PS MODULE
(End User)
If you are working as planning engineer and involving in day-to-day operation matters of projects.
Contents
DAY-1 (Half Day + Practice) DAY-3
Claim Management – (Process adopted)
Legacy Systems Replaces by SAP
Data Archiving – (Process adopted)
SAP Modules implemented at Descon
Reports
SAP PS Module Commonly use terms
Issues faced by users
Project Life Cycle in SAP & Process Overview
Project Planning in SAP
Cost planning, Budgeting and versions
Revenue Planning
Procurement (Purchase Requisition – Material / Service)
SD
PM
CATs
Legacy Systems replaced by SAP
MM
FICO
FICO
Sales and
Distribution
(SD)
Document Plant
Management Maintenance
System (DMS) (PM)
SAP MODULES
Cross - Equipment
Tool and
Application Management
Time Sheets Project (ETM)
Systems
Quality Financial
Management Controlling
(QM) (FICO)
Human
Materials
Capital
Management
Management
(MM)
(HCM)
SAP PS Modules Common Terms
Controlling Area:
The SAP Controlling Area is an organizational unit used to represent a closed system for cost accounting purposes.
For DEL it is DES1, for ODICO it is DES2.
SAP PS Modules Common Terms
Plant:
A plant is an organizational unit subdivide an enterprise according to the logistics operation. e.g.
Corporate 1101 , Maintenance PAK BU 1108.
SAP PS Modules Common Terms
Profit Centre:
Profit Centre is an organizational unit used for reporting profit and loss of a defined area of
responsibility within the organization.
i.e. Project or Zone. e.g. HYUNDAI = 11080205, FATIME FERTILIZER = 11080101
Cost Centre:
Organizational unit within a controlling area that represents a location where cost occur is known
as Cost Center in SAP terminology. e.g. 11080205L Labor Cost Center
Cost Element:
Cost element means a distinct componentControlling
or categoryArea of costs (e.g. materials,
DES1 Column1
directColumn2
labor, Column3
Geographical Locations PAK OMAN QBU UAE
allocable direct costs, subcontracting costs, Company
other costs)
Code
which is assigned to
1100
a cost
1400
objective.
1300 1200
A cost element is the cost of a resourcePlant that is
/ ISD consumed by an activity.
1108 e.g.
1408 800560
1308 = 1208
Coating/Wrapping material, 810003 = Sub Contract Engineering Services 11080205
Profit Centre
Cost Centre 11080205E
11080205L
PS Module / Coding Mask - ISD TP TO TQ TA
PS Module / Coding Mask - Maf. DM / DR
Project Structure in PS Module (IS Division)
Coding Scheme:
Plants:
- Turnaround: TP.0XXXX
- Manpower Supply Jobs: TP.1XXXX
Controlling Area- DES1
- Retrofit Construction: TP.2XXXX
- E&I Jobs: TP.3XXXX PAK OMAN QBU UAE
- EPC Retrofit Jobs: TA.4XXXX
Company 1100 1400 1300 1200
Revenue TP.00061-RV
VC TP.00061-VC
Direct Labor TP.00061-VC-L
PPE TP.00061-VC-L-PP
PACKAGE TP.00061-VC-L-DL
Processes Overview: Planning & Budgeting
Project
Project Award Project Scheduling •BPO Creation
Budgeting
•BPO Planning
• Inquiry • WBS
• Sales Order •Run Cost plan
• Quotation • Activities • Dates •Revenue Planning •Copy plan to
• New Project Budget
•Approvals
Cost & Revenue •Release
Proposal Project Structuring Budget
Planning
• Budget Allocation
• Budget Release • Revaluation Process
• Budget Transfer Period End • RAKey Process
Budgeting Closing
• Budget Supplement
SD
Submit
Create Sales Project awarded
Quotation
Order
1. PO / LOI Copy
2. In case of PO / LOI not issued,
2.1. Client email that shall be confirming project value
2.2. Approval by Incharge Planning
3. Client Name
4. Project Duration: Start date and end date
5. Project Type: Shutdown / Retrofit / Manpower Supply / E&I
Budget Release Protocol – As per policy 13.1
In order to cater for initial mobilization before Project Budget upload in SAP.
5% of approved BID cost to be released for EPC, Construction and IP Division’s projects.
10% of approved BID cost to be released for Manufacturing and MAINTENANCE Division’s projects
Required Documents,
a. Approved Bid Copy (as per applicable bid approval limits) to be submitted (Bid Summary Report/BSR)
b. Complete project WBS Structure to be created with top nodes for cost booking (Budget Rev 00) Top
sheet.
To proceed for 100% successful release of budget in SAP. Following documents shall be required
for Division approval,
Work Breakdown Structure defines cost heads to record actual and plan cost in a hierarchical structure.
Following functions are adopted
•We plan cost on WBS Level
•Budget Control is activated on WBS Level
•Actual cost is summarized on WBS level to compare with plan.
