Boiler Overhaul & Mod Check List COS

Uploaded by

Jhajjar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views

Boiler Overhaul & Mod Check List COS

Uploaded by

Jhajjar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

BoilerOverhaul/Modification Pre S/D Check List

SL
ACTIVITIES STATUS TARGET DATE REMARK
NO

1 CRANE

2 CIVIL GROUTING WORK

4 RH COIL SHIFTING

5 RH HEADER SHIFTING

6 CRISS CROSS LINK PIPE

7 LOOSE RH TUBES

8 BENT TUBES

NUMBERING & BUNCHING OF COILS / BEND


9
TUBES / LOOSE TUBES

10 CASSETTE BAFFLE SHIFTING

11 OTHER ATTACHMETS

12 SHOP WELD JOINT RADIOGRAPHY

13 RADIOGRAPHY DEFECT REPAIR

14 STEAM CLEANING OF COIL

15 SPONGE BALL TEST OF COIL & CAPPING

16 ACCOMMODATION FOR ALL MANPOWER

17 VEHICLE ARRANGEMENT

18 FOOD ARRANGMENT

19 ISSUE OF PPE & SAFETY TRANING


20 HEALTH CHECKUP OF OF WORKERS

21 SECURITY

22 FORM-V

23 LABOUR GATE PASS

24 CONTRACT AGREEMENT

25 ESI OF WORKMEN

26 T&P SHIFTING

27 LOAD TEST OF HOISTING EQUIPMENT

28 WELDING M/C TESTING

29 GRINDING M/C TESTING

30 LOAD TEST CERTIFICATE

31 ARGON TEST

32 WELDER TEST

33 Tube Test Piece

34 P22 PIPE WELDER TEST

35 PIPE TEST PIECE READINESS

36 ISSUE OF FLOOD LIGHTS

37 DA, O2 MOBILISATION

38 POWER SUPPLY ARRANGEMENT

39 STUDY OF DRAWINGS

40 OFFICE READINESS

41 TECHNICAL DISCUSSION with agency


42 TEMPORARY STORAGE SHED

43 BOILER LICENSE-ODISHA RENEWAL

44 AGENCY APPROVAL

45 WELDING SCHEDULE APPROVAL

46 PRE ASSY JOINTS OF RH LOOP

47 STRUCTURAL STEEL SHIFTING

48 WORK ORDER RELEASE

49 HANGER ITEM SHIFTING

50 UT AGENCY

51 SR AGENCY

52 RT SOURCE MOBILISATION

GANG FOR RH NRV OPENING AND BOX UP


53
WORK

54 ARRANGEMENT OF PORTABLE DUSTBIN

ARRANGEMENT OF VIBRATORS FOR


55
REFRACTORY BRAKING & SUB-AGENCY

MATERIAL CHECKING OF BEND TUBES &


56
OTHERS BY ALLOY ANALYSER
57 TOILET AT BOILER

58 DRINKING WATER

AVAILABILITY OF PENT HOUSE ASH


59
EVACUATION SYSTEM

ADDITIONAL PENT HOUSE COOLING FAN &


60 ALTERNATE POWER SUPPLY FOR FANS TO
ENSURE THEIR AVALABILITY DURING WASHING

DOVE TAIL ARRGT. FOR RH HEADER


61
ALIGNMENT
62 SAFETY & HYGINE LETTER TO AGENCY

PRE AWARD ACTIVITIES


BMD
MARKING OF 5X5X1.5M FOR CIVIL GROUTING
1
FOR CRANE
SITE SURVEY ALONG WITH CRANE SERVICE
2
ENGG AND RIGGER ON 28.04.2017
3 MOBILISATION LETTER TO AGENCY
4 15TH FLOOR HOIST READINESS
5 12TH FLOOR (55M) PLATEFORM EXTENSION

