0% found this document useful (0 votes)
7 views

Ksphc usermanual

Uploaded by

1si19pcv01
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

Ksphc usermanual

Uploaded by

1si19pcv01
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 104

KARNATAKA STATE POLICE HOUSING

CORPORATION LIMITED
(Karnataka Government Undertaking)
No. 59, Richmond Road, Bangalore - 560025

User Manual
Project Management System
(Microsoft Project 2003)
Table of Contents
Introduction
Introduction
C & MD's Vision

Introduction to Project Management


What Is a Project?
What Is Project Management?
Understanding the Project Management Process

Overview of KSPHC PMS


Overview of KSPHC PMS
Stakeholders and their roles
KSPHC operational hierarchy

Block Diagram of Software Usage


Block Diagram of Software Usage
Users/ Email/ Access Control Guidelines

Introduction to Microsoft Project 2003


What is Microsoft Project?
Microsoft Project Professional 2003
Working with Microsoft Project Professional 2003 as an Enterprise Client

Introduction to Project Server 2003


Project Server and Web Access
Getting Started with Microsoft Project Web Access
Project Server Menus

Documentation on Customization of Project Server for KSPHC PMS


Customized menus

Interface to the KSPHC Website

Conclusion
Introduction
Introduction / KSPHC White Paper

Over the Years, KSPHC - Karnataka State Police Housing Corporation


has served the needs of the Police community by building quality projects.
The drawbacks of their paper based approach was that it required KSPHC employees to
do a lot of paper work for recording of the Progress of the tasks of various KSPHC
projects.
It was also critical for the KSPHC employees to maintain an accurate assessment of
projects, tasks assigned to Resources within each project, and hours were devoted to
each task. Yet, this process could not capture that level of detail. Nor could it provide
time traces, consolidated views, or a clear tracking of hours worked toward a given
project phase or milestone.

CMD's VISION

The mandate of KPHC is to manage the Police infrastructure. This means building Police
quarters, SP's offices in Districts and Police Stations. This year they have a budget of
over 500 Crores for the same.

1. One of the key jobs of the department is to monitor the progress and manage the
projects.
2. Key elements of the construction are Quality, timely delivery and executions,
being transparent in the process of execution, provide the citizens right to
information.
3. Mr. Srikumar wants a comprehensive MIS system which will give him the
following:
a. Status of the constructions
b. Cost structure and management,
c. It will have to be web based.
d. Information should be of high integrity and be secure.
e. Project status
f. A sort of mechanism to upload video files and static picture files.
g. There should be a database engine to collect all the information.
h. PPL at the field should be able to send text mail to the department.
i. Web based environment that is hosted in a data center.
j. The Staff will also have role-based access to information.
Introduction to Project Management
What Is a Project?
A project is a series of tasks that will culminate in the creation or completion
of some new initiative, product, or activity by a specific end date or in other
word we can say that "A Project is a job that has a beginning and an end
(time), a specified outcome (scope), at a stated level of quality
(performance), and a budget (cost)." Some project examples include an office
move, a new product launch, the construction of a building, and a political
campaign, developing a new software application.

Projects come in all sizes. One project might consist of 100 tasks, another
10,000. One project might be implemented by a single resource, another by
500. One project might take two months to complete; another might take ten
years. There can be projects within projects, linked together with a master
project consolidating them all. These sub-projects, however, are all unique
and temporary, and all have a specific outcome and end date.

What Is a Project Management?


Project management is the coordinating effort to fulfill the goals of the
project. The project manager, as the leader of the project team, is
responsible for this effort and its ultimate result. Project managers use
knowledge, skills, tools, and methodologies to:

Identify the goals, objectives, requirements, and limitations of the project.

Coordinate the different needs and expectations of the various project stake-
holders, including team members, resource managers, senior management,
customers, and sponsors.

Plan, execute, and control the tasks, phases, and deliverables of the project
based on the identified project goals and objectives.

Close the project when completed and capture knowledge accrued.

Project managers are also responsible for balancing and integrating


competing demands to implement all aspects of the project successfully, as
follows:

ƒ Project scope: Outlining the specific work to be done for the project.
ƒ Project time: Specifying the finish date of the project as well as any
interim deadlines for phases, milestones, and deliverables.
ƒ Project cost: Indicating the project costs and budget.
ƒ Project human resources: Signing on the team members who will
carry out the tasks of the project.
ƒ Project procurement: Acquiring the material and equipment
resources with which to carry out project tasks.
ƒ Project communications: Conveying assignments, updates, reports,
and other information with team members and other stakeholders.
ƒ Project quality: Specifying the acceptable level of quality for the
project goals and objectives.
ƒ Project risk: Analyzing potential project risks and response planning.
Understanding the Project Management Process
The project management process can be broken down into four manageable
phases:

ƒ Initiating and planning the project


ƒ Executing the project
ƒ Controlling the project
ƒ Closing the project

Planning the Project


The project's planning phase starts after an authoritative stakeholder has
decided to implement the project. The outcome of this planning phase will be
a workable project plan and a team ready to start working the project. When
planning the project we have to:

Look at the project in holistic way. Before we get too far into the nuts and
bolts of planning, we need a comprehensive vision of where we are going
with our project. We shape this vision by first identifying the project goals and
objectives. This helps us to set the scope of the project. We learn the
expectations, limitations, and assumptions for this project, and they all go
into the mix. We also identify possible risks and contingency plans for the
project.

Identify the project's milestones, deliverables, and tasks. Subdivide the


project into its component tasks and then organize and sequence the tasks to
accurately reflect the project scope.

Develop and refine the project schedule. To turn the task list into a workable
project schedule, specify task durations and relate tasks to each other. We
can create task dependencies, that is, a model of how the start of one task
depends on the completion of another task, for example. If we have any
specific deadlines for deliverables, we can enter those as task constraints. At
that point, Microsoft Project can start to calculate a realistic schedule for tasks
in particular and the project as a whole. With this plan, we can accurately
forecast the scope, schedule, and budget for the project. We can also
determine which resources are needed, how many, and at what time.

Identify skills, equipment, and materials needed. After the tasks are
identified, we can determine the skills, equipment, and materials needed to
carry out the work for those tasks. We obtain the needed resources and
assign them to the appropriate tasks. We can now calculate when the project
can be completed and how much it will cost. If it looks like we are exceeding
the allowable deadline or budget, we can make the necessary adjustments.

Executing the Project


The second phase of the project management process is execution. At this
point, we have your project plan in hand. The tasks are scheduled and the
resources are assigned. Everyone's at the starting gate waiting for the project
manager to say "Go!"

He gives the word, and the project moves from the planning phase to the
execution and controlling phase. In the course of executing the project, we:

Save a baseline plan for comparison. To get good tracking information, we


keep a copy of certain project plan information in hand so we can compare
our plan to actual progress as the project moves along.
Monitor the resources as they carry out their assigned tasks. We need to keep
an eye on their progress in completing their tasks.

Track task progress. We can track progress in terms of percent complete, how
long a task takes from beginning to end, or how many hours a resource
spends on a task. As we gather this information, we can see whether tasks
will be finished on time. We can also gather information about costs of
resources, tasks, and the project as a whole.

Controlling the Project


While our project team is executing the tasks, we are making sure the project
stays within the prescribed deadline and budget while maintaining the scope
outlined in the project goals. In project management, this is referred to as
"controlling the project." In the controlling phase, we monitor all task
activities, compare the plan to actual progress, and make adjustments as
needed. To control the project, we do the following:

Analyze project information. Analyze the information we're gathering and use
this analysis to solve problems and make decisions. Often, we need to decide
how to recover a slipped schedule or a budget overrun. Sometimes we're in
the happy position of deciding what to do with extra time or money.

Communicate and report. Throughout the execution of the project, we will be


in constant communication with our team members and other stakeholders.
We need to keep upper management, customers, and other stakeholders
informed of any potential problems, new decisions, and our overall progress.

Closing the Project


In the final phase of the project, we have successfully fulfilled the goals of the
project and it's now complete. Before we move on to the next project, it's a
good idea to capture the knowledge we gained from this one. When closing
the project, we:

Identify lessons learned. Work with our project team and conduct a
"postmortem" meeting to learn what went well and what could be improved.

Create a project template. Save the project plan along with tasks, duration
metrics, task relationships, resource skills, and the like, so the next time we
or someone else manages a similar project, our wheel will not need to be
reinvented.

Overview of KSPHC PMS


KSPHC has gained superiority in managing a large number of projects
successfully. It has a pool of skilled technical and operational human
resources. The PMC (Projects Monitoring Cell) monitors and controls the
projects while the projects are in ongoing stage. It's very important to
understand the KSPHC management hierarchy, role of the managerial
personnel, its functional behavior, its operational activities, and the way it
integrates with the third party construction companies.

