C27-Emtp_simulation_of_synchronous_machine_from_standstill_to_synchronization
C27-Emtp_simulation_of_synchronous_machine_from_standstill_to_synchronization
+
islanded system and the simulation results are presented.
PLL
II. PUMPED STORAGE POWER PLANT AND
PROPOSED SIMULATION MODEL Grid Grid
+
frequency angle
Ire
The simplified single line diagram of the PSPP is given in
Fig. 1. At the pump storage station, there are four 250 MVA Current -
Controller +
synchronous machines operating at 18 kV and each generator
is connected to a 250 MVA, 18/400kV generator step-up Ire
transformer. Two SFCs fed from the auxiliary bus of the
Current
+
station provide the source of variable voltage-variable Limiter
frequency that supplies the synchronous machines during
starting process in pumping mode.
The SFC is basically composed of a rectifier bridge that
converts the input from AC to DC and an inverter bridge that
Control
The inverter is configured as a current source inverter [5]. PLL
+
A. Static Frequency Convertor (SFC) Control Inverter
Controller
The inverter is realized with gate turn-off controlled
+
semiconductors (GTO), which can be forced to stop Rotor Position
conduction from the control circuit. The control strategy of SM
the inverter for synchronous machine starting is divided in
-
SM frequency
+
two stages. The first stage requires forced commutation until
Activated Activated Frequency
10% of the machine rated speed, the second stage uses natural Excitation Voltage control when
System when f > 47 Hz Controller
commutation supported by the voltage induced in the machine f > 47 Hz
windings.
SM
-
voltage
-
are illustrated in Fig. 2 and Fig. 3 respectively (see [5] for
+
Grid Grid Activated
more details, see also [6]). The control algorithm of the SFC voltage frequency
when Angle
is based on the rotor position, speed and terminal voltage. The Δf < 1Hz Controller
SM angle
Δθ < 45°
inverter of the SFC is fired according to the rotor position of
Grid angle -+
the machine in order to follow the speed of the motor and the
rectifier controls the magnitude of the current injected into the Fig. 2. Circuit layout for SFC fed synchronous motor drive
machine. The rectifier control is composed of two main Forced Commutation Stage
control closed loops: an internal loop and an external loop. The generated voltage by the machine rotating at low
The internal loop is the current controller and it calculates the speeds is not sufficient to force the commutation of the
thyristor firing angle according to the reference and actual thyristors in the inverter and hence, forced commutation is
value of current. The external loop determines the torque required. However, during the forced commutation stage,
control strategy by generating the current reference. It is when GTOs are forced to turn off, the overvoltage generated
composed of speed, frequency and angle controllers. by the current source inductor at the DC interface might be
very high and intolerable for the connected equipment.
High Voltage Substation
Therefore, the forced commutation stage includes a DC
Step-up current cancellation mechanism, which is simply changing the
Transformer operation mode of the rectifier to inverter. The cancellation of
the current in the DC interface allows the commutation of the
SFC GTOs in the inverter and prevents the excessive overvoltage
generated by the current source inductor at the DC interface.
Natural Commutation Stage
Generator/ This stage uses natural commutation supported by the
Motor voltage induced in the machine windings. The speed
Fig. 1. Simplified one-line diagram of Pumped Storage Station controller provides acceleration of the machine up to 47 Hz
Authorized licensed use limited to: ULAKBIM UASL - MIDDLE EAST TECHNICAL UNIVERSITY. Downloaded on January 12,2025 at 17:43:50 UTC from IEEE Xplore. Restrictions apply.
3
with constant torque by keeping the DC current constant and frequency values which are different from the generator
hence the corresponding AC currents of the machine constant. electrical speed during the forced commutation period (f <
As the machine speed exceeds 47 Hz, the frequency controller 5 Hz), due to the highly distorted voltage waveform at the
is activated to bring the machine speed within the frequency measuring point. It can be seen from Fig. 5, that the frequency
margin needed for synchronization (fmach – fsys = +1Hz). meter’s accuracy range is above 6.4 Hz. The frequency
Following the frequency controller, the angle controller is controller of the SFC utilizes this frequency meter’s output
activated to bring the angle difference between the voltages of values as the frequency exceeds 47 Hz.
the system and the machine terminal within the margin As shown in Fig. 6, with the proposed controller
required for synchronization. parameters, the rotor speed is expected to enter into the
synchronization margin at about 111 s. Following frequency
controller, angle controller is initiated and the necessary
condition for synchronization is expected to take place within
a few seconds, as illustrated in Fig. 7.
