m of the chimney.
500mm
centres and have support directly below
each socket. This does not apply to a floorboard,
skirting, dado or picture rail, mantelshelf
SOCKETED FLUE PIPE FLUE PIPE SERVING
or architrave.
FLUES A GAS APPLIANCE
The height H of an unrestrained chimney Ensure that the core is removed on ridge
terminal alternative
should not exceed 4½ times the least plan completion of the chimney. outlet position
dimension of the chimney W (see diagram),
provided the density of the masonry is at (e) drying
least 1500kg/m3, unless designed by an A chimney should be allowed to dry
Engineer in accordance with Technical naturally for at least 14 days before use. twin wall
flue pipe with
supports at
Requirement R5. 1.8m centres
(f) masonry chimneys maximum
45°
maximum
BRICKS
H H Frost resistant bricks should be used above
offset transfer
the roof unless protected by a capping block
w w
projecting at least 50mm. In Scotland, roof space
frost resistant bricks should be used for all
facing brickwork.
Below roof level the bricks and mortar
(b) wall thickness may be the same as those used for general
Chimneys of block, brick or stone should brickwork.
have a minimum wall thickness of 100mm
excluding the lining thickness. Mortar should be as specified for areas
of Severe and Very Severe exposure
A chimney forming part of a compartment in Chapter 6.1 ‘External masonry walls’
wall and not back to back with an adjacent Appendix 6.1-C. (1 : ½ : 4 to 4½, cement :
chimney should have a wall thickness of at lime : sand or 1 : 3 or 4, cement : sand with
least 200mm separating it from the other plasticiser).
building or dwelling.
Sulfate resisting cement should be used in
Chimneys built in a cavity separating wall the mortar where flue gases are liable to
should form two leaves each of at least affect the masonry, eg. above roof level.
first floor
of the chimney with the surface of the roof for gas appliances. Their suitability lintel block
through which the chimney passes. should be checked before connecting any may be
appliance. one or
two piece
Metal elements making up dpcs and set starter block
coated where in contact with cement. proofed in accordance with the design ELEVATION SHOWING AN INDIVIDUAL FLUE TO A GAS FIRE
and manufacturers’ instructions. A high
Occasional damp penetration below roof level standard of workmanship should be
may occur in chimneys which exit close to the maintained to ensure that the flue is clean The design will show how the extra
ridge of a pitched roof. This is acceptable in a and sealed. thickness is incorporated by either:
well ventilated roof space provided that any • increasing the overall width of the
dampness penetrating downwards is unlikely Flue blocks should be correctly bonded to
the flanking masonry. cavity, or
to reach the living areas. • making the flue block flush with the
Where chimneys exit close to the eaves of a Where gas flue blocks are shown in the inside of the cavity but projecting into
pitched roof or through a flat roof, trays and design they will be at least 140mm wide. the room as a false chimney breast.
flashings should be installed in the chimney This may be wider than the wall leaf.
brick
so that all damp penetration is prevented. cavity
non-combustible insulation
plasterboard on dabs FLUES FOR SOLID FUEL APPLIANCES
(not polystyrene)
minimum Coring ball test
CAVITY WALL WITH CAVITY INSULATION AND VERTICAL DPM 50mm
projection When a visual test cannot be carried out or
is inconclusive, the coring ball test should
Plaster should not be applied directly to be carried out.
flue blocks. A plasterboard lining with an
A suitable concrete or metal ball is
airspace or non-combustible insulation
Appendix 6.8-C gives details of brickwork attached to a strong cord or rope. The ball
behind should be provided. Insulated dry
capping. is lowered slowly from the flue outlet to
lining may be unsuitable in this situation
the bottom of the flue (the fireplace recess
unless separated from the flue block.
(b) jointing or the appliance connection). If a blockage
(h) connection between flue block The terminal of a masonry flue should or obstruction is found it must be removed
chimney and roof outlet be jointed to the flue lining with cement and the test repeated until the flue is
Connections between flue blocks and ridge mortar to form a seal. completely clear of obstruction.
terminals should be made as detailed in
(c) size Smoke test
the design using the correct fittings and
Terminals should be the same cross This test is designed to show that a flue
supports as specified by the manufacturers
sectional area as the flue which for solid draws adequately and that there are no
of the flue blocks, flue pipe and the ridge
fuel is not less than 200mm diameter. leaks between the appliance and the
terminal.
terminal.
ridge tile
(d) draught improvement
adaptor In cases where down draughts may occur, The smoke test is carried out when neither
line of support brackets at 1.8m special terminals designed to increase up the flue to be tested nor adjacent flues are
ridge maximum centres
6.8
tiles draught should be fitted. in use. The flue is first warmed for about
10 minutes with a heat source such as a
flue pipe A special terminal will not overcome blow lamp. If an appliance is fitted it should
offset transfer
block problems caused by high pressure zones. be completely closed as should any flue
Where relevant, the Solid Fuel Association or access doors.
other authoritative body should be consulted.
Two purpose made smoke pellets are
(e) chimney capping then placed in the appliance firebox or in
Where a chimney is to be capped, a single the bottom of the flue and ignited. The
unjointed concrete or stone capping should appliance, chimney or fireplace opening
be used. The capping should project and should then be closed or sealed off and
be throated to cast rainwater away from the smoke allowed to rise. When smoke
the face of the chimney. The slab should appears at the top of the flue the outlet
project 50mm beyond the faces of the should be sealed with a blow-up rubber
chimney. The withes between flues should ball or other air tight closing system.
be carried to the underside of the slab.
(i) factory-made insulated chimneys The whole structure forming the flue
Factory-made insulated chimneys Decorative brick cappings should be should be inspected externally on all sides
should be assembled, erected, anchored carefully constructed to avoid rain and from top to bottom for smoke leakage.
and protected in accordance with penetration and frost damage. The use This should include the top of cavity walls
manufacturers’ instructions. of frost resistant bricks may be required. and any other possible smoke paths, even
All bricks used for facing brickwork in those terminating some distance from the
Scotland should be frost resistant. flue. The test should be continued for at
TERMINALS least 5 minutes.
6.8 -S5 Terminals shall assist the PROVISION OF
proper functioning of the flue FLUES FOR GAS APPLIANCES
COMBUSTION AIR More sophisticated flue tests may be
Terminals should be purpose made or
6.8 - S6 Installations shall have an required for some gas appliances.
formed by extending the flue lining not
adequate supply of air to ensure These tests should be carried out by the
less than 20mm above the head of the
satisfactory combustion of fuel and the appliance installer.
chimney. Various terminals are shown in
Appendix 6.8-C. efficient working of flues and chimneys
FLUES FOR OIL APPLIANCES
Combustion air is vital to the safe and Flues for oil fired appliances should
efficient operation of appliances. Reference be tested as required by the appliance
should be made to Appendix 6.8-A. manufacturer.
Appendix 6.8-A
England, Wales and Isle 50% of throat area*** 550mm2/kW above 5kW 500mm2/kW above 7kW input 550mm2/kW above 5kW
of Man rating for an appliance in a room rating for an appliance in a
or space room or space
Scotland 1500mm2 for fireplaces up As England and Wales As BS 5440: Part 2 (as As England and Wales
to 450mm wide (measured England and Wales)
between firebricks), for
fireplaces exceeding 450mm
width manufacturers’ details
should be followed
Northern Ireland As England and Wales 550mm2 up to 6kW rating. 450mm2 up to 8kW. Over As solid fuel closed appliance
Over 6kW add 550mm2 for 8kW add 450mm2 for each
each kW above 6kW. kW above 8kW
Notes:
Full details of ventilation requirements for all types of appliances are contained in the relevant building regulations.
* Decorative fuel effect gas appliances should have a provision for combustion air complying with the relevant part of BS 5871.
Normally a minimum of 10,000mm2 of purpose provided ventilation is required. Air vents should be direct to the external air or to an adjacent
room or internal space which has an air vent or vents to the external air of at least the same free area. Air vents should have aperture
dimensions no smaller than 5mm.
** Where closed appliances use a flue fitted with a draught stabiliser the total free area should be increased to 300mm2/kW for the first 5kw
plus 850mm2/kW for the balance of appliance output.
***In the case of a fire with a canopy the open air vents should be 50% of the flue area.
Appendix 6.8-B
6.8
Closed appliance up to 30kW rated output burning any fuel 150 diameter or square section of equivalent area
Closed appliance above 30kW and up to 50kW rated output burning any fuel 175 diameter or square section of equivalent area
Non fan-assisted individually flued gas burning appliances up to 70kW input excluding balanced flue
Serving Minimum flue size
Gas fire Round flue with a cross-sectional area of at least 12,000mm2 (125mm diameter) or rectangular flue with a cross-sectional area of at least
16,500mm2 with minimum dimension of 90mm
Any other At least the cross-sectional area of the outlet from the appliance
Appendix 6.8-C
ridge terminal
flue
lining
6.8
masonry masonry
gas flue chimney chimney
blocks as containing containing
part of the a flue a flue
wall
flue pipe
gas
appliance free standing open hearth
solid fuel appliance
joists
supported
on hangers
*in Scotland, joists, etc
should be at least
200mm from inner
surface of flue. Brickwork
or blockwork in chimney
construction should be at
least 100mm thick and
have a density of at least
1600 kg/m3. Aircrete
blocks may be used if at
least 150mm thick
prefabricated
cavity throating
cavity
tray
DETAIL A DETAIL B
flaunching
Freeze/thaw
resistant
(F2,S1) bricks
690 to 840mm
350mm
APPLIANCES RECESS -
WITH RAFT LINTEL, SUITABLE FOR FREE STANDING ROOM HEATER
vermiculite
concrete
6.8
350mm
690 to 840mm
FIREPLACE RECESS -
FOR INSET OPEN FIRE (WITHOUT BOILER UNIT) VARIOUS TERMINALS
(see Clause S5)
PLAN OF RECESS
head fixings
Appendix 6.8-D
Notes
1 The weather surface is the building external surface, such as its roof, tiles or
external walls.
