The activity details and their predecessors are given below use the PERT method to calculate the expected time (1 Mark) and construct the
network diagram (1 Mark) to find the critical path of the activity (1 Mark) also indicate the project duration (1 Mark) with the standard
deviation (1 Mark).
Activity Predecessors the expected Optimistic Most likely Pessimistic
time
time time time
(to) (tm) (tp)
A -- 4 9 16
B A 5 5 40
C A 1 1 1
D B,C 18 16 34
E C 6 24 6
F E 11 14 16
G E 6 14 4
H F,G 3 6 3
I D 5 14 19
J H,I 7 15 8
Note: Use upto 3 decimal in your answer and enter your answer in the box, also kindly upload your worked out sheet below.
Enter the expected activity time for A. 9.333
One possible correct answer is: 9.3333333333333
Enter the expected activity time for B. 10.83
One possible correct answer is: 10.833333333333
Enter the expected activity time for C. 1.000
One possible correct answer is: 1
Enter the expected activity time for D. 19.33
One possible correct answer is: 19.333333333333
Enter the expected activity time for E. 18.00
One possible correct answer is: 18
Enter the expected activity time for F. 13.83
One possible correct answer is: 13.833333333333
Enter the expected activity time for G. 11.00
One possible correct answer is: 11
Enter the expected activity time for G. 5.000
One possible correct answer is: 5
Enter the expected activity time for G. 13.33
One possible correct answer is: 13.333333333333
Enter the expected activity time for G. 12.50
One possible correct answer is: 12.5
Find the critical path value for the total project duration? 73.16
One possible correct answer is: 47.5
Standard deviation 5.947
One possible correct answer is: 0.37267799624996
Your answer is partially correct.
You have correctly answered 9 part(s) of this question.
Response history
Step Time Action State Marks
1 6/12/24, 10:12:39 Started Not yet
answered
2 9/12/24, 09:50:12 Saved: 9.333, 10.8333, 1.000, 19.333, 18.000, 13.833, 11.00, 5.000, 13.333, 12.500, Answer saved
73.167, 5.947
3 9/12/24, Attempt finished Partially 0.60
09:50:19 correct
Question 2
Partially correct
Mark 0.25 out of 2.00
v1 (latest)
A survey was conducted to study the relationship between expenditure on accommodation (X) and expenditure on Food and Entertainment
(Y) and the following results were obtained. Find a regression equation between expenditure on accommodation and expenditure on Food
and Entertainment (1 Mark). Then use the regression equation to find the expenditure on accommodation for 90 OMR (1 Mark) and for 200
OMR (1 Mark).
Expenditure Food
on accommodation expenditure &
(OMR) Entertainment
(OMR)
112 142
165 80
258 87.5
124 57.5
188 90.5
136 77.5
126 93
172 80
164 42.5
Note: Use upto 3 decimal in your answer and enter your answer in the box, also kindly upload your worked out sheet answer in link
provided below.
Enter the average expenditure on accommodation : 149.4
One possible correct answer is: 160.55555555556
Enter the average expenditure on Food and Entertainment : 83.38
One possible correct answer is: 83.388888888889
Enter the equation constant b value: -0.03
One possible correct answer is: -0.10601942425936
Enter the equation constant a value: 88.90
One possible correct answer is: 100.41089645053
Enter the expenditure on accommodation for OMR 90 : 85.58
One possible correct answer is: 90.869148267188
Enter the expenditure on accommodation for OMR 200 : 81.52
One possible correct answer is: 79.207011598658
Your answer is partially correct.
You have correctly answered 1 part(s) of this question.
Response history
Step Time Action State Marks
1 6/12/24, 10:12:39 Started Not yet answered
2 9/12/24, 09:50:12 Saved: 149.444, 83.389, -0.0369, 88.909, 85.584, 81.522 Answer saved
3 9/12/24, 09:50:19 Attempt finished Partially correct 0.25
Question 3
Partially correct
Mark 0.83 out of 1.00
v1 (latest)
ABC Ltd. uses EOQ logic to determine the order quantity for its various components and is planning its orders. The Annual consumption is
21200 units, Cost to place one order is 1175, Cost per unit is 63 and carrying cost is 22 % of Unit cost.
Calculate:
Note: use upto 3 decimal in your answer and also kindly upload your worked out sheet answer in link provided below.
A) Inventory carrying cost. 13.86
One possible correct answer is: 13.86
B) Economic Ordering Quantity. 1896
One possible correct answer is: 1895.9210412136
C) Optimum order interval in days. 32.63
One possible correct answer is: 32.64203679448
D) Average inventory at any time. 948.1
One possible correct answer is: 947.96052060682
E) storage cost at any time. 1313
One possible correct answer is: 13138.73281561
F) Minimum total inventory cost per year. 2956
One possible correct answer is: 26277.465631221
Your answer is partially correct.
You have correctly answered 5 part(s) of this question.
Response history
Step Time Action State Marks
1 6/12/24, 10:12:39 Started Not yet answered
2 9/12/24, 09:50:12 Saved: 13.864, 1896.373, 32.635, 948.187, 13137.548, 29563.958 Answer saved
3 9/12/24, 09:50:19 Attempt finished Partially correct 0.83
Question 4
Complete
Not graded
v1 (latest)
upload all your worksheets
Activity Completed (2).pdf
Response history
Step Time Action State Marks
1 6/12/24, 10:12:39 Started Not yet answered
2 9/12/24, 09:50:12 Saved: Attachments: Activity Completed (2).pdf (1.6 MB) Incomplete answer
3 9/12/24, 09:50:19 Attempt finished Complete