0.94
(47 Hz)
+
1
+ + PI Ire / Te
Hs+D
-
machine
Activated when frequency
f > 0.95pu
Kf
+
+
+
+
Activated when system
Δf < 0.02pu frequency
Ka
Δθ < 45°
+ + θ/f
-
machine
frequency
θ/f
angle/frequency
1
Margin for
0.8
Frequency (pu)
synchronization
0.6
measured
Fig. 3. Control algorithm of the system 0.4 simulated
The voltage controller is activated with the frequency
controller i.e. when the machine speed exceeds 47 Hz. This 0.2
controller brings the machine terminal voltage magnitude
0
within the margin required for synchronization. 0 60 20 80 40 100 120
Time (s)
The manufacturer data provided in [5] does not include the
Fig. 5. Frequency measurement and simulation
parameters of the controllers. Therefore, the simplified model
illustrated in Fig. 4 is simulated in Simulink and the 1.03
parameters for speed, frequency and angle controllers are 1.02
determined by a trial-and-error method. The Simulink measured
Frequency (pu)
1.01
simulation results of the system with the parameters utilized
in EMTP-RV simulations are illustrated in Fig. 5 to Fig. 7. 1
simulated
The provided field measurement for frequency was
0.99
obtained using the frequency meter of the SFC control
system. This frequency meter takes the secondary side voltage 0.98
of the voltage transformer which is connected to the generator 0.97
terminal as input, and calculates frequency from the number 110 116 112
118 114
120 122 124
Time (s)
of zero crossing points of the input voltage waveform. Fig. 6. Frequency measurement and simulation in the synchronization margin
Although this frequency meter has a forth order low pass
input filter with 100 Hz cut-off frequency, it measures
Authorized licensed use limited to: ULAKBIM UASL - MIDDLE EAST TECHNICAL UNIVERSITY. Downloaded on January 12,2025 at 17:43:50 UTC from IEEE Xplore. Restrictions apply.
4
0.95 synchronization
at 0 s, the SFC is activated at 4.1 s and the total simulation
0.9 frequency
terminal time is 125 s. Simulation results and measured values are
voltage compared in the following figures.
0.85
The measured and simulated frequency plots are presented
0.8 in Fig. 10 and zoomed on in Fig. 11. They demonstrate that
95 105 100 110 115 the proposed controller model and parameters for the SFC
Time (s)
Fig. 9. Measured values: frequency, field excitation current and machine representation can be considered to be acceptable to represent
terminal voltage the behavior of the actual controller. The small difference
between simulated and measured frequencies in the 6.4 Hz -
C. New SM module in EMTP-RV
47 Hz frequency range is mainly due to the shaft model of the
In EMTP-RV, the synchronous machine is represented
Authorized licensed use limited to: ULAKBIM UASL - MIDDLE EAST TECHNICAL UNIVERSITY. Downloaded on January 12,2025 at 17:43:50 UTC from IEEE Xplore. Restrictions apply.
5
turbine. More accurate simulations can be obtained by using affect the terminal voltage of the machine. The measured and
more accurate values of the inertia and speed damping simulated machine stator current plots are given in Fig. 17.
constants of the turbine. However, the difference between the The synchronization region is shown in Fig. 18. The
measured and simulated values becomes more apparent simulation of Case-2 produces more accurate results due to
following the operation of frequency and angle controllers more accurate representation of the effect of the voltage
(starting at 47 Hz), which is expected according to the results controller.
