STRU-MISC - Structural Manual - Rev 60 - 2024-03

Uploaded by

yh wan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views

STRU-MISC - Structural Manual - Rev 60 - 2024-03

Uploaded by

yh wan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 356

STRUCTURAL MANUAL

Ministry of Transportation Ontario


Transportation Infrastructure Management
Division, Standards and Contracts Branch
Structures Office
March 2024
ISBN 978-1-4868-7395-1
© The King’s Printer for Ontario.
Reproduced with permission.

Although the contents of this manual have been checked no warranty, expressed or implied, is
made by the Ministry of Transportation as to the accuracy of the contents of this manual, nor shall
the fact of distribution constitute any such warranty, and no responsibility is assumed by the
Ministry of Transportation in any connection therewith. It is the responsibility of the user to verify
its currency and appropriateness for the use intended, to obtain the revisions, and to disregard
obsolete or inapplicable information.
STRUCTURAL MANUAL

STRUCTURAL MANUAL ENQUIRIES

To all users of the: STRUCTURAL MANUAL

Enquiries regarding amendments, suggestions or comments should be directed to:

Manager, Structures Office


Ministry of Transportation Ontario
Transportation Infrastructure Management Division
Standards and Contracts Branch
Structures Office
2nd Floor, 301 St. Paul Street
St. Catharines, Ontario
L2R 7R4

Email: [email protected]
Phone: 905-704-2406

March 2024 Page 1 of 1 SM-D0-S02


STRUCTURAL MANUAL

RECORD OF REVISIONS

RECORD OF REVISIONS

This Structural Manual dated March 2024 includes Revision #60 and supersedes the previous
edition. Numerous changes were made from the previous edition by re-ordering and renumbering
of the clauses to group similar concepts together, along with other minor clarification corrections.
Major changes are summarised as follows:

DIVISION 1 - EXCEPTIONS TO THE CHBDC

Section 4:
• CHBDC reference clarified to use NBCC 2020 seismic hazard values. Slight adjustment
to calculation of Seismic Performance Category (SPC).

Section 8:
• Concrete crack width (allowable reinforcing steel stress) equation modified.

Section 10:
• Allowance for crash tested barriers for use on sidewalks.

Low Volume:
• Minor change in TL1 barrier warrants.

DIVISION 2 - PROCEDURES

Section 2:
• Description of 500 MPa reinforcing steel.
• Changes to standard drawing format.
• Addition of section on structure naming and clarification of site numbers.

Section 3:
• Renaming section as “Deep Foundations” and having separate sections for driven and
drilled foundations.

Section 4:
• Renaming of section as “Shallow Foundations”.

Section 5:
• Moved approach slabs from section 16 and allowing approach slabs >6 m length to
improve drainage.
• Moved slopes and slope protection segment from section 16.
• Updated section about Wingwall Design Aid to describe changes to DA-5-1 through 6.

Section 8:
• Added information about use and detailing of atmospheric corrosion resistant (ACR) steel.
• Permit additional types and grades of steel allowed in the CHBDC to be used. Steels
which are not ACR shall be coated.

March 2024 Page 1 of 3 SM-D0-S04


STRUCTURAL MANUAL

RECORD OF REVISIONS

• Addition of 1” bolts for bridges with spans greater than 50m.


• Clarified protection of steel clauses.
• Updated details and figures.

Section 9:
• Added section on partial depth precast deck panels.
• Added details for curb forming (still to come).

Section 10:
• Added Section on inspector Guards.
• Moved Noise walls/barriers section from Section 16 to Section 10.

Section 12:
• Added descriptions for 500 MPa reinforcing steel.
• Added information on reinforcement couplers.
• Moved segment on dowels from section 16 to Section 12.

Section 15:
• The entire section has been revised to include up to date information on sawn timber,
prefabricated mass timber and treatment with preservatives.

Section 16:
• Moved approach slabs and slopes and slope protection to section 5.
• Moved dowels in concrete to section 12.
• Removed most of the pedestrian bridge requirements and referred to CSA S7.
• Moved segment on Noise walls / barriers to section 10.

DIVISION 3 - DESIGN AIDS

• Revised DA5-1 through DA5-6 on cantilever wingwall design.


• Added design aid DA 10-1 & DA 10-2 containing dead load of permanent and temporary
barriers respectively.

DIVISION 4 - STRUCTURAL STANDARD DRAWINGS

Division 4 has been removed. All the Structural Standard Drawings have been included in the
Structural Standard Drawings Manual which is available on MTO’s Technical Publications
Website. They are available either individually, or collectively under the title “SSD Complete
Manual”. Changes and updates of Structural Standard drawings information about new and
archived drawings are listed in “SSD Revision Sheet All-Rev" and available on MTO’s Technical
Publication Website.

March 2024 Page 2 of 3 SM-D0-S04


STRUCTURAL MANUAL

RECORD OF REVISIONS

This page has been intentionally left blank.

March 2024 Page 3 of 3 SM-D0-S04


STRUCTURAL MANUAL

PREFACE

PREFACE

The Structural Manual was first developed by the Structural Office in the 1970's to provide a
convenient reference for procedures, policies, design provisions, design aids, and Structural
Standard Drawings that were to be used in the preparation of Ministry structural contract
documents. Subsequently the manual has been continuously updated to reflect changes due to
metrication, new bridge codes and current practices. Since its inception the Structural Manual
has been revised to be compatible with the AASHTO code, OHBDC, and now with this edition the
CHBDC. To accommodate the growth in bridge engineering knowledge the Structural Manual
will continue to be revised by the Structures Office when appropriate.

The current manual is divided into the following three divisions:

Division 1 - Exceptions to the Canadian Highway Bridge Design Code


Division 2 - Procedures
Division 3 - Design Aids

A Table of Contents or a List precedes each division as appropriate.

Although the Ministry of Transportation (MTO) has developed this manual as a standard for their
use, other bridge owners may use it as a resource document from which they can develop their
own standards and policies. However, any variation should not be a substantial departure from
the Structural Manual or cause an adverse effect on the safety and movement of people and
goods. Any deviation from this manual should be based on operational experience and objective
analysis. The MTO does not accept responsibility in any connection with the variations. For MTO
structures, any deviation from the requirements of this manual shall be approved by the MTO
Structural Section (of the Design and Engineering Branch) in consultation with Structures Office.
In MTO design-build projects, all uses of the word ‘should’ shall be interpreted as mandatory
requirements unless a higher standard is applied and approved by MTO Structural Section.

Suggestions for the improvement of this manual, or for the addition of new material, should be
forwarded to:

Manager, Structures Office


Ministry of Transportation Ontario
Transportation Infrastructure Management Division
Standards and Contracts Branch
Structures Office
2nd Floor, 301 St. Paul Street
St. Catharines, Ontario
L2R 7R4

Email: [email protected]
Phone: 905-704-2406

March 2024 Page 1 of 2 SM-D0-S06


STRUCTURAL MANUAL

PREFACE

This page is intentionally left blank.

March 2024 Page 2 of 2 SM-D0-S06


STRUCTURAL MANUAL

TABLE OF CONTENTS

TABLE OF CONTENTS
RECORD OF REVISIONS ......................................................................................................... 1
PREFACE .................................................................................................................................. 1
TABLE OF CONTENTS ............................................................................................................. 1
NOTATIONS .............................................................................................................................. 1
DIVISION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE DESIGN CODE2
1 EXCEPTIONS TO THE CHBDC, CSA S6-19 ............................................................... 2
1.1 Scope ........................................................................................................................ 2
1.2 Authority .................................................................................................................... 2
1.3 Implementation .......................................................................................................... 2
1.4 Exceptions ................................................................................................................. 2
2 APPENDIX A - GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME
ROADS ........................................................................................................................ 2
2.1 Scope ........................................................................................................................ 2
2.2 Introduction ................................................................................................................ 2
2.3 Definitions .................................................................................................................. 2
2.4 Provisions, Guidelines, and Commentaries ................................................................ 3
2.5 References ...............................................................................................................12
DIVISION 2 – PROCEDURES ........................................................................................ 2
1 INTRODUCTION.......................................................................................................... 2
1.1 General ...................................................................................................................... 2
1.2 Definitions .................................................................................................................. 2
1.3 Distribution of Structural Manual’s Copies.................................................................. 2
1.4 Numbering System of Structural Manual .................................................................... 2
1.5 Structural Standard Drawings .................................................................................... 3
1.6 Ontario Provincial Standard Drawings (OPSDs) ........................................................ 4
1.7 Ministry of Transportation Ontario Drawings (MTODs) ............................................... 5
1.8 Structures Office Policy Memos ................................................................................. 5
2 DESIGN AND GENERAL DRAFTING .......................................................................... 3
2.1 Design ....................................................................................................................... 3
2.2 Bridge Geometry........................................................................................................ 4
2.3 Geotechnical Design .................................................................................................10
2.4 Design - Material.......................................................................................................12
2.5 Miscellaneous Design Guidance ...............................................................................17
2.6 Drawings...................................................................................................................24

March 2024 Page 1 of 5 SM-D0-S08


STRUCTURAL MANUAL

TABLE OF CONTENTS

3 DEEP FOUNDATIONS ................................................................................................ 2


3.1 General ...................................................................................................................... 2
3.2 Driven Piles ............................................................................................................... 3
3.3 Drilled Shafts ............................................................................................................12
3.4 Pile Caps ..................................................................................................................14
4 SHALLOW FOUNDATIONS ......................................................................................... 2
4.1 General ...................................................................................................................... 2
4.2 Design Criteria ........................................................................................................... 2
5 ABUTMENTS AND EARTH RETAINING SUBSTRUCTURES ..................................... 2
5.1 General ...................................................................................................................... 2
5.2 Abutment Design ....................................................................................................... 3
5.3 Mechanically Stabilized Earth (MSE) Systems (RSS) ...............................................12
5.4 The Use of MSE (RSS) Walls Adjacent to Structures................................................12
5.5 Approach Slabs ........................................................................................................14
6 PIERS .......................................................................................................................... 2
6.1 Design ....................................................................................................................... 2
6.2 Miscellaneous Details ................................................................................................ 5
7 PRESTRESSED CONCRETE...................................................................................... 2
7.1 General ...................................................................................................................... 2
7.2 Precast, Prestressed Girders ..................................................................................... 3
7.3 Post-Tensioned Concrete Decks................................................................................ 8
8 STRUCTURAL STEEL ................................................................................................. 3
8.1 Design ....................................................................................................................... 3
8.2 Structural Steel Girders Profile ..................................................................................13
8.3 Details.......................................................................................................................15
8.4 Stiffeners and Connection Plates ..............................................................................20
8.5 Frames, Bracing and Diaphragms.............................................................................28
8.6 Weld Details .............................................................................................................30
8.7 Structural Steel Notes ...............................................................................................33
8.8 Steel Truss and Arch Design ....................................................................................37
9 BRIDGE DECKS .......................................................................................................... 2
9.1 General ...................................................................................................................... 2
9.2 Deck Geometry .......................................................................................................... 2
9.3 Deck Slab Design ...................................................................................................... 5
9.4 Construction .............................................................................................................10

March 2024 Page 2 of 5 SM-D0-S08


STRUCTURAL MANUAL

TABLE OF CONTENTS

9.5 Durability...................................................................................................................12
10 BARRIERS AND RAILING SYSTEMS ......................................................................... 2
10.1 General .................................................................................................................... 2
10.2 Approved Traffic Barriers.......................................................................................... 3
10.3 Combination Traffic/Bicycle Rail ..............................................................................10
10.4 Separation Barriers for Bridges with Multi use Pathways (MUPs) ............................12
10.5 Barrier Walls Beyond the Bridge Structure ..............................................................14
10.6 Other Barrier Types .................................................................................................16
10.7 Miscellaneous Details of Barriers ............................................................................21
10.8 Barrier Design Aid ...................................................................................................23
11 RIGID FRAMES ........................................................................................................... 2
11.1 General .................................................................................................................... 2
12 REINFORCING ............................................................................................................ 2
12.1 General .................................................................................................................... 2
12.2 Premium Reinforcing – Where Required .................................................................. 4
12.3 Reinforcing Geometry..............................................................................................10
12.4 Reinforcement Details .............................................................................................12
12.5 Anchors in Concrete ................................................................................................15
13 EXPANSION JOINTS AND BEARING ASSEMBLIES .................................................. 2
13.1 General .................................................................................................................... 2
13.2 Expansion Joints ...................................................................................................... 2
13.3 Bridge Bearings .......................................................................................................13
14 CULVERTS .................................................................................................................. 2
14.1 General .................................................................................................................... 2
14.2 Concrete Culverts..................................................................................................... 2
14.3 Metal Culverts .......................................................................................................... 4
15 WOOD STRUCTURES ................................................................................................ 2
15.1 Material Properties of Softwood................................................................................ 2
15.2 Design ...................................................................................................................... 4
15.3 Fabrication ............................................................................................................... 9
15.4 Wood Notes ............................................................................................................12
15.5 Maintenance Schedule ............................................................................................15
15.6 Sources of Information ............................................................................................16
16 MISCELLANEOUS....................................................................................................... 2
16.1 Utilities ..................................................................................................................... 2

March 2024 Page 3 of 5 SM-D0-S08


STRUCTURAL MANUAL

TABLE OF CONTENTS

16.2 Transportation and Fabricator Handling of Structural Components........................... 5


16.3 Modular Bridges ....................................................................................................... 6
16.4 High Mast Lighting Poles .......................................................................................... 8
16.5 Pedestrian, Bicycle and MUP Bridges .....................................................................10
16.6 Ethylene Vinyl Acetate (EVA) Foam ........................................................................10
17 COMPUTER APPLICATIONS - NOT USED ................................................................ 1
18 SIGN SUPPORTS........................................................................................................ 2
18.1 General .................................................................................................................... 2
18.2 Overhead Sign Supports .......................................................................................... 2
18.3 Ground Mounted Sign Supports ............................................................................... 3
19 BRIDGE REHABILITATION ......................................................................................... 2
19.1 Rehabilitation of Bridge Structures ........................................................................... 2
DIVISION 3 - DESIGN AIDS ........................................................................................... 2
1 INDEX OF DESIGN AIDS ............................................................................................ 1
2 GENERAL DESIGN AND DRAFTING .......................................................................... 1
3 PILES........................................................................................................................... 1
4 FOOTINGS .................................................................................................................. 1
5 ABUTMENTS, WINGWALLS AND RETAINING WALLS .............................................. 1
6 PIERS .......................................................................................................................... 1
7 PRESTRESSED CONCRETE...................................................................................... 1
8 STRUCTURAL STEEL ................................................................................................. 1
9 DECK AND CURBS ..................................................................................................... 1
10 BARRIERS AND RAILING SYSTEMS ......................................................................... 1
11 RIGID FRAMES ........................................................................................................... 2
12 REINFORCING STEEL ................................................................................................ 2
13 BEARING ASSEMBLIES AND EXPANSION JOINTS .................................................. 2
14 CULVERTS .................................................................................................................. 2
15 WOOD STRUCTURES ................................................................................................ 2
16 MISCELLANEOUS....................................................................................................... 2
17 COMPUTER APPLICATIONS ...................................................................................... 2
18 SIGN SUPPORTS........................................................................................................ 2

March 2024 Page 4 of 5 SM-D0-S08


STRUCTURAL MANUAL

TABLE OF CONTENTS

This page is intentionally left blank.

March 2024 Page 5 of 5 SM-D0-S08


STRUCTURAL MANUAL

NOTATIONS

NOTATIONS

AADT Average Annual Daily Traffic


AASHTO American Association of State Highways and Transportation Officials
ACR Atmospheric Corrosion Resistant
AREMA American Railway Engineering & Maintenance of Way Association
ASTM American Society for Testing and Materials
AWPA American Wood Preservers Association
CDED Contract Design, Estimating and Documentation
CHBDC Canadian Highway Bridge Design Code, CSA S6
CNWA Canadian Navigable Waters Act
CPCI Canadian Prestressed Concrete Institute
CPS Contract Preparation System
CSA Canadian Standards Association International
CSP Corrugated Steel Pipe
DA Design Aids
DD Design Details
DOT Department of Transportation
DSM Designated Sources of Materials
ERT Effective Rubber Thickness
FHWA Federal Highway Administration
FIDR Foundation Investigation and Design Report
FLS Fatigue Limit State
GFRP Glass Fibre Reinforced Polymer
HPC High Performance Concrete
HSS Hollow Structural Section
HWL High Water Level
kN kilo Newton
m metre
MASH Manual for Assessing Safety Hardware
mm millimetre
MPa Mega Pascals
MSE Mechanically Stabilized Earth system (also known as RSS, see Section 5.7.1)
MTOD Ministry of Transportation of Ontario Drawing

March 2024 Page 1 of 2 SM-D0-S10


STRUCTURAL MANUAL

NOTATIONS

MUP Multi-Use Path


NCHRP National Cooperative Highway Research Program
NSSP Non-Standard Special Provision
NTS Not to Scale
OHBDC Ontario Highway Bridge Design Code
OPSD Ontario Provincial Standard Drawing
OPSS Ontario Provincial Standard Specifications
PI Point of Intersection
PTFE Polytetrafluoroethylene Polymer
RSS Retained Soil System (also known as MSE, see Section 5.7.1)
SC Spiral to Curve
SLS Serviceability Limit States
SPCSP Structural Plate Corrugated Steel Pipe
SS Structural Standard
SSD Structural Standard Drawing
SSP Standard Special Provision
TAC Transportation Association of Canada
TC Tangent to Curve
TL Test Level
TMB Temporary Modular Bridge
TTI Texas Transportation Institute
ULS Ultimate Limit States
WP Work Project/Working Point
WWR Welded Wire Reinforcement

March 2024 Page 2 of 2 SM-D0-S10


STRUCTURAL MANUAL

DIVISION 1 - EXCEPTIONS
TO THE CANADIAN
HIGHWAY BRIDGE
DESIGN CODE

SM-D1-S00
STRUCTURAL MANUAL

This page is intentionally left blank.

SM-D1-S00
STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

Table of Contents

1 EXCEPTIONS TO THE CHBDC, CSA S6-19 ....................................................... 2


1.1 Scope........................................................................................................................... 2
1.2 Authority ....................................................................................................................... 2
1.3 Implementation ............................................................................................................ 2
1.4 Exceptions ................................................................................................................... 2

March 2024 Page 1 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

1 EXCEPTIONS TO THE CHBDC, CSA S6-19

1.1 Scope

These exceptions implement provisions that CSA S6-19, Canadian Highway Bridge
Design Code (CHBDC) and Commentary delegates to the Regulatory Authority for
highway structures in Ontario. They also set forth design criteria that are exceptions to
those included in the CHBDC. These exceptions may be in the form of deletions from,
additions to, or modifications of the CHBDC. All owners must always use these two
documents jointly to prepare contract plans and specifications for structural elements
and/or systems on Ontario highways. Such elements and/or systems include, but are not
limited to, bridges, overhead sign structures, earth retaining structures, buried structures
and miscellaneous roadway appurtenances.

Exceptions for low volume roads are provided in APPENDIX A - GUIDELINES FOR THE
DESIGN OF BRIDGES ON LOW VOLUME ROADS. In the event of any inconsistency or
conflict in its contents and the exceptions given in Section 1.4 below, the appendix will
take precedence and govern.

1.2 Authority

Ontario Regulation 104/97, and its amendments, made under the Public Transportation
and Highway Improvement Act (PTHIA).

1.3 Implementation

Immediately for all designs according to CHBDC.

1.4 Exceptions

In the following changes, the relevant CHBDC clause numbers are given next to each
provision and the latest version of any standard referred to shall apply.

CHBDC SECTION 1 GENERAL

1.3 Definitions

1.3.2 General Administrative Definitions

The definition for Regulatory Authority is amended by the addition of the following at the
end of the definition:
The nominee for the Minister of Transportation shall be the Chief Engineer of the Ministry
of Transportation of Ontario.

1.3.3 General Technical Definitions

The definition for Deck Width is deleted and replaced with the following:

March 2024 Page 2 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

Deck width — the horizontal distance, measured at deck level perpendicular to the
direction of travel, from face to face of sidewalks or curbs (or barrier walls if there are no
curbs), but not taken as less than the Bridge Width minus 1 m unless approved by the
Owner.

1.4 General Requirements

1.4.2 Design

1.4.2.5 Single-Load-Path Structures

This clause is amended by the addition of the following:


For bridges, a single load path structure shall not be used unless approved by the Owner.

1.4.4 Construction

1.4.4.5 Plans

The third paragraph is deleted and replaced with the following:


In order to validate and certify the design shown on the plans, the engineer and checker
shall each affix his or her Professional Engineers Ontario seal to each and every drawing,
and each shall sign and date the appropriate seal.

The following shall be added to the provisions of this clause:


Specifications for construction and rehabilitation shall be in accordance with the Ontario
Provincial Standards for Roads and Public Works, or another standard approved by the
Owner. In the event of any inconsistency or conflict in the contents of these standards
and the CHBDC, the Ontario Provincial Standards for Roads and Public Works, or other
standard approved by the Owner, will take precedence and govern.

1.5 Geometry

In this subsection all references to "…the Regulatory Authority, or in their absence, with
the TAC Geometric Design Guide for Canadian Roads." are deleted and replaced by
"…Transportation Association Canada (TAC) Geometric Design Guide for Canadian
Roads in conjunction with the MTO Design Supplement or other standard approved by the
Owner."

1.6 Barriers

In this subsection all references to "…the Regulatory Authority, or in their absence, with
the TAC Geometric Design Guide for Canadian Roads." are deleted and replaced by
"…the MTO Roadside Design Manual or other standard approved by the Owner."

March 2024 Page 3 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

1.9 Hydraulic Design

1.9.10.1 Stream stabilization works

The last paragraph is deleted and replaced with the following:

Stabilization works shall be designed to suit the requirements of the site and comply with
the requirements of the regulatory authority or with the Transportation Association of
Canada’s Guide to Bridge Hydraulics.

1.9.1 Design Criteria

1.9.1.2 Normal Design Flood

The first paragraph is deleted and replaced with the following:


The normal design flood in Ontario shall have a return period in accordance with the MTO
Highway Drainage Design Standard WC-1, Design Flows (Bridges and Culverts).

1.9.1.3 Check Flood

The first paragraph is deleted and replaced with the following:


The check flood in Ontario shall have a return period in accordance with the MTO Highway
Drainage Design Standard WC-1, Design Flows (Bridges and Culverts).

CHBDC SECTION 3 LOADS

3.8 Live Loads

3.8.3 Traffic Loads

3.8.3.1 Normal Traffic

3.8.3.1.1 CL-W loading

The last three paragraphs are deleted and replaced with the following:
A loading exceeding CL-625 may be specified by the Owner.

3.8.4 Application

3.8.4.3 Local Components

Item (b) is deleted and replaced by the following:


For modular expansion joints, the axle load considered shall be axle no. 4 of the CL-625-
ONT truck for ultimate and serviceability limit states, and axles 2 and 3 of the CL-625-ONT
truck for the fatigue limit state.

