EV Station IT Infrastructure Project Plan.

The document outlines a project plan with 25 tasks related to IT infrastructure setup, spanning from November to December 2024. Each task includes details such as task ID, name, category, assigned personnel, start and end dates, duration, dependencies, and status. All tasks are currently marked as 'Pending'.

Uploaded by

wasimakram020189
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views1 page

EV Station IT Infrastructure Project Plan.

The document outlines a project plan with 25 tasks related to IT infrastructure setup, spanning from November to December 2024. Each task includes details such as task ID, name, category, assigned personnel, start and end dates, duration, dependencies, and status. All tasks are currently marked as 'Pending'.

Uploaded by

wasimakram020189
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Task ID Task Name CategorySubcategory

Assigned ToStart Date End Date


Duration (Minutes)
Dependencies Status
1 Conduct sitPlanning a Feasibility Project Ma2024-11-2 2024-11-2 60 Pending
2 Finalize IT Planning a Design Infrastruct 2024-11-2 2024-11-2 120 1 Pending
3 Approvals Planning a Approvals Project Ma2024-11-2 2024-11-2 180 2 Pending
4 Identify veProcuremeVendor SelProcureme2024-11-2 2024-11-2 90 3 Pending
5 Place orderProcuremeOrdering Procureme2024-11-2 2024-11-2 60 4 Pending
6 Receive anProcuremeInspection IT Team 2024-11-2 2024-11-2 30 5 Pending
7 Setup netwo Network InCabling Network En2024-11-2 2024-11-2 180 6 Pending
8 Install net Network InInstallationNetwork En2024-11-2 2024-11-2 120 7 Pending
9 Configure Network InConfigurat Network En2024-11-2 2024-11-2 150 8 Pending
10 Perform neNetwork InTesting Network En2024-11-2 2024-11-2 90 9 Pending
11 Unpack andHardware UnpackingIT Team 2024-11-2 2024-11-2 60 10 Pending
12 Install and Hardware InstallationIT Team 2024-11-2 2024-11-2 90 11 Pending
13 Connect anHardware Power Set Electrical 2024-11-3 2024-11-3 60 12 Pending
14 Install ope Software COS Installa System Ad 2024-12-0 2024-12-0 120 13 Pending
15 Configure Software CConfigurat System Ad 2024-12-0 2024-12-0 180 14 Pending
16 Setup dataSoftware CDatabase SDBA 2024-12-0 2024-12-0 90 15 Pending
17 Install fire Security Firewall InsSecurity En2024-12-0 2024-12-0 120 16 Pending
18 Configure Security VPN ConfigSecurity En2024-12-0 2024-12-0 90 17 Pending
19 Conduct peSecurity Testing Security En2024-12-0 2024-12-0 180 18 Pending
20 Integrate IntegrationIntegrationIT Team 2024-12-0 2024-12-0 180 19 Pending
21 Perform enIntegrationTesting IT Team 2024-12-0 2024-12-0 120 20 Pending
22 Validate daIntegrationValidation IT Team 2024-12-0 2024-12-0 60 21 Pending
23 Document Handover
s DocumentaDocumentat 2024-12-0 2024-12-0 120 22 Pending
24 Train operaHandover Training Trainer 2024-12-0 2024-12-0 180 23 Pending
25 Conduct fi Handover Approval Project Ma2024-12-0 2024-12-0 90 24 Pending