A project pops up to KSPHC by the notification issue arrives from the


government. A measurement specification is prepared for the construction by
the AE (designs) and submitted to the C&MD. After the C&MD approves the
measurement specification, KSPHC looks out for a contractor to outsource the
construction by tendering of the project. Tendering may be carried out
differently based on the size of the projects. If the project is not so
significant, the tendering takes place at the division where construction site is
located, by the concerned KSPHC personnel. Else e-Tendering is done by

KSPHC head office. Contractors submit their implementation plan


(measurement specification) and their estimated cost for the construction.
This submitted cost and the e-Tender's reverse-auction amount are compared
and the most suitable contractor is opted for the project.

After the contract is made, a team of engineers (EE, AEE, AE, and/or JE) is
assigned to the project according to their working division. Sometimes a
mobilization advance is also made as per the request of the contractor to
quick-start the construction. The contractor can request only a limited
percentage of the total budget. And this amount is recovered by KSPHC from
the subsequent payment made to the contractor.

At this point of time the actual construction starts. The contractor finishes
implementing a part or full of the construction plan and applies for payment
by submitting a bill. The site is audited by KSPHC higher authority. If the
authority is satisfied by the amount of work is done and the level of quality
has been maintained, they approve the bill. And the payment is made by the
KSPHC account section. Similarly the total construction work is monitored by
the KSPHC personnel and at last the final bill is made if the project does not
have cost or time overrun.

As you have understood how KSPHC operates, it is time to be familiar with


the widgets used by KSPHC to leverage its project management. Here we are
specially talking about the software tools used by it. KSPHC uses Microsoft
Project 2003 (see the next section Introduction to Microsoft Project 2003 for
more information about Microsoft Project 2003 and other software-related
information) as the depository of its all project information, collaborate with
the team members, monitor and control the projects and publish project
summary information to its website to make it more transparent.

The software is used right from the very beginning of all projects. The AE as
the project manager accompanied by the contractor prepares the project plan
in Microsoft Project Professional 2003 with the list of tasks to be done, the
task durations, task relations, list of human resources, assignment of the

resources to specific tasks, task and resource specific costs and other
necessary project details. Once the project plan is finalized, the project
manager publishes the plan in the Microsoft Project Server 2003 and records
the baseline for future comparison of different project attributes. Once the
project is published in the server the project information becomes accessible

to the different project stakeholders. The project team and the contractor
update the project information through the Microsoft Project Web Access (see
section Introduction to Project Server 2003 on how to work with Microsoft
Project Web Access) as the actual construction proceeds. The billing is also
managed by the software. See the subsequent sections of this documentation
to get a clearer picture of how the software works.

Stakeholders and their roles


Every project has a set of stakeholders associated with it. Project
stakeholders are individuals or organizations who are somehow connected to
the project and can influence the project's outcome. Stakeholders include the
project manager, members of the project team, the sponsoring organization,
and customers.
Project manager: For any KSPHC project a specific Assistant Engineer (AE)
or Junior Engineer (JE) from that sub-division where the project is executed
will be the project manager. The responsibilities of a project manager are to

prepare the project plan, assign tasks to resources, accept or reject the
updates sent by the team members, monitoring and controlling as the project
proceeds (please refer to Microsoft Project Professional 2003 online help (the
Help menu of Project Professional 2003) for a complete reference about how
to work with Project Professional). Microsoft Project directly supports the
project manager with its scheduling, tracking, and communication
capabilities. Sometimes Project Monitoring Cell (PMC) acts as an alternative of
the project manager for monitoring the projects and other responsibilities.

Team members: Team members carry out the actual project work.
Contractor/agency is the only team member/stakeholder outside the
organization. He carries out the actual construction, capture progress
information from the site, submit to the authority for proving his
responsibility, prepare and submit the bill (refer sections Introduction to
Project Server 2003 and Documentation on Customization of Project Server
for KSPHC PMS for how to upload documents, update task progress, prepare
and submit the bills later in this document).

Project resource manager: The resource manager works in concern with


the project manager to help acquire and maintain necessary resources. A
resource manager analyzes resource utilization information and suggests
better resource allocation. Chairman & Managing Director (C&MD) is the
resource manager in KSPHC.

Senior managers, executives: Chairman & Managing Director (C&MD) and


Executive Director (ED) are the administrative officers concerned to the
progress of work and financial aspects. Financial Advisor (FA) and Chief
Accounts Officer (CAO) are the officers for the financial management of the
organization. The Chief Engineer (CE) and Superintendent Engineer (SE)
gives the overall technical direction. The above mentioned officers are based
on the head office. Executive Engineer (EE) is responsible for the division
level in respect of progress of work and other activities. Assistant Executive
Engineer (AEE) is responsible for the sub-division level in respect of work-
progress and other activities.
KSPHC Operational Hierarchy (Technical)

C&MD
(Chairman & Managing Director)

ED
(Executive Director)

CE
(Chief Engineer)

SE SE (Design)
(Superintendent Engineer) (Superintendent Engineer)

EE EE (PM) EE (QC)
(Executive Engineer) (Executive Engineer) (Executive Engineer)

AEE AEE (PM) AEE (QC)


(Asst. Executive Engineer) (Asst. Executive Engineer) (Asst. Executive Engineer)

AE/JE AE (PM) AEE (Design)


(Asst. Engineer/ Junior (Asst. Engineer) (Asst. Executive Engineer)
Engineer)

AE (Design)
(Asst. Engineer)
Block Diagram of Software Usage

Notification from
government for
the new project
Design and
measurement by
AE (Design)

Approval
from C&MD

Tendering of
the project

Preparing the
project plan in MS
Project Professional

Publish project
plan to the MS
Project Server
MS Project
Server 2003
Updating task
progress through MS
Project Web Access
by Pr. Mgr/Contractor

Review &
approve updates
by Project Mgr.

Generate/Submit
the bill Rs.

Close & archive


the project
Project Server

Project Professional

PMC

Prepare & publish


project plan,
monitor, accept
updates and
control project

Project Manager
Web Access

KSPHC Office Upload progress


information,
update tasks,
prepare & submit
bills

Contractor

Construction Site

KSPHC PMS Software Solution Infrastructure


Users/ Email/ Access Control Guidelines
To work all the stakeholders in an integrated fashion as part of the total
project management and more specifically the Microsoft Project Server 2003,
every user's credentials should be made available to the server. This actually
means creating a user account and storing his/her e-Mail address. The system
administrator from KSPHC creates the user account for a new user and
provides the user-name and password. The user can log-in to the KSPHC
domain through the Project Web Access. The URL for the project server is
http://wpms.ksphc.org/projectserver. The e-Mail address is used to send
notifications and alerts. Please see the section "Introduction to Project
Server 2003" for more details on using Project Web Access.

Introduction to Microsoft Project 2003


What is Microsoft Project?
Microsoft Project is a specialized database that stores and presents thousands
of pieces of data related to your project. Examples of such data include tasks,
durations, links, resource names, calendars, assignments, costs, deadlines,
and milestones.

You can manipulate and display elementary project information in various


views to analyze the planning and progress of your project. This information
helps you make decisions vital to the project's success.

You can also communicate your progress and provide the feedback necessary
to keep your team and other stakeholders informed of essential project
information create and print reports for status meetings or distribution to
stakeholders, and print or publish certain views or reports to your team's Web
site.

Microsoft Project Professional 2003


Microsoft Project Professional 2003 helps professional project managers
manage their portfolio and resources, collaborate on projects, and analyze
project information. Working with Microsoft Project Server, Microsoft Project
Professional's powerful project planning, reporting, scenario analysis, and
resource management capabilities provide organizations with a scalable and
customizable solution.

Microsoft Project Professional includes the following features:

ƒ Global templates, enterprise fields, and other elements, enabling a


system administrator to standardize and customize the use of
Microsoft Project for the way your enterprise manages projects.
ƒ The ability to choose and manage resources from the pool of a specific
group or the entire company. You can see resource availability across
multiple projects and have Microsoft Project automatically find
resources that will appropriately fill project team requirements.
ƒ High-level overviews of all the projects taking place throughout the
organization. With the new enterprise capabilities of Microsoft Project
Professional 2003, all information is gathered, organized, and reported
consistently throughout the organization, providing a complete and
accurate picture of all projects.
Working with Microsoft Project Professional 2003 as an
Enterprise Client

Introduction
This lesson is focused on the enterprise functionality that is available to users of the
system as opposed to the administrator(s) of the system.

There are many new features that are available when a user implements Microsoft®
Project Professional, all of which require a connection to Microsoft Project Server.

