METHOD STATEMENT OF
CONCRETE PAVEMENT
AEI-CVL-MES-0324-0005_A
PREPARED FOR
CONTRACTOR
PT. Tripatra
Sign :
Date :
EPC PEMBANGUNAN SP ABG STAGE 1 – AKASIA BAGUS
PAVING PAVEMENT METHOD STATEMENT
10
Page 2 of 10
EPC PEMBANGUNAN SP ABG STAGE 1 – AKASIA BAGUS
PAVING PAVEMENT METHOD STATEMENT
TABLE OF CONTENT
REVISION LOG REGISTER ...................................................................................................................2
TABLE OF CONTENT ............................................................................................................................ 3
1. Scope Of Work ................................................................................................................................. 4
2. Reference ......................................................................................................................................... 4
3. Definitions ......................................................................................................................................... 4
4. Responsibilities ................................................................................................................................. 4
4.1. Project Manager...................................................................................................................... 4
4.2. Construction Manager ............................................................................................................ 5
4.3. Site Engineer .......................................................................................................................... 5
4.4. QA/QC Engineer / Inspector ................................................................................................... 6
4.5. Surveyor .................................................................................................................................. 6
4.6. HSE Engineer/Officer ............................................................................................................. 6
4.7. Foremen/ Works Supervisor ................................................................................................... 7
5. MATERIAL, EQUIPMENT, AND METHOD TO BE EMPLOYED ..................................................... 7
5.1. Material Requirements ............................................................................................................ 7
5.2. Equipment List ........................................................................................................................ 7
5.3. Method Implemented .............................................................................................................. 8
Page 3 of 10
EPC PEMBANGUNAN SP ABG STAGE 1 – AKASIA BAGUS
PAVING PAVEMENT METHOD STATEMENT
1. Scope Of Work
2. Reference
9849-ABG-TPEC-CIV-RFP-0005_Rev A, RFP Pekerjaan Sipil dan Shelter
3. Definitions
COMPANY : PT. Tripatra
CONTRACTOR : PT. Asuka Engineering Indonesia
SUB-CONTRACTOR : The company that manufactures or supplies equipment and
services to perform duties specified by CONTRACTOR.
"VENDOR" covers Manufacturer/ Supplier/Sub-vendor.
4. Responsibilities
Group / person who will be responsible in the site is listed bellow :
1) Project Manager
2) Construction Manager
3) Site Engineer
4) QA/QC Inspector
5) Safety Officer
6) Foremen / Work Supervisors
7) Equipment Operators
8) Skilled and unskilled labourers
Page 4 of 10
EPC PEMBANGUNAN SP ABG STAGE 1 – AKASIA BAGUS
PAVING PAVEMENT METHOD STATEMENT
1. The engineer shall carry out his duties in a manner that shall be co-ordinated
by the project manager on a daily basis, and shall ensure proper distribution
of the workforce and equipment at required locations.
2. To be aware of test frequencies related to the formation level.
3. To control disposal of waste excavated material according to the instructions
received from the Project Manager.
4. To co-ordinate with the Safety Officer to maintain safe working and proper
housekeeping of the site. To comply with the safety measures and ensure that
all Safety Officer Teams are aware of the same to prevent accident and loss.
5. To monitor and check all activities and ensure that works shall be carried out
according to specifications, quality and approved drawings.
6. To inform the QC Inspector of the areas ready for inspection.
Page 5 of 10
EPC PEMBANGUNAN SP ABG STAGE 1 – AKASIA BAGUS
PAVING PAVEMENT METHOD STATEMENT
4.5. Surveyor
Page 6 of 10
EPC PEMBANGUNAN SP ABG STAGE 1 – AKASIA BAGUS
PAVING PAVEMENT METHOD STATEMENT
1. Ensure the works are progressed in the sequence as agreed with the Project
Manager.
2. Liaise with the Project / Construction Manager for the allocation of the work
force, ensuring adequate manpower is available.
3. Liaise with the site manager to ensure all the required plant / materials are
available to construct the works.
4. Full time supervision shall be required to ensure the works are carried out in
accordance to specifications, quality and approved drawings.
Page 7 of 10
EPC PEMBANGUNAN SP ABG STAGE 1 – AKASIA BAGUS
PAVING PAVEMENT METHOD STATEMENT
8) Concrete Pump
9) Vibrator
f. After 2 times passed, the compacted area tested with Plat Bearing,
and if the result is enough, the Vibro Roller will go onto next area that
needed to compact, if its not, the Vibro will need compact the area 2
times passed more.
g. Surveyors checked the checked the elevation of compacted area. If its
enough (same as planned elevation) then the lean concrete is spread.
h. Make a lean concrete from cement, black sand, and coral with 1 : 4 :
5 composition for lean concrete, then pour and spread it on top of the
compacted sand.
i. After the lean concrete has 1 days age, spread the plastic sheets and
then form a formwork and wiremesh form (that already form) on the
site.
j. Make sure the formwork and wiremesh is solid and sturdy
k. Make sure the wiremesh is tied with wire and bottow of wiremesh has
a decking between wiremesh and plastic sheet
l. Make sure the formwork doesn’t make leak the concrete, make sure
its all sealed.
m. After everything set, pour the ready mix due to strength specification
or pour the fresh concrete with approved composition into the form
work. Then use the Vibrator to flow and compact the concrete, and
don’t do it to much because it can lead into segregation. Do it every 30
cm of concrete thickness.
n. After the concrete poured all and stiff, scratch the top concrete with
manual tools.
o. In 12 hours laminate it with wet cloth / tarpaulin for curing.
p. Do the curing every day until 28 hours, it prefent concrete from
cracking.
q. After 7 days, the formwork can be opened
4) Longitudinal Joints
a. Longitudinal Joints is placed in the middle of the pavement.
b. Set out the longitudinal joint, D16 rebar per 750 mm, place it on 10 cm
top of lean concrete with rebal decking.
c. Paint the middle of longitudinal joint rebar with anticorrosion paint
around 10 cm.
d. Make sure the joint is sturdy and solid
Page 9 of 10
EPC PEMBANGUNAN SP ABG STAGE 1 – AKASIA BAGUS
PAVING PAVEMENT METHOD STATEMENT
e. After the concrete poured and become stiff, the gap between concrete
pavement in longitudinal join is filled by PVC filler and the top of filler
is sealed with Joint Sealant
8) Isolation Joints
Isolation Expansion Joints is placed in the intersection with drainage. And
after the concrete poured and become stiff, the gap between concrete
pavement with another pavement is filled by PVC filler and the top of filler
is sealed with Joint Sealant.
Page 10 of 10