2 A flat roof has a pitch less than 10°.
3 The clearance given for A or B, as appropriate, will also apply.
6.8
Appendix 6.8-E
600mm
boundary
2000mm
Q
I
B D,E
C
H
F
J
N
A
L
M
H
G
I H
boundary K
6.8
6.8
L From an opening in the car 1200 1200 (3) 1200
port into the building
M Vertically from a terminal 1200 1500 (3) 1500
on the same wall
N Horizontally from a 300 300 (3) 300
terminal on the same wall
P From a structure on the N/A N/A 1500mm if a ridge terminal. N/A
roof For any other terminal, as
given in BS 5440-1:2000
Q Above the highest point of N/A Site in accordance with Site in accordance with BS 150
intersection with the roof manufacturer’s instructions 5440-1:2000
Notes:
1 An opening here means an openable element, such as an openable window, or a fixed opening such as an air vent. However, in addition, the
outlet should not be nearer than 150mm (fanned draught) or 300mm (natural draught) to an opening into the building fabric formed for the
purpose of accommodating a built in element, such as a window frame.
2 Boundary as defined in Paragraph 0.4. of Approved Document J: smaller separations to the boundary may be acceptable for appliances that
have been shown to operate safely with such separations from surfaces adjacent to or opposite the flue outlet.
3 Should not be used.
4 This dimension may be reduced to 75mm for appliances of up to 5kW input (net).
5 N/A means not applicable.
Appendix 6.8-F
boundary
N
F C,D
J
B
A
H K
E F
G F L
boundary
Notes:
1 Terminals should only be positioned on walls where appliances have been approved for
such configurations when tested in accordance with BS EN 303-1:1999 or OFTEC standards
OFS A100 or OFS A101.
2 An opening means an openable element, such as an openable window, or a permanently
open air vent.
3 Notwithstanding the dimensions above, a terminal should be at least 300mm from
combustible material, e.g. a window frame.
4 A way of providing protection of combustible material would be to fit a heat shield at least
750mm wide.
5 Where a terminal is used with a vaporising burner, the terminal should be at least 2300mm
horizontally from the roof.
6 Outlets for vertical balanced flues in locations M, N and O should be in accordance with
manufacturer’s instructions.
INDEX
A G W
Appliances 3, 4 Gas appliances 3, 6, 9, 10 Walls 1, 8, 11
B H Weather resistance 2, 5
Back boilers 3 Hearths 1, 3, 4, 6
Balanced flues 4 Height 2, 15, 16, 17
Bricks and blocks 5, 8 M
C Masonry chimneys 3, 8
Cappings 3, 9, 12, 13 Mortar 6
Chimney breasts 12, 14 O
Chimney pots 2 Oil appliances 9, 10
Chimneys 2, 3, 4, 7, Outlets, position 2, 4, 5, 8, 9
12, 13, 14
P
Cleaning, flues 2, 7
Pressure zones 2
Combustion air 1, 3, 4, 9, 10
R
Coring 8
Recesses 1, 13, 14
D
Render 2
Damp penetration 4, 8
S
Damp proof courses 2, 6, 14
Smoke test 9
Draught control unit 7
Solid fuel 1, 3, 9, 10
F
Solid fuel effect appliances 3, 10
Fire hazards 1, 2, 7
Stability 2, 5, 7, 9
Fireplaces 1, 3, 4, 6,
Stone masonry 5
12, 13, 14
6.8
T
Flashings 6, 14
Terminals 2, 4, 5,
Flue block chimneys 3, 6, 8, 9
6, 13
Flue direction and length 2, 3, 4
Testing 9
Flue liners 2, 3, 5, 6, 7
Timber frame construction 5
Flue pipes 1, 3, 4, 7, 10
Twin wall flue systems 6
Flue size 1, 2, 3, 4, 10
Foundations 2
Frost resistance 2
Chapter 6.9
6.9
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
CONTENTS
MATERIALS
Material standards M1 8
Dpc/dpm materials M2 8
Glazing M3 8
Gaskets M4 8
Sealant M5 8
Thermal insulation M6 8
Breather membranes M7 8
Cavity barriers and fire-stops M8 8
Fixings M9 9
Timber preservation M10 9
Ventilation screens M11 9
SITEWORK
Sitework standards S1-S2 9
Handling and storage S3 9
Curtain walling
Location and fixing S4 9
Weather resistance S5 9
Glazing S6 10
Control of condensation S7 10
Allowance for movement S8 10
Tolerances S9 10
Testing S10 10
6.9
Licensed copy from CIS: [email protected], Silcock Dawson & Partners, 13/02/2013, Uncontrolled Copy.
6.9
the design, be ventilated.
Cladding panels
The outer layer of a rainscreen cladding
system that shields other parts of the
system from direct rain.
Curtain walling
A form of vertical building enclosure
that supports no load other than its own
weight and the environmental forces that
Typical curtain walling system
act upon it, e.g. wind, water and solar.
Curtain walling also includes slope glazing
and coupled door and window frame
RAINSCREEN CLADDING assemblies one storey or more in height
This Chapter deals with rainscreen (including spandrel panels).
cladding systems that comprise:
• an outer skin of panels, which have Curtain walling system
open, baffled, or labyrinth (rebated) The vertical building enclosure system,
joints. Joints should not be sealed including all frames, brackets, fixings,
• a pressure equalised air gap at least flashings, gutters, copings, glass, panels,
50mm wide between the insulation and gaskets and sealant that form the assembly.
the panels
CWCT
• an insulated airtight backing wall.
The Centre for Window and Cladding
Typical brick slip cladding system Technology at Bath University.
detailed guidance on performance and Packing of brackets to achieve surface • the junctions with roof constructions
testing. tolerance should be permitted only and parapets.
in accordance with the product
Other certification bodies or test (g) testing
manufacturer’s recommendations.
documentation may be acceptable if they Air and water testing of the ‘prototype’
are considered by NHBC to be a suitable (b) insulating glass units curtain walling system should be carried
alternative. Insulating glass units should be in out in accordance with and pass the CWCT
accordance with Chapter 6.7 ‘Doors, Standard (test sequence A or B) tested at a
The certification, together with all test
windows and glazing’. test pressure of 600 Pascals. Panels tested
documentation should be made available
should be of similar size and configuration
to NHBC before work on the curtain walling (c) weather resistance to those to be used on the building.
or cladding begins on site. The curtain walling system, including
doors, windows and other openings, should Where the maximum calculated design
The use of the system should be within
resist the passage of water to the inside of wind pressure is above 2400 Pascals the
the scope of the certification and test
the building, allow free drainage and not test pressure should be increased to 0.25 x
documentation.
trap water. It should have: the design wind pressure.
• external and internal air and water seals,
IN-SERVICE and
The ‘prototype’ should remain watertight
during and after the test.
PERFORMANCE • drained and ventilated glazing rebates.
At a test pressure of 600 Pascals an air
6.9 - D6 Curtain walling systems shall Particular attention should be given to infiltration rate no higher than 1.5m3/hr/
be designed and specified to ensure the interfaces between the curtain walling m2 for fixed glazed panels is permissible
adequate in-service performance system and other elements or cladding provided there is no evidence of
Items to be taken into account include: systems. concentrated leakage.
(a) loads, movement, brackets and External and internal air and water seals Wind resistance, serviceability and safety
fixings and a drained ventilated cavity should be testing should be carried out in accordance
Dead and live loads should be transferred provided at all interfaces. Guidance on with the CWCT Standard.
safely to the building’s structure without interfaces is provided in Appendix 6.9-A.
undue permanent deformation or (h) electrical continuity and earth
deflection of any component. (d) air infiltration bonding
Appropriate gaskets and sealants should The curtain walling system should
Imposed loads should be calculated in be used to resist the flow of air from the comply with BS 7671 ‘Requirements for
accordance with BS EN 1991-1-1 and BS EN outside to the interior surface of the Electrical Installations, formerly IEE Wiring
1991-1-4 and take account of both internal curtain walling system. Particular attention Regulations’ and BS EN 62305 ‘Protection
and external pressures, together with the should be given to the interfaces between against lightning. General principles’.
location, shape and size of the building. the curtain walling system and the walls,
Thermal-induced loads due to differential roof, doors, windows and cladding system. (i) durability
6.9
stresses caused by temperature gradients The curtain walling system should be
Pre-formed factory-moulded ‘picture
within materials or components should be constructed with corrosion resistant or
frame’ type vulcanised epdm or silicone
accommodated without any reduction in adequately protected materials. The risk of
internal gaskets should be used for all
performance. The stresses in components bimetallic corrosion should be avoided by
curtain walling systems.
and materials should not exceed the the isolation of dissimilar metals.
permissible values recommended by the Sealant should be specified in accordance
Aluminium components should be
product manufacturer. with BS 6213 and the manufacturer’s
separated from direct contact with
recommendations.