March 2024 Page 4 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

For structural components other than joint armouring, the horizontal load shall be 20% of
the vertical load applied at the roadway surface and considered individually or in
combination with vertical loads, whichever produces a greater load effect.

For the FLS, the truck shall be positioned anywhere along the length of the expansion joint
but need not be placed closer than 600 mm to a barrier wall.

The maximum (positive) stress at a given location in the joint shall be calculated from the
truck positioned at any location along the length of the expansion joint. The minimum
(negative) stress at that same location shall be calculated from the truck positioned at any
other location along the length of the expansion joint. The calculated fatigue stress range
at each location along the joint shall be the algebraic difference between the maximum
and minimum stress above.

The required length of the support bar shall be determined based on an installation
temperature of 15°C. Force effects shall be calculated based on factored movements in
relation to the joint’s articulation relative to its positions at 15°C.

CHBDC SECTION 4 SEISMIC DESIGN

4.4.3 Seismic Hazards

4.4.3.1 General

The first paragraph is amended with the addition of the following statement at the end.

The 2020 National Building Code of Canada Seismic Hazard Tool shall be used.

4.4.4 Seismic Performance Category

Table 4.10 shall be deleted and replaced with the following:

Table 4.10
Seismic performance category based on 5% damped 2% in 50-year
exceedance spectral values
(See Clauses 4.2, 4.4.4, 4.10.3, and 6.14.2.3)

All Bridges
Spectral accelerations
(Lifeline, Major route and other bridges).
S (1.0) < 0.10 1
0.10 ≤ S (1.0) < 0.30 2
S (1.0) ≥ 0.30 3
Note: For lifeline bridges in seismic performance category 1, detailing of structural
elements shall adopt requirements for seismic performance category 2 as a minimum.

March 2024 Page 5 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

4.11 Seismic evaluation of existing bridges

4.11.1 General

The contents of this clause are deleted and replaced by the following:

The evaluation shall assess the bridge for seismic performance objectives, as defined by
the owner, using one or more of the seismic hazard levels considered in Table 4.15, or as
defined by the owner in accordance with Clause 4.11.3. The evaluation and performance
criteria, including the selection of performance objectives and seismic hazard levels, may
adopt a risk-based approach that considers the remaining functional/intended life of the
bridge, the economic and societal consequences of damage to or failure of the bridge, its
age and condition, deficient details or arrangements, and any condition, strength or
functional upgrades that are envisaged.

4.11.3 Seismic hazard and evaluation

The contents of this clause are deleted and replaced by the following:

The evaluation shall assess the bridge for acceptable performance objectives targeted for
one or more seismic hazard levels considered in Table 4.15. For bridges in SPC 2 and 3,
the evaluation and seismic rehabilitation shall seek to prevent collapse of all or part of the
bridge at a hazard level not less than a 5% in 50-year probability of exceedance, unless a
higher probability of exceedance is specified by the owner.

CHBDC SECTION 5 METHODS OF ANALYSIS

5.5 Requirements for Specific Bridge Types

5.5.3 Voided slab

The contents of Clause (b) are deleted and replaced with the following:
b) for rectangular voids, the thickness of the web defined by adjacent voids shall be not
less than 20% of the total depth of the section. The depth of the void shall not exceed
80% of the total depth of the section and the transverse width of the void shall not
exceed 1.5 times its depth, although a ratio of up to 2.5 times the depth is permitted
with approval of the Owner.

CHBDC SECTION 6 FOUNDATIONS AND GEOTECHNICAL SYSTEMS

6.9 Geotechnical Resistance

Table 6.2 is amended with the addition of the following note:


The value of geotechnical resistance factor for Deep foundations and embankment fills
may be increased by up to 0.05, with approval of the Owner. The value of geotechnical
resistance factor for settlement of embankment fills may be increased to 1.0 with approval
of the Owner.

March 2024 Page 6 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

6.11 Deep Foundations

6.11.4 System Design and Construction Considerations

6.11.4.5 Degradation of Pile Foundations

This clause is amended by the addition of the following:


Exposed steel H and steel tube piles shall have an Approved protective coating applied
from an elevation 600 mm below the low water level or 1000 mm below finished ground
surface up to at least 1000mm above high-water level.

6.11.4.9 Splices

The last sentence is deleted and replaced with the following:


Wood piles shall not be spliced.

CHBDC SECTION 7 BURIED STRUCTURES

7.1 Scope

This subsection is amended by the addition of the following:


The provisions of this Section are mandatory only for structures that are greater than 3 m
in span.

Specifications for construction, rehabilitation, and design provisions, where applicable,


shall be in accordance with the Ontario Provincial Standards for Roads and Public Works,
or another standard approved by the Owner.

7.8 Reinforced Concrete Pipe, Boxes, and Three-Sided Buried Structures

7.8.9 Strength Design

7.8.9.2 Design for Shear

7.8.9.2.2 Box Structures without Stirrups or Ties

The contents of this clause are deleted and replaced with the following:
The shear strength shall be determined in accordance with Section 8, unless approved by
the Owner.

CHBDC SECTION 8 CONCRETE STRUCTURES

8.4 Materials

8.4.2 Reinforcing Bars and Deformed Wire

March 2024 Page 7 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

8.4.2.1 Reinforcing Bars

8.4.2.1.1 Specification

This clause is amended by the addition of the following:


Other grades of reinforcing bar not covered by CSA G30.18 are only permitted when
approved for use by the Ministry of Transportation Ontario (MTO).

8.5 Limit States

8.5.3 Fatigue Limit State

8.5.3.1 Reinforcing Bars

The clause is modified with the addition of the following paragraph, immediately following
the bulleted list.

Unless approved by the Owner, tack welding of reinforcing bars shall not be permitted. If
approved, tack welding shall follow the requirements of CSA W186.

8.8 Flexure and Axial Loads

8.8.4 Flexural Components

8.8.4.6 Prestressed Concrete Stress Limitations

The contents of Clause (a)(ii) are deleted and replaced with the following:
ii) For all prestressed concrete elements, the limiting concrete tensile stress at transfer
shall be 0.6fcri.

The contents of Clause (b)(iii) are deleted and replaced with the following:
iii) The maximum concrete tensile stresses in service shall not exceed 0.75fcr. Tension
shall not be permitted across the joints of segmental components unless bonded
reinforcing bars pass through the joints in the tensile zone.

8.11 Durability

8.11.2 Protective Measures

8.11.2.2 Concrete Quality

The contents of this clause are deleted and replaced with the following:
The durability properties for structural concrete shall be as specified in the Ontario
Provincial Standards for Roads and Public Works or other standard, approved by the
Owner, for the appropriate combination of deterioration mechanisms and environmental
conditions.

March 2024 Page 8 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

8.11.2.4 Concrete Cover

The title of this clause is deleted and replaced with the following:

8.11.2.4 Concrete Cover and Tolerances

The second paragraph is deleted and replaced with the following:


Tolerances for concrete cover shall be shown along with concrete covers on the plans or
in the specifications. Unless approved by the Owner, the tolerances shall be as follows:
a) Reinforcement in Cast in Place Concrete: ±10 mm against formed surfaces, ±20 mm
on finished surfaces and ±25 mm against earth.
b) Reinforcement in Precast Concrete: ±10 mm and +10/5 for precast, prestressed
girders.
c) Prestressing steel in Precast Concrete: ±5 mm.
d) Post-Tensioning Duct in Cast in Place Concrete: ±10 mm against formed surfaces,
and ±15 mm on finished surfaces.
e) Posttensioning Duct in Precast Concrete: ±10 mm.

Where approved by the Owner, the cover and tolerance for Stainless Steel bars shall be
the values for reinforcing steel found in CHBDC Table 8.5, reduced by 10 mm, however,
the minimum clear cover after consideration of tolerance shall not be less than 30 mm.

8.12 Control of Cracking

8.12.3 Crack Control Reinforcement in Zones of Computed Tensile Stress

8.12.3.2 Concrete Surface Categories

The contents of this clause are deleted and replaced with the following:
Concrete surfaces shall be classified as Category A, AA, or Category B in accordance
with the following criteria:
a) Category A surfaces are surfaces for which a high standard of appearance is required
and/or surfaces that will be exposed to one or more of the following agents: de-icing
chemicals, spray or surface runoff containing de-icing chemicals, marine spray,
swamp or marsh water, salt water, or aggressive backfill.
b) Category AA surfaces are Category A deck surfaces of slab on girder bridges built with
un-shored construction that are predominantly subject to live loads.
c) Category B surfaces are all surfaces that are not classified as Category A or AA.

Waterproofing membranes shall be disregarded in the classification of concrete surfaces.

March 2024 Page 9 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

8.12.3.4 Tensile Stress Limits for Reinforcing Steel

The contents of this clause are deleted and replaced with the following:
Tensile stress, fs, in reinforcing steel produced by the governing cases defined in Clause
8.12.3.3 shall not exceed either the following limits:

𝑊𝑊𝑐𝑐𝑐𝑐𝑐𝑐 𝑓𝑓𝑐𝑐𝑐𝑐 𝐸𝐸𝑠𝑠 𝐴𝐴𝑏𝑏 𝐸𝐸𝑠𝑠


𝑓𝑓𝑠𝑠 ≤ � �1 + � , 𝑎𝑎𝑎𝑎𝑎𝑎 𝑓𝑓𝑠𝑠 ≤ 0.75𝑓𝑓𝑦𝑦
𝛼𝛼𝑏𝑏 𝑑𝑑𝑏𝑏 2𝑐𝑐𝑏𝑏 𝑠𝑠𝐸𝐸𝑐𝑐

Where:
𝑊𝑊𝑐𝑐𝑐𝑐𝑐𝑐 is the category factor, taken as for 2.8 for Category A exposure, 1.6 for Category
AA exposure, 3.9 for Category B exposure.
𝛼𝛼𝑏𝑏 is the bar coating factor, taken to be equal to 1.0 for uncoated bars and 1.2 for
epoxy-coated bars.
𝑑𝑑𝑏𝑏 is the bar diameter, taken as the diameter of bar corresponding to the average
area of steel on the tensile face, in mm.
𝐴𝐴𝑏𝑏 is the average area of steel bar in the layer nearest the tensile face, in mm2.
𝑐𝑐𝑏𝑏 is the clear cover from the bar controlling the crack to the tensile face, but not
greater than 70 for more than 2 layers of reinforcement, in mm.
𝑠𝑠 is the average spacing of reinforcement nearest the tensile face, in mm.
𝐴𝐴𝑠𝑠 𝐸𝐸𝑠𝑠
and the steel/concrete ratio term �1 + � may be taken as unity in lieu of calculation.
2𝑐𝑐𝑏𝑏 𝑠𝑠𝐸𝐸𝑐𝑐

CHBDC SECTION 10 - STEEL STRUCTURES

A10.1 Construction Requirements for Structural Steel

A10.1.1 General

Clause A10.1.1.2 is deleted.

CHBDC SECTION 11 JOINTS AND BEARINGS

11.6 Bridge bearings

11.6.3 Sliding surfaces

11.6.3.3 Mating surface

This clause is amended as follows:

The words “stainless steel or anodized aluminum alloy” shall be replaced by “stainless

March 2024 Page 10 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

steel, anodized aluminum or other material approved by the owner”.

CHBDC SECTION 12 – BARRIERS AND HIGHWAY ACCESSORY SUPPORTS

12.4.3.4 Crash test requirements

12.4.3.4.1 General

This clause is amended with the addition of the following:

The above requirements may be waived where otherwise specified by the MTO standards.

CHBDC SECTION 14 EVALUATION

14.7 Material Strengths

14.7.4 Strengths Based on Date of Construction

14.7.4.4 Reinforcing Steel

The contents of Table 14.2 in this clause are deleted and replaced with the following:
Table 14.2
Minimum yield strengths of reinforcing steel, MPa
(See Clause 14.7.4.4)
Date of Bridge Structural Medium or Hard Unknown
Construction Grade Intermediate Grade Grade Grade
Before 1914 - - - 210
1914 1955 230 275 345 230
1956 - 1972 275 275 345 275
1973 - 1978 300 345 415 300
After 1978
300 350 400 300
- stirrups and ties
After 1978
300 350 400 350
- remainder

14.12 Target Reliability Index

14.12.1 General

This clause is amended by the addition of the following:

If the bridge is to be re-evaluated within 5 years for Normal Traffic, the Reliability Index, β,
specified in Table 14.5, shall be reduced by 0.25. This value shall not be less than 2.5.

March 2024 Page 11 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

14.14 Resistance

14.14.2 Resistance Adjustment Factor

The contents of this clause are deleted and replaced with the following:

For all components, which have no visible sign of defect or deterioration, the factored
resistance, as calculated in accordance with Clause 14.14.1, shall be multiplied by a
resistance adjustment factor, U. The value of U shall be as specified in Table 14.10 but
shall not be taken as less than U = 1.0. Where no value for U is specified in Table 14.10,
and in lieu of better information, a value of U = 1.0 may be used.

14.17 Bridge Posting

14.17.2 Calculation of Posting Loads

14.17.2.2 Based on Axle Weight

This clause is deleted.

14.17.3.4 Posting Sign for Axle Weight

This clause is deleted.


CHBDC SECTION 16 FIBRE-REINFORCED STRUCTURES

16.3 Abbreviations and Symbols

16.3.2 Symbols

The following definition of 𝜓𝜓𝑠𝑠 is added to the clause:

𝜓𝜓𝑠𝑠 = curvature at a section when the moment is MS , mm-1 (see Clause 16.8.2.1).

16.4 Durability

16.4.5 Cover to Reinforcement

The first sentence of this clause is deleted and replaced with the following:

The cover and tolerance for FRP bars and grids shall be the same as the values for
reinforcing steel found in Table 8.5, reduced by 10 mm, however, the minimum clear cover
after consideration of tolerance shall not be less than 30 mm.

16.5 Fibre-Reinforced Polymers

March 2024 Page 12 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

16.5.7 Minimum Bend Radius to Bar Diameter Ratio of Bent FRP Bars

The clause is deleted and replaced with the following:

The bend radius of an FRP bar, 𝑟𝑟, shall not be less than 4𝑑𝑑𝑏𝑏 unless approved by the
Owner.

16.8 Concrete Beams, Slabs, and Columns

16.8.2.1 Design for deformability

The equation in this clause is replaced with the following:

𝑀𝑀𝑢𝑢𝑢𝑢𝑢𝑢 𝛹𝛹𝑢𝑢𝑢𝑢𝑢𝑢
𝐽𝐽 =
𝑀𝑀𝑠𝑠 𝛹𝛹𝑠𝑠

16.8.4 Development Length for FRP Bars and Tendons

16.8.4.1 General

The clause is amended with the addition of the following at the end of the clause:

c) When the transverse reinforcement is steel, in the expression for shall be taken as 1.0.

16.8.4.3 Development length of FRP bent bar

The contents of this clause are deleted and replaced with the following:

The development length, 𝜆𝜆𝑑𝑑 , for FRP bent bars in tension shall be calculated using the
equation given in Clause 16.8.4.1.

However, the development length, 𝜆𝜆𝑑𝑑 , may be reduced by accounting for the tensile stress
taken by the bent portion of the bar, 𝜎𝜎𝜈𝜈 , for bars that are bent 90 degrees or more from
𝜎𝜎𝜈𝜈
straight. The development length may be reduced by an amount equal to, 𝑙𝑙𝑑𝑑 � �,
𝑓𝑓𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹
but 𝜆𝜆𝑑𝑑 shall not be less than 12𝑑𝑑𝑏𝑏 or 230 mm.

Where:

�0.05𝑟𝑟�𝑑𝑑 + 0.3�𝑓𝑓𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹
𝜎𝜎𝜈𝜈 =
1.5

The tail length of a bent bar, 𝜆𝜆𝑡𝑡 , should not be less than 12𝑑𝑑𝑏𝑏 .

16.8.7 Design for Shear and Torsion

March 2024 Page 13 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

16.8.7.3 Interface Shear Transfer

The contents of this clause and its subclauses are deleted and replaced with the following:

16.8.7.3.1 General

The interface shear resistance shall be designed so as to be provided by only one type of
shear-friction reinforcement material, either FRP or steel; the effects of FRP and steel
shear-friction reinforcement providing resistance simultaneously shall not be combined.
Where the shear-friction reinforcement is composed entirely of steel, the interface shall be
designed as per Clause 8.9.5.

Otherwise, a crack shall be assumed to occur along the shear plane and the relative
displacement shall be considered to be resisted by cohesion and friction maintained by
the shear-friction reinforcement crossing the crack. In lieu of more detailed calculations,
the factored shear resistance of the plane, 𝜈𝜈𝑟𝑟 , shall be calculated as follows:

𝜈𝜈𝑟𝑟 = 𝜙𝜙𝑐𝑐 (𝑐𝑐 + 𝜎𝜎)

Where 𝜈𝜈𝑟𝑟 shall not exceed the lesser of:

a) 0.25𝜙𝜙𝑐𝑐 𝑓𝑓′𝑐𝑐 , or

b) 6.5 Mpa.

16.8.7.3.2 Values of c, μ, and λ1

The title of this clause is deleted and replaced with the following:

16.8.7.3.2 Values of Compressive Normal Stress

The value of the compressive stress across the shear-friction plane shall be calculated as
follows:

𝜇𝜇𝜇𝜇
𝜎𝜎 = 𝛼𝛼𝑣𝑣 𝜌𝜌𝑣𝑣 𝑓𝑓𝑑𝑑 +
𝐴𝐴𝑐𝑐𝑐𝑐

Where 𝛼𝛼𝑣𝑣 is the dowel term reduction factor, 𝜌𝜌𝑣𝑣 is the shear reinforcement ratio, 𝑓𝑓𝑑𝑑 is the
dowel shear resistance contribution (MPa), 𝜇𝜇 is the coefficient of friction, 𝑁𝑁 is the
unfactored permanent load perpendicular to the shear plane (positive for compression and
negative for tension) (N), and 𝐴𝐴𝑐𝑐𝑐𝑐 is the area of concrete resisting shear transfer (mm2).

𝐴𝐴𝑣𝑣𝑣𝑣
𝜌𝜌𝑣𝑣 =
𝐴𝐴𝑐𝑐𝑐𝑐

Where 𝐴𝐴𝑣𝑣𝑣𝑣 is the area of shear-friction dowel reinforcement (mm2). A minimum amount

March 2024 Page 14 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

of reinforcement must be provided such that 𝜌𝜌𝑣𝑣 ≥ 0.44%.

16.8.7.3.3 Values of σ

The title of this clause is deleted and replaced with the following:

16.8.7.3.3 Values of 𝒄𝒄, 𝜶𝜶𝒗𝒗 , 𝒇𝒇𝒅𝒅 , and 𝝁𝝁

The following values shall be taken for 𝑐𝑐 , 𝛼𝛼𝑣𝑣 , 𝑓𝑓𝑑𝑑 , and 𝜇𝜇 in Clauses 16.8.7.3.1 and
16.8.7.3.2:

a) For concrete placed against hardened concrete, with the surface clean and free of
laitance but not intentionally roughened:
𝑐𝑐 = 0.25 MPa
𝜇𝜇 = 0.60𝜆𝜆1
𝛼𝛼𝑣𝑣 = 0.80
𝑓𝑓𝑑𝑑 = Transverse shear strength as per CSA S807-19, which may be taken as
180 MPa for straight or bent Grade III GFRP bars.

b) For concrete placed against hardened concrete, with the surface clean and free of
laitance and intentionally roughened to a full amplitude of about 5 mm and spacing of
about 15 mm:
𝑐𝑐 = 0.50 MPa
𝜇𝜇 = 1.00𝜆𝜆1
𝛼𝛼𝑣𝑣 = 𝜇𝜇
𝑓𝑓𝑑𝑑 = 0.0025𝐸𝐸𝐹𝐹𝐹𝐹𝐹𝐹

Where 𝐸𝐸𝐹𝐹𝐹𝐹𝐹𝐹 is the longitudinal modulus of elasticity as per CSA S807-19 and may be
taken as 60 GPa for straight Grade III GFRP bars and 50 GPa for bent Grade III GFRP
bars.

c) For concrete placed monolithically:


𝑐𝑐 = 1.00 MPa
𝜇𝜇 = 1.40𝜆𝜆1
𝛼𝛼𝑣𝑣 = 𝜇𝜇

and where 𝑓𝑓𝑑𝑑 is as per (b) above.

Where the values of 𝜆𝜆1 shall be as follows:


a) Normal density concrete: 1.00
b) Semi-low density concrete: 0.85
c) Low-density concrete: 0.75

March 2024 Page 15 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 1 - EXCEPTIONS TO THE CANADIAN HIGHWAY BRIDGE


DESIGN CODE (CHBDC), CSA S6-19

16.8.7.3.4 Anchorage of Shear-Friction Reinforcement

The title of this clause is deleted and replaced with the following:

16.8.7.3.4 Orientation and Anchorage of Shear-Friction Reinforcement

FRP reinforcement for shear-friction shall be oriented perpendicular to the shear plane.

FRP reinforcement for shear-friction shall be capable of developing a strength of 2𝑓𝑓𝑑𝑑 on


both sides of the shear-friction plane.

16.8.9 Compression Components

16.8.9.2 Maximum factored axial resistance

Clause 16.8.9.2 is deleted and replaced with the following:


The maximum factored axial load resistance, 𝑃𝑃𝑟𝑟 , of compression members shall be
calculated in accordance with Clauses 8.8.5.6 and 16.8.9.1, where 𝐴𝐴𝑠𝑠 shall be taken as
zero where longitudinal reinforcement is not steel.

16.8.9.4 Transverse Reinforcement

16.8.9.4.3 FRP ties

The requirements for items (b) and (d) of the list in this clause are deleted and replaced
with the following:
b) 24 times the minimum cross-sectional dimension (or diameter) of the GFRP tie or grid;
d) 300 mm in compression members.

16.8.11 Strut-and-Tie Model for Deep Beams, Corbels, and Short Walls

16.8.11.1 General

The contents of this clause are deleted and replaced with the following:

Strut-and-tie models shall be used only where approved by the Owner.

When approved, strut-and-tie models may be used to determine internal force effects near
supports and the points of application of concentrated loads, or for the design of deep
footings and pile caps or other situations in which the distance between the centres of
applied load and the supporting reaction is less than twice the component thickness.

March 2024 Page 16 of 16 SM-D1-S01


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

Table of Contents

2 APPENDIX A - GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW


VOLUME ROADS................................................................................................. 2
2.1 Scope........................................................................................................................... 2
2.2 Introduction .................................................................................................................. 2
2.3 Definitions .................................................................................................................... 2
2.4 Provisions, Guidelines, and Commentaries .................................................................. 3
2.5 References..................................................................................................................12

March 2024 Page 1 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

2 APPENDIX A - GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW


VOLUME ROADS

2.1 Scope

These design guidelines apply for bridges on roads with an average annual daily traffic
(AADT), in both directions, of 400 or less. These guidelines may also be used, with
Approval, for existing roadways where operational issues such as collisions, traffic delays,
etc. are minimal.

