Nhai Project

Uploaded by

syadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views46 pages

Nhai Project

Uploaded by

syadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 46

Completed PCC / PCOD Issued

Status as on 01 July 2024


All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
4L of Ichapuram to Narasannapeta from Km. 470.415 to Km. 581.700
1 Andhra Pradesh 16 13.45 EPC 4L 09/05/2018 SPL CCCL (JV)
(Capacity Augmentation) of NH-16 (Old NH-5)
Icchapuram - Narsannapeta (km 484.000 to km 580.700) under TOT
2 Andhra Pradesh 16 96.7 TOT 4L 29/08/2018 Icchapuram Tollway Private Limited
Bundle - 1
3 Andhra Pradesh 6 L of Narasannapeta - Ranastalam 16 54.2 HAM 6L 01/01/2019 APCO Infratech Pvt. Ltd.
Ranasthalam (Km.634.000) to Anandapuram (Km.681.000) of NH-16 in Ashoka Ranastalam Anandapuram
4 Andhra Pradesh 16 47 HAM 6L 16/11/2017
the State of Andhra Pradesh Road Limited
Visakhapatnam-Champavathi River from Km. 654.204 to Km. 701.170
5 Andhra Pradesh 16 46.2 EPC 4L 08/06/2001 UNITECH-NCC(JV)
(AP-3)
6 Andhra Pradesh Ankapalli - Annavaram (Tuni) from km. 741.255 to km. 830.525 16 89.27 BOT Annuity 4L 05/09/2002 GMR Infrastructure Ltd
Ankapalli - Annavaram (Tuni) from km. 741.255 to km. 830.525 under
7 Andhra Pradesh 16 88.532 TOT 4L 29/08/2018 Ankapalli Tollway Pvt., Ltd
TOT Bundle - 1
Gammon Engineers & Contractors
8 Andhra Pradesh Annavaram - Diwancheruvu (km 830.525 to km 901.500) 16 70.98 BOT Annuity 4L 30/05/2002
Pvt. Ltd.
Annavaram - Diwancheruvu (km 830.525 to km 901.500) under TOT
9 Andhra Pradesh 16 70.98 TOT 4L 29/08/2018 Safeway Concesssions Pvt Ltd.
Bundle - 1
1-Punj Lloyd Ltd, 2-Larsen & Toubro
10 Andhra Pradesh Diwancheruvu - Siddhantham from km. 901.500 to km. 950.542 216A 49.04 EPC 4L PS 17/06/2001
Ltd.
Gammon Engineers & Contractors
11 Andhra Pradesh Rajamahendravaram - Dharamavaram 16 53 BOT Annuity 4L 30/05/2002
Pvt. Ltd.
Diwancheruvu - Siddhantham from km. 901.500 to km. 950.542 under
12 Andhra Pradesh 16 49.042 TOT 4L 29/08/2018 Diwantham Tollway Pvt. Ltd
TOT Bundle - 1
Limak SOMA(JV) & Larsen & Toubro
13 Andhra Pradesh Siddhantham - Gundugolanu from km. 950.542 to km. 1022.494 216A 71.952 EPC 4L PS 17/06/2001
Ltd.
Siddhantham - Gundugolanu from km. 950.542 to km. 1022.494 under
14 Andhra Pradesh 16 71.952 TOT 4L 29/08/2018 Ankapalli Tollway Pvt., Ltd
TOT Bundle - 1
Major Maintenance for the stretch from KM. 1076.480 Chinna
Raghava Project Constructions
15 Andhra Pradesh Avutupalli to KM. 1100.254 Kanaka Durgamma Vardhi on Vijayawada - 16 23.774 Item Rate 4L 20/05/2023
Privated Limited
Gundugolanu section of NH-16
6L of Gundugolanu (Design km 1023.280) to Kalaparru (Design km
16 Andhra Pradesh 16 27.4 EPC 6L 27/01/2020 Varaha Infra Ltd. - JCEG (JV)
1050.680) of NH-5 (New NH-16)
6L of Kalaparru to Chinna Avutupalli including 6 lane Hanuman Lakshmi Infrastructure & Developers
17 Andhra Pradesh 16 27.4 EPC 6L 21/02/2019
Junction bypass Pvt Ltd
Construction of Half Flyover at Km 1082+320 (Design Chainage at Km.
0+740) at Vijayawada Airport near Gannavaram on Gundugolanu –
18 Andhra Pradesh 16 1.415 EPC 4L 29/07/2022 Trenzet Infra Private Limited
Vijayawada Section of NH-16 Mode towards rectification of Black Spot
ID: AP-(02)-093
3L western side flyover Before Jyothi Mahal Junction to Beyond
Lakshmi Infrastructure & Developers
19 Andhra Pradesh Ramesh Hospital Junction from Design Km 0.300 to Design Km 2.770 16 2.47 EPC 3L 05/11/2020
Pvt Ltd
on NH-16
Six Laning Of Chilkaluripet Vijaywada Section from km 355.00 to km
20 Andhra Pradesh 16 82.5 BOT Toll 6L 01/05/2009 IJM-IDFC (JV) Consortium
434.15
Chilakaluripet (1182.802) to Nellore (1366.547) of NH16 in Andhra
21 Andhra Pradesh 16 183.62 BOT Toll 6L 21/11/2011 KMC & BSCPL (JV) Consortium
Pradesh
22 Andhra Pradesh Nellore bypass (from Km. 161.034 to 178.200) 16 17 BOT Annuity 4L 27/10/2002 Navyuga Road Projects Pvt Ltd.
Development of Emergency Landing Facility on Chilakaluripet - Nellore
23 Andhra Pradesh 16 5 EPC 4L 06/03/2019 Venkat Rao Infra Projects Pvt. Ltd.
Section from km. 1210.00 to km. 1214.00
Operation and Maintenance including Incident Management of Arjunvaishnavi Infrastructure and
24 Andhra Pradesh 16 17.166 EPC 4L 18/06/2020
Nellore Bypass section from Km. 1366.547 to Km. 1383.713 of NH-16 Developers Pvt. Ltd.

Page 1 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Routine Maintenance including Incident Management (Excluding
Ambulance Services) for Nellore Bypass from Km. 1366.547 to Km.
1383.713 (Excluding from Km. 1379.340 to Km. 1380.957 & from Km.
25 Andhra Pradesh 1,667 40.811 Item Rate 2L/4L PS 15/03/2024 M Sanjeeva Raju
1382.690 to Km. 1383.713) (4L length 14.526 Km) section of NH-16 &
Badvel to chunculuru section from Km. 628.555 to Km. 652.200 (2L
length 23.645 Km) of NH-67.

Periodic Renewal of Nellore bypass section from km 1366.547 to km


26 Andhra Pradesh 1383.713 excluding the sections from km 1379.340 to km 1380.350 16 17.166 Item Rate 4L PS 11/03/2024 DDR and Co.
km 1382.690 to Km 1383.713 and major bridge NH-16 (Penna Bridge).
27 Andhra Pradesh 4L of Tada - Nellore from Km. 52.800 to 163.600 (110.52 km.) 16 159 BOT Toll 4L 16/09/2001 MAIF Investments India 3 Pte Ltd
4/6L of Tada - Nellore (Permanent restoration of flood damaged
28 Andhra Pradesh 16 3.82 EPC 4L/6L 13/12/2019 SRC Projects Pvt Ltd
stretches) from km. 83.35 to km. 83.68 and km. 136.91 to km. 140.40
29 Andhra Pradesh O&M of Anandapuram - Visakhapatnam - Anakapalle 16 58.27 OMT 4L
Anandapuram and Madhuravada from Km. 701.170 to Km. 741.051
30 Andhra Pradesh 16 38 EPC 4L 01/04/1995 KMC Construction Ltd.
(Visakhapatnam to Anakapalli)
Short Term Improvement and Routine Maintenance of Anandapuram-
Abhipsa Construction, Engineer and
31 Andhra Pradesh Vishakhapatnam-Anakapalli from Km.682.980 to Km.741.256 of NH- 16 58.276 OMT 4L
Contractors
16 (Old NH-5)
32 Andhra Pradesh Korlam-Ichapuram from Km. 470.415 to 503.415 (AP-4B) 16 33 EPC 4L 21/09/2001 ITD Cementation India Ltd
33 Andhra Pradesh Palasa-Korlam from Km. 503.415 to Km. 532.600 (AP-4A) 16 29 EPC 4L 21/09/2001 ITD Cementation India Ltd
34 Andhra Pradesh Srikakulam-Palasa from Km. 532.600 to Km. 606.204 (AP-2) 16 74 EPC 4L 12/06/2001 SPCL-IVRCL(JV)
Champavathi River - Srikakulam rom Km. 606.204 to Km., 654.204 (AP- YOUONE-MAHARIA(JV) & SEW
35 Andhra Pradesh 16 48 EPC 4L 08/06/2001
1) Constructions
36 Andhra Pradesh Srikakulam - Visakhapatnam - Bridges Section (AP-5) 16 94 EPC 4L 13/08/2001 PRASAD-SEW (JV)
37 Andhra Pradesh Ichapuram - Srikakulam - AP-6 (Bridge Package) 16 0 EPC 4L 29/09/2001 Navyuga Road Projects Pvt Ltd.
Maintenance from Km 1076.480 (Chinna Avutupalli) to Km 1100.254
(Kanaka Durgamma Varadhi) and Incident Management from
38 Andhra Pradesh Gundugolanu (Km 1023.280) to Kanaka Durgamma Varadhi (Km 16 23.774 Item Rate 4L 16/03/2022 Shiva Buildtech Pvt. Ltd.
1100.254) Section of Vijayawada–Gundugolanu Section of NH-16 (Old
NH-5)
Erection of Steel Tubular Railing (Fencing) along service road medians
underneath the Eastern Side Benz Circle Flyover from Km. 1076.480
39 Andhra Pradesh 16 1.47 EPC 4L 11/04/2022 Dhingra Brothers (India)
(Chinna Avutupalli) to Km 1100.254 (Kanaka Durgamma Varadhi)
Section of NH-16 (Old NH-5)
Hyderabad - Bangalore (Km 211.000 to Km 462.164 on Hyderabad -
40 Andhra Pradesh 44 251.16 OMT 4L 01/01/2022 Abhipsa Construction, Bhubaneswar.
Bangalore section of NH-44)
6L Grade Separated structures along with slip roads at Km 210+780
E5 Infrastructure Pvt. Ltd - Gawar
41 Andhra Pradesh (ITC Junction in Kurnool Town), Km 260+400 (Kambalapadu Junction, 44 3.17 EPC 6L 04/12/2020
Construction (JV)
Dhone) Km 263+558 (Dhone Exit, Dhone) on NH-44 (old NH-07 )
Periodical Renewal of balance section of the project stretch including
Lakshmi Infrastructure & Developers
42 Andhra Pradesh renewal of service road / slip road from Km 211.000 to Km 462.164 on 251.164 Item Rate 4L PS 25/04/2022
India Pvt. Ltd.
Hyderabad - Bangalore section of NH 44
4L of Gundugolanu Devarapalli Kovvuru from km 15.320 to Km 85.204
43 Andhra Pradesh 16 69.884 HAM 4L 22/10/2018 G R Infraprojects Limited
of NH-16
6L of Anandapuram Pendurthi Anakapalli Section from km. 681.000 to
44 Andhra Pradesh 16 50.78 HAM 6L 04/01/2019 Dilip Buildcon Ltd.
km. 731.780 of NH-16
45 Andhra Pradesh Chandragudem to AP/Telangana Border 30 38 EPC 2L PS 04/01/2016 Sai Balaji constructions
46 Andhra Pradesh 4L of Nandigama - Vijayawada 65 49 BOT Toll 4L 01/08/2001 Swarna Tollway Private Limited
Lakshmi Infrastructure & Developers
47 Andhra Pradesh Nandigama Bypass and Kanchikacherla bypass 65 14.34 EPC 6L 12/03/2018
Pvt Ltd

Page 2 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Four Laning of Kadapa (167.750) to Kurnool (356.502) of NH-40 (Old KMC Construction Ltd. IVRCL
48 Andhra Pradesh 40 188.75 BOT Toll 4L 15/11/2010
NH-18) Consortium
6L Korlam-Kantakapalle Section of NH-130CD Road from Km 421.100
49 Andhra Pradesh 130CD 24 HAM 6L 19/02/2022 Psk Infrastructure and Pvt. Ltd.
to Km 445.100 (Pkg-3)
Nalagampalli to Allkuppam (AP/KA Border) from Km. 172. 000 to Km
50 Andhra Pradesh 69 47.68 EPC 4L 15/11/2017 Dilip Buildcon Ltd.
219.687
Chittor (Design Km 0.000-Existing Km 158.000 of NH-4) to Mallavaram
51 Andhra Pradesh 140 61.13 HAM 6L 04/01/2019 KNR Constructions Limited
(Design Km 61.128-Existing Km 41.800 of NH-140)
Grade Seperator from H-7 Area to Port Connectivity Road bypassing
52 Andhra Pradesh 516C 0.773 EPC 6L 22/06/2018 MVR infra projects Pvt Ltd
Convent Junction
53 Andhra Pradesh Road Connectivity-Visakhapatnam Port Trust 12 EPC 4L 27/05/2002 M. Venkata Rao Infra Projects Pvt. Ltd.

54 Andhra Pradesh Giddalur-Vinukonda from Design km 212.983 to Design km 322.800 544D 112.8 HAM 2L PS 06/02/2019 GV Road Projects Private Limited
4L of Kathipudi to start of Kakinada bypass from Km 0.000 to Km
55 Andhra Pradesh 216 27.5 EPC 4L 18/05/2016 Dhyan Singh Prop Dhyan Singh
27.500 of NH-214 (New NH-216)
Operation and Maintenance of Tirupati Tiruttani Chennai Section of
56 Andhra Pradesh 716 107.18 Item Rate 2L/4L PS 01/08/2022 G.R Engineers & Contractors
NH 205
O&M of 2L PS Markapuram-Vaggampalle Section from Km. 198.694 to
57 Andhra Pradesh 565 94.572 OMT 2L PS 12/10/2021 Sai Balaji constructions
Km. 293.266 of NH-565
Routine maintenance including incident Management for O&M of
58 Andhra Pradesh Vaggampalli - Dornal T section from km 293.266 to km 359.422 of NH- 565 67.327 EPC 2L PS 12/07/2021 R R Associates
565
O&M of 2L PS Davulapalli to Markapuram Section from Km. 153.939
59 Andhra Pradesh 565 43.379 OMT 2L PS 12/10/2021 Sai Balaji constructions
to km.197.318 of NH-565
60 Andhra Pradesh Penchalkona - Yerpedu from Km 425.400 to Km 509.400 of Old NH-565 565 84 EPC 2L PS 28/08/2021 Garrison Constructions
4L of Vijayawada to Machilipatnam from Km. 0.000 to Km. 63.800 of
61 Andhra Pradesh 65 64.61 EPC 4L 24/11/2016 Dilip Buildcon Ltd.
Old NH-09 (New NH-65)
Routine Maintenance for Ibrahimpatnam – Chandragudem – Abhipsa Construction, Engineer and
62 Andhra Pradesh 30 70.19 Item Rate 2L PS 01/04/2022
AP/Telangana Border section from Km. 0.000 to Km. 70.190 of NH-30 Contractors
Maintenance of 2L PS Mydukuru – Dornala T Junction from Km
63 Andhra Pradesh 67 52 Item Rate 2L PS 22/04/2022 RP Projects Pvt Ltd
589.000 to 641.000 of NH-67
Routine Maintenance including incident Management of Dornala T
64 Andhra Pradesh Juction to Nellore section from km. 641.000 to Km. 741.950 of NH 67 67 100.95 Item Rate 2L PS 08/04/2022 R R Associates
(Designe length 100.95 Km) in the state of Andhra Pradesh.
4L of Bijni - Assam / WB Border from km. 60.0 to km. 30.00 of NH-31 C
65 Assam 31 C 30 EPC 4L 06/10/2005 Gayatri-ECI (JV)
(AS-11)
4L of Bijni - Assam/WB Border section of NH-31C from km. 93.00 to
66 Assam 31C 33 EPC 4L 06/10/2005 Gayatri - ECI (JV)
km. 60.00 (Contract Pkg- EW-II (AS-10))
Strengthening including Special Repair and operation, maintenance on
existing rigid and flexible 4-lane Pavement surface from km 30.000 to
67 Assam 31C 63 Item Rate 4L 05/04/2023 Raju Chandra Basumatary
ch. 93.000 on NH-31C (AS-10 & AS-11) (New NH No. 27) And Repair
and Rehabilitation of 8 Nos. of Distressed Brid
68 Assam Nalbari-Bijni(AS-08) from km.1013 to km.983 of Old NH-31 27 30 EPC 4L 15/12/2005 Punj Lloyd Infrastructue Ltd.
69 Assam Nalbari-Bijni(AS-09) from 983.00 km to 961.50 km of Old NH-31 27 22 EPC 4L 30/11/2005 Punj Lloyd Infrastructue Ltd.
Strengthening including Operation and Maintenance of 4L PS from
70 Assam Km. 961.500 to Km. 1013.000 on NH 27 (AS-08 & AS-09) (New NH No. 27 51.5 Item Rate 4L 26/04/2023 Raju Chandra Basumatary
27)
Nalbari to Bijni section of NH-31 from km. 1040.30 to Km. 1013.00
71 Assam 31 27.3 EPC 4L 21/10/2005 KMC Construction Ltd.
(Contract Package EW-II/ AS-07) in Assam

Page 3 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Nalbari to Bijni from Km. 1065.00 to km. 1040.300 (Contract Package
72 Assam 27 24.7 EPC 4L 10/11/2005 Brahmaputra Infrastructure Ltd.
AS-06)
Maintenance of Tihu to Puthimari section from Km. 1040.300 to Km.
73 Assam 27 52.7 EPC 4L 08/04/2022 Brahmaputra Infrastructure Ltd.
1093.000 of NH-31(NH-27 new)
Operation and Maintenance of stretch of Kaljhar to Nalbari of Contract
74 Assam 27 52 OMT 4L 08/03/2024 Raju Chandra Basumatary
Package AS-06 and AS-07
4L of Guwahati - Nalbari Section from km. 1121.00 to km. 1093.00 in
75 Assam 27 26.81 EPC 4L 02/12/2005 Brahmaputra Infrastructure Ltd.
Assam (AS-4)
2L to 4L of Nalbari - Puthimari (AS-5) section of Guwahati - Nalbari
76 Assam 27 28 EPC 4L 02/12/2005 Brahmaputra Infrastructure Ltd.
from km.1093.00 to km.1065.00
Maintenance work of Guwahati to Nalbari section from Km. 1119.814
77 Assam to Km. 1124.514 (AS-28) & from Km. 1093.000 to Km. 1119.814 (AS- 27 31.514 EPC 4L 01/02/2022 Brahmaputra Infrastructure Ltd.
04) of NH-27
4L of New Brahmaputra Bridge near Guwahati Contract Package No.
78 Assam 27 5 EPC 4L 22/10/2006 Brahmaputra Infrastructure Ltd.
EW-II (AS-28) from km. 1121.00 to km. 1126.00
Guwahati Bypass (Jalukbari - Khanapara (Koinadhara)) from km.
79 Assam 27 17.72 Item Rate 4L 16/06/2000 Valecha Engineering Ltd.
146.172 to km.163.985 (EW - 07)
6L flyover at Boragaon, Gorchuk, Lokhra & Basistha Junction on
80 Assam 27 16.448 EPC 6L 03/03/2022 Dhariwal Buildtech Limited
Guwahati Bypass section from Km 146.172 to Km 162.620 of NH-27
4L of Sonapur to Guwahati from Km 183.000 to Km 163.895 (Package
81 Assam 27 19.1 EPC 4L 20/09/2005 Simplex Infrastructure Limited
AS-03)
82 Assam Jagiroad-Dharamtul (AS-19) 27 25.5 EPC 4L 25/11/2005 Simplex Infrastructure Limited
Sonapur to Dharamtul section from Km 183.000 to Km 205.000 of NH -
83 Assam 37 22 EPC 4L 21/12/2005 Simplex Infrastructure Limited
27 (Package AS-20) in Assam
84 Assam Dharmatul-Raha (AS-2) 37 24.5 EPC 4L 25/11/2005 Simplex Infrastructure Limited
4L of km 262.70 to km 255.00 of NH-37 (old) Raha-Nagaon (AS-18)
85 Assam 27 23.66 Item Rate 4L 18/08/2005 Simplex Infrastructure Limited
(Including Nagaon Bypass)
IL&FS Engineering & Construction
86 Assam Nagaon - Doboka (AS-17) 36 30.36 EPC 4L 25/11/2005
Company Ltd
87 Assam Doboka - Lanka (AS-16) (Including Dobaka Bypass) 54 24.03 EPC 4L 29/11/2005 Punj Lloyd Ltd
4L of km 22.00 to km 40.00 of Lanka - Udali (AS-15) (Including Lanka
88 Assam 27 18 EPC 4L 27/01/2006 KNR Constructions Limited
Bypass of NH-54)
Maintenance work from Km. 5.500 to Km. 35.862 of Nagaon to
Doboka Section (AS-17) ;from Km. 0.000 to Km. 22.000 of Doboka to
89 Assam 27 72.562 EPC 4L 21/04/2022 Simplex Infrastructure Limited
Lanka Section (AS-16);from Km. 22.000 to Km. 40.200 of Lanka to
Udali Section (AS-15) of NH-27
Operation and Maintenance of Nagaon to Doboka section (Km 5.500
90 Assam to Km. 35.862) of Package AS-17 of NH-36 and Km. 0.000 to Km. NH-27 54.469 EPC 4L 19/01/2024 Basanta Kumar Kakati
22.000 including 2.107 Km. Doboka Bypass of AS-16 of NH-54
4L of Udali (km. 40.000) to Manderdisa (Km. 60.500) of NH-27 in
91 Assam 27 20.5 EPC 4L 15/10/2006 Gayatri-ECI (JV)
Assam (AS-27)
Routine Maintenance of Lanka to Hatikhali section (AS-15, 26, 27) Chaudhary Construction Company
92 Assam 27 61.4 OMT 4L 14/03/2024
from Km. 22.000 to Km 83.400 Km of NH 27EW Pvt. Ltd.
Manderdisa (Km. 60.500) to Hatikhali (Km. 83.400) of NH-27 in Assam
93 Assam 27 22.9 EPC 4L 24/07/2011 Simplex Infrastructure Limited
(AS-26 Bal.)
Hatikhali (Km 83.400) to Lailling (Km 111.000) of NH-27 in Assam (AS-
94 Assam 27 27.6 EPC 4L 02/03/2011 IL&FS Transportation Networks Ltd.
25 Bal.)
95 Assam Maibong - Lumding Section (AS-24) in Assam 27 15 EPC 4L 31/01/2011 NKC Projects Private Limited
Maibang to Nrimbanglo from Km. 126.450 to Km.140.700 & km.
96 Assam 27 15.57 EPC 4L 05/08/2006 Hindustan Construction Company Ltd.
164.080 to 165.400 of Jatinga Junction [EW-II] of AS-23
Maintenance of Maibang to Nrimbanglo from Km. 126.450 to
MSV International INC. in Association
97 Assam Km.140.700 of NH 54E (New NH-27EW) [EW-II] of Civil Contract 54E 14.25 Item Rate 4L 08/09/2022
with Manglam Associates
Package AS-23

Page 4 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
4L of Balachera - Silchar (AS-01) from km. 306.54 to km. 275.00 of NH-
98 Assam 27 25.76 EPC 4L 09/02/2004 Punj Lloyd Infrastructue Ltd.
54 (Pkg-EW-II)
Strengthening and Maintenance of 4L of Balachera - Silchar (AS-01)
99 Assam from km. 300.760 to km. 275.00 of NH-54(New NH-27EW) (EW-II) of 54E 25.76 EPC 4L 01/01/2023 D.C Ajmera
Civil Contract Package - N/02027/14001/AS
Maintenance work for Udali to Maibong Section from Km. 40.200 to
Km. 60.500 (AS-27); from Km. 60.500 to Km. 83.400 (AS-26); from Km.
100 Assam 27 86.25 EPC 4L 21/04/2022 Simplex Infrastructure Limited
83.400 to Km. 111.000 (AS-25) & from Km. 111.000 to Km. 126.450
(AS-24) of NH-27
Maintenance work from Km. 163.895 to Km. 278.685 of Khanapara to
101 Assam Uriagaon Section (for Packages AS-03, AS-20, AS-19, AS-02 & AS-18) of 27 114.79 EPC 4L 19/02/2022 Simplex Infrastructure Limited
NH-27
Strengthening work of stretch of Khanapara to Jagiroad from Km.
102 Assam 163.400 to Km. 205.000 (Balance Portion of Guwahati Bypass, Package NH-27 41.6 Item Rate 4L 15/04/2024 D.C Ajmera
no. AS-03 & AS-20) of NH 37
Operation & Maintenance work from Km. 162.620 to Km. 278.685 NH
103 Assam NH-27 116.065 EPC 4L 19/01/2024 Basanta Kumar Kakati
37 (New NH 27) in the state of Assam.
Maintenance of Hathikali to Narimbanglo section of NH-54E from Km.
104 Assam 83+400 to Km 140+700 (New NH-27) in the State of Assam on 27 57.3 OMT 4L 14/03/2024 D.C Ajmera
Performance Based Maintenance Contract (PMBC)
Routine Maintenance work from Km. 1065.000 to Km. 1124.514 of
105 Assam Package no. AS-05,AS-04 and AS-28 of NH 31 in the state of Assam NH-31 59.514 EPC 4L 20/03/2024 Basanta Kumar Kakati
(Length 59.514)
Varanasi - Mohania (GTRIP/5; Package - IV A): 4L of existing 2L section Progressive - Sunway Construction
106 Bihar 2 76 EPC 4L 31/03/2002
from km. 65 to km. 317 of NH-2 in UP and Bihar on NH-2 Berhad
Mohania - Sasaram (TNHP/5; Package - IV B) (4L of existing 2L section LG Engineering & Construction
107 Bihar 2 45 EPC 4L 12/01/2001
from km. 65 to km. 110 on NH-2) Corporation
Sasaram - Dehri-on-Sone (GTRIP/6; Package - IV C) 4L of existing 2L
108 Bihar 2 30 EPC 4L 31/03/2002 Somdatt Builders - NCC (JV)
section from km. 110 to km. 140 on NH-2
Dehri-on-Sone to Aurangabad (TNHP/6; Package - IV D) 4L of existing Ssang Yong - Oriental Structural
109 Bihar 2 40 EPC 4L 12/01/2001
2L section from km. 140 to km. 180 on NH-2 Engineers (JV)
Aurangabad - Barachatti (TNHP/7; Package - V A) 4L of existing 2L Oriental Structural Engineers Pvt. Ltd.-
110 Bihar 2 60 EPC 4L 31/07/2001
section from km. 180 to km. 240 on NH-2 (TNHP/7; Package - V A) Gammon India Ltd (JV)
111 Bihar Balance work of 4 laning of Gorakpur -Gopalganj 28 41.08 Item Rate 4L PS 30/06/2015 Punj Lloyd Infrastructue Ltd.
Strengthening of UP border - Devapur - Kotwa from Km 360.915 to Km
112 Bihar 27 79.085 Item Rate 4L 11/06/2021 Anmol Associates
440.00 of NH - 27
Overlaying/maintenance work of Gopalganj-Muzaffarpur from km
113 Bihar 28 38 OMT 4L
402.00 to km. 440.00 of NH-28
114 Bihar Kotwa (Motihari) – Mehsi - Muzaffarpur 27 80 EPC 4L 20/10/2020 Cube Highway
Kotwa (Motihari) – Mehsi - Muzaffarpur from km. 440.000 to km.
115 Bihar 27 80 TOT 4L Kotwa Muzaffarpur Tollway Limited
520.000 of NH-27 (Old NH-28) under TOT Bundle-3
4 Lane Bridge Across River Kosi including Approaches km 155 - km 165 Kosi Bridge Infrastructure Company
116 Bihar 27 10.64 BOT Annuity 4L 04/04/2007
of Nh-57 (BR-5) Limited
Muzaffarpur-Darbhanga-Purnea Section from km. 0.00 to km. 148.55
117 Bihar 27 277.053 OMT 4L SMS-AABS India Tollway Pvt Ltd
& km.159.357 to km. 287.86 of NH-57 (Old) (OMT Pkg No. 20)
Four Laning of Purnea Forbesganj (BR-1) - Gulabbagh Junction to End
118 Bihar of Araria Town from km. 310.00 to km. 267.500 (Contract Package - C- 57 42.5 EPC 4L 23/06/2005 Progressive Constructions Ltd.
II/BR-1)
Four Laning of Purnea Forbesganj (BR-2) - Start of Araria Town (km.
119 Bihar 57 37.5 EPC 4L 23/06/2005 Progressive Constructions Ltd.
267.500) to km. 230.00 (Contract Package - C-II/BR-2)
Forbesganj - Simarahi (BR-3) from km. 230.00 to km. 190.00 on East- Gammon Engineers & Contractors
120 Bihar 57 40 EPC 4L 08/04/2006
West Corridor (Contract Package - c- II / BR-3) Pvt. Ltd.

Page 5 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Simrahi to Ring bund (missing link) (BR-4) from km. 159.357 to km.
121 Bihar 57 15.03 Item Rate 4L 30/03/2006 Simplex Infrastructure Limited
174.382 (Contract Package - C-II/BR-4)
122 Bihar 2nd Flyover (LCW) Parallel to Existing Flyover in Kishanganj Town 31 3.18 EPC 2L 30/06/2018 Bihar Rajya Pul Nirman Nigam Ltd.
4L of Purnea - Dalkhola Section from Km. 410.700 to Km. 447.000 of
123 Bihar 27 36.3 Item Rate 4L 29/12/1999 R. K. Jain Infra Projects Pvt. Ltd.
Old NH-31
4L of Galgalia - Bahadurganj section from Km 0.000 to Km 49.000
124 Bihar 327E 49 HAM 4L 10/01/2022 GR Infra Projects Ltd
(Package-I) of NH327E
4L of Hajipur-Muzaffarpur Section of the existing NH-77 from Km.
125 Bihar 0+000 (Ramashish Chowk) to Km. 46+300 and new bypass starting at 22 63.17 BOT Annuity 4L 12/08/2010 Gammon Infrastructrure Projects Ltd.
Km. 46+300 and connecting NH-28 of E-W Corridor at Km. 515+045

Construction of balance work of Hajipur – Muzaffarupr section of NH-


126 Bihar 22 1.2 Item Rate 4L 11/02/2020 SRSC INFRA PRIVATE LIMITED
77 (New NH-22) from Ch. 9.400 to Ch. 10.600 in Sarai Market
Widening of left out portion of Hajipur - Muzaffarpur section of NH-77
127 Bihar 22 1.9 Item Rate 4L 22/06/2020 JMC Projects (India) Ltd.
from 46+300 to 48+200 (Madhoul to Ramdayalu)
128 Bihar Ara - Mohania (Pkg-I) 319 54.75 EPC 4L 16/01/2021 Ashoka Buildcon Limited
129 Bihar 2 laning with PS of Muzaffarpur-Barauni 122 108 BOT Toll 2L PS 08/07/2012 KNR Constructions Limited
4L of Forbesganj to Jogbani Section from Km. 0.000 to Km. 9.260 (IPC
130 Bihar 57A 9.26 EPC 4L 18/04/2016 JKM Infra Projects Ltd.
at Jogbani) of NH-57A
131 Bihar Patna Bakhtiyarpur section of NH-30 from km. 181.300 to km. 231.950 922 50.45 BOT Toll 4L 26/09/2011 BSC - C&C (JV)
132 Bihar Simaria (Km. 206.050) to Khagaria (Km. 266.282) 31 60.23 EPC 4L 05/10/2016 Punj Lloyd Infrastructue Ltd.
133 Bihar 2L PS of Khagaria - Purnea from km. 270.00 to km. 410.00 of NH-31 31 140 BOT Annuity 2L PS 05/10/2011 Punj Lloyd Infrastructue Ltd.
134 Bihar Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630 20 47.225 HAM 4L 28/04/2021 Gawar Construction Ltd
Chhapra - Rewaghat - Muzaffarpur from Km 1.300 to Km 74.200 and
135 Bihar 722 73.07 EPC 2L PS 05/04/2016 R. K. Jain Infra Projects Pvt. Ltd.
Km. 1.300 to Km. 7
136 Bihar 2L of Mokama-Munger from km. 1.43 to km. 70.00 of NH-80 80 68.57 BOT Annuity 2L 15/05/2011 BSCPL -C & C Consortium
137 Bihar Chhapra - Gopalganj section 531 94.26 EPC 2L PS 07/12/2015 G R Infraprojects Limited
138 Bihar Koilwar Bhojpur from km. 137.375 of NH- 30 to km. 27.37 of NH-84 922 43.85 EPC 4L PS 04/07/2017 PNC-SPSCPL (JV)
139 Bihar Bhojpur Buxar section of NH-84 from km.27.37 to km. 75.00 922 47.9 EPC 4L PS 18/04/2018 PNC-SPSCPL (JV)
140 Bihar Muzaffarpur - Sonbarsa Section of NH-77 from km 2.800 to km 89.000 77 86.2 BOT Annuity 2L PS 30/05/2011 BSC - C&C (JV)
2L PS of Biharsharif - Barbigha - Mokama from km. 94.478 to
141 Bihar 82 54.575 EPC 2L PS 06/10/2017 G R Infraprojects Limited
km.149.053 of NH-82
4L from km. 34.600 to km. 79.970 & 2LPS from km. 79.970 to km.
142 Bihar 131A 49 HAM 4L 18/03/2021 Dilip Buildcon Ltd.
82.000 of Narenpur - Purnea Section of NH-131A
Construction of Approach Road to Rail-cum- Road Bridge across river
143 Bihar 333B 14.52 EPC 2L 01/12/2018 S.P. Singla Construction Pvt. Ltd
Ganga at Munger Ghat ( NH-333 B)
Strengthening & Improvement of NH-31 (new NH 27) from Km
144 Bihar, West Bengal 447.000 To 551.000 Daikhola-Islampur-Ghoshpukur Section (Excluding 31 95 Item Rate 4L 23/01/2024 S&P Infrastructure Developers(P) Ltd
Islampur Bypass) in the State of West Bengal on O&M basis

145 Chhattisgarh End of Durg Bypass - MH/CG Border from km. 322.40 to km. 405.00 53 82.6 BOT Toll 4L 22/07/2008 Ashoka Buildcon Limited
146 Chhattisgarh Durg Bypass 53 18 BOT Toll 4L 01/04/2011 SMS
147 Chhattisgarh Raipur - Aurang from km. 239.00 to km. 281.00 53 43.46 BOT Toll 4L 11/04/2006 DSC
4L of Odisha/Chhattisgarh border-Aurang Section from Km.88.000 to
148 Chhattisgarh 53 151 BOT Toll 4L 15/02/2013 BSCPL Aurang Tollway Ltd
Km. 239.000 of NH-6
149 Chhattisgarh 4/6 Laning of Raipur-Simga (Pkg-I) from km. 0.00 to km. 48.58 30 48.58 EPC 4L/6L 21/04/2016 Punj Lloyd Infrastructue Ltd.
150 Chhattisgarh Simga (km 48.580) to Sargaon (km. 91.026) 130 42.45 EPC 4L 05/05/2016 Larsen & Toubro Ltd.