obtained during the parameter tuning study performed with 1250
40 1.5
measured
case-2 case-1
1 case-2
20
0.5
0
0 20 60 40 80 100 120 0
60 800 20 40 100 120
Time (s)
Time (s)
Fig. 10. Measured and simulated frequencies Fig. 13. Machine terminal rms line-to-line voltage
51
case-2 measured x 10
4
1.8
rms line-to-line voltage (V)
50 case-1
Frequency (Hz)
1.6
49 measured
synchronization
1.4
48 instants
synchronization instants case-2
case-1
1.2
47 100 110 80120 90
105 110 115 120 125 Time (s)
Time (s)
Fig. 14. Machine terminal rms line-to-line voltage, zoomed version of Fig. 13
Fig. 11. Measured and simulated frequencies, zoomed version of Fig. 10
Authorized licensed use limited to: ULAKBIM UASL - MIDDLE EAST TECHNICAL UNIVERSITY. Downloaded on January 12,2025 at 17:43:50 UTC from IEEE Xplore. Restrictions apply.
6
5
The units having ability to start quickly might be put in
synchronization service as a corrective action following an extreme
instants contingency in order to increase the security margin of the
0
Active Power (MW)
Authorized licensed use limited to: ULAKBIM UASL - MIDDLE EAST TECHNICAL UNIVERSITY. Downloaded on January 12,2025 at 17:43:50 UTC from IEEE Xplore. Restrictions apply.
7
C. Simulation Results operating conditions of the other units come closer to their
Following the busbar fault, the machines remain in operating points before islanding i.e. scheduled power.
synchronism. However, as seen from Table I, there is 82.8 However, the scheduled power of the second unit at
MW power injection loss due to system separation and the MURATLI is higher than the primary reserve on the other
primary reserve of the generating units in the island is 47 units. Therefore, the turbine speed at the new equilibrium
MW. Therefore the deceleration of the machine rotors point is slightly higher than 1 pu. As the system has reached
continue until the operation of the UFR. By the operation of the new equilibrium point, the tripped load at CARSAMBA
the UFR at 49 Hz, a 20 MW load at IYIDERE and a 30 MW substation is re-energized at 300 s. At the new equilibrium
load at CARSAMBA are tripped. As seen from Fig. 20, the point, the generation of each unit is very close to the
decrease in turbine speed is limited to 0.963 pu and the scheduled generation and hence, the turbine speeds are very
generation load balance is maintained when the turbine speed close to 1 pu.
TABLE I
is about 0.995 pu.
POWER INJECTIONS, TOTAL LOAD AND NETWORK LOSSES
P Q Installed
BORCKA 400 kV
SM
SM
BORCKA
2
1
1
SM
PI
2
MURATLI
PI
+
HOPA
PI
+
+
PI
PI
+
RIZE
LF
PI
IYIDERE
scheduled values.
LF
PI
PI
PI
+
1.02
TIREBOLU 400 kV
+
TRABZON
ARSIN
re-energizing
1.01 30 MW load
LF
LF
SM
PI
PI
1
+
DOGANKENT HPP
0.99
TIREBOLU-1
1
1
MURATLI
2
LF
PI
Unit-1 instant
+
0.97 MURATLI
PI
PI
PI
HPP
+
LF
1 2
PI
0.96 Unit-2
PI
PI
SM
+
+
+
EQUIVALENT
KURTUN HPP
PI
NETWORK
+
0.95
TORUL HPP
GIRESUN
2 1
400 kV
time (s)
LF
PI
+
+
1
ORDU
BORCKA HPP
CARSAMBA 400 kV
LF
PI
PI
+
FATSA
Unit-1
Active Power (pu)
LF
1
LF
PI
PI
0.6
+
+
2
LF
re-energization of
CARSAMBA 154 kV 30 MW load
0.4 synchronization
Fig. 19. Single line EMTP-RV diagram of the islanded system instant
MURATLI
The second unit at MURATLI is started at 60 s of HPP
0.2
simulation time with a speed set value corresponding to 50 Unit-2
MW generation at 1 pu speed, and its synchronization takes
place near 145 s. The slow acceleration of the turbine is due 0
0 50 100 150 200 250 300 350 400
to the modeling of the existing mechanical gate limiter which time (s)
is active before synchronization. As the loading of the unit Fig. 21. Active power generated by BORCKA and MURATLI HPP
increases, the speed of the turbine increase up to 1 pu and the
Authorized licensed use limited to: ULAKBIM UASL - MIDDLE EAST TECHNICAL UNIVERSITY. Downloaded on January 12,2025 at 17:43:50 UTC from IEEE Xplore. Restrictions apply.
