R03 C10C01 MHD Itp Ci 0009 C0

Uploaded by

Taiwo Oshin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Document Transmittal Form

RSG-DC-FRM-0001

General Information

Destination: RSG

To: Red Sea Global Transmittal No.:

Name: Shady Eissa Date: 06-Nov-2024

From: Al Masr Al Hadeeth Project/Department: Canteen CVO – R03-C10C01

R03-C10C01-MHD-ITP-
Address & Tel. No.: NA Aconex Ref No.:
CI-0009

Email: NA

The following is being transmitted:

☐ Drawings ☐ Specifications ☐ Samples ☐ Copy of Letter

☐ Plans ☐ Shop Drawings

X
☐ Others ( ITP )

Copies Document No. Description

1 R03-C10C01-MHD-ITP-CI-0009 R03-C10C01 – Inspection and Test Plan for Precast Element Installation

Transmitted via
☐ Hand Delivery ☒ Registered Mail (Aconex) ☐ Courier
Status
☒ For Accepted ☐ For Information ☐ For Acknowledgment
☐ For Your Use ☐ Accepted as Submitted ☐ Returned Corrected Prints
☐ For Review and Comment ☐ Accepted as Noted ☐ Returned for Corrections
☐ As Requested ☐ Resubmit Copies for Accepted ☐ Others (Please specify)

Remarks

Acknowledgement

Nasser Kamal 06-Nov-24


Name Signature Date

RSG-DC-FRM-0001
Rev. 02, 24 Jul 2024 Page 1 of 1
Inspection Test Plan
RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth

Reference/ Responsibility
Item No Task/Activity Controlling Frequency Record Remarks
Document Subcontractor Contractor Employer

1.0 Document Review

Project
Specification
Section 03 4100
Before QAQC Checklist
Precast
1.1 Verify Approval of Drawings. commencement of Approved Shop R R
Structural Concrete
• Employers
Activities drawing.
R/H R/H
Requirements
• IFC Drawings

Project
Specification
Section 03 4100 R/H R/H
Before
Precast Approved Material
1.2 Verify Approval of Materials commencement of R R
Structural Concrete Submittal
Activities
• Employers
Requirements
• IFC Drawings

Project
Specification
Section 03 4100
Before R/H R/H
Precast Approved Method
1.3 Approved Method Statement. commencement of R R
Structural Concrete statement
Activities
• Employers
Requirements
• IFC Drawings
Lift analysis calculation approval?
Approved Job Before
Verify that Risk assessment is in place
1.4 Safety Analysis/ commencement of Risk Assessment R R
and operators are wearing proper PPE.
Approved HSE Plan Activities

RSG-CN-TMP-0013
Rev. 00, 05 May 2024 1 of 5
Inspection Test Plan
Contractor Logo

RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth

Project
Specification Valid
Section 03 4100 Permits/Licen
Before
Precast ses from local
1.5 Permits and Licenses commencement of R R
Structural Concrete regulations
Activities
• Employers and other
Requirements Stakeholders
• IFC Drawings

1.6

2.0 Material Receiving

Project
Specification
Section 03 4100
Before
Precast MAR (Approved
2.1 Material Submittal commencement of H H
Structural Concrete Material Submittal)
Activities
• Employers R/H R/H
Requirements
• IFC Drawings

A. Store precast concrete units at manufacturer's plant or project


site to prevent cracking,
distortion, staining, or other physical damage, and so that markings
are visible. Do not use
Project
upper member of stacked tier as storage area for shorter member or
Specification
heavy equipment. Deliver
Section 03 4100
Precast Before
QAQC Checklist
R/H units to project site in such quantities and at such times to assure
Delivery Note/ Test continuity of installation.
2.2 Material delivery, Storage and Handling Structural Concrete commencement of H H
Reports/Approved B. Support units during shipment on nonstaining shock-absorbing
• Approved Method Activities
material Submittal material in same position as
Statement
during storage.
• Approved
C. Handle and transport units in a manner that avoids excessive
Material Submittal
stresses that cause cracking or
damage.
D. Lift and support units only at designated points indicated on Shop
Drawings.

Project
Specification
Section 03 4100
Precast R/H R/H
Prior to Installation MIR (Material
2.3 Material Inspection Structural Concrete H H
of Precast elements Inspection request)
• Approved Method
Statement
• Approved
Material Submittal

RSG-CN-TMP-0013
Rev. 00, 05 May 2024 2 of 5
Inspection Test Plan
Contractor Logo

RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth
3.0 Work Execution

Project
Specification
Section 03 4100
QAQC Checklist
Precast
Survey Setting Out for Precast Panels (Coordinates) During Installation Work inspection
3.1 Structural Concrete H H
(Verticality & Levels, Alignment and vertical steel (B/W PVL Loops) and release for grout Process request
• Approved Method
Survey reports R/H
Statement
• Approved
Material Submittal

Project
Specification
Section 03 4100
R/H
Precast
R/H
During Installation WIR & inspection
3.2 Surface Preparation Structural Concrete H H
Process checklist
• Approved Method
Statement
• Approved
Material Submittal

Provide temporary shoring and bracing as required to ensure stability


during erection. The erector shall brace unsymmetrical sections during
Project
erection and pouring of topping slabs to prevent rotation and instability
Specification
regardless of whether it is specified on the erection drawings. The
Section 03 4100
responsibility for bracing such members shall rest solely with
Precast
During Installation WIR & inspection the Erector.
3.3 Erection of Precast Elements Structural Concrete H S
Process checklist Properly align, plumb and level precast units. Level out variations between
• Approved Method
R/H adjacent members by shimming, loading or any other feasible method
Statement
recommended by the manufacturer and acceptable to the Architect and
• Approved
Engineer.
Material Submittal
Provide accurate placement and alignment of anchor bolts, plates or
dowels in supporting structural elements.

