Volume IV - Geotechnical Survey and Topography
Volume IV - Geotechnical Survey and Topography
1.0 INTRODUCTION......................................................................................... 1
• This test report relates only to the samples tested RP-009 Rev 05/ Mar 21
• This report shall not be reproduced (except in full) without written approval of the laboratory
TABLE OF CONTENTS (Cont’d….)
APPENDIX A:
▪ Site Plan Showing Borehole Locations
APPENDIX B:
▪ Key to Boreholes
▪ Borehole Logs
▪ Boreholes Correlation Chart
APPENDIX D:
▪ D-1 – General Notes & Guidelines
▪ D-2 – Standard Procedure for Site Investigation
APPENDIX E:
▪ E-1 – General Notes & Guidelines – Chemical Conditions &
Recommendations Related to Cement Type
▪ E-2 – Building Research Establishment Digest 363 (Extracts)
• This test report relates only to the samples tested RP-009 Rev 05/ Mar 21
• This report shall not be reproduced (except in full) without written approval of the laboratory
1.0 INTRODUCTION
This report presents the results of a geotechnical investigation and soil evaluation
carried out by Al Madeena Engineering Laboratory for: -
The work was carried out upon the request of HH Sheikh Ahmed Humaid Rashed
Al Noaimi.
The purpose of this investigation was: -
• To determine the soil and groundwater conditions at the investigated site
• To evaluate the suitability of the encountered soil to support the foundations
of the proposed project
• To make comments and lay recommendations related to the foundations to
be used in the project.
• Drilling Five (05) boreholes to a depth of fifteen (15) meters each located as
shown on the site plan in Appendix A.
• Performing the necessary field works and laboratory tests on the samples
obtained during the drilling works.
The SPT consist of driving a 50mm external diameter thick walled tube
(Split spoon sampler) into the bottom of the borehole using a 63.5 Kg
hammer falling freely through 760mm.
Initially the sampler is driven 150mm into the soil to be seated and to pass
through disturbed soil at the bottom of the borehole. The number of blows
required for driving the sampler a further 300mm is recorded and termed as
the “N” value. The results are shown on the attached borehole logs in
Appendix B.
The obtained split spoon samples from the above tests were properly
preserved, identified and sent to the laboratory for further testing.
Particle size distribution was carried out in accordance with B.S. 1377: 1990
Part 2: Method 9 “Determination of Particle Size Distribution”. Clause 9.2.
For this project, a total of (4) selected soil samples were mechanically
analysed by wet sieving for classification purposes.
BS 1377: Part 3: 2018 + A1:2021 Cl. 7.3 & 7.6 “Determination of the
Sulphate Content of soil and Groundwater.”
BS 1377: Part 3: 2018 + A1:2021 Cl. 9.2 “Determination of the Chloride
Content.”
BS 1377: Part 3: 2018 + A1:2021 Cl. 12.5 “Determination of the pH Value.”
For this project, (3) soil samples were tested and their chemical Analysis
Results are given in Appendix C. No tests were made on ground water
since it was not encountered till the end of the boring.
The geology of the United Arab Emirates and the Arabian Gulf area has been
substantially influenced by the deposition of marine sediments associated with
numerous sea level changes during relatively recent geological time. With the
exception of mountainous regions shared with Oman in the north-east, the country
is relatively low-lying with near-surface geology dominated by Quaternary to late
Pleistocene age, mobile Aeolian dune sands, and sabkha/evaporates deposits.
Observations concerning the ground water were made during and at completion of
the drilling operations. No ground water was established at any of the borehole
locations, thus, dewatering will not be required during excavation and
construction of the foundations.
The choice of particular type of foundation depends upon the character of the soil,
the presence of ground water at the site, the magnitude of the imposed loads, and
the project characteristics.
For this particular case, the following prevailing site conditions exist: -
• The proposed project is construction of (B+G+1) Villa.
• The topography of the site was generally level. Based on visual estimation,
the proposed construction area was of slightly uneven nature and its
average ground elevation is 10 cm to 50 cm below the adjacent asphalt
road level. At the time of investigation, no ground water was established
at any of the borehole locations.