Microsoft Project Server Accounts

Overview
Microsoft Project Professional introduces a number of enterprise features. All
enterprise features are dependent on the Microsoft Project Professional connection
with a Microsoft Project Server. Each Microsoft Project Server provides access to a
different set of enterprise projects and resources.

Within larger organizations, as the deployment of Microsoft Project continues, project


managers may need to interact with multiple Microsoft Project Servers, as well as
needing a method for running Microsoft Project Professional in an offline mode.
When a connection is made to a specific Microsoft Project Server, the global template
from that environment is used and is cached when the session is ended. This cached
global template is used when working offline from the Microsoft Project Server. While
working offline on My Computer the local template file is used.

A user can define one or more Microsoft Project Server accounts for Microsoft Project
Professional to access. Each account will require an authorized user ID and password
to be entered to enable access.

When Microsoft Project Professional is started, the dialog box displayed depends on
the options that have been set. If an automatic logon has been chosen, the default
account is selected and the Microsoft Project Server Security Login dialog box
(see Figure 1) shows the user ID to be used in the connection and requires the user
to enter the correct password. Once this has been done, click Go to complete the
connection. If a manual connection is selected, then the next dialog box (see Figure
2 ) shows a list of available accounts, of which one should be selected. The
Username and Password is then supplied and the Go button clicked. Alternatively
the user can choose to work offline from a Microsoft Project Server or completely
locally by working offline on My Computer.
Figure 1. Microsoft Project Server Security Login dialog box

There may be a situation where connection to another Microsoft Project Server is


required. In that case, the Microsoft Project Server Security Login dialog box
should be closed with the Cancel button. A second dialog box then appears that
shows all of the available connections (see Figure 2).

Note: The above dialog box may flash or not be seen at all by a user that has a
Microsoft Windows® authenticated account as the default account. Windows
accounts do not require users to enter passwords.

Figure 2. Project Server accounts selection

To access an alternate Microsoft Project Server to the default account

1. Start Microsoft Project 2003 Professional.

2. Cancel the opening dialog box that asks for a password (if it is presented given in
figure 1).

3. Select a connection from the list of servers.

4. Click the Connect button. The enterprise global template is opened from the
server identified in the profile and the enterprise features are enabled, based on
your permissions to that server.
Windows Authenticated Accounts
Users with Microsoft Windows accounts do not get the opportunity to cancel the login
dialog so they will need to change Microsoft Project Professional to manually control
the connection state. The option can be seen in Figure 3. Once the new option is
selected, the user should close Microsoft Project. When Microsoft Project is reopened,
the dialog box in Figure 2 will display. The user then has the option to choose the
account they would like to use to create a connection with Microsoft Project Server.
Work Offline can also be chosen for a Microsoft Project Server or with My
Computer, which uses the local global template file only. Or choose Cancel, which
dismisses the dialog box and closes the application.

To create a new or amend an existing Microsoft Project Server connection


1. Start Microsoft Project Professional.

2. From the Tools menu, click Enterprise Options.

3. Select Microsoft Project Server Accounts.

-Or-

1. From the Start menu, select Programs.

2. Choose Microsoft Office Tools.

3. Choose Microsoft Project Server Accounts.


In both cases, the dialog box in Figure 3 is displayed.

Figure 3. Add a Project Server account


Add
To create an account, click the Add button and the Account Properties dialog box
in Figure 4 is displayed.

Figure 4. Account Properties


1. Enter a valid name for your connection. This should reflect the server you are accessing or
perhaps the reason you are accessing it, or even the level of permissions you have on the
server.
2. Enter the URL for the Microsoft Project Server site in the form of
http://<server_name>/<virtual directory name>.
3. Click the Test Connection button to verify the URL that has been entered. If there is a
problem connecting to the URL, an alert displays with details about the error.
4. Determine the method used to access the server by selecting either the Use Windows user
account or Use a Microsoft Project Server account option in the When connecting
section of the dialog box. If Microsoft Project Server account is selected, then enter the user
name to be used when activating the connection. This name cannot be changed when
accessing Microsoft Project Server. Multiple user access requires multiple Microsoft Project
Server accounts.
5. If you wish this account to be your default for Microsoft Project startup, then select the Set as
default account checkbox.

Note: To identify which account is currently being used to connect to the server, see the value to
the right of Current account directly under the Add button (see Figure 3).

Properties

To amend the properties of an existing connection


1. Select an account name and then click Properties.

2. Edit details about the account in the same way you add a connection.
Set as Default

To create a default account when using automatic connection


This sets the specified account to the one that will be used to automatically make the connection
when Microsoft Project Professional is opened.

To set the default

• In the Account Properties dialog box (see Figure 4), check the Set as default account
option.

Remove

To remove an account that is no longer required, you must start Microsoft Project
Professional in a different account from the one you want to delete.
1. Select the account name.

2. Click Remove, which shows the dialog box in Figure 5.

3. Choosing OK will delete the Microsoft Project Server account, while choosing Cancel will not
delete the Microsoft Project Server account and return to the view of all project accounts.

Figure 5. Deleting a Microsoft Project Server account

These changes cannot always be made when there is an existing active connection. For
example, the properties of an open connection cannot be changed. To change properties,
Microsoft Project Professional must be closed and restarted. Then, when the connection dialog
box appears, Cancel it and select Work Offline.
There are two other options available in the main dialog box. On startup, there is a choice to
automatically detect connection state or manually control the connection state. Microsoft
Project Professional will connect to the server indicated by the default account on startup if
automatic is chosen. If manually detect the connection state is selected, then the connection
to the default Microsoft Project Server is not made and the user must select a connection directly.

Open and Save Projects

Opening an Enterprise Project Plan


When you open a project in Microsoft Project Professional while connected to the Microsoft
Project Server, the Open from Microsoft Project Server dialog box shown in Figure 6 is
presented.
Figure 6. Opening a project from Microsoft Project Server

This shows the current projects that are held in Microsoft Project Server that the user has
permissions to see. For each project, it shows the value for:

• Project name

• Version

• Checked out status

• Checked out by

• Date last modified

While the Read/write option button is selected, project names that are already checked-out
cannot be checked out again and so they are shown grayed out. Click the option button next to
Read-only and all projects are available.
If the project does not exist on Microsoft Project Server but, for example in a file folder as a .mpp
file, the Open from File command button will provide a dialog box that allows the user to browse
for and select the required file.

Saving an Enterprise Project

If a connection to the Microsoft Project Server has been established, the user will be prompted for
both a name and a version for the new project when an enterprise project is saved for the first
time. Internally, within Microsoft Project Professional, the project name and version are stored
together separated by a period. This has two purposes: it supports backward compatibility and
ensures all project names are unique to the system. It should be noted that saving a version
overwrites any information that was already saved as that version. If a project is to be saved as a
different version, the Save As command should be used and new version selected from those
available in the drop-down box.
Figure 7. Saving a project with a version and outline code
Every time a project is saved, the values for any required Enterprise Outline Codes or any
Enterprise Custom fields are validated. Microsoft Project ensures that there is an entry in each of
the required fields and that the value matches any validation set in the specific field. In the case
of Enterprise Outline Codes, for example, a drop-down box will support the selection of a valid
entry. Entries can be changed at this point as well, as long as they are valid. For example, one of
the Custom fields may relate to the stage or phase of the project. This could be one of an agreed
list of phases, but the specific value for a project will be modified with time.
Selecting Save as File will allow the user to save the file to a location other than the Microsoft
Project Server, such as the hard drive or network location.

Save As
The Save As function works in exactly the same way as in other versions of Microsoft Project,
with one small difference. When an Enterprise project is opened—for example, one stored in
Microsoft Project Server and opened via a Project Account Server connection—there are two
global templates to be considered. There is the local file and the Enterprise global template that
contains all of the corporate data and standards.

Saving As File
When a copy of an enterprise project is made outside of Microsoft Project Server, two choices are
available. The project can be saved with enterprise global items except outline codes or only the
currently loaded enterprise global items. Copy a project with the Save As command and chose
Save as File.

Figure 8. Save As File


There are two other aspects of projects in the enterprise environment that need to be noted:

Cross-project links must be between projects of the same version. When an enterprise project
is saved to another version, its CP links are transformed to the new version, even if the linked
project does not exist in this version.
Open project with orphaned links. If links are orphaned for any reason (for example, the user
elects to save a single project as described above) this can be resolved on the next open of the
project. In earlier releases of Microsoft Project, a dialog box displays that allows the user to
browse for broken links. When resolved, any other links to the same project get resolved as well.

Save Offline
Enterprise projects can be saved offline so that:

• They can be worked on while disconnected from the Microsoft Project Server.

• They can be worked upon over multiple sessions, avoiding the check-in of incomplete
changes.

