SEDIMENTAnswers
SEDIMENTAnswers
Q1.
Cheng’s formula:
1/3
𝑤𝑠 𝑑 (𝑠 − 1)𝑔
= [(25 + 1.2𝑑∗ 2 )1/2 − 5] 3/2 , where ∗
𝑑 = 𝑑[ ]
𝜈 𝜈2
Densities:
𝜌sand = 2650 kg m–3
𝜌air = 1.2 kg m–3
𝜌water = 1000 kg m–3
Kinematic viscosities:
𝜈air = 1.5 × 10–5 m2 s–1
𝜈water = 1.0 × 10–6 m2 s–1
Soulsby’s formula,
∗
0.30 𝜏𝑏
𝜏crit = + 0.055 [1 − exp(−0.020𝑑 ∗ )], where 𝜏∗ =
1 + 1.2𝑑 ∗ (𝜌𝑠 − 𝜌)𝑔𝑑
Hence,
∗
0.30
𝜏crit = + 0.055 [1 − exp(−0.020 × 25.30)] = 0.03141
1 + 1.2 × 25.30
∗
𝜏crit = 𝜏crit × (𝜌𝑠 − 𝜌)𝑔𝑑 = 0.03141 × (2650 − 1000) × 9.81 × 0.001 = 0.5084 N m−2
Answer: critical Shields parameter = 0.0314; critical shear stress = 0.508 N m–2
2 𝜏𝑏
𝑉=√
𝑐𝑓 𝜌
2 0.5084
𝑉=√ × = 0.4510 m s−1
0.005 1000
By definition,
𝜏𝑏 1 𝑐𝑓
𝑢𝜏 = √ = √𝑐𝑓 ( 𝑉 2 ) = 𝑉√
𝜌 2 2
Hence,
𝑐𝑓
𝑉√ = 𝑤𝑠
2
2 2
𝑉 = 𝑤𝑠 √ = 0.1115√ = 2.23 m s −1
𝑐𝑓 0.005
From the critical Shields stress we can determine the critical bed stress for incipient motion:
𝜏crit = 𝜏 ∗ (𝜌𝑠 − 𝜌)𝑔𝑑 = 0.056 × (2650 − 1000) × 9.81 × 0.06
= 54.39 N m−2
(b) Sluice gate assumption: total head the same on both sides of the gate.
𝑉12 𝑉22
𝑧𝑠1 + = 𝑧𝑠2 +
2𝑔 2𝑔
For a flat bed:
𝑞2 𝑞2
ℎ1 + = ℎ2 +
2𝑔ℎ12 2𝑔ℎ22
Substituting values:
0.04128
2.507 = ℎ2 +
ℎ22
Rearranging for the supercritical solution:
0.04128
ℎ2 = √
2.507 − ℎ2
Then:
𝑞 0.9
𝑉= = = 6.829 m s−1
ℎ2 0.1318
Answer: downstream depth = 0.132 m; bed stress exceeds the critical value
(c) Scour will continue with the depth increasing and the velocity and stress decreasing, until
the stress no longer exceeds the critical value. At this point:
𝜏𝑏 = 54.39 N m−2
1
𝑐𝑓 × 𝜌𝑉 2 = 54.39
2
2 54.39 2 54.39
𝑉 =√ × =√ × = 3.298 m s−1
𝑐𝑓 𝜌 0.01 1000
Sluice gate assumption: total head the same on both sides of the gate.
𝑉12 𝑉22
𝑧𝑠1 + = 𝑧𝑠2 +
2𝑔 2𝑔
Upstream, 𝑧𝑠1 = ℎ1 , but downstream there is a distinction between water level 𝑧𝑠2 = 0.1318 m
and depth ℎ2 = 0.2729 m.
𝑞2 𝑞2
ℎ1 + = 𝑧𝑠2 +
2𝑔ℎ12 2𝑔ℎ22
Substituting values:
0.04128
ℎ1 + = 0.6861
ℎ12
Rearranging for the subcritical solution:
0.04128
ℎ1 = 0.6861 −
ℎ12
Iteration (from, e.g., ℎ1 = 0.6861) gives
ℎ1 = 0.5493 m
Answer: depth of scour = 0.141 m; depth upstream = 0.549 m; depth downstream = 0.273 m
Settling velocity:
𝑤𝑠 = 1.1 m s –1 (given)
Friction velocity:
𝜏 233.2
𝑢𝜏 = √ =√ = 0.4829 m s−1
𝜌 1000
Here, the settling velocity greatly exceeds the friction velocity, so suspended load is negligible.