Page 6 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Sargaon (91.026) to Bilaspur (126.525) of NH-200 (New 130) in
151 Chhattisgarh 130 35.49 EPC 4L 21/04/2016 Dilip Buildcon Ltd.
Chhattisgarh
152 Chhattisgarh Raipur (Km 10.200) to Kodebod (Km 43.400) of NH - 30 in Chhattisgarh 30 33.2 EPC 4L 11/03/2017 GKC Projects Ltd.
153 Chhattisgarh Kodebod (Km 43.400) to Dhamtari (Km 82.209) 30 38.81 EPC 4L 11/03/2017 GKC Projects Ltd.
Adani Enterprises Ltd. and Prakash
154 Chhattisgarh Bilaspur-Pathrapalli from km. 0.00 to km. 53.30 130 53.3 HAM 4L PS 08/03/2019 Asphaltings & Toll Highways (India)
Ltd.
4 Laning with PS of Pathrapalli-Katghora km 53.3 to km 92.6 (Pkg-II of
155 Chhattisgarh 130 39.3 HAM 4L 04/12/2020 Dilip Buildcon Ltd.
Bilaspur Kathghora)
2L PS of Dhamtari - Kanker (Package - 1) from Km 81.500 to Km 130.00
156 Chhattisgarh 30 48.414 EPC 2L PS 24/03/2015 Barbrik - Dee Vee (JV)
of Old NH-43
2L PS of Bedma - Dahikhonga (Package - 3) Km 180.000 to Km 241.00
157 Chhattisgarh 30 61.17 EPC 2L PS 24/03/2015 Ramky - Barbrik (JV)
of Old NH-43
2L PS of Dahikhonga - Jagdalpur (Package - 4) Km 241.000 to Km
158 Chhattisgarh 30 56.9 EPC 2L PS 24/03/2015 Barbrik - Dee Vee (JV)
298.00 of Old NH-43
Output and performance based maintenance of road from
Rehabilitation and upgradation of NH 43 (New NH-30) from Dhamtari-
159 Chhattisgarh 30 166.5 EPC 2L 04/08/2023 Barbrik Project Limited
Kanker(81.500 to 130.00) , Bedma-Dahikonga (180.000 to 241.000)
and Dahikonga-Jagdalpur (241.000 to 298.000) section to 2L PS
Package-I- 6 laning of Delhi-Meerut Expressway and 8 laning of NH-24
160 Delhi from NH-24-Ring Road T-Junction to U.P. Gate (Km. 0.000 to Km. 9 8.72 HAM 6L 28/11/2016 Welspun Enterprises Ltd.
8.360)
Package-II of Delhi-Meerut Expressway - 6L from Km 0.000 to Km
161 Delhi 27.740 and 6/8 L from existing Km. 8.36 to existing Km. 27.74 of Old 24 19.38 HAM 6L 06/11/2017 APCO Infratech Pvt. Ltd.
NH-24 (Delhi-UP Border to Dasna)
Package-III- Delhi-Meerut Expressway- 6-laning of NH-24 from existing
162 Delhi 24 22.27 HAM 6L 19/12/2016 APCO Infratech Pvt. Ltd.
Km. 27.740 to existing Km. 49.346 (Dasna to Hapur)
163 Delhi Package-IV- Delhi Meerut Expressway Km.27.740 of NH-24 - Km.51.975 24 31.77 EPC 6L 27/02/2018 G R Infraprojects Limited
Access Controlled Highway of Delhi-Gurgaon section of NH-48 from
164 Delhi 48 28 BOT Toll 6L/8L 30/04/2003 Jaypee DSC Ventures Limited
km 14.30 to km 42.00
Improvement of T junction at Dhaula Kuan Metro Station & near
165 Delhi Defence Area including widening of National Highway from km. 11.06 48 2.78 EPC 8L 23/03/2018 Ram Kumar Contractor
to km. 13.84
166 Delhi Slip roads for Airport (T3), Airport (T1), Atlas chowk and Shyam chowk 48 27.76 EPC 2L 21/09/2018 Mahavir Prasad Gupta & Sons
Fixing of Paver Block from Km. 14.300 (RTR) to Km. 24.000 Delhi-
167 Delhi 48 9.7 EPC 6L/8L 22/01/2019 Atlas Construction Pvt. Ltd.
Gurgaon Border on NH-8 (New NH-48)
Development of 6L UER II [Package - III] (Nangloi - Najafgarh Road till Gawar Construction Ltd. - E5
168 Delhi 344M 9.66 EPC 6L 28/10/2021
Sector 24 Dwarka) from km. 28.45 to km. 38.111 Infrastructure Pvt. Ltd (JV)
Additional Works under 6L of Badarpur Elevated Highway on Delhi -
169 Delhi 19 4.4 EPC 6L 14/01/2020 Dynasty Promoters Pvt. Ltd.
Agra Section from km. 16.100 to km. 20.500
O&M of 6L of Badarpur Elevated Highway on Delhi - Agra Section from
170 Delhi 19 4.4 Item Rate 6L 24/01/2020 Krishna Constructions.
km. 16.100 to km. 20.500
Square Pipe Fencing in Six Laning of Delhi - Agra section from Km.
171 Delhi 20.500 to Km. 36.150 & Construction of Boundary Wall and Building 2 15.65 Item Rate 6L 15/11/2019 Rakesh Kumar
work in NHAI Admn. Block in Faridabad.
Construction of Residential Accommodation for NHAI staff at Pocket B-
172 Delhi NA 0 Item Rate TBD
5, Sector-17, Dwarka, New Delhi
173 Goa Verna Junction to Varunpuri Junction 566 13 EPC 4L 29/04/2002 Jogendra Chodhary
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-29)
174 Gujarat NE-4 22.5 EPC 8L 16/04/2021 PNC Infratech Limited
(Ch.780+920 to Ch.803+420) [Bhamaiya Village to Baletiya Village]

Page 7 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Vadodara Mumbai Expressway (Padra to Vadodara) (Phase IA - Pkg I)
175 Gujarat NE-4 23.74 HAM 8L 18/01/2019 IRB Infrastructure Developers Ltd.
[Km 355.00 to Km 378.740]
Vadodara Mumbai Expressway (Sanpa to Padra) (Phase IA - Pkg II) [Km
176 Gujarat NE-4 32 HAM 8L 31/01/2019 IRCON International Limited
323.00 to Km 355.00]
177 Gujarat Vadodara Mumbai Expressway (Manubar to Sanpa) (Phase IA - Pkg III) TBD 31 HAM 8L 08/03/2019 Patel Infrastructure Limited
Vadodara Mumbai Expressway (Ankleshwar to Manubar) (Phase IA- Ashoka Ankleshwar Manubar
178 Gujarat TBD 13 HAM 8L 10/12/2018
Pkg IV) Expressway Private Limited
Four Laning of Ahmedabad-Vadodara Expressway from km.0.000 to
179 Gujarat NE-I 93.3 BOT Toll 4L 01/01/2013 IRB Infrastructure Developers Ltd.
km 93.302
180 Gujarat 4L of Shamla ji to Motachilodha 48 93 EPC 4L 01/04/2000 Mohandas V Rajani
Repair & Maintenance of Shamlaji-Himmatnagar from Km 447.385 to
181 Gujarat 48 93.21 Item Rate 6L 29/01/2022 Roadlink Infratech Pvt. Ltd.
Km 540.595 section of NH-48
6L of Chiloda-Naroda section from Km. 540.595 to Km. 555.595 of NH-
182 Gujarat 08 15.31 EPC 6L 11/05/2017 KCC Buildcon Pvt. Ltd.
8(Package-VII)
6 Laning of Ahmedabad - Vadodara Section from km 6.400 to km
183 Gujarat 48 102 BOT Toll 6L 01/01/2013 IRB Infrastructure Developers Ltd.
108.700
Operations of Way Side Amenities at Km. 23.00 (RHS) of Ahmedabad -
184 Gujarat 48 0 OMT 6L
Vadodra Expressway
Operations of Way Side Amenities at Km. 78.00 (LHS) of Ahmedabad -
185 Gujarat 48 0 OMT 6L
Vadodra Expressway
Improvement Works at Dumad Junction at Merging of Ahmedabad
186 Gujarat Vadodara Section of NH-48, Ahmedabad Vadodara NE-1 & Sama-Savli 48 2.69 EPC 6L 21/12/2021 Apex Tarmac Pvt. Ltd.
Road
One time improvement and Operation and Maintenance of the toilet
blocks constructed at the toll plazas located on Ahmedabad Vadodara Akhil Pariyavaran Evam Gramya Vikas
187 Gujarat 48 102.3 Item Rate Others 08/02/2023
Expressway NE 1 and Ahmedabad Vadodara section of NH 48 under Sansthan
the Swachchh Bharat Mission
Six laning of Vadodara-Bharuch Section from km 108.700 to km
188 Gujarat 48 83.3 BOT Toll 6L 30/01/2007 Larsen & Toubro Ltd.
192.000
Operations & Maintenance of Vadodara – Bharuch from Km 108.700
189 Gujarat 48 83.3 Item Rate 6L 18/05/2022 A. S. Patel
to 192.000 Section of NH-48
190 Gujarat Bharuch - Surat from km. 198.00 to km. 263.00 (Package BOT -II) 48 65.4 BOT Toll 4L/6L 14/03/2011 IDDA Infrastructure Pvt Ltd
Short term improvement and routine maintenance of Surat - Bharuch
191 Gujarat 48 65.3 OMT 4L/6L 18/05/2022 A. S. Patel
from Km 198.700 to Km 263.000 Section of NH-48
Maintenance works and activities on section from Bharuch to Surat
192 Gujarat 48 65 PBMC 6L 10/03/2024 Shiwalay Infra Projects Pvt Ltd
(km. 198.000 to km. 263.000) of NH-48 in the state of Gujarat
193 Gujarat Narmada Bridge (Vadodara-Surat Section) 48 6.75 EPC 4L/6L 03/03/2014 Larsen & Toubro Ltd.
6L of km. 192.00 to km. 198.00 between Vadodara - Surat section of
194 Gujarat 48 6 EPC 6L 03/03/2014 Larsen & Toubro Ltd.
NH-48 including 4L extra dosed Bridge across Narmada

Repair & Maintenance on 2nd Narmada Bridge with its approaches


195 Gujarat 48 1.34 Item Rate 2L 07/10/2020 J M Shah
from Km 192.000 to Km 198.000 of NH-8 (New NH-48)
6L of Dahisar - Surat Section of Old NH-8 from km 263.000 to km
196 Gujarat 48 239 BOT Toll 6L 20/02/2009 IRB Infrastructure Developers Ltd.
502.000
Strengthening of Surat - Dahisar section from Km.263.000 to
197 Gujarat 48 118 Item Rate 6L 18/06/2022 R. K. Jain Infra Projects Pvt. Ltd.
Km.381.000 on NH-48
Strengthening and major maintenance work from Km. 263.000 to Km.
198 Gujarat 48 118 EPC 6L 15/03/2024 Skylark Infra Engineering Pvt. Ltd.
381.000 of NH-48 (from Surat to Vapi section)
4 Laning of Surat – Manor Pkg-I (Chalthan – Atul) from km. 263.400 to JV of SKEC of Korea and Dodsal & Co.
199 Gujarat 8 79.6 EPC 4L 01/11/2000
km. 343.00 of NH-8 (Mumbai)

Page 8 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
LG Engineering & Construction
4 Laning of Surat – Manor Pkg-II (Atul - Kajali) from km. 343.00 to km.
200 Gujarat 8 38.6 EPC 4L 01/11/2000 Corporation (Korea) and Patel
381.60 of NH-8
Engineering Company
Rehabilitation and upgradation of Surat-Manor Section from Km
201 Gujarat 48 79.6 EPC 4L
263.4000 to Km 343.000 of NH-8 (New NH-48)
Short term Improvement and Routine Maintenance of Porbandar -
202 Gujarat 27 115.64 EPC 4L 26/04/2018 Safeway Concesssions Pvt Ltd.
Bhiladi - Jetpur from km. 01.96 to km. 117.60 of Old NH- 8B
Porbandar - Bhiladi - Jetpur from km. 01.96 to km. 117.00 under TOT
203 Gujarat 8B 115.64 TOT 4L 11/02/2005 Safeway Concesssions Pvt Ltd.
Bundle - 1
4L of Porbandar - Bhiladi from km. 02.00 to km. 52.50 of Old NH-8B Longjian Road and Bridge Road Ltd.
204 Gujarat 27 50.5 EPC 4L 21/01/2005
(Contract Pkg-EW - I) Co.
4L of Bhiladi - Jetpur from km. 52.50 to km. 117.00 of Old NH-8B
205 Gujarat 27 64.5 EPC 4L 28/12/2004 Limak Soma
(Contract Pkg-EW - II)
206 Gujarat Gondal Chokdi Flyover at Rajkot 27 1.5 EPC 6L 04/01/2019 Vidya InfraBuilt Pvt. Ltd.
Providing long term Improvement to identified 7 Black spot at isolated
207 Gujarat locations on 4L Jetpur - Gondal -Rajkot section from Km. 117.600 to 27 4 EPC 4L 18/08/2016 Gawar Construction Ltd
185.000 on NH 8B (New NH 27)
Short term Improvement and Routine Maintenance of 4L Jetpur Kalthia Engineering & Construction
208 Gujarat 27 67.4 Item Rate 4L 08/04/2022
–Gondal –Rajkot Section From Km.117.600 to Km. 185.000 of NH-27 Ltd.
209 Gujarat Bamanbore - Garamore from 182.6 km. to 254.54 km. 27 72 EPC 4L 01/04/2000 DIC-NCC
Bamanbore - Garamore from 182.6 km. to 254.54 km. under TOT
210 Gujarat 8A 71.94 TOT 4L
Bundle - 1
211 Gujarat Garamore - Samakhiyali section from km 254.54 - km 306.00 27 51.46 EPC 4L 29/08/2018 Garamore Tollway Pvt. Ltd.
Garamore - Samakhiyali section from km 254.54 - km 306.00 under
212 Gujarat TBD 51.46 TOT 4L 29/08/2018 Garamore Tollway Pvt. Ltd.
TOT Bundle - 1
213 Gujarat Palanpur - Radhanpur - Samakhiyali (OMT-1) 27 261 Item Rate 4L 29/08/2019 B.D. Sorathia
4L Elevated Corridor in Deesa Town from km. 565.850 to km. 569.600
214 Gujarat 27 3.75 EPC 4L 03/01/2019 Rachana Construction Co.
of NH-27
4L of Garamore-Gagodhar Road Section of NH-8A & NH-15 from Km Daelim Industrial Co Ltd. - Nagarjuna
215 Gujarat 15 90.3 EPC 4L 12/02/2005
254.000 to Km 308.000 and from Km 281.300 to Km 245.000 Construction Co. (JV)
4L of Gagodhar-Radhanpur Section from Km 138.800 to Km 245.000 of
216 Gujarat 15 106.2 EPC 4L 12/02/2005 JILIN - Sadbhav (JV)
NH-15
4L of Radhanpur - Deesa Section from Km 372.600 to Km 458.000 of Daelim Industrial Co Ltd. - Nagarjuna
217 Gujarat 15 85.4 EPC 4L 12/02/2005
NH-14 Construction Co. (JV)
4L of Aburoad-Palanpur Section of NH-14 from Km 340.000 to Km Dineshchandra R. Agrawal Infracon
218 Gujarat 15 90.3 EPC 4L 04/01/2001
350.000 Pvt. Ltd.
4L of Palanpur-Deesa Section of NH-14 from Km 350.000 to Km Dineshchandra R. Agrawal Infracon
219 Gujarat 15 22 EPC 4L 30/08/2001
372.700 Pvt. Ltd.
Short term Improvement and routine Maintenance of Samakhiyali-
220 Gujarat 27 261.3 EPC 4L 13/09/2021 Shiva Build Tech
Radhanpur-Palanpur from Km.339.700 to Km.601.000 of NH-27
Tolling, Operation, Maintenance & Transfer of Palanpur-Radhanpur-
221 Gujarat Samakhiyali section of NH-27 from Km. 536+000 to Km. 430+100 in 27 105.9 TOT 4L PS 15/04/2022 D.P. Jain & Co. Infrastructure Pvt. Ltd.
the state of Gujarat (TOT Bundle 5A2)
Strengthening work under TOT/InvIT of Palanpur-Radhanpur-
222 Gujarat Samakhiyali section of NH-27 from Km. 589+600 to Km. 536+000 (TOT 27 53.6 TOT 4L PS 25/11/2021 Adani Road Transport Ltd.
Bundle 5A1)
223 Gujarat Halvad Cross Road 27 1 EPC 6L 23/02/2017 Gawar Construction Ltd
Improvement of Samakhiyali-Santalpur section of Nh-27 (from
224 Gujarat Km.339.700 to Km. 430.100 and Km 589.600 to Km. 601.000) in the 101.8 Item Rate 4L PS 06/09/2022 V.P. Sethi Construction
sate of Gujarat
Palanpur/ Khemana - Abu Road - Swaroopganj from km. 340.00 to km.
225 Gujarat 27 76 BOT Annuity 4L 24/09/2006 Larsen & Toubro Ltd.
264.00

Page 9 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Sanchore - Santalpur from km 4.888 - km 35.000 of NH-754K (AJ-RGBS- Ravi Infrabuild Projects Private
226 Gujarat 754K 30.11 EPC 6L 02/06/2021
Package-1) Limited
Sanchore - Santalpur from km 35.000 - km 67.000 of NH-754K (AJ- Ravi Infrabuild Projects Private
227 Gujarat 754K 32 EPC 6L 19/02/2021
RGBS-Package-2) Limited
4L of Dhrol-Bhadra-Patiya section from 0.000 to km 13.600 and
228 Gujarat 151A 50.416 HAM 4L 28/10/2021 Dilip Buildcon Ltd.
Bhadra Patiya - Pipaliya section from 73.00 to km 24.00 of NH-151A

229 Gujarat Samakhiyali to Gandhidham section km 306.0 to km 362.160 of NH-8A 41 56 BOT Toll 6L 11/09/2010 Larsen & Toubro Ltd.
Four Laning of NH-8A from Padana (km. 346.00) to Gandhidham (km.
230 Gujarat 357.00) and strengthening of existing 4 Lanes including drainage 8A 16.16 Item Rate 4L 16/04/1999 Agrawal -Sadbhav - Backbone (JV)
improvement from km. 357.00 to km. 362.16 (Pkg - III)
231 Gujarat 4L of Ahmedabad-Godhra from km. 04.200 to km. 122.420 of NH-59 59 117.6 BOT Toll 4L 27/12/2010 Essel Infraprojects Ltd

Repair and Maintenance of Ahmedabad-Godhra section from Km.


232 Gujarat 47 45 Item Rate 4L 08/06/2021 Tacon Infrastructure Pvt. Ltd.
04.200 to Km. 122.420 with overlay work at several locations of NH-47
Strengthening of Ahmedabad – Godhra section of NH-47 in the State
233 Gujarat 47 72.571 Item Rate 4L 21/10/2022 Shiwalay Infra Projects Pvt Ltd
of Gujarat
Repair and Rehabilitation of Bridges located at km58.569 (from
km58.569 to km58.696), km86.500 (from km86.500 to km86.620) and Rehabilitation Engineering (prop.
234 Gujarat 47 117.6 Item Rate 4L 22/10/2022
km99.575(RHS) (from km99.575 to km99.687) on 04 lane Ahmedabad Hemangini Bharatchandra Shewale)
– Godhra section of NH-47
Annual Maintenance and Incident Management of Ahmedabad -
235 Gujarat Godhra Section from Km. 4.200 to Km.122.420 on NH-47 in the State 47 117.6 Item Rate 4L 17/04/2023 Roadlink Infratech Pvt. Ltd.
of Gujarat
4L of Godhra to Gujarat/M.P. Border Section from Km. 129.000 to Km.
236 Gujarat 47 87.1 BOT Toll 4L 01/03/2011 BSCPL Infrastructure Ltd.
215.900 of NH-47 (Old NH-59)
237 Gujarat Gujarat / Maharashtra Border - Surat - Hazira Port 53 131.5 BOT Toll 4L/6L 30/03/2010 Isolux-Soma Consortium (JV)
Construction of one 6L VUP at km 120.275 on Surat Hazira Port
238 Gujarat 53 1.1 EPC 4L 13/09/2019 APCO Infratech Pvt. Ltd.
Section (Stand Alone EPC Contract)
Maintenance of km93+880 to km110+851 (Pipli – Dholera section) and
239 Gujarat km 129+800 to km 136+000 (Bavaliyari – Adhelai section) of SH-06 NH-751 23.171 Item Rate 2L 13/03/2024 Shivam murlidhar deore
(now declared NH-751) in the state of Gujarat.
Kalthia Engineering & Construction
240 Gujarat Pipli Bhavnagar-Package 1 from km 136.025 to km 169.328 751 33.31 HAM 4L 05/02/2019
Ltd. JP Iscon Pvt. Ltd. Consortium
Maintenance of existing road from Budhel Junction to Nari Circle from
241 Gujarat 51 10.75 Item Rate 2L 25/05/2022 Mohandas V Rajani
0.900 to Km 11.650 section of NH-51
Routine Maintenance of 2L Varsana Chokdi– Bhuj section from 0.000
242 Gujarat 341 59.75 Item Rate 4L 19/03/2021 Hardik Construction Company
Km to 54.680 Km & from 60.620 Km to 65.478 Km of NH-341
Bal. Work of Gandhidham (Kandla) to Mundra port section of NH8A
243 Gujarat 41 6.93 Item Rate 4L/6L 12/03/2020 Shiva Build Tech
(Extn.) between Km. 0.000 to Km. 71.400
Short term improvement and routine maintenance of 4L Gandhidham
244 Gujarat (Kandla)-Mundra port section from Km 0.00 to Km. 71.4 of NH-8A 8A (Extn.) 64.52 Item Rate 4L 22/11/2021 Laxmi Builders
(Extn.)
4L of Dwarka-Khambaliya-Devariya section from km 203.500 to km
245 Gujarat 151A 71.89 HAM 4L 08/02/2020 G R Infraprojects Limited
176.500 and from km 171.800 to km 125.000 of NH-151A
G R Infraprojects Limited & VINOD
246 Gujarat Porbandar-Dwarka (Package VIII) from km. 379.100 to km. 496.848 51 117.74 HAM 4L 12/02/2018
KUMAR AGRAWAL
One Time Improvement & Maintenance of Porbandar–Bypass road
247 Gujarat 51 18.9 Item Rate 2L 15/03/2022 Laxmi Builders
from Km.357.100 to Km.376.000 of NH-51

Page 10 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Providing lighting facility and safety grill on ROB cum fly over of
248 Gujarat Porbandar - Dwarka section at junction of NH-27 at Km. 2.550 and NH- 51 0 Item Rate 4L 04/03/2021 Current Infra Private Ltd
51 at Km. 369.200 near Narsang Tekri at Porbandar
Kalthia Engineering & Construction
249 Gujarat Gadu -Porbandar (Package VII) 51 91.67 HAM 2L PS 04/09/2017
Ltd.
Four Laning of Una to Kodinar from km. 180.478 to km. 221.610
250 Gujarat 8E 40.95 HAM 4L PS 09/02/2017 Sadbhav Engineering Pvt. Ltd.
(Package-V)
One Time Improvement and maintenance work of existing Una
251 Gujarat bypass, Nathal bypass, Simasi bypass and Dolasa bypass of Una- 51 40.95 Item Rate 2L 06/09/2022 Spiral Construction Corporation
Kodinar Section of NH-51(Old).
Agroh Infrastructre & Developer Pvt.
252 Gujarat Kagvadar - Una (Package-IV) 51 40.98 HAM 4L PS 20/03/2017
Ltd.
4L of Bhavnagar - Talaja (Package-I) from Km. 6.945 to Km. 54.990 of
253 Gujarat 51 48.05 HAM 4L PS 07/02/2017 Sadbhav Engineering Pvt. Ltd.
Old NH-8E
254 Gujarat Strengthening and Maintenance of Radhanpur-Patan section of NH-68 68 56.7 Item Rate 2L 27/04/2023 Jai Buildcon Pvt Ltd
255 Gujarat O&M of Gozaria-Prantij section of NH-68 68 37.385 Item Rate 2L 17/04/2023 Laxmi Builders
O&M of 4L of Jetpur- Somnath Section from Km 0.00 to Km 127.600 of
256 Gujarat 151 127 OMT 4L Mohandas V Rajani
Old NH-8D
257 Gujarat Junagadh Bypass 151 20.6 EPC 4L 03/04/2018 Gawar Construction Ltd
Strengthening of project from Maharashtra border-Sagbara-
258 Gujarat Dediapada-Netrang section of NH-753B from Km. 117.400 to Km. 753B 58 Item Rate 4L 27/06/2023 J M Shah
175.400 in the state of Gujarat
259 Gujarat, Rajasthan Maintenance work on section from Padhi -Dahod of NH-113 113 85.588 EPC 2L PS 01/05/2022 Mohandas V Rajani
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-01) (Ch. 0+000
260 Haryana to Ch. 18+461) [Sohna-Gurugram Road (NH-248A) near Alipur Village 148N 18.5 EPC 8L 13/09/2019 APCO Infratech Pvt. Ltd.
and ending before KMP Expressway]
Eastern Peripheral Expressway Package - I from km 1.000 to km 22.00
261 Haryana NE-II 21 EPC 6L 14/09/2015 Sadbhav Engineering Pvt. Ltd.
in the State of Haryana and Uttar Pradesh
Eastern Peripheral Expressway Package - VI from Km 114.000 to Km
262 Haryana NE-II 22 EPC 6L 14/09/2015 Gayatri Projects Limited
136.000 in the state of Haryana.
Monetization of Public Funded operational National Highway Projects NCR Eastern Peripheral Expressway
263 Haryana NE-II 135 TOT 6L 11/11/2022
under Tolling, Operation, Maintenance and Transfer (ToT) – Bundle-7 Pvt. Ltd.

264 Haryana Three Underpasses at Rajiv Chowk, Signature Tower and IFFCO Chowk 48 6.31 EPC 8L 01/12/2016 Gawar Construction Ltd
Under Ground U-turn near Ambience Mall and Elevated U-Turn near
265 Haryana Shankar Chowk from km. 23.66 to km. 24.446 & km. 25.684 to km. 48 2.78 EPC 4L 05/03/2019 Ram Kumar Contractor
26.123
Permanent Longitudinal Drain for disposal of Storm Water along Old
266 Haryana NH-8 from Rajiv Chowk to Kherki Dhaula Toll Plaza (except the project 48 5.49 EPC Others NKC Projects Private Limited
limits of Hero Honda Flyover)
267 Haryana Foot Over Bridge across NH-2 2 0 EPC 4L/MIP 07/03/2018 Atlas Construction Pvt. Ltd.
Additional Structures under Six Laning of Delhi-Agra section of NH-44 Gawar Construction Ltd. - E5
268 Haryana 44 0 EPC 6L 19/09/2019
in the State of Haryana between km. 34.0 and km. 93.00 Infrastructure Pvt. Ltd (JV)
269 Haryana Major Saraswati Bridge 44 0.51 EPC 6L 14/08/2018 Ram Kumar Contractor
O&M of 6L Panipat-Jalandhar section from Km. 96.000 to Km. 387.100
270 Haryana 44 291.1 Item Rate 6L 01/10/2021 Ceigall India Ltd.
of NH-44
Construction of balance works of FoBs of Panipat-Jalandhar section
271 Haryana 44 0.8 Item Rate 6L 16/11/2021 Dhingra Brothers (India)
from km. 96.000 to km. 387.100 on NH-44
Repair of Slip road (LHS) joining Kali Paltoon bridge at Km. 200.600
272 Haryana including dismantling and reconstruction of retaining wall at km. 44 0.3 Item Rate 6L 07/09/2021 Dhingra Brothers (India)
200.600 of NH-44

Page 11 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Construction of 05 Nos. steel Foot Over Bridge at various locations of
273 Haryana 44 1 Item Rate 6L 27/04/2021 Pawansut Infra Projects Pvt. Ltd
Panipat – Jalandhar section of NH-44
6L Panipat – Jalandhar Section for providing Highway Lighting work in
274 Haryana selected reaches and fixing of view cutter on PAP Flyover at Km. 44 291.1 Item Rate 6L 05/07/2021 Rajinder Infrastructure Private Limited
372.525 and Rama Mandi Flyover at Km.371.500.
275 Haryana Providing and fixing of Additional Signages 291.1 Item Rate 6L 07/05/2022 Vibgyor Industries
Avenue Plantation/Median Plantation work in Panipat-Jalandhar
276 Haryana 175.1 Item Rate 6L 22/07/2022 Amrinder Singh Contractor
section of NH-01 (New NH-44) in the State of Punjab
Chaudhary Construction Company
277 Haryana Rectification of Rain Cuts NH-44 (Old NH-1) 291.1 Item Rate 6L 04/05/2022
Pvt. Ltd.
Panipat Elevated Flyover from km. 86.00 to km. 96.00 on NH-44 (old
278 Haryana 44 10 BOT Toll 6L 23/01/2006 Larsen & Toubro Ltd.
NH-1)
8L of Mukarba Chowk in Delhi to Panipat in Haryana from km 15.500
279 Haryana 44 70.7 BOT Toll 8L 08/06/2020 Welspun Enterprises Ltd.
to km 86.000 of NH-44 (Old NH-1)
6L Access Controlled Highway from Jn. with Sector 62/65 dividing road
Dineshchandra R. Agrawal Infracon
280 Haryana on Faridabad - Ballabhgarh Bypass to Jn. with KMP Expressway with 148NA 26.06 HAM 6L 14/05/2021
Pvt. Ltd.
NH-148NA from km. 33.00 to km. 59.063
281 Haryana Gurgaon Sohna Pkg-I (Km.2.74 to Km.11.682) 248A 8.94 HAM 6L 01/02/2019 Oriental Structural Engineers Pvt. Ltd.
6L of Gurgaon Sohna Pkg-II from existing Km.11.682 to existing
282 Haryana 248A 12.72 HAM 6L 30/01/2019 H.G. Infra Engineering Limited
km.24.40
Punjab/ Haryana border Jind section from km 238.695 to km 307.000 Dineshchandra R. Agrawal Infracon
283 Haryana 352 70.17 EPC 4L PS 05/06/2017
of NH 71 Pvt. Ltd.
Jind-Gohana road from Design Km.0 000 to Km. 50 505 of NH-352A
284 Haryana 352A 50.51 EPC 2L PS 11/09/2018 Gawar Construction Ltd
under NH (O)
JiangXi Construction Engineering
Ismailabad - Narnaul (Pkg- 01) (Ch. 0+000 to Ch. 23+000) [Ismailabad
285 Haryana 152D 23 EPC 6L 04/02/2020 (Group) Corporation Ltd. - CEIGALL -
to Junction with Karnal-Pehowa road (SH-9) near Dhand]
Shiv Build India Pvt. Ltd. (JV)
Ismailabad - Narnaul (Pkg- 02) (Ch. 23+000 to 56+000) [Junction with
286 Haryana Karnal-Pehowa road (SH-9) near Dhand village to Junction with Kaithal- 152D 33 EPC 6L 28/01/2020 Gawar Construction Ltd
Safidon (SH-11) road near Rajound]
Ismailabad - Narnaul (Pkg- 03) (Ch. 56+000 to 80+000) [Junction with
Galfar Engineering & Contracting
287 Haryana Kaithal-Safidon road (SH-11) near Rajound to Junction with Jind- 152D 24 EPC 6L 01/06/2020
(India) Pvt. Ltd.
Safidon road (SH-14) near Kheri village]
Ismailabad - Narnaul (Pkg- 04) (Ch. 80+000 to 108+000) [Junction with JiangXi Construction Engineering
288 Haryana Jind-Safidon road (SH-14) near Kheri village to Junction with NH-352 152D 28 EPC 6L 29/02/2020 (Group) Corporation Ltd. - Shiv Build
(Jind-Gohana section) near Julana] India Pvt. Ltd. (JV)
Ismailabad - Narnaul (Pkg- 05) (Ch. 108+000 to 131+000) [Junction
289 Haryana with NH-352 (Jind-Gohana) near Julana to Junction with NH-9 (Rohtak- 152D 23 EPC 6L 12/02/2020 Gawar Construction Ltd
Jind section) near Kharkara]
Ismailabad - Narnaul (Pkg- 06) (Ch. 131+000 to 165+000) [Junction
290 Haryana with NH-9 (Rohtak-Jind section) near Kharkara to Junction with NH- 152D 34 EPC 6L 01/08/2020 Gawar Construction Ltd
334B (Charkhi Dadri-Jhajjar section) near Charkhi Dadri]
Ismailabad - Narnaul (Pkg- 07) (Ch. 165+0 to 200+0) [Junction with NH-
Gawar Constructions Ltd. - Shivalaya
291 Haryana 334B (Charkhi Dadri-Jhajjar section) near Charkhi Dadri to Junction 152D 35 EPC 6L 25/06/2020
Construction Co. Pvt. Ltd.
with Rewari-Kanina road (SH-24) near Kanina]
Ismailabad - Narnaul (Pkg- 08) (Ch. 200+000 to 227+020) [Junction
292 Haryana 152D 27.02 EPC 6L 26/12/2019 Gawar Construction Ltd
with Rewari-Kanina road (SH-24) near Kanina to Narnaul]
Delhi/ Haryana Border to Rohtak section including Bahadurgarh and
293 Haryana 9 63.49 BOT Toll 4L/6L 03/05/2008 Era Infra Engineering Ltd.
Rohtak by-passes from km. 29.70 to km. 87.00
Delhi Haryana Border to Rohtak Section of NH-09 from Km. 29.650 to
294 Haryana 09 63.49 Item Rate 4L/6L 25/05/2022 Mahavir Prasad Gupta & Sons
Km. 93.140