To save an enterprise project offline


1. Connect to the Microsoft Project Server.

2. Open the enterprise project that you want to work with from the server.

3. Choose Save Offline from the File menu.

Only the user who saves an enterprise project offline can work with it Read/write and only on the
computer on which the project was saved. Other users can open the project read-only but will
only view the project as it was at the time it was saved offline. Changes made in offline sessions
will not be visible until the project is saved online again.

Opening an Offline Project


An offline project is available in future sessions of the user who saved it offline, both connected
and working offline from the server.

To open a project saved offline


1. Start Microsoft Project Professional on the computer that the project was saved offline with
an account on the Microsoft Project Server (from which the offline project came, either
connected or working offline).
2. On the File menu, select Open (see Figure 9).

3. Select the offline project and click Open, or double-click the offline project. Offline projects
are denoted as such in the Checked-Out column.
Figure 9. Opening a project saved offline
Most of the changes that can be made online, such as adding and editing tasks and assignments,
are possible when working offline except those needing connection to the Microsoft Project
Server, including:

• Opening the enterprise resource pool or enterprise global.

• Collaboration functionality.

• Building team from enterprise.

When the active project in Microsoft Project is offline, the window title has the [Offline] suffix.

Save Online
All the changes made to an offline project, even over multiple sessions, are not saved to the
Microsoft Project Server until the project is saved online sessions of the user who saved it offline,
both connected and working offline from the server.
To save an offline project back to the server
1. Start Microsoft Project Professional on the computer that the project was saved offline with
an account on the Microsoft Project Server (from which the offline project came, either
connected or working offline).
2. From the File menu, click Open, and open the offline project.

3. From the File menu, choose Save Online.

4. In the Microsoft Project save dialog box, choose Yes to save all changes made offline back to
the Microsoft Project Server, choose No to discard the changes, or choose Cancel to return
to the project.

Figure 10. Save dialog box


5. The project will now be checked in and available to other users.
Introduction to Project Server 2003

Project Server and Web Access


Microsoft Project Server is the companion program that accompanies
Microsoft Project Professional 2003. Microsoft Project Server provides for
team collaboration among project managers, team members, and other
stakeholders.

Project managers use Microsoft Project to enter, store, and update project
information. They can then send project information, such as assignments or
task updates, to specific team members through Microsoft Project Server.

Team members and other associated stakeholders in the project can view and
work with the information held in Microsoft Project Server through the use of
a Web-based user interface called Microsoft Project Web Access. Not only can
team members review their assigned tasks and other project information in
Microsoft Project Web Access, they can add tasks, update progress
information, and send status reports through Project Server. This ultimately
updates the project plan being maintained by the project manage

Getting Started with Microsoft Project Web Access


The project manager and project system administrator are responsible for
setting up Microsoft Project Web Access user accounts for all team members
and other stakeholders on the project team. Access your account by doing the
following:

ƒ Open Internet Explorer on your computer.


ƒ In the Internet Explorer Address box, enter the Microsoft Project Web
Access URL (http://wpms.ksphc.org/projectserver) that your project
manager or project system administrator has provided for you. Press
Enter.
ƒ Enter your user name and password and then click the Log In button.
Your Microsoft Project Web Access Home page appears.
Figure 11.

On this page, you can click a link to learn more about new or updated tasks,
click a link in the left pane, or click a menu to display a different page.

When you're ready to end your Microsoft Project Web Access session, click the
Log Off menu.

Project Server Menus

Home
Homepage
Microsoft Project Web Access is the interface you use to work with information stored
in Microsoft Project Server. After you log on, the Home page lists outstanding tasks,
status reports, Alerts and other important project information that involves you. You
can click the links on the Home page to perform activities. You can also change
several of your Microsoft Project Web Access settings from the Home center's side
pane. And finally, you can click the links at the top of the window to view other
parts, or centers, of Microsoft Project Web Access.
Figure 12.

Alert me about my tasks and status reports


You can use this page to set e-mail notifications for tasks, issues, documents, and
status reports. You also use this page to set e-mail reminders for your own tasks and
status reports.
You can define when Microsoft Project Server sends e-mail messages relating to your
assignments, status reports, or other project information, such as documents or
issues. Managers can also set up e-mail notifications for you so that you receive both
the manager-defined notifications (for example for overdue tasks or status reports)
and the notifications you've defined yourself.

• In the side left pane, under Activities in home (click Alert me about my tasks and status
reports

• Follow the instructions that appear. For example, if you want to receive an e-
mail notification each time the start or finish dates or duration change on any
task you are assigned to, select the My project tasks are modified check
box.
• To avoid missing notifications of important events, you may want to check
more notifications and reminders than you think you need, and then, over
time, clear the notifications and reminders that are not useful to you.
• Click save Changes.
Figure 13.

Alert me about my tasks and status reports


You can use this page to set e-mail reminders for resources about their tasks or
status reports. You can define under what conditions Microsoft Project Server sends
team members or managers e-mail messages about their assignments, status
reports, or other project information. For each type of reminder you can choose to
have Microsoft Project Server send a reminder to just you, just the team member, or
both of you.
• In the side pane, click Alert me about my resources on tasks and status reports
• Follow the instructions that appear on your screen.
• Click save Changes.
Figure 14.
Tasks
The Tasks center lets you view, edit, and update project task assignments that have
been made in Microsoft Project. You can work with tasks in either a Gantt Chart or a
timesheet view. You can see which projects and tasks team members are working
on, a time phased breakdown of the amount of total work planned and actual work
done, and any nonproject time (such as vacations) that resources have entered. You
can only see information for the team members that the Microsoft Project Server
administrator has given you permission to see.

You can use the Tasks center to:


• View a time phased breakdown of work and actual work entered for each
resource.
• Enter vacation time, sick time, or other nonproject time and notify project
managers of the change.
• Add Microsoft Outlook tasks to your task list.
• Delegate tasks to other team members.
• Enter the work completed on tasks and automatically notify the project
managers.
• Filter, sort, and group project information to view or print it.
• Search for specific project information in one project or multiple projects.
Note: Depending on the permissions settings with which you logged on to Microsoft
Project Server, you may or may not be able to perform various activities in the Tasks
center.

View My Tasks
On clicking this, you can view the tasks assigned to you.
Figure 16.

Create a new Task

Project managers can add new tasks directly to resources' timesheets. Resources can
add tasks to their own timesheets and then submit them for approval. After you
update the timesheet, the new task is added to the selected project plan.

You can also create tasks for to-do lists to track personal tasks or small projects that
don't need formal scheduling.

Create a new task for a project:

1. In the side pane, click Create a New Task.


2. In the Project list, select the project to add the task to.
3. Under What outline level do you want to create the new task in?, choose the
level at which you'd like the new task to appear.
• To add a subtask that must be completed as part of an existing task
assigned to you, click Make the new task a subtask of, and then select
the existing task.
• To add a new task that isn't part of any existing tasks, click Create the
new task at the top outline level.

4. Under Task information, enter information about the new task.


Save New Task to add the task to the timesheet.
5. Click
Note: Clicking Save New Task sends a new task request to the selected project's
project manager. The project manager must approve the request before the task is
added to the project plan.
Create a new task for a to-do list:

1. In the side pane, click Create a New Task.


2. In the Where do you want the new task(s) to be created? section, in the note,
click Create a New To-do list.
3. On the next page, in the To-do list Name box, type a name for your list.
4. Specify users who can view this list:
• To make the list viewable by any user, click Anyone.
• To make the list viewable only by the people working on its tasks, click
All resources who are assigned tasks from this to-do list.

• To create a personal to-do list, click Me (only).

5. Click Next.
6. On the next page, enter the names and details of tasks you want on your to-do list.
7. Click Save New Task(s).

To add a task above the selected task, click Insert new task. To delete the selected task,
click Delete task.

Figure 17.
Delegate a task
You can delegate project tasks to others from a timesheet. When a resource delegates a
task to another team member, the change is sent to the project manager for approval.
Meanwhile, the task appears in the new team member's timesheet with an indicator that it
is pending approval.

When delegating a task you can:

• Delegate all responsibility for the task.


• Keep a copy of the task to view its status.
• Assume a lead role on the task to approve or reject the resource updates on the
task.
When you delegate a task to another team member, an e-mail notification is automatically
sent to the person. If a team member delegates task to another team member, the project
manager is also notified.

• In the side pane, click Delegate Tasks.


• If the task you want to delegate does not appear and it is assigned to you, make
sure that Show my tasks in addition to delegated tasks is selected. If the task
you want to delegate does not belong to you, select Show and then select the
category that contains this task.
• In the timesheet, select the task you want to delegate, click Delegate Task, and
then follow the instructions that appear on your screen.
Note: You will receive a message notifying you of the status of this task. Depending on
your role in the project team, the task delegation may be complete, the change may
require approval, or it may not be a task that you are eligible to delegate. (Depending on
how e-mail notification is set up by the server administrator, team members may or may
not receive e-mail notification messages.)