The bed is mobile if and only if the bed shear stress exceeds the critical stress for incipient
motion. Alternatively, one may compare the velocity with a critical velocity found using the
friction coefficient – this is more convenient here.
2 𝜏crit 2 8.093
𝑉crit = √ =√ × = 1.272 m s−1
𝑐𝑓 𝜌 0.01 1000
If critical-flow conditions occur at the throat then the total head there would be
2 1/3 1/3 1/3
3 3 𝑞𝑚 3 𝑄2 3 52
𝐻𝑐 = ℎ𝑐 = ( ) = ( 2 ) = ( 2 ) = 0.9850 m
2 2 𝑔 2 𝑏min 𝑔 2 3 × 9.81
Since the upstream head exceeds that required for critical-flow conditions the flow remains
subcritical throughout, with total head in the restricted section, 𝐻 = 1.051 m. The depth ℎ is
given by:
𝑉2 𝑄2
𝐻 =ℎ+ =ℎ+ 2
2𝑔 2𝑔𝑏min ℎ2
Rearranging as an iterative formula for the subcritical value of ℎ:
Hence we have:
• in the 5 m width, 𝑉 = 1.0 m s–1 < 𝑉crit and the bed is stationary;
• in the 3 m width, 𝑉 = 1.94 m s –1 > 𝑉crit and the bed is mobile.
(b) The bed will erode in the restricted section until 𝑉 = 𝑉crit . Then the flow depth is given by
𝑄 = 𝑉crit × ℎ𝑏min
𝑄 5
ℎ= = = 1.310 m
𝑏min × 𝑉crit 3 × 1.272
If Δ𝑧𝑏 is the change in height of the bed, then the total head is given by
𝑉2
𝐻 = Δ𝑧𝑏 + 𝐸 = Δ𝑧𝑏 + ℎ +
2𝑔
Hence,
𝑉2 1.2722
Δ𝑧𝑏 = 𝐻 − ℎ − = 1.051 − 1.310 − = −0.3415 m
2𝑔 2 × 9.81
Answer: 0.342 m
Let the minimum stone diameter (corresponding to incipient motion) be 𝑑. Then the critical
shear stress for incipient motion is given by
∗
𝜏crit = 𝜏crit (𝜌𝑠 − 𝜌)𝑔𝑑 = 0.056 × (2650 − 1000) × 9.81 × 𝑑 = 906.4𝑑
The corresponding depth of flow ℎ is given by the expression for 𝑅ℎ in a rectangular channel,
ℎ
30.80𝑑 =
2ℎ
1+
𝑏
With 𝑏 = 12 m this gives (after some rearrangement) an expression for ℎ in terms of 𝑑:
30.8𝑑
ℎ= (**)
1 − 5.133𝑑
Measuring head relative to the top of the weir, noting that the upstream head is just the
freeboard and the head over the weir is 3/2 times critical depth:
1/3
3 𝑞2
ℎ0 = ( )
2 𝑔
Hence, the flow rate (per metre width of embankment) is
3/2
𝑞 = (2/3)3/2 𝑔1/2 ℎ0 = (2/3)3/2 × 9.811/2 × 0.153/2 = 0.09905 m2 s −1
Critical depth:
2 2
ℎ𝑐 = ℎ = × 0.15 = 0.1 m
3 0 3
Answer: flow rate (per metre width) = 0.0990 m2 s–1; depth over embankment = 0.1 m
(b)
𝑆 = 0.125
𝑛 = 0.013 m–1/3 s
Normal Depth
1 2/3
𝑞 = 𝑉ℎ, where 𝑉 = 𝑛 𝑅ℎ 𝑆 1/2, 𝑅ℎ = ℎ (wide channel)
1 5/3 1/2
𝑞= ℎ 𝑆
𝑛
Velocity
𝑞 0.09905
𝑉= = = 2.878 m s −1
ℎ 0.03442
Answer: depth = 0.034 m; velocity = 2.88 m s–1; bed stress = 42.2 N m–2
∗
0.30
𝜏crit = + 0.055 [1 − exp(−0.020𝑑∗ )] = 0.03987
1 + 1.2𝑑 ∗
∗
𝜏 ∗ is far in excess of 𝜏crit ; hence the surface will erode.