Movement within the curtain walling cementitious surfaces.
should be accommodated without any (e) condensation The curtain walling system should not
reduction in performance. Causes of The curtain walling system should be include materials liable to infestation
movement include: designed to minimise the risk of surface attack by micro-organisms, fungi, insects
• dead and live loads and interstitial condensation by the use of or vermin.
• changes in temperature thermal breaks and a continuous vapour
• changes in the moisture content of control layer. Where timber is used it should be treated
components in accordance with the guidance in Chapter
Thermal bridging should be controlled to 2.3 ‘Timber preservation (natural solid
• freezing of retained moisture
ensure no part of the curtain wall is more timber)’. Timber should only be used
• creep.
at risk of surface condensation forming where it can be easily inspected and
Fixings and supports should be designed than the glazing. replaced without disturbing the curtain
to accommodate specified loads and take walling system.
account of the product manufacturer’s (f) acoustic performance
recommendations. Noise from the curtain walling system (j) tolerances
caused by loads, movements and changes The design should allow for the line, level,
Pull-out or destructive testing of anchors in the environmental conditions should be plumb and plane of the completed curtain
and fixings should be carried out in accommodated without being intrusive. wall to be within reasonable tolerances.
accordance with the design, BS 5080
The curtain walling system should be See Chapter 1.2 ‘A consistent approach to
and the Construction Fixings Association
designed to resist the passage of airborne finishes’.
Guidance Note ‘Procedure for Site Testing
Construction Fixings’. Tests should be and impact sound within the building.
carried out at a suitable rate agreed with Particular attention should be given to
NHBC. The test results should be made flanking transmission at:
available to NHBC. • the edges of separating floors
• the outer ends of separating walls
• the outer ends of partition walls
Rainscreen cladding • freezing of retained moisture The air gap should be adequately
• creep. ventilated. Dpc/dpm trays with stop ends
CERTIFICATION Fixing rails, frames, fixings and fasteners
should be provided above openings, at the
base of the rainscreen and at interfaces
6.9 - D7 Rainscreen cladding systems should be designed to accommodate
where necessary, to ensure water is
shall be designed and certificated in specified loads and take account of the
drained to the outside.
accordance with appropriate Standards product manufacturer’s recommendations.
Particular attention should be given to the
Rainscreen cladding systems, including Pull-out or destructive testing of anchors
interface between the rainscreen cladding
panels, should have current certification and fixings should be carried out in
system and the walls, roof, doors, windows,
confirming satisfactory assessment by accordance with the design, BS 5080
other cladding systems, and curtain
an appropriate independent technical and the Construction Fixings Association
walling. External and internal air and water
approvals authority accepted by NHBC, Guidance Note ‘Procedure for Site Testing
seals should be provided at all interfaces.
including: British Board of Agrément (BBA) Construction Fixings’. Tests should be
Guidance on interfaces is provided in
or Building Research Establishment (BRE) carried out at a suitable rate agreed with
Appendix 6.9-A.
Certification. NHBC. The test results should be made
available to NHBC. Open, baffled or labyrinth (rebated) joints
Systems that are assessed and certificated should normally have a minimum opening
by an appropriate independent technical Bonded fixings should be specified only
of 10mm.
approvals organisation in accordance where there is no suitable alternative and
with the CWCT Standard for Systemised should be designed in accordance with the
Building Envelopes will normally be product manufacturer’s recommendations.
acceptable to NHBC.
Packing of the supporting rails,
10mm (min) open joint
Other certification bodies or test frame or the panel fixings to achieve
documentation, may be acceptable if they surface tolerance should be permitted
are considered by NHBC to be a suitable only in accordance with the product
alternative. manufacturer’s recommendations.
The certification, together with all test The air gap between the face of the
documentation should be made available insulation and the back of the rainscreen
to NHBC before work on the rainscreen panels should be of sufficient width to 10mm (min) baffled joint
IN-SERVICE
Where the insulation is fixed to the backing
PERFORMANCE
horizontal cavity
closer at each
wall a minimum of one non-combustible floor level
fixing per square metre or per insulation 6.9 - D10 Insulated render systems shall
batt, whichever is the lesser, should be be designed and specified to ensure
provided in addition to the other fixings. adequate in-service performance
This compartmentation is in addition
Reference should be made to BRE to the requirements of the Building Items to be taken into account include:
document BR135 - 2003 ‘Fire performance Regulations for cavity barriers to control (a) loads, movement and fixings
of external thermal insulation for walls of the spread of smoke and fire. However, the Dead and live loads should be transferred
multi-storey buildings’ when specifying the same cavity barriers may be used for the safely to the building’s structure without
type of insulation system to be installed. compartmentation. undue permanent deformation or
The design should ensure that the deflection of any component.
(g) acoustic performance
insulation is continuous around Imposed loads should be calculated in
Noise from the rainscreen cladding system
penetrations through the rainscreen accordance with BS EN 1991-1-1 and BS EN
caused by rain striking the outer surface of
cladding system. 1991-1-4 and take account of the location,
panels should be accommodated without
6.9
Where the rainscreen panel joints are open being intrusive e.g. by the use of noise shape and size of the building.
and the performance of the insulation absorbing or anti-drumming material.
Thermal-induced loads due to differential
could be diminished by moisture, a stresses caused by temperature gradients
breather membrane should be provided (h) electrical continuity and earth
bonding within materials or components should be
over the outer face of the insulation. accommodated without any reduction in
The rainscreen cladding system should
comply with BS 7671 ‘Requirements for performance. The stresses in components
(d) thermal bridging and condensation
Electrical Installations, formerly IEE Wiring and materials should not exceed the
The rainscreen cladding system should be
Regulations’ and BS EN 62305 ‘Protection permissible values recommended by the
designed to minimise the risk of thermal
against lightning. General principles’. manufacturer.
bridging and, surface and interstitial
condensation. Movement within the insulated render
(i) durability
system should be accommodated without
A vapour control layer should be provided The rainscreen cladding system should
any reduction in performance. Causes of
unless a condensation risk analysis in be designed with corrosion resistant,
movement include:
accordance with BS 5250 shows that one adequately protected or durable materials.
• dead and live loads
is not necessary. The vapour control layer
Fixings and bracketry should normally be • changes in temperature
should be fixed on the warm side of the
stainless steel or a suitable non-ferrous • changes in the moisture content of
wall insulation.
metal. components
(e) air infiltration • freezing of retained moisture
The risk of bimetallic corrosion should • creep.
The rainscreen cladding system should be
be avoided by the isolation of dissimilar
fixed to a backing wall that is reasonably
metals. Movement joints in the backing wall should
airtight, e.g:
be continued through the insulated render
• masonry walls jointed to a high standard Aluminium components should be system and formed in accordance with the
with all joints filled separated from direct contact with manufacturer’s recommendations.
• framed walls with a rigid sheathing on cementitious surfaces.
the cavity face with all joints taped or Fixing rails, frames, mechanical and
sealed. The rainscreen cladding system should bonded fixings should be designed
not include materials liable to infestation to accommodate specified loads and
Where reasonable airtightness cannot be attack by micro-organisms, fungi, insects take account of the manufacturer’s
achieved, a separate continuous vapour or vermin. recommendations.
permeable air barrier with joints taped or
sealed should be provided on the outer (j) tolerances Pull-out or destructive testing of anchors
face of the backing wall. The design should allow for the line, and fixings should be carried out in
level, plumb and plane of the completed
accordance with the design, BS 5080 Where appropriate, a screen to prevent (f) render
and the Construction Fixings Association birds and animals entering the cavity Proprietary render systems should
Guidance Note ‘Procedure for Site Testing should be provided at the top and bottom be specified in accordance with the
Construction Fixings’. Tests should be of the cavity and to penetrations through manufacturer’s recommendations and
carried out at a suitable rate agreed with the cladding. include the correct number and thickness
NHBC. The test results should be made of render coats.
available to NHBC. (c) insulation
The insulation type should be suitable for Corners, returns and features should
(b) weather resistance the intended purpose and be appropriately be formed with appropriate trims in
Insulated render systems, together with keyed to receive the render finish. accordance with the manufacturer’s
the backing wall to which they are applied, recommendations.
The insulated render system should be
should satisfactorily resist the passage of
securely fixed to the support frame or (g) durability
moisture to the inside of the building.
backing wall with appropriate fixings/ The insulated render system should be
For timber and steel framed backing adhesive in accordance with the designed with corrosion resistant or
walls a cavity of at least 15mm should manufacturer’s recommendations. adequately protected materials.
be provided between the wall and the non-combustible fixings
Fixings and bracketry should normally be
insulation to allow any moisture to drain
stainless steel, suitable non-ferrous metal
away.
or suitable plastics.
Where the backing wall is timber framed
The risk of bimetallic corrosion should
the cavity should be ventilated in
be avoided by the isolation of dissimilar
accordance with Chapter 6.2 ‘External
metals.
timber framed walls’ (Design).
steel frame timber frame The insulated render system should not
include materials liable to infestation
attack by micro-organisms, fungi, insects
or vermin.
Thermal-induced loads due to differential steel frame timber frame Reference should be made to BRE
stresses caused by temperature gradients document BR135 - 2003 ‘Fire performance
within materials or components should be of external thermal insulation for walls of
accommodated without any reduction in multi-storey buildings’ when specifying the
performance. The stresses in components type of insulation system to be installed.
and materials should not exceed
The design should ensure the continuity
permissible values recommended by the
of insulation around openings and other
manufacturer.
penetrations.