Figure 18.
View and report on your tasks from your Outlook calendar

1. In the side pane, View and report on your tasks from your Outlook calendar
2. In the first page of the wizard, select an update option, My manager or The
Microsoft Web Access Timesheet, and then click Next.
Note: If you want the nonworking time submitted to your project manager to be added to
the project plan, select My manager. The Microsoft Web Access Timesheet is only
available if your organization has enabled this option. Selecting this option inserts the
nonworking time in your timesheet but does not transfer it to the project plan, even when
you send task status updates.

3. In the next page, specify the dates and the minimum duration of the calendar
entries to transfer. Click Next.

Tips:

• You can screen out appointments or other short-term nonworking time by


entering a length of time, such as 1 hour or 90 minutes, in the Do not transfer
calendar entries shorter than box.
• Use the following abbreviations for times: m for minute, d for day, and w for
week. For example, type 2 weeks as 2w.

4 In the next page, select the entries that you want to transfer.
Note: If you chose to transfer entries to your timesheet in the first step, you must chose
a category in the Category column.

5 In the next page, if you chose to send an update of the transfer to your manager in
the first step, select one or more managers to notify.
Tips:
• To select a manager, click the name and then click Add. You can select more than
one at a time. To select adjacent names, holding down SHIFT, and then click the
first and last names you want. To select nonadjacent names, hold down CTRL,
and then click the names you want.
• To remove a name from the list, click Remove.
6. In the last page of the wizard, verify the dates and times to transfer, and then click
Send. If you want to change any information in the table before sending it, click Back.

Tips: At any point in the wizard, you can click Back to return to a previous page to
review or change information
Figure 19.

Notify Your Manager of a Change in Working Days

You can notify project managers of a change in working days and times from Microsoft
Project Web Access.

1. In the side pane, click Notify your manager of a change in your working days.
2. On the first page, select the type of change in working time and the time period, and
then click Next.
3. On the next page, select one or more managers to notify, and then click Next.

Tips
To select a manager, click the name and then click Add. You can select more than one at
a time. To select adjacent names, holding down SHIFT, and then click the first and last
names you want. To select nonadjacent names, hold down CTRL, and then click the
names you want.
To remove a name from the list, click Remove.

4. On the last page, verify the dates and times to transfer, and then click Send. If you
want to change any information in the table before sending it, click Back.
Figure 20.

Projects
In the Project Center you can view portfolios of projects or individual projects. You can
see either summary information about multiple projects or detailed information about
individual projects.
To-do lists are lists of tasks that are not associated with a project but that you want to
track. You can use a to-do list to break an assigned project task into smaller tasks, to
manage an informal team project, or to track a personal project. You can assign to-do list
tasks to other resources. You can also promote a to-do list to a project.

View Projects in Project center


You can view projects that have been published to Microsoft Project Server. You can see
summary information about multiple projects and review detailed information about
specific projects.
• In the side pane, click View Projects in Project Center.
• In the Choose a view box, click the view that contains the information you want.
• The chart portion of the Gantt Chart displays each project as a summary Gantt
bar. Different fields are displayed in the sheet portion of the view, depending on
the view you choose.
• To view a subset of the listed projects or to organize them into groups, click
Filter, Group, Search and then select the appropriate options
Project Center views display indicators about project-related information. For example,
document or issue indicators are displayed when documents or issues are linked to a
project.
To open the project from within Microsoft Project, select the project, and then click
Open in Microsoft Project.
Depending on permission settings, you can edit a project. Select the project you want to
edit, and then click Edit Project Details.
To create a shortcut to this view, click Save a Link.

Figure 23.
Create a New Personal or Shared to-do list
A to-do list is a named collection of tasks that are tracked and managed entirely in
Microsoft Project Server
Unlike projects, to-do lists don't support scheduling features such as dependencies,
outlining, and calendars. The tasks in a to-do list can have start and due dates and
resources can be assigned to them, but the time resources spend on these tasks isn't
accounted for in projects or other to-do lists.

To-do lists are easy to use and work well for small, informally-structured projects or
personal projects. For large or complex projects, Microsoft Project is a better solution.
To-do lists can be promoted into Microsoft Project projects from the to-do list options
page.
You can create a to-do list on Microsoft Project Server to track personal tasks or small
projects that don't need formal scheduling.

• To allow any user to view the list, click Anyone.


• In the side pane, click Create a personal or shared to-do list.
• On the next page, in the To-do list Name box, type a name for your list.
• Specify users who can view this list:

To allow only the people working on its tasks to view the list, click All resources who
are assigned tasks from this to-do list.

To create a personal to-do list, click Me (only).

• Click Next.
• On the next page, enter the names and details for tasks you want to include on
your to-do list.
• Click Save New Task(s).

Figure 24.
Create A New Task
Project managers can add new tasks directly to resources' timesheets. Resources can add
tasks to their own timesheets and then submit them for approval. After you update the
timesheet, the new task is added to the selected project plan.

You can also create tasks for to-do lists to track personal tasks or small projects that don't
need formal scheduling.

Create a new task for a project:

1. In the side pane, click Create a New Task.


2. In the Project list, select the project to add the task to.
3. Under What outline level do you want to create the new task in? , choose the
level at which you'd like the new task to appear.
• To add a subtask that must be completed as part of an existing task
assigned to you, click Make the new task a subtask of, and then select
the existing task.
• To add a new task that isn't part of any existing tasks, click Create the
new task at the top outline level.
4 Under Task information, enter information about the new task.
5 Click Save New Task to add the task to the timesheet.

Note: Clicking Save New Task sends a new task request to the selected project's project
manager. The project manager must approve the request before the task is added to the
project plan.
You can include more detailed task information, such as an explanation of why you are
adding this task, by adding a note to the task. The note appears with the new task in the
timesheet. Learn how to attach information to a task.

Create a new task for a to-do list:

• In the side pane, click Create a New Task.


• In the Where do you want the new task(s) to be created? Section, in the note,
click Create a New To-do list.
• On the next page, in the To-do list Name box, type a name for your list.
• Specify users who can view this list:

To make the list viewable by any user, click Anyone.

To make the list viewable only by the people working on its tasks, click All resources
who are assigned tasks from this to-do list.
To create a personal to-do list, click Me (only).

• Click Next.
• On the next page, enter the names and details of tasks you want on your to-do list.
• Click Save New Task(s).

To add a task above the selected task, click Insert new task. To delete the selected task,
click Delete.

Figure 25.
Manage My To-Do List

You can track the progress of tasks in to-do lists and update their progress. Like project
tasks, tasks on the to-do list are displayed in a Gantt Chart.

• In the side pane, click Manage my to-do lists.


• On the next page, to view the time tasks were started and finished, as well as the
date, or to view tasks at different outline levels, click View Options, and then
select the appropriate options.
To view a subset of the listed reports or to organize the reports into groups, click
Filter, Group, Search and then select the appropriate options.

• In the sheet, update the task information as needed.


• To track progress, type the percentage of the task that has been completed in the
% Work Complete field.
• If this field is not displayed on screen, scroll to the right until it becomes visible.

• To insert other tasks, click New Task(s), enter information in the task sheet, and
then click Save New Task.
• Click Save Changes.

You can quickly scroll to the start of a task in the chart portion of the Gantt Chart view.
Select a task, and then click the Scroll the Gantt Chart to the start of the selected task
button on the toolbar.
To see a different date range in the chart portion of the Gantt Chart view, click the Zoom
in and Zoom out buttons on the toolbar.
To attach additional information to a specific task, select the task, and then click Insert
Notes on the toolbar.
To delete the selected task, click Delete on the toolbar.

Figure 26.
To-Do List Options

Transfer a to-do list to another team member

If you transfer a to-do list to someone else, that person becomes the to-do list owner and
can work with the list, for example, by completing and delegating, the list's tasks or
updating and deleting tasks.

• In the side pane, click To-do list options.


• On the next page, under First, choose a to-do list, select the to-do list you want
to transfer.
• Under Transfer this to-do list, in the Transfer ownership of this to-do list to
box, select the person you want to transfer the to-do list to.
• Click Save.

If necessary, you can rename the to-do list. Under Rename this to-do list, in the
New to-do list name box, type a new name for the to-do list.

Turn a to-do list into a project

You may have to-do lists that have grown in scale, or you may have used a to-do list to
detail the tasks for a project. At any time, you can promote a to-do list to a project, or you
can use a to-do list to create a new project. Promoting a list to a project allows you to use
Microsoft Project's powerful scheduling abilities. You can create project phases, show
dependencies between tasks, schedule resources based on their work calendars, and much
more.

Note: You must have Microsoft Project installed before promoting a to-do list.