Page 12 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Incident Management and O&M on 4/6-laning of Delhi/Haryana
295 Haryana Border to Rohtak section of NH-10 from Km. 29.650 to Km. 93.140 9 63.49 Item Rate 4L/6L 29/02/2024 ABS Construction Co.
including Bahadurgarh and Rohtak bypasses
4L of Rohtak - Hisar section from km. 87.00 to km. 170.00 on NH-10
296 Haryana including connecting link from km. 87.000 (NH-10) to km. 348.000 (NH- 9 98.81 BOT Toll 4L 26/12/2013 DS Enterprise
71)
Four laning of Rohtak to Hisar section of NH-10 (from km 87+000 to
km 170+000) including connecting link from Km 87+000 (NH-10) to Km
297 Haryana 9 98.82 EPC 4L 31/05/2022 DS Enterprise
348+000 (NH-71) on EPC mode under NHDP Phase III in the state of
Haryana
4 laning of Rohtak-Hisar section of NH-9 (Old NH-10) from Km. 87.000
298 Haryana to Km.170.000 including connection link from Km 87.000 (NH-10) to 09 98.81 Item Rate 4L PS 29/02/2024 ABS Construction Co.
Km 348.000 (NH-71)
299 Haryana Hisar - Dabwali (Pkg-I) (km 170.000 to km 227.000) 9 57 EPC 4L 09/08/2015 DS Enterprise
300 Haryana Operation and Maintenance of Hisar-Dabwali section of NH-9/10 9/10 144.66 Item Rate 4L PS 22/06/2022 DS Enterprise
Operation & maintenance of four laning of Hisar to Dabwali section of
301 Haryana NH-10 (new NH-09) from Km 170.000 to Km 314.660 with paved 09 144.66 Item Rate 4L PS 01/03/2024 ABS Construction Co.
shoulder in the state of Haryana
302 Haryana Hisar - Dabwali (Pkg-II) (km 227.000 to km 314.660) 9 88 EPC 4L 18/11/2015 DS Enterprise
303 Haryana Bhatinda Suratgarh 9 1 EPC 4L 24/06/2010 Gawar Construction Ltd
Paniyala Mor (NH-48 Jn) to Narnaul Sec. of NH-148B & Narnaul to
304 Haryana 11/148B 45.3 HAM 4L/6L 19/09/2019 Gawar Construction Ltd
Pacheri Kalan Sec. of NH-11 (Pkg-I)
Narnaul Bypass & Ateli Mandi to Narnaul section of NH-11 km 43.445
305 Haryana 11/148B 40.8 HAM 4L/6L 28/02/2020 H.G. Infra Engineering Limited
to km 56.900
Upgradation of 4 lane of Rewari-Ateli Mandi Section of NH-11 from
306 Haryana 11 31 HAM 4L 14/01/2020 H.G. Infra Engineering Limited
Km11.780 to Rewari to Ex. Km 43.445 near Ateli Mandi
307 Haryana Four Laning of Rewari Bypass Pkg-IV 11 14.4 HAM 4L 15/01/2021 H.G. Infra Engineering Limited
308 Haryana Rohtak-Panipat Section of NH-71A from Km. 0.00 to Km. 80.858 709 81 BOT Toll 4L 18/04/2011 DS Enterprise
Operation & Maintenance including Incident Management of Rohtak-
309 Haryana 709 80.858 Item Rate 4L PS 28/10/2023 ABS Construction Co.
Panipat section of NH-709 (Old NH-71A) from Km. 0.000 to Km. 80.858
Rohtak - Bawal section NH-71 from km.363.300 (Design km.363.300)
310 Haryana 352 84 BOT Toll 4L 10/05/2011 JMC Projects (India) Ltd.
to km.450.800 (design km.445.883)
311 Haryana Rohtak-Bawal Section of NH-71 (New NH-352) NH-71 83.655 Item Rate 4L 01/06/2022 Roadlink Infratech Pvt. Ltd.
Overlay, Routine Maintenance and Incident Management works on
four lane Rohtak-Bawal Section of NH-352 (Old NH-71) from Km.
312 Haryana 352 83.655 Item Rate 4L PS 01/11/2023 SKS Nirman Vaanijay Pvt. Ltd.
363.300 (intersection with NH-09) to Km. 446.955 (intersection with
NH-48)
Four Laning of Yamunanagar - Panchkula Section of Old NH 73 (Pkg - 3)
313 Haryana 7 & 344 19.2 EPC 4L 05/11/2016 Gawar Construction Ltd
from km. 160.357 to km. 179.248
Yamunanagar - Saha - Barwala - Panchkula Section from km 115.400 to
314 Haryana 32 41.79 EPC 4L 18/10/2015 A. S. Patel
km 157.192 (Package - 2)
Strengthening of Yamunanagar-Saha-Panchkula section of NH-73 (New
315 Haryana 344 41.792 Item Rate 4L PS 20/10/2023 Gaurav Singh
NH- 344) from km. 115.400 to km. 157.192 (Package-2)
Shiv Build India Pvt. Ltd. - Kaluwala
316 Haryana Saha - Shahbad from Km. 14.840 to Km. 31.760 444A 16.92 EPC 4L 29/01/2021
Construction Pvt Ltd. (JV)
Repair & Maintenance of Bhiwani - Hansi - Barwala Section from km.
317 Haryana NH-148B 23.2 Item Rate 2L 01/12/2023 SKS Nirman Vaanijay Pvt. Ltd.
126.270 to km 197.200 of NH -148B
Ambala (ch. 0.00 km ) to Pehowa (ch. 50.860 km) of Nh- 65 in Haryana Dilip Buildcon Ltd. - Varaha Infra
318 Haryana 65 50.86 EPC 4L 18/12/2015
( Package-1) Limited (JV)
Ambala (Km 50.860) to Pehowa (Km 95.383) of NH-65 in Haryana
319 Haryana 65 44.52 EPC 4L 09/01/2016 Sadbhav Engineering Pvt. Ltd.
(Package-2)

Page 13 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Construction of Service Road and RCC Drain from Km 60.550 to Km
320 Haryana 152 0.43 Item Rate Others 19/05/2023 Suraj Construction Company
60.980 BHS in village Bherian on Pehowa to Kaithal section of NH-152

321 Haryana Kaithal to Rajasthan border from Design Ch. Km. 0.50 to Km. 165.759 152&52 166 BOT Toll 4L PS 15/07/2015 IRB Infrastructure Developers Ltd.
Bhiwani - Mundhal - Jind from Km.6.875 to Km. 68.857 of NH-709A
322 Haryana 709A 61.98 EPC 2L PS 11/09/2018 Gawar Construction Ltd
(Package-I) under NH (O)
Jind - Karnal from junction with Narwana road (NH-352) at Subhash
323 Haryana Chowk to ITI Chowk (intersection with NH-1 of NH-709A from km. 709A 85.36 EPC 2L PS 11/09/2018 Gawar Construction Ltd
68.660 to km. 153.700
Strengthening and improvement of 2/4L PS of Jind-Karnal section from
324 Haryana 709A 13.37 EPC 2L/4L 11/02/2022 Kaluwala Construction Private Limited
km. 68.857 to km. 82.227 of NH-709A
325 Haryana Ambala - Saha 444A 14.84 EPC 4L 20/11/2019 Ceigall India Ltd.
Four Laning of Yamunanagar-Panchkula section of Old NH 73 from Km
326 Haryana 7 & 344 44.57 EPC 4L 18/11/2015 Sadbhav Engineering Pvt. Ltd.
70.830 to Km 115.400 (Pkg-I)
Routine Maintenance and Incident Management of Yamunanagar
327 Haryana Panchkula Highway Section of NH-344 (Old NH-73) from km. 70.830 to 344 86.36 Item Rate 4L PS 05/04/2023 A. S. Patel
km. 157.192 (Package-I and Package-II)
328 Haryana UP/HR Border - Sonepat - Jhajjar 334B 40.5 HAM 4L 22/01/2020 Gawar Construction Ltd
Four Laning of Rohna/ Hassangarh section from Km.44.800 to
329 Haryana 334B 35.45 HAM 4L 18/12/2018 Gawar Construction Ltd
km.80.250 (Package-2)
Ceigall India Ltd. - Shiv Buildtech Pvt.
330 Haryana Jhajjar - Loharu from Km.130.770 to Km. 228.630 334B 97.86 EPC 2L PS 17/12/2018
Ltd. (JV)
Improvement of section from km 173.050 to 177.770 (design ch.
331 Haryana 42.280 to 47.000) and from km 212.130 to 213.130 (design ch. 81.360 NH-334B 97.864 Item Rate 2L PS 15/05/2023 Suraj Construction Company
to 82.360) of Jhajjar-Loharu section of NH-334B
Zirakpur -Parwanoo from km.39.96 to km. 67.65 including Pinjore -
332 Haryana 5 27.59 BOT Toll 4L 28/02/2008 HEL
Kalka Parwanoo Bypass in the State of PB, HR, HP
Construction of Half VUP for Amravati Enclave at Km.53.550 on
333 Haryana 05 1 EPC 4L 09/09/2019 Singla constructions Limited
Zirakpur-Parwanoo section of NH-05
Providing access from service road to MCW (BHS)at Km.62.200 in
334 Haryana 05 1 Item Rate 4L PS 22/09/2022 Jassu Construction Company
village Tipra
335 Haryana Dharuhera-Bhiwadi 71B 8.6 Item Rate 4L 29/06/2018 Atlas Construction Pvt. Ltd.
Overlay work on Ambala-Kala Amb section of NH-72 from km 1.000 to
336 Haryana Km. 9.250, from 13.750 to km. 16.800, from 24.600 to km. 26.600 & 72 25.38 Item Rate 2L PS 02/02/2024 Jassu Construction Company
Patch work in km 26.600 to km 38.680
Overlay work on Jagadhri-Poanta Sahib old NH-73A (New NH-907)
337 Haryana form Km 2.500 to Km 5.000 and from Km. 5.000 to Km. 7.520 LHS and 907 11.255 Item Rate 2L PS 22/05/2023 Mahipal Construction Co.
from Km.9.400 to Km 15.635
Short term Operation & Maintenance (O&M) of Access Controlled
338 Haryana, Delhi Six/Eight lane Highway of Delhi-Gurugram Section of NH-48 from Km. 48 27.7 Item Rate 6L/8L 15/03/2023 Krishna Constructions.
14.300 (Rao Tula Ram Marg in Delhi) to Km. 42.000
Operation and Maintenance including Routine Maintenance and
339 Haryana, Punjab incident Management of 6L Panipat-Jalandhar Section of NH-44 from NH44 291.1 Item Rate 6L 12/11/2022 Rajinder Infrastructure Private Limited
KM 96.000 to 387.000
Operation and Maintenance of Six Laning of Panipat-Jalandhar Section
of NH-1 from KM 96.000 to 387.000 in state of Haryana and Punjab Chaudhary Construction Company
340 Haryana, Punjab 4,444 291.1 Item Rate 6L 05/01/2023
Major Maintenance Works Including construction of boundary walls Pvt. Ltd.
and rectification of WIM & SWB at Toll Plazas
Rectification/closure of unauthorized Median Cuts and unauthorized
341 Haryana, Punjab access from Main Carriage on Six laning of Panipat-Jalandhar old NH-1 44 9.05 Item Rate 6L 10/07/2023 Satish Aggarwal & Co
(New NH-44) from Km 96.000 to Km 387.100 (length-291.100 km)

Page 14 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Balance Work for Four laning of Kiratpur to Nerchowk section of NH-
342 Himachal Pradesh 21 from km. 0.00 to km. 12.75 & km. 158.50 to km. 182.215 (excluding 3, 154, 205 30.66 EPC 4L 27/11/2019 Ceigall India Ltd.
Sunder Nagar Bypass)
Balance Work of 4L of Kiratpur to Nerchowk section of NH-21 (from
343 Himachal Pradesh KM 12.750 to km 26.500, km 126.500 to km 158.500 including ACC 3 47.75 HAM 4L 12/08/2021 Gawar Construction Ltd
link road from km 0.000 to km 2.003) Greenfield Alignment (Pkg-2)

Strengthening with renewal work from Km 159+945 to km 167+080 Gawar Kiratpur Nerchowk Highway
344 Himachal Pradesh 1,54,154 11.49 Item Rate 4L 05/11/2023
(Jarol to Pung) & km 177+860 to km 182+215 (Dadour to nagchala) Private Limited
Pandoh bypass (221.305) to Takoli (242.000) of NH-21 in the state of Shapoorji Pallonji Pandoh Takoli
345 Himachal Pradesh 3 18.91 HAM 4L 26/03/2018
Himachal Pradesh Highway Private Limited
346 Himachal Pradesh Takoli ( 242.000) to Kullu (272.000) 3 28.69 EPC 4L 02/06/2017 NKC Projects Private Limited
Kullu ( 272.000) to Manali ( 309.345) of NH-21 in the state of Himachal
347 Himachal Pradesh 3 37.35 EPC 2L 09/02/2017 Gawar Construction Ltd
Pradesh
Strengthening and maintenance of existing 02 lane National Highway
348 Himachal Pradesh 154 13.135 Item Rate 2L 18/05/2023 Gawar Construction Ltd
NH-154 section from Rajol at km 72 to Thanpuri at km 85.135
Strengthening of existing stretch in patches from km. 1.000 to km.
349 Himachal Pradesh 2.000, Km. 10.000 to km. 24.000, km. 30.000 to km. 34.000 & km. 205 58.6 Item Rate 2L 03/06/2022 P K Construction Shimla Pvt. Ltd.
49.000 to km. 51.000 of Shimla-Mataur section of NH-205
350 Himachal Pradesh Parwanoo (Km 67.00) to Solan (Km 106.14) 5 39.14 EPC 4L 21/09/2015 G R Infraprojects Limited
Construction of 6 nos. Foot Over Bridges (FOBs) on Parwanoo to SOlan
351 Himachal Pradesh Section of NH-22 (Now NH-05) from Km. 67.000 to Km 106.139 in the 05 0.095 EPC Others 24/01/2024 Shiva Associates
satae of Himachal Pradesh on EPC Mode.
Maintenance of existing highway from Kaithlighat to Dhalli bypassed
352 Himachal Pradesh by proposed Shimla bypass (Kaithlighat to Dhalli Section) of New NH- 05 27.45 Item Rate 2L
05 from Km. 129.050 to Km 156.507
Strengthening under One time improvement from km. 0.000 to km.
353 Himachal Pradesh 24.250 & km. 153.180 to km. 156.500 of existing Kaithlighat to Dhalli 555 41.63 Item Rate 2L 28/06/2021 State PWD
section of NH-05
Banihal to Srinagar (KM 187.00 to KM 189.35 and KM 220.70 to KM SRINAGAR BANIHAL EXPRESSWAY
354 Jammu and Kashmir 44 65.41 BOT Annuity 4L 27/06/2011
286.11) LIMITED
355 Jammu and Kashmir Banihal (Km 189.350) to Quazigund (KM 220.700) 44 16.27 BOT Annuity 4L 05/06/2011 Navyuga Road Projects Pvt Ltd.
Udhampur - Ramban section of NH-1A from km. 67.00 to km. 89.00 Gammon Engineers & Contractors
356 Jammu and Kashmir 44 40.07 EPC 4L 28/12/2015
and km. 130.00 to km. 151.00 Pvt. Ltd.
4L of Chenani - Nashri including 9 Km long tunnel (2L) with parallel
357 Jammu and Kashmir 44 10.87 BOT Annuity 2L/4L 23/05/2011 Chenani Nashri Tunnelway Limited
escape tunnel
4L of Chenani - Nashri (old Alignment) via Patnitop from Km. 89.00 to
358 Jammu and Kashmir 44 41 OMT 4L
Km. 130.00 of NH-44
4L of Jammu - Udhampur from km. 15.00 to km. 67.00 [Jammu Bypass Athaang Jammu Udhampur Highway
359 Jammu and Kashmir 44 64.59 BOT Annuity 4L 17/06/2011
- Udhampur] (Pkg No. NHDP-II/BOT/VI/J&K) Private Limited
Stand-alone Ring road/bypass around Jammu City from Raya Morh
360 Jammu and Kashmir 58.26 EPC 4L 08/01/2018 Gayatri- KMB (JV)
km. -0.687 to Jagti km. 57.568
4L of Kunjwani - Vijaypur from km. 80.00 to km. 97.20 of Pathankot -
361 Jammu and Kashmir 44 17 Item Rate 4L 01/04/2002 Border Roads Organisation
Jammu (NS-15)
4L of Vijaypur-Hiranagar from km. 50.00 to km. 80.00 of Pathankot -
362 Jammu and Kashmir 44 30 EPC 4L 01/09/2005 ITD Cementation India Ltd
Jammu (NS-35)
Rectification of 02 Nos. Black spots at Maheshwar (From Km. 65.338
363 Jammu and Kashmir to Km. 65.746, From Km. 66.175 to Km. 66.885) & at Chichi Mata 44 1.744 EPC 4L 21/12/2021 Ceigall India Ltd.
(From Km. 70.684 to Km. 71.310) in District Samba of NH-44(Pkg-IV)
Rectification of Black Spot at Samba from Km. 67.180 to Km 69.030 of
364 Jammu and Kashmir 44 1.85 EPC 4L 07/10/2021 Kaluwala Construction Private Limited
NH-44 (Pkg-V)

Page 15 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Rectification of Black Spot at Mansar Morh from Km. 69.780 to Km.
365 Jammu and Kashmir 44 0.91 EPC 4L 14/10/2021 Shree Associates
70.690 of NH-44
366 Jammu and Kashmir Improvement and Routine and repair to floor protection to Bridges 44 4 Item Rate 4L 17/01/2024 Jai Buildcon Pvt Ltd
4L of Hiranagar - Lakhanpur from km. 16.35 to km. 50.00 of Pathankot
367 Jammu and Kashmir 44 33.65 Item Rate 4L 01/09/2005 ITD Cementation India Ltd
- Jammu (NS-34)
Value addition works on 4L Hiranagar-Lakhanpur from km. 16.35 to
368 Jammu and Kashmir 44 33.65 TBD TBD
km. 50.00
Rectification Of Black Spot - Pkg 2 from Km. 31.640 to Km. 32.700 PRL Projects and Infrastructure
369 Jammu and Kashmir 44 1.06 EPC 4L 07/05/2021
(PALLI MORH) of NH-44 Limited
Rectification of 02 Nos. Black spots at Lakhanpur Golden Gate (Km
PRL Projects and Infrastructure
370 Jammu and Kashmir 17.711 to Km 18.892) & Logate Morh (Km 26.900 to Km 28.720) of NH- 44 3.001 EPC 4L 16/07/2021
Limited
44 (Pkg-1)
4L of of Pathankot - Jammu Section from km. 00.00 to km. 15.00
371 Jammu and Kashmir 44 15 Item Rate 4L 01/11/2005 Mohandas V Rajani
(Contract Package NS-33/J&K)
4L of Bihar - Jharkhand Border (Barachatti to Gorhar) (Contract Pkg V- Larsen & Toubro Ltd. - Hindustan
372 Jharkhand 2 71.28 EPC 4L 26/03/2002
B) (GTRIP-7) from Km. 240.00 to Km. 320.000 on NH-2 Construction Company Ltd. (JV)
6L of Gorhar to Khairatunda Section of NH-2 from Km. 320.810 to
373 Jharkhand 2 40.19 HAM 6L 19/07/2019 Dilip Buildcon Ltd.
Km.360.300 (Pkg I)
Khairatunda to Barwa Adda Section of NH 2 from km. 360.300 to km. Ashoka Khairatunda Barwa Adda
374 Jharkhand 19 40.33 HAM 6L 08/01/2019
400.132 (Pkg II) Road Limited
375 Jharkhand 4L of Piska More (Km. 2.90) to Palma (Km. 26.00) of NH- 23 23 22.4 EPC 4L 27/12/2017 Ram Kripal Singh Construction Pvt. Ltd
2L /4L of Chas-Bokaro-Gola-Ramgarh section of NH-23 from km 0.00
376 Jharkhand 23 78.31 EPC 2L/4L 31/12/2014 Shiva Build Tech
to 78.31
2L/4L of Chas - Bokaro-Gola-Ramgarh section of Nh-23 from km. 0.00
377 Jharkhand 23 78.31 OMT 2L/4L 31/12/2021 Shiva Build Tech
to Km. 78.31
4L/2L PS of Govindpur (Raiganj) - Chas - WB border section of from
378 Jharkhand 18 56.89 EPC 4L/2L PS 10/12/2017 Ashoka Buildcon Limited
km. 0.00 to km. 56.889 of Old NH-32
4L of Mahulia (km 277.500) to Baharagora (km 333.500) of NH-33 and
379 Jharkhand 18 71.61 EPC 4L 12/09/2016 Dilip Buildcon Ltd.
Baharagora (km 199.200) to Chichira (km. 183.587) of NH-06
Balance work of Ranchi-Mahulia Section of NH-33 from Km 140.000
380 Jharkhand 33 77.3 EPC 4L 03/06/2019 Bvepl Bhartia JV
(Rampur) to Km 217.300 (Chowka) (Pkg-II)
Balance work of Ranchi-Mahulia Section of NH-33 from Km 217.300
381 Jharkhand 33 16.05 EPC 4L 12/07/2019 Ram Kripal Singh Construction Pvt. Ltd
(Chowka) to Km 233.350 (Saharbeda) (pkg-III)
Balance work of Ranchi-Mahulia Section of NH-33 from Km 233.350
382 Jharkhand 33 44.22 EPC 4L/6L 11/06/2019 Iron Triangle Ltd
(Saharbeda) to Km 277.568 (Mahulia) (Package -IV)
4L from km 196.87 (Sankha) to km 219.6 (Khajuri) on NH-75 [Rehla /
383 Jharkhand 75 22.73 HAM 4L 07/10/2021 Shivalaya Construction Co. Pvt. Ltd.
Garhwa Bypass]
384 Jharkhand Bijupara (Km. 34.00) to Kuru (Km. 55.00) of NH-75 in Jharkhand 75 21 EPC 4L 27/12/2017 Jaiprakesh Associates Ltd.
4L of Kutchery Chowk - Piska More - Bijupara from Km. 0.00 - Km. Varaha Infra Ltd. - Sunil Hitech
385 Jharkhand 75 34 EPC 4L 27/12/2017
34.00 of NH - 75 Engineers Ltd (JV)
386 Jharkhand Barhi (Km 0.000 ) to Hazaribagh (40.500) of NH-33 in Jharkhand 33 41.28 EPC 4L 14/02/2017 Ramky Infrastructure Ltd.
4L of Hazaribagh-Ranchi stretch of NH33 from Km 40.5 to Km114 IL&FS Transportation Networks Ltd
387 Jharkhand 33 73.5 BOT Annuity 4L 01/08/2010
including Kujju bypass and Punj Lloyd Ltd.
388 Jharkhand Construction of VUP at Km 92.50 ( Patel Chowk) of NH-33 33 1 EPC 6L 22/12/2020 Anand Construction
4L of Belgaum - Maharashtra Border from km. 515.00 to km. 592.24 of
389 Karnataka 48 77.24 BOT Annuity 4L 20/06/2002 Jaihind Road Builders
Old NH- 04
Six laning of Belgaum - Dharwad section of NH-4 from km 433.00 to
390 Karnataka 48 79.36 BOT Toll 6L 04/05/2011 Ashoka Buildcon Limited
km 515.00
Four laning of Belgaum - Dharwad section of NH-4 from km 433.00 to
391 Karnataka 48 62 EPC 4L 12/04/2002 Sunway Construction Ltd.
km 495.00
Six laning of Haveri (Km 340) to Hubli (Km 403.400) section of NH4 in Montecarlo Hubli Haveri Private
392 Karnataka 48 63.4 HAM 6L 22/02/2018
Karnataka Limited

Page 16 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
393 Karnataka 4L of Haveri - Hubli section of NH-4 from km. 340.00 to km. 404.00 4 64 EPC 4L 30/06/2001 Afcon Infrastructure Ltd.
Avenue and Median Plantation on Six laning of Hubli-Haveri section
394 Karnataka 48 63.4 EPC 6L 01/02/2022 ADVANTAGE
from km 340+000 to km 403+400 of NH-48 (Old NH-4)
Davanagere - Haveri of NH-48 (Old NH-4) from km. 260.00 to km.
395 Karnataka 48 78.92 HAM 6L 24/01/2018 IRCON International Limited
338.923
Gammon Engineers & Contractors
396 Karnataka Harihar - Haveri from Km. 284 to Km. 340 48 56 EPC 4L 22/11/2008
Pvt. Ltd.
Chitradurga - Davanagere including Chitradurga bypass of NH-48 (Old
397 Karnataka 48 72.7 HAM 6L 27/12/2017 PNC Infratech Pvt. Ltd.
NH-4)
Gammon Engineers & Contractors
398 Karnataka Chitradurga - Harihar from Km. 207 to Km. 284 48 77 EPC 4L 31/10/2008
Pvt. Ltd.
399 Karnataka Tumkur-Chitradurga 48 114 BOT Toll 6L 04/06/2011 IRB Infrastructure Developers Ltd.
400 Karnataka Tumkur - Nelamangala(4L) 48 32.5 BOT Toll 4L 01/04/2000 Abhijeet Infrastructure Limited
401 Karnataka Tumkur Bypass from Km. 62 to Km. 75 48 13 EPC 4L 26/09/2009 Ganapathi Stone Crusher
O&M Routine Maintenance cum incident Management along with
Road Safety Enhancement of Access Controlled Highway Project of
402 Karnataka 48 19.5 Item Rate 4L/6L 04/04/2024 L Kasi Reddy
Bengaluru Nelamangala section of NH-48 (old NH -4) from Km.10+000
to Km.29+500 in the State of Karnataka
4L of km 0.00 to km 42.00 of Dobbaspet to Doddaballapura Bypass Shankarnarayana Constructions Pvt.
403 Karnataka 648 42 HAM 4L 19/04/2021
section of NH-648 (old NH-207)] [Bangalore Ring Road Pkg 1] Ltd.
4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of
404 Karnataka 648 38 HAM 4L 22/02/2021 Dilip Buildcon Ltd.
NH-648 ( Old NH-207) [Bangalore Ring Road Pkg 2]
Bangalore Elevated Tollway Private
405 Karnataka Silk Board Junction (Bangalore) to TN Border (Hosur) 44 24 BOT Toll 6L 25/07/2006
Limited
406 Karnataka AP/ Karnataka Border - Devanhalli 44 71.45 BOT Annuity 4L/6L 25/03/2007 B S Reddy
Devanhalli - Bengaluru (Pkg No NS-2/BOT/KNT-2) from km 534.720 to
407 Karnataka 44 22 BOT Toll 6L 30/11/2010 Navyuga Road Projects Pvt Ltd.
km 556.84 of NH-7
408 Karnataka Goa / Karnataka (Km.93.700) to Kundapur (Km.283.30) 66 187.24 BOT Toll 4L 03/03/2014 IRB Infrastructure Developers Ltd.
Strengthening of Existing Kumta town limits Road from km 170.98 to
km 178.627 of Goa-KNT Border to Kundapur section including repair
409 Karnataka 66 7.65 Item Rate 2L 11/12/2019 IRB Infrastructure Developers Ltd.
and rehabilitation of Major Bridge at km 175.60 and Minor Bridge at
km 170.15.
Kundapur (Km.283.300) to Surathkal (Km358.686) and Nantoor
410 Karnataka 66 90.08 BOT Toll 4L 05/06/2010 Navyuga Road Projects Pvt Ltd.
(Km.1.900) to Talapady (Km.17.200)
MH/KNT Border to Sangareddy Section from km. 433.00 to km. 515.00
411 Karnataka 65 145 BOT Toll 4L 01/04/2014 Larsen & Toubro Ltd.
of NH-65
412 Karnataka Bellary to Byrapura Section km 253.600 to km 308.550 of NH-150A 150A 54.95 HAM 4L 24/10/2019 Dilip Buildcon Ltd.
4L of Byrapura to Challakere Section from km 308.550 to km 358.500
413 Karnataka 150A 49.95 HAM 4L 31/12/2018 Dilip Buildcon Ltd.
of NH-150 A
414 Karnataka Bengaluru-Hoskote-Mulbagal 75 80 BOT Toll 4L/6L 05/01/2008 LANCO Infratech Ltd
415 Karnataka AP/KNT border-Mulbagal 69&75 22 BOT Toll 4L 22/05/2013 J.B.Reddy
416 Karnataka Neelamangala - Devihalli from km. 28.20 to km. 110.00 75 80.26 BOT Toll 4L 05/01/2008 LANCO Infratech Ltd
417 Karnataka Devihalli - Hassan 75 77 BOT Toll 4L 14/12/2010 Larsen & Toubro Ltd
418 Karnataka B.C. Road - Padil (Suratkal-Nantur)(New Mangalore Port) 66 37 EPC 4L 16/06/2005 IRCON International Limited
419 Karnataka Bangalore-Nidagatta (Pkg. I) 275 56.2 HAM 6L 14/05/2019 Dilip Buildcon Ltd.
420 Karnataka Nidagatta-Mysore (Pkg II) 275 61 HAM 6L 10/12/2019 Dilip Buildcon Ltd.
Strengthening of 2/4L of Kerala Border - Kollegal Section of Km
421 Karnataka 766 129.443 EPC 2L/4L 27/05/2020 PRN Infratech Private Limited
136.600 to Km 268.475 of Old NH-212
422 Karnataka 4L of Hubli - Hospet Section of NH-63 from: Km 128.850 to Km 272.571 67 143.72 EPC 4L 15/03/2017 BSC - KNR (JV)
4 laning of Bijapur-Hungund Section of NH-13 from km 102.00 to km Sadbhav Engineering Limited &
423 Karnataka 50 97.212 BOT Toll 4L 08/02/2010
202.00 Montecarlo Construction Ltd.