(Alternatively, one could compute the absolute critical stress 𝜏crit to compare with 𝜏).
(b)
1 2/3 1/2
𝑞 = 𝑉ℎ, where 𝑉= 𝑅 𝑆 , 𝑅ℎ = ℎ
𝑛 ℎ
Hence,
1 5/3 1/2
𝑞= ℎ 𝑆
𝑛
or
𝑛𝑞 3/5
ℎ=( ) = 1.532 m
√𝑆
Answer: 1.53 m
(c)
𝜏𝑏 = ρ𝑔𝑅ℎ 𝑆 = 18.79 N m−2
(d)
1/3
∗
(𝑠 − 1)𝑔
𝑑 = 𝑑[ ] = 75.89
𝜈2
By Soulsby’s formula,
∗
0.30
𝜏crit = + 0.055 [1 − exp(−0.020𝑑∗ )] = 0.04620
1 + 1.2𝑑 ∗
Here,
𝜏𝑏
𝜏∗ = = 0.3869
(𝜌𝑠 − 𝜌)𝑔𝑑
∗
As 𝜏 ∗ > 𝜏crit the bed is mobile.
Van Rijn
0.053
𝑞∗ = 2.1 = 0.9604
𝜏∗
(𝑑 ∗ 0.3 ) ( ∗ − 1)
𝜏crit
Hence,
𝑞𝑏 = 𝑞 ∗ √(𝑠 − 1)𝑔𝑑3 = 6.349 × 10−4 m2 s −1
Answer: bed load = 1.0510–3 m2 s–1 (Meyer-Peter and Müller); 6.3510–4 m2 s–1 (Van Rijn)
By definition,
𝜏𝑏
𝑢𝜏 = √ = 0.1371 m s−1
𝜌
(a)
𝑑1/6 (5 × 10−4 )1/6
𝑛= = = 0.01335 m−1/3 s
21.1 21.1
(b)
1 2/3 1/2
𝑞 = 𝑉ℎ, where 𝑉= 𝑅 𝑆 , 𝑅ℎ = ℎ
𝑛 ℎ
Hence,
1 5/3 1/2
𝑞= ℎ 𝑆
𝑛
Answer: 1.46 m
(c)
𝜏𝑏 = 𝜌𝑔𝑅ℎ 𝑆 = 1000 × 9.81 × 1.464 × 0.00125 = 17.95 N m−2
(d)
1/3 1/3
∗
(𝑠 − 1)𝑔 (2.65 − 1) × 9.81
𝑑 =𝑑 [ ] = 0.0005 × [ ] = 12.65
𝜈2 (1.0 × 10−6 )2
∗
As 𝜏 ∗ > 𝜏crit the bed is mobile.
Nielsen
∗
𝑞 ∗ = 12(𝜏 ∗ − 𝜏crit )√𝜏 ∗ = 12 × (2.218 − 0.03084)√2.218 = 39.09
Hence,
𝑞𝑏 = 𝑞 ∗ √(𝑠 − 1)𝑔𝑑3 = 39.09 × √1.65 × 9.81 × 0.00053 = 1.758 × 10−3 m2 s−1
Answer: bed load = 1.1610–3 m2 s–1 (Meyer-Peter and Müller); 1.7610–3 m2 s–1 (Nielsen)
𝜏𝑏 17.95
𝑢𝜏 = √ =√ = 0.1340 m s−1
𝜌 1000
(f)
0.117 𝜏 ∗ 0.117 2.218
𝐶ref = min { ( ∗ − 1) , 0.65} = min { ( − 1) , 0.65}
𝑑 ∗ 𝜏crit 12.65 0.03084
⬚ = min{0.6559, 0.65} = 0.65
A simple Fortran code for doing the numerical integration is given on the following page. The
code can be modified for any alternative values of 𝑘𝑠 or velocity and concentration profiles.