• In the side pane, click To-do list options.


• Under First, choose a to-do list, select the name of your to-do list.
• Under Promote this to-do list to a project, click Promote to Project.
• On the next page, under Promote to a Project, click Promote to Project.

Note: To add to-do list tasks to an existing project, in Microsoft Project, you can copy
the tasks from the newly promoted project and paste them into the existing project.
To-do list conversion is permanent; after you've promoted a to-do list to a project you
cannot revert to a to-do list.

Change viewing permissions for a to-do list


To allow or restrict access to your to-do list, you can change viewing permissions.

• In the side pane, click To-do list options.


• On the next page, under Change viewing permissions for this to-do list, click the
options you want.
• Click Save
Figure 27.
Updates

You use the Updates center to review updates to project tasks and to resource working
times and update your Microsoft Project plans with the latest information. There are two
ways to update information in your Microsoft Project plans:

Manually. As you open each task change submitted by a resource, click Update to
update the Microsoft Project plan. If you reply to the change before updating it, the
change is removed from your Messages list until the person that you sent the task change
to replies back to you. For some task changes, such as New Task and Delegation
Requests, you can send a reply and update the Microsoft Project plan at the same time.
Automatically, using rules. You can create and run rules to automatically update the
project plan with changes you don't feel you need to review before approving them. You
can create rules that run on only specific projects or on all projects and that run for only
specific resources or for resources at specific levels.
Note Unless you create and run rules to automatically process task updates, resource
submissions in Microsoft Project Server never affect the Microsoft Project plan without
your explicit approval.
The types of task changes you might receive include:

• Task updates
• New task requests
• Task delegation requests
• Resource declined assignments
• Resource declined task delegation requests

Update task changes submitted by resources into Microsoft Project

When resources submit task updates via Microsoft Project Server, you can approve or
reject them. The task updates you approve are posted to the Microsoft Project plan, where
they appear as actual work. Unless you create and run rules to automatically process task
updates, resource submissions in Microsoft Project Server never affect the Microsoft
Project plan without your explicit approval. Learn how to create rules.

1. In the side pane, click Update task changes submitted by resources into Microsoft
Project.
Note If you have updates pending approval, they are also listed on your Home page and
can be updated from there.

2. On the page that appears, in the Accept? Column, click Accept or Reject for the task
updates you want.
Tips

Accepting or rejecting a task update for an entire project or resource automatically


accepts or rejects the subtask updates associated with that project or resource. If you
accept some subtasks but reject others, the status (Mixed) appears at the summary levels.
To quickly accept all pending updates, click Accept all.

3. At the top of the page, click Update.


Microsoft Project Server sends a status update for the updated tasks to Microsoft Project
and attempts to open the project plan in Microsoft Project so you can verify the updates.

Notes

After you accept task changes, they remain visible until you save the updated Microsoft
Project plan.
After you accept a task delegation request and updated the Microsoft Project plan, you
cannot disapprove the delegation request.
Figure 28.

View History of Past Task Changes

You can view the task updates you have processed over the last 30 days. This history
is for review purposes only; you cannot edit past updates.

1. In the side pane, click View history of past task changes.


The task updates of the past 30 days appear, presented in a grid format.

2. In the task updates history grid, scroll to the right to see more details about each
update.

Tip Task updates appear in the grid after you have processed (either accepted or
rejected) them. To quickly jump to the page where you can process task updates, click
Show Task.
Figure 29.

Documentation on Customization of Project Server for


KSPHC PMS
Customized Menus

ProjectMgmt
Project Management is managing the projects and the activities related to the
projects. Here the contractors and engineers execute commands related to the
projects by selecting each project from the given list of projects. The activities
include the viewing and uploading of the documents, pictures, video clips, Q.C.
Reports. Engineers can enter their site visits under project management by selecting
the project first and then clicking the sitevisits link. Different reports and tests are to
be uploaded for the project in support for the working of projects. For this formats
are available under Project Management in Web Access. You can view and download
the templates for different Q.C (Quality Control) formats. All these activities grouped
together forms the Project Management.
Figure 30.

Project Info

View/Upload Documents
This page helps you to view or upload documents of a particular project. To work
with a particular project, first select the project name from the drop-down list. And
then click on the first link which is View/Upload Documents. The View/Upload
Documents page appears on the screen.
Figure 31.

There are two sections on this page. One section is for uploading the documents.
And the other section is for viewing the details about the documents, and link to the
actual document.

For uploading any document, click on the Browse button to locate the document
from your computer. A File Open dialog box appears, go to the location where your
file resides and select the file you want to upload and click Open button. The file
path is displayed now in the Local Path text box. Now, write some description about
the file in the Description textbox. Finally click the Upload button and then the file
is uploaded. Now you can see the details such as File Name, Size, Date Uploaded,
Description etc of the uploaded file in the lower section of the page. There are also
other two links namely View and Copy which allows you to perform following
operations.

• View Click on the view icon to see the document, which will be opened in a
new window.

• Copy If you want the same document to be available for other project, click
on the Copy icon, a Copy File window appears, select the project name to
which you want to copy the document. The actual description appears in the
Description textbox. You can change the description if you want to. Click the
Done button. The window disappears. This completes the copying of the
document to another project. Repeat the same steps if you want to copy the
document for other projects.
View/Upload Pictures
Follow the same instructions as specified above in the topic View/Upload
Documents to View/Upload Pictures. There is only one exception that is you
need to mention the Pic. Tkn Dt (the date on which the picture is taken) while
uploading the Pictures. There is a button next to Pic. Tkn Dt textbox. Click the
button. A window will appear containing a calendar. Select the date and click
Choose This Date link.

Figure 32.

View/Upload Video Clips


Follow the same instructions as specified above in the topic View/Upload
Documents to View/Upload Video Clips.
Figure 33.
View Drawings
*Note for documenters: Only AEDES can upload the drawings. The rest can only
view.

AEDES:
Follow the same instructions as specified above in the topic View/Upload
Documents for View/Upload Drawings.

Others:
You can see the details such as File Name, Size, Date Uploaded, Description,
view etc in this page. Click on the view icon to see the drawing, which will be
opened in a new window.

View/Upload Q.C. Reports


Follow the same instructions as specified above in the topic View/Upload
Documents for View/Upload Q.C. Reports.
Figure 34.

Site Visits
The site visit information can be recorded through this page. The Project Name,
Location, Your Designation are displayed. Select the type of inspection from the
Inspection Type dropdown list. Select the Date of Visit. There is a button next to
Date of Visit textbox. Click the button. A window will appear containing a calendar.
Select the date and click Choose This Date link. Now the date is displayed in the
textbox. Enter your brief comments about the inspection or site visit in the
Comments box. There are two types of inspections namely Normal and Quality. If
you select the Inspection Type as Quality then the other options will be available
below the Inspection Type dropdown list…….[*Note for documenters: To be
continued.]. Click Submit button to upload the site visit details.
Figure 35.

Q.C. Format
Click on any of the links below to download the templates of particular Q.C. Format
for creating reports. These templates are in Excel format. You can save it to your
computer and reuse it.

• Coarse Aggregate
• Fine Aggregate
• Physical Tests on Cement
• Sand for Deleterious Materials
• Test Reports on Steel
• Test on Cement
• Test on Concrete
• Test Results of Bricks
• Test Cement Concrete Cubes
Financial

Add/Edit/Update options for all the rates and items used in the billing and Scheme
related information are available under this category.

Figure 36.
Scheduled Rate Entry Form

Figure 37.

Use this form for entering a new record in the SR Database for a particular task.
Basic Rates, Constants can be added in this Scheduled Rate Entry Form for
different tasks of the construction activities. Click Save button to save the entry.
There are two more operations accessible through the Show List and Search
buttons.
• Show List To edit the entries which were already saved, click the Show List
button. Now Update Page appears with the rates for all the tasks and
information related to each task for all nine circles. You can select a
particular/all circle(s) from the Select The Name Of The Circle dropdown
list. You can edit the information and save it by clicking the Save button.

Figure 38.
• Search To go to the Search Page and search for rates and constants of a
specific task, click on Search button. In the Search Page type your search
text in the textbox provided and select the circle name from the Select The
Name Of The Circle dropdown list. Click the Search button. All the records
matching the search criteria will be displayed. You can edit and save them.

Figure 39.
Lead Rates Entry Form
Lead Rates Entry Form enables you to edit and update the Lead Rates for different
items such as sand, brick, jelly, earth and laterite.

Figure 40.
Scheme Details

In the Scheme Details page you can add a new scheme, view the details of the
schemes, edit/update the details of an existing scheme and delete a scheme. To do
this use the four links available on this page.

Figure 41.
• Add New On this page you can enter the details of the scheme in the
textboxes provided and save it.

