R03 C10C01 MHD Itp Ci 0009 C0
R03 C10C01 MHD Itp Ci 0009 C0
RSG-DC-FRM-0001
General Information
Destination: RSG
R03-C10C01-MHD-ITP-
Address & Tel. No.: NA Aconex Ref No.:
CI-0009
Email: NA
X
☐ Others ( ITP )
1 R03-C10C01-MHD-ITP-CI-0009 R03-C10C01 – Inspection and Test Plan for Precast Element Installation
Transmitted via
☐ Hand Delivery ☒ Registered Mail (Aconex) ☐ Courier
Status
☒ For Accepted ☐ For Information ☐ For Acknowledgment
☐ For Your Use ☐ Accepted as Submitted ☐ Returned Corrected Prints
☐ For Review and Comment ☐ Accepted as Noted ☐ Returned for Corrections
☐ As Requested ☐ Resubmit Copies for Accepted ☐ Others (Please specify)
Remarks
Acknowledgement
RSG-DC-FRM-0001
Rev. 02, 24 Jul 2024 Page 1 of 1
Inspection Test Plan
RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth
Reference/ Responsibility
Item No Task/Activity Controlling Frequency Record Remarks
Document Subcontractor Contractor Employer
Project
Specification
Section 03 4100
Before QAQC Checklist
Precast
1.1 Verify Approval of Drawings. commencement of Approved Shop R R
Structural Concrete
• Employers
Activities drawing.
R/H R/H
Requirements
• IFC Drawings
Project
Specification
Section 03 4100 R/H R/H
Before
Precast Approved Material
1.2 Verify Approval of Materials commencement of R R
Structural Concrete Submittal
Activities
• Employers
Requirements
• IFC Drawings
Project
Specification
Section 03 4100
Before R/H R/H
Precast Approved Method
1.3 Approved Method Statement. commencement of R R
Structural Concrete statement
Activities
• Employers
Requirements
• IFC Drawings
Lift analysis calculation approval?
Approved Job Before
Verify that Risk assessment is in place
1.4 Safety Analysis/ commencement of Risk Assessment R R
and operators are wearing proper PPE.
Approved HSE Plan Activities
RSG-CN-TMP-0013
Rev. 00, 05 May 2024 1 of 5
Inspection Test Plan
Contractor Logo
RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth
Project
Specification Valid
Section 03 4100 Permits/Licen
Before
Precast ses from local
1.5 Permits and Licenses commencement of R R
Structural Concrete regulations
Activities
• Employers and other
Requirements Stakeholders
• IFC Drawings
1.6
Project
Specification
Section 03 4100
Before
Precast MAR (Approved
2.1 Material Submittal commencement of H H
Structural Concrete Material Submittal)
Activities
• Employers R/H R/H
Requirements
• IFC Drawings
Project
Specification
Section 03 4100
Precast R/H R/H
Prior to Installation MIR (Material
2.3 Material Inspection Structural Concrete H H
of Precast elements Inspection request)
• Approved Method
Statement
• Approved
Material Submittal
RSG-CN-TMP-0013
Rev. 00, 05 May 2024 2 of 5
Inspection Test Plan
Contractor Logo
RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth
3.0 Work Execution
Project
Specification
Section 03 4100
QAQC Checklist
Precast
Survey Setting Out for Precast Panels (Coordinates) During Installation Work inspection
3.1 Structural Concrete H H
(Verticality & Levels, Alignment and vertical steel (B/W PVL Loops) and release for grout Process request
• Approved Method
Survey reports R/H
Statement
• Approved
Material Submittal
Project
Specification
Section 03 4100
R/H
Precast
R/H
During Installation WIR & inspection
3.2 Surface Preparation Structural Concrete H H
Process checklist
• Approved Method
Statement
• Approved
Material Submittal
Project Inspection Field Inspection: Acceptance of erected precast concrete will be made by
Specification Checklist the Architect and Engineer for general conformance with the plans and
Section 03 4100 Approved Work R/H R/H specifications.