2.2 Introduction

Present design codes, standards and policies have typically been developed for bridges
with high traffic volumes. It has become apparent, however, that for bridges with low traffic
volumes these requirements have become too stringent. In order to achieve economies
by the relaxing of requirements, and without compromising safety, a task force with MTO
Regional and Provincial Office participation was set up to develop guidelines for this
purpose. As a result, this section has been formulated. Where applicable, the CHBDC
clause number that is being modified is provided, along with the reference to justify the
provision. A commentary is also provided.

Application of these recommendations to bridges on low volume roads will provide an


opportunity for savings on structures in these situations. Examples of changes in design
criteria that will be effective in achieving this aim are:

• Reduction in minimum soffit clearance over waterways it was considered that the
temporary consequences of possible flooding, including disruption to traffic, were
tolerable.

• Reduction in minimum lane and shoulder width with the lower traffic volumes it is
believed that the probability of vehicles encountering or stopping on bridges was not
a high risk.

2.3 Definitions

Recreational Road means a road used for the access of parks, scenic and historic sites,
or seasonal cottages.

Resource Access Road means a road used for mining, forestry, and energy
development.

Local Road means a road primarily used for land access.

Collector Road means a road providing for land access and traffic circulation.

Arterial Road means a road primarily used for high volumes of through traffic.

March 2024 Page 2 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

AADT means Average annual daily traffic.

TL-0 (formerly LVPL1) means a railing able to successfully redirect a ¾ ton pick-up truck
with a speed of 25 km/h and an impact angle of 15°. The level of performance is less than
that for TL-1 and is intended for very low volume and low speed traffic.

TL-1 means a Test Level 1 (TL-1) as described in CHBDC and satisfies NCHRP
Report 350, successfully redirecting a ¾ ton pick-up truck with a speed of 50 km/h and an
impact angle of 25˚. The level of performance is intended for low volume traffic at
moderate speeds.

CHBDC means CSA-S6-19, Canadian Highway Bridge Design Code.

2.4 Provisions, Guidelines, and Commentaries

The CHBDC should be used for all bridges with the following exemptions allowed for
bridges on low volume roads. The relevant CHBDC clause numbers are given next to
each provision.

CHBDC SECTION 1 - GENERAL

1.4 General Requirements

1.4.2 Design

1.4.2.3 Design Life

a) The design life of the bridge shall be 75 years unless reduced at the request of the
Owner (Cl. 1.4.2.3).

Commentary: Certain cases may require a lower life. Consideration should be given to a lower
life cycle where alignments are substandard, but improvements are cost prohibitive. In those
situations, the owner may not be able to correct the alignments but may also not wish to be
committed to the substandard alignment for 75 years.

1.4.2.5 Single-Load-Path Structures

a) Some single load path structures such as trusses and 2 girder bridges are
acceptable. Alternate load paths may be desirable due to the lack of maintenance that
is common on low volume roads (Cl. 1.4.2.5).

Commentary: This overrides the CHBDC Exceptions and allows their use.

March 2024 Page 3 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

1.5 Geometry

1.5.1 Planning

a) The 10-year growth need not be considered for AADT unless a significant change
in the road use is foreseen (Cl. 1.5.1).

Commentary: For these roads, the growth would generally be small.

b) The horizontal and vertical alignment should be determined using roadway design
criteria and not the bridge code. Where existing roadway alignments have proven to
perform well, then the existing alignment can be used (Cl. 1.5.1).

Commentary: This allows structure replacement at same location if old structure was adequate.

1.5.2 Structure Geometry

a) The use of single lane bridges is acceptable for bridges on some low volume roads.
(Cl. 1.5.2) The minimum bridge, lane, and shoulder widths shall be as given in Table
2.4-1 (Ref. 2,3). Adequate warning should be given to traffic in the case of narrow or
single-lane bridges.

Commentary: Reduced widths result in lower costs. With AADT less than 200, the probability of
2 vehicles meeting on the bridge is low.

March 2024 Page 4 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

TABLE 2.4-1 - MINIMUM LANE, SHOULDER, AND BRIDGE WIDTHS

AADT Design Speed # Lanes Min. Lane Min. Shoulder Min. Bridge
(km/h) Width (m) Width (m) Width (m)1
4.02,3,4
1 3.0 0.5
≤ 60 (4.9 m max)5
≤ 200
26 2.75 0.25 6.0
≥ 70 2 3.0 0.5 7.0
4.02,3,4
1 3.0 0.5
≤ 40 (4.9 m max)5

> 200 and ≤ 4007 26 2.75 0.25 6.0


50 to 60 2 3.0 0.5 7.0
≥ 70 2 3.38 0.68 7.58
Table 2.4-1 Notes:
1 - Width measured between the inside face of the barriers, guiderails, or curbs.
2 - Horizontal and vertical sight distances, or adequate turn-outs, shall be provided to allow
approaching motorists to observe an opposing vehicle on a single lane bridge or its far
approach. If there are sight distance issues, a single lane bridge should not be used.
3 - Farm or other special vehicles may require larger widths. Consultation shall be made with
local officials. It may also be acceptable to have a lower barrier to accommodate these farm
or other special vehicles.
4 - For AADT > 400, or for locations where the Seasonal Average Daily Traffic is significantly
> 400, consideration should be given to using additional traffic control measures at the bridge
for single lane structures (i.e., traffic signals, yield sign for one direction, stop sign, etc.).
5 - New single lane bridges wider than 4.9 m should be avoided as they may give the appearance
of a full two-lane bridge.
6 - Two lane bridge is also an acceptable alternative if a 4.9 m single lane bridge cannot
accommodate the traffic (i.e., farm or special vehicles, sight distances, etc.).
7 - Range also applies to existing roadways with AADT > 400, where operational issues have
been minimal and Approval for use of these guidelines has been obtained from the Owner.
8 - For AADT > 400, or for locations where the Seasonal Average Daily Traffic is significantly
> 400, lane width of 3.25 m, shoulder width of 1.0 m and minimum bridge width of 8.5 m shall
apply.

1.7 Auxiliary Components

1.7.2 Approach Slabs

a) The approach slabs may be omitted. Approach slabs may be beneficial for high
abutments to reduce the effects of live load surcharge (Cl. 1.7.2).

Commentary: These roads are generally lower service roads and settlement would not be a great
inconvenience compared to other hazards on the road.

March 2024 Page 5 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

1.8 Durability and Maintenance

1.8.2 Bridge Deck Drainage

1.8.2.3 Drainage Systems

1.8.2.3.1 General

a) Deck drains are only required as given by Clause 1.8.2.3.1. Shorter bridges and
bridges with catch basins at the ends of the structure often do not require deck drains.

Commentary: Traditionally, bridges generally had more drains than required.

1.9 Hydraulic Design

a) Hydrologic and Hydraulic design standards shall be as specified in the Highway


Drainage Design Standards, January 2008.

1.9.9 Channel Erosion Control

1.9.9.1 Slope Protection

a) Slope protection, where required, needs only to be extended 150 mm above HWL
(Cl. 1.9.9.1).

b) Scour and erosion protection is required only for susceptible structures. The stone
sizes for scour and erosion protection may be taken from Table 2.4-2 instead of RTAC
recommendations (Cl. 1.9.9.1) (Ref. 5).

Commentary: Slightly smaller stones are acceptable.

TABLE 2.4-2 – REQUIRED STONE SIZE FOR SCOUR AND EROSION PROTECTION

Velocity (m/s) < 2.0 < 2.6 < 3.0 < 3.5 < 4.0 < 4.7 < 5.2
Nominal Stone Size* (mm) 100 200 300 400 500 800 1000
* Maximum stone size to be 1½ times the nominal stone size. 80% of stones (by mass) must have
diameter of at least 60% of nominal stone size.

1.9.11 Culverts

1.9.11.6 Closed-Invert Culverts

1.9.11.6.5 Concrete Box Structures

a) For closed culverts in scour resistant soils, a concrete cut-off wall is not required
(Cl. 1.9.11.6.5).

March 2024 Page 6 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

CHBDC SECTION 3 - LOADS

3.4 Limit States Criteria

3.4.4 Serviceability Limit States

a) The deflection limit may be reduced to L/360 and need not be checked for
temporary modular bridges (Cl. 3.4.4).
Commentary: A reduced passenger comfort is allowed.

3.5 Load Factors and Load Combinations

a) The full DLA and load factors should be used (Cl. 3.5 & 3.8.4.5.3).

3.8 Live Loads

3.8.3 Traffic Loads

3.8.3.1 Normal Traffic

3.8.3.1.1 CL-W Loading

a) The bridge can be designed to a load lower than the CHBDC CL-625 truck
(Cl. 3.8.3.1.1) provided that the bridge will be properly posted. The live load surcharge
can be proportionately decreased with the decrease in truck load (Cl. 6.12.5).
Emergency and maintenance vehicle weights should be considered when determining
the appropriate design loading.

Commentary: If properly posted and for specific uses, a lower load limit bridge may be adequate.

3.8.3.1.3 CL-W Lane Load

a) Lane load need not be considered (Cl. 3.8.3.1.3).

Commentary: Only 1 truck will be present in the lane.

3.8.4 Application

3.8.4.5 Dynamic Load Allowance

3.8.4.5.3 Components Other than Buried Structures

a) See 3.5 above.

CHBDC SECTION 6 - FOUNDATIONS

6.12 Ground Pressures

March 2024 Page 7 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

6.12.5 Surcharge
a) Bridges designed to a lower live load than the CHBDC CL-625 truck may have the
800 mm live load surcharge reduced proportionately (Cl. 6.12.5).
Commentary: 800 mm surcharge load is calibrated for the full design truck.

b) See 3.8.3.1.1 above.

CHBDC SECTION 8 - CONCRETE STRUCTURES

8.18 Special Provisions for Deck Slabs

8.18.2 General

8.18.2.4 Allowance for Wear

a) The 10 mm allowance for wear on exposed concrete decks may be omitted


(Cl. 8.18.2.4).

CHBDC SECTION 9 - WOOD STRUCTURES

9.11 Sawn Wood

a) Hardwoods may be used, and strengths and other properties shall be taken from
CSA O86-14 (Cl. 9.11) (Ref. 10).

9.17 Durability

9.17.12 Stress-Laminated Timber Decking

a) Water borne preservatives may be used for stress laminated timber decks with a
minimum dimension of less than 50 mm (Cl. 9.17.12).

Commentary: Stressing closes the gap between laminates, minimizing ingress of water.

9.21 Nail-Laminated Wood Decks

9.21.2 Transversely Laminated Wood Decks

9.21.2.2 Assembly
9.21.2.2.1 Nailing

a) Transverse nail laminated decks shall have a nail length that pass through two
laminates and 10 mm into the third laminate (Cl. 9.21.2.2.1).

Commentary: This slightly shorter length permits the use of 3½” nails.

March 2024 Page 8 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

9.21.3 Longitudinal Nail-Laminated Wood Decks

a) Longitudinally nail laminated decks can be used and the truck load shall be
assumed to be distributed over a width of 1.7 m. (Cl. 9.21.3).

Commentary: Taken from AASHTO and applies to low volume roads where limited traffic means
less chance of nails loosening.

CHBDC SECTION 11 - JOINTS AND BEARINGS

Commentary: Joint systems that are used for high volume bridges need not be used for low
volume bridges upon Approval by Owner.

CHBDC SECTION 12 - BARRIERS AND HIGHWAY ACCESSORY SUPPORTS

12.4 Barriers

12.4.3 Traffic Barriers

12.4.3.2 Test Level

12.4.3.2.5 Test Level for Barriers on Low Volume Roads

a) A lower performance level is acceptable for some low volume roads


(Cl. 12.4.3.2.5) (Ref. 8).

Commentary: The lower performance barriers can be used on lower speed, low height bridges.

b) A TL-0 and TL-1 railing can be used for bridges meeting the criteria of Table 2.4-3.
If the criteria of Table 2.4-3 are not met, a TL-1 barrier may be used where the barrier
exposure index, Be, is less than 20% of the TL-2 limit shown in CHBDC Table 12.5
through 12.7. Otherwise CHBDC TL-2 through TL-5 must be used. (Cl. 12.4.3.2.5).

c) If the bridge has significant pedestrian and bicycle traffic, the height of the barrier
shall be increased according to Table 12.8 as long as the vehicle barrier interaction is
not adversely affected.

TABLE 2.4-3 – BARRIER SELECTION CRITERIA

AADT Height above water Design Speed Bridge Width


≤ 30 km/hr no limit
TL-0 ≤ 100 ≤ 2.5 m
≤ 40 km/hr ≤ 5.0 m
≤ 50 km/hr no limit
TL-1 ≤ 400* ≤ 5.0 m
≤ 80 km/hr ≤ 5.0 m
* Range can be higher for existing roadways where operational issues have been minimal and
Approval for use of these guidelines has been obtained.

March 2024 Page 9 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

12.4.3.4 Crash Test Requirements

12.4.3.4.2 Crash Test Requirements for Traffic Barriers

a) Railings that have been successfully crash tested to the above performance limits
are given in Figure 2.4.1 and Figure 2.4.2. Other railings that satisfy the crash test
requirements may be used (Cl. 12.4.3.4.2).

Commentary: These have been used for low volume roads in the United States.

FIGURE 2.4.1 – APPROVED TL-1 BARRIER

March 2024 Page 10 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

FIGURE 2.4.2 – APPROVED TL-0 BARRIER SYSTEMS

March 2024 Page 11 of 12 SM-D1-S02


STRUCTURAL MANUAL DIVISION 1 - EXCEPTIONS TO THE CHBDC

SECTION 2 - APPENDIX A
GUIDELINES FOR THE DESIGN OF BRIDGES ON LOW VOLUME ROADS

CHBDC SECTION 15 - REHABILITATION AND REPAIR

15.8 Structural Steel

15.8.1 Member and Connection Repair and Strengthening

15.8.1.1 General

a) Reuse of existing bridge materials may be considered at the Owner’s discretion.


Material condition and physical properties should be determined prior to their use
(Cl. 15.8.1.1).

Commentary: Cost savings from used material may be significant.

2.5 References
Alberta Transportation and Infrastructure. "Design Bulletin #1, Navigable Waters
Protection Act Approvals for Bridge Projects." 2004.
CSA Group. Canadian Highway Bridge Design Code. 12th. CSA Group, 2019.
—. Engineering design in wood. 11th. CSA Group, 2019.
Design and Contract Standards Office. MTO Design Supplement for TAC Geometric
Design Guide for Canadian Roads. Downsview: Queen's Printer for Ontario, 2017.
Faller, Ronald K., et al. "Design and Evaluation of Two Bridge Railings for Low-Volume
Roads." National Academy Press 2 (1995): 357-372.
Gangarao, V. S. Hota and Michael J. Hegarty. "Development of New Design and
Construction Guidelines for Low-Volume Road Bridges." Transportation Research
Record 1106 (1987): 122-130.
GreenStein, Jacob. "Issues Related to Administration of Low-Volume Roads in Developing
Countries." Transportation Research Record 1426 (1993): 65-73.
Ministry of Transportation and Communications. Ontario Highway Bridge Design Code.
2nd. Downsview: Queen's Printer for Ontario, 1983.
Ontario Ministry of Transportation. Drainage Management Manual. Downsview: Queen's
Printer for Ontario, 1997.
—. Highway Drainage Design Standards. Downsview: Queen's Printer for Ontario, 2008.
Otte, Eddie, Van Wyle and Andries J. Pienaar. "Low-Level Stream Crossings in
Developing Areas." Sixth International Conference on Low-Volume Roads.
Minneapolis: Transportation Research Board, 1995. 339-342.
Transportation Association of Canada. Geometric Design Guide for Canadian Roads.
Transportation Association of Canada, 2020.

March 2024 Page 12 of 12 SM-D1-S02


STRUCTURAL MANUAL

DIVISION 2 –
PROCEDURES

SM-D2-S00
STRUCTURAL MANUAL

This page is intentionally left blank.

SM-D2-S00
STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 1 - INTRODUCTION

1 INTRODUCTION .................................................................................................. 2
1.1 General ........................................................................................................................ 2
1.2 Definitions .................................................................................................................... 2
1.3 Distribution of Structural Manual’s Copies .................................................................... 2
1.4 Numbering System of Structural Manual ...................................................................... 2
1.5 Structural Standard Drawings....................................................................................... 3
1.5.1 Format of Structural Standards Drawings ............................................................. 3
1.5.2 Use of Structural Standards Drawings .................................................................. 3
1.5.3 Completion of Structural Standards Drawings ....................................................... 3
1.5.4 Availability of Structural Standards Drawings ........................................................ 4
1.6 Ontario Provincial Standard Drawings (OPSDs) ........................................................... 4
1.7 Ministry of Transportation Ontario Drawings (MTODs) ................................................. 5
1.8 Structures Office Policy Memos ................................................................................... 5

March 2024 Page 1 of 6 SM-D2-S01


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 1 - INTRODUCTION

1 INTRODUCTION

1.1 General

The design and drafting procedures in this division are to be followed when preparing
structural contract documents for the Ministry. The preparation of contract documents
estimation of quantities, and the referencing of Ontario Provincial Standard Specifications
(OPSS) are not covered in this manual. Technical revisions and additions to the
Procedures Division are indicated by the date shown in the left portion of the footer block.

When additions or revisions are necessary, they will be made available through online
website, as detailed in Section 1.3.

1.2 Definitions

For the purpose of this manual the following definitions apply:

Average Annual Daily Traffic (AADT) means the total yearly traffic volume on a given
road/highway, in all lanes and both directions including over twin bridges of divided
highways, divided by the number of days in the year.

Engineer means an engineer who is licensed by Professional Engineers Ontario (PEO).

Ministry means Ministry of Transportation, Ontario.

MTO means Ministry of Transportation, Ontario.

1.3 Distribution of Structural Manual’s Copies

Digital copies of the Manual and revisions may be obtained from the MTO Technical
Publications website.

1.4 Numbering System of Structural Manual

Design aids bear the prefix DA and Structural Standard Drawings bear the prefix SS.
Procedures have no prefix. All Structural Standard Drawings are assigned with a three-
digit number with a drawing number after the prefix (1XX-Y). The first digit (1) is common
for all groups. The next two digits (XX) show the Section Number of the procedure’s
division. Y represents the drawing number within the Section, which contains 1 to 3 digits.
All divisions use the same subject-oriented section numbering system. E.g., SS113-3
would represent the Section 13 of the procedure’s division, `Bearing Assemblies and
Expansion Joints' - Drawing 3. The same principle applies to design aids.

The Structural Standard Drawing numbers in the system are not sequential. This is to
permit the addition of future sheets in the appropriate place without disrupting the
numbering system.

March 2024 Page 2 of 6 SM-D2-S01


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 1 - INTRODUCTION

1.5 Structural Standard Drawings

1.5.1 Format of Structural Standards Drawings

The following two formats are used for Structural Standard (SS) drawings:

a) Structural Standard drawings for attachment on or insertion into rest of the contract
drawings in the manner specified in Section 2.6.13. These drawings do not require
the designer to fill in any additional information from what is shown:

b) Structural Standard drawings requiring project specific information for use as contract
drawings. These drawings serve as templates for a standard structure or element e.g.,
NU prestressed concrete girder, Sign Support Structure, Traffic Barrier, etc. In this
category of Structural Standard Drawings, the designer shall complete all the required
information specific to the design of the structure or element under consideration.

Some Structural Standard Drawings being issued in category (a) are in 216 x 279 mm
(letter size) format. Standards in this category are referred to as "small size" Structural
Standard Drawings.

Structural Standard drawings in category (b) are issued in the structural contract
drawing format of size 914 x 610 mm. They contain two title blocks that must be
completed by the user. Standards in this category are referred to as "full size"
Structural Standard Drawings.

Copies of all the full size Structural Standard Drawings are available in Structural
Standard Drawings Manual which can be downloaded from the MTO Technical
Publications website.

1.5.2 Use of Structural Standards Drawings

Most Structural Standard Drawings bearing an "SS" prefix require project specific
information to be added by the user. The project specific information should be added at
the time the standards are included in the contract drawings package.

AutoCAD file names are established by removing one "S" from the standard drawing name
prefix and adding the extension "DWG".

The AutoCAD layer named "UPDATE" in the digital file, contains a revision information
sheet for the current revision of the drawing.

AutoCAD files of Structural Standard Drawings shall have the drawing and drawing check
initial blocks filled in.

1.5.3 Completion of Structural Standards Drawings

Structural Standard drawings shall be reviewed to determine what information, if any,


needs to be added to them or to be modified to suit the project under consideration.

March 2024 Page 3 of 6 SM-D2-S01


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 1 - INTRODUCTION

Where information in tables and dimensions are transferred to a Structural Standard


Drawing from an MTO manual for its completion, the drawing shall bear the seal, date,
and signature of an Engineer. This Engineer accepts full responsibility for the accuracy
of the added information only.

Where details and notes shown on a Structural Standard Drawing are not applicable, they
shall be deleted, the drawing shall be identified as “Modified”, and shall bear the seal,
date, and signature of an Engineer. This Engineer accepts full responsibility for the
modifications to the drawing only.

Where project-specific information is added, or changes are made on Structural Standard


Drawing that affect or alter the original details, the drawing shall be identified as "Modified"
and shall bear the seals, dates and signatures of design Engineer and a design-checking
Engineer. These Engineers accept full responsibility for the design that results from the
changes.

Those drawings without a Stamping Block are intended to be inserted into the contract
package and are complementary to another Structural Standard Drawing. They do not
require any engineering seal. If they are modified for any reason, they need to be labelled
as such and bear the seals, dates and signatures of design Engineer and a design-
checking Engineer.

1.5.4 Availability of Structural Standards Drawings

Electronic CAD files containing standard drawings in AutoCAD may be obtained from the
CPS.

1.6 Ontario Provincial Standard Drawings (OPSDs)

OPSD's are standards for provincial roads and municipal services which have been
developed in consultation with provincial and municipal owners, designers, and
contractors. They are suitable for use by all owners and reflect a consensus of opinion
about acceptable practices to ensure owners’ standard requirements for quality and the
contractor's need for efficiency are satisfied.

OPSD's are provincial publications and are not automatically used by the Ministry. Those
that the Ministry has implemented may be found in chapter F of the Ministry's Contract
Design, Estimating and Documentation (CDED) Manual, and the CPS. Sometimes it
happens that the Ministry implements or deletes standards prior to publishing in the CDED
Manual. In this case, confirmation of implementation dates prior to CDED manual
revisions will be shown on the CPS News File of the CPS Main Menu.

OPSD standards are to be referenced by drawing number in the contract documents and
their copies are not to be included with the contract drawings.