Movement within the brick slip system
should be accommodated without any (d) thermal bridging and condensation
reduction in performance. Causes of The brick slip cladding system should be
movement include: designed to minimise the risk of thermal
• dead and live loads bridging and surface and interstitial
• changes in temperature 15mm (min)
drained cavity
15mm (min) drained
and ventilated cavity
condensation.
• changes in the moisture content of A vapour control layer should be provided
components The introduction of a cavity is likely to
increase the risk of impact damage to unless a condensation risk analysis in
• freezing of retained moisture accordance with BS 5250 shows that one
• creep. vulnerable areas of the brick slip cladding
system, e.g. at low level, around balconies is not necessary. The vapour control layer
Movement joints in the backing wall and where cradle systems, etc. can come should be fixed on the warm side of the
should be continued through the brick slip into contact with the façade. Suitable wall insulation.
cladding system and formed in accordance precautions to resist impact damage (e) carriers
with the manufacturer’s recommendations. should be included in the design e.g. by Proprietary carriers forming an integral
the provision of a rigid board behind the part of the brick slip cladding system
Fixing rails, frames, fixings and fasteners
insulation whilst maintaining the cavity. should be fixed with appropriate
should be designed to accommodate
specified loads and take account of the Dpc/dpm trays with stop ends should be fixings/adhesive in accordance with the
manufacturer’s recommendations. provided above openings, above cavity manufacturer’s recommendations.
barriers, at the base of the brick slip
Bonded fixings of rails, frames, fixings (f) brick slips
cladding system and at interfaces where
and fasteners should be specified only Brick slips should be specified and
necessary to ensure water is drained to
where there is no suitable alternative and fixed in accordance with the system
the outside. The brick slip support system
should be designed in accordance with the manufacturer’s recommendations.
should not obstruct the drainage paths.
manufacturer’s recommendations.
The design should ensure that excessive
Brick slip cladding systems can be applied
Pull-out or destructive testing of anchors cutting of brick slips is avoided, e.g. in
direct to concrete panels or masonry
and fixings should be carried out in the storey heights, at corners and around
backing walls without a cavity being
6.9
accordance with the design, BS 5080 openings. Coursing should be arranged to
provided.
and the Construction Fixings Association suit lintel heights.
Guidance Note ‘Procedure for Site Testing Particular attention should be given to the
Construction Fixings’. Tests should be interfaces between the brick slip cladding
carried out at a suitable rate agreed with system and the walls, roof, doors, windows,
NHBC. The test results should be made other cladding systems and curtain walling.
insulation (carrier)
available to NHBC. Guidance on interfaces is provided in neatly cut
around opening
Appendix 6.9-A.
(b) weather resistance
Brick slip cladding systems, together with Sealants should be specified in accordance
the backing wall to which they are applied, with BS 6213 and the manufacturer’s
should satisfactorily resist the passage of recommendations.
moisture.
Where appropriate a screen to prevent
For timber and steel framed backing birds and animals entering the cavity
walls a cavity of at least 15mm should be should be provided at the top and bottom
provided between the wall and the brick of the cavity and to penetrations through (g) joints
slip cladding system to allow any moisture the cladding. Mortars, proprietary mortars and grouts
to drain away. should be specified in accordance with the
(c) insulation
Where the backing wall is timber framed Insulation forming an integral part of system manufacturer’s recommendations
the cavity should be ventilated in the brick slip cladding system should to enable each joint to be adequately filled
accordance with Chapter 6.2 ‘External be specified and fixed with appropriate and appropriately struck.
timber framed walls’ (Design). fixings/adhesive in accordance with the (h) durability
manufacturer’s recommendations. Fixings for the brick slip cladding
Other insulation included in the design system should be corrosion resistant or
should be suitable for its intended purpose adequately protected materials.
and be specified and fixed with appropriate Fixings and bracketry should normally be
fixings/adhesive in accordance with the stainless steel, suitable non-ferrous metal
manufacturer’s recommendations. or appropriate plastics.
A minimum of one non-combustible fixing The risk of bimetallic corrosion should
per square metre or per insulation batt, be avoided by the isolation of dissimilar
whichever is the lesser, should be provided metals.
in addition to the other fixings.
The brick slip cladding system should References to British Standards and Codes Sealant should be selected and applied in
not include materials liable to infestation of Practice include those made under the accordance with BS 6213 and BS EN ISO
attack by micro-organisms, fungi, insects Construction Products Directive (89/106/ 11600.
or vermin. EEC) and, in particular, appropriate
Sealant to be used in locations where
European Technical Specifications
(i) tolerances differential movement may be expected,
approved by a European Committee for
The design should allow for the line, e.g. interfaces between the façade and the
Standardisation (CEN).
level, plumb and plane of the completed structure, should be one of the following:
brick slip cladding system to be within • two part polysulphide
reasonable tolerances for the materials
DPC/DPM MATERIALS • one part polysulphide
involved. See Chapter 1.2 ‘ A consistent 6.9 - M2 Materials for damp-proofing • one part silicone
approach to finishes’. shall resist adequately the passage of • one or two part polyurethane.
moisture Other materials may be used if
General Items to be taken into account include: satisfactorily assessed in accordance with
(a) dpcs/dpms Technical Requirement R3.
PROVISION OF The following materials are acceptable for
use as dpcs/dpms:
INFORMATION • polyethylene to BS 6515
THERMAL INSULATION
6.9 - D13 Designs and specifications • EPDM 6.9 - M6 Insulation materials shall
shall be produced in a clearly • neoprene provide the degree of insulation to
understandable format and include all • proprietary materials assessed in comply with the design
relevant information accordance with Technical Requirement
Insulation materials should be inert,
R3.
Drawings and specifications should durable, rot and vermin proof and should
include: Materials for dpcs/dpms should be not be adversely affected by moisture or
• full set of drawings compatible with adjoining materials. vapour.
• schedule of revisions
Dpcs/dpms and flexible cavity trays should Insulation materials that comply with the
• manufacturer’s specification
be of the correct dimensions to suit the following Standards are acceptable:
• fixing schedules
detailed design. • mineral wool to BS EN 13162
• specific details of all interfaces
• FR grade (flame retardant) expanded
• manufacturer’s recommendations For complicated junctions, preformed polystyrene to BS EN 13163
relating to proprietary items cavity trays are recommended. • FR grade (flame retardant) extruded
• on-site testing regime.
polystyrene to BS EN 13164
(b) flashings
6.9 - D14 All relevant information shall • rigid polyurethane foam and
The following are acceptable as flashings:
be distributed to appropriate personnel polyisocyanurate to BS EN 13165
• rolled lead sheet (at least code 4)
• phenolic foam to BS EN 13166
Ensure that design and specification complying with BS EN 12588
6.9
6.9
• hold a certificate confirming they sealants should be used in accordance
TIMBER PRESERVATION have been trained by the system with the design and the manufacturer’s
manufacturer, supplier or installer. recommendations.
6.9 - M10 Timber shall be either
naturally durable or preservative treated Pre-formed factory-moulded ‘picture
to provide adequate protection against
HANDLING AND STORAGE frame’ type vulcanised epdm or silicone
rot and insect attack 6.9 - S3 Materials, products and internal gaskets should be used.
systems shall be protected and stored
Reference should be made to Chapter 2.3
in a satisfactory manner to prevent
‘Timber preservation (natural solid timber)’
damage, distortion, uneven weathering
(each section) for guidance on preservative
and degradation picture frame gasket
treatments.
Items to be taken into account include:
VENTILATION SCREENS (a) handling and storage
The curtain walling or cladding system
6.9 - M11 Ventilation openings shall be
should be transported, lifted, handled
protected from the entry of birds and
and stored in accordance with the
animals manufacturer’s recommendations.
Ventilation openings where the least
Insulated glass units should be carefully
dimension exceeds 10mm should be
stored and protected in a sheltered dry
protected to prevent the entry of birds and
area.
animals.
Acceptable protection of openings can be (b) protection
provided by: All practical steps should be taken to avoid typical profile
• rigid fabrications with width of opening the risk of damage to the curtain walling or
greater than 3mm and less than 10mm cladding system during construction.
(no restriction on length) External and internal air and water seals
• rigid fabrications with round holes Curtain walling and a drained cavity should be provided
greater than 3mm and less than 10mm at all interfaces. Guidance on interfaces is
diameter LOCATION AND FIXING provided in Appendix 6.9-A.
• square or rectangular mesh where the
6.9 - S4 Curtain walling systems shall (c) dpcs/dpms
clear opening size is greater than 3mm
be correctly located and securely fixed Dpcs/dpms should be installed correctly to
and less than 10mm.
in accordance with the design provide a physical barrier to the passage
of moisture. Dpc/dpm arrangements which
rely solely on sealant should not be used. including all joints and interfaces which • the isolation of aluminium from
Guidance on the use of dpcs/dpms at are designed to be permanently closed and cementitious material.
interfaces is provided in Appendix 6.9-A. watertight.
Dpc/dpm arrangements should extend Representative samples of the finished WEATHER RESISTANCE
the full height of the curtain walling installation should be hose tested on site 6.9 - S12 Rainscreen cladding systems
system and have appropriate details at in accordance with the current CWCT shall be correctly installed to prevent
all interfaces including floors, walls, roofs, Standard for curtain walling. moisture entering the building
balconies and terraces, to ensure moisture
is directed to the outside. Items to be taken into account include:
(a) weathertightness
(d) opening doors and lights Rainscreen cladding systems including
Opening doors and lights should be fitted door, window and other openings and
in accordance with the design, hang square cover flashings, should be installed
hose test of
within the curtain wall frame and fit neatly typical interface correctly to ensure satisfactory in-service
with minimum gaps to ensure effective performance.
weatherproofing.