Page 17 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
4/6 Laning of Hungund - Hospet from km. 323.00 to km. 420.00 of Old GMR - Oriental Structural Engineers
424 Karnataka 50 97 BOT Toll 4L/6L 08/09/2010
NH-13 (NH-50) Pvt. Ltd.
425 Karnataka Hospet - Chitradurga from km. 299.00 to km. 418.750 50 120.18 BOT Toll 4L 18/02/2016 TRIL Roads Pvt. Ltd.
Maintenance work of BRT Tiger Reserve Boundary to Bangalore
426 Karnataka 209 23 Item Rate 2L/4L 17/02/2022 Ganapathi Stone Crusher
Section from Km. 287.520 to Km. 461.550 of NH-209
4L Tumkur-Shimoga (Pkg-I) from Mallasandra to Karadi village of NH- Ashoka Mallasandra Karadi Road
427 Karnataka 73 52.89 HAM 4L 15/10/2019
206 (from Km. 12.300 to Km. 65.195) Private Limited
4L of Tumkur-Shimoga (Pkg-II) from Km 65.195 (Karadi) to Km 121.900
428 Karnataka 73 56.71 HAM 4L 15/10/2019 Ashoka Buildcon Limited
(Banawara) of NH-206
Tumkur-Shimoga (Pkg-III) from Km 121.900 (Banawara) to Km 170.415 Ashoka Banwara Bettadahalli Road
429 Karnataka 206 48.52 HAM 4L 15/03/2021
(Bettadahalli) of Old NH-206 Private Limited
Bijapur (Km.195.000) - Gulbarga - Homnabad (Km. 418.00) of NH-218
430 Karnataka 50 220.01 EPC 2L PS 30/03/2015 Larsen & Toubro Ltd.
(New NH-50)
Ashoka Belgaum Khanapur Road
431 Karnataka Belgaum-Khanapur Pkg I (Km 0.000-Km 30.800) of NH-4A 748 30 HAM 4L 07/03/2019
Private Limited
4L of Walayar to Vadakkanchery from Km 182.250 to Km 240 (Section
432 Kerala 544 53.5 BOT Toll 4L 18/05/2013 KNR Constructions Limited
NS2/BOT/KL-02) of NH 544
Vadakkenchery (Km 236.000) to Thrissur (Km 264.490) of NH - 544 in
433 Kerala 544 28.36 BOT Toll 6L 15/09/2012 KMC Construction Ltd.
Kerala
4/6 L Thrissur (km 270) to Angamali (km 316.700) i/c Maintenance of
434 Kerala 544 65.3 BOT Toll 4L/6L 22/09/2006 KMC-SREI Consortium
Angamali (km 316.700) to Edapally (km 342) Section NS-2/BOT/KL/01

435 Kerala Service Road on ICTT (Kalamassery-Vallapardam) (Additional Works) 966A 2.6 EPC 2L 11/08/2018 Yoga & Co. - Notch India Projects (JV)
436 Kerala NH Connectivity to ICTT Vallarpadam 966A 17.12 EPC 4L 10/08/2007 G.R Engineers & Contractors
4 lane ROB and its approaches including allied works near
437 Kerala 66 0.78 EPC 4L 13/05/2018 EKK Infrastructure Limited
Neleshwaram town (Pallikara Railway Gate) Kasargad district
Thalassery Mahe Bypass (Km 170.600 to Km 189.200) of NH-17(New GHV India Pvt. Ltd. -EKK
438 Kerala 66 18.6 EPC 4L 04/12/2017
NH-66) in Kerala Infrastructure Pvt. Ltd(JV)
439 Kerala Edappally-Vyttila-Aroor Section 66 17 EPC 4L 31/10/2008 RDS-CVCC (JV)
440 Kerala Kazhakkoottam to Mukkola Section from Km 0.000 to Km 26.500 66 26.8 EPC 4L 12/06/2015 KNR Constructions Limited
4L of Kazhakuttam Junction - Technopark Junction from km. 547.080
441 Kerala 66 2.72 EPC 4L 05/04/2019 RDS-CVCC (JV)
to km. 549.801
Maintenance work of Kazhakkoottam (Km.1+800) to Mukkola
442 Kerala 66 24.998 EPC 4L 03/07/2023 KLR constructions
(Km.26.798)
Operation and Maintenance of Four laning of Thiruvanthapuram
443 Kerala Bypass from Kazhakkoottam to Mukkola section of NH-66 in the State 66 24.998 PBMC 4L 01/03/2024 TTK Construction
of Kerala on PBMC.
Mukkola Junction to Kerala/ Tamil Nadu Border from Km 26.5 to Km
444 Kerala 66 16.2 EPC 4L 15/06/2016 Larsen & Toubro Ltd.
43.00 of NH 66 ( old NH 47)
Maintenance of Kozhikode to Palakkad from Km 15.656 (junction with
445 Kerala NH-66 near Ferokh) to Km 140.960 (Junction with NH-544 near 966 125.304 Item Rate 2L
Palakkad) of NH-966
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-17) (Ch. JiangXi Construction Engineering
446 Madhya Pradesh 452+420 to Ch. 484+420) [Rajasthan/MP Border to Jodmi village of 148N 32 EPC 8L 08/10/2020 (Group) Corporation Ltd. - MKC
Mandsaur district] Infrastructure Ltd. (JV)
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-18) (Ch.
447 Madhya Pradesh 484+420 to Ch. 517+420) [Jodmi village to Bani village of Mandsaur 148N 33 EPC 8L 07/02/2020 G R Infraprojects Limited
district]
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-19) (Ch. JiangXi Construction Engineering
448 Madhya Pradesh 517+420 to Ch.546+920) [Bani village to Bardawadi village of 148N 29.5 EPC 8L 05/11/2020 (Group) Corporation Ltd. - MKC
Mandsaur district] Infrastructure Ltd. (JV)
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-20) (Ch.
449 Madhya Pradesh 546+920 to Ch. 572+220) [Bardawadi village of Mandsaur district to 148N 25.3 EPC 8L 06/12/2019 GHV (India) Pvt Ltd.
Kamliya village of Ratlam district]

Page 18 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-21) (Ch.
450 Madhya Pradesh 572+220 to Ch. 602+420) [Kamliya village to Kandarwasa village of 148N 30.2 EPC 8L 10/12/2019 G R Infraprojects Limited
Ratlam district]
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-22) (Ch.
451 Madhya Pradesh 602+420 to Ch. 627+420) [Kandarwasa village to Bawadi village (Near 148N 25 EPC 8L 20/11/2020 Larsen & Toubro Ltd.
Shivgarh) of Ratlam district]
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-23) (Ch.
452 Madhya Pradesh 627+420 to Ch.652+720) [Bawadi village (Near Shivgarh) of Ratlam 148N 25.3 EPC 8L 29/05/2020 G R Infraprojects Limited
district to Ranni Village of Jhabua district]
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-24) (Ch.
453 Madhya Pradesh 652+720 to Ch.674+420) [Ranni Village to Miyati Village of Jhabua 148N 21.05 EPC 8L 05/03/2020 G R Infraprojects Limited
district]
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-25) (Ch.673.770
454 Madhya Pradesh 148N 23.15 EPC 8L 05/03/2020 G R Infraprojects Limited
to Ch.696.920) [Miyati Village to MP-Gujarat Border]
Four Lane Flyover at km. 80.742 from km. 79.780 to km. 81.200 at
455 Madhya Pradesh 44 1.42 EPC 4L 14/03/2018 Shree Manglam Buildcon
Morena Town
456 Madhya Pradesh Balance work of Gwalior - Jhansi section 44 82.46 Item Rate 4L 28/08/2018 Gawar Construction Ltd
Gwalior Jhansi Section of NH-75 from km. 16.00 to km. 96.127
457 Madhya Pradesh 44 82.46 BOT Annuity 4L 05/06/2007 DSC - Apollo Consortium
[NS1/BOT/MP-UP] in Madhya Pradesh
4L of Jhansi-Lakhanadon section from km 136.99 to km 192.693 of NH-
458 Madhya Pradesh 44 55.52 EPC 4L 27/05/2006 IJM Corporation Berhad Ltd.
26 in the state of MP (Civil Contract Package No. ADB-II/C-4)

4L of Jhansi-Lakhanadon section from km 192.693 to km 219.492 of Ssangyong Engineering Construction


459 Madhya Pradesh 44 26.73 EPC 4L 28/05/2006
NH-26 in the state of MP (Civil Contract Package No. ADB-II/C-5) Co. Ltd., South Korea

4L of Jhansi-Lakhanadon section from km 219.492 to km 262.739 of Ssangyong Engineering Construction


460 Madhya Pradesh 44 43.24 EPC 4L 28/05/2006
NH-26 in the state of MP (Civil Contract Package No. ADB-II/C-6) Co. Ltd., South Korea
4L of Jhansi Lakhnadon Section from Km. 262.739 to Km. 305.825 of B.Seenaiah & Company (Projects)
461 Madhya Pradesh 44 42 EPC 4L 27/05/2006
NH-26 (ADB-II/C-7) Limited
4L of Jhansi Lakhnadon Section from Km. 305.825 to Km. 360.092 of Ssangyong Engineering Construction
462 Madhya Pradesh 44 54 EPC 4L 27/05/2006
NH-26 (ADB-II/C-8) Co. Ltd., South Korea
4L of Jhansi Lakhnadon Section from Km. 360.092 to Km. 415.089 of Ssangyong Engineering Construction
463 Madhya Pradesh 44 54.77 EPC 4L 27/05/2006
NH-26 (ADB-II/C-9) Co. Ltd., South Korea
Nava Bharat Ferro Alloys Ltd
464 Madhya Pradesh Lakhnadon - Seoni MP 2 44 40 BOT Annuity 4L PS 28/03/2007
Hyderabad
465 Madhya Pradesh Lakhnadon-Seoni (left out delinked stretches of MP-2 Package) 44 9 EPC 4L PS 20/10/2016 Udit Infrastructure Private Limited
Widening and Reconstruction of 4 laning of Lakhnadon –Seoni section
466 Madhya Pradesh from km 551.6 to km 553.1 km 557.4 to km 557.80 km 558.93 to 44 9.24 EPC 4L 20/10/2016 Udit Infrastructure Private Limited
562.450 563.760 to 567.55 (left out stretches) of NH 7
Major Maintenance of the MP-2 delink Stretch of 9.24 km at stretches
(i) km.551.600 to km.553.100 (ii) km. 557.400 to km. 557.800 (iii) km.
467 Madhya Pradesh 44 9.24 Item Rate 4L 16/03/2024 Ravi Shankar Jaiswal
558.930 to km. 562.450 and (iv) Km.563.760 to km. 567.550 at NH 44
under PIU Chhindwara
468 Madhya Pradesh Seoni to MP/MH Border (MP 3) (Seoni - Mohgaon) 44 27.77 BOT Annuity 4L PS 26/11/2007 Sadbhav -SREI
469 Madhya Pradesh Delinked stretch of Seoni - MP/MH Border (MP 3) 44 29.29 EPC 4L 10/08/2018 Dilip Buildcon Ltd.
Baran-Kota Naka, Madhya Pradesh (Raj/MP Border) and Kota Naka,
470 Madhya Pradesh 27 121 OMT 4L 13/09/2019 APCO Infratech Pvt. Ltd.
Madhya Pradesh (Raj/MP Border)-Ghasarahi (Shivpuri)
Multai- Chhindwara-Seoni & Narsinghpur- Chhindwara Saoner
471 Madhya Pradesh 347&547 417.53 EPC 2L PS 31/10/2011 Sadbhav Engineering Pvt. Ltd.
including Chhindwara Ring Road

Page 19 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Strengthening & Maintenance work of Chhindwara Soaner Section &
Chhindwara ring road (133.222 km), Chhindwara - Amarwara -
472 Madhya Pradesh 347 383.097 EPC 2L PS 21/03/2022 KRC Infraprojects Pvt. Ltd.
Narsingpur Section (113.000 km), Chhindwara - Multai & Sonakhar -
Seoni section (136.877 km) of NH – 347
2L PS of Saoner-Chhindwara from Km.0.000 to 75.460 and Chhindwara
473 Madhya Pradesh 547 132.662 OMT 2L PS Sadbhav Engineering Pvt. Ltd.
Ring Road from Km. 0.000 to 57.070 section of NH-547
2L PS of Chhindwara-Narsinghpur from Km. 97.600 to 210.010 section
474 Madhya Pradesh 547 112.41 OMT 2L PS Sadbhav Engineering Pvt. Ltd.
of NH-547
Balance work of 4L of Gwalior - Shivpuri Section from Km. 100.757 to
475 Madhya Pradesh NH3 6.5 EPC 4L 01/06/2021 KRC Infraprojects Pvt. Ltd.
Km 107.350 through Madhav National Park of NH-03
476 Madhya Pradesh Gwalior bypass 44 42 BOT Annuity 4L 07/04/2007 Era Infra Engineering Ltd.
477 Madhya Pradesh Rayroo - Nayagaon (103+200km to 130+100km) 46 28.35 Item Rate 2L PS R R Infraa Construction
O&M of 4L of Gwalior-Shivpuri Section from Km. 15.600 of NH-75 (End
478 Madhya Pradesh 46 125.3 BOT Toll 4L 01/02/2020 G.R Engineers & Contractors
of Gwalior Bypass) to Km. 236.000 of NH-46
479 Madhya Pradesh Shivpuri to Guna Package -1 3 85.31 BOT Toll 4L 25/01/2016 IRCON International Limited
4L of Guna Bypass section from Km. 210.740 to Km 223.130 ( Stage-II
480 Madhya Pradesh 46 12.39 BOT Toll 4L 25/01/2016 IRCON International Limited
) of NH - 46
481 Madhya Pradesh Guna Bypass Section 3 12.25 BOT Toll 2L 05/01/2006 Guna Infrastructure Ltd
482 Madhya Pradesh Guna-Biaora [BoT(Toll] 4L with PS 46 93.5 BOT Toll 4L 07/09/2016 Dilip Buildcon Ltd.
Improvement of bypassed town portions in Shivpuri-Guna (Kolaras,
483 Madhya Pradesh Lukwasa, Badarwas) & Guna-Biaora( Ruthiyai and Binagan) section of 3 16.5 Item Rate 2L DIC-NCC
NH-3
Four laning of Biaora to Dewas Section from Km 426+100 to Km
484 Madhya Pradesh 52 141.26 BOT Toll 4L 09/07/2016 Oriental Structural Engineers Pvt. Ltd.
566+450 of NH-3
Strengthening & Maintenance, Improvement in riding quality and
Periodic Repair of 6-lane highway (45km) and service road (58km
DG Belhekar and Company - Shree
485 Madhya Pradesh linear length) including maintenance of structures and lightening of NH-52 45.05 Item Rate 6L 25/07/2023
Associates (JV)
Indore Dewas section of NH-52 from km. 577+550 to km. 610+000 and
km. 0+000 to km. 12+600
486 Madhya Pradesh Service Road on Indore-Dewas 52 32 EPC 6L 18/12/2017 Gayatri Projects Limited
4L of Indore-Khalghat section from km 12.600 to km 84.700 of Old NH-
487 Madhya Pradesh 52 72.1 BOT Toll 4L 06/09/2006 Oriental Structural Engineers Pvt. Ltd.
3
Four Laning of Khalghat-MP/MH Border from km 84.700 to km Uniquest Infra Ventures Private
488 Madhya Pradesh 52 82.8 BOT Toll 4L 19/11/2008
167.500 Limited
Indore - Gujarat / MP Border from km. Km 9.500 to Km 171.000 of NH-
489 Madhya Pradesh 47 161.5 BOT Toll 4L 20/08/2010 IVRCL Infrastructures & Projects Ltd.
59 in MP
Bhopal (Km. 0.000) to Sanchi (Km. 53.775) of NH-86 (Ext.) in Madhya Backbone Enterprises Limited - Ashish
490 Madhya Pradesh 86 53.78 EPC 2L PS 02/01/2017
Pradesh infracon Pvt. Ltd.
Jabalpur (Km 465.500) to Lakhnadon (Km 546.425) of NH-7 in Madhya
491 Madhya Pradesh 30&34 80.82 EPC 4L PS 04/06/2015 Larsen & Toubro Ltd.
Pradesh
Routine Maintenance and Incident Management of four Lane Jabalpur-
30 (Old NH-7),34
492 Madhya Pradesh Lakhnadon Section of NH-7 from Km 465.600 to Km 546.425 in the 80.82 Item Rate 4L PS 02/03/2024 Shree Construction
(Old NH-7)
state of Madhya Pradesh.
Sleemnabad (KM 397.000) to Jabalpur (Km 465.500) [Rewa - Katni -
493 Madhya Pradesh 30 68.26 EPC 4L PS 15/06/2015 Larsen & Toubro Ltd.
Jabalpur Pkg IV]
Routine Maintenance and Incident Management of Four Lanning of
494 Madhya Pradesh Rewa-Katni Jabalpur Section of NH-7 (new NH-30 from Km 397.000 to 30 68.5 Item Rate 4L 21/10/2023 Laxmi Builders
Km 465.500 (Package- lV)
Maihar (Km 311.000) to Katni (Km 359.500) and Katni (Km 378.500) to
495 Madhya Pradesh 30 69.07 EPC 4L 17/06/2015 Larsen & Toubro Ltd.
Sleemnabad (Km 397.000)[Rewa - Katni - Jabalpur Pkg II]
Rewa(Km 242.600) to Maihar (Km 311.000) of NH-7 (New NH-30) in
496 Madhya Pradesh 30 69.18 EPC 4L 17/06/2015 Larsen & Toubro Ltd.
Madhya Pradesh [Rewa - Katni - Jabalpur Pkg I]

Page 20 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Prakash Asphaltings and Toll
497 Madhya Pradesh 4L of Harda - Betul (Pkg-I) from Km.0 to Km.30.20 [Harda - Temagaon] 47 30 HAM 4L 10/09/2021
Highways (India) Ltd.
498 Madhya Pradesh Harda - Betul (Pkg-III) from Km. 81.00 to Km.121.248 [Chicholi - Betul] 47 40.24 HAM 4L 15/09/2021 Bansal Construction Works Pvt. Ltd.
499 Madhya Pradesh Hiran River to Sindoor River (Km.66.00 - Km.130.00) 45 64 EPC 4L 25/07/2018 Gawar Construction Ltd
2L PS of Ujjain - Jhalawar (upto RJ Border) from Km. -0.620 to Km.
500 Madhya Pradesh 552G 128.92 EPC 2L 22/06/2021 GHV (India) Pvt Ltd.
132.955 of NH-552G
4L of Khedakhajuriya to Suhagadi from Km. 41.400 to Km. 89.200 of Ravi Infrabuild Projects Private
501 Madhya Pradesh 752D 47.8 HAM 4L 17/10/2022
NH-148NG (New NH 752D) (Pkg-II) Limited
Obaidullaganj Km. 2.800 to Km. 8.300 and Km. 20.700 to Itarsi Km.
502 Madhya Pradesh 46 46.3 EPC 4L 14/11/2017 NKC - CDS
63.000 of NH-69 in Madhya Pradesh
4L of Dewas - Ujjain from km. 0.0 to km. 19.76 of Old SH 18 (New
503 Madhya Pradesh 752D) including Ujjain Bypass (Km. 19.76 to km. 26.9) & Dewas Bypass 752D 41.42 HAM 4L 06/07/2021 Gawar Construction Ltd
(Km. 0.00 to km. 14.52)
504 Madhya Pradesh Katni-Umaria 43 69.1 Item Rate 2L PS
505 Madhya Pradesh Shahdol Anuppur MP/CG border 43 91.8 OMT 2L PS
506 Madhya Pradesh Jhansi - Khajuraho(PKG-I) 39 76.61 HAM 4L 18/05/2018 PNC Infratech Pvt. Ltd.
507 Madhya Pradesh Jhansi-Khajuraho from Km. 76.3 to Km. 161.7 near Bamitha Town 39 85.4 HAM 4L 13/02/2018 PNC Infratech Pvt. Ltd.
Mubarakpur (Km. 324.000) to Biaora (KM. 423.000) in Madhya Centrodorstoy India Pvt. Ltd. - NKC
508 Madhya Pradesh 46 97.33 EPC 4L 19/01/2018
Pradesh [Bhopal-biaora Pkg II] Projects (JV)
Lalghati (Bhopal) (Km. 315.73) to Mubarakpur (Km. 324.00) in Madhya
509 Madhya Pradesh 46 8.28 EPC 4L 28/11/2017 Centrodorstroy India Pvt. Ltd
Pradesh
2L PS of Multai-Chhindwara from Km. 0.000 to 75.592 and
510 Madhya Pradesh 347 136.88 OMT 2L PS 31/10/2011 Sadbhav Engineering Pvt. Ltd.
Chhindwara-Seoni from Km. 91.066 to 152.351 section of NH-347
511 Madhya Pradesh Rewa - Sidhi 39 58 EPC 2L 20/01/2015 Nitin Barsainya
512 Madhya Pradesh Churhat Bypass of Rewa Sidhi Section 39 15.35 HAM 4L 14/12/2018 Dilip Buildcon Ltd.
Manegaon -Barela section of NH-30 (old NH-12A) from Km. 0+000 to Shyam Constructions Electrical & civil
513 Madhya Pradesh 30 5.7 EPC 2L 13/06/2022
Km. 21.850 (Package-I) Contractors
Two Lane with paved shoulders for Rehabilitation and up-gradation of
Mandla-Chilpi Section from Design Ch Km. 85+400 to Km. 177+750 of
514 Madhya Pradesh 12A 92.35 EPC 2L 01/09/2023 VMAKS Constructions Private Limited
NH-12A (New NH-30) in the state of Madhya Pradesh on EPC mode
under NHDP-IV
Lion Engineering Consultants private
Operation and Maintenance of Baran - Shivpuri section from Km. Limited ln association with Hadimba
515 Madhya Pradesh, Rajasthan 27 120.765 Item Rate 4L 11/10/2005
1184.322 to Km. 1305.087 of NH-27 Consultants Professionals &
Technocrats
Madhya Pradesh, Uttar Tolling, Operation, Maintenance & Transfer of Shivpuri - Jhansi Section
516 27 75.3 InvIT 4L 16/02/2024 M/s Naseeb Construction Company
Pradesh from Km. 1305.087 to Km. 1380.387 of NH-27 through InVIT model
Madhya
Prakash Asphaltings and Toll
517 Pradesh,Rajasthan,Uttar Agra-Gwalior 44 95 OMT 4L 18/02/2015
Highways (India) Ltd.
Pradesh
Madhya
518 Pradesh,Rajasthan,Uttar Baran-Shivpuri-Jhansi 27 196 EPC 4L 26/08/2011 BSeenaiah & Company (Projects) Ltd
Pradesh
Madhya Pradesh,Uttar
519 Lalitpur - Sagar - Lakhnadon OMT 44 316.08 TOT 4L 06/10/2013 IRB Lalitpur Tollways Pvt. Ltd.
Pradesh
Madhya Pradesh,Uttar
520 4L of Agra-Gwalior section from Km. 85.00 to Km. 103.00 of NH-44 44 18 EPC 4L 30/08/2001 Backbone Project ltd.
Pradesh,Rajasthan
Incident Management, routine O&M and other work on Achhad
521 Maharashtra Dahisar (from km 381.00 to km 502.00) section of NH-48 in state of 48 121 OMT 6L 11/03/2024 Roadlink Infratech Pvt. Ltd.
Maharashtra

Page 21 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
4 Laning of Surat – Manor Pkg-III (Kajali – Manor) from km. 381.60 to
522 Maharashtra 8 57.4 EPC 4L 01/11/2000 Larsen & Toubro Ltd.
km. 439.00 of NH-8
Satara (Km 725.000) to Pune (Km 865.350) of NH - 4 (New NH - 48) in
523 Maharashtra 48 140.35 BOT Toll 6L 01/10/2010 Reliance Infrastructure Ltd.
Maharashtra
4L of Westerly Diversion to Pune City from km. 0.00 to km. 34.423 of
524 Maharashtra 4 34.42 EPC 4L 01/06/2000 Ashoka Buildcon Limited
NH-04
4 Laning of Satara-Kagal from km. 592.40 to km. 725.00 of NH-48 (Old
525 Maharashtra 48 132.76 BOT Toll 4L 04/01/2002 MSRDC
NH-4)
Design and Construction of Standalone VUP for the rectification of
Raj Infrastructure Development (I)
526 Maharashtra Accident Blackspot at Masur Phata (km. 697.800) Kagal - Satara 48 1.06 EPC 6L 16/06/2021
Pvt. Ltd.
section of NH-48
Design and Construction of Standalone VUP for the rectification of
Raj Infrastructure Development (I)
527 Maharashtra Accident Blackspot at Indoli Phata (Km. 704.200) on Kagal - Satara 48 1.18 EPC 6L 15/06/2021
Pvt. Ltd.
section of NH-48
Design and Construction of Service Road for improvement of Accident
528 Maharashtra 48 1.4 EPC 6L 15/06/2021 Uday D. Jadhav Constructions
Black spot at Kashil (km. 708.000) on Kagal - Satara section of NH-48

Development of Multilane Carriageway from Kanhan to Automotive


529 Maharashtra Square from km 704.200 to km 723.000 section of urban link of 44 17.16 EPC 6L 27/04/2017 KCC Buildcon Pvt. Ltd.
Nagpur Kamptee section of Nagpur Jabalpur road of NH-44
4L of MP/MH Border-Nagpur including Kamptee-Kanhan and Nagpur
530 Maharashtra Bypass and Maintenance of Nagpur-Hyderabad from Km.14.585 to 44 117.08 BOT Toll 4L 03/04/2010 Oriental Structural Engineers Pvt. Ltd.
Km. 36.600
Flyover at Dumri Junction (from km 697.580 to km 698.56) with slip/
531 Maharashtra 44 0.98 EPC 4L 20/01/2020 Brijesh Agrawal
service road on Nagpur Bypass section
4 Lane Stand Alone Ring Road/ Bypasses for Nagpur City, Package - I
532 Maharashtra Outer Ring Road 33.5 HAM 4L PS 05/01/2017 Bansal Pathways (NRR-1) Pvt. Ltd.
from Km 0.500 to Km 34.000
2L ROB including one Minor bridge and approaches with retaining wall D.P. Jain & Co. Infrastructure Pvt. Ltd.
533 Maharashtra 44 1.12 EPC 2L 29/03/2017
from Km.8.674 near Khapri (Nagpur) (City Portion) & Khalatkar Construction (JV)
Mahanagar Metro Rail Corporation
534 Maharashtra Flyover from Radisson Blue Hotel to Pride Hotel TBD 2 EPC 4L 07/08/2018
Ltd.
Flyover from Hotel Pride to Ajni Square with the Metro Viaduct and
535 Maharashtra ROB from Manish Nagar on Wardha road at Ujjwal Nagar and 2 lane 44 2.5 EPC 2L
underpass
Flyover at Butibori MIDC T Junction on NH-44 (Old NH - 7) (from
536 Maharashtra 44 1.69 EPC 4L 01/12/2018 T&T Infra Pvt. Ltd.
25.250 km to 26.940 km)
537 Maharashtra Borkhedi - JamWadner OMT-29 44 54.5 EPC 4L 29/06/2005 Sunrise Constructions
Hinganghat ROB including approaches, underpasses and service road KVenkata Raju Engineers &
538 Maharashtra 44 1.15 EPC 4L 15/11/2010
at Km.76.380 of Nagpur - Hyderabad section. Contractors
Flyover at km 77.750 of Hinganghat – Nandgaon Junction of NH - 44
539 Maharashtra 44 1.14 EPC 4L 04/12/2018 Vidya InfraBuilt Pvt. Ltd.
(from 77.250 km to 78.390 km)
National Highways Infra Projects Pvt.
540 Maharashtra Wadner (Km 94.000) to Devdhari(Km 123.000) 7 29 EPC 4L 28/07/2016
Ltd.
Deodhari - Kelapur from Km. 123.00 to Km.153.00 (Package no. NS-61 National Highways Infra Projects Pvt.
541 Maharashtra 44 30 EPC 4L 10/04/2005
(MH)) Ltd.
National Highways Infra Projects Pvt.
542 Maharashtra Kelapur(Km 153.000) to Pimpalkhuti(Km 175.000) of NH-7 7 21.25 EPC 4L 28/07/2016
Ltd.
Pimpalkhuti ROB (km 173.050) to (km 173.750) (Package No. NS-62A
543 Maharashtra 7 0.7 EPC 2L 25/11/2017 Assosiated Engineers Enterprises
(MH) Bal.)
4L of Saoner - Dhapewada - Kalmeshwar Gondkhiari (Pkg II) from km
544 Maharashtra 547E 29 EPC 4L 24/08/2019 Dilip Buildcon Ltd.
4.700 to km 33.575
Gammon Engineers & Contractors
545 Maharashtra 4L of Vadape - Gonde (km 539.500 to km 440.00) section of Old NH-3 160 96.64 BOT Toll 4L 12/04/2006
Pvt. Ltd.

Page 22 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Maintenance of the stretch of Kopargaon – Vaijapur – Aurangabad
546 Maharashtra 752I 88.1 OMT 2L 18/01/2021 M/ s. Mascot Construction Co.
from km. 0.000 to km. 88.100 of NH-752I
547 Maharashtra Talegaon - Amravati from km. 100.000 to km. 166.725 53 66.73 BOT Toll 4L/6L 18/11/2009 IRB MRM Consortium
548 Maharashtra Four Laning of Kondhali-Talegaon section from km 50.00 to 100.00 53 50 BOT Toll 4L 05/09/2006 Oriental Structural Engineers Pvt. Ltd.
549 Maharashtra Flyover at Karanja on NH-53 6 1 EPC 4L 25/06/2020 Jandu Construction Company
4L of Nagpur - Kondhali Section from km 9.200 - km 50.000 of Old NH-
550 Maharashtra 53 40.44 BOT Toll 4L PS 05/06/2006 Atlanta SREI Consortium (JV)
6
551 Maharashtra Nagpur-Wainganga bridge 53 45.43 BOT Toll 4L 09/04/2012 JMC Projects (India) Ltd.
Flyover in Sakoli town on NH-53 (Old NH - 6) (from 451.244 km to
552 Maharashtra 53 2.94 EPC 6L 23/05/2018 JMC Projects (India) Ltd.
454.184 km)
553 Maharashtra Wainganga Bridge - MH/CG Border 53 80 BOT Toll 4L 15/03/2008 Ashoka- IDFC(consortium)
Flyover in Lakhani town on NH-53 (Old NH-6) (from 469.920 km to
554 Maharashtra 53 3.5 EPC 6L 23/05/2018 JMC Projects (India) Ltd.
473.420 km)
555 Maharashtra Four Laning of MP/MH Border-Dhule from km. 168.50 to km. 265.00 52 88.8 BOT Toll 4L 21/12/2009 Sadbhav Engineering Pvt. Ltd.
IRCON International Limited - Soma
556 Maharashtra Dhule-Pimpalgaon Baswant 60 118.15 BOT Toll 4L 27/03/2006
(JV)
Operation and Maintenance of 6L Pimpalgaon-Nashik-Gonde (Km
557 Maharashtra 160 60 OMT 6L Jaihind Road Builders
380.00 to Km 440.00) Section of NH-3
Balance / Additional Works in Pimpalgaon - Nashik - Gonde Section of Dineshchandra R. Agrawal Infracon
558 Maharashtra 60 & 160 7.57 EPC 6L 23/04/2018
NH-3 from Km.380.00 to Km.440.0 [EPC-II] Pvt. Ltd.
Road Safety / Balance Works of 6L of Pimpalgaon - Nashik - Gonde
559 Maharashtra 60 & 160 4.54 EPC 6L 20/06/2017 B. P. Sangle Constructions Pvt. Ltd
Section of NH-3 from Km.380.00 to Km.440.0 [EPC-I]
4L of Akola - Medshi from km. 0.00 to km. 47.70 of NH-161 including
560 Maharashtra 161 47.7 EPC 4L 16/11/2020 Montecarlo Ltd
bypasses at Patur and Medshi
Montecarlo Vadodara Mumbai
561 Maharashtra Medshi (km 47.700) to Washim (km 92.200) of NH-161 in Maharashtra 161 44.5 EPC 4L 03/10/2019
Expressway P2P1 Private Limited
562 Maharashtra Washim(km 92.200) to Pangare(134.500) of NH-161 in Maharashtra 161 42.3 EPC 4L 15/05/2019 Montecarlo Ltd
4L of Pangare to Waranga Phata Section (Package- IV) from km
Rajendra Singh Bhamboo Infra Pvt.
563 Maharashtra 134.500 to km 174.645 (Design Chainage) of NH-161 including 161 41.645 EPC 4L 01/07/2021
Ltd.
Bypasses at Kalamanuri and Akhada Balapur
4L of Pune - Solapur Section from km. 40.00 to km. 144.40 of NH 65
564 Maharashtra 65 110.05 BOT Toll 4L 14/11/2009 Tata Realty & Atlantia
(Pkg-1)
4L of Pune Solapur Section from km. 144.40 to km.249.00 of Old NH 9
565 Maharashtra 65 101.3 BOT Toll 4L PS 28/09/2011 IL&FS Transportation Networks Ltd.
(Pkg-II)
J.M. Mhatre infra Pvt. Ltd. & S.M.
566 Maharashtra Khudus - Dharampuri km 77.8 to km 117.0 Pkg III of Mohol Alangi 965 39.2 EPC 4L 31/01/2020
Autade Pvt. Ltd. (JV)
J.M. Mhatre infra Pvt. Ltd. & S.M.
567 Maharashtra Wakhari - Khudus km 44.7 to km 77.8 Pkg II of Mohol Alangi 965 33.1 EPC 4L 31/01/2020
Autade Pvt. Ltd. (JV)
J.M. Mhatre infra Pvt. Ltd. & S.M.
568 Maharashtra Mohol - Wakhari km 0.0 to km 44.77 Pkg. I of Mohol Alangi 965 44.7 EPC 4L 31/01/2020
Autade Pvt. Ltd. (JV)
Solapur to Maharashtra - Karnataka Border Section of NH-9 from Km.
569 Maharashtra 65 100.06 BOT Toll 4L 03/06/2014 SREI
251.325 To 348.800
Solapur to Maharashtra - Karnataka Border Section of NH-9 (New NH-
570 Maharashtra 65 60 EPC 4L 12/01/2023 Triveni Mudrai Project Limited
65) from Km. 249.00 to 309.000
Solapur to Maharashtra - Karnataka Border Section of NH-9 (New NH-
571 Maharashtra 65 40.06 EPC 4L 12/01/2023 PBA Infrastructure Limited
65) from Km. 309.000 To 348.800
Pune to Solapur from Km. 14 to Km. 40 (transferred to NHAI from
572 Maharashtra 65 26 BOT Toll 4L
State PWD)
Four Laning of Akkalkot to Solapur (including Akkalkot Bypass of
573 Maharashtra 150E 38.95 HAM 4L 14/12/2018 G R Infraprojects Limited
Length 7.35 km.) from km. 99.400 to km. 138.352 of NH-150 E
574 Maharashtra Tarsod - Fagne section of NH-6 53 87.3 HAM 4L 14/01/2019 MBL Infrastructures Ltd.