• Based on the visual identification, SPT results and laboratory testing made
on selected representative samples from those obtained from the
boreholes, the generalized and prevailing descriptions of the soil strata
encountered from the ground level down to the end of the boreholes are as
follows: -
Based on the above discussions and from careful reading of the borehole
logs with other data, SHALLOW FOUNDATIONS is suitable for the project
subject to the following considerations and requirements.
Considering above, and before starting the construction of the foundations, the
following should be made for the preparation and improvement of the foundation
ground:-
Considering above, and before starting the construction of the foundations, the
following should be made for the preparation and improvement of the foundation
ground:-
▪ Key to Boreholes
▪ Borehole Logs
▪ Boreholes Correlation Chart
KEY TO BOREHOLES (BS 5930:2015)
SOIL TYPES
ROCK TYPES
SOILS
Non-Cohesive Soils Cohesive Soils
SPT N Value Relative Angle of Internal Consistency Undrained Shear Strength
(Blows / 300mm) Density Friction* (kN/m2)
0–4 Very Loose < 30o Very Soft < 20
4 – 10 Loose 30o- 35o Soft 20 – 40
10 – 30 Medium 35o- 40o Firm 40 – 75
Dense
30 – 50 Dense 40o- 45o Stiff 75 – 150
> 50 Very Dense > 45o Very Stiff 150 – 300
* After Meyerhof Hard > 300
ROCK
Rock Strength Classification
Light Cable Percussion Boring BS 5930: 2015 Sec.4, Cl.24.9
Unconfined Compressive Description
Rotary Core Drilling BS 5930: 2015 Sec.4, Cl.24.11
Strength ( MN/m2 ) Standard Penetration Test BS 1377: Part 9: 1990 Sec.
3.3; BS EN ISO 22476-3:2005
Extremely weak 0.6 – 1.0 Groundwater Level Measurement BS 5930: 2015 Sec. 8 CL.
26.4& 52.2; EN ISO 22475-1
Very weak 1 - 5.0
Weak 5 - 25
Medium Strong 25 to 50
Strong 50 to 100
Very Strong 100 to 250
Extremely strong >250
APPENDIX C
GIR24-11493
SITE PLAN SHOWING BOREHOLE LOCATIONS
Report No. : GIR24 – 11493
Consultant
M/S BOREHOLE LOG Borehole No. : BH01 Sheet (1/2)
Project : Proposed (B+G+1) Villa Borehole Diameter : 150 mm
: Plot No. 1363 – Humaideya (2) Drilling Date : 04/08/2024
Location
– Mid Sector -Ajman – UAE Boreholes Depth (m): 15.0 m
*Ground Level (m): ±0.0
: HH Sheikh Ahmed Humaid Method of Drilling : Percussion Coordinates: N : -2810202 E: -352288
Owner
Rashed Al Noaimi Operator : Amir Ground Water Level: Not Encountered
Standard Penetration Test (SPT)
Samples
No. of Blows
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
mm mm mm
0 ±0.0
SPT 1 0.5 – 0.95 3 4 6 10
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
Mm Mm Mm
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
mm mm mm
0 ±0.0
SPT 1 0.5 – 0.95 4 4 6 10
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
Mm Mm Mm
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
mm mm mm
0 ±0.0
SPT 1 0.5 – 0.95 2 4 4 8
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
Mm Mm Mm
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
mm mm mm
0 ±0.0
SPT 1 0.5 – 0.95 3 3 4 7
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
Mm Mm Mm
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
mm mm mm
0 ±0.0
SPT 1 0.5 – 0.95 2 4 4 8
Legend
Reduced
Depth Seating Test Drive TCR SCR RQD
(m) (%) (%) (%) Description of Strata Level
Type & Depth (m) N (m)
No From - To 150 150 150 Value
Mm Mm Mm
Plot No. 1363 – Humaideya (2) – Mid Sector - Test Date Completed 13/08/2024
Project Location
Ajman – UAE Sampling Date 04-08/08/2024
Customer Reference Nil Sampled By MEL REP.
Sample Description light brown Sand Sample Brought By MEL REP.