Precast Inspection Request B. Defective Work: Precast concrete units which do not conform to
During Installation
3.3 Inspection of Precast Vertical Elements Structural Concrete Approved Survey H H specified requirements, including strength, tolerances, and finishes, shall
Process
• Approved Method report be repaired or replaced with precast concrete units that meet
Statement Erection Tolerances requirements of this section as directed by the Architect and Engineer. The
• Approved shall conform to Contractor shall also be responsible for the cost to any other work affected
Material Submittal PCI MNL-135 by or resulting from corrections to precast concrete work
RSG-CN-TMP-0013
Rev. 00, 05 May 2024 3 of 5
Inspection Test Plan
Contractor Logo
RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth
Project
Specification
Section 03 4100
Precast Inspection
During Installation
3.4 Inspection of Grouting Connections and Precast Accessories Structural Concrete Checklist H H
Process
• Approved Method MEP clearance.
R/H R/H
Statement
• Approved
Material Submittal
Project
Specification
Section 03 4100 R/H
Precast R/H
Inspection of Installed HCS During Installation WIR & inspection
3.5 Structural Concrete H H
Slabs Process checklist
• Approved Method
Statement
• Approved
Material Submittal
Project
Specification
Section 03 4100
A. Clean surfaces after installation and completion of joint treatment
Precast For every
Inspection to remove weld marks, other markings, dirt, and stains.
5.1 CLEANING Structural Concrete area on S S
Checklist B. Clean mortar, plaster, fireproofing, and other deleterious material
• Approved Method completion
from concrete surfaces and adjacent materials immediately.
Statement
• Approved
Material Submittal
RSG-CN-TMP-0013
Rev. 00, 05 May 2024 4 of 5
Inspection Test Plan
Contractor Logo
RSG-CN-TMP-0013
ITP No/ Issue Date Approved on Discipline
Precast Element Installation
6/11/2024 Civil / Architecture
Project Name Turtle Bay Canteen Contract # Contractor Sub-Contractor
Package Name Main Contractor Builders Works R03-C10C01-8100 Al Masar Al Hadeeth
Project
Specification
Section 03 4100 R/H R/H
Precast For every
Approved WIR
5.2 Final Inspection of Installed Precast Elements Structural Concrete area on H H
Checklist
• Approved Method completion
Statement
• Approved
Material Submittal
General Notes
1 Employer: An authorized employee who represents RSG and is empowered to take action in the activity. This role can be filled by a Quality Supervisor, Quality Manager, Technical Engineer, or Construction Engineer as defined in the Method Statement and PQP.
2 Review Point: Employer shall review the task results before moving on.
3 Surveillance Point: Monitoring work in progress, which does not require a written notification. A surveillance report may be issued to document the activity.
4 Witness Point: The Employer shall be notified in advance, in writing, about the timing of inspections or tests. However, if there is no written approval or presence from the Employer, the inspection or test shall proceed as scheduled.
5 Hold Point: The Employer shall be notified in advance, in writing, about the timing of inspections or tests. Subsequent activities should not be carried out without written approval from the Employer.
Legend
H Hold Point W Witness Point S Surveillance Point R Review Point PQP Project Quality Plan ICA Independent Commissioning Agent (Employer assigned entity)
RSG-CN-TMP-0013
Rev. 00, 05 May 2024 5 of 5
Main Contractor Builders Works
Location: Date:
MHD RSG
Item Process Elements Requiring Control Main Contractor Representative Remarks
4. Wall Erection
c. Check if the elements are correctly positioned and aligned in its location
d. Check if all connection loops bolts are tightened for stability of elements
5. Beam Erection
b. Check if the elements are correctly positioned and aligned in its location
a. Check if the elements are correctly positioned and aligned in its location
7. Grouting
Comments: