Unit 5 Notes
Unit 5 Notes
CONTROL
Forecasting – Qualitative and Quantitative forecasting techniques – Types of production
– Process planning – Economic Batch Quantity– Loading – Scheduling and control of
production – Dispatching–Progress control.
5.1 INTRODUCTION
Forecasting is the first major activity in the planning. It involves careful study of past data and present
scenario. The main purpose of forecasting is to estimate the occurrence, timing, or magnitude of future
events. For example, the trend of past ten years in the demand of cars and corresponding purchasing
power of the consumers may form a basis of forecasting the demand of cars during next year. Once, the
reliable forecast for the demand is available, a good planning of activities is needed to meet the future
demand. Forecasting, thus, provides the input to the planning and scheduling process.
Precise forecasting of economic activities, such as product demand, is almost impossible because of
many interactive factors, which are difficult to model. Despite the fact that highly reliable forecast is
unrealistic, the approximate estimate forms the basis of planning process.
5.2 BENEFITS OF FORECASTING
Good forecast of material, labour and other resources for operation are essentially needed by the
managers.
If good projection of future demand is available, the management may take suitable action regarding
inventory. Similarly, if production activities are accurately forecasted, then balanced work-load may be
planned. Good labour relations may be maintained as there would be lesser hiring and firing activities
by the management with better manpower planning. Therefore, forecasting is useful due to following
benefits:
1. Effective handling of uncertainty
2. Better labour relations
3. Balanced work-load
4. Minimisation in the fluctuations of production
5. Better use of production facilities
6. Better material management
7. Better customer service
8. Better utilisation of capital and resources
9. Better design of facilities and production system.
Efforts in forecasting activity involve two types of costs. While more effort in forecasting causes
increased cost due to data collection and analysis, lesser forecasting activity involves lost revenue,
which may be due to unplanned labour, unplanned material or unplanned capital cost (Figure 5.1).
Therefore, each firm should maintain a balance in its forecasting effort and stick to a zone near to
accuracy cost trade off (Figure 5.2).
Difference between Forecasting and Prediction
Forecasting and prediction are two different things (Table 5.1). Forecasting is objective, scientific,
reproduce, free from individual bias and error analysis is possible in it. Prediction, on the other hand, is
subjective, mostly intuitive, non-reproducible and contains individual bias. Only limited error analysis
is possible in prediction.
Table 5.1 Difference between Forecasting and Prediction
ACCURACY OF FORECAST.
It is almost impossible to obtain an exactly right forecast every time. This is due to many factors, which
affect the trend in data. It is difficult to capture the exact interrelation of these influencing factors.
Therefore, some error in forecasted value and actual value is quite common.
Sometimes, it is important to know if the forecaster (a forecasting technique) is unbiased or not. An
unbiased model should overestimate or underestimate the forecast in almost equal ratio.
5.6.1 Measures of Forecasting Error
1. Mean Absolute Deviation (MAD):' This is calculated as the average of absolute value of difference
between actual and forecasted value. The negative sign in this difference is ignored as overestimate as
well as underestimate are both off-target and thus undesirable.
2. Mean Sum of Square Error (MSE): The average of square of all errors in the forecast is termed as
MSE. Its interpretation is same as MAD.
4. Tracking Signal (TS): It is used to identify those items, which do not keep pace with either positive
or negative bias or trend.
where, Di is the actual demand for the i th period n is the number of periods included in each average.
Example 5.1 Forecast for 3-Month Simple Moving Average.
It may be observed in SMA approach:
1. The longer the moving-average period, the greater the random elements smoothening.
2. In case of trend (increasing/decreasing), the SMA has adverse trend. This is due to lagging trend.
3. The longer is the time span, the smoother is the forecast but with lagging trend.
4. Simple moving average method involves quite large data handling as we go fol. large period average
(Figure 5.5).
5.7.3 Weighted Moving Average
This approach is based on the principle that more weightage should be given to relatively newer data.
The forecast is the weighted • average of data. Thus:
It may be noted that when more weight is given to the recent values, the forecast is nearer to the likely
trend. Weighted moving average is advantageous as compared to simple moving average as it is able to
give more importance to recent data.
5.7.4 Exponential Smoothing
In exponential smoothing method, the weightage of the data diminishes exponentially as the data
become older. In simple moving average, the only few past data are accounted. However, in exponential
smoothing, all past data are accounted. The weightage of every previous data decreases by (1 - a) times,
where a is called as exponential smoothing constant. For example, when a is equal to 0.3, the weightage
of last period data is 0.3 and weightage of last to last period data is 0.3 (1 - 0.3) or 0.21.
Example 5.4 Comparison of Exponential Smoothing Forecast for Different Values of Smoothing
Constant. Let us consider demand of an item for ten weeks, given in the following table. The forecast
for different value of a is also shown.