OPSD drawings are not to be modified. If a designer, however, determines that an OPSD
drawing, as published, does not meet their project’s needs, then it may be modified
provided that:

March 2024 Page 4 of 6 SM-D2-S01


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 1 - INTRODUCTION

• the modified drawing is marked with the date of modification and the contract
number and name of the project to which the drawing applies.

• all references to Ontario Provincial Standards, the logo and the OPSD title, are
removed from the original drawing.

• the drawing shall bear the seal, date and signature of an Engineer and a design-
checking Engineer who have done the modifications. The copies of modified
OPSDs are required to be inserted in the contract drawings package.

1.7 Ministry of Transportation Ontario Drawings (MTODs)

MTODs are developed for use on provincial highway projects. MTODs typically introduce
pilot products and/or designs for highway construction not currently covered by OPSDs.
MTODs successfully used on ministry contracts will be forwarded to the appropriate
Ontario Provincial Standard (OPS) committee for consideration of conversion into OPSDs
at a later date.

MTODs are published and implemented in the Ministry’s CPS and also available at MTO
Technical Publications website.

Reference to the MTODs selected (by MTOD number only) shall also be included as
appropriate in the contract drawings/documents. Copies of MTODs are not to be inserted
into contract drawings package unless modified for a specific project.

Details on the use and modification of MTODs shall follow the policy and procedures
described in CDED Manual.

1.8 Structures Office Policy Memos

Whenever an immediate change to manuals, codes, procedures, policies, or an innovation


is required, the Structures Office issues Policy Memos. These memos enable their
content to be implemented on date of issue, thereby avoiding delay due to waiting for
revision of the corresponding publication. Where conflict occurs with the content of two
documents, the publication/memo with the latest date takes precedence.

Current policy memos may be obtained from the MTO Technical Publications website.

March 2024 Page 5 of 6 SM-D2-S01


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 1 - INTRODUCTION

This page is intentionally left blank.

March 2024 Page 6 of 6 SM-D2-S01


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

2 DESIGN AND GENERAL DRAFTING .................................................................. 3


2.1 Design .......................................................................................................................... 3
2.1.1 Design Specifications............................................................................................ 3
2.1.2 Design and Design-Checking Calculations ........................................................... 3
2.1.3 Structural Continuity.............................................................................................. 3
2.1.4 Critical Design Details ........................................................................................... 4
2.1.5 Shored Construction for Bridges ........................................................................... 4
2.1.6 Live Load Design Forces in Slab-on-Girder Bridges.............................................. 4
2.2 Bridge Geometry .......................................................................................................... 4
2.2.1 Bridge Deck Cross-Sections ................................................................................. 4
2.2.2 Horizontal Clear Zone Width Requirements at Bridge Substructures .................... 4
2.2.3 Treatment of Slopes in Front of Abutments ........................................................... 6
2.2.4 Clearances for CNWA Structures.......................................................................... 9
2.2.5 Vertical Clearance ................................................................................................ 9
2.3 Geotechnical Design ...................................................................................................10
2.3.1 Protection Systems ..............................................................................................10
2.3.2 Sheet Piling Around Footings ...............................................................................11
2.3.3 Fill Stages at Structures .......................................................................................12
2.3.4 Sub-Excavation and Fill at Structures ..................................................................12
2.4 Design - Material .........................................................................................................12
2.4.1 Specified 28-Day Concrete Compressive Strengths.............................................12
2.4.2 Mass Concrete.....................................................................................................13
2.4.3 Availability of Concrete ........................................................................................13
2.4.4 Reinforcing Steel (Grade 500W) ..........................................................................14
2.4.5 Durability..............................................................................................................14
2.4.6 Cover to Reinforcing Steel, P.S. Strands, and P.S. Tendon Ducts .......................15
2.4.7 Requirements for Sulphate Resistance in Bridge Elements .................................15
2.4.8 Corrosion Protection Policy for Concrete Bridge Components .............................16
2.5 Miscellaneous Design Guidance .................................................................................17
2.5.1 Design for Protection of MSE Systems Abutments and Walls ..............................18
2.5.2 Design for Fire Protection of Tunnel Like Structures ............................................18
2.5.3 Design Guidance for Seismic Importance Categories ..........................................19
2.6 Drawings .....................................................................................................................24
2.6.1 Drawing Numbers ................................................................................................24
2.6.2 Sequence and Titles of Structure Drawings .........................................................24

March 2024 Page 1 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

2.6.3 Existing Bridges Access to Contract Drawings .....................................................25


2.6.4 Water Level Designations ....................................................................................25
2.6.5 Notes and Labels Forming Part of Views and Details...........................................26
2.6.6 General Notes......................................................................................................26
2.6.7 Contract Drawing Border .....................................................................................31
2.6.8 General Arrangement Drawings Content and Format ..........................................33
2.6.9 Use of Word "MINIMUM" on Drawings .................................................................38
2.6.10 Construction Staging and Sequence ....................................................................39
2.6.11 Site Numbers .......................................................................................................39
2.6.12 Structure Name....................................................................................................43
2.6.13 Small Size Standard Drawings .............................................................................45
2.6.14 Referencing Standards on Structural Drawings....................................................46
2.6.15 Drafting Scales ....................................................................................................46
2.6.16 Revisions to Drawings .........................................................................................46

March 2024 Page 2 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

2 DESIGN AND GENERAL DRAFTING

2.1 Design

This section discusses general structural design aspects of structural elements.

2.1.1 Design Specifications

All structures (bridges, culverts, and tunnels with spans equal or greater than 3 m and
retaining walls/systems and sign support structures) shall be designed in accordance with
the CHBDC and exceptions to CHBDC provided in Division I of this manual. CHBDC
clauses identified in this revision refer to the 2019 edition of the CHBDC CSA S6.
Structures supporting railway loading shall be designed to criteria provided by the railway
authority.

2.1.2 Design and Design-Checking Calculations

The scope of the design check should be sufficient for the engineer to confirm the contract
package is complete and accurate for construction, and the structural design is compliant
with the requirements of CSA S6 and MTO Exceptions.

For all Ministry bridges designed in-house, the design and the design-checking
calculations, shall be filed with the Bridge Design Section, Structures Office or Structural
Section as applicable. This shall be done by the design Engineer immediately after the
design and the design-checking are completed and the design drawings are sealed, dated
and signed.

For consultant’s designs, a copy of calculations of the final new and rehabilitation bridge
designs including any changes as a result of design checking shall be submitted to the
Ministry project manager, within six (6) weeks of the executive review. For Design Build
Projects, the design and design checking Calculations along with all the changes shall be
submitted minimum six (6) weeks before the start of construction. The design calculations
shall be submitted on letter or legal-size paper. The use of any commercial computer
software, its name and version shall be clearly identified, and a hard copy of the input and
output data and graphs of computer model and output shall also be included with the
design calculations.

The submission shall identify the designer and design checker and shall be dated. The
MTO Structural Engineer shall be responsible for adding the submission to the Bridge
Management System for future reference.

2.1.3 Structural Continuity

All bridges shall be designed as continuous over intermediate supports unless approved
by the Structural Section. Continuity may be achieved with either a continuous
superstructure, or through continuity of the deck slab by means of a flexible link slab.

All bridges with a skew of up to 30 degrees and 100 m or less shall be designed as rigid
frames or integral abutment bridges, where foundation conditions allow. For skew up to

March 2024 Page 3 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

20 degrees, steel and concrete girder bridges of up to 150 m shall be designed as integral
abutment bridges where foundation conditions allow.

2.1.4 Critical Design Details

During the new and rehabilitation design process of structures, the designer shall identify
all critical details and ensure that they can be easily inspected in the future after
construction.

2.1.5 Shored Construction for Bridges

For all slab on girder bridges, the girders shall be designed for un-shored construction,
unless approved by the Structural Section.

2.1.6 Live Load Design Forces in Slab-on-Girder Bridges

To protect for future staging and rehabilitation and the possible future change in functional
use of a bridge, at ULS and SLS, live load effects used for the design of girders shall not
be less than the factors determined in accordance with the simplified methods of analysis
in Clause 5.6 of the CHBDC, unless approved by the Head of Structural Section. If a
bridge does not satisfy the conditions for use of the simplified methods of analysis, the
traffic load fraction used for girder design shall not be less than those determined if the
bridge had met these criteria.

2.2 Bridge Geometry

2.2.1 Bridge Deck Cross-Sections

The CHBDC, CHBDC Commentary and the TAC Geometric Design Guide for Canadian
Roads (2017) in conjunction with the MTO Design Supplement shall be used to determine
deck cross-sections and side clearances.

In deciding the bridge deck cross-section, and determining the dimensions, location, and
design of the structure as a whole, the designer shall aim to provide a bridge on which
driver reaction and vehicle placement will be essentially the same as elsewhere on the
highway considering planned future needs.

2.2.2 Horizontal Clear Zone Width Requirements at Bridge Substructures

This subsection gives direction in setting the ministry's clear zone width requirements to
highway bridge abutments and piers. The railway owner shall be contacted for clearance
envelopes on railway overhead bridges.

For the purpose of this subsection the following definitions apply:

Auxiliary Lane means a lane in addition to, and placed adjacent to, a through lane
intended for a specific manoeuvre such as turning, merging, diverging, weaving, and for
slow vehicles, but not for parking.

March 2024 Page 4 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

Clear Zone means the unobstructed, traversable area provided beyond the edge of the
through travelled way available for use by errant vehicles. The clear zone includes
shoulders, bike lanes, and auxiliary lanes, except those auxiliary lanes that function like
through lanes. The clear zone also includes recoverable slopes, and non-recoverable
slopes with a clear run-out area. The selected clear zone width is dependent upon traffic
volumes and design speed, and roadside geometry.

Clear Zone Width means the distance from the edge of the travelled way to the face of
an unprotected hazard.

Freeway means a fully controlled access road limited to through traffic, with access
through interchanges.

Gore Area means the area between edge of highway, edge of ramp and bullnose.

Travelled Way means that part of a roadway intended for vehicular travel. This includes
through lanes, turn lanes, and other auxiliary lanes. This does not include shoulders or
ancillary space.

Through Lane means a lane intended for through traffic movement.

Through Travelled Way means that part of a roadway intended for vehicular use,
excluding shoulders and auxiliary lanes.

For further information, refer to the Roadside Design Manual.

Minimum horizontal clear zone on Freeways

The minimum horizontal clear zone width from the outside edge of the ultimate through
travelled way to the face of abutments or bridge piers for all bridges over freeways shall
be the greater of:

i) 10 m;

ii) 10 m multiplied by the appropriate horizontal curve adjustment factors given in the
Roadside Design Manual for the design speed and radius of the through travelled way;

iii) Width of gore area plus width of auxiliary lane or ramp plus 7 m from the outside edge
of the auxiliary lane or ramp.

For exceptions see below.

Minimum horizontal clear zone on Non-Freeways

The minimum horizontal clear zone width from the outside edge of the ultimate through
travelled way to the face of abutments or bridge piers for all bridges over non-freeways
shall be the greater of:

i) The clear zone width as given in the Roadside Design Manual for the appropriate

March 2024 Page 5 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

design speed for AADT ≥ 6000 and radius of the through travelled way;

ii) Width of gore area plus width of auxiliary lane or ramp plus the clear zone width given
in (i) from the outside edge of the auxiliary lane or ramp.

For exceptions see below.

Exceptions

Where the requirements above cannot be met due to constraints including those resulting
from alignment, physical, environmental, and property concerns, or would lead to a cost
prohibitive structure, a reduction in the minimum horizontal clear zone width may be
considered with mitigation, and with approval of the Structural Section. When this occurs,
reasons for this deviation from the policy above shall be demonstrated and documented
in the structural design report. Mitigation measures can include an approved barrier
system as specified in the Roadside Design Manual. The barrier system shall be
positioned a distance in front of the abutment or pier to allow for a deflection characteristic
of the barrier system. The offset from the traffic face of the barrier system to the edge of
the closest travelled lane shall be the greater of the following requirements:

i) The minimum clearance to barriers as required by the Roadside Design Manual;

ii) The shoulder widths on the approaches as required by the TAC Geometric Design
Guide for Canadian Roads (2017) in conjunction with the MTO Design
Supplement.

Consideration shall also be given to provide greater clearances that would not increase
the cost of the structure where the bridge configuration would allow it. For example, when
the abutment height exceeds 8 to 8.5 metres, it is sometimes less expensive to increase
the span and reduce the abutment height especially when the bridge is narrow. An open
abutment arrangement is more pleasing and is preferred wherever possible without an
impact on cost.

Bridge abutments and slope treatments shall also be offset adequately to provide the
necessary stopping sight distances.

2.2.3 Treatment of Slopes in Front of Abutments

At overpass and underpass locations where the back slope parallel to the roadway in front
of the abutment is within the clear zone width and at a slope not steeper than 2H:1V,
protection is not warranted provided the slope is free of obstacles and of a smoothness
that allows it to be traversable. However, if the abutment is on an intersecting fill slope as
shown in Figure 2.2.1 this slope and the exposed side of the abutment may be hazardous
to errant vehicles. In this case the approach grading shall be flattened and contoured to
redirect errant vehicles away from the exposed side of the abutment. An example of such
grading is shown in Figure 2.2.1.

Flattening and contouring the grading on the approaches is preferred and is generally a
safer and more economical practice than placing a traffic barrier in front of the abutment.

March 2024 Page 6 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

A traffic barrier is also a hazard, and it is closer to traffic and significantly longer than an
abutment, which is not desirable.
In situations where it is not practical to contour the approaches to the abutment fill, for
example at closed abutments, appropriate mitigation measures such as traffic barriers
shall be considered.

March 2024 Page 7 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

FIGURE 2.2.1 – TREATMENT OF SLOPES IN FRONT OF ABUTMENTS

March 2024 Page 8 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

2.2.4 Clearances for CNWA Structures

For structures over navigable waterways, the minimum clearance provided above the
appropriate water level and as specified in the structural design report shall be shown on
the preliminary and final versions of the general arrangement.

This minimum clearance shall be assumed to apply during as well as after construction
unless the drawings indicate otherwise. If a lesser clearance during construction has been
approved, it must be shown as the "Construction" clearance. This construction clearance
should be given in the structural planning report or be covered by subsequent
correspondence.

2.2.5 Vertical Clearance

Vertical clearances for structures are prescribed in the publications "TAC Geometric
Design Guide for Canadian Roads (2017) in conjunction with the MTO Design
Supplement". Possible reduction of vertical clearance, due to settlement of an overpass
structure, shall be investigated. If the expected settlement exceeds 25 mm, it shall be
added to the specified clearance.

For the purposes of vertical clearance, voided concrete slab bridges would qualify for
reduced clearance shall have exterior web no less than 500mm thick.

The determination of a new structure's profile shall also take into account required
falsework clearances and falsework depth. Table 2.2.1 lists typical falsework dimensions
for various lane arrangements.

TABLE 2.2.1 – TYPICAL FALSEWORK CLEARANCES

Required Opening 2 lanes 3 lanes


Steel beam depth 24 in. / 610 mm 36 in. / 915 mm
Joist depth (mm) 90 140 90 140
Plywood (mm) 17 17 17 17
Crossfall + camber (mm) 150 150 150 150
TOTAL (mm) 867 917 1172 1222

Existing structures with a clearance of less than 4.5 m must be posted.

Resurfacing or reconstruction that reduces clearance under a structure to less than 4.5 m
is not permitted. In addition, any reduction of clearance below that specified for new
bridges requires Ministry approval and shall be avoided if this can be achieved at
reasonable cost.

March 2024 Page 9 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

2.3 Geotechnical Design

2.3.1 Protection Systems

Excavations required for construction of foundations, culverts, and other below-grade


components or structures are generally made with sloping sides or with vertical or near
vertical sides. These conditions depend on a variety of factors such as available space,
type of soil, water table, depth of cut, duration of work etc. In all cases, the conditions
shall provide for the stability and protection of the new construction, adjacent existing
structures, and the safety of the public and construction workers. Where the actual site,
soil and neighbouring conditions will not permit construction with allowable slopes, then
supplementary measures shall be provided such as a "Protection system."

Protection systems are structures designed to protect and preserve existing structures,
materials, utilities, or other works while facilitating the safe construction of new work.
Roadways, adjacent buildings, property, railways, existing bridge work (new and old), gas
and water mains, are examples of items that may require protection. They are, in general,
temporary structures required, essentially, to keep the earth out of excavations.

The type of retaining structure or protection system is selected and designed by the
contractor except as modified below. Contractors may design their schemes according to
their proposed staging, available materials, expertise, and enterprise. The result shall be
a scheme that is structurally adequate and economic to both the owner and contractor.
The design shall not compromise the safety of the public, construction workers and the
protection requirements.

The following policy applies to Ministry projects:

1. The complete design of protection systems shall not be detailed on the contract
drawings, except as follows:

a) Where the protection system will be incorporated into the final design of the
structure.

b) If the owner whose property is being protected, such as a railway company,


requests a detailed design to be part of the contract documents.

c) Special cases where the Ministry perceives that, for significant safety concerns,
control of the protection system’s design should remain with the permanent
structure designer.

For these situations the structural design report shall make the appropriate
recommendations for the protection system’s design.

In order for the Ministry to benefit from a contractor's design, construction ingenuity,
experience, and ability to work through or around restrictions, the contractor may still
submit alternate schemes. These, however, will only be allowed under certain
conditions. Some important elements that should form part of these conditions are:

March 2024 Page 10 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

• There should be a cost saving which the ministry shares with the contractor.
• The change proposal shall not compromise any essential design criteria, safety or
preliminary engineering commitments.
• The change proposal cannot be the basis for a contract claim.

Where applicable, the criteria above shall be included in the contract documents.

2. When an anticipated protection system is not detailed on contract documents,


adequate information shall be given on the contract drawings to enable the contractor
to design and construct the protection system. Such information shall include all or
some of the following:

a) Approximate location;
b) Allowable slope geometry;
c) Earth pressure parameters;
d) Design bond stress for anchors where applicable;
e) Performance level;
f) Operational constraints;
g) Known utilities;
h) Live load surcharge.

3. For all protection systems, the design and construction shall meet the requirements of
the Ontario Provincial Standard Specification OPSS 539 "Construction specification
for temporary protection systems".

4. It is possible that a protection system may not be anticipated but required because of
the contractor's method of operation. In this situation, drawings of the contractor’s
proposal shall be submitted to the Contract Administrator (CA) as required by OPSS
539. Review of these cases will be at the discretion of the regional office.

5. The protection systems proposals shall be submitted to CA for information only. For
a complex system included in the contract, Structural Section may be involved in the
review with the CA before construction, the Structures Office may also be consulted
at the discretion of the Structural Section.

For assistance in the design or review of protection systems the designer may consult the
"Guide Design Specifications for Bridge Temporary Works, 2nd edition" 2020 INTERIM
REVISIONS, AASHTO and the "Construction Handbook for Bridge Temporary Works, 2nd
edition", published by AASHTO in 2017 shall be referenced. Where conflict occurs in
these publications with OPSS 539 or the recommendations of the Foundation Section, the
requirements of the latter shall take precedence.

2.3.2 Sheet Piling Around Footings

When sheet piling is to be left permanently in place around a footing, typically as scour or
tremie concrete protection, it shall be stated on the contract drawings. The cut-off and tip
elevations shall be specified, together with the minimum thickness and minimum section
modulus per unit width. In this case, payment for such work shall be included in the tender
item for concrete in footings.

March 2024 Page 11 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

Shoring and bracing required to do the work are usually not shown on the contract
drawings but shall remain the responsibility of the contractor.

2.3.3 Fill Stages at Structures

Where fill is to be brought up to footing level, piles (if any) driven, etc., the first fill stage or
interim grade line shall be shown to the bottom of footing elevation on the general
arrangement drawing.

When piles are to be driven through the fill, a note is required limiting the maximum particle
size in the fill to 75 mm when steel H-piles are specified, and 50 mm when tube piles are
specified. If either type of piles may be used, the maximum particle size for tube piles
shall be specified.

2.3.4 Sub-Excavation and Fill at Structures

When the foundation investigation report recommends sub-excavation of unacceptable


material in the vicinity of structures and replacement with granular material, the type of
granular material shall be established in consultation with the Foundation Section and the
Structural Section and shall be specified on the general arrangement drawing. When the
extent of sub-excavation is not shown on structural drawings, a note saying "FOR LIMITS
OF SUB-EXCAVATION, SEE GRADING DRAWING" is required, close to where the sub-
excavation is indicated.

2.4 Design - Material

2.4.1 Specified 28-Day Concrete Compressive Strengths

The 28-day concrete compressive strength shall be specified based on Table 2.4.1 below.
The concrete compressive strength is the concrete strength, which is determined by
means of cylinders or cores, tested at 28 days of age, as specified by the governing OPSS.
The 28-Day compressive strengths listed below are to be specified for normal concrete.
MTO performs in-situ testing for Rapid Concrete Permeability (RCP), and salt scaling as
means of improving the durability of in-place concrete. Specifications currently require
concrete RCP values of between 1000 and 2500 Coulombs, depending on the use and
type of concrete. As such, concrete strength should be specified only for structural
requirements since the durability properties can be achieved by other various means
allowed in the concrete specifications.

Higher strengths of concrete come with increased cost, higher carbon footprint, generate
more heat, and have higher shrinkage which may result in more cracking. In typical bridge
designs, it is difficult to make use of the higher strength in the structural design since shear
and tensile cracking are a function of the square root of the concrete strength. Acceptable
28-day compressive strengths of concrete for various applications are as follows:

March 2024 Page 12 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

TABLE 2.4.1 – 28-DAY CONCRETE COMPRESSIVE STRENGTHS

28-day Compressive
Applications
Strength
<30 MPa Not used for structural purposes.
For bridge decks, curbs, sidewalks, approach slabs, barrier walls, cast-in-
30 MPa
place concrete culverts and substructures.
For precast culverts with span 3m and less, prestressed post-tensioned
35 MPa concrete, columns where strength requirements dictate, and cast in place
segmental structures.
For precast prestressed panels, and precast segmental units. (See also
40 MPa
Section 7.2)
45 MPa For precast concrete culverts with spans greater than 3m
50 MPa For precast prestressed box beams. (See also Section 7.2)
60 MPa For precast prestressed NU girders. (See also Section 7.2)

Higher strengths are permissible only with justification and if written approval at no later
than its 30% design is obtained by the designer from the Head of Structural Section.

The required concrete strength shall be shown on the preliminary version of the general
arrangement drawing.

2.4.2 Mass Concrete

According to OPSS 904, components with the least dimension thicker than 1.5 m are
classified as mass concrete. For mass concrete components, a temperature control plan
is required by OPSS 904 and is to be developed by the Contractor. To mitigate against
excess heat development during curing of the concrete, components should be no thicker
than necessary, should be detailed with the lowest practical strength of concrete, and
should use the largest practical aggregated size. Nevertheless, there are situations where
the designer may need to include additional provisions in design to ensure the temperature
limits are controlled. In design, this could include planned and designed construction joints
through a component to limit the size of each placement to allow for natural cooling
between staged concrete placements which usually requires additional reinforcement to
be designed.