Sample Source Site Tested By MA
Sampling Method BS 5930: 2015
Sample Preparation Method for Sulphate Content BS 1377: Part 3: 2018 + A1:2021 Cl. 7.3.2
Sample Preparation Method for Chloride Content BS 1377: Part 3: 2018 + A1:2021 Cl. 9.2.3
Sample Preparation Method for pH Value BS 1377: Part 3: 2018 + A1:2021 Cl. 12.4
Test Method for Sulphate Content (Water Soluble) BS 1377: Part 3: 2018 + A1:2021 Cl. 7.3 & 7.6
Test Method for Chloride Content (Water Soluble) BS 1377: Part 3: 2018 + A1:2021 Cl. 9.2
Test Method for pH Value BS 1377: Part 3: 2018 + A1:2021 Cl. 12.5
RESULTS:
Method Variation:
Remarks : Water to Soil ratio is 2:1 for Water Soluble Sulphate and Chloride Content Analysis.
The following points must be taken into consideration as general notes and guidelines in
conjunction with the recommendations included in this report.
1. As mentioned in the report, the boreholes made were of 150 mm in diameter. The
information received from the limited number and the stipulated diameter of boreholes
may not represent the entire site and may not reveal all the weak layers or conditions
especially when they are localized. Hence, no responsibilities can be born for conditions
not revealed by boreholes or trial pits made on the site. In case of any such findings, we
shall be contacted immediately to arrange a site visit by our engineer to make an on site
study of such conditions after which recommendations if it is deemed necessary will be
revised.
2. There are many methods to calculate the allowable bearing pressure of the soil and
there are considerable variations in the values obtained by different methods and hence,
it is practically impossible to fix a single value for a particular site for a given breadth and
type of foundations even after considering the same magnitude for factor of safety. This
is because of the many uncertainties in determining the allowable bearing pressure
values. Most of uncertainty components are coming from the complex behavior of the
soil, limited investigation of the subsurface conditions, changing environmental
conditions in the site, etc. Based on our experience, we may be assigning different
values for factor of safety for different areas in UAE and this will be a minimum of 3.0 for
shallow foundations and 2.5 for piled foundations.
3. The ground water table reported is expected to vary subject to seasonal variations or any
dewatering process in the vicinity. Hence, it is advisable to install a standpipe
Piezometer and monitor the ground water table at regular intervals until it was
established that the water level in borehole had reached equilibrium. At the time of
construction, it shall be made sure that the excavation levels for foundation are at least
0.3 m above the ground water table so that compaction process at the excavated level
can be properly carried out to the required degree mentioned in our report. In case of
any difficulty in achieving proper compaction, a 250 mm layer thick granular fill material
shall be placed and compacted to the required degree of compaction.
4. Where the construction area levels are less than the proposed foundation level, filling
below the foundation level shall be carried out in layers not exceeding 250 mm and each
layer shall be compacted to at least 95% of the maximum dry density of the soil in case
of fine material or 98% in case of granular fill (road base). The compaction percentages
attained shall be confirmed by carrying out in-situ density tests for each compacted layer.
5. For excavation deeper than 2.0 m, suitable side protections have to be ensured so that
the excavation shall not cause a threat to the personnel working on the site or cause any
damage to nearby existing buildings or roads.
6. While carrying out dewatering, it shall be ensured that no excessive settlement is caused
to the nearby structures and the process shall be carried out in stages. Moreover,
suitable precautions have to be taken especially in areas with weak strata.
7. Where the foundations are required to be placed on the existing ground level, it is
advisable to remove at least the top 200 mm layer in case of sand stratum so that any
organic matter, contaminants or deleterious material on the surface be removed.
8. In case there is an existing structure which is waiting for demolition and the soil
investigation has to be carried out outside the existing structure, it is advisable to sink
one or two more boreholes after demolition to confirm the bearing pressure.
9. In case there is any clay strata above the groundwater table, care should be taken to
avoid any water from reaching this layer by providing enough drainage of the domestic
waste water and making the area immediately surrounding the building impermeable so
that no water from any source will reach the clay layer.
10. It is advisable to keep the foundations at least 1.0 m below the finished ground level so
that any future excavations for service lines may not undermine the foundations.
11. It is considered undesirable to place the foundations directly over amorphous gypsum
(with high content) layer, and hence, a minimum of 150 mm layer thick approved fill
material has to be placed and compacted to not less than 95% of the maximum dry
density of the fill material.
12. In case ground improvements are necessary to be carried out, techniques suitable for
any particular site shall be selected in consultation with geotechnical engineer.
13. In case of any hard strata like the sandstone, siltstone or any other rock types, use of
special excavators for excavations of such strata shall be considered.
