A AL HARITH SAIF GHANEEM AL AMRY
Status Finished
Started Sunday, 8 December 2024, 11:09 PM
Completed Monday, 9 December 2024, 1:12 AM
Duration 2 hours 2 mins
Grade 0.70 out of 5.00 (14%)
Question 1
Partially correct
Mark 0.20 out of 2.00
v1 (latest)
The activity details and their predecessors are given below use the PERT method to calculate the expected time (1 Mark) and construct the
network diagram (1 Mark) to find the critical path of the activity (1 Mark) also indicate the project duration (1 Mark) with the standard
deviation (1 Mark).
Activity Predecessors the expected Optimistic Most likely Pessimistic
time
time time time
(to) (tm) (tp)
A -- 4 9 28
B A 3 17 30
C A 1 1 1
D B,C 2 16 30
E C 6 24 6
F E 5 8 22
G E 6 14 4
H F,G 3 6 3
I D 3 6 16
J H,I 7 15 8
Note: Use upto 3 decimal in your answer and enter your answer in the box, also kindly upload your worked out sheet below.
Enter the expected activity time for A. 11.33
One possible correct answer is: 11.333333333333
Enter the expected activity time for B. 18.16
One possible correct answer is: 16.833333333333
Enter the expected activity time for C. 1.000
One possible correct answer is: 1
Enter the expected activity time for D. 16.33
One possible correct answer is: 16
Enter the expected activity time for E. 13.00
One possible correct answer is: 18
Enter the expected activity time for F. 9.500
One possible correct answer is: 9.8333333333333
Enter the expected activity time for G. 11.33
One possible correct answer is: 11
Enter the expected activity time for G. 4.500
One possible correct answer is: 5
Enter the expected activity time for G. 7.000
One possible correct answer is: 7.1666666666667
Enter the expected activity time for G. 12.50
One possible correct answer is: 12.5
Find the critical path value for the total project duration? 36.66
One possible correct answer is: 47.5
Standard deviation 7.921
One possible correct answer is: 0.37267799624996
Your answer is partially correct.
You have correctly answered 3 part(s) of this question.
Response history
Step Time Action State Marks
1 8/12/24, 23:09:27 Started Not yet
answered
2 9/12/24, 01:06:47 Saved: 11.333, 18.167, 1.000, 16.333, 13.000, 9.500, 11.333, 4.500, 7.000, 12.500, Answer saved
36.667, 7.921
3 9/12/24, Attempt finished Partially 0.20
01:12:24 correct
Question 2
Partially correct
Mark 0.50 out of 2.00
v1 (latest)
The following data relate to advertisement expenditure and their corresponding sales, create a scatter plot and find a regression equation
between advertisement expenditure and their corresponding sales (1 Mark). Then use the regression equation to find sales the advertisement
expenditure for 35 (1 Mark) and 100 (1 Mark).
Note: Use upto 3 decimal in your answer and enter your answer in the box, also kindly upload your worked out sheet answer in link
provided below.
Advertisement Sales
expenditure
44 107
55 85
86 34.5
64 48
79 72
50 87.5
67 87
75 62.5
55 43
Enter the average advertisement expenditure : 63.88
One possible correct answer is: 63.888888888889
Enter the average corresponding sales : 69.61
One possible correct answer is: 69.611111111111
Enter the equation constant b value: -0.73
One possible correct answer is: -1.0394517116616
Enter the equation constant a value: 116.8
One possible correct answer is: 136.02052602282
Enter the sales for 35 advertisements : 91.64
One possible correct answer is: 99.639716114667
Enter the sales for 100 advertisements : 43.39
One possible correct answer is: 32.075354856666
Your answer is partially correct.
You have correctly answered 2 part(s) of this question.
Response history
Step Time Action State Marks
1 8/12/24, 23:09:27 Started Not yet answered
2 9/12/24, 01:06:47 Saved: 63.888, 69.611, -0.735, 116.897, 91.646, 43.397 Answer saved
3 9/12/24, 01:12:24 Attempt finished Partially correct 0.50
Question 3
Incorrect
Mark 0.00 out of 1.00
v1 (latest)
Raymond Bro. has been buying a given item in lots of 8226 units. The cost per unit is 20 and the order cost is 46 per order and the carrying
cost is 31 %.
Calculate:
Note: use up to 3 decimal in your answer and also kindly upload your worked out sheet answer in link provided below.
A) Inventory carrying cost. 2550
One possible correct answer is: 6.2
B) Economic Ordering Quantity. 6674
One possible correct answer is: 349.3754796869
C) Optimum order interval in days. 0.811
One possible correct answer is: 15.502315838283
D) Average inventory at any time. 3337
One possible correct answer is: 174.68773984345
E) storage cost at any time. 2069
One possible correct answer is: 1083.0639870294
F) Minimum total inventory cost per year. 4138
One possible correct answer is: 2166.1279740588
Your answer is incorrect.
Response history
Step Time Action State Marks
1 8/12/24, 23:09:27 Started Not yet
answered
2 9/12/24, 01:06:47 Saved: 25500.6, 6674.809167, 0.811428297, 3337.404584, 20691.90842, Answer saved
41383.81684
3 9/12/24, Attempt finished Incorrect 0.00
01:12:24
Question 4
Complete
Not graded
v1 (latest)
upload all your worksheets
note : I could not transfer two files from my phone due to some reason which are 1 page answer for each of the question 2,3 and I tried
doing them on Ms EXEL and it didnt work either ,so now Im forced to submit becuase I dont have much time left.
Thank you Dr.
Have a nice day.
screen shot Q1.pdf
Response history
Step Time Action State Marks
1 8/12/24, Started Not yet
23:09:27 answered
2 9/12/24, Saved: Incomplete
01:06:47 answer
3 9/12/24, Saved: note : I could not transfer two files from my phone due to some reason which are 1 Answer
01:12:19 page answer for each of the question 2,3 and I tried doing them on Ms EXEL and it didnt saved
work either ,so now Im forced to submit becuase I dont have much time left. Thank you Dr.
Have a nice day.Attachments: screen shot Q1.pdf (429.4 KB)
4 9/12/24, Attempt finished Complete
01:12:24