Page 23 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Improvement of NH-53 passing through Jalgaon City to four lane along
575 Maharashtra 53 7 EPC 4L 06/09/2019 Jandu Construction Company
with construction of VUPs & PUP
576 Maharashtra 4L of Chikhli - Tarsod section of NH-6 from km 360.00 - km 422.700 53 62.7 HAM 4L 16/01/2019 Vishwaraj Environmental Pvt. Ltd.

One Time Maintenance/Improvement of existing road passing through


Sant Satramdas Infrastructure Private
577 Maharashtra Varangaon City (Km.387.500 to Km. 390.400)on Chikhali – Tarsod 2.9 EPC 2L 12/08/2022
Limited
(Package-IIA) Section of NH-53 in the State of Maharashtra
Balance Works of 4L Amravati - Chikhli (Pkg - I) [Amravati - Kurankhed Raj Path Infracon Pvt Ltd - Eagle Infra
578 Maharashtra 53 54 HAM 4L 10/07/2021
from km. 166.00 to km. 220.00] Ltd (Consortium)
Balance Works of 4L Amravati - Chikhli (Pkg - II) [Kurankhed - Shelad Raj Path Infracon Pvt Ltd - Eagle Infra
579 Maharashtra 53 50 HAM 4L 29/06/2021
from km. 220.00 to km. 270.00] Ltd (Consortium)
Balance Works of 4L Amravati - Chikhli (Pkg - III) [Shelad - Nandura Montecarlo Amravati Chikhli Highway
580 Maharashtra 53 45 HAM 4L 14/01/2021
from km. 270.00 to km. 315.00] Private Limited
Balance Works of 4L Amravati - Chikhli (Pkg - IV) [Nandura - Chikhli
581 Maharashtra 53 45 HAM 4L 19/05/2021 Kalyan Toll Infrastructure Ltd.
from km. 315.00 to km. 360.00]
Strengthening to Existing National Highway NH 53 passing through
582 Maharashtra 53 6.6 Item Rate 2L PS 28/10/2021 V.P. Sethi Construction
Nandura Town in Maharashtra
Upgradation of 4 laning of old NH-6 from Km.296 to 304 passing
583 Maharashtra 53 7.3 EPC 4L PS 28/08/2018 Jandu Construction Company
through Khamgaon City
Akola City -Shivar-PKV Square-Nehru Park Square - Dakshata Nagar
584 Maharashtra 6 13 EPC 2L/4L 16/08/2019 B. P. Sangle Constructions Pvt. Ltd
Square-Nimwadi Chowk -Washim Bypass -Ridhora Bypass road
Ram Kumar Contractor - Jandu
585 Maharashtra Flyovers in Akola City 53 4.8 EPC 4L PS 27/02/2019
Construction Company (JV)
586 Maharashtra Ahmednagar Bypass 222 40.6 HAM 4L 21/07/2021 GHV (India) Pvt Ltd.
4L of Ahmednagar - Mirajgaon - Karmala - Tembhurni (Pkg-I)
587 Maharashtra 516A 38.78 HAM 4L 28/12/2021 GHV (India) Pvt Ltd.
[Ahmednagar to Ghogargaon] from km. 0.00 to km. 38.775 of NH-516A
4L of Ahmednagar - Mirajgaon - Karmala - Tembhurni (Pkg-II)
Anish Infracon India Pvt. Ltd. - GHV
588 Maharashtra [Ghogargaon to Ahmednagar- Solpaur District Border] from km. 516A 41.62 HAM 4L 13/01/2022
(India) Pvt Ltd.
38.775 to km. 80.390 of NH-516A
Four Laning of Tuljapur to Ausa section (including Tuljapur Bypass of
589 Maharashtra 361 67.43 HAM 4L 22/11/2017 Dilip Buildcon Ltd.
11.593 km.) of NH-361 from Km 0.000 to Km 55.835
590 Maharashtra 4L of Ausa-Chakur Section from km 55.835 to Km 114.345 of NH-361 361 58.51 HAM 4L 25/03/2019 Gangamai Kalyan ACR Pvt. Ltd.
Chakur Loha Nanded Highways Pvt.
591 Maharashtra Chakur Loha Section of NH-361 from km 114.600 to km 187.80 361 73.35 HAM 4L 25/03/2019
Ltd.
Four Laning of Mahagaon to Yavatmal (Pkg- II) of NH-361 from km.
592 Maharashtra 361 80.19 HAM 4L 28/02/2018 Dilip Buildcon Ltd.
320.580 to km. 400.575
Four Laning of Yavatmal to Wardha (Pkg-III) of NH-361 from Km
593 Maharashtra 361 64.93 HAM 4L 05/02/2018 Dilip Buildcon Ltd.
400.575 to Km 465.500
Four Laning of Wardha - Butibori of NH-361 (Pkg - IV) from km. 465.50
594 Maharashtra 361 59.19 HAM 4L 30/11/2017 Dilip Buildcon Ltd.
to km. 524.69
Solapur Yedashi Section of NH-211 From Km. 0.000 To 100.000 in the
595 Maharashtra 52 98.72 BOT Toll 4L 21/01/2015 IRB Infrastructure Developers Ltd.
State of Maharashtra
Development of existing roads in Ule, Suratgaon, Malumbra, Tuljapur,
596 Maharashtra 52&65 22.51 EPC 2L/4L 16/11/2018 S M Autade Pvt Ltd
Shingoli, Yedeshi, Naldurg and Omerga
597 Maharashtra Yedshi (Km.100.000) to Aurangabad (Km.290.200) 52 190.2 BOT Toll 4L 01/07/2015 IRB Infrastructure Developers Ltd.
One time improvement of the bypassed stretch of Beed city from km.
598 Maharashtra 172.950 to km. 183.040 on Yedshi – Aurangabad section of NH-211 52 10.09 EPC 2L/4L 03/09/2021 Annappa Maharudrappa Guddodagi
(New NH 52)

Page 24 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
One Time Improvement of the bypass / realigned of (i) Pargaonviilage
(Km.136.761 to Km.138.700), (ii) Georai Village (Km.206.420 to
212.600) (iii) Chousala Village (Km.140.300 to Km.145.100) (iv) Pachod
599 Maharashtra Village (Km.246.160 to Km.251.100) (v) Rajapur Village (Km.268.120 to 22.87 EPC 2L 25/07/2022 V.P. Sethi Construction
Km.268.870) (vi) Adul Village (Km.270.800 to Km.273.860) and (vii)
PimpalgaonPandhari (Km.274.050 to Km.275.250) on Yedshi-
Aurangabad Section of NH-52 in the State of Maharashtra

600 Maharashtra Aurangabad - Karodi km 290.00 - km 320.104 of NH 211 (New NH 52) 52 30.44 EPC 4L 12/02/2019 Larsen & Toubro Ltd.

601 Maharashtra Karodi - Telwadi km 320.104 - km 375.00 of NH 211 (New NH-52) 52 55.61 EPC 4L/6L 09/10/2018 Dilip Buildcon Ltd.
Periodical Repairs from Km. 375.000 to Km. 390.000 including Autram Sant Satramdas Infrastructure Private
602 Maharashtra 52 15 OMT 4L 31/08/2021
Ghat of NH-52 Limited
603 Maharashtra Nagpur-Betul Section of NH-69 47 174.512 BOT Annuity 4L 28/02/2011 Oriental Structural Engineers Pvt. Ltd.
Flyover from Liberty cinema to Mental Hospital on Nagpur-
604 Maharashtra 47 3.96 EPC 4L 29/03/2017 KCC Buildcon Pvt. Ltd.
Obedullagunj road.
Development of Multi Lane Carriageway of Jalna Road in Aurangabad
605 Maharashtra city from Nagarnaka Junction to Cambridge School Road Section from 211 14.93 EPC 4L 19/03/2020 Shrushti Contech Pvt. Ltd.
km. 0.00 to km. 14.293
Balance work under Phase-I for 4L of Khed Sinner Section comprising
of the stretches (i) Khed Bypass (km 42.000 to km 46.981), (ii) Peth
606 Maharashtra 60 14.137 EPC 4L 14/10/2020 T&T Infra Pvt. Ltd.
(km 56.100 to km 56.780), (iii) Manchar bypass and (iv) linear length of
Eklahre from km 60.100 to km 68.576
Balance work of Khed Ghat realignment & Narayangaon bypass on
607 Maharashtra 60 9.31 EPC 4L Roadway Solutions India Infra Ltd.
Khed Sinnar section of NH-60
Strengthening of existing stretch (i.e. Strengthening (DBM +BC ) and
608 Maharashtra other Maintenance of 4/6L of Khed (42.00) to Sinnar (Km. 177.00) of 60 137.94 OMT 4L/6L 25/08/2020 MD-Infra India Pvt. Ltd.
Old NH - 50 (New NH - 60)
Development of existing road in Khed and Narayangaon town
609 Maharashtra 60 9.31 EPC 4L 31/08/2018 Roadway Solutions India Infra Ltd.
excluding rehabilitation of bridges on Khed Sinnar section of NH-60
4L Elevated Structure (Flyover) from Sakkar Chowk to SB Chowk on Dineshchandra R. Agrawal Infracon
610 Maharashtra 222 3.08 EPC 4L 18/12/2020
Pune - Aurangabad Road in Ahmednagar city Pvt. Ltd.
Altis - Holding Corporation and V.P.
611 Maharashtra Periodical Repairs of Jalna - Karanja - Pimpalgaon - Talegaon - Pulgaon SH207 285.4 Item Rate 2L PS 24/11/2020
Sethi Construction (JV)
Montecarlo Vadodara Mumbai
612 Maharashtra Sinnar-Shirdi (including Sinnar Bypass) 160 50.94 HAM 4L 18/08/2020
Expressway P2P1 Private Limited
JNPT Package 1 Km 3.600 to 6.073 of NH-4B and from Km 5.300 to Km J Kumar InfraProjects Ltd and J.M.
613 Maharashtra 348 4.59 EPC 6L/8L 16/05/2016
7.422 of NH-348 (old SH-54) in Maharashtra Mhatre Infra Pvt Ltd
JNPT Package 2 Gavanphata Interchange from 14.740 to Km 15.894 ( J Kumar InfraProjects Ltd and J.M.
614 Maharashtra 348 18.27 EPC 6L/8L 16/05/2016
Old SH -54) Mhatre Infra Pvt Ltd
JNPT Package 3 from Km-7.422-Km-13.160 and Amra Marg from Km- J Kumar InfraProjects Ltd and J.M.
615 Maharashtra 348A 11.09 EPC 6L/8L 16/05/2016
0.000-Km-5.360 Mhatre Infra Pvt Ltd
JNPT Package 4 FROM KM 21.200 TO KM 27.270 (D TO E SECTION)
616 Maharashtra 348 10.56 EPC 8L 16/05/2016 Ashoka Buildcon Limited
AND FROM KM 0.000 TO KM 4.492 (D TO G SECTION)
617 Maharashtra Solapur-Vijayapur 52 109.07 BOT Toll 4L 26/10/2018 IJM Corporation Berhad Ltd.
Four Laning of Sangli - Solapur (Pkg IV) [Mangalwedha-Solapur] from
618 Maharashtra 166 56.5 HAM 4L 23/05/2019 Dilip Buildcon Ltd.
km 321.6 - km 378.10
Four Laning of Sangli - Solapur (Pkg III) [Watambare-Mangalwedha]
619 Maharashtra 166 45.6 HAM 4L 31/12/2018 G R Infraprojects Limited
from km 276.0 - km 321.60
Four Laning of Sangli - Solapur (Pkg II) [Boregaon-Watambare] from
620 Maharashtra 166 52 HAM 4L 22/04/2019 Dilip Buildcon Ltd.
km. 224.00 to km. 276.00

Page 25 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Four Laning of Sangli - Solapur (Pkg I) [Sangli - Borgaon km 182.556 -
621 Maharashtra 166 41.44 HAM 4L 23/05/2019 Dilip Buildcon Ltd.
km 224.00]
4L of Nagpur - Umred section (From 7.300 km to 48.400 km of NH-
622 Maharashtra 353D 41.1 EPC 4L 09/08/2019 D.P. Jain & Co. Infrastructure Pvt. Ltd.
353D
623 Maharashtra End of Malshej Ghat - Ane Ghat from km. 101 to km. 161.57 61 60.57 EPC 2L PS 10/11/2014 SA infrastructure Consultants Pvt. Ltd.

Operation and Maintenance of NH-222 (New NH-61) from End of Ane


624 Maharashtra Ghat to start of Ahmednagar Section from ( Km 161/212 to km 61 49.43 EPC 2L PS 05/11/2014 Ashoka Buildcon Limited
210/527) NH-222 (New NH-61) in the State of Maharashtra.
Kharwandi Kasar to Junction with NH-211 (km. 284 to km. 337) section Montecarlo Vadodara Mumbai
625 Maharashtra 61 51.69 EPC 2L PS 20/11/2014
of NH-61 Expressway P2P1 Private Limited
Kalyan Toll Infrastructure Ltd. - Shelke
626 Maharashtra Patas-Vasunde Phata - Baramati Bypass 965G 41.4 EPC 4L 09/09/2021
Construction (JV)
JiangXi Construction - Agrawal Global
627 Maharashtra Warora - Wani from km. 313.850 to km. 332.160 930 18.31 EPC 4L 28/10/2019
Infratech (JV)
Maintenance of the stretch from Km 29.00 to Km 250.05 of NH-160
628 Maharashtra 160 221 OMT 2L
from Phaltan – Dahivadi – Mayani – Satara/Sangli dist. Border
4L of Jorabat Shillong (Barapani) section from 0.000 to km 61.800 of IL&FS Transportation Networks Ltd.
629 Meghalaya 6 61.8 BOT Annuity 4L 12/01/2011
Old NH-40 and Ramky Infrastructure Ltd
2L of Shillong Bypass from km. 61.80 of Old NH-40 to km. 34.85 of Old
630 Meghalaya 6 48.76 BOT Annuity 2L 07/02/2011 GR Infra Projects Ltd
NH-44
Construction of Major Bridge at Km 12.865 on Shillong bypass
631 Meghalaya 44 0.275 EPC 2L 01/09/2022 Dhariwal Buildtech Limited
connecting NH-40 & NH-44
Jowai-Meghalayal Assam Border Section of NH-44 from km 69.200 to
632 Meghalaya 6 102.25 EPC 2L PS 18/11/2015 M R Construction
km 173.200 in Meghalaya
Strengthening/ improvement including regular maintenance work
from the ch. Km 69.200 to 120.200 of the project "Two Lane with
633 Meghalaya paved shoulders configuration in Jowai Meghalaya Assam Border 6 51 Item Rate 2L PS 23/03/2024 Purbanchal Buildtech Pvt Ltd
Section of NH44(New NH-6) from Km 69.200 to Km 173.200 (design
Ch 171.455)
Strengthening/ improvement including regular maintenance work
from the ch. Km 120.200 to 171.455 of the project "Two Lane with
634 Meghalaya 6 51.255 Item Rate 2L PS 22/03/2024 Dhar Construction Company
paved shoulders configuration in Jowai-Meghalaya Assam Border
Section of NH-44 from Km 69.200 to Km 173.200 (design Ch 171.455)
Balance Work of 4/6L of existing 2L of Bhadrak (km. 136.500) to Backbone Enterprises Ltd. -
635 Odisha 16 62.64 Item Rate 4L/6L 11/11/2008
Baleshwar (km. 199.141) of NH-5 Meenakshi Infrastructure Pvt. Ltd.
636 Odisha 6L of Chandikhole (km 62.000) to Bhadrak (km136.500) 16 74.5 HAM 6L 16/12/2018 Dilip Buildcon Ltd.
4L of Chandikhole-Balasore (Contract Package OR-V from Km. 61.000 Gammon Engineers & Contractors
637 Odisha 16 138 Item Rate 4L 01/07/2017
to km. 199.141 of NH-5 (new NH-16) Pvt. Ltd.
Shree Jagannath Expressways Private
638 Odisha 6L of Bhubaneswar - Jagatpur - Chandikhole Section of NH-16 16 67 BOT Toll 6L 14/12/2011
Limited
639 Odisha Khandagiri Chowk Grade Separator (km 412.00) 16 2.23 EPC 6L 03/05/2018 RKD Construction Pvt. Ltd.
640 Odisha Tangi to Bhubaneswar (km 355.0 to km 414.0) of NH-5 (New NH-16) 16 56.78 EPC 6L 10/04/2019 Punj Lloyd Infrastructue Ltd.

641 Odisha 4L of Bhubaneswar-Sunakhala 16 78 EPC 4L 05/03/2002 Gammon Atlanta JV, SMJ-RK-SD(JV)


4/6 L of existing 2L Khurda-Bhubaneswar from Km.387.700 to
642 Odisha 16 26.3 Item Rate 4L
Km.414.000 of Old NH-5 (Contract Package OR-I)
643 Odisha Puintola to Tangi (km 284.00 to km 355.00) of NH-5 (New NH-16) 16 75.36 EPC 6L 17/12/2018 Punj Lloyd Infrastructue Ltd.
644 Odisha Puintola - Icchapuram km 419.60 - km 484.00 16 107 EPC 4L 03/04/2008 KNR Construction, KMC-RK-SD(JV)

Page 26 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
645 Odisha Puintola - Icchapuram km 419.60 - km 484.00 under TOT Bundle - 1 16 64.4 TOT 4L 11/02/2019 Puintola Tollway Private Limited
Strengthening under one time improvement of CG/OD Border -
646 Odisha 53 88 BOT Toll 4L 14/11/2011 Ashoka Buildcon Limited
Baragarh - Sambalpur from km. 0.00 to km. 88.00
Four Laning of Teleibani - Sambalpur from Km.493.30 to Km.521.30
647 Odisha 53 50.75 EPC 4L PS 25/05/2017 Punj Lloyd Infrastructue Ltd.
and Km.545.176 to Km.567.40
Repair and Maintenance of Teleibani - Sambalpur section from
648 Odisha NH-53 26.026 OMT 2L 12/01/2024 Enfive Systems Private Limited
Km.521.300 to Km.545.176 of NH-53 (Old NH-6)
649 Odisha Binjhabahal - Telebani from km. 414.000 to km. 491.71 49 78.32 HAM 4L PS 15/01/2018 Oriental Structural Engineers Pvt. Ltd.
Montecarlo Vadodara Mumbai
650 Odisha Singhara - Binjhabahal from km. 310.806 to km. 414.982 49 104.17 HAM 4L PS 28/09/2018
Expressway P2P1 Private Limited
651 Odisha Baharagora (199.606 Km) to Singhara (310.806 Km) of NH-6 49 111.61 EPC 4L PS 21/10/2017 Larsen & Toubro Ltd.
Repair & Maintenance of 2L existing road at Ghat section and elephant
652 Odisha crossing location in Buffer Zone of Similipal Tiger Reserve and in 49 22.496 Item Rate 4L 07/01/2022 Jai Mata Dee Construction
Jashipur by-pass section of NH-49
Balasore - Baripada - Jharpokharia - section of NH-5 (km 0.00 to km
653 Odisha 18 81.257 EPC 4L PS 05/01/2017 ITL-MCL (JV)
80.6)
O&M from Chainage 0+000 (Keonjhar) to Chainage 89+051 (Duburi) of
654 Odisha NH-720 89.051 Item Rate 2L/4L 16/07/2023 Fortune group
NH-720
2L PS of Kanaktora - Jharsuguda from Km 0.0 to Km 68.0 including by- Abhipsa Construction, Engineer and
655 Odisha 200 68 EPC 2L PS 29/05/2020
pass at Beipahar at Km. 52.00 of NH-200 Contractors
Repair and rehabilitation of the Major Bridge, Expansion joint,
VARSHITAH CONCRETE
656 Odisha Guniting, Epoxy Grouting, Replacement of Bearing etc. for major NH-49 0.148 Item Rate 2L 01/01/2024
TECHNOLOGIES PRIVATE LIMITED
Bridge at Km.0.065 in Kanaktora-Jharsuguda section of NH-49.
Repair and maintenance from Km. 0.000 to Km. 60.000 (Pkg-I) of
657 Odisha 20 60 Item Rate 4L RKH Construction Pvt Ltd
Panikoili – Rimuli Section of NH-215 (New NH-20)
Repair and maintenance from Km. 60.000 to Km. 113.300 (Pkg-II) of
658 Odisha 20 53.3 Item Rate 4L 15/07/2022 RKH Construction Pvt Ltd
Panikoili – Rimuli Section of NH-215 (New NH-20)
Repair and maintenance from Km. 113.300 to Km. 166.173 (Pkg-III) of
659 Odisha 20 52.873 Item Rate 4L Fortune group
Panikoili – Rimuli Section of NH-215 (New NH-20)
Urgent Repair, Maintenance & Incident Management of Panikoili-
660 Odisha Rimuli Section of NH 215 (New NH-20) from Km 0.00 to Km 163.000 in NH-20 166.173 Item Rate 4L 15/03/2024 Abhipsa Construction, Bhubaneswar.
the state of Odisha.
661 Odisha Chandikhole-Paradip 53 77 EPC 4L 19/02/2004 Hindustan Construction Company Ltd.

Short Term Improvement and Routine Maintenance of Chandikhole – Abhipsa Construction, Engineer and
662 Odisha 53 76.588 OMT 4L 16/12/2020
Paradip from Km.0.000 to Km.76.588 of NH – 53 (old NH-5A) Contractors
4 laning of End of Kamakhyanagar Bypass - Duburi from km. 335.946
663 Odisha 53 51.1 EPC 4L PS 23/02/2019 G R Infraprojects Limited
to km 388.382 (Pkg-II)
Rehabilitation and Upgradation of NH-149 from Km.0.000 to
664 Odisha Km.68.280 (Pallahara to Pitiri section) to 2-lanes with paved shoulders 149 68.28 EPC 2L 14/01/2015 KMC - RKD (JV)
under NHDO-IV in the state of Odisha on EPC Mode
665 Odisha Birmitrapur - Brahmani Bypass end of NH-23 143 29.1 EPC 4L PS 23/05/2018 GKC Projects Ltd.
Urgent Repair and Maintenance of existing road of Birmitrapur Town
666 Odisha 143 4.7 Item Rate 2L 26/12/2022 RKD Construction Pvt. Ltd.
area from Km 211.200 to Km 215.900
667 Odisha Brahmani Bypass Rajmunda 143 46.95 EPC 4L PS 31/12/2018 RKD Construction Pvt. Ltd.
668 Odisha Rimuli Koida km 163 - km 206 of NH 215 520 43.2 EPC 4L PS 12/05/2018 Montecarlo Limited
669 Odisha Koida- Rajamunda (Pkg-II) km 206.00 - km 259.453 of NH 215 520 53.25 EPC 4L 08/05/2018 KMC - RKD (JV)
Urgent Repair and Maintenance/Strengthening of existing 2-Lane
670 Odisha Road from Ch.234.280 to Ch.235.600 at Roxy (De-scoped length) in the NH-520 1.32 Item Rate 2L PS 17/01/2023 Kapilash Infrasol Projects Pvt. Ltd.
Stretch of Koida to Rajamunda Section of NH-215 (New NH-520)

Page 27 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
O&M of 4L Bhubneshwar - Puri Section from km. 0.00 to km. 56.500 of Abhipsa Construction, Engineer and
671 Odisha 316 56.5 OMT 4L 01/04/2022
NH-316 Contractors
Maintenance from Km 0.000 to Km 56.500 of Bhubaneswar-Puri
672 Odisha 316 56.5 OMT 4L 11/03/2024 Abhipsa Construction, Bhubaneswar.
Section of NH-316 (Old NH-203) in the State of Odisha.
Balance Work of Puri By Pass Road of Bhubaneswar-Puri Section from
673 Odisha 316 10.9 EPC 4L PS 20/04/2018 RKD Construction Pvt. Ltd.
km. 56.500 to km. 67.500
Jalandhar-Pathankot (Punjab/J&K Border) (from Km. 4.23 to Km. Prakash Asphaltings and Toll
674 Punjab 44 125.87 OMT 4L 28/03/2017
117.75/4.00 & km.4.00 to km. 16.35) of NH-44 Highways (India) Ltd.
4L of km. 4.230 to km. 26.00 of Jalandhar - Pathankot Section of Old
675 Punjab 44 21.77 EPC 4L 30/08/2001 Bumihiway SDN. BHD.
NH- 1A (Contract Package No. NS-16 (PB)
Bal. work of 4L of Bhogpur - Mukerian from km. 26.00 to km. 70.00 of
676 Punjab 44 44 EPC 4L 22/02/2010 IVRCL Infrastructures & Projects Ltd.
Old NH- 1A (Contract Package No. NS-38 (PB)
4L of Mukerian - Pathankot from km. 70.00 to km. 110.00 of
677 Punjab Pathankot - Jammu Section of Old NH- 1A (Contract Package No. NS-37 44 40 EPC 4L 22/11/2005 ITD Cementation India Ltd
(PB)
4L of km. 110.450 to km. 117.750 and km. 4.00 to km. 16.350 of
678 Punjab Pathankot - Jammu Section of Old NH- 1A (Contract Package No. NS-36 44 19.65 EPC 4L 22/11/2005 Venkat Rao Infra Projects Pvt. Ltd.
(PB)
Elevated structure including appraoches from km.352+675 to
679 Punjab km.354+430 and VUP at km.355+400 including approaches at 44 2.55 EPC 6L 05/07/2019 Ceigall India Ltd.
Phagwara City
Flyover at km 315.200 & entry ramp from km 320.300 to km 321.200
i/c FOB at km 320.840 and construction of Additional 2L on both sides
680 Punjab 44 3.5 EPC 6L 15/03/2021 Ram Kumar Contractor
of existing 4L ROB at km 311.865 along with approaches and VUP at
km 311.770 along with improvement of NH-44

Up gradation of existing highway Lighting on 6L Panipat-Jalandhar


681 Punjab 44 291.1 Item Rate 6L 12/11/2022 Dhingra Brothers (India)
Section of NH-44 (Old Name-NH-1) from KM 96.000 to 387.000
Rectification of Pavement Surface using Micro Surfacing (2nd Call) on
INCKAH Infrastructure Technologies
682 Punjab 6L Panipat-Jalandhar Section of NH-44 (Old Name-NH-1) from KM 44 291.1 Item Rate 6L 12/11/2022
Pvt. Ltd.
96.000 to 387.000
Construction of 6 Foot Over Bridges at various locations on Panipat -
683 Punjab 44 162 Item Rate 6L 25/09/2023 Satish Aggarwal & Co
Jalandhar section
Laddowal Bypass (Km. 0.000) to (Km. 17.041) Linking with NH-95 with
684 Punjab 5 17.04 HAM 4L 28/06/2017 Eagle Infra Pvt. Ltd.
NH-1 Via Laddowal Seed Farm of NH-95 in Punjab
Service road from km 9.135 to km 9.645, km 11.000 to km 11.450 and
685 Punjab Construction of U-Turn at km 16.632 at Ludhiana (Ladowall Bypass 95 1 Item Rate 4L/6L 30/11/2022 NKC Constructions Pvt. ltd.
Section)
4 Lane Elevated Highway between Samrala Chowk (Design Chainage
km 0+000) to Ludhiana Municipal Limit (Design Chainage km 12+951)
686 Punjab 95 3.44 Item Rate 4L/6L 26/12/2022 Rebuild struct Associates
of NH-95 in the State of Punjab-Replacement of Expansion Joints of
existing Flyovers/ROB from km 1+570 to km 5+010

4L PS Tallewal-Barnala section from existing km. 114 to km 136.07 of


687 Punjab NH-71 (New NH No. 703) including Barnala Bypass from existing km. 703 29.64 EPC 4L 14/09/2016 Shanti Road and Construction
136.070 of NH-71 to existing km. 149.00 of NH-64
Improvement of Amritsar Bypass by construction of additional
688 Punjab 3 24.55 EPC 4L 30/11/2015 Varaha Infra Ltd.
structures and service road on NH-1 (km 448.510 - km 473.068)
Short term repair, routine maintenance and incident Management of
Amritsar Taran Taran- Harike Section from Km 112.575 to Km 158.500
689 Punjab 54 55.825 Item Rate 4L 20/08/2022 Roadlink Infratech Pvt. Ltd.
of NH-15 (New NH-54) including Harike Bypass from Km 158.500 to
Km 168.400

Page 28 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Periodic Renewal and Operation and Maintenance of Amritsar Tarn-
690 Punjab Taran-Harike section from km. 112.575 to km. 168.400 in the State of 54 55.825 Item Rate 4L 01/04/2024 Satish Aggarwal & Co
Punjab.
O&M of 4L PS of Harike-Zira-Faridkot section from existing Km
691 Punjab 54 56.7 EPC 4L PS 23/06/2016 Gurbachan Singh
166.925 to 221.380 of NH-15 (New NH-54)
Faridkot-Kotkapura-Bathinda section of NH-15 (New NH.No 54) from
692 Punjab 54 62.115 EPC 4L PS 18/06/2016 Gurbachan Singh
existing Km 221.380 to Km 287.615
O&M of 4L PS of Harike-Bypass from existing Km. 158.350 to Km.
693 Punjab 54 9.9 EPC 4L 23/03/2016 S.P. Singla Construction Pvt. Ltd
166.925 of NH- 54
Rehabilitation and Up-Gradation of 4L Zirakpur to Patiala Section from
694 Punjab 07 50 Item Rate 4L 07/09/2015 VMAKS Constructions Private Limited
Km 0.000 to Km 50.000 of NH-64 (New NH-7)
4L Zirakpur to Patiala section of NH-64 (NH-07) from Km. 0.000 to
695 Punjab 64 0.8 EPC 4L 13/09/2022 VMAKS Constructions Private Limited
50.000 under NHDP -IV
Overlay work on 4-lane Rajpura to Patiala from Chainage Km.28.110 to
696 Punjab Km.50.00 and Existing Patiala Bypass Section of NH-64 (New NH-07) 64 41.17 Item Rate 4L PS 25/10/2023 Shri Balaji Constructions
from Chainage Km 50.00 to Km 69.280
Milling and BC Overlay of Zirakpur to Rajpura Section of NH-64 (New
697 Punjab 64 28.11 Item Rate 4L PS 12/12/2023 Rajinder Infrastructure Private Limited
NH-07) from Km. 0.000 to Km. 28.110
4L of Patiala bypass section from km 50.000 to km 69.870 of NH-64
698 Punjab 7 19.28 EPC 4L 17/06/2015 VMAKS Constructions Private Limited
(New NH-07)
4L of End of Patiala Bypass to start of Sangrur Bypass section from km
699 Punjab 7 41.44 EPC 4L 07/08/2015 Graystone Infratech Private limited
69.870 to km 110.720 of NH-64 (New NH-07)
Improvement and routine maintenance of 4L Patiala Bypass Section
700 Punjab 07 19.28 Item Rate 4L A. S. Patel
from Km 50.000 to Km 69.280 of NH-64 (New NH - 07)
Improvement and Routine maintenance of 4L Sangrur Bypass to
701 Punjab 07 41.44 Item Rate 4L 26/02/2015 A. S. Patel
Patiala Bypass from km 69.280 to km 110.720 of NH-64 (New NH-07)
Operation and Maintenance of 4L PS from Km 110.720 to Km 123.900
702 Punjab (Sangrur bypass) and from km 144.900 to Km 149.960 (Dhanaula 7 18.24 EPC 4L PS 01/01/2015 A. S. Patel
Bypass) of NH-64( New NH 7)
Operation and Maintenance of 4L PS of Sangrur to Dogal Kalan section
703 Punjab 52 29.585 EPC 4L 27/02/2015 Jogendra Chodhary
from km 181.805 to km 211.390 of NH-71 (new NH-52)
Operation and Maintenance of 4L PS of Dogal Kalan to
704 Punjab Punjab/Haryana border section from km 211.390 to km 238.695 of NH- 52 27.305 EPC 4L 26/12/2014 Era Infra Engineering Ltd.
71 (new NH-52)
Milling and BC overlay of four lane with paved shoulder of end of
705 Punjab Patiala bypass to end of Sangrur bypass section of NH-64 (New NH-67) 64 54.62 Item Rate 4L PS 01/02/2024 NKC Constructions Pvt. ltd.
from Km 69.280 to 123.900 in the State of Punjab.
Repair, routine maintenance and Incident Management of Start of
706 Punjab Sangrur to Punjab/Haryana Border section from Km 181.805 to Km 52 56.89 Item Rate 4L 15/12/2023 VMAKS Constructions Private Limited
238.695 of NH-71 (New NH-52)
End of Sangrur Bypass to Tapa from design Chainage 123.900 to
707 Punjab 7 46.91 EPC 4L PS 21/08/2014 A. S. Patel
144.900 & 149.960 to175.000 section of NH-64 (New NH No-7)
4L PS of Tapa to Bathinda section from Km. 168.00 to 209.500 of NH
708 Punjab 7 41.35 EPC 4L PS 28/07/2015 A. S. Patel
No. 07
4L of Malout-Mandi Dabwali section (Pkg-01) [Danewala at km 7.000 E5 Infrastructure Pvt. Ltd - Gawar
709 Punjab 09 22.5 EPC 4L 15/12/2021
to Mandi Dabwali at km 29.500] of NH-09 Construction (JV)
4L PS of Lambra – Shahkot section from existing Km. 12.000 to Km.
710 Punjab 44.600 (Design Ch. From Km. 12.120 to Km. 45.500) including 703 33.38 EPC 4L 30/09/2015 Patel Infrastructure Limited
construction of Nakodar and Shahkot bypasses of NH-71 (New NH-703)
4-laning of Ludhiana-Talwandi (km 85.98 to km 92.00) section of NH-
711 Punjab 5 6.02 EPC 4L 06/07/2015 Ceigall India Ltd.
95 under NHDP-III on EPC basis.