Installation should prevent water reaching
any parts of the wall that could be
GLAZING adversely affected by the presence of
6.9 - S6 Glazing shall be carried out in moisture.
accordance with relevant standards
The following minimum air gap should be
Glazing should be carried out in maintained behind all rainscreen panels:
accordance with Chapter 6.7 ‘Doors, • 50mm for panels with open joints, or
windows and glazing’ (Design and • 38mm for panels with baffle or labyrinth
Sitework). (rebated) joints.
50mm (min) 38mm (min)
At least 5% of the completed curtain
CONTROL OF walling system should be tested, with
CONDENSATION particular focus on vulnerable areas such
6.9 - S7 Installation shall ensure that as joints and interfaces.
the risk of condensation is minimised Other testing may be acceptable if it
Insulation should be installed in is considered by NHBC to be a suitable
accordance with the design, ensuring that alternative.
all interfaces are adequately insulated. The results of all testing should be made
A continuous, durable vapour control layer available to NHBC.
6.9
be in accordance with the design. See Anchors, fixings and bracketry should
Chapter 1.2 ‘ A consistent approach to normally be stainless steel or a suitable
finishes’. non-ferrous metal.
Proprietary fixings should be used in
TESTING accordance with the manufacturer’s
6.9 - S10 Site hose testing shall be recommendations with particular attention 10mm (min) labyrinth (rebated) joint
the cavity should be provided at the top (d) compartmentation ALLOWANCE FOR
and bottom of the rainscreen and to To help achieve pressure equalisation in
penetrations through the cladding. open jointed rainscreen cladding systems, MOVEMENT
the cavity should be compartmented by: 6.9 - S13 Installation shall allow
Where required by the design, dpcs/dpms
• a horizontal cavity closer at each floor movement of the rainscreen cladding
should be installed correctly to provide a
level, and system and the building without causing
physical barrier to the passage of moisture.
• vertical cavity closers at centres not damage or deformation
Dpc/dpm arrangements which rely solely
exceeding 6.0m, and
on sealant should not be used. Allowance for movement e.g. at interfaces
• vertical cavity closers at centres not
exceeding 1.5m in the area within 6.0m and at gaps between panels, should be
To ensure moisture is directed to the
of an internal or external corner, and provided in accordance with the design.
outside, dpc/dpm arrangements should be
correctly formed with suitable upstands • a vertical cavity closer as close as
and stop ends including at the junction possible to an external corner, normally TOLERANCES
between the rainscreen cladding and any within 300mm.
6.9 - S14 Installation shall achieve the
other component or system. External and 1.5m (max) design tolerances
internal air and water seals and a drained 6.0m (max)
cavity should be provided at all interfaces. Installation should allow for the line,
Guidance on interfaces is provided in level, plumb and plane of the completed
Appendix 6.9-A. rainscreen cladding system to be within
reasonable tolerances for the materials
Appropriate sealants should be used horizontal cavity involved. See Chapter 1.2 ‘ A consistent
closer at each
in accordance with the design and the floor level approach to finishes’.
manufacturer’s recommendations to
ensure satisfactory performance.
Insulated Render Systems
(b) insulation and condensation This compartmentation is in addition
Where insulation forms part of the to the requirements of the Building FIXING
rainscreen, it should be installed in Regulations for cavity barriers to control 6.9 - S15 Insulated render systems shall
accordance with the design and the the spread of smoke and fire. However, the
be securely fixed in accordance with the
manufacturer’s recommendations, same cavity barriers may be used for the
design
ensuring that all parts of the backing wall compartmentation.
are adequately insulated. Insulated render systems should be
Cavity closers should be rigid and securely fixed in accordance with
Where the rainscreen panel joints are be installed in accordance with the the design and the manufacturer’s
open and the insulation could be adversely manufacturer’s recommendations with recommendations.
affected by the presence of water, a particular attention given to maintaining
continuous durable breather membrane ventilation and drainage in accordance The type, size and positioning of all
with the design. anchors, fixing rails, frames, fixings,
6.9
should be provided to the outer face of the
insulation. fasteners and bonded joints should be in
(e) durability accordance with the design.
Where the insulation is fixed to the backing The rainscreen cladding system should
wall, a minimum of one non-combustible be fabricated and installed with corrosion Anchors, fixings and bracketry should
fixing per square metre or per batt, resistant or adequately protected normally be stainless steel, suitable non-
whichever is the lesser, should be provided materials. ferrous metal or appropriate plastics.
in addition to the other fixings. For mechanically-fixed systems particular
Fixings and bracketry should normally
Installation should ensure that the be stainless steel or suitable non-ferrous attention should be given to:
insulation is continuous around metal. • correct embedment, spacing and edge
penetrations through the rainscreen. distances
The risk of bimetallic corrosion should • correct torque settings
The rainscreen cladding system should be be avoided by the isolation of dissimilar • provision of suitable locking nuts and
installed to minimise the risk of thermal metals. washers
bridging and surface and interstitial • the isolation of dissimilar metals
Aluminium components should be
condensation. • the isolation of aluminium from
separated from direct contact with
cementitious material.
(c) air infiltration cementitious surfaces.
The rainscreen cladding system should be For adhesive-fixed systems particular
The rainscreen cladding system should
fixed to a backing wall that is reasonably attention should be given to:
not include materials liable to infestation
airtight, e.g: • thorough assessment of the backing wall
attack by micro-organisms, fungi, insects
• masonry walls jointed to a high standard to confirm adhesive fixing is suitable
or vermin.
with all joints filled • suitable preparation of the backing wall
• framed walls with a rigid sheathing on (f) testing to receive the adhesive
the cavity face with all joints taped or On-site hose or sparge bar testing should • the provision of supplementary
sealed. be carried out with particular emphasis mechanical fixings as required by the
on interfaces that are designed to be design.
Where reasonable airtightness cannot be
permanently closed and watertight.
achieved, a separate continuous vapour
permeable air barrier with joints taped or The building should remain watertight
WEATHER RESISTANCE
sealed should be provided on the outer during and after the test. 6.9 - S16 Insulated render systems
face of the backing wall. shall be correctly installed to prevent
moisture entering the building
Items to be taken into account include:
(a) weathertightness Insulation should be returned into window Where coloured pigments are specified,
Insulated render systems should be and door openings and be continuous batching should be undertaken with care
installed correctly to ensure satisfactory around penetrations through the wall. to ensure colour consistency.
in-service performance.
Insulated render systems should prevent TOLERANCES
water reaching any parts of the wall 6.9 - S17 Installation shall achieve the
that could be adversely affected by the design tolerances
presence of moisture.
Installation should allow for the line,
Where the backing wall is timber or steel level, plumb and plane of the completed
framed a cavity of at least 15mm should insulated render system to be within
be provided between the wall and the reasonable tolerances for the materials
insulation to allow moisture to drain away. involved. See Chapter 1.2 ‘ A consistent
approach to finishes’.
Where the backing wall is timber framed
the cavity should be ventilated in
accordance with Chapter 6.2 ‘External Brick Slip Cladding Systems
timber framed walls’ (Design).
steel frame timber frame
FIXING
6.9 - S18 Brick slip cladding systems
all layers neatly cut
shall be securely fixed in accordance
around flue outlet with the design
Brick slip cladding systems should
(c) air infiltration be securely fixed in accordance with
The backing wall should be reasonably the design and the manufacturer’s
airtight before installation of the insulated recommendations.
render system, e.g.
• masonry walls jointed to a high standard The type, size and positioning of all
with all joints etc filled anchors, fixing rails, frames, fixings,
15mm (min) 15mm (min) drained
• framed walls with a rigid sheathing on fasteners and bonded joints should be in
drained cavity and ventilated cavity
the cavity face with all joints taped and accordance with the design.
Suitable precautions to resist impact sealed. Anchors, fixings and bracketry should
damage should be provided in accordance
(d) reinforcement normally be stainless steel, suitable non-
with the design.
Reinforcement mesh should be provided in ferrous metal or appropriate plastics.
Where required by the design a screen accordance with the design taking account Particular attention should be given to:
should be provided to prevent birds and
6.9
6.9
To ensure moisture is directed to the avoided. external dpc/dpm
ensuring that all parts of the backing wall the manufacturer’s recommendations.
internal
are adequately insulated. Each joint should be adequately filled and dpc/dpm
appropriately struck.
Insulation should be returned into window
and door openings and be continuous
around penetrations through the wall.