14. The recommendations given in this report need not to be considered as final and
binding. These recommendations may be altered (where the soil parameters permit)
depending on the design requirements and by agreement with the geotechnical
engineer.
APPENDIX D-2
STANDARD PROCEDURE FOR SITE INVESTIGATION
The following notes outline the general procedures adopted in geotechnical site investigation
contracts and should be read in conjunction with the report. These procedures are generally
in accordance with British Standards BS 5930: 2015 code of site investigation and BS 1377:
1990, Method of test for soils for Civil Engineering Purposes.
Boring Technique
The standard method of boring in soil for site investigation is known as the “cable
percussion” method. It consists of using a shell in non-cohesive soil and a clay cutter in
cohesive soil both being wire cables operated. Chiseling breaks up very hard soil, boulders
or other hard obstructions and the fragments removed with the shell. Unless otherwise
stated, the “Percussion Technique” has been employed in sand while “Rotary Drilling” is
used in rocky layers. Rotary core drilling can be undertaken either in an existing borehole
that has been taken down to rock head or on virgin ground. It is essentially a rock drilling
process, but good cores can also be obtained of certain types of drift material such as hard
clay or boulder clay.
Routine Sampling
The standard penetration test count quoted on the borehole logs have been obtained using
SPT equipment conforming to both British and American Standards. A thick wall sample
tube, 50-mm external diameter, is driven into the soil by a hammer weighing 63.5 kg and
with a free fall drop of 760mm. The number gives a guide to consistency of the soil and also
used to estimate the bearing capacity of the soil.
Disturbed Samples
Disturbed samples are taken from the boring tools or from the standard penetration test
sample tube at suitable depths so that together with the undisturbed sample there is a
representative sample at the top of each change in stratum and there after at regular interval
down the borehole until the next stratum is encountered.
Groundwater Levels
The ground water levels entered on the boring logs are those recorded at the time of
investigation. It is to be noted that ground water level are subject to variation caused by
seasonal effects or changes in local drainage and or pumping conditions. Borehole water
levels are recorded together with the depth at which seepage of water or inflows can be
detected and the observances do not give an accurate indication of the actual ground water
condition. Standpipes are installed whenever an accurate record of the ground water level is
required.
APPENDIX E-1
NOTES & GUIDELINES
CHEMICAL CONDITIONS & RECOMMENDATIONS RELATED TO CEMENT TYPE
RECOMMENDED CEMENT TYPES
In practice, the use of proper cement type in the foundation should take into consideration
the sulphate and chloride contents encountered. However, one of the usual reasons for
using other than the Ordinary Portland Cement (OPC) is to reduce the effects of chemical
attack on the concrete.
Since the following concepts play a crucial role in cement reactions, it is felt necessary to
explain them with respect to CIRIA Special Publication 31 (CIRIA Guide to Concrete
Construction in the Gulf Region).
Tricalcium Aluminate (C3A) is the component of the cement, which reacts with
sulphates and expands. C3A (with high content) reacts with Sulphates and causes
undesirable expansion in concrete, while it reacts with Chloride to avoid the
expected chloride attack on reinforcement.
Thus, Sulphate-Resisting Portland Cement (SRC) contains less C3A than OPC to
reduce the effect of the reaction between C3A and Sulphate. However, C3A can also
combine with Chlorides, which might otherwise cause reinforcement to rust, and
current research grounds increasing concern that where sulphates and chlorides
occur together, the use of sulphate-resisting cement maybe inadvisable. Sulphate-
resisting cement do not make concrete immune from Sulphate attack, but only make
it better able to withstand moderate concentrations of sulphates.
Based on the above, CIRIA has concluded that the use of Ordinary Portland Cement
(OPC) is safer in case of:
Higher contents of both sulphates and chlorides are occurring together so as to
satisfy a balance in aforementioned behaviors.
Higher contents of chlorides and lower contents of sulphates are available.
Admixtures are preferable also to be used here to avoid or decrease the possibility of
chlorides (with high contents) attacking the reinforcement.
Otherwise, it is recommended that the use of Sulphate-Resisting Portland Cements
(SRC) is safer when:
Lower contents of both sulphates and chlorides are occurring together.
Higher contents of sulphate and lower contents of chloride are present.