The designer shall review and determine if large concrete components potentially require
thermal intervention during curing. If the temperature of the components is likely to exceed
70° C and cannot be mitigated by routine construction measures (e.g. lowering the initial
concrete temperature, adding supplementary cementing materials to the limits allowed in
OPSS 904), an NSSP should be added to the contract where cooling systems are
anticipated. For components which are not exposed to de-icing salts, alternate concrete
mix designs should be considered. Notes should be added to the GA to account for any
optional construction joints or cooling system(s).

2.4.3 Availability of Concrete

There are areas in the province where cast-in-place concrete is difficult to obtain. The

March 2024 Page 13 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

designer shall confirm the availability of cast in place concrete, from a certified ready-
mix plant, before starting the design.

2.4.4 Reinforcing Steel (Grade 500W)

In 2021, the Ministry announced the policy to move towards a higher grade of 500W MPa
strength steel reinforcement. Since 2010, Grade 400W reinforcing steel has been
specified according to CSA G30.18-09 (R2014): Carbon Steel Bars for Concrete
Reinforcement, as the standard grade of reinforcing steel on MTO contracts. The same
CSA specification and its current version includes grade 500W which is 25% stronger than
400W. The higher strength of 500W steel helps to reduce the total area of steel in
reinforced concrete and precast elements. This specially becomes advantageous in
reducing the rebar congestions and offers additional advantages such as:

• Reduced time and labour costs to place reinforcing steel;


• Easier concrete placement and result in improved quality;
• Lower greenhouse gas emissions due to less tonnage of reinforcing steel; and,
• Design yield strength of 500 MPa aligns with current design yield strength of
500 MPa for stainless reinforcing steel.

As per MTO’s policy the switch to 500W reinforcing steel began in 2022 with new designs
started to use the new grade. By April 2024, it is expected that all projects currently in
design phase l will have been completed, and all projects after that time will only use 500W
grade in design.

The following policy shall be applied:

1. The designer shall utilize only the 500W grade, mixing of 400W and 500W on the same
structure is not permitted;

2. The designer shall consider and take advantage of the higher yield strength, where
permitted by CHBDC;

3. For SSD’s, any reference from 400W shall be changed to 500W. Structures Office is
in the process of updating the drawings to 500W and has determined that there are
no negative implications in using the currently specified reinforcement quantities with
the higher strength;

4. For OPSD’s, and MTOD’s, which are not allowed to be modified, the drawings shall
be replicated, but with the steel grade changed to grade 500W, and inserted into the
drawing package for the bridge. The drawings shall be signed and sealed by the
design engineer as per Section 1.5.3.

2.4.5 Durability

Durability requirements for new structures, rehabilitation and replacement work shall meet
the provisions of Section 2 of the CHBDC except, where modified by the contents of this
manual.

March 2024 Page 14 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

2.4.6 Cover to Reinforcing Steel, P.S. Strands, and P.S. Tendon Ducts

The nominal cover and tolerance specified on drawings are based on CHBDC Table 8.5,
and the CHBDC Exceptions. Contrary to CHBDC Commentary Clause C8.11.2.4 and
based on satisfactory past performance, MTO treats the overhead deck slab soffit as a
moderate (and not severe) environmental exposure and does not increase the cover by
the 10mm suggested in the notes to CHBDC Table 8.5.

The concrete cover, and placement tolerances for several typical conditions are provided
in Section 2.6.6 which shall be added to the Contract Drawings as General Notes. For
member types, surfaces and exposure conditions not listed, the designer shall refer to
Clause 8.11.2.4 of the CHBDC. Some nominal alterations to the cover are specified in
MTO Structural Standard Drawings, with the specific values for concrete cover and
tolerance shown on the individual drawings. Some reductions in cover due to the use of
Premium Reinforcement have already been incorporated into values provided in Section
2.6.6 and in the Structural Standard Drawings which are applicable in conjunction with the
details and practices used throughout this Manual.

In detailing and scheduling reinforcing steel it is important to ensure that nothing will
prevent obtaining the specified cover. Particular attention is drawn to the following:

1) Stirrups which extend from the bottom to the top of the deck shall be sized to fit without
causing an encroachment on the cover in any location. Generally, this results in the
stirrups being 120 mm min. less than the deck depth at the shallowest location where
the stirrups are to be placed;

2) In slabs and walls, stirrups need not be hooked over the outer-most reinforcing bars.
They may be hooked over bars in the lower layer of the top mat with 135 degree hooks
or greater;

3) The appropriate standard drawing showing the method of supporting the reinforcing
steel shall be referenced as follows:

• OPSD 3329.101 for thick slabs;


• OPSD 3329.100 for thin slabs (i.e., less than 300 mm thick);

4) If fanned bars are used, a location shall be found for them such that there is no
encroachment on cover and that location shall be clearly shown in plan and section.

2.4.7 Requirements for Sulphate Resistance in Bridge Elements

Concrete used in buried concrete structural elements including but not limited to piles,
caissons, footings, retaining walls, pile caps, culverts, pipes, utility chambers, box
maintenance holes and retained soil systems can be exposed to sulphate attack.
Concrete is considered subject to sulphate attack when:
• Water-soluble sulphate (SO4) content of the adjacent soil is equal to or greater
than 0.10%; or,
• Sulphate (SO4) in groundwater is equal to or greater than 150 mg/L.

March 2024 Page 15 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

When concrete is identified as subject to sulphate attack, the concrete shall be resistant
to sulphate attack as required by Special Provision CONC0006.

2.4.8 Corrosion Protection Policy for Concrete Bridge Components

Definitions

Black Steel means carbon steel as per CSA G30.18.

Corrosion Resistant Materials means Premium Reinforcement and HPC.

Premium Reinforcement or Premium Reinforcing means Stainless Steel or GFRP.

Conventional concrete means concrete containing no silica fume, having a rapid chloride
permeability at 28 days of 2500 coulombs or less, and having a minimum specified 28-
day compressive strength of 30 to 60 MPa, in accordance with OPSS 1350.

High Performance Concrete (HPC) High Performance Concrete (HPC) means concrete
with a minimum specified 28-Day compressive strength of at least 50 MPa that includes
silica fume and may include other supplementary cementing materials and having
specified rapid chloride permeability at 28 to 32 Days of 1,000 coulombs or less.

Stainless Reinforcing Steel means stainless steel reinforcing bars conforming to ASTM
A276 and ASTM A955M, minimum grade 500, Type 316 LN or 2205 Duplex or 2304
Duplex. All structural designs which specify stainless reinforcing steel in accordance with
OPSS 1440 and this manual shall take advantage of the higher yield strength of 500 MPa
in proportioning the reinforcement size and spacing.

GFRP Reinforcing means Grade III Glass Fibre Reinforced Polymer reinforcing bars
meeting the high durability as D1 category, with nominal areas according to CSA S807,
and material properties according to OPSS 1640.

Background

Current corrosion protection strategies include use of black (carbon) steel in low
susceptible bridge components, the use of deck waterproofing membrane and the use of
Premium Reinforcement for bridge components within salt susceptible areas, including
the splash zones as defined in Table 12.2.1 of the Structural Manual. These strategies
were developed based on life-cycle financial analysis. Given the higher unit price of
Premium Reinforcement, the Ministry uses it judiciously and only in those components for
which a life-cycle benefit can be demonstrated.

The Ministry conducted studies on a number of decks built with epoxy-coated rebars in
the early 1980’s. The studies showed that the waterproofing membrane and the concrete
cover were effective in minimizing the ingress of moisture and chlorides, making a service
life of 75 years possible provided the waterproofing is replaced every 30 years. Studies
have also shown that epoxy coated steel was not effective in providing additional corrosion
protection and it is therefore no longer used by the Ministry as a corrosion protection
strategy.

March 2024 Page 16 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

The Structures Office, in conjunction with the Engineering Materials Office, continues to
explore new types of corrosion resistant reinforcement and corrosion protection strategies
will be reviewed from time to time as new cost-effective materials are identified.

Corrosion Protection Requirements

1. Premium Reinforcing shall be used in proximity to all bridge surfaces within the splash
zone or otherwise exposed to chlorides. Details of reinforcement and locations are
provided in Section 12.

2. Normal concrete is typically used. However, when considered appropriate by the


Structural Section, HPC may be specified for bridge components except the following:

• Footings;
• Post-tensioned bridges;
• Precast pre-stressed concrete girders with 28-day design strength less than or
equal to 50 MPa.

3. All concrete decks shall be protected by a hot poured rubberized asphalt waterproofing
system with protection board, followed by paving with asphalt. In rare cases where
the Structural Section decides to use exposed concrete decks (e.g., to reduce dead
loads), Premium Reinforcement shall be required in the deck beyond what is specified
in Section 12 of this manual.

Additional Guidelines for Rehabilitation

In addition to the requirements described above, the following policies shall be followed
with respect to the application of premium corrosion protection systems in rehabilitated
concrete bridges:

• Concrete patch repairs:


Conventional concrete or proprietary patching materials shall be used in patch
repairs, depending on the size and dimensions of the repair area. HPC shall not
be used in patch repairs, regardless of the remaining life of the bridge or its
exposure condition.

• Overlays:
Two low permeability concrete overlay options are available, silica fume concrete
and latex-modified concrete, as outlined in the Structure Rehabilitation Manual.
There is no “HPC” overlay option available in current MTO specifications and this
shall not be specified. The current strength specification for silica fume concrete
overlay is 40 MPa compressive strength at 28 days. Conventional concrete
remains an option for overlays.

Premium Reinforcement requirements for Rehabilitations shall be as per Section 12 of this


manual.

2.5 Miscellaneous Design Guidance

March 2024 Page 17 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

2.5.1 Design for Protection of MSE Systems Abutments and Walls

The use of Mechanically Stabilized Earth (MSE) Systems (RSS) for false and true
abutments allows them to be constructed close to travelled lanes and in salt splash zones
which exposes them to deterioration, requiring the use of premium reinforcement. They
are also susceptible to loss of integrity in the event they are hit by errant vehicles. The
MSE false abutment may also be designed as an integral or semi-integral abutment that
may be vulnerable to an impact from vehicles unless it is designed to absorb the traffic
load, or it is adequately protected. Integral abutment bridges supported on a single row of
piles are somewhat more vulnerable than semi-integral abutment bridges, which are
supported on columns on rigid foundations. Consideration therefore shall be given to their
protection as indicated below:

i) Where MSE concrete facing panels are located within the clear recovery zone,
they shall be protected by an approved traffic barrier system or a slope treatment.

a. The approved traffic barrier system shall be installed at least the TL-5 cab Zone
of Intrusion distance in front face of the abutment wall, which is 1.3 m for OPSD
911.132 concrete tall wall barrier or 1.65 m for MTOD 912.600 steel railing:

b. The slope treatment should have a 2H:1V to 2.5H:1V upward slope for a
distance of at least 4.0 m measured horizontally from the edge of shoulder to
the face of panels and the approach grading should be flattened and contoured
as described in the previous section;

ii) Where integral or semi integral abutment design is used, the deflection and 4.0 m
distance shown in i) shall be increased by 0.8m.

2.5.2 Design for Fire Protection of Tunnel Like Structures

Structures that span over a roadway with vehicular access limited only to the two ends of
the enclosed area can be considered to be tunnels irrespective of the presence of fill on
top of the structure. These structures present specific safety challenges in the case of a
fire breaking out within the structure; the degree of risk to life safety depends on the length
of the roadway between access points.

In the absence of a policy dealing with the fire protection of tunnel-like highway structures,
designers were left to their own professional judgement on when to implement fire
protection. Although internationally recognised standards like National Fire Protection
Association (NFPA) 502 provide guidelines for fire resilience design of road tunnels, many
practising bridge engineers may not be aware of its requirements and there is no direct
reference to it in the CHBDC. Furthermore, the CHBDC does not have load combination
factors involving fire events nor provisions for material properties at elevated
temperatures. The guidelines described below are to ensure a consistent design
approach for fire protection of tunnel like structures and to ensure life safety related to fire
events is duly considered where there is a higher risk of occurrence of a large hydrocarbon
fire.

A highway structure will be treated as a tunnel for the purposes of fire resilient design

March 2024 Page 18 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

when:

a) The structure spans over a motor vehicle roadway; and,

b) The vehicular access is limited to the two ends of the fully or partially enclosed area;
and,

c) The distance between any open-air access points for emergency equipment to the
roadway below is greater than 90m.

A structure, through an engineering analysis according to NFPA 502 Chapter 4, may also
be categorized as a fire resilient design tunnel by the ministry.

Unless otherwise approved by the ministry, new highway structures categorised as


tunnels and with AADT for the enclosed roadway exceeding 1500 shall be designed for
fire resilience according to the following requirements:

1. Design for fire resilience shall be according to Chapter 7 of the latest edition of NFPA
502;

2. Road tunnels shall be designed to withstand the required fire exposure without
structural collapse for a minimum duration of 2 hours under all dead loads. Load
factors for all permanent loads including snow load, fill and landscaping, as applicable,
shall be 1.0. Material properties at elevated temperatures shall be according to EN-
1991-1-2 Eurocode 2: Design of Concrete Structures Part 1-2, General Rules –
Structural Fire Design, 2004 edition, unless otherwise specified by the Ministry. Steel
structures shall not be used unless approved by the Ministry.

3. In addition to criteria (2) above, road tunnels that carry vehicular traffic on top shall be
designed to withstand the required fire exposure without structural collapse for a
minimum duration of 1 hour with full traffic live load and all dead loads. Load factors
for live loads and all permanent loads including snow load, fill and landscaping, as
applicable, shall be 1.0 and with no application of dynamic load allowance. Material
properties at elevated temperatures shall be as stated in criteria (2) above;

4. Any fire protection materials used to retard the temperature increase of structural
components shall be durable and able to withstand moisture, chloride, freeze thaw
cycles and the dynamic effect due to in-service live load for a service life of 50 years.

New tunnels with AADT less than 1500 and rehabilitation of existing tunnels, including
extending the width or length of a structure to meet the above criteria a) through c) for a
tunnel, shall be required to follow the above design requirements 1) through 4) only when
specified by the ministry.

2.5.3 Design Guidance for Seismic Importance Categories

The seismic importance category shall be shown in the structural planning report and shall
be determined as follows:

March 2024 Page 19 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

i) Lifeline bridges shall include all bridges:

a) With AADT exceeding 20,000 and overall length exceeding 1000 m, or deck area
exceeding 10,000 m2; or,

b) Identified in an economic planning exercise as structures that are vital to the


integrity of the regional transportation network, the ongoing economy, and/or the
security of the region and/or represents significant investment and would be time-
consuming to repair, with approval of the Structures Office;

ii) Major-route bridges shall include all bridges:

a) Carrying Core and Feeder National Highway System bridges (see Figure 2.5.1 and
Table 2.5.1); or,

b) Carrying 400 series highways; or,

c) Exceeding 300 m in length; or,

d) Exceeding 5000 m2 of deck area; or,

e) That provide sole access to emergency vehicles and those with exceptionally long
detour lengths, with the approval of the Structural Section; or,

f) Identified in an emergency planning exercise as being critical to an emergency


response of a community, with approval of the Structural Section;

iii) Other bridges are all remaining bridges.

Note: AADT and deck area, in the case of twin bridges and core/collector freeways, shall
be for all lanes of traffic.

March 2024 Page 20 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

FIGURE 2.5.1 – CANADA’S NATIONAL HIGHWAY SYSTEM – ONTARIO

Source: Annual Report 2017 (https://www.comt.ca/Reports/NHS%20Annual%202017.pdf)

March 2024 Page 21 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

TABLE 2.5.1 – CANADA’S NATIONAL HIGHWAY SYSTEM – ONTARIO HIGHWAYS


AND LOCATIONS

Source: Annual Report 2017 (https://www.comt.ca/Reports/NHS%20Annual%202017.pdf)


Northern
Ontario Core Feeder and
Remote
Length
Route From To km km km
(km)
QEW Fort Erie Toronto 139.0 139.0
401 Que. Border Windsor 827.0 827.0
402.0 London U.S. Border (Sarnia) 102.6 102.6
U.S. Border (Queenston -
405 QEW 8.8 8.8
Lewiston Bridge)
427 Hwy 401 QEW 7.7 7.7
137 Hwy 401 U.S. Border (Lansdowne) 4.3 4.3
416 Ottawa (Jct. 417) Hwy 401 75.9 75.9
16 Hwy 416 U.S. Border (Prescott) 3.8 3.8
417 Quebec Border Hwy 17 Sheel Drive (Arnprior) 194.0 194.0
400 Toronto (Jct. Hwy 401) Hwy 69 (IC-241) 225.0 225.0
69 Hwy 400 (IC-241) Sudbury (Jct. Southwest Bypass) 139.0 139.0
Hwy 417 Sheel Drive
17 Manitoba Border 1,948.0 1,948.0
(Arnprior)
66 Quebec Border Kirkland Lake 58.0 58.0
11 North Bay Nipigon 991.0 991.0
U.S. Border (Fort
71 Hwy 17 194.0 194.0
Frances)
U.S. Border (Pigeon
61 Thunder Bay (Jct. 17) 61.0 61.0
River)
403 QEW (Burlington) Hwy 401 (Woodstock) 82.0 82.0
11 / 400A Barrie North Bay 239.0 239.0
35 / 115 Hwy 401 Peterborough (S Jct. Hwy 7 / 115) 44.8 44.8
Peterborough (S Jct.
7 / 115 Ottawa (Jct. Hwy 417) 250.0 250.0
Hwy 7 / 115)
Peterborough (S Jct.
7 / 12 Hwy 11 130.0 130.0
Hwy 7 / 115)
12 N Jct. Hwy 11 Hwy 400 21.0 21.0
26 Hwy 400 (Barrie) Collingwood (County Road 19) 63.0 63.0
6.0 Hwy 403 (Hamilton) Hwy 401 (Guelph) 25.9 25.9
6.0 Hwy 401 (Guelph) Guelph (Woodlawn Rd.) 15.4 15.4
Guelph (Woodlawn
7.0 Kitchener (Conestoga Parkway) 21.0 21.0
Rd.)
Kitchener (Conestoga
8.0 Stratford (Erie) 45.0 45.0
Parkway)
8.0 Hwy 401 Kitchener (Conestoga Parkway) 7.7 7.7
108 Hwy 17 Elliot Lake (Hillside Dr.) 27.2 27.2
34 Hwy 417 Hawkesbury (Quebec Border) 19.2 19.2
17B Hwy 17 U.S. Border (Sault Ste. Marie) 10.6 10.6

March 2024 Page 22 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

Northern
Ontario Core Feeder and
Remote
Length
Route From To km km km
(km)
3.0 Hwy 401 U.S. Border (Ambassador Bridge) 11.0 11.0
U.S. Border (Detroit-Windsor
3B Hwy 401 11.0 11.0
Tunnel)
420 QEW U.S. Border (Rainbow Bridge) 5.0 5.0
Nicholas / Rideau /
Hwy 417 Quebec Border (Gatineau) 4.0 4.0
King Edward
403 QEW Hwy 401 21.0 21.0
410 Hwy 401 Hwy 10 24.0 24.0
427 Hwy 401 York Regional Road 7 12.3 12.3
409 Hwy 401 Hwy 427 6.0 6.0
6 Hwy 403 Hamilton Airport (Airport Rd.) 10.0 10.0
Bronson / Airport
Hwy 417 Ottawa Airport 9.8 9.8
Parkway
Airport Rd. /
Hwy 401 London Airport 10.0 10.0
Oxford St. E
RR7 / RR50 / CP Intermodal Terminal
Hwy 427 6.0 6.0
Rutherford (Vaughan)
Steeles / Airport CN Intermodal Terminal
Hwy 410 (Bovaird Dr.) 7.1 7.1
Rd / Intermodal Dr. (Brampton)
Derry Rd / Airport Steeles Ave. - CN Intermodal
Hwy 427 5.6 5.6
Rd / Intermodal Dr. Terminal (Brampton)
Gardiner Expy /
Hwy 427 CP Obico Intermodal Terminal 3.5 3.5
Kipling / Queen
Derry Rd. - CP Expressway
Trafalgar Hwy 401 1.7 1.7
Intermodal Terminal
RR7 / Keele / CN RoadRailer Intermodal
Hwy 400 4.3 4.3
Administration Terminal (Vaughan)
CP Expressway Intermodal
McCowan Road Hwy 401 1.6 1.6
Terminal (Scarborough)
138 Hwy 401 Hwy 417 35.0 35
138 U.S. Border (Cornwall) Hwy 401 IC 8.0 8
CR17 Hawkesbury E Hwy 417 10.0 10.0
144 / 101 Hwy 17 (Sudbury) Timmins (Mountjoy St.) 292.0 292
101 Timmins (Mountjoy St.) Hwy 11 62.0 62
12 Hwy 400 Midland (Hwy 93) 18.0 18.0
10 Hwy 410 Owen Sound (Hwy 26) 136.0 136
77 Hwy 401 Leamington (Hwy 3) 23.0 23
3.0 Leamington (Hwy 77) Hwy 401 39.0 39
19 Hwy 401 Tillsonburg (Vienna Rd.) 23.0 23
24 Hwy 403 Simcoe (Hwy 3 / Queensway Dr.) 36.0 36
Total 6,816.8 6,134.8 682.0 -

March 2024 Page 23 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

2.6 Drawings

This section provides criteria and guidance on the preparation on design drawings and
contract packages.

2.6.1 Drawing Numbers

Final drawings for all new structures are numbered consecutively with numbers only. The
drawing number is added to the lower title block, as explained in 2.6.7.

Preliminary drawings are numbered with the letter P1 for the first scheme. If preliminary
drawings are revised and re-issued, the number is incremented, e.g., from P1 to P2. If
more than one preliminary scheme is prepared, the drawings are numbered PA1, PB1 etc.
For cases where there is more than one drawing per scheme then it shall be numbered
PA1, PA2, etc.

Rehabilitations or modifications shall be numbered with the prefix RX-1, 2, etc., where X
represents the number of times it has been rehabilitated.

In the following examples, the simplest and the most complex results are shown, however
improbable the latter.

50 A bridge final, fiftieth drawing.


P1 Bridge preliminary, one scheme, one drawing.
PA2 Bridge preliminary, first scheme, second sheet.
R4-P1 Bridge rehabilitation preliminary, fourth rehab, one proposal.
R4-12 The rehabilitation above, final drawing, twelfth sheet.

2.6.2 Sequence and Titles of Structure Drawings

The structure drawings are generally placed in the order of construction, with some
standard detail and electrical drawings located at the end. Drawings shall be included as
appropriate for specific bridges in the order shown below.