TOLERANCES
roofing membrane
6.9 - S20 Installation shall achieve
satisfactory appearance
Installation should allow for the line,
level, plumb and plane of the completed
brick slip cladding system to be within 2. Curtain walling to balcony/terrace
reasonable tolerances for the materials Vertical section
involved. See Chapter 1.2 ‘ A consistent
approach to finishes’.
internal seal
dpc/dpm
roofing
membrane
dpc/dpm
external seal
external seal
external
dpc/dpm
internal
dpc/dpm
external seal
external seal
4. Curtain walling to soffit 6. Brick slip cladding to insulated render 8. Penetration of gas flue through
Vertical section system insulated render system on light gauge
Horizontal section steel frame
6.9
Horizontal section
INDEX
A E M
Accessibility for 2 Earth bonding 3, 5 Movement 2, 4, 5, 6,
maintenance Electrical continuity 3, 5 9, 11
Acoustic performance 3, 5 F P
Air infiltration 3, 4, 10, Fire-stops 8 Primary components 2
12, 13 Provision of information 7
Fixings 2, 4, 5, 6, 8
B R
G
Backing wall 1, 4, 5, 6, 7 Reinforcement 6, 12
Gaskets 8, 9
Brackets 2 Replaceable components 2
H
Breather membranes 8 S
Handling and storage 9
Brick slips 7, 13 Sealant 8, 9
I
C Secondary components 2
In-service performance 2, 4, 5, 6
Carriers 7 T
Insulated glass units 3
Cavity barriers 8 Testing 3, 10, 11
Insulated render 1, 5, 11
Certification 2, 3, 5, 6 Tolerances 3, 5, 6, 7, 9,
Insulation 4, 6, 7, 8,
Compartmentation 5, 11 10, 12, 13 11, 12, 13
Condensation 3, 4, 6, 7, Interfaces 13 V
9, 10 Ventilation screens 8
J
D W
Joints 7, 13
Design life 2 Weather resistance 3, 4, 5, 6,
L
Dpcs/dpms 8, 9 9, 10, 11, 12
Loads 2, 4, 5, 6
Durability 3, 5, 6, 7, 11 Weathertightness 9, 10, 11, 12
CONTENTS SCOPE
DESIGN Clause Page This Chapter gives guidance on meeting the Technical
Design standards D1 1 Requirements and recommendations for light steel framed walls
and floors.
Statutory requirements D2 1
Steel and fixings D3 1
Loadbearing walls D4 1
Non-loadbearing walls D5 1
Moisture control and insulation D6 2
Exterior cladding D7 2
Floors D8 2
Services D9 4
Acoustic performance D10 4
Control of fire D11 4
Provision of information D12-D13 4
Certification D14 4
MATERIALS
Material standards M1 4
Steel and fixings M2 4
Damp-proof courses M3 5
Wallties and fixings M4 5
Sheathing M5 5
Breather membranes M6 5
Thermal insulation M7 5
Vapour control layers M8 5
Plasterboard M9 5
6.10
SITEWORK
Sitework standards S1 6
Construction of loadbearing walls and S2 6
external infillwalls
Insulation S3 7
Breather membranes S4 7
Wallties and fixings S5 7
Vapour control layers S6 7
Cladding S7 7
Construction of non-loadbearing internal S8 8
walls
Separating walls S9 8
Light steel joists S10-S15 8 -10
Separating floors S16 10
Services S17 10
Control of fire S18 10
APPENDIX 6.10-A
Certification procedure 10
INDEX 11
6.10
1-1, BS EN 1991-1-3 and BS EN 1991-1-4 (e) racking
STATUTORY including: Wall panels may provide resistance to
• dead loads
REQUIREMENTS • imposed loads
racking forces using one or more of the
following techniques:
6.10 - D2 Design shall comply with all • wind loads. • internal bracing
relevant statutory requirements • snow loads • crossed flat bracing
Design should be in accordance with • internal sheathing board
(c) structural elements
relevant Building Regulations and other • external lining board
Individual studs should not be less than
statutory requirements. • rigid frame action.
36mm wide, spaced at not more than
600mm centres, unless agreed with NHBC Methods adopted should be justified either
STEEL AND FIXINGS and other support is provided for wall by design to BS EN 1993-1-1 or tested to BS
boards and fixings. EN 594.
6.10 - D3 Steel and fixings shall be
suitable for the design and adequately A lintel should be provided to any opening
protected against corrosion in loadbearing panels where one or more NON-LOADBEARING
Items to be taken into account include:
studs is cut or displaced to form the WALLS
opening. A lintel is not required where an
(a) steel opening falls between studs. 6.10 - D5 Non-loadbearing walls
Steel should be grade S280 or S350 to BS incorporating light steel members shall
EN 10326. Grade S390 steel may be used lintel above window opening
have adequate strength and support
if it has a nominal yield strength of 390N/
mm2 and meets with the concepts of BS Items to take into account include:
EN 10326. (a) construction
The following form of construction is
To provide adequate protection against acceptable:
corrosion due to condensation and the • light steel partitions using studs, head
environment, steel should be pre-galvanised and base rails from sections not smaller
in accordance with BS EN 10326 to provide than 43mm x 32mm x 0.45mm
a minimum zinc coating of 275 g/m2. • stud spacings to suit the thickness of
plasterboard, as follows:
- not more than 450mm spacing for
9.5mm boards
- not more than 600mm spacing for
12.5mm or thicker boards.
(b) movement joints Dpcs and trays should be provided at EXTERIOR CLADDING
Non-loadbearing walls should not bridge openings to prevent rain penetration.
movement joints in the main structure. 6.10 - D7 Exterior cladding shall be
(b) membranes compatible with the steel frame
A joint should be constructed between the Breather membranes and other barriers,
frame and any chimney or flue to prevent Items to be taken into account include:
where provided, should be lapped so that
load transfer onto the chimney or flue. each joint is protected and moisture drains (a) wall ties
outwards. Wall ties for masonry claddings should be:
(c) support • of a type which accommodates
Non-loadbearing walls should be supported (c) cavities in external walls differential movement between the light
from the structural floor, not by a floating A clear cavity should be provided to reduce steel frame and the cladding - see clause
floor that incorporates a compressible the risk of rain penetrating to the frame. D7(c) below
layer, unless the floating floor is The following minimum cavity widths, • fixed through to the studs, not the
specifically designed for that purpose. measured between the claddings and sheathing
sheathings, should be provided: • installed at a minimum density of 3.7
Allowance should be made for the possible
ties/m2 e.g. spaced at a maximum
deflection of floors at the head of non-
Cladding Cavity width of 600mm horizontally and 450mm
loadbearing walls to prevent the wall
vertically (see Sitework clause 6.10 - S5)
becoming loadbearing. Masonry 50mm nominal
• spaced at jambs of openings a maximum
Render on backed 25mm nominal of 300mm vertically within 225mm of
lathing the masonry reveal. Additional studs
Vertical tile No vertical cavity may be needed to achieve this
hanging without required when a • inclined away from the light steel
underlay breather membrane is framing.
provided
Other cladding* 15mm nominal (b) masonry claddings
Soft joints should be provided to allow for
* see Chapter 6.9 ‘Curtain walling and differential movement. A gap of 1mm per
cladding’ metre of masonry should be provided at
openings and soffits.
The cavity should extend at least 150mm
below the dpc and be kept clear to allow
drainage. Weep holes or other suitable
SUPPORT WHERE WALL IS means of drainage should be provided
PARALLEL AND BETWEEN JOISTS
where necessary to prevent water build up
in the cavity.
6.10
channel fixed to
structure over (d) insulation and interstitial
condensation
head rail should
The BRE Report ‘Thermal insulation:
compressible joint
not be connected
to top track
avoiding risks’ discusses aspects of to be 1.0mm thick
per metre of masonry
insulation relevant to external light to allow for vertical
movement
steel framed walls. In England and Wales
account should be taken of Accredited
Details for Part L.
A vapour control layer should be provided
unless a condensation risk analysis in (c) other claddings
accordance with BS 5250 shows that one For other claddings reference should be
is not necessary. The vapour control layer made to Chapter 6.9 ‘Curtain walling and
should be fixed on the warm side of the cladding’ (Design and Sitework).
wall insulation.
SUPPORT WHERE FLOOR OR
BEAM IS ABOVE WALL
The vapour control layer should cover the
FLOORS
external wall including base rails, head 6.10 - D8 Suspended floors shall be
rails, studs, lintels and window reveals. designed to support and transmit loads
MOISTURE CONTROL AND safely to the supporting structure
INSULATION Vapour control layers should be of
without undue deflection
500g polyethylene or vapour control
6.10 - D6 Wall designs shall ensure that plasterboard. Items to be taken into account include:
the structure is adequately protected (a) dead and imposed loads
from the effects of moisture Insulation should continue 150mm below
Floors should be designed to resist loading
the base rail of the steel wall to minimise
Items to be taken into account include: in accordance with BS EN 1991-1-1 including:
thermal bridging.
• dead loads
(a) provision of dpcs and dpms
Insulation with an integral facing on one • imposed loads.
Dpcs should be installed beneath and
for the full width of the lowest section of side only, e.g. a foil facing, should have the
Information concerning balcony loading
framing (e.g. all ground floor walls and facing on the cavity side. The facing should
is given in Chapter 7.1 ‘Flat roofs and
internal partitions) to protect the steel not be used as the vapour control layer.
balconies’ (Design and Sitework).
from corrosion due to moisture. The dpc Service pipes, conduits, etc within walls
should be wide enough to lap with the should be on the warm side of the (b) joist spacing
dpm. insulation. Steel joists should be spaced at centres
not greater than 600mm.
(c) deflection each other at the cross-over point and (g) openings
The in-service performance of light create noise Suitably sized trimmers should be provided
steel joists should be controlled by four around floor openings.
serviceability criteria:
(h) notching and holing
Static criteria: The flanges of light steel joists should
i) the maximum deflection for a single joist not be notched except to accommodate
due to imposed load should be limited to connections.
span/450 • solid blocking provided to every third
ii) the maximum deflection for a single joist pair of joists with ties between them Drilling or punching through the web
due to dead and imposed loads should be should only be carried out within
limited to the lesser of span/350 or 15mm. recognised limits (see Sitework clause
6.10-S11).