Figure 42.
• Edit/Update On this page you can select the Scheme which you want to edit
from the Select Scheme Name dropdown list. Make the changes required
and save.

Figure 43.
• View On this page you can see the details of all the available schemes.

Figure 44.
• Delete On this page you can select the Scheme which you want to edit from
the Select Scheme Name dropdown list. Click Delete button to delete the
selected scheme.

Figure 45.
Royalty Charges

Royalty Charges page enables you to edit and update the Royalty Charges for
different items such as sand, brick, jelly, earth and size-stone.

Figure 46
Cement Rates Entry Form

Cement Rates Entry Form page enables you to edit and update the Cement Rates
for different circles.

Figure 47.
Archive

The Projects that were migrated from earlier version (MS Project 2000) are made
available under Archive Project Information. Here information such as Project
Details, Milestones of all the projects and Site Visits.

Project Details
Click on this link to go to Archive Project Management page where you can view,
add, edit/update and delete the old Projects Details.

Figure 48.
• Add New Click on Add New link to go to the Archive Project Entry Form
page. Enter the Project Details in the textboxes provided on this page and
save.

Figure 49.
• Edit/Update On this page you can select the Project Name which you want
to edit from the Select Project dropdown list. Make the changes required
and save.

Figure 50.
• View On this page you can see the details of all the available Archived
Projects.

Figure 51.
• Delete On this page you can select the Project Name which you want to edit
from the Select Project dropdown list. Click Delete button to delete the
selected Project and its Details.

Figure 52.
Edit Site Visits
Click on this link to go to Archive Project Site Visits page. Select the Project Name
for which you want to edit Site Visits from the Select Project Name dropdown list.
You now will view all the site visits for the selected project. Click on the edit link in
corresponding site visit row. Site Visit Update page will appear with Project Name,
District Name, Date of Visit and Description. You can edit the Date of Visit and
Description.

Figure 53.
Edit Milestones Info
Click on this link to go to Archive Project Milestones page. Select the Project
Name for which you want to edit Milestones from the Select Project Name
dropdown list. You now will view all the Milestones for the selected project. You can
change the status of Milestones as completed by clicking the update link under Set
as Complete column. Click on the update link under Set as Incomplete column to
make the milestone incomplete.

Figure 54.

FinancialMgmt
All the financial aspects of the KSPHC construction projects are grouped under a
category named Financial Management. The contractor has to maintain an MB book
which reflects the measurements for the work executed for each task. This MB book will
be uploaded by the contractor for a project and it will be referred by the other officials in
the hierarchy. Once the Contractor send updates and the project manager accepts those
task updates then the contractor can generate a bill. The MB book uploaded for that bill
will be a reference to the officers reviewing the bill in the hierarchy. All the different
rates/charges used in billing are made available for reference in the financial
management. The other aspects like mobilization advance request, Adhoc payment
request, final bill generation comes under this category.
Financial Management section includes all the functionalities related to the
financial aspects of all the KSPHC projects. These include the functionalities like
viewing different types of rates and other financial aspects used in billing, paid bills, and
pending bills. In prospective of a contractor, this is the place where he can generate

different kinds of bills. For generating the bills, viewing the MB and adding extra items
first you need to select the Project Name from Select Project Name dropdown list and
proceed.

Figure 55.

Generate Bill
After selecting the project name from Select Project Name dropdown list, click on
Generate Bill link to generate the bill for the selected project. Now you can see the bill
with bill number on the top. The table in the page displays the tasks, unit, estimated qty,
rate, previous, present, and up-to-date quantities and amounts along with the remarks.
Review the bill summary (royalty, F.S.D, Income tax etc) at the bottom of the page. Click
the submit button to submit the generated bill. It will ask for Confirmation of the Bill. If
everything is correct then you click the Yes Button to submit the bill. If there is any
work-slip for this bill then the Lead Rate Calculation window appears. Enter the
distance information for all the items in the window. Click the Submit button to submit
the lead rates for the bill. The Work Slip window will be displayed. Enter your
comments in the remarks column. Click the Submit button. A message "Mail has been
successfully Forwarded." appears on the screen. Click the Close button to dismiss the
window. One more message "Submit the bill now." is displayed. Click Ok. Now click
the Yes button again. And your bill will be submitted.
SR Rates
Click on this link to view SR Rates and constants for different activities for nine different
circles on SR Rates page. You can select the circle name from Select the Name of the
Circle dropdown list for which you want to see the Rates and constants. The rates shown
with the detailed information like the serial number and description of the rates, basic

rates, and constants for different types of items such as sand, brick, jelly, earth , size-
stone etc.

Figure 56.
Royalty Charges

Royalty Charges page enables you to view the Royalty Charges for different items such
as sand, brick, jelly, earth and size-stone.

Figure 57.
MB Book Template

Figure 58.

Click on MB Book Template link to download the template of MB Book. This template
is in Excel format. You can save it to your computer and reuse it.
Figure 59.

View/Upload MB Book
This page helps you to view or upload MB Book of a particular project. To work with a
particular project, first select the project name from the drop-down list. And then click on
the link which is View/Upload MB Book. The View/Upload MB Book page appears on
the screen.
Figure 60.

There are two sections on this page. One section is for uploading the MB Book. And the
other section is for viewing the details about the MB Book, and link to the actual MB
Book file.

For uploading any MB Book, click on the Browse button to locate the MB Book file
from your computer. A File Open dialog box appears, go to the location where your file
resides and select the file you want to upload and click Open button. The file path is
displayed now in the Local Path text box. Now, write some description about the file in
the Description textbox. Finally click the Upload button and then the file is uploaded.
Now you can see the details such as File Name, Size, Date Uploaded, Description etc of
the uploaded file in the lower section of the page. There are also other two links namely
View and Copy which allows you to perform following operations.

• View Click on the view icon to see the MB Book, which will be opened in a new
window.

• Copy If you want the same MB Book to be available for other projects, click on
the Copy icon, a Copy File window appears, select the project name to which you
want to copy the document. The actual description appears in the Description
textbox. You can change the description if you want to. Click the Done button.
The window disappears. This completes the copying of the MB Book to another
project. Repeat the same steps if you want to copy the MB Book for other
projects.
Packagewise Summary
Click on Package Summary link to see the package wise details of the amounts for the
projects. On this page, select the package name from Package Name dropdown list for
which you want to view the details. Now you can see all the projects that come under that
package with the details of Contract Amt, Previous Amt, Present Amt, Up-to-date Amt
and approximate work slip Amt. Package wise summary is shown at the bottom of the
table with total number of locations in that package.

Figure 62.
Generate Final Bill
Click on this link to Generate Final Bill for a selected project. Once you generate the
Final Bill, you cannot generate any other bills. This page has the same functionality as
the Generate Bill link. So, follow the instructions as mentioned for Generate Bill to
generate final bill.

Add Extra Item


When you click the Add Extra Item link you will be directed to the Extra Item Form.
Adding extra item means adding the number of tasks under special circumstances to the
project which were not specified in the project plan. Follow a note displayed at the top of
the page. The numbers of tasks that are already available in the database are included in
the Select Item of Work dropdown list. Select the task from the list if the task is
matching with the task you want to add. Else click on the Click Here to Enter Item of
Work button. Type-in the task in the Item of Work textbox. Select any of the two option
button next to the Item of Work textbox according to the type of task. Select unit from
the Unit drop-down list box. If the unit is not available in the list select other from the
list and type the Unit in the textbox next to the list. Enter the quantity in the Approximate
Quantity textbox. Then to calculate the rate, just click on the button next to the Rate
textbox. On clicking this, a Lead Rates Calculation window will appear. In that, enter
the distance in the distance column. Then click on Submit button. The amount will
automatically be calculated and displayed in the Amount textbox. Then specify the time
taken in days, select either additional or alternative from the next dropdown list and
provide other necessary details. Then click the Submit button to add one extra item.
Repeat the same process specified above to add more extra items. But the new items you
have just added will have no immediate effect, until you click on the Send Mail button to
send a request with all added extra item details to the Project Manager. And that finally
completes adding extra items.

Lead Rates
Lead Rates page enables you to view the Lead Charges for different items such as sand,
brick, jelly, earth and laterite.

Figure 63.
Paid Bills

Figure 64.

Click on this link to see the paid bills on Paid Bills page. You will see the KSPHC
hierarchy on the top left part of the page. Click on any of the username in the hierarchy.
Now you will see the projects assigned to the username you clicked on the hierarchy.
You can see the paid bills such as Bills, Work slips, Extra Items, Archive sub-links for
each project. Drill down the tree view to check the bills. When you select a bill from the
tree view, that bill is displayed.
Pending Bills
Click on this link to see the pending bills on the Pending Bills page. You will now see
the list of pending bills in a tabular form with the details such as Project Name, Agency,
Bill submitted by which person, Bill pending with whom, Bill Type, Estimated project
Cost, Up-to-date Amount and days lapsed. You can sort by any column and see the
details. Click on the Project Name to view the bill/work slip/extra item etc.

