Madheshwari Est
Madheshwari Est
EST AMOUNT=Rs.11,78,000/-
DIEMENSIONS(m) QTY UNIT RATE AMOUNT
S.NO DISCRIPTION OF ITEM NOS L (m) B (m)D (m) Column1 (Rs) (RS)
GROUND FLOOR DETAILS
1 Earthwork excavation for 9 1.20 1.20 1.2 15.55 cum 120 1866.24
footings
Excavation - walls around 1 38.53 0.60 0.85 19.65 cum 120 2357.79
excavation - between walls(inner) 1 12.20 0.60 0.85 6.22 cum 120 746.64
2 P.C.C in foundation by using mix 9 1.20 1.20 0.15 1.94 cum 4850 9428.40
1:4:8 and 40mm H.G metal
3 R.C.C Footing by using 1:2:4 mix and 9 1.20 1.20 0.45 5.83 cum 5850 34117.20
20mm H.G metal
4 R.C.C column by using 1:2:4 mix and 5 0.23 0.23 5.5 1.45
20mm H.G metal 4 0.23 0.23 5.5 1.16
2.62 cum 8510 22283.86
49.16
Deduction for (window,door,Open)
WINDOW 2 0.90 0.23 1.2 0.42
WINDOW 2 0.90 0.23 1.2 0.50
MAIN DOOR 1 1.15 0.23 2.1 0.56
DOOR 1 0.90 0.23 2.1 0.43
DOOR1 1 0.75 0.23 2.1 0.36
OPENING 2 1.20 0.23 2.1 1.16
V 1 0.60 0.23 0.3 0.04
3.47065
ENIGNEER /LBS