Dynamic criteria:
iii) the natural frequency of the floor (i) ground floors
should be limited to 8Hz for dead load Light steel joists used in ground floor
plus 0.2 x imposed load. This can be • joists alternately reversed and tied construction should have thermal
achieved by limiting the deflection of a together in pairs insulation positioned to ensure that
single joist to 5mm for the given condensation does not form on the joists.
loading
The junction between the ground floor
iv) the deflection of the floor (i.e. a series
joists and their support should be designed
of joists plus the floor decking) when
to maintain the durability of the floor. Light
subject to a 1kN point load should be
steel floor joists and ring beams in ground
limited to the following values: • joists alternately reversed and floors should be galvanised to 450g/m2.
continuous ties (e.g. resilient bar) fixed Alternatively they can be galvanised to
Span (m) Max. deflection (mm)
to the joist flanges. 275g/m2 with additional protection of a
3.5 1.7
two-coat bitumen based coating to BS
3.8 1.6
1070, BS 3416 or BS 6949, or have a two
4.2 1.5 coat liquid asphaltic composition applied.
4.6 1.4 Ring beams to ground floors should be
5.3 1.3 totally protected and joists protected
6.2 1.2 (f) floor decking for 300mm adjacent to an external wall
The correct thickness of decking should be support or ring beam.
The deflection of a single joist is specified for the joist centres used.
(j) resistance to ground moisture
dependent on the overall floor The thickness should be not less than Provision should be made to prevent
construction and the number of effective
6.10
those shown in this table for normal ground moisture affecting light steel
joists that are deemed to share the applied domestic loads, i.e. an imposed load of floors.
1kN point load. The following table gives 1.5kN/m2.
typical values: This can be achieved by either:
• 50mm concrete or 50mm fine aggregate
Floor configuration Number of effective Floor decking Thickness of decking
[mm] on a polyethylene membrane laid on
joists 50mm sand blinding, or
Joist centres
Joist centres • 100mm concrete.
400mm 600mm
400mm 600mm
Chipboard 18 22 Where necessary, oversite concrete should
Chipboard, plywood 2.5 2.35 be protected against sulfate attack by the
or oriented strand Plywood 15 18/19
use of a polyethylene sheet dpm, not less
board Oriented strand 15 18/19
board
than 1200 gauge (0.3mm) (or 1000 gauge
Built-up acoustic 4 3.5 if assessed in accordance with Technical
floor
Note Requirement R3), properly lapped.
(d) attachment to supporting structure Oriented strand board should be laid with
(k) ventilation of underfloor voids
Light steel joists should be fixed to the stronger axis at right angles to the
A minimum ventilation void of 150mm
supporting walls by web cleats, direct supports. Other decking materials not listed
should be provided below the floor.
attachment to wall studs, or by bearing in the table should comply with Technical
onto the supporting structure. In the latter Requirement R3. The above thicknesses On shrinkable soils where heave could take
configuration, bearing stiffeners may be may not be adequate to achieve a mass place, an allowance for movement should
required. for floor decking of 15 kg/m2 for sound be added to the underfloor ventilation
insulation requirements of floors in England requirement to determine the minimum
(e) prevention of roll & Wales. dimension of the floor void. The allowance
Floors constructed using joists with an for movement relates to the shrinkage
The floor deck is generally used as a
asymmetric web (e.g. of ‘C’ or Sigma potential of the soil as follows:
diaphragm and, to achieve this, floor
profile) can cause the floor to ‘roll’. To • high potential - 150mm
boarding should be attached using self-
avoid this, one of the following alternatives • medium potential - 100mm
drilling, self-tapping screws, ring shank
should be used where the span exceeds • low potential - 50mm.
nails or other approved fixings at 300mm
3.5m for ‘C’ joists or 4.2m for Sigma joists:
maximum centres. T&g joints should be Voids should be ventilated by openings
• a continuous line (or lines) of proprietary
glued. providing not less than either 1500mm2
steel herringbone struts provided
between the joists. The pairs of struts per metre run of external wall or 500mm2
should have a physical gap between per m2 of floor area, whichever gives the
them so that they do not rub against greater opening area.
Ensure that design and specification if it has a nominal yield strength of 390N/
6.10 - D11 Walls and floors shall resist information is issued to site supervisors mm2 and meets the concepts of
the spread of fire and relevant specialist subcontractors and/ BS EN 10326.
All structural elements should have or suppliers. To provide adequate protection against
adequate fire resistance. Where proprietary products are to be corrosion due to condensation and the
used, manufacturers usually have specific environment, the steel should be pre-
Items to be taken into account include: galvanised in accordance with BS EN 10326 to
requirements for fixing and/or assembly
(a) ceilings provide a minimum zinc coating of 275g/m2.
of their products. This information should
Ceilings should provide the necessary fire
also be made available for reference Light steel floor joists and ring beams
protection to floors constructed with light
on site so that work can be carried out in ground floors should be galvanised
steel joists. Either one or two layers of
satisfactorily in accordance with the design to 450g/m2. Alternatively they can be
plasterboard are required and at least one
and specification. galvanised to 275g/m2 with additional
of these should be fire-rated. When two
layers of board are used, joints should be Copies of the assembly instructions should protection of a two-coat bitumen based
staggered between layers. Boards should be given to the person doing the job. coating to BS 1070, BS 3416 or BS 6949,
be attached using self-drilling, self-tapping or have a two coat liquid asphaltic
composition applied. Ring beams to ground
screws. CERTIFICATION floors should be totally protected and
(b) cavity barriers 6.10 - D14 Design of the superstructure joists protected for 300mm adjacent to the
Cavity barriers should be provided shall be checked by an NHBC steel frame support or ring beam.
in accordance with relevant Building certifier
Regulations. (b) compatibility
The specific project details should be Where two metals are to be joined they
Horizontal cavity barriers (except under checked by an NHBC steel frame certifier should be compatible and not cause
eaves) should be protected with a dpc tray. so that a certificate can be issued in bimetallic corrosion in that environment.
The tray should have a minimum upstand accordance with Appendix 6.10-A. The Alternatively the two metals should be
of 100mm. Alternatively polyethylene project certificate should be made isolated from each other.
encased cavity barriers providing a available on site for inspection by NHBC.
minimum upstand of 100mm should be The choice of fixings needs to take account
used. of bimetallic corrosion which can occur
when two dissimilar metals are in contact.
(c) connectors Plywood sheathing should be: Minimum 500 gauge polyethylene sheet
The following connectors are acceptable: • of performance characteristics or vapour control plasterboard should be
• zinc plated bolts should be in determined in accordance with BS EN used.
accordance with BS 4190 13986 table 7
Vapour control products manufactured
• countersunk bolts should be in • suitable for in humid conditions to BS
from recycled materials should be
accordance with BS 4933 EN 636
assessed in accordance with Technical
• screws should be in accordance with • at least 5.5mm thick
Requirement R3.
BS 5427 • appropriate to the exposure of the
• rivets should be in accordance with the building.
manufacturer’s recommendations PLASTERBOARD
Oriented strand board should be OSB3 to
• self-piercing rivets should be in 6.10 - M9 Plasterboard shall be of a
BS EN 300 and be at least 8mm thick.
accordance with the manufacturer’s suitable thickness for its intended use
recommendations Proprietary sheathing materials should
• ring shank nails should be in accordance be assessed in accordance with Technical Plasterboard should be to BS 1230.
with BS EN 10263 Requirement R3 and used in accordance Plasterboard thickness should be not less
• welded connections should be in with the assessment. than:
accordance with BS 5135. The welding • 9.5mm for stud spacings up to 450mm
wire should be in accordance with • 12.5mm for stud spacing up to 600mm.
BS 2901.
BREATHER MEMBRANES
To provide fire-resistance, fire-rated boards
6.10 - M6 Breather membranes shall be
Cleats should comply with the should be used and installed in accordance
capable of allowing water vapour from
requirements of BS EN 1993-1-1. with the manufacturer’s instructions.
within the frame to pass out into the
cavity and protect the sheathing and
(d) holding down devices
frame from external moisture CAVITY BARRIERS AND
Holding down devices should be
manufactured from mild steel with zinc Breather membranes should be: FIRE-STOPS
coating to BS 729 or BS 1706 and be • vapour resistant to less than 0.6MNs/g 6.10 - M10 Materials used for cavity
suitable for the environment they will be when calculated from the results of tests barriers and fire-stops shall be capable
exposed to. carried out in accordance with BS 3177 of providing adequate resistance to fire
at 25°C and relative humidity of 75% and smoke
Holding down devices manufactured from
• capable of resisting water penetration
stainless steel to BS EN 10095 will be Materials specified in statutory requirements
• self-extinguishing
suitable in any environment. are acceptable.
• durable
• adequately strong when wet to resist Suitable fire-stopping materials include:
DAMP-PROOF COURSES site damage • mineral wool
6.10 - M3 Materials for damp-proofing • Type 1 to BS 4016 in areas of Very • glass wool
6.10
shall adequately resist the passage of Severe exposure. • cement mortar
moisture • gypsum plaster
Materials which are acceptable for use as THERMAL INSULATION • intumescent mastic or preformed strip
• proprietary sealing systems (particularly
dpcs include: 6.10 - M7 Insulation materials shall be of
those designed for service penetrations)
• polyethylene to BS 6515 a suitable thickness to comply with the
assessed in accordance with Technical
• bitumen to BS 6398 design and statutory requirements Requirement R3 to maintain the fire
• proprietary materials assessed in
Insulation materials should be inert, resistance of the wall.
accordance with Technical Requirement
durable, rot and vermin proof and should
R3.
not be adversely affected by moisture or FLOOR DECKING
vapour.