Page 29 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Operation and maintenance of Ludhiana-Talwandi Section of old NH-
712 Punjab 95 (New NH-05) from Km. 86.000 to Km. 151.000 and Incident 95 65 Item Rate 4L PS 01/07/2022 VMAKS Constructions Private Limited
Management System in the State of Punjab
4/6 laning of Ludhiana Talwandi section of old NH-95 (new NH-05)
from km 92.000 to 170.000 (length-78km) in the State of Punjab to be
713 Punjab 95 6.02 Item Rate 4L/6L 27/07/2022 Sri Kaushal Sharma
executed on BOT (Toll) on DBFOT basis under NHDP Phase - Balance
work of Project Highway
Proposal for kaner replacement and gap filling by new plantation on
714 Punjab the Ludhiana-Talwandi Section of Old NH-95 (new NH-05) from Km. 5 84.02 Item Rate 4L PS 26/08/2022 VMAKS Constructions Private Limited
85.980 to Km. 170.000 in the State of Punjab
Repair and Rectification of defect and deficiencies at the Risk and Cost
715 Punjab of concessionaire of Project Highway from km 92.000 to 170.000 on 95 78 Item Rate 4L/6L 30/11/2022 NKC Constructions Pvt. ltd.
Ludhiana Talwandi section of old NH-95 (new NH-05)

Rehabilitation and Strengthening work by Overlaying of 4/6 laning of


716 Punjab 95 6.02 Item Rate 4L 26/12/2022 NKC Constructions Pvt. ltd.
Ludhiana-Talwandi section from km 85.980 to 92.000 of NH-05
Operation and Maintenance including Incident Management System
717 Punjab for Ludhiana-Talwandi Section of NH-95 (New NH-05) from Km 85.980 5 84.02 Item Rate 4L PS 01/12/2023 VMAKS Constructions Private Limited
to Km 170.000
Ceigall India Ltd. - Shiv Buildtech Pvt.
718 Punjab Talwandi - Ferozepur 5 23.66 EPC 4L 15/01/2019
Ltd. (JV)
Dineshchandra R. Agrawal Infracon
719 Punjab Bhatinda - Malout from km. 0.00 to km. 38.642 7 38.67 EPC 4L 13/07/2020
Pvt. Ltd.
720 Punjab Malout - Abohar - Sadhuwali 7 65 HAM 4L 06/01/2022 Ceigall India Ltd.
Ambala - Chandigarh from km. 5.735 to km. 39.960 of Old NH-22 and
721 Punjab 152 35.1 BOT Toll 4L 10/12/2005 GMR ENERGY LTD
km. 0.000 to km. 0.870 of Old NH-21
2L PS/4L of Khemkaran to Gurdaspur (Package-II) [Khemkaran to start Ceigall India Ltd. Inderjit Mehta
722 Punjab 354 48.82 EPC 4L/2L PS 27/07/2018
of Amritsar Bypass] from km. 22.673 to km. 71.496 Construction Pvt. Ltd. (JV)
Short Term Operation & Maintenance of Khemkaran to Mannan NH-
723 Punjab 354 48.823 Item Rate 2L/4L PS 06/02/2024 Jassu Construction Company
354 from Km. 22.673 to 71.496 in the State of Punjab
2L PS/4L of Khemkaran to Gurdaspur (Package-V) [Ramdas to
Ceigall India Ltd. Inderjit Mehta
724 Punjab Gurdaspur] km 140.00 - km 187.492 and 4.19 km CoS (Kartarpur 354 51.68 EPC 4L/2L PS 13/12/2018
Construction Pvt. Ltd. (JV)
Corridor)
725 Punjab Kharar(km15.765) to Kurali(kn29.90) oh NH-205 in Punjab 205 14 EPC 4L 18/12/2016 VMAKS Constructions Private Limited
726 Punjab Kiratpur - Kurali from km. 28.60 to km. 73.20 205 44.6 BOT Toll 4L 09/02/2008 BSC-C&C Kurali Toll Road Ltd
Chandigarh (km.0.000) to Kharar (km10.185) of NH-21 and NH-95 in
727 Punjab 205 & 05 10.18 EPC 4L 09/06/2016 Larsen & Toubro Ltd.
Punjab
728 Punjab 4L of Phagwara -Rupnagar from km. 0.00 to km. 80.82 of NH-344A 344A 80.82 HAM 4L 06/10/2017 GR Infra Projects Ltd
729 Punjab 4L of Pathankot-Amritsar from km 6.082 to km 108.502 54 101.68 BOT Toll 4L 30/05/2010 IRB Infrastructure Developers Ltd.
Kharar Km. 10.185 (Design Chainage) to Samrala Chowk, Ludhiana Km
730 Punjab 5 76.01 HAM 4L/6L 15/03/2017 Ashoka Kharar Ludhiana Road Limited
86.199 (Design Chainage) In the State Of Punjab
One Time maintenance of Bypassed Section (Samrala City Road) on
731 Punjab 05 6.875 EPC 4L/6L 23/08/2021 Bhambhu Builders
Kharar - Ludhiana section of NH-05
732 Punjab Four Laning of Jalandhar-Amritsar of NH 1 from 407.1 to km 456.1 3 48.74 BOT Toll 4L 30/05/2006 IVRCL Infrastructures & Projects Ltd.
Six Laning of Jalandhar - Amritsar Section of NH-1 from Km.387.100 to Dineshchandra R. Agrawal Infracon
733 Punjab 3 20 EPC 6L 20/01/2014
Km.407.100 (Bidhipur Dhilwan) Pvt. Ltd.
Operation & Maintenance of Bidhipur To dhilwan section of NH-1
734 Punjab 3 20 Item Rate 6L 24/01/2023 Gurbachan Singh
(New NH-03) from Km. 387.100 to km. 407.100
Short Term Operation & Maintenance of Bidhipur to Verka Junction
735 Punjab Section of NH-01 (New NH-03) from Km. 387.100 to Km. 456.100 in 3 69 Item Rate 4L/6L 06/02/2024 Roadlink Infratech Pvt. Ltd.
the State of Punjab

Page 30 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Amritsar - Wagah Border section of NH-1 from km 456.100 - km
736 Punjab 3 35.93 BOT Annuity 4L 12/06/2008 Rohan Rajdeep Infra Private Limited
492.030
Road lighting work on four laning of Amritsar - Wagah section of old
737 Punjab 3 39.9 Item Rate 4L 20/02/2023 Dhingra Brothers (India)
NH -01 (new NH-03) from km. 450+000 km to km.489+900
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-04) (Ch. 78+800
738 Rajasthan 148N 36.9 EPC 8L 10/12/2019 H.G. Infra Engineering Limited
to Ch. 115+700) [HR/Raj Border to Jn. with SH-44]
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-05)
739 Rajasthan 148N 36.14 EPC 8L 10/12/2019 KCC Buildcon Pvt. Ltd.
(Ch.115+700 to Ch. 151+840) [Jn. at SH-44 to Jn. Keshopura road]

Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-06)


740 Rajasthan 148N 31.16 EPC 8L 20/11/2019 KCC Buildcon Pvt. Ltd.
(Ch.151+840 to Ch. 183+000) (Keshopura Road - Junction with NH-11)
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-07) (Ch.183.000
741 Rajasthan to Ch. 214.260) (Junction with NH-11 - Start of RoB near junction with 148N 31.26 EPC 8L 07/02/2020 Gawar Construction Ltd
NH-11A)
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-08) (Ch. 214.260
742 Rajasthan - Ch. 247.31) [Start of RoB near junction with NH-11A to Junction with 148N 33.05 EPC 8L 07/11/2020 H.G. Infra Engineering Limited
MDR-1 (Baonli-Jhalai road)]
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-16) (Ch. 427.300
Dineshchandra R. Agrawal Infracon
743 Rajasthan to Ch.452.420) [Major bridge over Takli river near Nayagaon Jageer 148N 25.13 EPC 8L 05/01/2021
Pvt. Ltd.
village to Rajasthan/MP Border]
Strengthening with Overlaying on 6L Gurgaon-Kotputli-Jaipur Section
744 Rajasthan 48 80.9 Item Rate 6L 01/08/2023 Patel Infrastructure Limited
from Km. 107.100 to Km. 188.000 of NH-48 (Old NH-8)
Strengthening with Overlaying on Six lane Gurgaon – Kotputli – Jaipur
745 Rajasthan 48 80.3 Item Rate 6L 01/08/2023 Patel Infrastructure Limited
section from Km 188.000 to Km 268.300 of NH 48 (Old NH- 8)
Routine maintenance and incident management of Gurgaon - Kotputli -
New India Contractors & Developers
746 Rajasthan Jaipur section of NH-08 (New NH-48) from Km. 107+100 to Km. NH-48 161.2 Item Rate 6L 15/12/2023
Pvt Ltd
273+000 in the state of Rajasthan
Balance works of 6L of Jaipur Ring Road from Agra Road (Km. 0.300) to
747 Rajasthan 148C 46.4 EPC 6L 18/01/2018 LR BLC - Gawar (JV)
Ajmer Road (46.700) section
GVK International NV and Leighton
748 Rajasthan Six Laning of Jaipur-Kishangarh from km 273.500 to km 363.885 48 90.39 BOT Toll 6L 01/04/2003 Contractors (India) Private Limited
with GVK International NV
Kishangarh (km 0.000) to Gulabpura (km 90.000) of NH-79A and NH-
749 Rajasthan 48 90 BOT Toll 6L 21/02/2018 IRB Infrastructure Developers Ltd.
79 in Rajasthan
Gulabpura (Km 90.000) to Chittorgarh (Km 214.870) of NH-79 in
750 Rajasthan 79 124.87 BOT Toll 6L 04/11/2017 IRB Infrastructure Developers Ltd.
Rajasthan
751 Rajasthan Chittorgarh-Udaipur Section of NH76 48 93.5 BOT Toll 6L 03/07/2017 TRIL Roads Pvt. Ltd.
Six Lane Greenfield Udaipur Bypass [Connection between NH- 76 at
752 Rajasthan Existing Km. 118.500 at Debari to NH-8 Km. 287.400 at Kaya Village] 48 23.88 HAM 6L 30/11/2017 Sadbhav Engineering Pvt. Ltd.
(Pkg-IV)
753 Rajasthan 6L of Udaipur to Shamlaji from Km 287.400 to km 401.200 of Old NH-8 48 113.8 BOT Toll 6L 03/09/2017 IRB Infrastructure Developers Ltd.
4L of Udaipur - Ratanpur - Gandhinagar (Pkg-I) from km. 278.00 to km.
754 Rajasthan 8 62 Item Rate 4L 30/10/2001 KMC Construction Ltd.
340.00 of NH-8
Swaroopganj - Pindwara Section from km. 264.00 to km. 248.70 of NH-
755 Rajasthan 27 120.02 EPC 4L 01/04/2022 Jai Buildcon Pvt Ltd
14 & Pindwara - Udaipur from km. 0.00 to km. 104.724 of NH-76
Swaroopganj - Pindwara Section from km. 264.00 to km. 249.70 of NH-
Dineshchandra R. Agrawal Infracon
756 Rajasthan 14 & Pindwara - Udaipur from km. 0.00 to km. 29.00 of NH-76 27 43.3 EPC 4L 08/12/2005
Pvt. Ltd.
(Contract Package EW-II RJ-I)
Bekaria - Gogunda from km. 29.00 to km. 73.00 of NH-76 (Contract
757 Rajasthan 27 44 EPC 4L 06/11/2005 SOMA-BSCPL (JV)
Package EW-II RJ-II)

Page 31 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Gogunda - Udaipur from km. 73.00 to km. 104.724 of NH-76 (Contract
758 Rajasthan 27 31.73 EPC 4L 14/01/2006 Ranjit Tarmat (JV)
Package EW-II RJ-III)
Kalthia Engineering & Construction
759 Rajasthan Chittorgarh - Kota 27 160.5 OMT 4L 16/12/2021
Ltd.
China Gezhouba Water &
760 Rajasthan Chittorgarh Bypass (RJ-6) km.253 to km. 213 27 40 Item Rate 4L 30/06/2005
Power(Group) Co. Ltd.
CEC - Hindustan Construction
761 Rajasthan Kota to Chittorgarh (RJ-7) km.316 to km. 253 27 63 Item Rate 4L 30/06/2005
Company Ltd. (JV)
762 Rajasthan Kota to Chittorgarh (RJ-8) km 381 to km 316 27 65 Item Rate 4L 30/06/2005 Punj Lloyd Infrastructue Ltd.
Tolling, operation, Maintenance & Transfer of Chittorgarh Bypass to National Highways Infra Projects Pvt.
763 Rajasthan 27 160.5 TOT 4L 15/12/2021
Kota Section (from km 891.929 to Km 1052.429) of NH-27 Ltd.
764 Rajasthan Kota bypass on NH-76 Contract Package (RJ-4) 27 26.42 Item Rate 4L 12/04/2006 IRB KOTA TOLLWAY PVT LTD
Cable Stayed Bridge across Chambal river on Kota Bypass (Contract
765 Rajasthan 27 1.4 EPC 6L 07/11/2006 IRB KOTA TOLLWAY PVT LTD
Package RJ-05)
766 Rajasthan Kota - Baran section of NH-27 from km. 1080.263 to km. 1184.322 27 104.06 EPC 4L 20/05/2005 Murari Lal Agrawal
Kishangarh-Ajmar- Beawar from km 364.125 - km 396.00 and km 0.00 Kishangarh-Beawar NH-8 Tollway Pvt.
767 Rajasthan 448 & 58 93.56 BOT Toll 6L 14/11/2009
to km 58.245 Ltd.
Sadbhav Engineering Pvt. Ltd.
768 Rajasthan Gomati Chauraha - Udaipur km 177.00 - km 260.100 of NH-8 58 79 BOT Toll 4L 18/04/2012
(Shreenathji Udaipur Tollway Pvt Ltd)
Sangariya (near Chautala)-Rasisar (near Bikaner) (Phase-I) (AJ/SR-
769 Rajasthan 754K 29 EPC 6L 07/10/2021 Krishna Constructions.
Package-1) From Ch. (-) 00.300 to Ch.28.700
Sangariya (near Chautala)-Rasisar (near Bikaner) (Phase-I) (AJ/SR-
770 Rajasthan 754K 24.3 EPC 6L 25/10/2021 Krishna Constructions.
Package-2)
Dineshchandra R. Agrawal Infracon
Sangariya (near Chautala)-Rasisar (near Bikaner) (Phase-I) (AJ/SR-
771 Rajasthan 754K 35 EPC 6L 17/10/2020 Pvt. Ltd. - Ganeshgarhia Construction
Package-3)
Co. (JV)
772 Rajasthan Sangariya (near Chautala)-Rasisar (near Bikaner) (AJ/SR-Package-4) 754K 27 EPC 6L 24/06/2020 Krishna Constructions.
Sangariya (near Chautala)-Rasisar (near Bikaner) (Phase-I) (AJ/SR-
773 Rajasthan 754K 25 EPC 6L 07/10/2020 Raj Shyama Constructions Pvt. Ltd.
Package-5)
Sangariya (near Chautala)-Rasisar (near Bikaner) (Phase-I) (AJ/SR-
774 Rajasthan 754K 30 EPC 6L 18/10/2020 Gawar Construction Ltd
Package-6)
Sangariya (near Chautala)-Rasisar (near Bikaner) section of NH-754K Rajendra Singh Bhamboo Infra Pvt.
775 Rajasthan 754K 30 EPC 6L 30/06/2021
(Phase-I) (AJ/SR-Package-7) Ltd.-A.G. Constructor (J.V.)
Sangariya (near Chautala)-Rasisar (near Bikaner) (Phase-I) (AJ/SR- VRC construction (India) Pvt Ltd.- S&P
776 Rajasthan 754K 25 EPC 6L 23/10/2020
Package-8) Infrastructure Developers Pvt. Ltd.(JV)
Raj Shyama Constructions Pvt. Ltd. -
777 Rajasthan Sangariya (near Chautala)-Rasisar (near Bikaner) (AJ/SR-Package-9) 754K 27.5 EPC 6L 01/07/2020
RCC Developers Ltd. (JV)
Rasisar (near Bikaner)-Deogarh (near Dhandhaniya) (Phase-I) (AJ/RD-
778 Rajasthan 754K 28.1 EPC 6L 19/10/2020 NKC Projects Private Limited
Package-1)
Rasisar (near Bikaner)-Deogarh (near Dhandhaniya) (Phase-I) (AJ/RD-
779 Rajasthan 754K 30 EPC 6L 09/01/2020 NKC Projects Private Limited
Package-2)
Rasisar (near Bikaner)-Deogarh (near Dhandhaniya) (Phase-I) (AJ/RD-
780 Rajasthan 754K 30 EPC 6L 22/01/2020 NKC Projects Private Limited
Package-3)
Rasisar (near Bikaner)-Deogarh (near Dhandhaniya) (Phase-I) (AJ/RD-
781 Rajasthan 754K 30 EPC 6L 06/12/2019 VRC-VCL-CIL JV
Package-4)
Rasisar (near Bikaner)-Deogarh (near Dhandhaniya) (Phase-I) (AJ/RD-
782 Rajasthan 754K 28 EPC 6L 25/11/2019 NKC Projects Private Limited
Package-5)
Rasisar (near Bikaner)-Deogarh (near Dhandhaniya) (Phase-I) (AJ/RD-
783 Rajasthan 754K 29.658 EPC 6L 31/07/2020 NKC Projects Private Limited
Package-6)

Page 32 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Deogarh (near Dhandhaniya)-Rajasthan/Gujarat Border (Phase-I)
784 Rajasthan 754K 22.14 EPC 6L 13/03/2020 VRC Constructions (India) Pvt. Ltd.
(AJ/DRGB-Package-1)
VRC Construction (India) Pvt. Ltd. -
Deogarh (near Dhandhaniya)-Rajasthan/Gujarat Border (Phase-I)
785 Rajasthan 754K 27 EPC 6L 12/02/2020 Varindera Construction Ltd. - S&P
(AJ/DRGB-Package-2)
Infrastructure Developers Pvt Ltd (JV)
Deogarh (near Dhandhaniya)-Rajasthan/Gujarat Border (Phase-I)
786 Rajasthan 754K 24 EPC 6L 08/12/2020 NKC Projects Private Limited
(AJ/DRGB-Package-3)
Deogarh (near Dhandhaniya)-Rajasthan/Gujarat Border (Phase-I) Lakshmi Infrastructure & Developers
787 Rajasthan 754K 25 EPC 6L 25/11/2020
(AJ/DRGB-Package-4) Pvt Ltd
Deogarh (near Dhandhaniya)-Rajasthan/Gujarat Border (Phase-I)
788 Rajasthan 754K 28 EPC 6L 18/03/2021 NG Projects Ltd.
(AJ/DRGB-Package-5)
4L of Beawar- Pali- Pindwara Section of NH 14 (km 0.000 to km
789 Rajasthan 14 244.12 BOT Toll 4L 19/12/2011 Larsen & Toubro Ltd.
244.120)
790 Rajasthan Four Laning of Mahua-Jaipur from Km 120.00 to Km 228.00 21 108 BOT Toll 4L 20/03/2006 Jaipur-Mahua Tollway Limited
791 Rajasthan 4L of Bharatpur-Mahua from km. 63.00 to km. 120.00 of Old NH 11 21 57 BOT Toll 4L 10/04/2006 Madhucon Projects Ltd

792 Rajasthan Four Laning of Agra-Bharatpur from km 17.756 to km 62.295 of NH-21 21 44.54 BOT Toll 4L 06/09/2006 Oriental Structural Engineers Pvt. Ltd.
4 Lane from Km 299.000 to 346.540 (Darah-Jhalawar-Teendhar
793 Rajasthan 52 48.88 HAM 4L 24/05/2018 Patel Infrastructure Limited
section) of NH-12.
Strengthening and Maintenance of 4L Jaipur-Reengus section of NH-52
794 Rajasthan 52 51.842 BOT Toll 4L 13/07/2023 K K Gupta Construction Pvt.
(Old NH-11) from Km. 246.300 to Km. 298.075
795 Rajasthan Reengus-Sikar Section of NH-52 52 43.887 BOT Annuity 2L PS 05/03/2012 Reengus - Sikar Exressway Pvt. Ltd.
796 Rajasthan Rajsamand-Bhilwara 758 87.25 BOT Toll 4L 09/10/2013 Sadbhav Engineering Pvt. Ltd.
797 Rajasthan Bhilwara-Ladpura 758 68 EPC 2L PS 04/03/2014 Laxmi Builders
Gangaria Baori Kalan-Serwa-Bakhasar section of NH-925 (km 0.000 to
798 Rajasthan 136.520) and Sata Gandhav Section oh NH-925-A (km 0.000 to km 925 & 925 A 196.97 EPC 4L/2L PS 24/09/2018 GHV (India) Pvt Ltd.
60.450)
Raisinghnagar - Anupgarh - Gharsana - Rojri - Sattasar - Pugal- (Part-2)
799 Rajasthan 911 162.46 EPC 2L PS 27/02/2019 G R Infraprojects Limited
(Pkg-BM/6)
Munabao(NH-25E)- Sundra- Myajlar-Dhanana-Asutar -Ghotaru-Tanot Dineshchandra R. Agrawal Infracon
800 Rajasthan 70 273.87 HAM 4L/2L PS 01/01/2019
[Design Chinange Km 0.0 to Km 46.00 and km 82.60 to Km 310.467] Pvt. Ltd.
Strengthening of the existing road from Sundra to Binjrad ka tala Via
801 Rajasthan 70 36.6 Item Rate 4L/2L PS 02/01/2024 Mundan Construction Company
myajlar from Km 46.000 to Km 82.600 of NH 70
Khajuwala-Poogal - Dantour- Jaggasar- Gokul- Goddu -Ranjeetpura-
802 Rajasthan 911 & 911 A 217.051 HAM 2L/4L 22/05/2019 Gawar Construction Ltd
Charanwala- Naukh-Bap section of NH
Rajasthan Border (Km 0.000) to Salasar (km 154.141) of NH-52 and 58 Galfar Engineering & Contracting
803 Rajasthan 52&58 154.14 BOT Toll 2L PS 06/02/2014
(old-65) in Rajasthan SAOG
Dineshchandra R. Agrawal Infracon
804 Rajasthan Salasar (Km 151.141) to Nagaur (Km 270.735) of NH-65 in Rajasthan 58 120 HAM 2L PS 28/03/2017
Pvt. Ltd.
805 Rajasthan Bikaner (km 4.20) to Phalodi (km 163.5) of NH - 15 in Rajasthan 11 159.17 BOT Toll 4L/2L PS 14/10/2015 IRCON International Limited
806 Rajasthan Phalodi (km 163.400) to Jaisalmer (km 323.857) of NH- 15 in Rajasthan 11 160.46 EPC 2L/4L 11/09/2015 Brahmaputra Infrastructure Ltd.
De-scoped section of NH-68 (Km 123.550 to 125.573) & Jaisalmer-
807 Rajasthan 6,811 162.48 Item Rate 2L PS 30/09/2023 Brahmaputra Infrastructure Ltd.
Phalodi section of NH-11 (km 105.143 to 265.600)
Bar-Bilara-Jodhpur (Km 0.000 to Km 111.000) of NH-112 in the State of
808 Rajasthan 112 109.65 EPC 4L PS 27/03/2017 Larsen & Toubro Ltd.
Rajasthan
Jodhpur Ring Road Package-I [4-laning of Dangiawas (Km. 96.595) to
809 Rajasthan 74.619 HAM 4L 14/12/2018 Gawar Construction Ltd
Jajiwal (Km. 283.500)
Bhimji Velji Sorathia Construction Pvt.
810 Rajasthan Jodhpur-Pokaran (2LPS) 125 164.43 EPC 2L PS 25/07/2015
Ltd.

Page 33 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
2L PS Jodhpur-Pokaran Section of NH-125 from km 11+000 to
Bhimji Velji Sorathia Construction Pvt.
811 Rajasthan 16+700,km 18+560 to51+740, km 53+070 to 101+400,km 126+500 to 1,25,12,51,25,125 136.143 EPC 2L/4L PS 24/06/2022
Ltd.
175+433 (Total length 136+143 km)
812 Rajasthan Jaisalmer-Barmer (4/2LPS) 68 131 EPC 2L PS 30/08/2015 Brahmaputra Infrastructure Ltd.
Jaisalmer-Barmer section of NH-68 from km 0.000 to 122.880 &
813 Rajasthan 6,868 131.414 Item Rate 2L/4L PS 17/08/2022 Brahmaputra Infrastructure Ltd.
144.500 to 153.034
Barmer-Sanchore-Gujarat Border (Upto Gandhav Bridge) Section of Bhimji Velji Sorathia Construction Pvt.
814 Rajasthan 68 106 EPC 4L/2L PS 13/08/2015
NH-15 from Km 153.000 to 259.300 Ltd.
2L PS /4L of Gandhav Bridge to Gujarat Border from km.259.300 to
815 Rajasthan 68 37.9 OMT 4L/2L PS 01/11/2019 Mahavir Sharma
km. 297.200 of NH-68
Barmer-Sanchore-Gujarat Border (Upto Gandhav Bridge) Section of Bhimji Velji Sorathia Construction Pvt.
816 Rajasthan 68 106.3 EPC 2L/4L PS 14/12/2022
NH-68 from km 153.000 to km 259.300 Ltd.
Varindera Constructions Limited
BC overlay work on Barmer Sanchore Gujarat Border (upto Gandhav
(Lead Member of JV - Varindera
817 Rajasthan Bridge) section of NH-68 from KM 153.034 to 259.300 in the State of 68 106.266 Item Rate 2L/4L PS 13/03/2024
Constructions Ltd. and Vijai
Rajasthan
Construction (India) Pvt. Ltd.)
818 Rajasthan 4 Laning of Jaipur to Deoli Section of NH-12 (Km 18.700 to km 165.000) 52 148.77 BOT Toll 4L 14/06/2010 IRB Infrastructure Developers Ltd.
819 Rajasthan Deoli (Km 165/0) to Jn. of NH-76 on Kota Bypass 12 82.52 BOT Toll 4L 05/01/2011 Shiva Build Tech
Operation & Maintenance of Four Laning of Deoli-Kota Section of NH-
820 Rajasthan 12 (New NH-52) from Km 167+624 to Km 250+144 (Approx. Length 52 82.52 OMT 4L PS 27/08/2020 Laxmi Builders
83.04 Kms)
821 Rajasthan Jhalawar- RJ/MP Border (2L PS) under Jhalawar-Biaora-Bhopal Corridor 52 62 EPC 2L PS 15/01/2014 Jogendra Choudhary

Operation & Maintenance of 2L PS of Jhalawar-Rajasthan /M.P. Border


822 Rajasthan NH-52 62.16 Item Rate 2L PS 05/12/2022 Jogendra Choudhary
section of NH-12 (NEW NH-52) from km. 346.540 to km. 408.700
2L PS of Nimbijiodha (near Ladnu) - Degana - Merta City from km. 0.00
823 Rajasthan 458 139.9 EPC 2L PS 21/01/2014 Shiva Build Tech
to km. 139.90 of NH-458
Strengthening & Maintenance of 2L PS of Nimbijiodha (near Ladnu) -
824 Rajasthan 458 128.1 EPC 2L PS 16/10/2019 LNA Infraprojects Pvt. Ltd
Degana- Merta City from km. 0 to km. 139.90 of NH-458

Strengthening and Maintenance 2L PS of Nimbijiodha (near Ladnu) -


825 Rajasthan 458 128.1 PBMC 2L PS 01/07/2023 LNA Infraprojects Pvt. Ltd
Degana - Merta City from km. 0.00 to km. 139.90 of NH-458 pkg-1
826 Rajasthan Jodhpur - Pachpedra Pkg-I(2/4 LPS) 25 86 EPC 2L PS 18/10/2014 Sadbhav Engineering Pvt. Ltd.
Operation & Maintenance of 2L PS of Jodhpur-Pachpadra section of
827 Rajasthan 25 84.165 EPC 2L/4L PS 30/01/2023 Mahavir Sharma
NH-25 from km. 95.140 to 114.610 and from km. 116.060 to 180.755
Kalthia Engineering & Construction
828 Rajasthan Bagundi - Barmer (2LPS) 25 74 EPC 2L PS 17/10/2014
Ltd.
Dilip Buildcon Ltd. -Ranjit Buildcon
829 Rajasthan Gulabpura(Km 69.267) to Uniara(282.936) of NH-148D in Rajasthan 148D 203.97 EPC 2L PS 30/10/2015
Ltd (JV)
830 Rajasthan Manoharpur - Dausa section of NH-11 A (New NH-148) 148 62.31 EPC 2L PS 20/10/2016 H.G. Infra Engineering Limited
Short Term Improvement & Routine Maintenance of Two-lane with
paved shoulders of Manoharpur-Dausa section of NH-11A (New NH-
831 Rajasthan 148 62.318 Item Rate 2L PS 08/09/2023 Espan Infrastructure (I) Limited
148) from Km. 0.000 (Design Ch. 0.000) to Km. 62.318 (Design Ch.
62.318)
Dausa - Lalsot - Kothun section of NH11 A Extn. (Ch. 0.000 to Ch.
832 Rajasthan 23 & 148 83.45 HAM 4L/2L PS 31/05/2017 PNC Rajasthan Highways Pvt. Ltd.
83.453)
833 Rajasthan 2L PS of Karauli - Dholpur from km 83.960 to 184.460 of Old NH-11B 23 100.9 EPC 2L PS 16/09/2014 SRSC INFRA PRIVATE LIMITED
834 Rajasthan Padhi (km 180.000) to Dahod (km 265.59) of NH-113 113 85.59 EPC 2L PS 19/11/2014 Mohandas V Rajani
835 Rajasthan Uncha Nagla - Dholpur Section of NH-123 (0.000 to 75.008). 123 75 EPC 2L PS 24/02/2016 H.G. Infra Engineering Limited
836 Rajasthan Parsoli - Gulabpura 148D 69 EPC 2L PS 11/01/2014 Laxmi Builders

