ARCHITECTURAL PERMIT (1)
ARCHITECTURAL PERMIT (1)
ARCHITECTURAL PERMIT
APPLICATION NO. AP NO. BUILDING PERMIT NO.
LOCATION OF CONSTRUCTION: LOT NO. ________ BLK NO. ________ TCT NO. ________ TAX DECLARATION __________________
STREET __________________________ BARANGAY ______________________ CITY/MUNICIPALITY _________________________
SCOPE OF WORK
□ NEW CONSTRUCTION □ RENOVATION_______________ □ RAISING _______________________________________
□ ERECTION □ CONVERSION _______________ □ ACCESSORY BUILDING STRUCTURE _________________
□ ADDITION □ REPAIR ____________________ □ OTHERS (Specify) _______________________________
□ ALTERATION □ MOVING ___________________ ______________________________________________
BOX 3 BOX 4
DESIGN PROFESSIONAL, PLANS AND SPECIFICATIONS SUPERVISOR/IN‐CHARGE OF ARCHITECTURAL WORKS
Address Address
PRC No. Validity PRC No. Validity
IAPOA No. O.R. NO. Date Issued IAPOA No. O.R. No. Date Issued
PTR No. Place Issued Date Issued PTR No. Place Issued Date Issued
TIN TIN
BOX 5 BOX 6
BUILDING OWNER WITH MY CONSENT: LOT OWNER
__________________________________ __________________________________
(Signature and Sealed Over Printed Name) (Signature and Sealed Over Printed Name)
Date _________________ Date _________________
Address Address
C.T.C No. Date Issued Place Issued C.T.C No. Date Issued Place Issued
NBC FORMS
□ 1. VICINITY MAP/LOCATION PLAN WITHIN A TWO‐KILOMETER □ 8. DETAILS OF RAMPS, PARKING FOR THE DISABLED,
RADIUS STAIRS, FIRE ESCAPES, CABINETS AND PARTITIONS
□ 2. SITE DEVELOPMENT PLAN □ 9. SCHEDULE OF DOOR AND WINDOWS
□ 3. PERPECTIVE □ 10. SCHEDULE OF FINISHES FLOORS, CEILINGS AND WALL
□ 4. FLOORS PLANS □ 11. ARCHITECTURAL INTERIOR
□ 5. ELEVATIONS, AT LEAST FOUR (4) □ 12. SPECIFICATIONS
□ 6. SECTIONS, AT LEAST TWO (2) □ 13. COST ESTIMATE
□ 7. CEILING PLANS SHOWING LIGHTNING FIXTURES AND □ 14. OTHERS (Specify)
DIFFUSERS __________________________________________
__________________________________________
BOX 8
PROGRESS FLOW
BOX 9
ACTION TAKEN
1. That under Article 1723 of the Civil Code of the Philippines, the architect (and engineer) who drew up the plans
and specifications for a building/structure is responsible for damages if within fifteen (15) years from the
completion of the building/structure, the same should collapse due to defect in the plans or specifications or
defects in the ground. The engineer or architect who supervises the construction shall be solidary liable with
the contractor the edifice collapse due to defect in the construction or the use of inferior materials.
2. That the proposed architectural works shall be in accordance with the architectural plans filed with this office
and in conformity with the latest Architectural Code of the Philippines, the National Building Code and its IRR.
3. That prior to any construction activity, a duly accomplished prescribed “Notice of Construction” shall be
submitted to the Office of the Building Official.
4. That upon the completion of the construction, the licensed full‐time inspector and supervisor/in‐charge of
construction works shall submit the entry to the logbook duly signed and sealed to the Building Official including
as‐built plans and other documents, and shall also accomplish the Certificate of Completion stating that the
architectural works conform to the provisions Architectural Code, the National Building Code and its IRR.
5. That this permit is null and void unless accompanied by the building permit.
01/03/22