WALL TIES AND FIXINGS 6.10 - M11 The type and thickness of the
The following materials are acceptable: decking material shall have adequate
6.10 - M4 Wall ties and fixings shall • mineral wool to BS EN 13162 strength and moisture resistance
connect the steel frame to the cladding • FR (flame retardant) grade expanded
in accordance with the design polystyrene to BS EN 13163 The following materials are acceptable:
• FR (flame retardant) grade extruded • moisture-resistant chipboard Type P5 to
For masonry claddings wall ties should
polystyrene to BS EN 13164 BS EN 312
be of austenitic stainless steel, phosphor
• rigid polyurethane foam and • oriented strand board Type OSB3 to BS
bronze or silicon bronze. Materials for wall
polyisocyanurate to BS EN 13165 EN 300
ties should be compatible. Stainless steel,
• phenolic foam to BS EN 13166 • plywood in accordance with BS EN 636.
phosphor bronze and silicon bronze are
compatible with each other. • cellular glass to BS EN 13167. Fixings and supports should be as
Other insulation materials should be recommended by the manufacturer.
For other claddings, ties and fixings should
be assessed in accordance with Technical assessed in accordance with Technical Floor decking materials not covered by
Requirement R3. Requirement R3. a British Standard should be assessed in
accordance with Technical Requirement R3.
SHEATHING VAPOUR CONTROL
6.10 - M5 Sheathing shall be durable LAYERS
and capable of providing structural 6.10 - M8 Vapour control layers shall
resistance to racking restrict the passage of water vapour
Cement bonded particle board sheathing from within the dwelling to the steel
should be in accordance with BS EN 634 frame
and BS EN 13986.
set out in accordance with the design. The Wall panels should be securely fixed together
loads from the light steel frame should be and to floors in accordance with the design.
supported as detailed in the design. 25x25mm
spacing blocks 20mm 30mm (f) masonry claddings
Soft joints should be provided to allow for
10m differential movement. A gap of 1mm per
metre of wall height should be provided at
openings and soffits.
(c) anchoring the frame
The frame should be anchored to resist
both lateral movement and uplift as
required by the design.
compressible joint
chemical anchor at to be 1.0mm thick
overhangs should frame maximum 12mm from 20o from vertical per metre of masonry
not exceed 12mm edge with ledge protected to allow for vertical
movement
6.10
framing
Masonry 50mm nominal
• be kept clean and free from mortar CLADDING
Render on backed 25mm nominal
droppings. 6.10 - S7 Cladding shall be correctly
lathing
Vertical tile hanging No vertical cavity Wall ties should be spaced as required by installed
without underlay required when a the design but not less than 3.7 ties/ Masonry cladding should be constructed
breather membrane is m2 e.g. spaced at a maximum of 600mm in accordance with Chapter 6.1 ‘External
provided
horizontally and 450mm vertically. At masonry walls’ (Design and Sitework).
Other cladding* 15mm nominal jambs of openings the spacing should be
a maximum of 300mm vertically with ties For other claddings reference should be
* see Chapter 6.9 ‘Curtain walling and set within 225mm of the masonry reveal. made to Chapter 6.9 ‘Curtain walling and
cladding’ cladding’ (Design and Sitework).
Other fixings should be of the type
The cavity should be extended at least specified, and be fixed in accordance with A clear cavity should be provided between
150mm below the dpc and be kept clear the design. the sheathing and the cladding. The cavity
to allow drainage. Weep holes or other should be drained. Where wall areas are
suitable means of drainage should be divided by cavity barriers, the drainage of
provided where necessary to prevent water the cavity should be maintained or cavity
build up in the cavity. trays and weep holes installed.
Drainage at the base of the cladding
system should be equivalent to 500mm2 /m
run (e.g. for masonry, one open perpend
150mm minimum
every 1.5m).
Openings for drainage should be placed to
prevent the ingress of rain.
The cavity should be kept clean, free of
obstructions and should be capable of
draining freely.
(c) alterations
Steelwork should only be altered with the Noggings or straps should be provided
approval of the designer. Welded or flame as required to support fittings, such as
cut edges should be cleaned and treated radiators, wall-mounted boilers, sanitary
with a zinc-rich paint to prevent corrosion. fittings, kitchen units, etc.
(d) support and fixings Fixing and finishing of partitions should be
Non-loadbearing partitions should be fixed in accordance with Chapter 8.2 ‘Wall and
in accordance with the design. They should ceiling finishes’ (Sitework).
be fixed to the floor on which they stand,
at the head, to each other and to abutting SEPARATING WALLS
walls. Noggings or extra studs should be
used where shown in the design. 6.10 - S9 Construction of separating floor joists supported on ‘Z‘
section attached to wall frame
walls shall ensure adequate sound
insulation
The design details should be carefully
followed.
There should be no gaps in the:
• mineral wool quilt or batts
• wallboard layers
• fire-stopping.
Services in or adjacent to separating walls
should be installed in accordance with the
design. (See clause 6.10 - S17).
(d) joist length and end support span exceeds 3.5m for ‘C’ joists or 4.2m for reinforced service hole
Sigma joists unless otherwise specified in
the design:
• a continuous line (or lines) of proprietary
steel herringbone strutting provided grommet (to all punched holes)
between the joists. The pairs of ties
should have a physical gap between
them so that they do not rub against elongated service hole
each other at the cross-over point and
cause noise
6.10
properly fixed to prevent disruption of
Where joists bear onto steelwork or finishes
are supported by cleats, blocking is not Where joists overlap on loadbearing
unacceptable notch
necessary adjacent to the supports. intermediate walls they should be fixed
(i) alterations together with bolts or screws to prevent
Joists should only be altered with the the floor decking being pushed up or
approval of the designer. Welded or flame the ceiling being cracked when the
cut edges should be cleaned and treated cantilevered part of the joist moves
with a zinc-rich paint to prevent corrosion. upwards.
6.10 - S15 Floor decking and ceilings Grommets should be used around the edge • A detailed description of the system
shall be adequately fixed of service holes to protect electrical cables • Details of any limitations of its use
and reduce the risk of bimetallic corrosion • Information for reference by the
Items to be taken into account include:
between the light steel framing and copper designer and steel frame project
(a) decking pipes. certifier.
Flooring should be attached using
self-drilling, self-tapping screws, ring Swaged holes will not require grommets * The manufacturer is the company which
shank nails or other approved fixings in for the passage of electric cables and assembles the steel frame sections to form
accordance with the design at centres not plastic piping. the wall and/or floor panels.
more than 300mm. T&g joints should be
In Scotland services are not permitted If in doubt consult with NHBC Technical.
glued.
within a separating wall cavity.
Stage 2 - Project certification
CONTROL OF FIRE NHBC requires the builder to appoint a
steel frame project certifier to check the
6.10 - S18 Fire spread shall be controlled specific design of the steel framed housing
as detailed in the design on the specific site.
Items to be taken into account include: The steel frame project certifier will ensure
(a) walls that the proposals are in accordance with:
Walls should be constructed in accordance • The manufacturer’s system certificate
with the design and relevant Building issued by SCI, and
Regulations to achieve the necessary fire • NHBC Standards Chapter 6.10 ‘Light
resistance. steel framed walls and floors’.
Topic Description
Description of system Key features
Application The use(s) to which the system can be put, e.g. max number of storeys,
type of cladding
Durability Confirmation that design life is at least 60 years
Grade of steel
Corrosion protection
Supplementary protection
Strength and stability Structural design philosophy including Codes of Practice referenced
and test reports
Grade of steel (traceability)
Section properties
Loading
Ultimate Limit State
Serviceability Limit State
Resistance to overturning
Racking resistance
Holding down
Connections
Structural integrity
Positions and sizes of holes through members
Claddings Which claddings are acceptable?
Provision of cavity
Type of wall ties
Behaviour in relation to fire Which internal linings are necessary?
Fire-stops and cavity barriers
Condensation risk Type, thickness and location of insulation material
6.10
Sound insulation Does specification comply with Building Regulations/Robust Details?
Balconies, terraces, and Any specific design considerations
parapets
Other Other information of relevance to the designer and steel frame certifier
INDEX
A G S
Accuracy 6 Ground floors 3 Separating walls 8
Alterations 6, 8, 9 H Services 4, 10
B Holding down 5 Setting out 6, 8
Breather membranes 2, 5, 7 I Sheathing 5
C Insulation 2, 5, 7 Sound insulation 4, 10
Cavities 2, 7 J Steel 1, 4, 8, 9
Cavity barriers and fire-stops 4, 5, 10 Joists 2, 8 System Certification 4, 10
Claddings 2, 6, 7 L T
Compatibility 1, 4 Loadbearing walls 1 Thermal insulation 5
Connections 1 M V
Connectors 5 Moisture control 2 Vapour control layers 5, 7
Control of fire 4, 10 N Ventilation (of voids) 3
D Non-loadbearing walls 1, 8 W
Deflection 3 P Wall ties and fixings 2, 5, 7
Design 1 Plasterboard 5
Dpc and dpm 2, 5 Project certification 4, 10
F R
Fixings 4, 5, 6, 7 Restraint strapping 9
Floor decking 3, 5, 10 Roll 3, 9
Floors 2, 3, 4