Page 34 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Maintenance of 2L PS of Bheem - Gulabpura including Parasoli Bypass
837 Rajasthan NH 148D 69.267 EPC 2L PS 01/09/2020 Laxmi Builders
from KM 0.000 to KM 69.267 of NH-148D
Two Laning with paved shoulders of Bheem-Gulabpura including
838 Rajasthan Parasoli Bypass from Km 0+000 to Km 69+267 of NH-148D (Package-I NH-148 D 69.267 PBMC 2L PS 28/02/2024 Murari Lal Agrawal
& II)
Tonk (Km 1.300) to Sawaimadhopur (Km 69.750) of NH-116 in
839 Rajasthan 552 66.8 EPC 2L PS 18/01/2017 H.G. Infra Engineering Limited
Rajasthan
840 Rajasthan Lambia - Raipur (Package-II) from Km.163.800 to Km.218.563 458 54.76 EPC 2L PS 30/06/2014 GR Infra Projects Ltd
841 Rajasthan Lambia - Raipur (Package-II) from Km.163.800 to Km.216.600 458 54.76 Item Rate 2L PS 09/04/2022 Parul Construction Company
Strengtheing, Short term Improvement and Reparing Maintenance on
842 Rajasthan Lambia-Raipur Section Of NH-458 (Package -||) From Km. 458 54.763 Item Rate 2L PS 29/03/2024 Shri Balaji Constructions
163.800(Existing Chainage Km.218.563)
Operation and Maintenance of Maduravoyal to Sriperumbudur from
843 Tamil Nadu 48 23.2 OMT 4L 01/04/2023 Govindaraj Contractor & Earth Movers
Km 13.800 to km 37.000 section of NH-4
844 Tamil Nadu Four laning of Hathipalli to Hosur from km 33 to km 48.6 44 15.59 EPC 4L 29/12/1999 Reliance Infrastructure Ltd.
6-laning of Hosur to Krishnagiri from Km.33.13 to Km. 93.000 on NH7
845 Tamil Nadu 44 59.87 BOT Toll 6L 07/06/2011 Reliance Infrastructure Ltd.
under NHDP-V
Shakthikumar M Sanchetti Ltd &
846 Tamil Nadu Four laning of Hosur to Krishnagiri 44 45.4 EPC 4L 26/02/2002
Bholasingh Jaiprakash ConstLtd(JV)
6-laning of Krishnagiri (Km.0.000) to Walajahpet (Km.148.300) section
847 Tamil Nadu 48 148.3 BOT Toll 6L 07/06/2011 Larsen & Toubro Ltd.
on NH-46 under NHDP-V
848 Tamil Nadu Four laning of Krishnagiri to Vaniyambadi 48 50.11 EPC 4L 20/11/2002 Patel - KNR (JV)
849 Tamil Nadu Four laning of Vaniyambadi to Pallikonda 48 50.76 EPC 4L 21/11/2001 ITD Cementation India Ltd
850 Tamil Nadu Four laning of Pallikonda to Walajahpet 48 47.33 EPC 4L 20/02/2004 ITD Cementation India Ltd
851 Tamil Nadu Four laning of Walajahpet to Kancheepuram 48 36.2 EPC 4L 23/03/2002 Larsen & Toubro Ltd.
852 Tamil Nadu Four laning of Kancheepuram to Poonamallee km 70.2 - km 13.8 48 56.4 EPC 4L 31/05/2005 Afcon Infrastructure Ltd.
4 Grade Seperated Structures (Padi, Kathipara, Maduravoyal &
Som Dutt Builders - Simplex
853 Tamil Nadu Koyambedu - Improvement of Access to GQ by Free Flow Facilities 4, 5 & 205 3.8 Item Rate 2L 07/04/2005
Infrastructure Ltd.
along NH4, 5 & 205 within Chennai City
6 laning of Balance Work of Chennai - Tada from km. 21.40 to km.
854 Tamil Nadu 16 33 EPC 6L 28/03/2018 SPL Infrastructure Pvt. Ltd
54.40
855 Tamil Nadu 4 laning of Chennai - Tada from km. 11.000 to km. 52.800 16 42.8 EPC 4L 08/06/2001 Larsen & Toubro Ltd.
Operation & Maintenance of Chennai Tada Section of NH-5 from
856 Tamil Nadu NH-5 10.4 OMT 4L PS 27/07/2023 Sai Balaji constructions
Km.11/000 to Km.21/400
Krishnagiri - Thumbipadi - Thoppur Ghat - Omalur from km. 94.00 to
857 Tamil Nadu 44 86 BOT Toll 4L 15/07/2006 Larsen & Toubro Ltd.
km. 180.00 (Package No. NS-2/BOT/TN-1)
4 laning of km 156.000 to km 163.400 of Thoppurghat section on NH-7
858 Tamil Nadu 44 7.4 EPC 4L PS 29/12/1999 PT Sumber Mitra Jaya
in the State of TamilNadu (Pack No. NS-14/TN)
Four laning of from km.163/400 to km.180/00 from Thoppurghat to
859 Tamil Nadu Thumbipadi section of NH-7 in the State of Tamil Nadu - (Contract 44 16.6 EPC 4L PS 27/02/2005 JSR Constructions (P) Ltd
Package no.NS-25-TN)
Thumbipadi-Namakkal from km. 180.00 to km. 248.625 (Package No.
860 Tamil Nadu 44 68.63 BOT Toll 4L 15/08/2006 IRB Infrastructure Developers Ltd.
NS-2/BOT/TN-02)
Four laning of Km 180.000 to 199.200 of Bangalore - Salem - Madurai
861 Tamil Nadu section of NH-7 (Thumbipadi to Namakkal) in the state of Tamilnadu 44 19.2 EPC 4L PS 30/08/2001 Bhagheeratha Engineering Ltd
Contract package No. NS-26/TN
862 Tamil Nadu Namakkul - Karur section including Namakkul Bypass 44 41.37 BOT Toll 4L 29/07/2006 Reliance Infrastructure Ltd.
Four laning of Namakkal Bypass of NH-7 in the State of Tamil Nadu
863 Tamil Nadu 44 8.4 EPC 4L 30/08/2001 VIijay Engineering Enterprises
(Contract Package no.NS-27-TN)
Rectification of Black Spot TN-(02)-641 by constructing a VUP(VUP-
864 Tamil Nadu 12x5.5M) at Km.278.020 (Thavittupalayam Village) in the project of 44 1 EPC 4L 10/11/2021 VALAR & CO
Namakkal – Karur section of NH-44 (Old NH-7)
Start of Karur Bypass - Dindigul from km. 292.600 to km. 305.600
865 Tamil Nadu 44 77.725 BOT Toll 4L 17/10/2006 TN (DK) Expressways Ltd.
(Contract Package No. NS2/BOT/TN-4)

Page 35 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Rectification of Black Spot TN-02 (287) by Construction of 6L V.U.P at
866 Tamil Nadu Km 349.770 on NH-44, RE Wall & RE Wall approaches, 2L Service Road 44 0.67 EPC 4L 26/06/2022 TTK Construction
(B/s), Reconstruction/Widening of Culverts
Rectification of Blackspot (TN-02-596) by Construction of 4L V.U.P at
867 Tamil Nadu Km 290.153 on NH-7 (New no. NH-44) Semmadai, RE Wall & RE Wall 44 0.7 EPC 4L 27/07/2022 TTK Construction
approaches, 2L Service Road (B/s)
868 Tamil Nadu Dindigul Bypass - Samyanallore from km. 373.275 to km. 426.00 44 53.05 BOT Toll 4L 29/07/2006 Reliance Infrastructure Ltd.
869 Tamil Nadu Madurai - Kanyakumari from km. 0.00 to km. 243.170 44 243.17 EPC 4L 30/11/2005 Cube Highway
Madurai to Kanyakumari from Km 000.000 to Km 52.300 Section of
870 Tamil Nadu 7 52.3 TOT 4L 20/10/2020 Cube Highway
NH 7 under TOT Bundle-3
Madurai to Kanyakumari from Km 52.300 to Km 116.500 Section of
871 Tamil Nadu 7 64.2 TOT 4L 20/10/2020 Cube Highway
NH 7 under TOT Bundle-3
Madurai to Kanyakumari from Km 116.500 to Km 180.00 Section of
872 Tamil Nadu 7 63.5 TOT 4L 20/10/2020 Cube Highway
NH 7 under TOT Bundle-3
Madurai to Kanyakumari from Km 180.00 to Km 243.470 Section of
873 Tamil Nadu 7 63.47 TOT 4L 20/10/2020 Cube Highway
NH 7 under TOT Bundle-3
Salem - Kumarapalaym from km. 0.00 to km. 53.00 (Package No. NS-
874 Tamil Nadu 47 53.53 BOT Toll 4L 19/07/2006 IVRCL Infrastructures & Projects Ltd.
2/BOT/TN-06)
Kumarapalayam - Chengalpalli from km. 53.525 to km. 102.035
875 Tamil Nadu 47 48.51 BOT Toll 4L 20/07/2006 IVRCL Infrastructures & Projects Ltd.
(Package No. NS-2/BOT/TN-07)
Chengapalli (km 102.035) to Neelambur (Km144.680) and Madukkarai
876 Tamil Nadu 544 54.87 BOT Toll 4L/6L 09/09/2010 IVRCL Infrastructures & Projects Ltd.
(Km 170.880) to Walayar (K183.010) (Package No. NS-2/BOT/TN-08)
877 Tamil Nadu Salem - A.Pallipatti from km. 0.00 to km. 35.60 in Tamil Nadu 179A 35.6 OMT 2L
Four laning of km 199/200 to km 207/600 of Salem Bypass Section on
878 Tamil Nadu 44 8.4 EPC 4L PS 29/12/1999 SRC Projects Pvt Ltd
NH-7 in the State of TamilNadu (Pack No. NS-12/TN)
Jittandahalli to Dharampuri Section of NH-844 from km 60.100 to km Dineshchandra R. Agrawal Infracon
879 Tamil Nadu 844 34.36 HAM 4L 22/08/2021
94.460 [Hosur to Dhamrapuri Pkg-3] Pvt. Ltd.
Maintenance of Existing two laning from KL/TN border to Kanyakamri
880 Tamil Nadu in the section Km 599.000 to 655.000 (one time improvement as NH47 21.236 Item Rate 2L 01/08/2022 KCC Buildcon Pvt. Ltd.
Deposit work in selected stretch)
Operation & Maintenance of Nagercoil – Kavalkinaru Section from Km
881 Tamil Nadu 944 16.276 EPC 4L/2L PS 09/12/2022 KL Enterprices
0/000 to Km 16/276 of NH944(EPC) in the State of Tamil Nadu.
Hindustan Construction Co Ltd
882 Tamil Nadu Chennai Bypass 32&48 32.6 EPC 6L 15/06/1998
Mumbai & IJM-SCL Joint Venture
6L of Chennai Bypass Phase - II connecting NH-4 and NH-5 and
883 Tamil Nadu widening of Chennai Phase -I connecting NH-45 and NH - 4 (From Km 32 32.6 EPC 6L 15/05/2005 Jogendra Chodhary
0/00 to Km.32.600)
Four Laning of Tambaram - Tindivaram section of Old NH 45 from Km
884 Tamil Nadu 32 93 BOT Annuity 4L 26/06/2002 M. Sindhu
28.000 to Km 121.000
8L widening of Vandalur - Guduvanchery Section from km. 32.700 to
885 Tamil Nadu 45 5.3 EPC 8L 09/03/2019 Suganya Constructions
km. 38.00 of NH-45
8L of Guduvanchery (Km 38.00) - Maraimalai Nagar (km 42.00) -
886 Tamil Nadu Singaperumal Koil (47.00) - Chettipuniyam Mahindra city (51.300) 45 13.3 EPC 8L 01/04/2021 KCP Engineers Pvt. Ltd..
Section of NH 45
4L Tambaram to Tindivanam section of NH-32 (Old NH-45) from km
887 Tamil Nadu NH-32 93 OMT 4L 21/10/2022 Sindhu Muruga Construction Pvt. Ltd.
28.000 to km 121.000
Construction of Foot Over Bridge at km 40.420 (Potheri) on Tambaram
888 Tamil Nadu NH-32 0.003 Item Rate 8L 18/08/2022 Govindaraj Contractor & Earth Movers
– Tindivanam section of NH-45
Construction of Foot Over Bridge at km 43.600 (Maraimalai Nagar) on
889 Tamil Nadu NH-32 0.003 Item Rate 8L 16/06/2022 Govindaraj Contractor & Earth Movers
Tambaram – Tindivanam section of NH-45

Page 36 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Construction of 06 Nos of New Toilet Blocks and Repairing 14 Nos of
890 Tamil Nadu existing Toilet Blocks under Swatch Bharat Mission on Tambaram NH-32 0.001 Item Rate Others 31/01/2024 Bridge and Roads
(Km28/000) to Tindivanam (Km121/000) Section of NH32(Old NH-45)
891 Tamil Nadu Tindivanam - Ulundurpet from km 121.00 to km 193.90 45 72.9 BOT Toll 4L 16/10/2006 Ulundurpet Expressways Pvt. Ltd
Four Laning of Ulundupet-Padalur from km. 192.25 to km. 285.00 of IJM Corporation Berhad Ltd. -
892 Tamil Nadu 38 93.89 BOT Toll 4L 26/12/2006
Old NH-45 (Pkg VI-B) Shapoorji Pallonji & Co. Ltd.(JV)
4L of Padalur - Trichy section from km. 285.00 to km. 325.00 of NH -
893 Tamil Nadu 45 38.42 BOT Toll 4L 25/11/2006 Indu Navayuga Infra Projects Pvt. Ltd.
45 (Pkg VI-C)
Four Laning of Trichy Bypass - Tovarankurichi - Madurai from km. 0.00
894 Tamil Nadu 38 124.84 EPC 4L 09/02/2006 Agarwal - JMC (JV)
to km. 124.840 of Old NH-45B
O&M of 4L Trichy Bypass from Tovarankurichi - Madurai ( km. 0.00 to
895 Tamil Nadu 38 124.8 Item Rate 4L 18/07/2018 M/s. V.M. and Co.
km. 124.840) of Old NH-45B
896 Tamil Nadu Madurai - Tuticorin section from Km 138.800 to Km 266.865 38 128.065 Item Rate 4L 29/09/2023 SK Constructions
2 lane with paved shoulders of Karur - Kangeyam section of NH-67 (KC-
897 Tamil Nadu 67 59.2 EPC 2L PS 20/08/2006 SRC Projects Pvt Ltd
1)
2 lane with paved shoulders of Kangeyam - Coimbatore section of NH-
898 Tamil Nadu 67 55.2 EPC 2L PS 20/08/2007 SRC Projects Pvt Ltd
67 (KC-2)
899 Tamil Nadu Trichy (135.800) to Karur (218.000) section of NH-67 - Trichy Bypass 81 79.82 BOT Toll 4L/2L PS 19/07/2007 Reliance Infrastructure Ltd.
4L Multi-span Flyover at Km 127+700 (BHEL) on Thanjavur - Trichy
900 Tamil Nadu 83 1.2 Item Rate 4L 30/09/2019 SD Infra Contractor
section of NH-83 for Blackspot removal
Operation and Maintenance including Incident Management for One
901 Tamil Nadu year from Km 80.000 to Km 136.490 of Thanjavur to Trichy Section of 83 56.49 Item Rate 4L 26/09/2023 SK Empire
NH-67 (New NH-83)
Thanjavur - Pudukkottai section of NH 226 from Km.0/000 to
902 Tamil Nadu 36 55.23 EPC 2L/4L 14/11/2014 Sharvaa Associates
Km.55/228
903 Tamil Nadu Tuticorin - Tirunelveli from km. 0.00 to km. 47.250 138 47.25 EPC 4L 25/04/2010 Transstroy - OJSC (JV)
Emergency Repair for Existing Carriageway from Mugaiyur
904 Tamil Nadu (Km.86+115) to Koonimedu (Km.130+000) on Chennai to Puducherry NH-332A 43.885 Item Rate 2L 22/12/2022 M. Muthukrishnan, Tirunelveli
section of NH-332A (ECR)
One Time Maintenance and Enhancing Safety Provisions on Existing
905 Tamil Nadu Carriage Way from Mamallapuram (Km.52+900) to Koonimedu NH-332A 77.1 Item Rate 2L 13/01/2023 EKK Infrastructure Limited
(Km.130+000) on Chennai to Puducherry section of NH-332A (ECR)
4L of Natham - Thuvarankurichi from km. 36.69 to km. 61.115 of NH-
906 Tamil Nadu 785E 24.42 EPC 4L 28/02/2020 R R Infraa Construction
785E
Operation & Maintenance of Ennore Expressway from Km 0.000 to Km
7.538, Manali Oil Refinery Road from Km 0.000 to Km 5.600,
907 Tamil Nadu SH-56 29.138 EPC 4L/6L 01/11/2023 Lucky Associates
Thiruvottiyur – Ponneri - Panchetti Road from Km 4.500 to 13.500 and
Inner Ring Road from Km 18.000 to 25.000
Four Laning of Trichy - Dindigul from km. 333.00 to km. 421.273 of NH-
908 Tamil Nadu 83 88.27 BOT Toll 4L 15/01/2008 Reliance Infrastructure Ltd.
45
Balance work of Dindigul - Theni from km. 2.75 to km. 73.40 of NH-
909 Tamil Nadu 45E and 220 44.06 Item Rate 2L PS 09/09/2019 EKK Infrastructure Limited
45E and Theni - Kumili from km. 215.5 to km. 273.60 of NH-220
Operation and Maintenance including Incident Management from Km
910 Tamil Nadu 2+750 to Km 136+543 in Dindigul to Kumili Section of NH-183 (Old NH- 183 133.793 OMT 2L PS 30/01/2023 T. Ramar
45E & 220)
Pollachi to Coimbatore Section from km. 123.55 to km. 150.40 of
911 Tamil Nadu 83 26.85 EPC 4L PS 01/12/2016 B.V.K.Reddy
Dindigul - Bangalore Road
Short Term Maintenance of Coimbatore to Pollachi Section (Km 0+000
912 Tamil Nadu NH 83 27.03 EPC 4L PS 09/02/2024 B. Venkata Krishna Reddy
to Km 27+030 of NH 209 (New NH 83)) in the State of Tamilnadu
913 Tamil Nadu Oddanchatram - Madathukulam from km. 29.00 to km. 74.38 83 45.38 HAM 4L PS 05/10/2020 KNR Constructions Limited

Page 37 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
4L of Madathukulam - Pollachi from km. 74.38 to km. 116.95 of old
914 Tamil Nadu 83 50.07 HAM 4L 04/12/2020 D.P. Jain & Co. Infrastructure Pvt. Ltd.
NH-209 (New NH-83)
Oddanchatram Bypass from Km 23.100 to Km 33.200 of NH-209 in Om Sakthi Constructions - I.Vetrivel
915 Tamil Nadu 83 10.1 EPC 6L 22/11/2017
Tamil Nadu (JV)
Madurai - Paramakudi and 2 lane with paved shoulders of Paramakudi
916 Tamil Nadu 85&87 115.48 EPC 4L/2L PS 21/05/2015 KNR Constructions Limited
- Ramanathapuram section of NH-49
Operation and Maintenance including Incident Management for 6
Months of Four laning of Madurai - Paramakudi section from Km
917 Tamil Nadu 5/000 to Km 81/064 and Two laning with Paved Shoulders of 8,587 115.484 Item Rate 4L/2L PS 11/11/2023 Shri B. Murugan
Paramakudi – Ramanathapuram section from Km 81/064 to Km
120/484 of NH-49 (New NH-85 & 87)
Strengthening and Periodic Renewal of Trichy – Karaikudi Section of
918 Tamil Nadu 3,36,36,53,683 106.968 Item Rate 2L PS 02/04/2023 V. Rasappan & Co.
NH-210 including Trichy Bypass of NH-67
Karaikudi - Ramanathapuram section from Km.94/000 to Km.174/000
919 Tamil Nadu 536 80 EPC 2L PS 01/11/2017 DRA-SP-VM(JV)
including 500 m on SH 35
Trichirapalli (Km 0.000) to Kallagam (Km. 38.700) of NH-227 in Tamil
920 Tamil Nadu 81 38.7 HAM 4L 01/03/2019 KNR Srirangam Infra Pvt. Ltd
Nadu
Kallagam (km.38.700) to Meensurutti (Km.98.433) of NH-227 in Tamil Kallagam Meensurutti Highways Pvt.
921 Tamil Nadu 81 59.73 HAM 4L/2L PS 23/04/2019
Nadu Ltd.
922 Tamil Nadu Meensurutti (Km.98.433) to Chidambaram (Km.129.965) of NH-227 227 31.53 HAM 2L 09/08/2021 Sunway RNSIL MC Pvt. Ltd

923 Tamil Nadu Salem - Ulundurpet section from km 0.313 to km 136.670 of NH-68 79 136.36 BOT Toll 2L/4L 15/01/2008 Reliance Infrastructure Ltd.
924 Tamil Nadu Thirumayam - Manamadurai 36 77.73 EPC 2L PS 17/07/2014 V. M and CO
Thirumayam - Manamadurai Section of NH-226 (New NH No. 36) from
925 Tamil Nadu 36 77.729 EPC 2L PS 21/09/2022 V. M and CO
Km.77.200 to Km.154.929
Nagarjuna Construction Company
926 Tamil Nadu,Puducherry Four Laning of Pondicherry - Tindivanam from km. 0.00 to km. 37.29 66 38.62 BOT Toll 4L 15/01/2008
Limited.
927 Telangana AP/Mah Border-Islam Nagar (AP 6) 44 55 BOT Annuity 4L 02/11/2007 Adilabad Expressway Pvt. Ltd
928 Telangana Islam Nagar-Kadthal (AP 7) 44 53 BOT Annuity 4L 11/06/2007 Patel - KNR (JV)
929 Telangana Four-laning of Kadtal to Armur from km.278.0 to km.308.0 of Old NH-7 44 30.9 BOT Annuity 4L PS 30/10/2007 Nirmal BOT Ltd
930 Telangana Armur - Adloor Yellareddy (Nagpur-Hyderabad) 44 60 BOT Toll 4L 02/02/2010 Navyuga Road Projects Pvt Ltd.
Km 367.000 (Adloor Yellareddy) to Km 447.000 and Improvement,
931 Telangana Operation & Maintenance of Km 447.000 to Km 464.000 (Gundla 44 103 BOT Annuity 4L 26/09/2006 GMR Infrastructure Ltd
Pochanpalli) on Nagpur - Hyderabad section of NH-44 AP-2
4L of Gundlapochanpally to Bowenpally from km. 464.000 to km.
932 Telangana 474.000 of Nagpur-Hyderabad Section of NH-7 (New No. NH-44) 44 10 EPC 4L 16/06/2021 KLR constructions
Contract Package No: NS-23 (TS)
933 Telangana Construction of two VUPs at Kompally on Nagpur - Hyderabad section 44 0 EPC 4L 05/05/2018 GHAI Construction Ltd.

934 Telangana Thondupally-Jadcherla 44 58 BOT Toll 4L 19/08/2006 Jadcherla Expressways Private Limited
935 Telangana Jadcherla-Kothakotta Bypass 44 56 BOT Toll 4L 19/08/2006 Larsen & Toubro Ltd.
936 Telangana Mangloor to Telangana Maharashtra Border 161 49 HAM 4L 12/04/2019 Dilip Buildcon Ltd.
937 Telangana Sangareddy - Nanded (Pkg. II) Ramsanpalle to Mangloor 161 46.8 HAM 4L 02/05/2019 KNR Constructions Limited
Ashoka Kandi Ramsanpalle Road
938 Telangana Sangareddy - Nanded - Akola (Pkg-I) [From Kandi to Ramsanpalle] 161 40 HAM 4L 05/10/2020
Private Limited
Adani Enterprises Ltd. and Prakash
939 Telangana 4L of Suryapet to Khamam from Km. 0.420 to Km.59.046 of NH 365BB 365BB 58.62 HAM 4L 27/12/2019 Asphaltings & Toll Highways (India)
Ltd.
Operation and Maintenance of 2L from Khammam 0.000 Km to
940 Telangana 365 BB 122.2 EPC 2L
Aswaraopet 122.200 Km. from NH365 BB
941 Telangana Kalyan to Nirmal Section from km. 615.00 to km. 668.60 61 54 EPC 2L PS 12/03/2014 Annapurna Constructions

Page 38 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
942 Telangana Hyderabad-Yadagiri 163 36 BOT Toll 4L 30/07/2010 Sadbhav Engineering Pvt. Ltd.
943 Telangana Yadagiri (km 54.000) to Warangal (km 150.000) of NH-163 in Telengana 163 99.1 EPC 4L 01/06/2016 Larsen & Toubro Ltd.
4L VUP at Aler-Jeedikal Cross Road at Km 72.010 along with
944 Telangana 163 1.68 EPC 4L 01/09/2021 Rockeira Engineering LLP
Slip/Service Roads on Hyderabad- Warangal section of NH-163
4L of NH-363 from Repallewada from Km.288.510 to TL/MH Border
945 Telangana 363 52.6 HAM 4L 01/03/2021 Dilip Buildcon Ltd.
Km.342.00
Adani Enterprises Ltd. and Prakash
946 Telangana 4L of Mancherial to Repallelwada km 251.900 to km 288.510 363 42 HAM 4L 17/08/2020 Asphaltings & Toll Highways (India)
Ltd.
947 Telangana AP/Telangana Border to Rudrampur section of NH-221 (New NH-30) 30 49.17 EPC 2L/4L 24/12/2014 Abhipsa Construction, Bhubaneswar.
948 Telangana Mangalwarpet to Mallampalli Section 365 33 EPC 2L 12/03/2014 Dilip Buildcon Ltd.
O&M of existing stretch from Km 125.00 to Km 248.00 of Warangal-
949 Telangana 563 123 EPC 2L PS
Khammam section of NH-563
950 Telangana Hyderabad to Dindi Section from km. 23.00 to km. 108.80 765 85.8 EPC 2L PS 12/03/2014 G.R Engineers & Contractors
951 Telangana Thanamcherla-Jamandlapally (2LPS) 365 48 EPC 2L PS 12/03/2014 SK Constructions
Periodic Renewal of 2L of Sangareddy - Narasapur - Toopran - Gajwel -
952 Telangana 161AA 158 EPC 2L
Choutippal of NH-161AA
953 Telangana,Andhra Pradesh Kothakota bypass–Kurnool 44 74.62 BOT Annuity 4L 01/09/2006 IL&FS-CTNL Consortium

954 Telangana,Andhra Pradesh Hyderabad-Vijayawada 65 182 BOT Toll 4L/6L 06/04/2010 GMR Infrastructure Ltd
Eastern Peripheral Expressway Package - II from km 22.000 to km
955 Uttar Pradesh NE-II 25 EPC 6L 14/09/2015 Sadbhav Engineering Pvt. Ltd.
46.500 in the State of Haryana and Uttar Pradesh
Eastern Peripheral Expressway Package - III from km 46.500 to km
956 Uttar Pradesh NE-II 25 EPC 6L 14/09/2015 Jaiprakesh Associates Ltd.
71.00 in the State of Uttar Pradesh
Eastern Peripheral Expressway Package - IV from Km 71.000 to Km Ashoka Khairatunda Barwa Adda
957 Uttar Pradesh NE-II 22 EPC 6L 14/09/2015
93.000 in the state of Uttar Pradesh Road Limited
Eastern Peripheral Expressway Package - V from Km 93.000 to Km
958 Uttar Pradesh NE-II 21 EPC 6L 14/09/2015 Oriental Structural Engineers Pvt. Ltd.
114.000 in the state of Haryana and Uttar Pradesh.
Six Laning of Delhi - Agra section from Km.20.500 to Km.200 in the
959 Uttar Pradesh 19&44 179.5 BOT Toll 6L 16/10/2012 Reliance Infrastructure Ltd.
State of Haryana and U.P.
Grade seperated Structures including Highways at refinery Township
960 Uttar Pradesh 2 0 EPC 2L PS/MIP
Gate in NH-2 near Mohini Petrol P
961 Uttar Pradesh Construction of FOB across (i) Langde ki Chowki (ii) Lalaki Dargah 2 0 EPC Others 07/06/2018 Spacechem Enterprises
Chaudhary Construction Company
962 Uttar Pradesh Construction of 14 no. FOB on NH-2 in Mathura District 2 0 EPC Others 07/06/2018
Pvt. Ltd.
Additional Structures under Six Laning of Delhi-Agra section of NH-44
963 Uttar Pradesh 44 0 EPC 6L 01/01/2020 Atlas Construction Pvt. Ltd.
in the State of Uttar Pradesh between km. 143.0 and km. 195.10
Short term improvement and routine maintenance of 6L Delhi - Agra
964 Uttar Pradesh section from Km. 20.500 to Km. 200.00 of NH-2 in HR/UP for six 19 179.5 Item Rate 6L 20/05/2020 SEC Buildtech Pvt. Ltd.
months.
Providing and fixing square pipe fencing (1.95m height) in the portion
965 Uttar Pradesh from Km.134.000 to Km.151.750 in Mathura Town and Km.184.000 19 33.4 Item Rate 6L 01/09/2020 SEC Buildtech Pvt. Ltd.
to Km.199.650 in Agra Town in Section of Old NH-2
Agra - Etawah Bypass Section of NH-2 from Km. 199.660 to Km.
966 Uttar Pradesh 19 124.48 BOT Toll 6L 01/08/2016 Agra Etawah Tollways Ltd
323.525 in the State of Uttar Pradesh
967 Uttar Pradesh Etawah Bypass section km 307.500 to km 321.100 19 13.6 Item Rate 4L 01/03/2006 PNC Infratech Pvt. Ltd.
Oriental Structural Engineers Pvt. Ltd.
968 Uttar Pradesh Agra - Makhanpur km 199.660 - km 250.500 of NH-2 Pkg 1A 19 50.84 Item Rate 4L 30/03/2002
- GIL (JV)
969 Uttar Pradesh Makhanpur - Etawah from km 250.500 - km 307.500 of NH-2 Pkg 1B 19 57 Item Rate 4L 06/09/2005 Progressive Constructions Ltd.

Page 39 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
970 Uttar Pradesh 6L of Etawah - Chakeri from km. 323.475 to km. 483.687 of NH-19 19 160.21 BOT Toll 6L 13/03/2013 Oriental Structural Engineers Pvt. Ltd.

971 Uttar Pradesh Etawah - Sikandra (Kanpur Dehat) km 321.100 - km 393.00 Pkg 1C 19 72.825 Item Rate 4L 30/03/2002 PATI - BEL (JV)

972 Uttar Pradesh 6L of Chakeri - Allahabad from 483.687 to km. 628.753 of Old NH-02 19 145.07 HAM 6L 12/01/2019 PNC Infratech Pvt. Ltd.
973 Uttar Pradesh Allahabad Bypass (3B) (Packages ABP-I, II, III ) 19 84.708 Item Rate 4L 25/04/2014 Cube Highway
4L of Allahabad Bypass - Construction of Bridge across river Ganga
974 Uttar Pradesh 19 1.02 Item Rate 4L 07/10/2003 Larsen & Toubro Ltd.
from km. 163.28 to km. 164.30 (Construction Package ABP-I)

4L of Allahabad Bypass - Construction of Road from km. 158.00 to km.


975 Uttar Pradesh 19 40 Item Rate 4L 09/06/2004 Hindustan Construction Company Ltd.
198.00 (Except Ganga Bridge) (Construction Package ABP-II)
4L of Allahabad Bypass - Construction of Road from km. 198.00 to km. Oriental Structural Engineers Pvt. Ltd.
976 Uttar Pradesh 19 44.71 Item Rate 4L 04/11/2004
242.708 (Construction Package ABP-III) - KMC (JV)
4L Cable-stayed Naini Bridge with Approaches from Km -1.117 to Km
977 Uttar Pradesh 30 5.41 EPC 4L 01/05/2022 Krishna Constructions.
0.4.293 on Old NH-27 (NH-30)
978 Uttar Pradesh 6L of Handia to Varanasi Section from Km 712.900 to Km 785.544 19 72.644 HAM 6L 05/12/2017 G R Infraprojects Limited

979 Uttar Pradesh 4L of Handia - Rajatalab Section Km. 245.00 to Km 317.398 of Old NH-2 19 72.398 Item Rate 4L G R Infraprojects Limited
Varanasi bypass (Ring Road, Phase-I) from Harhua (Km 0.000) to
980 Uttar Pradesh 31 17 EPC 4L 15/05/2015 APCO Infratech Pvt. Ltd.
Sandaha (Km 16.550)
4L Bypass connecting NH-2 (Rakhauna Village km. 782.546 of NH-2)
with NH-56 (Vajidpur Village km. 271.300 of NH-56) of Varanasi Ring
981 Uttar Pradesh 31 16.98 EPC 4L 15/09/2019 G R Infraprojects Limited
Road (Pkg-I, Phase -II) from km. 0.00 to km. 16.400 i/c Interchange
Loop at NH-2
Agra Bypass connecting km 176.8 of NH-2 to km 13.03 of NH-3 (km
982 Uttar Pradesh 19 32.8 Item Rate 4L 11/06/2011 SKS Infra Projects Pvt. Ltd.
0.000 to km 32.800)
Jhansi - Lalitpur section 1/2 from km. 0.00 to km. 49.70 (Package -
983 Uttar Pradesh 44 49.7 BOT Annuity 4L 28/03/2007 Gayatri Projects Limited
NS1/BOT/UP-2)
Jhansi - Lalitpur section 2/2 from km. 49.70 to km. 99.005 (Package -
984 Uttar Pradesh 44 49.3 BOT Annuity 4L 28/03/2007 Gayatri Projects Limited
NS1/BOT/UP-3)
4L of Jhansi-Lakhanadon section from km 99 to km 136.99 of NH-26 in Nagarjuna Construction Company
985 Uttar Pradesh 44 93.69 EPC 4L 24/06/2006
the state of UP (Civil Contract Package No. ADB-II/C-3) Limited.
Prakash Asphaltings and Toll
986 Uttar Pradesh Jhansi-Orai from Km. 90.300 to Km. 225.713 of NH-27 (OMT-Pkg 12) 27 135.41 EPC 4L 28/10/2016
Highways (India) Ltd.
4L of Orai - Bhognipur - Barah from km. 220.0 to km. 255.00 of Old NH-
987 Uttar Pradesh 25 & from km. 421.20 to km. 449.00 on Old NH-02 (Pkg No. EW-II/BOT- 27 62.8 BOT Annuity 4L 24/10/2006 O.B Infrastructure Pvt. Ltd. (OBIL)
UP)
988 Uttar Pradesh Kanpur - Lucknow - Ayodhya OMT - 10 27 217.315 OMT 4L 01/08/2013 PNC Kanpur Ayodhya Tollroad Pvt. Ltd

989 Uttar Pradesh Lucknow-Faizabad Section of NH-28, LMNHP-EW-II (WB-1) 28 36 EPC 4L 13/10/2005 Hindustan Construction Company Ltd.

990 Uttar Pradesh Lucknow-Faizabad Section of NH-28, LMNHP-EW-II (WB-2) 28 47 EPC 4L 13/10/2005 Hindustan Construction Company Ltd.