Figure 65.
Collaboration
Collaboration is all about communicating with other members of the project team. Here
you can post messages on the board as how you put messages on the notice board and
post alerts for the team members. First select the project name from Select Project Name
dropdown list for which you want to post/view messages or alerts.

Figure 67.
Notice Board
Notice Board is a place where you can post your comments and also can view the
comments placed by others.

Post Message
Click on Post Message link to post a message on to the notice board of the selected
project. You can see the Project Name, logged-in username, Subject textbox and Message
textbox on the Post Message to Notice Board page. You can type the subject of the
message in the subject textbox and type your message in the message textbox.

Figure 68.
Click on Submit button to save the message to notice board. A message appears as
Message has been saved successfully. Click back button and you will be taken back to
Collaboration page.

Figure 69.
View messages
Click on View Messages link to view the messages posted by the team members on to
the notice board for the selected project. On the View Notice Board page you can see the
Project Name and different messages posted for that project with details such as subject
of the message, username of the person who posted the message, Date on which the
message has been posted, District name for the selected project and the actual message.

Figure 70.

Alerts
Alerts links are used to notify the team members of a project against some events or
actions. These alerts can be raised by any team member of the project and can be notified
by e-mails from the post message page.

Post Alerts
Click on Post Alert link to post an alert on a topic for the selected project. You can see
the Project Name, logged-in username in Name textbox, Email textbox, Topic textbox
and Description textbox on the Post Alert/Post Topic page. You can type the topic on
which you want to post an alert in the topic textbox and type the details of the topic in the
description textbox. An address book is provided on this page with names of all
members of the team. You can tick in the each checkbox to select the persons to whom
you want to send notification about the alert. If you want to notify to all persons then tick
select all check box. The selected persons email ids are automatically displayed in the
email textbox when you tick in the check box. Click Submit button to send the alert.
Figure 71.
View Alerts:

View Alert page displays all the alert messages for the selected project. You can see the
date, topic, description, user and action taken for the alerts. Topic is hyperlinked here.
Click on any topic to view the details for that particular topic.

Figure 72.

On this page you can see the topic and all the replies or responses sent for that topic.
Click on the topic or replies then you can see the description of the selected topic or reply
in the bottom frame on the same page. You can send responses or replies to the topics by
clicking on Respond to topic link on the top of the page.
Figure 73.

On Respond to topic page you can see the description on the top of the page. The other
things are same as in the Post Alert page and you can submit the replies here.
Figure 74.

Figure 75.
Click on the Final Action Taken link on the top right corner on the View Alert/View
Topic page to send/save the final action taken for the alert. You can send/save the final
action taken on the topic you have selected as explained in the Post Alert page. Once the
final action was taken the topic will be closed and responses/replies cannot be made for
that topic.

Delete Alerts:
This page is for administrative purpose. All the topics which are closed and final action
has been taken will be listed on this page for the selected project. You can delete the topic
along with the replies by selecting from the checkbox against the topic.

Figure 76.
View/Upload images:
This page allows the PMC to access the mails sent to [email protected]. All the emails
sent using mms technology can be retrieved from this page. Here you can edit the data
and save it. You can also edit the picture and put some comments on the picture. You can
save these pictures, documents, etc to the project. Once you copy the document/picture to
a project it is shown as uploaded and with different background color for that message.
You can delete the record after copying to project.

Figure 77.
Figure 78.

ReportMgmt

Report Management helps you generating many different types of reports which depict
the progress of the projects, corporate summary, financial status, and physical
construction information.
Figure 79.

Project progress

Contractor Wise
Agency Wise Report page allows you to get the reports according to a particular
Contractor/Agency. You can also select different Division and District name to filter the
information of a particular contractor. On the Agency Wise Report page serial number,
project name, site handover date, est. end date, act start date, act end date, PDC(Probable
Date of Completion), total delay, budget cost, up-to-date expenditure, cost over, last task
completed, and send mail information is available. Click on the link under project name
for the project you want see the project details. Click on the Send Mail link to send an e-
Mail to the contractor.
Figure 80.

Figure 81.
Division Wise
Division Wise Report page allows you to get the reports according to a particular
Division. You can also select different Agency and District name to filter the information
of a particular Division. This page is conceptually identical to the Agency Wise Report
page. Please refer to the Contractor Wise section described previously on this page.

Figure 82.

Scheme Wise
On the Scheme Report page the details related to each schemes are shown. The details
such as scheme name, Scheme budget, amount spent, Number of residential and non-
residential buildings (categorized as to-be built, ongoing and completed), Costoverrun,
time overrun and quality overrun are shown. The overruns are shown in green color in
normal case and in red color if there is any overrun. These are hyperlinked and will take
you to the reports on which overrun you click.

• Time overrun report will show the projects for the selected scheme with project
details such as project name, contractor name, EE, est start date, est end date, act
start date, act end date, PDC, Total projected delay, last task completed and the
send email link. Send email link will open the email form to send an email
regarding the selected project to the team members of the project. The Project
name is hyperlinked and on clicking, it will open the project details summary in a
separate window. Total delay is also hyperlinked and on clicking, it will show the
Tasks summary report with the details such as task name, baseline start date,
baseline end date, act start date, act end date, task delay, est qty, rate, act qty and
excess qty, excess amt if any. The summary is shown on the top of the page. The
tasks that are overrun are shown in red.
• Cost overrun report will show the projects for the selected scheme with details
such as project name, contractor name, division, EE, Budget Amount, up-to-date
expenditure, Excess amount against estimated (overrun), last task completed and
send mail link. The projects that are overrun are shown in red. Excess amount
against estimated is hyperlinked and on clicking it bill details report for the
project is shown.
• Time overrun report will show the projects that have quality overrun for the
selected scheme. The details such as project name, contractor name, division, EE,
start date, end date, last task completed, number of quality defects and send mail
link are shown on this report. Send mail and project name are hyperlinked in the
same manner as explained in the time and cost overrun. Number of quality defects
column is hyperlinked and on clicking it will show the quality defects reported by
the engineers of KSPHC. The details such as Employee designation, date of visit,
quality defect rating and comments are shown.

Figure 83.

District Wise

District Wise Report page allows you to get the District wise details. Click on any
particular district, of which you want to see the report, you will get a list of Ongoing,
Completed as well as Proposed projects belonging to that District with the schemes
showing on one side. Click on any project and you can see the summary information
belonging to that project.
Figure 84.

Figure 85.
Figure 86.

Corporate Summary:

Site visit Report


Site Visit report shows all the site visits uploaded by the team members of the projects.
Here select the project name from the select the project name drop-down list and select
the designation/person from the Site Visit by drop-down list box. Now all the site visits
for the selected project uploaded by the selected person are shown with the details of
employee/designation, date of visit, quality defect, quality index, project name and
description.
Figure 87.
Update Details:
Update Details report is designed to check the update details of the projects. The projects
which were not up-to-date in uploading photos, site visits, documents and project's
progress are shown here with the last updated dates. Send mail link is provided to send
email to the members of the project.
Figure 88.
Generalized Query
Generalized query is used to generate different kinds of report as per request generated by
selecting the columns and filters provided on the page.
Figure 89.
Interface to the KSPHC Website

To make the operations and activities of the organization more transparent


KSPHC continually publishes project related summary information on its
website to be viewed by any common man.

To review the projects' summary information type the URL of the website
http://www.ksphc.org in your internet browser's (for example Microsoft
Internet Explorer) Address box. When the home page is loaded, click on the
projects link, which is located in the top portion of the page. The new page
displays a map containing all the districts of Karnataka state. Click on any
district. All the KSPHC projects under the district are listed. You can know the
status of a project by the font color of the project name. The color is red if the
project in at ongoing stage, green if it's completed and yellowish pink if it is
just proposed. Click on any project name to view the detail information of the
project.

Figure 91.

You can view more information about KSPHC projects by visiting the Our
performance highlights link on the home page of the website. The
destination page of this link includes several links which contains information
like Buildings handed over by KSPHC, Financial highlights, Live streaming etc.
Figure 92.

Conclusion

With the KSPHC PMS based on Microsoft Project , Microsoft Project Server and
Customised Web Pages, KSPHC Employees are finding it easier to collaborate on
complex and demanding projects, to provide highly detailed and accurate project
estimates, and to stay informed about schedules and milestones no matter where they
happen to be working. For KSPHC, this means a workforce that is not only more
productive but also more focused on what ultimately matters the most - Quality Projects
done within the Budget and On-Time!!!.
.

You might also like