Level - 1
Level - 2
Level - 3
Network & Activity
A network organizes the activities under the WBS of the project. Whereas activity is created
under the WBS where we assign the resources. Activity is used to create PR and Man hours
posting through CATs.
Activity Element
Activity element is created under the activity as per equipment requirement.
It is used to post actual machine hours.
Project Structure
(Network & Activity)
Network
Activity
Project Financial Planning (Cost & Revenue)
PS
PS
Copy Cost plan to CO PS
Run Cost plan using
Version E01 (Budget Plan Revenue
mapping file
Rev0)
Cost Plan
Cost Plan = ZWPP (Phasing) x BPO
Firstly, BPOs are linked with WBS in excel standard format and then uploaded in
SAP
Object Currency:
It is the local currency for the respective BU. For QBU its QAR
LF or Budget
Week/Month/Year Plan
WPP Distribution Basis
(MHRS or Quantity)
Start of date
Excel File
Format must
match this
order
Cost Plan - Work Progress Plan (WPP)-zcp-cj40
(upload through Excel) – T code ZWPPR
Cost Planning - Base Planning Object (BPO)
BPO – Base Planning Object is a building block for cost planning*
BPO –
BPO -
Fixed
Labor
Assets
BPO –
BPO -
Material
Project Misc.
Expenses
ZCP Creation
Cost Plan (ZCP) is first set in excel, then we upload it in SAP (T code: ZCP).
A typical excel ZCP looks like this,
Cost Plan Uploading (T code : ZCP REPORT)
DES1
To clear
Previous
cost
Cost Plan Uploading (Cj40)
Project Financial Planning (Cost & Revenue)
Now the final two steps in cost planning are Cost and Revenue Planning
3. Copy View
1. Click Current
Budget
4.Enter
Percentage
5.Total Up and
then Save
2. Select All
Project Financial Planning (Revenue Planning CJ42)
1. Double Click
3. Go to Detailed
PLanning
5. Press Control+S
two Times
4.Enter Revenue
2. Select Year on relevant Cost
element
Revenue Planning in SAP (CJ42)
To select
Period/WBS
category
Planned PAT%
Project Financial Planning (Cost & Revenue)
Budget Supplement
If there is an increase in one cost head and it cannot be compensated through contingencies or
management reserve (resultantly having a direct impact on project profitability
An additional budget will be provided to that cost head after the approval (Same hierarchy which
approves the budget). - SOP-06 reference
Project Budgeting (Supplement T code: CJ37)
Budget Supplement & Transfer
Project Budgeting (Transfer)
Revenue Planning in SAP (Period Wise: T code CJ42)
Enter
Planned
Values
here
Other SAP Modules Integration with PS Module
Procurement
(Purchase Requisition for Material/Services)
PR is approved by single identity which is Project Manager (as per SAP position)
These PRs then converted into PO/WO by the Commercial or Subcontracting department.
Comes Automatically
Procurement (Material PR)
Material Purchase Requisition can also raised though cj20n Project Builder under relevant WBS.
Material
Purchase
Requisition
Procurement (Service PR)
Service Purchase Requisition can also raised though cj20n Project Builder under relevant WBS.
Service
E&P
Purchase
Requisition
Procurement
(Service PR)
Procurement (PR Release)
Procurement (PO Release) – 3542
(40001/00062)
Invoicing
Press Save
1. Go to Accounting
2. Note Accounting
Document Number
Go to VF02 Transaction Code
1. Enter Billing Document Number 2. Press Release for Accounting
Project Execution and Monitoring (cost actualization)
QM
Material Inspection,
CAR/PAR, NCR,
MM
RFI, Puchlist, Audits ETM/PM
Material Receiving
and Issuance Requisition, Planning,
Shipping, Logbook,
Service Entry & Billing, Maintenance
Acceptance
CATS
P6-PS
Actual Progress &
Dates
Project Man-hour Entry,
Approval, and Transfer
to HCM/PS
Project Monitoring (Support)
DMS
Document
Attachments PS
SD Claim Management
(Variation Order for Extra &
Actual Revenue (Billing Additional Work)
documents) Back Charging
Scrap Sales
CMDG
QM
Customer, Vendor,
Employee, Position, Project RFI, CAR/PAR, NCR,
Puchlist, Audits
Recipient etc
Personnel Cost Plan (PCP) from (HCM)
There are some key points for PCP:
Positions against which persons are not at site should be mentioned as TBN and their budgeted
salaries will be mentioned.
Service Entry Sheet (SES) against the Work Order using t-Code ML81N, for the work done by
the vendor.
Actual Booking / Mhrs
Labor Time sheet
During the month Labor and Equipment cost is calculated on these rates.