991 Uttar Pradesh Lucknow-Faizabad Section of NH-28, LMNHP-EW-II (WB-3) 28 46 EPC 4L 19/08/2005 Hindustan Construction Company Ltd.
Balance work of construction of segment of lucknow Bypass
Prakash Atlanta in (JV) with NKG
992 Uttar Pradesh connecting NH-25 and NH-28 via NH-56 passing through Lucknow city 56A & 56B 22.85 EPC 4L 02/03/2009
Infrastructure
(Contract Package No. EW-15A/UP)
4L of Km 11.380 to Km 21.800 of Lucknow-Kanpur section of NH-25 in
993 Uttar Pradesh 25 10.42 EPC 4L 04/04/2000 Vilayati Ram Mittal
the State of Uttar Pradesh (Contract Package No. EW-2/UP
4L of Km 21.800 to Km 44.000 of Lucknow-Kanpur section of NH-25
994 Uttar Pradesh 25 22.2 EPC 4L 30/08/2001 Vilayati Ram Mittal
(NSEW Phase-II) (Contract Package No. EW-8/UP)

Page 40 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
4L of Km 44.000 to Km 59.500 of Lucknow-Kanpur section of NH-25
995 Uttar Pradesh 25 15.5 EPC 4L 30/08/2001 BRA/TRG Bharat (JV)
(NSEW Phase-II) (Contract Package No. EW-9/UP)
4L of Km 59.500 to Km 75.500 of Lucknow-Kanpur section of NH-25
996 Uttar Pradesh 25 16 EPC 4L 02/02/2010 Vilayati Ram Mittal
(Contract Package No. EW-3A/UP) including EW/3
Strengthening, Improvement and routine maintenance of Lucknow-
Kanpur section from km. 28.00 to km. 76.300 of NH-27 (Old NH-25)
997 Uttar Pradesh including construction of Drain & Service Road, rehabilitation of 27 71.175 Item Rate 4L 05/01/2023 Krishna Constructions.
Unnao RoB and Shaheed Path from Km. 0.000 to 22.875 of NH-27 (Old
NH-56A&B)
Operation & Maintenance of Lucknow-Ayodhya Section from Km.
998 Uttar Pradesh 27 129.97 Item Rate 4L 15/03/2023 S&P Infrastructure Developers(P) Ltd
8+000 to Km. 137+970 Stretch of NH-27 (Old NH-28)
Strengthening, Improvement and routine maintenance of Lucknow-
Kanpur section from km. 27.700 to km. 75.500 of NH-27 (Old NH-25)
999 Uttar Pradesh NH-27 47.8 PBMC 4L PS 30/03/2024 G. S. Express Private Limited
including construction of Drain & Service Road, rehabilitation of
Unnao RoB
S&P Infrastructure Developers Pvt.
Strenthening and major maintenance work from Km 8.000 to Km
1000 Uttar Pradesh NH-27 60.9 EPC 4L PS 10/01/2024 Ltd. in Joint Venture with Surya
68.900 of NH-28 (new NH-27) of Lucknow-Ayodhya Section Pkg-1
Construction Company
Strengthening and Improvement of Lucknow Ayodhya section of NH-
1001 Uttar Pradesh NH-27 52.7 EPC 4L PS 10/01/2024 SKS Infra Projects Pvt. Ltd.
28 (New NH-27) from Km. 68.900 to Km. 121.600 (Pkg-II).
Lucknow Ring Road Pkg-1 (Sultanpur Road to Behta Road) [Bypass
1002 Uttar Pradesh 56 31.75 EPC 4L 07/02/2020 PNC Infratech Pvt. Ltd.
connecting NH-56 at km. 17.40 and terminating near Behta Road]
4L of Lucknow Ring Road Package-3B from Km.17.600 to MDR-77C and
1003 Uttar Pradesh 28 14.71 EPC 4L 01/08/2017 Gawar Construction Ltd
terminating at Km.15.650 of NH-28
Dineshchandra R. Agrawal Infracon
1004 Uttar Pradesh Lucknow Ring Road Pkg 3A (Sitapur Road to Kursi Road) 24 14.61 EPC 4L 15/01/2019
Pvt. Ltd.
Operation and Maintenance of Lucknow Bypass Section (Km. 0.000 to
Km. 22.875) of NH-56 A&B, Lucknow Outer Ring Road-3B
1005 Uttar Pradesh LRR 49.04 PBMC 4L 26/06/2024 G. S. Express Private Limited
(Km.79.516/79.000 to Km. 94.457/93.473) and Lucknow Outer Ring
Road-Kisan Path (Km.0.491/0.495 to Km. 11.660/12.210)
1006 Uttar Pradesh Construction of Drain and Service Road TBD 4.54 EPC 2L 02/03/2020 Anmol Associates
Ayodhya - Gorakhpur Section from km. 137.97 to km. 252.86 of Old
1007 Uttar Pradesh 27 116.1 Item Rate 4L 05/03/2013 Authorized Signatory,Acton India Ltd.
NH-28 (Pkg No.1/NHAI/OMT/Pkg-11/2011)
4L from Km. 135.000 to Km. 164.000 of Ayodhya - Gorakhpur Section
1008 Uttar Pradesh 27 27.24 EPC 4L 29/11/2005 Hindustan Construction Company Ltd.
of NH-28[Contract Package- LMNHP-EW-II (WB)-4]
4L from Km. 164.000 to Km. 208.000 of Ayodhya - Gorakhpur Section Nagarjuna Construction Company
1009 Uttar Pradesh 27 44 EPC 4L 18/10/2005
of NH-28[Contract Package- LMNHP-EW-II (WB)-5] Limited.
4L from Km. 208.000 to Km. 251.700 of Ayodhya - Gorakhpur Section B.Seenaiah & Company (Projects)
1010 Uttar Pradesh 27 44.86 EPC 4L 24/10/2005
of NH-28[Contract Package- LMNHP-EW-II (WB)-6] Limited
Four laning of Gorakhpur Bypass from km. 79.670 of NH - 29E to km. Monte Carlo Ltd. - Backbone
1011 Uttar Pradesh 29E & 28 17.66 EPC 4L 08/05/2017
251.700 of NH - 28 Enterprises Ltd (JV).
Gorakhpur Infrastructure Company
1012 Uttar Pradesh Gorakhpur Bypass (Km. 0.000 to Km. 32.27 connecting NH28) 27 32.27 BOT Annuity 4L 06/04/2007
Limited
Jajmau-Ramadevi (rehabilitation of Ganga Bridge and upgradation of Gammon Engineers & Contractors
1013 Uttar Pradesh 27 5.46 EPC 4L 05/12/2005
4L divided carriageway) Pvt. Ltd.
1. NCC Ltd. , 2.Simplex Infrastructures
1014 Uttar Pradesh Gorakhpur - Kasya - UP/Bihar Border OMT-27A 27 81.12 EPC 4L 22/05/2015
Ltd
4L from Km. 279.800 to Km. 319.800 of Gorakhpur - Kasia/U.P. Bihar Nagarjuna Construction Company -
1015 Uttar Pradesh 27 40 EPC 4L 14/12/2005
Border Section of NH-28[Contract Package- LMNHP-EW-II (WB)-7] Vijai Expressway Engineers (JV)

4L from Km. 319.800 to Km. 360.915 of Gorakhpur - Kasia/U.P. Bihar


1016 Uttar Pradesh 27 41.12 EPC 4L 08/12/2005 Simplex Infrastructure Limited
Border Section of NH-28[Contract Package- LMNHP-EW-II (WB)-8]

Page 41 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
4 laning of Sikandra - Bhaunti Section Coonstruction Pkg II-B (km
1017 Uttar Pradesh 19 51.5 EPC 4L 01/04/2002 Somdatt Builders Ltd.-NCC-NEC(JV)
470.00 to km 38.00 of old NH-2 (Contract No. GTRIP/4)
1018 Uttar Pradesh Kanpur - Kabrai from km. 0.00 to km. 123.863 34 124 BOT Toll 2L PS 21/01/2013 PNC Infratech Pvt. Ltd.
1019 Uttar Pradesh Lalganj-Hanumana km 96.80 - km 140.200 35 43.4 EPC 4L 01/02/2019 Dilip Buildcon Ltd.
1020 Uttar Pradesh Dagamagpur to Lalganj (km 49.1 - km 96.8) 35 47.7 EPC 4L 13/12/2018 Dilip Buildcon Ltd.
1021 Uttar Pradesh Varanasi-Degamapur [km. 15.1 - km. 49.1] 35 34 EPC 4L 09/08/2019 Dilip Buildcon Ltd.
1022 Uttar Pradesh Garh Mukteshwar - Moradabad section 9 56.25 EPC 4L 31/03/2005 PNC Infratech Pvt. Ltd.- BELK (JV)
1023 Uttar Pradesh Hapur - Garh Mukteshwar 9 35 Item Rate 4L 12/03/2005 Mohandas V Rajani
Repair & Rehabilitation of existing old Ganga Bridge at Km 92.395 of
1024 Uttar Pradesh NH-24 and balance work of its approaches on Hapur Bypass to 24 0.7 EPC 4L
Moradabad Section of NH-24
1025 Uttar Pradesh Balance left out works on Hapur Bypass to Moradabad 9 3 EPC 4L PS 28/03/2017 Gawar Construction Ltd
4 L of Moradabad - Bareilly section of NH-24 from km 149.25 to km
1026 Uttar Pradesh 9, 530, 30 121.8 BOT Toll 4L 04/12/2010 IL&FS Transportation Networks Ltd.
271.05
Balance Work of ROB at Km. 290.445 of Bareilly - Sitapur Section of PRL Projects and Infrastructure
1027 Uttar Pradesh 30 1.24 Item Rate 4L 11/08/2020
Old NH-24 Limited
Construction of ROB at Km. 314.385 over existing NH-24 in Bareilly-
1028 Uttar Pradesh 24 0.858 EPC 6L 24/10/2022 Kaluwala Construction Private Limited
Shahjahanpur section for proposed private railway siding of KFL

Apollo Enterprises Ltd. - John Laing


1029 Uttar Pradesh Four Laning of Lucknow-Sitapur from km 488.270 to km 413.200 30 75.93 BOT Toll 4L 30/06/2006
International Ltd. (Consortium),
4L Elevated Corridor from near Madiaon to IIM Crossing (KM. 486.285
1030 Uttar Pradesh 30 1.946 EPC 4L 15/06/2022 Kaluwala Construction Private Limited
to km. 488.231) on Lucknow – Sitapur section of NH-24
1031 Uttar Pradesh Ghaziabad - Aligarh 34 126.3 BOT Toll 4L/6L 25/02/2011 PNC - SREI - Gawar (JV)
4/6 L THDCIL Bypass for Re-routing of Ghaziabad Aligarh (NH-91) from
1032 Uttar Pradesh 91 9.285 EPC 4L/6L 11/02/2021 Raj Shyama Constructions Pvt. Ltd.
Dushehra Village to Arnia Khurd (Deposit Work)
1033 Uttar Pradesh Aligarh-Kanpur (Pkg I) [Aligarh-Bhadwas] 34 45.83 HAM 4L/6L 25/02/2019 Brij Gopal Construction Pvt. Ltd.
1034 Uttar Pradesh Aligarh-Kanpur (Pkg II) [Bhadwas to Kalyanpur] 34 45.2 HAM 4L/6L 29/01/2019 PNC Infratech Pvt. Ltd.
1035 Uttar Pradesh Aligarh-Kanpur (Pkg III) [Kalyanpur - Naviganj] 34 61.2 HAM 4L/6L 07/06/2019 APCO Infratech Pvt. Ltd.
1036 Uttar Pradesh Aligarh-Kanpur section (Package-IV from Naviganj - Mitrasen) 91 71 HAM 4L 18/02/2021 G R Infraprojects Limited
1037 Uttar Pradesh Aligarh-Kanpur section (Package-V from Mitrasen-Kanpur) 91 60.6 HAM 4L 15/03/2021 PNC Infratech Pvt. Ltd.
4L PS of EPE Cossing to start of Shamli Bypass from Km. 92.20 to Km.
1038 Uttar Pradesh 709B 61.41 EPC 4L PS 21/11/2018 Krishna Constructions.
155.025 of existing NH-709-B
1039 Uttar Pradesh Lucknow - Raibareili 30 70 BOT Annuity 4L 18/07/2012 Essel Infraprojects Ltd
4L PS of Meerut to after Bridge over River Yamuna, Haryana via Shamli- Dineshchandra R. Agrawal Infracon
1040 Uttar Pradesh 709A 83.8 EPC 4L 04/01/2021
from km. 0.00 to km. 88.476 of NH-709A Pvt. Ltd.
User fee collection at Mungari Toll Plaza at Km. 417.250 of NH-76E
1041 Uttar Pradesh (New NH-35) of 2L PS from Km. 400.878 to Km. 450.000 (Prayagraj – 35 49.122 EPC 2L PS
Mirzapur Section)
2L of HR/UP Border - Baghpat - Meerut from km. 0.00 to km. 41.36 &
1042 Uttar Pradesh 334B 43.78 EPC 2L 01/02/2020 Raj Shyama Constructions Pvt. Ltd.
from km. 45.84 to km. 48.26
1043 Uttar Pradesh Agra -Aligarh 509 81 BOT Toll 2L 09/10/2012 Brijbhoomi Expressways Pvt. Ltd
1044 Uttar Pradesh Panipat - Shamli 709AD 35.78 EPC 4L 18/09/2020 G R Infraprojects Limited
1045 Uttar Pradesh Shamli - Muzzafarnagar 709AD 42.87 EPC 4L 23/10/2020 G R Infraprojects Limited
Balance Work of 2L PS of Sitarganj-Bareilly from Km. 254.820 to Km.
1046 Uttar Pradesh 30 74.46 Item Rate 2L PS 10/03/2021 SRSC INFRA PRIVATE LIMITED
329.280 section of Old NH-74
4L PS of Prayagraj to UP/MP Border section of NH-27 (New NH-30)
1047 Uttar Pradesh 30 41.34 EPC 4L PS 06/05/2016 Shree Construction enterprises
from Km. 4.285 to Km 45.627
1048 Uttar Pradesh Jarwal to Bahraich 927 50 EPC 2L PS 28/10/2014 Hindustan Construction
1049 Uttar Pradesh Barabanki to Jarwal Road(28C Pkg-1) 927 43 Item Rate 2L PS 19/03/2015 Hindustan Construction
1050 Uttar Pradesh Bahraich Bypass - Rupadiha 731 54 EPC 2L PS 30/10/2014 Hindustan Construction
1051 Uttar Pradesh 2L PS of Sonauli - Gorakhpur from km. 0.00 to km. 80.00 of Old NH-29E 29E 80 EPC 2L PS 27/06/2014 Bravior Infrastructure Pvt Ltd
1052 Uttar Pradesh Unnao - Lalganj Section from km 0.000 to 70.000 31 70 HAM 4L 19/05/2021 PNC Infratech Pvt. Ltd.

Page 42 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
1053 Uttar Pradesh 2L PS of Raebareilly-Jaunpur from km. 0.00 to km. 166.400 of NH-231 31 166 BOT Annuity 2L PS 04/06/2014 PNC Infratech Pvt. Ltd.
Maintenance from Km 21.00 to km 53.170 of Prayagraj Bypass
1054 Uttar Pradesh 319D 32.17 Item Rate 2L/4L 27/04/2022 Bravior Infrastructure Pvt Ltd
junction - Mungra Badshahpur section of Nh-319D
1055 Uttar Pradesh Lucknow (11.500) to Sultanpur (138.925) of NH-56 in Uttar Pradesh 731 127.43 HAM 4L PS 08/05/2017 Dilip Buildcon Ltd.
Four Laning of Sultanpur to Varanasi (PKG-I) [from Sultanpur (Km
1056 Uttar Pradesh 56 74.53 EPC 4L 01/01/2016 Gayatri Projects Limited
134.700) to Jaunpur (Km 209.230)]
One Time Improvement & Maintenance of Sultanpur to Varanasi
1057 Uttar Pradesh 731 71.163 Item Rate 2L 20/05/2021 SRSC INFRA PRIVATE LIMITED
Section from km 134.70 to km 263.00 of NH-56(New NH-731)
Construction of ROB at Project Ch. 146.533 of NH-56 (Pkg-I) along with
1058 Uttar Pradesh 56 1.02 EPC 4L 19/10/2022 Vidya InfraBuilt Pvt. Ltd.
its approaches and slip roads on New NH-731
Four Laning of Sultanpur to Varanasi (PKG-II) [from Jaunpur (Km
1059 Uttar Pradesh 56 63.36 EPC 4L 01/01/2016 Gayatri Projects Limited
209.230) to Varanasi (Km 272.590)]
Maintenance from km 263.400 (NH-Junction, near Jaunpur) to km
1060 Uttar Pradesh 295.000 (Khujjhi) & km 299.000 (Chandwak) to km 320.180 (NH- 731 52.78 EPC 2L
Junction, near Saidpur) of NH-731
Raebareli (Km. 152.533) to Banda ( Km. 285.818) of NH-232 in Uttar
1061 Uttar Pradesh 232 133.28 EPC 2L PS 22/04/2014 Constrctora Sanjose S.A.
Pradesh
Operation and Maintenance including Partial Strengthening of
1062 Uttar Pradesh 232 120.775 PBMC 2L PS 30/03/2024 M/s. DPS Contractor Pvt. Ltd.
Raebareli to Banda section of NH-232 Under PBMC mode
Four Lanning of Jagdishpur-Faizabad Section from km 47.930 to km
1063 Uttar Pradesh 330A 60.22 HAM 4L 15/03/2021 PNC Infratech Pvt. Ltd.
107.680 of NH-330A
Repair and Maintenance of Rouza Chouraha (Ghazipur)- Phephna
1064 Uttar Pradesh 31 68.37 Item Rate 2L 03/02/2022 SRSC INFRA PRIVATE LIMITED
(Ballia) Section from Km 405.030 to Km 473.400 on NH-31 (Pkg-1)

Special Repair and Maintenance of Phephna (Ballia) - Chiraiya More MCCMAHADEO Constructions Private
1065 Uttar Pradesh 31 45.1 Item Rate 2L 03/02/2022
(Barria) Section from Km 473.400 to Km 518.500 on NH-31 (Pkg-2) Limited

Repair and Maintenance of Rouza Chouraha (Ghazipur)- Phephna


1066 Uttar Pradesh 31 68.37 Item Rate 2L 05/02/2022 SRSC INFRA PRIVATE LIMITED
(Ballia) Section from Km 405.030 to Km 473.400 on NH-31 (Pkg-1)

Special Repair and Maintenance of Phephna (Ballia) - Chiraiya More MCCMAHADEO Constructions Private
1067 Uttar Pradesh 31 45.1 Item Rate 2L 25/02/2022
(Barria) Section from Km 473.400 to Km 518.500 on NH-31 (Pkg-2) Limited
Shakarpur( Km 8.800) to Akbarpur (Km 73.512) of NH-235 in Uttar
1068 Uttar Pradesh 334 61.19 HAM 4L 28/04/2017 APCO Infratech Pvt. Ltd.
Pradesh (Meerut - Bulandshahar)
Nagarjuna Construction Company
1069 Uttar Pradesh Meerut - Muzaffarnagar 58 78.31 BOT Toll 4L PS 07/03/2006
Limited.
1070 Uttar Pradesh Meerut - Muzaffarnagar - Addl. Works (Structures) 334 78 EPC 4L 20/03/2018 Krishna Constructions.
1071 Uttar Pradesh Varanasi Gorakhpur Section from km. 84.160 to 149.540 ( PKG III) 24 65.38 EPC 4L 10/04/2017 Jaiprakesh Associates Ltd.
Varanasi (Km 12.01) to Birnon (Km 84.160) [Varanasi - Gorakpur] ( PKG-
1072 Uttar Pradesh 29 72.15 EPC 4L 31/03/2017 PNC Infratech Pvt. Ltd.
II)
Ambedkar Nagar (Km 0.000) to Raebareilly (Km 155.900) of NH-232 in
1073 Uttar Pradesh 128 155.9 EPC 2L PS 22/04/2014 GKC Projects Ltd.
UP
Operation and Maintenance including Partial Strengthening of
1074 Uttar Pradesh 128 148.9 PBMC 2L PS 30/03/2024 Kaluwala Construction Private Limited
Ambedkar Nagar to Raebareli section of NH-128 Under PBMC mode
2L PS of of Rudhauli to Basti side approach of Ghaghara Bridge Section
1075 Uttar Pradesh 28 54.36 EPC 2L PS 25/03/2015 KMC Construction Ltd.
from Km. 65.870 to Km. 122.270) of NH 233
Rehabilitation and Up-Gradation of 2L - PS Indo/ Nepal Border to JSP Projects Pvt Ltd. - Vijay
1076 Uttar Pradesh 28 65.87 EPC 2L PS 27/11/2018
Rudhauli Section from Km. 0.000 to Km. 65.870 of NH-28 Construction Pvt. Ltd. (JV)
1077 Uttar Pradesh Ghaghra Bridge to Varanasi Section of NH-233 (Package-1) 233 58.62 EPC 4L 15/12/2015 Dilip Buildcon Ltd.

Page 43 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
One Time Improvement & Maintenance of Ghaghra Bridge - Varanasi
1078 Uttar Pradesh section from km 180.420 to km 299.350 of NH-233(New NH-28) ( Pkg. 28 21.05 Item Rate 2L 08/07/2021 Uma Associates
II & III )
Four Laning of Ghaghra Bridge to Varanasi (PKG-II) [Budhanpur Urban
1079 Uttar Pradesh 233 59.92 EPC 4L 01/01/2016 Gayatri Projects Limited
section (Km 180.420) to Gossai ki bazaar bypass (Km 240.340)]
Four Laning of Ghaghra Bridge to Varanasi (PKG-III) [Gossai ki bazaar
1080 Uttar Pradesh 233 59.01 EPC 4L 01/01/2016 Gayatri Projects Limited
bypass (Km 240.340) to Varanasi (Km 299.350)]
Gagalheri-Saharanpur- Yamunanagar (UP/ Haryana Border) Section of
1081 Uttar Pradesh 344 51.45 HAM 4L 27/01/2018 MBL Infrastructures Ltd.
NH-73
2L PS of Aligarh - Moradabad section from km 85.650 to km 232.00 of
1082 Uttar Pradesh 509 146.35 EPC 2L PS 26/01/2017 PNC Infratech Pvt. Ltd.
Old NH-93
One-Time Improvement and Maintenance of the existing section of
1083 Uttar Pradesh 9 1.4 Item Rate 2L 10/05/2022 State PWD
NH-87 (New NH-9) (Mankara Kadeem)
Repair and Maintenance of NH-128C starting its junction with NH-28
1084 Uttar Pradesh near Azamgarh and terminating at its junction with NH-24 near 40.8 Item Rate 2L PS 01/08/2022 Jagdamba Enterprises
Dohrighat
1085 Uttarakhand 4L of Nagina-Kashipur section from km. 73.00 to km. 175.00 of NH-74 74 98.79 EPC 4L 28/10/2017 PNC Infratech Pvt. Ltd.
4L of Kashipur Sitarganj Section of NH-74 from km. 175.000 to km. Galfar Engineering & Contracting
1086 Uttarakhand 74 77.2 BOT Toll 4L 05/03/2014
252.200 (India) Pvt. Ltd.
Balance work of 4L of Muzaffarnagar - Haridwar [Package -I] (Design
1087 Uttarakhand Chainage km 130.360 to km 167.200) [Muzaffarnagar to Start of 58 38.84 Item Rate 4L 25/11/2019 Raj Shyama Constructions Pvt. Ltd.
Roorkee bypass]
Balance work of 4L of Muzaffarnagar - Haridwar [Package -II] (Design
1088 Uttarakhand 58 13.1 Item Rate 4L 25/11/2019 Sam India Builtwell Pvt Ltd.
Chainage km 167.200 to km 180.300) [Roorkee bypass]
Balance work of 4L of Muzaffarnagar - Haridwar [Package -III] (Design
1089 Uttarakhand Chainage km 180.300 to km 208.620) [End of Roorkee Bypass to 58 28.12 Item Rate 4L 25/11/2019 Sam India Builtwell Pvt Ltd.
Haridwar]
Operation and Maintenance work of Haridwar to Muzzaffarnagar
1090 Uttarakhand section from 354.050 km to 360.270 km of NH-34 & from 0.000 km to 34 & 334 42.62 Item Rate 4L 30/03/2022 KOSHER INFRASTRUCTURE PVT LTD
36.400 km of NH-334.
Operation and Maintenance of Haridwar to Muzzaffarnagar from CH.
1091 Uttarakhand 334 35.5 Item Rate 4L 04/05/2022 SHRI KRISHNA AND COMPANY
36.400 to CH. 71.900 section of NH 334 [Package2]
Elevated Structure including Major Bridge on Mayapuri Escape
1092 Uttarakhand 58 1.05 EPC 2L PS 01/11/2018 Ram Kumar Contractor
Channel on Muzzaffarnagar - Haridwar Section
Sitarganj Tankpur Section of NH-125 from km. 0.000 to km. 52.200 in
1093 Uttarakhand 125 43.88 EPC 2L PS 02/09/2015 SHRI KRISHNA AND COMPANY
State of Uttarakhand
Routine Maintenance & Incident Management work of from Km.
0.000 to (Km. 254.600 of NH-74) to Km. 52.200 under NHDP IV on EPC
1094 Uttarakhand 09 43.945 EPC 2L PS 18/07/2022 SHRI KRISHNA AND COMPANY
Mode of 2L PS of section of NH-125 ( New NH-09) excluding Khatima
Bypass of length 8.255Km
Chutmalpur Ganeshpur section and Roorkee Chutmalpur Gagalheri
1095 Uttarakhand 72A 53.3 HAM 4L 28/02/2018 MBL Infrastructures Ltd.
section
Rampur - Rudrapur Section from km. 0.000 to km. 43.446 [Rampur
1096 Uttarakhand 87 43.45 HAM 4L 31/03/2017 Sadbhav Engineering Pvt. Ltd.
Kathgodam (Package-1)]
Rudrapur Kathgodam Section from km. 43.446 to km. 93.226 of Gawar Nainital Highways Private
1097 Uttarakhand 87 49.78 HAM 4L 28/10/2017
Rampur Kathgodam (Package-2) Limited
One-Time Improvement and Maintenance of the existing section of
1098 Uttarakhand NH 87 (New NH-109) (in Haldwani from Teen Pani to Mandi Chowk) 109 2.05 Item Rate 2L 07/02/2020 State PWD
bypassed by Haldwani bypass.

Page 44 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
One time improvement of existing NH87 km. 82+000(Mandi gate) to
km. 91+000 (Nariman chowk) passing through Haldwani town falling
1099 Uttarakhand 87 8.65 Item Rate 4L 17/02/2023 State PWD
under Four laning of Rampur-Kathgodam section of NH-87 from
Km.42.791 to Km 88.000 (Package-II) under NHDP Phase-III on HAM
Najibabad - Kotdwar Section from km. 112.545 to km. 138.635 of NH-
1100 Uttarakhand 119 26.09 Item Rate 2L 18/09/2009 UPPWD
119
1101 Uttarakhand Remaining works of Haridwar Dehradun (Pkg I) (Haridwar - Lalatappar) 58 & 72 14.95 Item Rate 4L 01/02/2019 UP State Bridge Corporation Ltd.
Remaining works of Haridwar Dehradun (Pkg II) (Lalatappar -
1102 Uttarakhand 58 & 72 22.2 Item Rate 4L 01/02/2019 Atlas Construction Pvt. Ltd. - NKC (JV)
Mohakampur)
Routine Maintenance & Incident Management Services work of
Haridwar to Dehradun Section from Km.208.620 to Km.216.824 of NH-
1103 Uttarakhand 07,34 37.625 Item Rate 4L 01/08/2022 Hindustan Construction
58 (New NH-34) & from Km.188.324 to Km.158.900 of NH-72 (New
NH-07) in the State of Uttarakhand
6L of Dhankuni to Kharagpur from km 17.600 to km 129.000 of Old
1104 West Bengal 16 111.4 BOT Toll 6L 01/04/2012 Ashoka Buildcon Limited
NH-06
1105 West Bengal Four Laning of Balasore to Kharagpur from km. 0.00 to km. 119.30 16 119.3 BOT Toll 4L 01/11/2013 IL&FS Transportation Networks Ltd.
Development of Emergency Landing Facility on Balasore - Kharagpur
1106 West Bengal 60 5 EPC 4L 11/12/2020 Nad Bindu Infra Tech. Pvt. Ltd.
Section from km. 83.400 to km. 88.400
4L of Barwa Adda (Km. 398.750) to Barakar (Km. 441.440) [Project
1107 West Bengal 19 42.69 EPC 4L
completed under ADB Loan assistance in the year 2001]
1108 West Bengal 4L of Palsit-Panagarh 19 65 BOT Annuity 4L 21/06/2002 S&P Infrastructure Developers(P) Ltd
1109 West Bengal Palsit - Dhankuni (4L) km 581.457 to km 646.000 of NH-2 19 64.54 BOT Annuity 4L 27/10/2002 Kalyan Toll Infrastructure Ltd.
Repair & Maintenance of Stretch of NH- 2 from km 649.546 to km
1110 West Bengal 651.368 (New chainage km 645.546 to km 647.368) from NH-6/NH-2 2 1.822 OMT 4L
Junction to FCI Crossing including Maitypara Bridge
Sister Nivedita Bridge (2nd Vivekananda Bridge) & its approaches from Second Vivekananda Bridge Tollway
1111 West Bengal 19 6 BOT Toll 6L 01/04/2000
km. 653.010 to km. 659.05 of Old NH-2 Co Pvt Ltd
4L of Raniganj to Panagarh (km. 474.000 to km. 515.236) and
1112 West Bengal strengthening of existing two lane pavement from km. 474.000 to km. 19 41.236 EPC 4L 04/07/1997 BSC-RBM-PATI(JV)
515.236 section of NH 19
1113 West Bengal Dalkhola-Islampur (Pkg-EW/5) 27 61.6 EPC 4L 29/12/1999 Sarada Construction
Islampur Bypass of NH-31 (New NH-27) of 10.31 km length in the state
1114 West Bengal 27 10.31 EPC 4L 15/01/2016 Ashoka Buildcon Limited
of West Bengal
1115 West Bengal Siliguri-Islampur EW-II (WB-6) 27 70.7 EPC 4L 05/04/2006 Sarada Construction
1116 West Bengal Ghoshpukur (km 0.000) to Dhupguri (km 83.785) of NH-31D 27 83.78 EPC 4L 17/12/2015 Larsen & Toubro Ltd.
Short term improvement and Routine maintenance of NH-31D from
1117 West Bengal 31D 41.654 Item Rate 4L 12/07/2023 Biswajyoti Bhattacharyya
Km. 113.200 to Km. 154.854(Pkg IIA), Falakata to Salsalabari section

O&M of Dalkhola-Islampur-Sonapur-Ghospukur from Km.447.000 to


1118 West Bengal 31 96.28 OMT 4L 10/10/2023
Km.551.500 (excluding Km.498.780 to Km.507.000)
1119 West Bengal Salsalabari-Assam Bengal Border 27 27 EPC 4L 01/06/2006 Biswajyoti Bhattacharyya
Short term Improvement and Routine Maintenance from Km.228.000
1120 West Bengal to Km.254.500 of Salsalabari to Assam Bengal Border section of NH- 27 26.5 OMT 4L 08/01/2022 Biswajyoti Bhattacharyya
31C (New NH-27)
4L of Chichra - Kharagpur section from Km. 129.600 to Km. 185.150
1121 West Bengal including rehabilitation of existing 4 lane from km. 134.40 to 49 55.55 EPC 4L 16/03/2017 Dilip Buildcon Ltd.
Km.129.60 of Old NH-6
Dineshchandra R. Agrawal Infracon
1122 West Bengal ROB cum Flyover at Ranichak, Haldia 41 1.392 EPC 4L PS 18/05/2016
Pvt. Ltd.

Page 45 of 46
Completed PCC / PCOD Issued
Status as on 01 July 2024
All length in Km.

Appointed Date/Start Date-


Sr. No. State Project Name NH(New) Total Length Mode Lanes Concessionaire
Contractor
Kolaghat-Haldia from km. 0.00 to km. 53.72 including ROB cum Eagledeep Kolaghat Haldia OMT
1123 West Bengal 41 53 EPC 4L 10/09/2008
Flyover from km. 52.08 to km. 53.472 Project Pvt. Ltd.
Strengthening of existing stretch of Barasat-Barajaguli Section from
1124 West Bengal 12 17.553 Item Rate 2L 11/09/2023 Midaas Construction Co Pvt. Ltd.
KM. 31.000 to KM. 48.553 of NH-34
Krishnagar - Berhampore section from km 115.00 to km 193.00 of NH-
1125 West Bengal 12 78 BOT Annuity 4L PS 10/01/2012 SEW Infrastructure Limited
34
Berhampore (191.700) to Farakka (292.300) of NH-34 in the State of
1126 West Bengal 12 100.6 BOT Toll 4L 03/02/2011 Hindustan Construction Company Ltd.
West Bengal
1127 West Bengal Strengthening to NH-12 (old NH-34) 12 100.6 BOT Toll 4L 29/01/2024 Hindustan Construction Company Ltd.
Farakka (295.000) to Raiganj (395.000) of NH-34 in the state of West
1128 West Bengal 12 100.2 BOT Toll 4L 03/02/2011 Hindustan Construction Company Ltd.
Bengal
Balance Work for Raiganj Dalkola section from km 398.00 to km Dineshchandra R. Agrawal Infracon
1129 West Bengal 12 50.29 EPC 4L 08/03/2019
452.700 (excl. Dalkola Bypass) Pvt. Ltd.
4L of Dalkhola Bypass including ROB from Km. 446.740 to Km. 452.162
1130 West Bengal 12 5.46 EPC 4L 11/10/2017 ABCI Infrastructures Pvt. Ltd.
of NH-34
Belghoria Expressway - Repair & Maintenenace from km. 0.00 to km.
1131 West Bengal 2-E 7.363 Item Rate 4L 03/01/2022 Biswajyoti Bhattacharyya
7.363 (Up Lane) & from km. 0.00 to km. 5.563 (Down Lane) of NH-2E
Construction of RCC drain (1m x1m) along the road and draining the
water on the drain of Municipality through a 1.2m Hume pipe beneath
1132 West Bengal 2 0 OMT Others
the RHS carriageway at 2½ no Airport gate of Belghoria Expressway
under North 24 Parganas District

Page 46 of 46