16TH FLOOR PLATEFORM FABRICATION ON


6
BOTH LHS & RHS

7 IDENTIFICATION OF MATERIAL STORAGE AREA

8 MATERIAL SEGREGATION
9 PIPE TEST PIECE AVAILABILITY - 15 Nos

10 TUBE(T22,T91 & SS) TEST PIECE READINESS

RH HYDRO TEST MATERIAL LIKE GASKET, O


11
RING PROCUREMENT

12 WELDING SUPPLY

13 LIGHTING SUPPLY

14 C&I CABLE REMOVAL

15 ELECTRICAL SYSTEMS REMOVAL

CONTACT DETAILS OF IBR WELDERS,


16 FITTERS,GRINDERS, FOREMAN GANG, HELPER
GANG, RIGGER GANG)

17 MTM PAD & CLAMP AVAILABILITY

18 STEAM CLEANING ARRANGEMENT

19 SPONGE BALL TEST ARRANGEMENT

STICKER FOR STEAM CLEANING, SPONGE BALL


20
TEST & SHOP WELD JOINT RADIOGRAPHY
VACUUM CLEANING ARRANGEMENT FOR PENT
21
HOUSE

22 TOILET,DARK ROOM,WELDER REST


ROOM,AGENCY O/H OFFICE
23
DRINKING WATER SUPPLY FACILITY AT BOILER
24
COVERING ALL SPARES WITH TARPAULINE
25 PROTOCOLS TO BE FINALISED

26 WELDING SCHEDULE APPROVAL FROM


DOFB,ODISHA
UPL PEOPLE TO BE TAKEN AND TRAINING TO BE
27
DONE
28 CHECKING OF NTPC WELDING M/C READINESS

29 CHECKING OF NTPC SR M/C READINESS


CHECKING OF NTPC CHAIN PULLEY BLOCK
30
READINESS
31 MULTIPLE COPIES OF DWG
32 MULTIPLE COPIES OF IBR CERTIFICATE

MATERIAL
1 54MM SIZE CLAMP PROCUREMENT
2 TARPAULIN PROCUREMENT
3 2 Nos TEMPERATURE GUN PROCUREMENT

4 LTSH STRAIGHT & BEND SHIELD PROCUREMENT


5 METTALIC END CAP PROCUREMENT

6 CERAMIC WOOL PROCUREMENT


POURABLE INSULATION PROCUREMENT - 50
7
MT
AQUALSOUL WATER SOLUBLE PURGE PAPER
8
PROCUREMENT -20 +60 ROLLS

9 HOIST ROPE PROCUREMENT

CORRUGATED SHEET FOR PENT HOUSE ROOF


10
PROCUREMENT
11 STRUCTURAL STEEL FROM SAIL
12 FILLER WIRES
13 ELECTRODES
14 INSULATION MATTRESS
15 ALUMINIUM CLADDING SHEET

EMD
ADDITIONAL HALOGEN LAMPS,LIGHTING &
1
WELDING SUPPLY POINTS (WITH ELCB)

2 ALTERNATE POWER SUPPLY FROM OTHER UNIT

ELECTRICAL HOIST SERVICING (BOILER REAR


3
SIDE 50 MTR ECONOMISER HOIST)

CABLE TRAY RE-ROUTING-SECOND PASS 50


4
MTR / 26 MTR

5 WINCH SUPPLY POINT -3 WINCHES/UNIT

NEW LIGHTING FOR PLATFORM (50MTR) TO


6
BE EXTENDED & PENTHOUSE ROOF

WELDING RB POINTS AT PENT HOUSE /


7
17TH FLOOR
8 SUPPLY POINTS FOR SR MACHINES-06 No.s

C&I
REMOVAL & RESTORATION OF
1
THERMOCOUPLES
REMOVAL OF LHS & RHS JB AND CABLE TRAY AT
2
16TH Floor

FQA
1 Evaluation of RT films at Boiler 12th Floor

2 Discussion on RT of Pipe Joints

OTHERS
DEPUTATION OF ADDITIONAL EXECUTIVES
1
FROM OTHER DEPT

2 ARRANGEMENT OF INSULATION PIT


*Check List complience responsibility is of area engineer.