General Arrangement
Borehole Locations and Soil Strata
Construction Staging
Roadway (Track) Protection
Foundation Layout
Footing Reinforcement
North (West) Abutment
For all types of bridges:
North (West) Wingwall
South (East) Abutment
South (East) Wingwall
Retaining Walls
Mechanically Stabilized Earth (MSE) System (RSS)
Piers
Bearings

March 2024 Page 24 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

Deck Details
For bridges with
Longitudinal Tendons I, II, etc.
post-tensioned decks:
Transverse Tendons I, II, etc.
For bridges with precast, Prestressed Girders
prestressed concrete Prestressed Girders and Bearings
girders: Deck Details
For bridges with steel Structural Steel I, II, etc.
girders: Deck Details
Deck Reinforcement
Joint Anchorage and Armouring
Barrier Wall with Railing
Barrier Wall w/o Railing
Railing for Barrier Wall
For all types of bridges: 6000mm Approach Slab
Details of Concrete Slope Paving
As Constructed Elevations and Dimensions.
Pile Driving Control
Standard Details I, II, etc.
Electrical Embedded Work

2.6.3 Existing Bridges Access to Contract Drawings

Requests for contract drawings and shop drawings of existing structures shall be
submitted to the Structural Section. The Structural Section may contact the Structures
Office if the drawings are not available in their files.

2.6.4 Water Level Designations

The following procedure shall apply to the designation of water levels on drawings:

a) A water level shall be shown;

b) The water level shown shall be a factual one, i.e., an elevation taken at some specific
time, such as when the profile was run, and E plan contours obtained. This elevation
shall be shown on the drawings with the date, e.g., "429.00 (day/month/year)";

c) If more than one elevation is known, the Head of Structural Section shall be consulted
as to the benefits of showing water levels measured at different dates;

d) An estimated High Water Level (HWL), required for the assessment of waterway
opening, shall be shown on the preliminary version of the general arrangement
drawing only. This water level shall be removed for the final version;

e) The Structural Section shall be responsible for supplying all pertinent water levels in
the structural planning report.

f) When the Structural Section deems it prudent, an additional water level, to be used for

March 2024 Page 25 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

the design of protection schemes, shall be included on the general arrangement


drawing with the note:

PROTECTION SCHEME DESIGN WATER LEVEL ________

2.6.5 Notes and Labels Forming Part of Views and Details

Notes are used to complement the information described graphically and should be placed
directly at the end of leaders. Use of item references, in the form of numbers or letters at
the end leaders referring to a legend or list, shall be avoided. Notes placed on views or
details, describing components or requirements shall be precise, unambiguous, contain
no unnecessary words, and be used only when necessary.

Some common examples are as follow:

a) "Barrier wall and rail". There is no need for the word "Standard". The note shall state
whether or not there is a rail. This note is required on the preliminary and final versions
of the general arrangement drawing on the elevation. It shall not be repeated on the
cross section;

b) "Slope paving (typ.)". There is no need for other description and the note shall appear
only once on the elevation;

c) "Top of concrete end dams to suit pavement profile". This note shall always appear
on the abutment drawing;

d) "Top of cleat to be cast 35 mm below approach slab ledge". Reference to the to


closed-cell extruded polystyrene or neoprene is unnecessary since this is on the
approach slab drawing.

e) Notes calling for the removal of formwork or expanded polystyrene shall never be
used. The specifications require all formwork be removed and if expanded polystyrene
is not to be left in place, it shall not be shown at all;

f) Notes concerning construction joint grooves and sealing shall not duplicate or conflict
with OPSD-3950.100 if this standard is included in the drawings.

2.6.6 General Notes

The following are standard notes to be shown below the title block on the general
arrangement drawing. The notes shall be worded to cover the requirements specific to
the particular project and should only be used if applicable. Other notes may be required
in special circumstances.

In specifying the classes of concrete, different components may be itemised together if


the classes are the same.

For clarity the wording of the notes is shown in upper case (capital) lettering. Explanations
shown in brackets in lower case lettering are not part of the notes.

March 2024 Page 26 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

a. General Arrangement Drawings Slab-On-Girder Bridges

1) SPECIFIED 28-DAY COMPRESSIVE STRENGTH

30 MPa

XX MPa (CLOSURE POURS) (if applicable)

SPECIFIED 28-DAY COMPRESSIVE STRENGTH FOR PRECAST GIRDERS ARE


GIVEN ON PRESTRESSED GIRDER DRAWINGS

2) Clear Cover to Reinforcing Steel

FOOTINGS 100 ± 25

DECK TOP 70 ± 20
BOTTOM 40 ± 10

PIER COLUMNS, SHAFTS AND CAPS 70 ± 10

REMAINDER 70 ± 20 UNLESS OTHERWISE NOTED

3) Reinforcing Steel

REINFORCING STEEL SHALL BE GRADE 500W.

UNLESS SHOWN OTHERWISE, TENSION LAP SPLICES FOR REINFORCING


STEEL BARS SHALL BE CLASS B.

STAINLESS REINFORCING STEEL SHALL BE TYPE 316LN OR DUPLEX 2205


AND HAVE A MINIMUM YIELD STRENGTH OF 500 MPa, UNLESS OTHERWISE
SPECIFIED.

BAR MARKS WITH PREFIX ‘S’ DENOTE STAINLESS STEEL BARS.

GLASS FIBRE REINFORCED POLYMER REINFORCING BARS SHALL BE GRADE


III, AND THE NOMINAL DIAMETER, TENSILE MODULUS OF ELASTICITY AND
GUARANTEED MINIMUM TENSILE STRENGTH SHALL BE AS SPECIFIED IN THE
CONTRACT DOCUMENTS.

BAR MARKS WITH THE PREFIX ‘G’ DENOTE GRADE III GLASS FIBRE
REINFORCED POLYMER BARS.

BAR HOOKS SHALL HAVE STANDARD HOOK DIMENSIONS USING MINIMUM


BEND DIAMETERS, WHILE STIRRUPS AND TIES SHALL HAVE MINIMUM HOOK
DIMENSIONS. ALL HOOKS SHALL BE IN ACCORDANCE WITH THE
STRUCTURAL STANDARD DRAWING SS112-1, UNLESS INDICATED
OTHERWISE. HOOKS AND BENDS FOR GFRP BARS SHALL HAVE A MINIMUM
BEND-RADIUS-TO-BAR-DIAMETER RATIO (r/d) OF 4.0.

March 2024 Page 27 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

(The designer shall include SS112-1 on the contract drawings).

4) Mechanically Stabilized Earth (MSE) System (RSS) (where applicable)

APPLICATION: (To be completed according to MTO RSS guidelines)

PERFORMANCE: (To be completed according to MTO RSS guidelines)

APPEARANCE: (To be completed according to MTO RSS guidelines)

5) Construction Notes

(Notes as applicable, see list under Section 2.6.7(d) below)

b. General Arrangement Drawings Concrete Rigid Frames and Integral


Abutments

1) SPECIFIED 28-DAY COMPRESSIVE STRENGTH


30 MPa

2) CLEAR COVER TO REINFORCING STEEL

FOOTINGS 100 ± 25
DECK TOP 70 ± 20
BOTTOM 50 ± 10 (if deck slab <300, then 40mm +/-
10mm)

PIER COLUMNS, SHAFTS AND CAPS 70 ± 10

REMAINDER 70 ± 20 UNLESS OTHERWISE NOTED

3) REINFORCING STEEL

Same as Notes for Slab-on-Girder Bridge (Section 2.6.7(a).3).

4) MECHANICALLY STABILIZED EARTH (MSE) SYSTEM (RSS) (where applicable)

Same as Notes for Slab-on-Girder Bridge (Section 2.6.7(a).4).

5) CONSTRUCTION NOTES

BACKFILL SHALL NOT BE PLACED BEHIND THE ABUTMENTS UNTIL THE DECK
SLAB IS IN PLACE AND HAS REACHED 70% OF ITS DESIGN STRENGTH.

(See Section 11.1.1 of this Manual for Exception)

BACKFILL SHALL BE PLACED SIMULTANEOUSLY BEHIND BOTH ABUTMENTS


KEEPING THE HEIGHT OF THE BACKFILL APPROXIMATELY THE SAME. AT NO
TIME SHALL THE DIFFERENCE IN ELEVATION BE GREATER THAN 500 mm.

March 2024 Page 28 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

(See Section 11.1.1 of this Manual for note to be used for special site access
conditions)

CONSTRUCT ABUTMENTS AND WINGWALLS TO THE BEARING SEAT


ELEVATIONS. THE CONTRACTOR SHALL SUPPLY TEMPORARY LATERAL
BRACING FOR THE ABUTMENTS. FORMWORK AND LATERAL BRACING SHALL
NOT BE REMOVED UNTIL CONCRETE HAS REACHED 70% OF ITS SPECIFIED
28-DAY STRENGTH.

(Other notes as applicable, see list under Section 2.6.7(d) below).

c. General Arrangement Drawings Cast-In-Place Post Tensioned Concrete


Bridges

1) SPECIFIED 28-DAY COMPRESSIVE STRENGTH

DECK & SIDEWALKS 35 MPa

REMAINDER 30 MPa

2) CLEAR COVER TO REINFORCING STEEL

FOOTINGS 100 ± 25

PIER COLUMNS, SHAFTS AND CAPS 70 ± 10

ROUND VOIDED DECKS

DECK TOP 70 ± 20
BOTTOM, SIDES, WEBS 50 ± 10

REMAINDER 70 ± 20 UNLESS OTHERWISE NOTED

RECTANGULAR VOIDED DECKS

DECK TOP SLAB, TOP 70 ± 20


TOP SLAB, BOT 40 ± 10
BOT SLAB, TOP 40 ± 10
BOT SLAB, BOT 50 ± 10
SIDES, WEBS 60 ± 10

REMAINDER 70 +
_ 20 UNLESS OTHERWISE NOTED

3) REINFORCING STEEL

Same as Notes for Slab-on-Girder Bridge (Section 2.6.7(a).3).

4) MECHANICALLY STABILIZED EARTH (MSE) SYSTEM (RSS) (where applicable)

March 2024 Page 29 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

Same as Notes for Slab-on-Girder Bridge (Section 2.6.7(a).4).

5) CONSTRUCTION NOTES

Notes as applicable, see list under Section 2.6.7(d) below.

d. CONSTRUCTION NOTES (To be used where applicable.)

THE CONTRACTOR SHALL ESTABLISH THE BEARING SEAT ELEVATIONS BY


DEDUCTING THE ACTUAL BEARING THICKNESSES FROM THE TOP OF BEARING
ELEVATIONS. IF THE ACTUAL BEARING THICKNESSES ARE DIFFERENT FROM
THOSE GIVEN WITH THE BEARING DESIGN DATA, THE CONTRACTOR SHALL
ADJUST THE REINFORCING STEEL TO SUIT.

(In addition to the preceding note, the following shall be shown on the drawing where top
of bearing elevations are shown: Top of bearing elevations shall be denoted with an
asterisk (*), and add note,) " * SEE CONSTRUCTION NOTES ON DRAWING 1 ".

THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS, DETAILS AND ELEVATIONS


OF THE EXISTING STRUCTURE THAT ARE RELEVANT TO THE WORK SHOWN ON
THE DRAWINGS PRIOR TO COMMENCEMENT OF THE WORK. ANY
DISCREPANCIES SHALL BE REPORTED TO THE CONTRACT ADMINISTRATOR AND
THE PROPOSED ADJUSTMENT OF THE WORK REQUIRED TO MATCH THE
EXISTING STRUCTURE SHALL BE SUBMITTED FOR APPROVAL.

(use for the rehabilitation of structures).

SIDES OF FOOTINGS TO BE CAST AGAINST UNDISTURBED SOIL.

(use when factored horizontal forces exceed factored sliding resistance at the bottom of
footing).

SHEET PILING INDICATED ON THE CONTRACT IS REQUIRED AS A PERMANENT


PART OF THE STRUCTURE. IT IS NOT INTENDED TO REPRESENT A COMPLETE
SHORING SCHEME.

(use when sheet piling is indicated on the contract.)

CONCRETE BARRIER WALLS ON RETAINING WALLS SHALL NOT BE CAST UNTIL


THE RETAINING WALL BACKFILL HAS BEEN COMPLETED.

COMPACTED FILL, MAXIMUM GRAIN SIZE 50 mm SHALL BE PLACED UP TO THE


BOTTOM OF FOOTING ELEVATION PRIOR TO DRIVING PILES (see Section 2.3.3, 50
mm is for tube piles).

EXISTING ROADBED IN AREAS THROUGH WHICH PILES MUST PENETRATE TO BE


REMOVED BEFORE PLACING FILL.

IF THE DEPTH OF BLOCKOUT FOR THE SELECTED MODULAR JOINT IS

March 2024 Page 30 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

DIFFERENT FROM THAT GIVEN ON THE MODULAR EXPANSION JOINT ASSEMBLY


DRAWINGS, THE CONTRACTOR SHALL ADJUST THE DEPTH OF BLOCKOUT AND
THE REINFORCING STEEL TO SUIT THE SELECTED MODULAR JOINT.

e. (For structural plate corrugated steel structures only. Only standard metric
material may be used).

STRUCTURAL PLATE CORRUGATED STEEL PIPE SHALL CONFORM TO CSA G401,


EXCEPT THAT THE ZINC COATING MASS (TOTAL ON BOTH SIDES) SHALL BE NOT
LESS THAN 915 g/m2 WHEN TESTED BY THE TRIPLE SPOT TEST (TST). NOMINAL
BASE METAL THICKNESS (give) mm. LONGITUDINAL SEAM BOLT SPACING (give
number) PER CORRUGATION.

PRIOR TO ALLOWING HEAVY CONSTRUCTION EQUIPMENT OVER THE


STRUCTURE, THE DEPTH OF COMPACTED COVER MATERIAL SHALL BE NOT
LESS THAN (give depth).

f. STRUCTURAL STEEL NOTES

See Section 8.7.

g. PRE-TENSIONED GIRDER NOTES

See Section 7.2.9.

h. POST TENSIONED DECK NOTES

See Section 7.3.8.

i. PRESERVATIVE TREATED WOOD STRUCTURE NOTES

See Section 15.4.

j. MISCELLANEOUS

1. No instruction or note on the drawings shall imply that there is more than one
contractor. For example, reference must be to "THE CONTRACTOR" only and not to
"THE STRUCTURAL STEEL CONTRACTOR".

2. For temperatures, only the Celsius scale shall be used. Temperatures shall be shown
thus: 23°C, 0°C, 10°C, etc.

2.6.7 Contract Drawing Border

All structural drawings shall use the master drawing border for which a reduced scale
hardcopy is shown in Figure 2.6.1. Line thicknesses and text sizes given are specified to
ensure legibility after drawing reduction. A "thin" line shall be as thin as can be depended
upon to print clearly after 1/2 size reduction. This width is between 0.2 and 0.3 mm. A
"medium" line width is between 0.35 and 0.5 mm and a "thick" line shall have a width

March 2024 Page 31 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

between 0.6 and 0.7 mm. Text need be used in only three sizes: large 4 to 4.5 mm high,
medium 3 to 3.5 mm, and small 2.5 mm. Vertical, uppercase, Roman Simplex text font
is preferred. Text within the upper title block shall be 3.5 mm high. All drawings shall be
identified as Metric.

Upper Title Block

The Ontario Ministry of Transportation logo shall be present at the top of the title block. If
desired when a design is completed by a consultant, the design engineering firm’s name
and logo may be added at the bottom of the upper title block, not larger than 20 mm tall.

The name of the structure (see Section 2.6.10) and the W.P. number shall be as given in
the structural design report. For clarification in the use of some terms, such as, underpass,
overpass, subway and overhead, see Figure 2.6.2 and Figure 2.6.3.

The Contract number and the sheet numbers are required to be shown when they become
known, which may be close to the time of tendering.

The standard north point, pointing true north, shall be shown on the general arrangement
drawing upper title block and on other drawings which contain a plan view.

The drawing title shall be as given in Section 2.6.2.

The highway number is not required in the title block but shall appear on the plan.

FIGURE 2.6.1 – MASTER DRAWING BORDER

March 2024 Page 32 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

Revision Block

All revisions, after tender prints have been prepared, must be identified by a number
placed in a hexagon. In the "Revision" column, the same symbol shall be used. The date,
initials of the drafter making the changes and a short description of the nature of the
revision shall also be given. See Section 2.6.15 for more details.

Lower Title Block

All information shall be filled as indicated below and illustrated on Figure 2.6.1.

DESIGN Initials of actual designer for the work depicted on the drawing. For the
general arrangement drawing the initials shall indicate general
responsibility for the preliminary design, and not that complete design
computations have been carried out. The designation of professional
responsibility is made by the application of an engineer’s seal
performing or overseeing the work.
CHK Initials of actual design checker who checked the design, for the work
(DESIGN) depicted on the drawing.
CODE Name of design code used in design. For current MTO projects this is
the Canadian Highway Bridge Design Code (CHBDC) and shall be
designated as CSA-S6-19. For railway structures this may be
American Railway Engineering & Maintenance of Way Association
Manual for Railway Engineering (AREMA).
LOAD Loading used in design specified in the applicable code above. For
new MTO highway structures this will be CL-625-ONT. Railway
loading may be according to AREMA and rehabilitations as per
Sections 14 and 15 of the Canadian Highway Bridge Design Code.
DATE The month and year when final drawings were completed and
submitted to the Structural Section, or to Planning and Design.
DRAWN Initials of drafter or technician who produced the drawing.
CHK Initials of checker with responsibility for checking accuracy,
(DRAWN) dimensions, geometry, etc. of the drawing.
SITE Add site number as per Section 2.6.11.
DWG Add drawing number as per Section 2.6.1.

2.6.8 General Arrangement Drawings Content and Format

The following instructions are not exhaustive and are intended only to provide guidance in
the preparation and checking of general arrangement drawings. A general arrangement
drawing shall appear as the first drawing for work on any structure.

Key Plan

A key plan is not required on the general arrangement if it is to appear on the soils drawing

March 2024 Page 33 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

or elsewhere on a drawing that will remain on the structural file and appear in the contract
documents.

If a key plan is required, it shall normally be to a scale of 1:50 000, not smaller than 100
mm x 100 mm and not larger than 150 mm x 150 mm and appear just to the left of or
below the title block (top right-hand corner). The structure site shall be clearly indicated,
and the plan shall be oriented with north to the top and a north point shown. If a place
shown on the Ontario Road map does not occur within the key plan, notes shall be added
indicating the direction and distance of two such places along routes appearing on the key
plan. If this is not practicable, a smaller scale plan shall be considered.

The key plan shall show only major roads, railroads, rivers, lakes, and towns. The roads
shall be shown in thick single lines, railroads thus +++++++++++++, lakes and rivers in
thin "shaky" lines. Double parallel lines shall be avoided unless, for example, a river is of
great width. The title of "Key Plan" shall appear below the plan in large text with a scale
in small text that is also given as a graduated line. A medium line border shall surround
the plan itself with a thick line border around plan, title, and scale.

Plan

The plan, located at the top and left portion of the drawing, shall be to a scale of 1:200
unless the size of the structure precludes this, in which case scales of 1:250, 1:500, 1:750,
1:1000, 1:1250 shall be considered to obtain the largest plan possible within the space
limits of the master drawing border.

The plan shall be oriented with the upper roadway direction as nearly horizontal as
possible and with the chainage increasing from left to right, if this can be arranged. A
construction north arrow, rotated up to 45o from true north, may also be shown on the plan
and marked "North for Construction", but this shall be done only if the various parts of the
structure could not otherwise be unambiguously named.

North arrows that point downwards are very undesirable and shall not occur normally
because chainages throughout the province are supposed to increase from west to east
and from south to north. If it is found that the north point points downwards, the problem
shall be discussed with Project Delivery Section to find out if the chainage direction was
correctly determined and to ensure consistency between the road and bridge drawings.

Existing contours shall always be shown, dashed (or dotted) if and where new work will
change them and solid if not. If final contours are available or are specifically requested,
these shall be shown, using short-dashed lines in this case for all existing contours.
Contours normally are required at 1 m intervals, but larger intervals may be used for steep
surfaces. Lines used shall be thin, except that 5 m interval contours may be of medium
thickness.

On the plan, the following are required:

a) Creek water edges in thick lines, consistent with the given water level and ground
contours; direction of flow; name of creek in large text written along the creek and to
be read from the right-hand side of the drawing.

March 2024 Page 34 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

b) All centre lines and control lines, pier centre lines and abutment bearing centre lines
in thin centre lines.

c) Edges of pavement, except on a bridge deck where no physical demarcation other


than painted lines will exist; curbs and copings; approach slabs; deck-ballast wall
joints; top and bottom of slopes; shoulder edges, retaining wall, pier and wingwall
stems, when not hidden, and drainage openings shall be shown in lines of medium
thickness. Railings shall not be shown.

Hidden work such as pier or column shafts, abutment faces and grading details under the
structure shall be shown in thin dashed lines. Footing outlines shall be shown to indicate
proximity to pavements, tracks, creeks, etc., but shall not be shown for abutments that are
remote from such features. Services likely to affect or be affected by construction shall
be indicated with centre lines and a description that includes the words "existing" or
"proposed".

Unless a careful study of the structure by the project Engineer has indicated that none is
required, the position and length of roadway or track protection shall be shown in medium
double lines with the words "Track Protection" or "Roadway Protection" in small text. If it
is necessary to show Traffic Protection, centre lines of medium thickness shall be used.

Dimensions for roadway widths, spans, final horizontal clearances, wingwall lengths,
extent of rock protection, etc., shall be shown using thin lines and small text. If the overall
length of the bridge cannot be clearly shown on the Elevation, it shall be shown on the
Plan.

A plan title shall be shown in large text and the scale in small text. The direction and
location of the cross-section plane and the direction of the elevation projection shall be
shown by triangular symbols on the plan.

Working points, at the intersection of all centre or control lines and pier or abutment
bearing centre lines shall be shown and labelled WP #1, WP #2, etc; names shall be
written along all centre or control lines and the skew angle should be given, all in small
text. In small text also, give stations, slopes, at least one top of pavement elevation at
some well-defined central point, and control line geometry, e.g., degree of curvature,
azimuth, etc. If coordinates are available or obtainable, they shall be shown for TC's,
SC's, PI's, etc., on the general arrangement drawing, and for WP's, on the foundation
layout. In any case, they shall be shown together with stations. These coordinates may
be tabulated separately to avoid congestion on the Plan.

On the approach slab the following note should appear "6000 mm approach slab with 90
mm asphalt and waterproofing". This note shall be shown with a dimension line showing
the 6000 mm dimension. The "6000 mm" shall appear above the dimension line and the
remainder of the note below it.

Elevation

The elevation shall be immediately below the plan, located as if projected from it, and to
the same scale. Normally the view is obtained as if by projecting the elevation parallel to

March 2024 Page 35 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

pier centre lines or abutment faces onto a plane through the face of the bridge that is at
the bottom of the plan, and then projecting vertically downwards to the location of the
elevation. The ground lines shown therefore, shall be at the near bridge face and skew
effects do not appear.