8
It is important to emphasize that the computer time for Sébastien Dennetière graduated from École Supérieure d’Electricité, Supélec,
France, in 2002. He received the M.A.Sc. degree from École Polytechnique de
400 s of simulation is close to 380 s with a time-step of Montréal, Montréal, QC, Canada, in 2003. From 2002 to 2004, he was with
250 μs . The computer is a 2 GHz dual core with 4 GB of IREQ (Hydro-Québec) working on research and development activities related
RAM memory. It is a demonstration that such studies can to the simulation and analysis of electromagnetic transients. In 2004, he joined
the research center of Électricité de France, Paris, where his interests are
have acceptable performance in an EMTP-type software. currently in the field of insulation coordination and power system simulations.
V. CONCLUSIONS
This paper presented the modeling and simulation studies
of the startup of a 250 MVA pumped storage unit in pumping
mode and the startup of a 65 MVA hydraulic unit as a
correction action following an uncontrolled islanding of an
area due to an extreme contingency. The simulation results
and field measurements regarding electrical startup of the
pumped storage unit demonstrate the capability to simulate
synchronous machine behavior from standstill to rated speed
conditions. Moreover, the proposed controller model and
parameters can be considered to be acceptable to represent
the behavior of the actual controller. The proposed modeling
method can be used to investigate the effects of disturbances
in the voltage waveforms at the machine terminal and other
connected equipments due to the operation of the SFC. In
addition, this paper demonstrated that it is possible to apply
EMTP-type methods for the simulation of the startup of
hydraulic units during system restoration plan preparation.
The advantages are in unification of environment and
increased precision.
REFERENCES
[1] G. Magsaysay et al., “Use of a Static Frequency Converter for Rapid Load
Response in Pumped-Storage Plants,” IEEE Trans. on Energy Conversion,
Vol. 10, No. 4, December 1995.
[2] J. Mahseredjian, S. Dennetière, L. Dubé, B. Khodabakhchian and L.
Gérin-Lajoie: “On a new approach for the simulation of transients in
power systems”. Electric Power Systems Research, Volume 77, Issue 11,
September 2007, pp. 1514-1520.
[3] http://www.mathworks.com/
[4] B. Kirby and E. Hirst: “Maintaining system blackstart in competitive bulk-
power markets”, avaible online: http://www.ornl.gov/
[5] L. Pierrat and J. Courault, Système Électronique de Lancement
D’alternateurs Hydrauliques de Pompage, Électricité de France, 1984
[6] S. P. Rosado “Analysis of Electric Disturbances from the Static Frequency
Converter of a Pumped Storage Station” M.Sc. thesis, Virginia Polytechnic
Institute and State University, Blacksburg, Virginia, 2001.
[7] J. Mahseredjian, EMTP-RV documentation, 2007.
BIOGRAPHIES
Ulas Karaagac received the M.S. and B.S. degrees from Middle East Technical
University (METU), Ankara, Turkey, in 1999 and 2002, respectively, both in
electrical and electronic engineering. Since 2007 he has been pursuing the Ph.D.
degree in electrical engineering from École Polytechnique de Montréal,
Montréal, QC, Canada. He worked as an R&D power engineer at Information
Technology and Electronics Research Institute (BILTEN) of the Scientific and
Technical Research Council of Turkey (TUBITAK), from 1999 to 2007. His
research areas include modeling and simulation of large scale power systems.
Jean Mahseredjian received the M.A.Sc. and Ph.D. degrees from the École
Polytechnique de Montréal, Montréal, QC, Canada, in 1985 and 1991,
respectively. From 1987 to 2004, he was with IREQ (Hydro-Québec) working
on research and development activities related to the simulation and analysis of
electromagnetic transients. In December 2004, he joined the Faculty of Electrical
Engineering at École Polytechnique de Montréal. He is the creator and main
developer of EMTP-RV.
Authorized licensed use limited to: ULAKBIM UASL - MIDDLE EAST TECHNICAL UNIVERSITY. Downloaded on January 12,2025 at 17:43:50 UTC from IEEE Xplore. Restrictions apply.