Activity Type-Rates (Labor)
Activity Type-Rates (Equipment)
Actual Booking (Man-hours)
• Time Sheet entry (CATA) and its approval (Out of System)
Actual Booking (Man-hours)
• Time Sheet Entry & Approval
Actual Booking (Man-hours)
Timesheet Transfer to HR and PS
Actual Booking (Machine Hours)
• Log book Sheet (Out of system)
Actual Booking (Machine Hours)
PM ETM CO PS
PM Order Rental Price Calculation Project
Settlement Settlement and Postings Revaluation
PS
FI PS
Result Analysis
Period Closed Settlement
Key
Re-Evaluation Process (S_ALR_87013611)
For every Month Closing, we execute a
transaction of Re-Evaluation. In this
method, Cost of Man-hours and Machine
Hours are re-calculated on the basis of
Actual Cost & Hours.
Costs
Subject
Document Management System – DATA ARCHIVING IN SAP
T.Code= CV01N
Document Management System
T-Code= CV04N
Project Closing /cj20n
The following processes or steps should be taken into account before closing the project
All the activities should be 100% confirmed or set completed status (P6 / SAP)
*Status TECO – Technically Completed should be set (This status will close open Reservations and Purchase Requisitions)
Open Purchase Orders (Material) should be fully delivered or closed
Project Material Stock should be transferred to surplus plant
Open Invoices should be cleared
Payments to vendor should be cleared
Set Project Close status (CLSD)
Adobe Acrobat
Document
Reports
S No Report T-Code Purpose
1 CN48N Actual Man-hours and Machine Hours Posting on Daily Basis)
2 CJI3 Actual Cost Booking against WBS
3 CJI5 Commitment Cost (PRs/POs/WOs)
4 S_alr_87013532 WBS wise (Plan / Actual Cost)
5 S_alr_87013542 WBS wise & Cost Element wise (Plan / Commitment / Actual Cost)
6 ME5J Project wise List of PRs
7 ME2J Project wise List of POs
8 S_alr_87013558 WBS Wise (Budget / Actual / Variance)
9 MBBS Material Stock Report
10 ZPJYD Analytical Study
11 S_ALR_87013611 Cost Center Actual/Plan/Variance
12 S_ALR_87013565 Execute Drill Down report planned contribution margin
13 S_ALR_87100185 Actual Cost per month (Current Fiscal Year)
14 S_ALR_87100186 Plan Cost per month (Current Fiscal Year)
15 S_ALR_87013542 Actual/Cumulative/Total/Plan
16 KKA2 Result Analysis for Project
Report
(CN48N)
• In order check Man-hours against project network.
Report
(CN48N)
• In order to check Machine-hours against Project network.
Report
(CJI3)
• Actual Cost Booking WBS wise
Report
(CJI5)
• Commitment Cost WBS wise (PRs + POs + WOs)
Report
(s_alr_87013532)
• Planned / Actual Cost (WBS wise)
Report
(s_alr_87013542)
• Planned / Commitment / Actual Cost (WBS wise)
Report
(ME5J)
• List of PRs
Report
(ME2J)
• List of POs
Report
(S_alr_87013558)
• WBS Wise (Budget / Actual / Variance)
Report
(ZPJYD)
Total
Project’s
Actual
Periodic/Monthly Value
Revenue
Received Revenue
Total
Project’s
Cost
PAT
POC Revenue
RA Key Process
Result Analysis
Cost-Based POC Method
Revenue-Based Method - With Profit
Realization
A.Commonly there are 3 issues: 1) Budget availability 2) Wrong selection of G/L 3) Version not updated after any change in raised PR.
A. Appropriate selection of G/L while raising PR and expense voucher booking in correct WBS as per planned budget.
A. PO version either not updated nor approved. Refer buyer needs to resolve
Q. While creating BPO, user usually asked for BPO category selection ?
A. M category shall be used for Material, Labor / Equipment ‘E’ Category, Services ‘N’ category, In case of variable (general items) ‘V’
Q. BPO Uploading process available in SAP. Usually error faced while uploading of BPO / ZWPP / ZCP
A. BPO creation / uploading are carried out with specific format defined. So fill data in proper manner for successful uploading.
Q. During Month end closing, Multiple error appears w.r.t maintain labor and Equipment, Project Open and Work
Centre not assigned Kp26, Project open, Work center not assigned
A.In order to avoid monthly end closing error, All project activity type rate should be maintained at start of project,
Work center should be assigned against respective WBS. Respective Zonal Planning Coordinator / In charge planning
A. Commitment closing is important process for project closure. In charge Planning / PM emphasized on commitment
closing and locking of Project in SAP. Commitment can be closed by closing PR / PO, SES actualization and Invoices
booking and Posting. Lastly Project status marked as TECO (to avoid any upcoming cost) and CLSD after successful
process performed.
Q. What are the reports that planning engineer usually review prior to perform budget related
processes. ?
A. In SAP there are many standard reports available that can support user to review as an when
required basis. As reporting is real time and budget errors can be immediately analyze by right
access of the report. Some reports are already shared in aforementioned slides.
Q&A