A significant number of trapezia is necessary (probably 200+), although this could be reduced
by using Simpson’s rule instead. For any numerical method you should always perform the
calculations with more, shorter, subintervals to confirm that numerical accuracy is sufficient.
The need to be able to vary the number of intervals is one reason why a spreadsheet alone is
not particularly good at this, as it would require intervention to change the number of trapezia.
WRITE( *, "('Suspended load: ', ES10.3, ' m3/s per metre')" ) INTEGRAL
!--------------------------------------
END FUNCTION C
!--------------------------------------
END FUNCTION U
(b)
For normal flow:
1 2/3 1/2
𝑞 = 𝑉ℎ, where 𝑉= 𝑅 𝑆 , 𝑅ℎ = ℎ
𝑛 ℎ
1 5/3 1/2
𝑞= ℎ 𝑆
𝑛
3/5
Average velocity:
𝑞 3.5
𝑉= = = 2.087 m s−1
ℎ 1.677
∗
0.30
𝜏crit = + 0.055 [1 − exp(−0.020𝑑 ∗ )]
1 + 1.2𝑑 ∗
0.30
= + 0.055 [1 − exp(−0.020 × 63.24)] = 0.04338
1 + 1.2 × 63.24
Answer: bed shear stress = 11.0 N m–2 and exceeds the critical shear stress
(e)
By Cheng’s formula:
3/2 1 3/2
∗ 2 1/2
𝑤𝑠∗ = [(25 + 1.2𝑑 ) − 5] 2 )2
= [(25 + 1.2 × 63.24 − 5] = 517.5
𝜈 1.0 × 10−6
𝑤𝑠 = × 𝑤𝑠∗ = × 517.5 = 0.2070 m s−1
𝑑 0.0025
𝜏𝑏 10.97
𝑢𝜏 = √ =√ = 0.1047 m s−1
𝜌 1000
Expanding:
drag 𝜈
= 24 ×
1 2 𝑤𝑠 𝑑
(projected area)
2 ρ𝑤𝑠 ×
Hence,
1 3
6 π(𝜌𝑠 − 𝜌)𝑔𝑑 = 24 𝜈
1 2 1 2 𝑤𝑠 𝑑
2 𝜌𝑤𝑠 × 4 π𝑑
𝜌𝑠
4 ( 𝜌 − 1) 𝑔𝑑 𝜈
2
= 24
3 𝑤𝑠 𝑤𝑠 𝑑
1 (𝑠 − 1)𝑔𝑑2
= 𝑤𝑠
18 𝜈
Integrating by parts:
ℎ
𝑢𝜏 𝑧 ℎ
𝑉ℎ = {[𝑧 ln (33 )] − ∫ d𝑧}
𝜅 𝑘𝑠 0 0
𝑢𝜏 ℎ
𝑉ℎ = {ℎ ln (33 ) − ℎ}
𝜅 𝑘𝑠
𝑢𝜏 ℎ
𝑉= {ln (33 ) − 1}
𝜅 𝑘𝑠
or, since ln e = 1,
𝑢𝜏 33 ℎ 𝑢𝜏 ℎ
𝑉= ln ( ) = ln (12 )
𝜅 𝑒 𝑘𝑠 𝜅 𝑘𝑠
(with 2 sig. fig. accuracy for the constant)
𝜏𝑏
𝑢𝜏 = √
𝜌
(c) According to Fick’s gradient-diffusion law the net upward flux of sediment volume across
a horizontal area A is
d𝐶
−𝐾 𝐴
d𝑧
whilst the net downward flux due to settling is volume flux concentration, or
𝑤𝑠 𝐴𝐶
At equilibrium these are equal and hence
d𝐶
−𝐾 𝐴 = 𝑤𝑠 𝐴𝐶
d𝑧
Dividing by A and rearranging:
d𝐶
𝐾 + 𝑤𝑠 𝐶 = 0
d𝑧
(d)
(Note that all sketches below have the independent variable – here the vertical coordinate – on
the vertical axis.)
Velocity:
Eddy viscosity:
nt
(e)
Bed-load transport:
• set in motion by the fluid stress;
• main mechanisms: sliding, rolling, saltating (small jumps).