The outline appearing on the elevation, in lines of medium thickness, shall include barriers,
an indication of railings, coping, soffit, and parts of piers, abutment faces and wingwalls
that are above ground, final ground line, and preliminary grading lines (see Section 2.3.3).
Hidden detail lines, thin and dashed, shall show footings, piles, and other parts of piers
and abutments that are buried.

A thin long-dashed line shall show the existing ground line. Do not show centre lines of
piers and abutment bearings unless essential for a particular purpose. Dimension the
overall length of the bridge, generally the total barrier wall length, the thickness of any pier
shafts, and both the required and the actual minimum vertical clearances under the
structure, with the location of the critical point indicated. Sometimes it is not possible to
indicate this location clearly on the elevation and an indication also has to be given on the
plan. Use a leader pointing to a circle with 45° cross. Print in small text footing top
elevations, water levels, (see Section 2.6.4) an approximate lower pavement level, bearing
types ("exp" or "fixed"), existing ground line designation, minimum soffit elevation for water
crossings, railing type, railing anchorage required, rock protection or slope paving notes,
and such other notes as are necessary. Note that elevations shall always be given to the
top of footings and never to the bottom. If it is necessary to define the bottom of footing
level, give the top elevation and dimension the footing depth.

A triangular numbered symbol (optional elevation title) followed by the scale shall show,
by reference to the corresponding symbol on the plan, where and in what direction the
view is taken.

Cross-Section

The cross-section shall be located to the right of the Plan but may be placed elsewhere if
the Plan extends across the width of the sheet. The scale shall be 1:100 if possible. One
cross-section is generally sufficient. If the cross-section varies in some way, this may be
shown by giving more than one value to a dimension or taking half of the section at one
point and half at another. Such a split shall be clearly shown on the plan in association
with the triangular symbol and a plane of section line. If dimensions are given showing
"varies," limits shall be given.

The cross-section should show the outline of the deck together with barrier walls, railing,
wearing surface, exterior beams (others may be shown by beam centre lines), pier cap,
pier shaft or columns, typical drainage outlet if any, and utilities.

Centre lines and control lines shall be thin lines and shall be labelled with small text.

Dimensions shall be given showing overall cross-section width, distances between centre
lines, curb or median widths, barrier wall face to outer deck edge width, slab thickness,
pier shaft width or column diameter and the lane and shoulder widths even if there is no
physical demarcation between them. Beam spacing shall be covered by a note stating

March 2024 Page 36 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

the number, type and spacing of the beams.

The following note shall be given, where applicable, with an arrow pointing to the wearing
surface:

"ASPHALT AND WATERPROOFING SYSTEM, 90 mm TOTAL".

No title shall be used, but a triangular symbol, numbered to agree with the one showing
the section plane on the plan. This shall appear beneath the Cross-Section, followed by
the scale in small text. The direction of the cross-section shall be indicated also by
labelling the sides of the bridge "East", "North", etc., in medium text. This is unnecessary
if the section is symmetrical. Notes in small text shall be added to show crossfall, wearing
surface, number, size and type of ducts, etc. The section shall be taken looking in the
direction of increasing chainage.

Crossfall and super-elevation are normally stated as a percentage, for example, 2%.
Slopes for embankment slopes, curb side, backslopes and concrete slope paving shall be
given by a numerical ratio X:Y, where X is the horizontal dimension and Y is the vertical
dimension of a right-angle triangle, the hypotenuse of which parallels the slope, for
example 2H:1V. The use of a symbol as shown in the following example is preferable:

Bench Mark

In the lower left corner of the drawing, give in medium text, the elevation of the benchmark
to be used, e.g., BM 217.565 and below it in small text, the datum and description of the
bench mark given on the E Plan (Bridge Site Plan).

General Notes

In a column about 150 mm wide below the title block and under the title "General Notes"
in large text, give the notes in small text as specified elsewhere (See Section 2.6.7). These
include Construction Notes.

List of Drawings

Below, or if necessary, to the left of the general notes, list vertically the number and title
of all drawings forming part of the structural contract documents (see Section 2.6.2). This
may include embedded work drawings. For reference to SSD, OPSD and MTOD, see
Section 2.6.13.

Profiles

To the left of the general notes, show diagrammatically the profiles of all roadways,
railroads and if available, new channel beds. Roadway profiles should be given only to
top of pavement. The profile line should be a medium line. In thin lines, show tangent
extensions and PI's. The location and length of the structure should be shown on the
profile where appropriate. A title in large text is required below each profile giving the

March 2024 Page 37 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

name of the profile, under which "N.T.S." should appear in small text. At each end of each
profile, print in medium text, "North", "East", etc. The location of the profile (e.g.,
"COUNTY RD. 10") should be shown in medium text.

In small text, give PI elevations and stations, curve visibility and length and grades.
Directions (e.g., "To Beaverton") at each end of the profiles are helpful and shall be given
especially if the compass directions could be misinterpreted.

Miscellaneous

When road, rail or water traffic is permitted under the structure during construction,
construction clearances shall be shown and unless these can be clearly specified by a
single dimension on the elevation, a separate diagram is necessary. If the clearances are
standard, OPSD 3390.150 can be referenced. A separate final clearance diagram is
always required for a railway opening and this shall show construction clearances if these
are less than final clearances.

Non-standard backfill requirements shall be shown as specified in Section 5.2.1.2.

Functions of skew angles shall not be given.

Hatching shall be used where required to show a specific material (asphalt, etc.) or
differences in materials (concrete, steel, etc.). In rehabilitation projects, hatching is used
to indicate areas to be removed.

The signed P.Eng. stamps of the designer and checker shall appear to the left of the
revision block (bottom right-side corner). P.Eng. stamps shall always be signed and
dated.

Preliminary Version of the General Arrangement

The preliminary version shall be the same in content and format as the general
arrangement. On the preliminary version however, it is not necessary to show a drawing
list, and the drawing number shall be "P1" rather than 1. The title shall be "General
Arrangement".

The "Design/Check" initial block need not be completed at this stage, but the
"Drawn/Check" block must be. A P.Eng. stamp is not required.

The profile shown on the preliminary version of the general arrangement drawing may in
some cases be a proposal by the designer, necessary because of insufficient or excess
clearance. If so, this shall be clearly noted, and some assurance that it is feasible shall
be obtained by telephone before issuing the preliminary version. The note shall not
appear on the final drawing.

2.6.9 Use of Word "MINIMUM" on Drawings

There is a possibility of a contractor taking advantage when the word "minimum" is used
to specify the depth of footing or the depth to which a footing is to be recessed into rock.

March 2024 Page 38 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

When the word "minimum" is used in such a manner, the Ministry may be obliged to pay
for unnecessary over excavation and additional concrete.

The word "minimum" shall not be used in such cases. The required depth of footing and
the required recess into rock should be shown (see Section 4.2.2). The word "minimum"
shall not be used to specify the strength of concrete, as it results in a conflict with the
strength requirements in OPSS 1350. Concrete shall be specified by metric Specified 28-
day Compressive Strength (see Section 2.4.1).

2.6.10 Construction Staging and Sequence

When the bridge is constructed in two or more stages, a construction staging drawing shall
be included in the contract drawings which includes a typical section in each stage, along
with a list of the work to be done in each stage.

When tasks within a construction stage are provided, the words “suggested” or “proposed”
shall not be used in notes on drawings.

For new bridges, a construction sequence shall not be provided unless required by Clause
1.4.4.3 of CHBDC.

2.6.11 Site Numbers

Every structure owned by the Ministry, or located within the Ministry’s right-of-way, is
identified by an alphanumeric structure identifier which is commonly known as the “site
number”.

Based on the descriptions below, the following highway structures shall receive a site
number:

1) Bridge, with span 3m or larger.

2) Culverts (buried structures), defined as follows:


a) all culverts with spans 3m and greater, or
b) all multi-cell and adjacent culverts, separated by not more than the span of the
smallest culvert, with individual span greater than 2 m, or
c) all other culverts of importance that are managed by the Regional Structural
Sections.

3) Tunnels, with a minimum length of 90 m (<90m may be categorized as a bridge or


culvert). Tunnels are typically constructed below water level or through soil, used to
convey pedestrian, highway or railway traffic, and is usually incorporated with some
other design considerations (e.g., special lighting, ventilation, fire protection systems
or emergency egress measures).

4) Retaining Walls:
a) with exposed wall height greater than 2 metres, or
b) within 2 times the wall height from a travelled lane, or
c) whose failure would cause significant adverse effects (e.g., a wall near utilities,

March 2024 Page 39 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

or wall near limit of MTO property, or wall retaining superimposed surcharge


loads).

Retaining walls are deemed to be Standalone by:


i) being built away from (not immediately adjacent to) a structure (bridge, culvert,
etc.), or
ii) being built immediately adjacent to a structure, but exceedingly longer than
typical – in which case a construction joint, different year of construction,
different material, or other convenient point – is used to differentiate the portion
of wall associated with the bridge from the standalone wall.

By extension, they are not deemed Standalone if they are reasonably short and
can be inspected and/or rehabbed easily with the structure, as a result simply
become an element of the bridge, culvert, etc. (see also, Figure 2.6.2).

5) Ferry Docks, used to convey passengers and motor vehicles encompassing docks,
piers, wharfs, ramp and other accessories.

6) Sign Support Structures that extend over the roadway, including overhead span,
cantilever, bridge mounted and pole mounted types as well as tolling gantries.

Once a site number is assigned to a structure, the site should retain this number even
after the structure has been modified or replaced with the exception of its 3rd segment (i.e.,
it’s suffix). For example, in situations where a bridge changes to a culvert, or vice versa,
the 3rd segment would change to suit the type of structure and similarly, in situations where
a bridge becomes twinned or part of a core/collector system by the addition of structure(s),
the 3rd segment shall be modified to follow Figure 2.6.3. Where twin structures are
merged, they should change their previous “/1” and “/2” numbering and become “/0”;
unless there are unusual circumstances that benefit the management of the structure.

In preparing contract documents for new bridges, a bridge replacement or bridge


rehabilitation, such that the existing site number was removed, MTOD 3941.210 should
be used to have the site number cast back on the bridge. The MTOD also includes a year
of construction – which shall be the year of superstructure construction, not the year a
particular less extensive rehabilitation is being done (i.e., barrier wall and patch,
waterproof and pave).

The following precise format for site numbering was established in May 2018 and is
required for managing all assets digitally. The site number is composed of 9 alphanumeric
characters with no spaces in-between. The site number is divided into three segments by
the symbols “-“ and “/”:

1st segment 2nd segment 3rd segment

- /

March 2024 Page 40 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

1st Segment:

The first two boxes are used to identify the county, based on the counties in existence in
the 1960’s when the county numbering system was first developed. For a single digit
number, a leading zero is required. The last box is used for the county code. For counties
38, 39, 41 or 48 in the large northern regions, county code can be equal to N, S, E, W or
C. For all other counties, county code is X.

03X Carleton 37X York 39E Cochrane 48C Thunder Bay

2nd Segment:

These four boxes are used to give a unique identifier for each structure within a given
county, using a number from 0000 to 9999. If the site number is less than 4 digits, leading
zeroes are required to fill all the boxes.

Note: Do not duplicate the 2nd segment number for different structure types (i.e., a bridge
with a Stand-Alone retaining wall etc.) with the exception of bridge mounted signs.

03X-0225 37X-1206 39E-0201 48C-0087

3rd Segment:

The first character is used to identify the type of structure.

B - Bridge (except ferry dock bridges) 39E-0201/B0


C - Culvert 21X-0495/C0
T - Tunnel 06X-0709/T0
W - Retaining wall 24X-0792/W0
F - Ferry dock structure 17X-0223/F0
S - Overhead sign support structure 33X-0406/S0

The second character is used:

a) For bridges culverts and tunnels, as the traffic stream (e.g., direction NB) and facility
(e.g., Core, Collector, etc.), identifier is as follows:

When there is only one structure at the site – Note: Multi-cell culverts, as
0
described above, are considered one structure.

Note: Typically, a single structure always receives a single number (e.g., “/B0”, “/C0”).

However, CR has situations where they have treated a single freeway bridge as separate
structures (i.e., B1, B2, B3, etc.) as shown below based on travel streams on the bridge.
This typically occurs on an overpass or river crossing structure which is sufficiently wide
(e.g., a rigid frame or culvert) and carries several travels streams (e.g., core and collector)
or directions.

March 2024 Page 41 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

This unusual practice is intended to be limited to the Greater Toronto Area where core
and collectors exist. All other typical overpass and underpass structures that do not carry
‘core + collector’ should generally not be divided into multiple site numbers, since these
structures can be inspected and rehabbed as one structure.

When there is more than one structure at the same site location:

NB or EB lanes in twin structures or


1
NB or EB collector lanes of core/collector system
For:
- bridge carrying SB or WB lanes in twin structures or
2
- culvert under SB or WB collector lanes of core/collector system
3 - tunnel carrying NB or EB core lanes of core/collector system
4 SB or WB core lanes of core/collector system
For other structures (e.g., ramps) at the same site. A sequential number is
5, 6 etc.
assigned to each structure. See example below in Figure 2.6.3.
Note: For sites on highways that change directions at times the site numbers should
be created according to the predominant direction of the highway (Ex. 401 is
East/West, QEW is North/South).

b) For Overhead Sign support structures, as the sign number at the site, which is as
follows:

For all sign support structures except bridge mounted supports and tolling
0
gantries
For bridge mounted sign supports on the same bridge site, sequential numbers
are assigned. The same 1st and 2nd segments as the bridge should be used.
See example.
1,2 etc.
For tolling gantries, which are always found in pairs, assign 1 to the first structure
and 2 to the second structure based on the direction of traffic.

See Figure 2.6.3.

c) For standalone Retaining walls, as the wall number, which is as follows:

0 For a standalone retaining wall.


1,2 etc. In virtually all cases, “0” is used, but other sequential numbers may be used
for unique situations.
Note: Retaining walls, either RSS (MSE) or concrete walls, that are associated with
the structure should be entered as an Element within the structure, and a separate
Site Number is not required.

March 2024 Page 42 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

FIGURE 2.6.2 – STRUCTURE IDENTIFICATION OF MSE WALLS

FIGURE 2.6.3 – SITE NUMBERS FOR BRIDGES AND SIGN SUPPORTS

2.6.12 Structure Name

The structure name appears in the Structural Design Report and is typically assigned
based on the following:

1. The bridge shall be identified in relation to the highway it is on, and where highways
are concurrent, the more major highway taken using the following order, QEW, then
the 400 series highways, numerically starting from 400, then other highways
numerically starting with highway 2.

2. The major obstacle being crossed appears in the bridge name,

a. when multiple obstacles are being spanned, the most significant obstacle
name is provided; with the most significant obstacles being bodies of water,
then railways, then roads.

March 2024 Page 43 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

b. Where the body of water is small, and/or the roads are major, the order may
be altered. An additional obstacle being crossed may be added to the bridge
name when multiple significant obstacles are crossed.

c. Where twin bridges exist, the highway direction (and Express and Collector
Lanes) shall be included in the name - See Figure 2.6.3.

d. Where the same obstacle is crossed multiple times, a geographic location may
be added for clarity (i.e., south crossing, at Hearst, etc.).

e. A complex interchange shall contain the bridge number.

3. The next part of the name shall be whether the major crossing is passing over or under
the obstacle, using the terminology from Figure 2.6.4.

a. When crossing water, “Bridge” shall be added and “Overpass” is not required,
while for roadway crossing, “Bridge” is not required, and “Overpass” or
“Underpass” is required.

b. Abbreviations U/P, O/P, O/H maybe be used.

4. Where required for clarity, the highway number may be added at the end of the bridge
name.

5. Interchange should be added to the name when applicable, which may be abbreviated
as I/C.

6. When approved by the Assistant Deputy Minister (ADM) of Transportation


Infrastructure Division (TIMD), or when pre-existing, the bridge may be named after a
person.

a. The name description in #2 shall become the secondary name, unless short
enough to fit in the primary name.

b. For bridges named for fallen officers, this shall appear as a secondary name.

c. The secondary name may be added to the title block, when space permits.

7. The bridge name is not legally binding and may be changed if the highway or waterway
changes names. The former name may be retained as the secondary name.

Some examples of bridge names are shown in below:


Primary Name Secondary Name
Keele Street U/P (I/C on Hwy. 401)
Glendale Ave. NBL O/P (I/C) (on Hwy. 406)
Etobicoke Creek Bridge WBL Express (Hwy. 401)
Hwy. 40 O/P (on Hwy. 401) Sgt. Margaret Eve Bridge

March 2024 Page 44 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

CNR O/H @ East of Rossport (on Hwy. 17)


Sgt. Aubrey Cosens V.C. Memorial Bridge Montreal River Bridge @
Latchford (on Hwy. 11)
Trout River Bridge (on Hwy. 11/17)
Jones Creek Culvert East Crossing (on Hwy. 15)
McLean Young Bridge over Penetangore River (on
Hwy. 21)
Hwy. 400/401 I/C Bridge #5 401 W.B. RAMP TO 400S.B.
CNR Subway @ Pickering (on Hwy. 401)
Welland River/CPR Bridge (on QEW)
Magnetawan River/Hwy. 520 Bridge (on Hwy. 11).
Still River/Hwy. 526/CPR Bridge (on Hwy. 69)

Sign supports shall be named as per the Ontario Sign Support Inspection Manual.
Retaining walls shall be named after the highway they are associated with, the nearest
road or feature, and the ordinal or quadrant (e.g., N, S, NE, etc.) they are located in.

FIGURE 2.6.4 – UNDERPASS, OVERPASS, SUBWAY AND OVERHEAD BRIDGES

2.6.13 Small Size Standard Drawings

For inclusion with contract drawings, small size drawings bearing an SS number shall be
added to a full-size standard drawing sheet as per Section 1.5.1 of this manual.

The title block of the full-size drawing shall be completed. The title should be "Standard
Details I" or II, (etc.). Initials are required as per Section 1.5.2 of this manual.

March 2024 Page 45 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

2.6.14 Referencing Standards on Structural Drawings

OPSD and/or MTOD only, shall be listed on the particular drawing showing the details to
which they apply. The number and title of the standard shall be listed just above the
revision block under the heading "Applicable Standard Drawings".

If there is any ambiguity as to a standard's application, reference to the standard drawing


shall also be made in close proximity to the affected detail.

2.6.15 Drafting Scales

For Structural drawings, the following scales are acceptable:

• 1:20, 1:25, 1:50, 1:75, 1:100, and 1:125.

The scales above are widely used in other highway design work and are preferred. The
recommended range of scales may be extended, provided that the required scale is
derived from a recommended scale by multiplying by whole number powers of 10 (e.g.,
1:2, 1:20, 1:200). Scales with decimal number denominators are not acceptable such as
1:12.5.

In addition, the following intermediate scales may be used to avoid detail views on
excessively large or small drawings. They may only be used in such cases.

• 1:30, 1:40, 1:60, 1:150, and 1:250.

2.6.16 Revisions to Drawings

The following procedure shall be followed in making revisions to drawings for all
structures, including culverts and sign supports.

a. For all Structures not Requiring Railway or CNWA Approval

1) Revisions Prior to Submitting Contract Package for Tendering


- Revisions generally may be made freely
- Revisions shall be conveyed to Structural Section and Project Manager to ensure
implications to the broader project are understood.

2) Revisions During Tendering Period, but Prior to Award


- Sheet number shall have a letter to designate the revision number (i.e., Sheet 22A,
22B, etc.).
- General description of revisions added to revision block.
- Actual revision on drawings shall be issued with an addendum and may be
highlighted with revision cloud as directed by Project Manager or Contract
Management Office.
- Must allow for at least 10 business days for most contracts before tender close, or
tender close must be extended. Details shall be obtained from Project Manager or
Contract Management Office as some larger contracts require a longer time.
- Drawings shall be sealed in the same manner as drawings prepared for tender.

March 2024 Page 46 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 2 - GENERAL DESIGN AND DRAFTING

3) Revisions to Contract Package after Award

- Sheet number shall have a letter to designate the revision number (i.e., Sheet 22A,
22B, etc.).
- General description of revisions added to revision block.
- Actual revision on drawings shall be highlighted with revision cloud.
- As-built drawings should include all changes, revisions from the tendered package
after completion of the contract.
- Drawings shall be sealed in the same manner as drawings prepared for tender.

b. For all Railway Overheads and Subways, and Structures Subject to the
CNWA

1) Before the First Submission to the Appropriate Authority for Approval

The procedures for the revisions outlined in section (a), paragraph 1 applies.

2) After the First Submission to the Appropriate Authority for Approval/Record

The procedures for revisions outlined in section (a), paragraph 3 applies, when
changes affect the design requirements such as clearances, etc. affecting the
authority.

March 2024 Page 47 of 47 SM-D2-S02


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

3 DEEP FOUNDATIONS ......................................................................................... 2


3.1 General ........................................................................................................................ 2
3.1.1 Design Criteria ...................................................................................................... 2
3.2 Driven Piles .................................................................................................................. 3
3.2.1 Design .................................................................................................................. 3
3.2.2 Pile Materials ........................................................................................................ 5
3.2.3 Drawings............................................................................................................... 7
3.3 Drilled Shafts...............................................................................................................12
3.3.1 Design .................................................................................................................12
3.3.2 Materials ..............................................................................................................14
3.3.3 Drawings..............................................................................................................14
3.4 Pile Caps.....................................................................................................................14

March 2024 Page 1 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

3 DEEP FOUNDATIONS

3.1 General

Deep foundations achieve the required foundation capacity by transferring the


superstructure loads to deeper layers of soil, which are either more competent than the
top layers or soil or less susceptible to erosion. They can generally be divided into two
installation methods; driven piles and drilled shafts.

3.1.1 Design Criteria

Prior to the initiation of the foundation engineering investigation, the structural Engineer
shall provide the geotechnical Engineer with a conceptual layout of the proposed structure
foundations.

The subsequent Foundation Investigation and Design Report (FIDR) produced by the
geotechnical Engineer shall contain information and recommendations with respect to
deep foundations. When deep foundations are selected, the final design shall be
developed through consultation between the structural Engineer and the geotechnical
Engineer.

In the Foundation Investigation and Design Report, the geotechnical Engineer shall
provide recommendations for:

i) Type of foundations, e.g., spread footing, driven piles, drilled shafts, etc.;

ii) Axial and horizontal resistances for a single pile with the provision that these values
may require modifications to account for the pile group effect once a proposed pile
layout is known. They shall be given as follows:

• Factored axial and horizontal resistances at ULS where the resistances are based
on the geotechnical resistance of the piles.

