ECDSWC CONSTRA MoF 3 MSRA CL 002
ECDSWC CONSTRA MoF 3 MSRA CL 002
EARTH WORK
October, 2022
TABLE OF CONTENTS
1. PURPOSE & SCOPE: ......................................................................................................... 1
2. DEFINITIONS & ABBREVATIONS: ..................................................................................... 1
3. WORKING ACCESS: The access/egress for the construction vehicles for the installation of
activities shall be as per the traffic management plan. .......................................................... 2
4. LIGHTING ........................................................................................................................ 2
5. TOOLS AND EQUIPMENTS ............................................................................................... 2
General: ................................................................................................................................ 2
Personal Protective Equipment: .................................................................................................... 2
6. MATERIALS: .................................................................................................................... 3
7. SQUENECE OF WORK: ..................................................................................................... 3
8. QUALITY CONTROL ......................................................................................................... 4
9. PROGRAMME ................................................................................................................. 4
10. RISKS & CONTROLS ...................................................................................................... 4
11. EMERGENCY ARRANGEMENTS..................................................................................... 4
General........................................................................................................................................ 4
Fire Precautions ........................................................................................................................... 4
Communication............................................................................................................................ 5
12. TRAINING .................................................................................................................... 5
13. SUPERVISION .............................................................................................................. 5
14. WORKING HOURS........................................................................................................ 5
15. ATTACHMENTS ............................................................................................................ 5
Document Title:
This Method Statement Provides the Control Sequence and methodology that will be used for
excavation & earth work in compliance with contract specifications and drawings.
The scope of this method statement is to define all the procedures used in excavation & earth
work including sitting out, disconnecting electrical connections, carta way and disposals works.
___________________________________________________________________________
Document No.: ECDSWC/CONSTR./MoF-3/MSRA/CL/0002 1
Revision: 0 [17-October-2022]
Document Title:
3. WORKING ACCESS:
The access/egress for the construction vehicles for the installation of activities shall be as per
the traffic management plan.
4. LIGHTING
I. Safety lighting: The minimum safety lighting as per General requirements will be
provided.
II. Task lighting: Task lighting shall be provided in addition to the safety lighting to
undertake the task with the proper level of lighting to meet acceptable safety and
quality of workmanship standards.
5. TOOLS AND EQUIPMENTS
General:
• Appropriate plants and equipment shall be used for the execution of the activity.
1 Excavator
2 Dozer
3 Loader
4 Grader
5 Shovel
6 Dump Track
7 Compactor
___________________________________________________________________________
Document No.: ECDSWC/CONSTR./MoF-3/MSRA/CL/0002 2
Revision: 0 [17-October-2022]
Document Title:
6. MATERIALS:
SLNo. Material Description MAR Ref No. Status Remarks
1
2
3
7. SQUENECE OF WORK:
___________________________________________________________________________
Document No.: ECDSWC/CONSTR./MoF-3/MSRA/CL/0002 3
Revision: 0 [17-October-2022]
8. QUALITY CONTROL
9. PROGRAMME
• Hazards' Risks, please refer the file to be attached for the Risk Assessment
• Control Measures' Permits Please refer the file to be attached for the Risk Assessment
11.EMERGENCY ARRANGEMENTS
General
• The Site HSE department shall be responsible to arrange and coordinate with site execution
teams in arranging Day & Night emergency procedures.
• First Aid facilities shall be established to carry on first aid on site in case of any injuries.
• In case of any emergency the HSE will be informed about the emergency.
• Emergency assembly point shall be allotted and communicated to all the operatives involved
in the job
• Ensure clear access to the emergency assembly area with signage’s in place.
• No construction activity shall block the access leading to the emergency assembly point. In case
of any deviation the access has to divert and the same shall be communicated to all the operatives
on site.
Fire Precautions
• Fire extinguishers shall be put in place in each working zone and a clear access shall be provided
to the location.
• All the operatives shall be trained for fire precautions on site.
• A fire warden is appointed and trained from each team of operatives
___________________________________________________________________________
Document No.: MSRA-MoF 3-CL-001 4
Revision: 0 [17-October-2022]
Communication
• The communication on site shall be through appropriate means of communications including
mobile phones or by two-way wireless radio systems (If required)
• Formal communication between the engineer and the contractor shall be as per site
communication plan and through the created email loop.
• Inspection requests shall be submitted in hardcopies with necessary attachment at least 24 Hr.
prior to planned date of inspection.
12.TRAINING
Necessary safety, Quality and operational training shall be provided to the operatives involved in the
activities.
13.SUPERVISION
14.WORKING HOURS
Working hours will be 08:00 am to 06:00 pm (Mon to Sat) on regular basis. Whenever required for additional
hours and/or Night shift work, it will be on the discretion of the project manager. The PM is responsible for
informing client and consultant/engineer.
15.ATTACHMENTS
• ITP
___________________________________________________________________________
Document No.: MSRA-MoF 3-CL-001 5
Revision: 0 [17-October-2022]