Suspended-load transport:
• occurs for sufficiently vigorous turbulent fluid motion;
• balance between net upward transport by turbulent eddies and downward settling;
• usually quantified by solving a diffusion equation (see the following question), then
integrating the resultant flux density (𝐶𝑈) over the flow cross-section.
Separating variables:
d𝐶 𝑤𝑠 d𝑧
=−
𝐶 𝜅𝑢𝜏 𝑧 (1 − 𝑧 )
ℎ
𝐶 𝑤𝑠 𝑧 ℎ−𝑧
ln =− (ln − ln )
𝐶ref 𝜅𝑢𝜏 𝑧ref ℎ − 𝑧ref
𝐶 𝑤𝑠 𝑧ref ℎ − 𝑧
ln = ln ( )
𝐶ref 𝜅𝑢𝜏 𝑧 ℎ − 𝑧ref
On the RHS, inside the logarithm divide both numerator and denominator by 𝑧 × 𝑧ref :
𝑤𝑠
ℎ 𝜅𝑢𝜏
𝐶 − 1
ln = ln ( 𝑧 )
𝐶ref ℎ
− 1
𝑧ref
𝑤𝑠
ℎ 𝜅𝑢𝜏
𝐶 − 1
=( 𝑧 )
𝐶ref ℎ
− 1
𝑧ref
dC
C+l
dz
C ws
dC
C-l
dz
(b)
𝑧
𝜅𝑢𝜏 𝑧 (1 − ) d𝐶
− ℎ = 𝑤𝑠 𝐶
d𝑧
Separating variables:
d𝐶 𝑤𝑠 d𝑧
=−
𝐶 𝜅𝑢𝜏 𝑧 (1 − 𝑧 )
ℎ
d𝐶 𝑤𝑠 1 1
=− ( + ) d𝑧
𝐶 𝜅𝑢𝜏 𝑧 ℎ − 𝑧
Integrating between a reference height 𝑧ref and 𝑧:
C
d𝐶 𝑤𝑠 𝑧 1 1
∫ =− ∫ ( + ) d𝑧
𝐶ref 𝐶 𝜅𝑢𝜏 𝑧ref 𝑧 ℎ − 𝑧
𝐶 𝑤𝑠 𝑧ref ℎ − 𝑧
ln = ln ( )
𝐶ref 𝜅𝑢𝜏 𝑧 ℎ − 𝑧ref
Dividing top and bottom of the last fraction by 𝑧 and 𝑧ref :
𝑤𝑠
ℎ κ𝑢τ
𝐶 − 1
ln = ln ( 𝑧 )
𝐶ref ℎ
− 1
𝑧ref
𝑤𝑠
ℎ 𝜅𝑢𝜏
𝐶 − 1
=( 𝑧 )
𝐶ref ℎ
− 1
𝑧ref
(c) The sediment flux can be determined by summing contributions 𝐶(𝑈 d𝐴) over a cross-
section, where d𝐴 = 𝑏 d𝑧 and 𝑏 is the width of the channel:
ℎ
𝑄𝑠 = 𝑏 ∫ 𝐶𝑈 d𝑧
𝑧ref
Using the trapezium rule (no need to learn this formula – just sum trapezoidal areas if you
prefer) on 𝑁 intervals (here, 𝑁 = 3) this is approximated by
Δ𝑧
𝑄𝑠 = 𝑏 (*)
2(𝑓0 + 2 ∑𝑁−1
𝑖=1 𝑓𝑖 + 𝑓𝑁 )
In this case,
𝑏 =5m
ℎ − 𝑧ref 1.5 − 0.001
Δ𝑧 = = = 0.4997 m
𝑁 3
𝑤𝑠
𝜅𝑢𝜏 0.3659
ℎ 1.5
−1 −1
𝐶 = 𝐶ref ( 𝑧 ) = 0.65 ( 𝑧 )
ℎ 1499
𝑧ref − 1
𝑢𝜏 𝑧
𝑈 = ln (33 ) = 0.4878 ln(33000𝑧)
𝜅 𝑘𝑠
𝑓 = 𝐶𝑈
Using (*),
0.4997
𝑄𝑠 = 5 × × (1.1089 + 2 × (0.2731 + 0.1762) + 0) = 2.508 m3 s−1
2