M4 PMC 21CV733
M4 PMC 21CV733
Fig. 1: Tractor
It is important equipment for earth movement. It converts engine energy into tractive energy.
Tractors are usually worked by diesel engines.
Fig. 7: Dragline
Operations of a Dragline: Excavation is started by swinging the empty bucket to the digging
position at the same time slackening the drag and the hoist cables. Excavation is done by pulling
the bucket toward the machine while maintaining tension in the hoist cable. When the bucket is
filled, the operator takes in the hoist cable while paying out the drag cable. Dumping is done by
releasing the drag cable. Filling the bucket, hoisting, swinging and dumping of the loaded bucket,
followed in that order, constitute one cycle. An experienced operator can cast the excavated
1 Sand Content IS: 2720 (Part – 4) Two tests per 3000 cum
2 Plasticity test IS: 2720 (Part – 5) Each type, two tests per 3000 cum
3 Density test IS: 2720 (Part – 8) Two tests per 3000 cum subject to a
minimum of one test per 1000 Sqm.
5 Moisture Content IS: 2720 (Part – 2) One test per 250 cum.
Material Properties:
MDD: 15.2 kN/Cum for embankment up to 3.0m height, 16.0 kN/Cum for embankment more
than 3.0m height. For fly ash, separate density requirement as per contract shall be applicable.
CBR: Minimum CBR requirement NIL
Coarse material: Size not more than 75mm
Free swell index: Not exceeding 50% (to be used only below 500mm of top of the
embankment)
Liquid Limit: Not exceeding 70
Plasticity Index: Not exceeding 45
1 Sand Content IS: 2720 (Part – 4) Two tests per 3000 cum
2 Atterberg’s limits IS: 2720 (Part – 5) Two tests per 3000 cum
3 Density test IS: 2720 (Part – 8) Two tests per 3000 cum subject to a
minimum of one test per 1000 Sqm.
5 Moisture Content IS: 2720 (Part – 2) Two tests per 3000 cum.
6 CBR Test IS: 2720 (Part – 16) One test per 3000 cum
7 Density of IS: 2720 (Part – 28) Ten tests per 3000 cum
compacted layer