Project Inspection Field Inspection: Acceptance of erected precast concrete will be made by
Specification Checklist the Architect and Engineer for general conformance with the plans and
Section 03 4100 Approved Work R/H R/H specifications.
Precast Inspection Request B. Defective Work: Precast concrete units which do not conform to
During Installation
3.3 Inspection of Precast Vertical Elements Structural Concrete Approved Survey H H specified requirements, including strength, tolerances, and finishes, shall
Process
• Approved Method report be repaired or replaced with precast concrete units that meet
Statement Erection Tolerances requirements of this section as directed by the Architect and Engineer. The
• Approved shall conform to Contractor shall also be responsible for the cost to any other work affected
Material Submittal PCI MNL-135 by or resulting from corrections to precast concrete work

RSG-CN-TMP-0013
Rev. 00, 05 May 2024 3 of 5
Inspection Test Plan
Contractor Logo

RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth

Project
Specification
Section 03 4100
Precast Inspection
During Installation
3.4 Inspection of Grouting Connections and Precast Accessories Structural Concrete Checklist H H
Process
• Approved Method MEP clearance.
R/H R/H
Statement
• Approved
Material Submittal

Project
Specification
Section 03 4100 R/H
Precast R/H
Inspection of Installed HCS During Installation WIR & inspection
3.5 Structural Concrete H H
Slabs Process checklist
• Approved Method
Statement
• Approved
Material Submittal

Reinforcement installation for Project


Specification
the topping slab missing Section 03 4100
Precast R/H R/H
During Installation WIR & inspection
3.6 Casting of Structural toppings for Hollow core slabs. Structural Concrete H H
Process checklist
• Approved Method
Statement
• Approved
Material Submittal

Project For every Inspection


3.7 Curing H S
Specification area on Checklist
5.0 Activity Close-out

Project
Specification
Section 03 4100
A. Clean surfaces after installation and completion of joint treatment
Precast For every
Inspection to remove weld marks, other markings, dirt, and stains.
5.1 CLEANING Structural Concrete area on S S
Checklist B. Clean mortar, plaster, fireproofing, and other deleterious material
• Approved Method completion
from concrete surfaces and adjacent materials immediately.
Statement
• Approved
Material Submittal

RSG-CN-TMP-0013
Rev. 00, 05 May 2024 4 of 5
Inspection Test Plan
Contractor Logo

RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth

Project
Specification
Section 03 4100 R/H R/H
Precast For every
Approved WIR
5.2 Final Inspection of Installed Precast Elements Structural Concrete area on H H
Checklist
• Approved Method completion
Statement
• Approved
Material Submittal

Project For every As-Built Survey


5.3 As-Built Survey H H
Specification area on report

General Notes

1 Employer: An authorized employee who represents RSG and is empowered to take action in the activity. This role can be filled by a Quality Supervisor, Quality Manager, Technical Engineer, or Construction Engineer as defined in the Method Statement and PQP.

2 Review Point: Employer shall review the task results before moving on.

3 Surveillance Point: Monitoring work in progress, which does not require a written notification. A surveillance report may be issued to document the activity.

4 Witness Point: The Employer shall be notified in advance, in writing, about the timing of inspections or tests. However, if there is no written approval or presence from the Employer, the inspection or test shall proceed as scheduled.

5 Hold Point: The Employer shall be notified in advance, in writing, about the timing of inspections or tests. Subsequent activities should not be carried out without written approval from the Employer.

Legend
H Hold Point W Witness Point S Surveillance Point R Review Point PQP Project Quality Plan ICA Independent Commissioning Agent (Employer assigned entity)

RSG-CN-TMP-0013
Rev. 00, 05 May 2024 5 of 5
Main Contractor Builders Works

Precast Element Installation Inspection Check Sheet (ICS)


Drawing / Specifications: WIR Ref

Location: Date:

MHD RSG
Item Process Elements Requiring Control Main Contractor Representative Remarks

1 Check if Shop Drawings are Approved

2 Check if Method Statement is Approved

3 Check if Material Submittal is Approved

4. Wall Erection

a. Check for the location and placement of wall panels

b. Check for adjusting level of nut to support column

c. Check if the elements are correctly positioned and aligned in its location

d. Check if all connection loops bolts are tightened for stability of elements

e. Check if elements are grouted prior to roof elements erection

5. Beam Erection

a. Check if bearing pads are located as shown on the drawings

b. Check if the elements are correctly positioned and aligned in its location

c. Check if elements are grouted prior to roof elements erection

6. HCS- SS Slab Erection

a. Check if the elements are correctly positioned and aligned in its location

b. Check if bearing pads are located as shown on the drawings

c. Check if elements have at least minimum bearing as shown on the drawings

7. Grouting

a. Check if elements are grouted with approved materials at all connections


Main Contractor Builders Works

8. Final surface check

9. Check for any defects

MHD QA/QC Engineer Name/Signature: Date:

ALL OF THE ABOVE HAVE BEEN COMPLIED WITH FULLY


Client Engineer: Name/Signature: Date:

Comments:

✓: Accepted, X: Not accepted, NA- Not Applicable