(N.B. Factored geotechnical resistance at ULS = Ultimate geotechnical resistance


x resistance factor);

• Axial and horizontal resistances at SLS for identified settlements or displacements


and corresponding subgrade reactions. Where deformations of piles are larger
than 15 mm, including integral abutments or foundations elements that provide
lateral resistances under any loading conditions, p-y curves shall be provided. Pile
resistances at SLS should be determined from the consideration of stress/strain
characteristics of the pile and unfactored geotechnical parameters of the soil
appropriate to the conditions of the site.

(N.B. Geotechnical reaction at SLS = Values calculated for specific settlement or


displacement based on stress/strain performance);

iii) Depth to which the pile should be driven;

March 2024 Page 2 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

iv) Requirements for pile tip reinforcement to be used;

v) Any pile driving constraints licence (e.g., noise, driving hours) and obstacles (e.g.,
boulders).

Pile resistances given in the Foundation Investigation and Design Report are based on
the assumption that the piles will be driven into soil that provides full lateral support against
buckling. The structural Engineer may need to modify the resistances, taking into account
the un-supported length of the pile, if piles are driven and left partially exposed or
immersed in water.

Minimum pile length should be kept to 5.0 m. When piles less than 5 m in length are
required for pile foundations, the elastic shortening of the piles is not sufficient to distribute
the loads according to the inertia method and an advanced method of analysis shall be
used. Piled foundations with piles less than 3 m long shall not be used. In such cases,
alternate foundation systems such as spread footings on compacted granular pad
(engineered fill) or on mass concrete should be investigated.

Where pile lateral displacement exceeds 15 mm, p-y curves shall be used in the final
structural design.

3.2 Driven Piles

Driven piles are appropriate for a wide range of subsurface conditions encountered in
Ontario and the resistance may be achieved by end bearing or shaft friction, or a
combination of both. For steel piles which rely on shaft friction to develop their resistance,
the section with the highest surface area to cross-sectional area shall be used unless
driving conditions dictate a larger size of pile.

3.2.1 Design

The designer shall specify the pile tip treatment and embedment of the piles into the pile
cap and shall account for deterioration of the pile over the design service life of the
structure. Steel piles shall be embedded a minimum of 300 mm into the pile cap when
the foundation relies only of the axial resistance of the pile (e.g., a single column supported
on a pile cap with grid of piles, battered to resist horizontal loads), and a minimum of 600
mm where the foundation relies on transfer of bending into the pile (e.g., integral
abutments).

3.2.1.1 Pile Tip Treatment

The following recommendations on pile tip treatment are guidelines only and may be
superseded by the geotechnical Engineer on a project-specific basis:

1) For piles driven to a specified elevation in soft or moderate driving conditions, no pile
tip treatment is required;

2) For piles driven to end bearing on a hard material, through materials presenting only
soft to moderate driving conditions and no obstructions or only minor obstructions,

March 2024 Page 3 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

reinforced flanges per OPSD 3000.100 or OPSD 3001.100 respectively for H-piles or
tube piles are required;

3) For piles driven to end bearing on hard material, through material presenting hard
driving or obstructions such as boulders, bearing points such as the Titus ‘H’ bearing
pile point or APF hard bite, standard model shall be specified;

4) For piles driven to and seated into bedrock (usually where the angle of intersection of
pile and bedrock is less than 60°), Oslo Point rock points, as per OPSD 3000.201 shall
be specified and set into bedrock as detailed in the contract.

3.2.1.2 Corrosion of Steel Piles

The corrosion rate of steel piles embedded in soil is influenced by a number of factors
such as oxygen availability, pH, chloride content, sulphate content, sulphide ion content
and soil moisture content. Measurement of these parameters can give an indication of
the corrosivity of the soil; however, because of the number of factors involved and the
complex nature of their interaction, actual corrosion rates are challenging to estimate.

In general, the corrosion behaviour of steel piles embedded in soil can be divided into two
categories, corrosion in disturbed soil and corrosion in undisturbed soil. A disturbed or
freshly placed soil is defined as a soil in which digging, backfilling or other soil upheaval
has taken place allowing the creation of an oxygen-reach environment. Driven steel piles
generally have the majority of their length in undisturbed soil; however, excavation and
backfilling for footing and pile caps create a region of disturbed soil near the top of the
piles, increasing the availability of oxygen and the opportunity for corrosion.

Although this may not be an issue with piles under axial compression alone, as is the case
with pile groups under piers or typical abutments in bridges with joints, in integral
abutments the piles are under coincident axial compression and bending and the
consequences of section loss due to corrosion become more serious.

In typical integral abutment situations, the upper three metres of the pile is encased in a
corrugated steel pipe which is subsequently filled with uniformly graded loose sand. This
upper part of the pile is in an oxygen rich environment and although the backfill is usually
non-aggressive. After a number of movement cycles, there is a strong probability that
there may be a void between the bottom of the concrete abutment wall and the top of the
sand leaving that part of the pile exposed to oxygen. In addition, the pile at this location
is usually under the maximum coincident axial compression and bending making any
section loss critical.

Consequently, design Engineers shall account for a loss of 1.0 mm steel thickness per
exposed face of steel piles in integral abutments instead of the allowance required by the
CHBDC Clause 2.3.6.11 Steel pile corrosion protection.

Steel piles shall not be used in corrosive ground water. Precast concrete piles may be
used under these conditions, if specified with sulphate resisting cement.

March 2024 Page 4 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

The designer shall not use steel piles that are exposed above ground or above low water
level without approval from the Structural Section. When approved, exposed piles shall
comply with the following criteria:

1) Exposed piles shall have an additional sacrificial steel thickness added based on the
chemical properties of the soil or water in which they are located and be coated, and/or
protected from corrosion by other means, over a length of at least 1000 mm above the
high water level to 600 mm below the low water level or 1000 mm below ground
elevation;

2) When concrete-filled circular steel piles are exposed, they shall have a diameter of not
less than 450 mm.

3.2.1.3 Other Considerations

1) Refer to Section 6 of the CHBDC for minimum pile edge distance, embedment and
spacing.

2) Maximum batter for all piles is 1:3. The geotechnical Engineer must approve
exceptions to this.

3) Pile driving tip reinforcement and rock points are to be used for steel piles only when
specified in the Foundation Investigation and Design Report (see Section 3.2.3.1).

4) Accessibility for pile driving equipment, allowing for batter, and any infringement on
required construction clearances during driving should be considered.

5) The possibility of causing damage to buried utilities by driving piles must always be
considered. Generally, if there are utilities within 3 m of piles measured at the
elevation of the utility, the piles should be pre-augured to an elevation below the
elevation of the utility.

3.2.2 Pile Materials

Steel piles are typically used with CSA G40.20/G21 350W and ASTM A572 grade. The
ministry has recently used for higher grade H-piles in various projects and ASTM A913
450 grade is readily available for some common sections. When considering the use of
high grade of H-piles, the designer should check the availability of sections in Ontario.

3.2.2.1 Steel H-Piles

Steel H piles are adequately described by giving the standard steel section designation
only, e.g., HP 310x110. The most common sizes specified in Ontario are HP 310x79, HP
310x110, HP 310x132, and HP 360x108.

For these H-piles, the width-thickness ratio requirement given in Section 10.9.2.1 of the
𝑏𝑏 200
CHBDC, � 𝑡𝑡 < �, need not be satisfied for them to be treated as Class 3 sections.
�𝐹𝐹𝑦𝑦

March 2024 Page 5 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

The type and grade of steel shall be specified by adding the following note to the
foundation drawing:

STEEL H-PILES SHALL CONFORM TO CSA G40.20/G40.21 GRADE ………. (Note: The
designer shall specify Grade 350W or Grade 450W depending on the structural capacity
required).

MTO allows substitution of G40.21/G40.21 piles with ASTM A572/A572M or ASTM


A913/A913M. The design shall be based on the yield strength of the grade of product per
G40.20/G40.21, and the imperial equivalents are deemed acceptable substitutions.
Splices for steel H-piles shall be according to OPSD 3000.150.

3.2.2.2 Steel Tube Piles

When steel tube piles are used in the design, the pile cross section must be specified by
giving the outside diameter and the wall thickness as part of the pile data. The piles may
or may not be filled with concrete, depending on soil conditions. ASTM A252 is the most
available tube for piles. Grade 3 has a yield strength of 310 MPa, and the design should
use the nominal wall thickness.

Steel tube piles with longitudinal or helical butt splices shall be used.

The most common sizes are O.D. Diameters of 324, 356, 406, 508, 610 mm with wall
thickness of 9.5, 11, and 13 mm.

The type and grade of steel shall be specified by adding the following note to the
foundation drawing:

STEEL TUBE PILES SHALL CONFORM TO ASTM A252 GRADE 3.

Splices for steel tube piles shall be according to OPSD 3001.150.

3.2.2.3 Wood Piles

When wood piles are used in the design the pile size must be specified as part of the pile
data table by giving the following:

i) Species;

ii) Minimum diameter at extreme butt or large end (mm); and,

iii) Minimum diameter at tip or small end (mm).

The sizes of wood piles which are normally available in Canada are given in the publication
Wood Piles published by the Canadian Wood Council or in CSA-056 Round Wood Piles.

Sometimes wood piles are designated as "Size 30.” Size designation in this case refers
to the minimum diameter at the extreme butt or large end in centimetres i.e., Size 30

March 2024 Page 6 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

means the minimum diameter of the pile at the large end is 30 cm or 300 mm. The most
common sizes used by MTO are Size 30 and Size 36.

The document Wood Piles referred to above is a useful aid for the design, protection,
construction and specification of wood piles in structures.

Splices in wood piles shall not be permitted.

Refer to Section 9 of the CHBDC for restrictions concerning the use of untreated wood
piles, which are less expensive than treated wood piles. Refer to Section 15.2.3 for
treatment requirements. Where required the type of preservative treatment must be given.

The maximum length of timber piles is typically 15 m or less.

3.2.2.4 Precast Concrete Piles

Proprietary precast concrete piles may be used with permission of the Structures Office
Manager.

3.2.3 Drawings

3.2.3.1 Pile Data Table

A table or a statement entitled "Pile Data" is required on the foundation layout drawing
giving the number, lengths, batter, cross section, and type of piles. The length should be
the length measured along the pile between cut off and tip elevations given or estimated
by the design Engineer, rounded up to the nearest 0.5 m.

Pile notes are required close to the pile data table as appropriate. See also Section
3.2.3.3.

The following are typical pile notes for various conditions:

1) PILE SPACING IS MEASURED AT THE UNDERSIDE OF FOOTINGS.

2) PILE LENGTHS SHOWN ARE THE THEORETICAL LENGTHS BELOW CUT-OFF.

3) THE PILE DRIVING EQUIPMENT SHALL BE APPROPRIATE TO THE DRIVING


CONDITIONS AND CAPABLE OF DELIVERING A MINIMUM SPECIFIED HAMMER
ENERGY OF … kJ.

4) PILES SHALL HAVE REINFORCED TIPS AS PER OPSD 3000.100 or OPSD


3001.100 TYPE … OR AS APPROVED. *(Specify if pile reinforcement is required, see
also Section 3.2.1.1.)

5) PILES SHALL HAVE DRIVING SHOES AS APPROVED.

6) PILES SHALL BE FITTED WITH ROCK POINTS AS PER OPSD 3000.201. (Specify
if rock points are required, and if so, the type. See also Section 3.2.1.1.)

March 2024 Page 7 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

7) PILE SPLICES SHALL BE AS PER OPSD 3000.150 or OPSD 3001.150 AND IN


ACCORDANCE WITH OPSS 903.

* Titus "H" Bearing Pile Points or APF Hard Bite are alternate products that are
acceptable.

3.2.3.2 Pile Driving Control

Pile driving control has been done using the Hiley formula for driven piles with uncertain
end bearing or friction. Recently, the ministry has been testing a newer method, Pile
Driving Analyzer (PDA), which appears to be more accurate than Hiley, and with less
scatter of results. For the time being, use of PDA requires approval of the Foundation
Section and is not applicable for general use.

3.2.3.2.1 Hiley Formula

Pile driving control is a construction technique that is used in the field to control pile
installations and thereby provide some assurance about the validity of design
assumptions.

MTO's pile driving control tool is the Hiley formula. This is an empirical formula that models
pile behaviour by relating the energy of the hammer blow to the penetration of the pile and
rebound of the hammer. That is, it is a monitoring tool, not a design tool. It provides a
reasonable approximation of actual pile resistance (for piles that are essentially friction-
type rather than end-bearing) in non-cohesive soils, but not in cohesive soils unless the
excess pore water pressures are accounted for or allowed to dissipate. Note that the
hammer has to rebound enough to maintain its energy per blow and hence the soil must
provide sufficient rebound for the Hiley formula to be effective.

In order to minimise misinterpretations of the Hiley formula that have occurred in practice,
Structural Standard Drawing SS103-11 has been revised, and renamed "Pile Driving
Control." Instead of the graphical method that was used in the past, SS103-11 now gives
only a calculation method to determine R, the ultimate pile capacity. The method of
applying the Hiley formula, as well as some explanatory notes are given on the Structural
Standard Drawing and are further elaborated here below.

When applying the Hiley formula, hammers should be operating at 100% of their available
capacity. That is, for example, controls for diesel hammers should be turned to full
capacity.

The formula for use with drop hammers and single-acting steam hammers is:

𝑛𝑛 𝑒𝑒𝑓𝑓 𝑊𝑊 𝑔𝑔 𝐻𝐻
𝑅𝑅 =
𝐶𝐶
𝑆𝑆 + 2

𝑒𝑒𝑓𝑓 = 0.75 𝑓𝑓𝑓𝑓𝑓𝑓 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎

March 2024 Page 8 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

The formula for use with double-acting, differential-acting steam and diesel hammers is:

𝑛𝑛 𝑒𝑒𝑓𝑓 𝐸𝐸
𝑅𝑅 =
𝐶𝐶
𝑆𝑆 + 2

𝑒𝑒𝑓𝑓 = 0.6 𝑡𝑡𝑡𝑡 0.8 𝑓𝑓𝑓𝑓𝑓𝑓 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎


𝑒𝑒𝑓𝑓 = 1.0 𝑓𝑓𝑓𝑓𝑓𝑓 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎

Diesel hammers are currently the most commonly used type.

Where:

𝑅𝑅 = 𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈𝑈 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 (𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐)𝑏𝑏𝑏𝑏 𝐻𝐻𝐻𝐻𝐻𝐻𝐻𝐻𝐻𝐻 𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 [𝑘𝑘𝑘𝑘]

𝑊𝑊 + 𝑃𝑃 𝑒𝑒 2
𝑛𝑛 = 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 𝑜𝑜𝑜𝑜 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 =
𝑊𝑊 + 𝑃𝑃

𝑒𝑒𝑓𝑓 = 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 𝑜𝑜𝑜𝑜 𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚’𝑠𝑠 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒


(𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 0.6 𝑡𝑡𝑡𝑡 0.8)

𝑊𝑊 = 𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 (𝑟𝑟𝑟𝑟𝑟𝑟) 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 (𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡) [𝑘𝑘𝑘𝑘]

𝑔𝑔 = 9.8 [𝑚𝑚/𝑠𝑠 2 ]

𝐻𝐻 = 𝐻𝐻𝐻𝐻𝐻𝐻𝐻𝐻ℎ𝑡𝑡 𝑜𝑜𝑜𝑜 𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 𝑜𝑜𝑜𝑜 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 [𝑚𝑚]

𝑆𝑆 = 𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑜𝑜𝑜𝑜 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑝𝑝𝑝𝑝𝑝𝑝 ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 [𝑚𝑚𝑚𝑚]

𝐶𝐶 = 𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝑜𝑜𝑜𝑜 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑝𝑝𝑝𝑝𝑝𝑝 ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 [𝑚𝑚𝑚𝑚]

𝐸𝐸 = 𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑚𝑚 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒 𝑜𝑜𝑜𝑜 ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 (𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐, 𝑜𝑜𝑜𝑜 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡)


[𝐽𝐽𝐽𝐽𝐽𝐽𝐽𝐽𝐽𝐽𝐽𝐽/𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏]

𝑃𝑃 = 𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 (𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 + 𝑐𝑐𝑐𝑐𝑐𝑐ℎ𝑖𝑖𝑖𝑖𝑖𝑖 + 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎) [𝑘𝑘𝑘𝑘]

𝑒𝑒 = 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶 𝑜𝑜𝑜𝑜 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟


𝑒𝑒 = 0.25 𝑓𝑓𝑓𝑓𝑓𝑓 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 𝑐𝑐𝑐𝑐𝑐𝑐ℎ𝑖𝑖𝑖𝑖𝑖𝑖
𝑒𝑒 = 0.32 𝑓𝑓𝑓𝑓𝑓𝑓 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑝𝑝𝑝𝑝𝑙𝑙𝑙𝑙 𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 𝑐𝑐𝑐𝑐𝑐𝑐ℎ𝑖𝑖𝑖𝑖𝑖𝑖
𝑒𝑒 = 0.55 𝑓𝑓𝑓𝑓𝑓𝑓 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑤𝑤𝑤𝑤𝑤𝑤ℎ𝑜𝑜𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐ℎ𝑖𝑖𝑖𝑖𝑖𝑖

A) Design Stage

The requirement for pile design is as follows:

Factored geotechnical resistance at ULS > Design load at ULS

March 2024 Page 9 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

Factored geotechnical resistance at ULS = Ultimate geotechnical resistance x


resistance factor

Factored geotechnical resistance at ULS: Given in the Geotechnical Report.

Ultimate geotechnical resistance: Established by the geotechnical Engineer, based on


formulae, field testing, or assessment.

Resistance factor: The factor by which the ultimate geotechnical resistance is


multiplied to establish the factored geotechnical resistance at ULS,
typically 0.5.

B) Construction Stage

The requirement for pile resistance is as follows:

Ultimate Pile Resistance R > Ultimate Geotechnical Resistance

• The Ultimate pile resistance R is calculated in the field by use of the Hiley formula,
based on measured observations of pile penetration (S) and rebound (C), and the pile
driving characteristics of energy of hammer and efficiency of blow.

• The Ultimate geotechnical resistance = 2 x design load at ULS and must be given
by the designer in the pile driving notes on the contract drawings.

In the equation above:

• R must be greater than 2 x design load at ULS (rather than 2 x factored


geotechnical resistance at ULS).

The design load at ULS, calculated by the structural Engineer is always less than or
equal to the factored geotechnical resistance at ULS established by the geotechnical
Engineer. The factor of 2 needs to provide safety for the actual ULS design load only, in
order that the pile not be driven to an unnecessarily high capacity, risking damage during
driving.

• The design load at ULS is the maximum factored design load per pile at the ultimate
limit states, calculated by the designer.

During the process of pile driving and its monitoring, if the required ultimate pile resistance
(as calculated by the Hiley formula) is not reached when expected at a prescribed
elevation or in a depth of stratum bounded by prescribed elevations, the advice and
recommendations of the geotechnical Engineer should be sought and followed.

It should be noted that the Hiley formula incorporates a factor to account for hammer
efficiency so that the maximum rated energy should be used in the equation.

MTO's principle alternate pile driving control tool is the Pile Driving Analyser (PDA) which
measures force imparted to the pile by measuring acceleration and/or strain of the pile in

March 2024 Page 10 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

response to blows and through wave equation analysis has the potential to provide a more
accurate model of pile resistance. It is used in critical applications that warrant the higher
monitoring costs involved.

3.2.3.3 Pile Driving Notes

When piles are specified, the pile driving notes shall be in the form of one of the seven
listed below.

When reference is made to SS103-11 (Hiley formula for steam and diesel hammers), it
shall be included in the drawings, which is usually the case unless the pile is driven to the
bedrock.

Foundation Investigation and Design Reports are to indicate which note is applicable.

1. PILES TO BE DRIVEN IN ACCORDANCE WITH STRUCTURAL STANDARD


DRAWING SS103-11 USING AN ULTIMATE GEOTECHNICAL RESISTANCE OF …
kN PER PILE.

2. PILES TO BE DRIVEN IN ACCORDANCE WITH STANDARD SS103-11 USING AN


ULTIMATE GEOTECHNICAL RESISTANCE OF … kN PER PILE BUT MUST BE
DRIVEN BELOW EL …

3. PILES TO BE DRIVEN IN ACCORDANCE WITH STRUCTURAL STANDARD


DRAWING SS103-11 USING AN ULTIMATE GEOTECHNICAL RESISTANCE OF …
kN PER PILE BUT NOT BELOW EL … WITHOUT APPROVAL OF THE ENGINEER.

4. PILES TO BE DRIVEN IN ACCORDANCE WITH STRUCTURAL STANDARD


DRAWING SS 103-11 USING AN ULTIMATE GEOTECHNICAL RESISTANCE OF …
kN PER PILE BUT MUST BE DRIVEN BELOW EL … AND NOT BELOW EL …
WITHOUT APPROVAL OF THE ENGINEER.

5. PILES TO BE DRIVEN TO BEDROCK.

6. PILES TO BE FITTED WITH ROCK POINTS AND DRIVEN INTO BEDROCK IN


ACCORDANCE WITH OPSS 903.
7. PILES TO BE DRIVEN TO EL …

The ultimate geotechnical resistance, given in notes (1) to (4) to be specified = 2 x


(maximum factored design load at ULS).

When using notes (5), (6), and (7), do not give ultimate resistance as part of the pile driving
note.

In a separate note, headed "PILE DESIGN DATA", the maximum factored design load at
the ULS and at SLS should be given and identified as such, e.g., MAX. FACTORED
LOADS: ULS 1450 kN, SLS 1055 kN.

March 2024 Page 11 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

3.3 Drilled Shafts

Drilled shafts are deep foundation elements. Drilled shafts, or caisson piles, are often a
viable alternative to driven piles. The casing may be either permanent or temporary based
on the recommendations of Foundation Investigation and Design Report (FIDR)
depending on the design and/or the site conditions.

3.3.1 Design

The capacity of a drilled shaft may be dependent upon end bearing, side friction or a
combination of the two. End bearing resistance is achieved by solid and full contact with
the bottom of the rock socket. Drilled Shafts are considered where footing conditions are
such that the structure's loads need to be carried to a rock formation and the following
conditions exist:

• Shallow foundations and driven piles would not be feasible and economical due to the
project specific constraints.

• There are concerns about pile driving vibrations, noise, or overhead clearance.

Completed diameters of caisson piles are based on available drilling equipment in Ontario
and 650, 750, 880, 1000, 1180, 1300, 1500, 1800 and 2000 mm sizes are commonly
available from the deep foundation contractors.

Design of caisson pile shall be a reinforced concrete column. The amount of reinforcing
steel in a cage must satisfy all structural requirements, taking into account combined
stresses of axial load, lateral load and bending moment. There should be sufficient clear
space between the longitudinal bars as well as the transverse bars or spiral loops to allow
free passage of concrete through the cage. Typical reinforced concrete column design
requires tight pitch spacing for spirals and concrete placement into the caisson pile
becomes often problematic. In order to minimize any caisson installation issues, 15M
spiral reinforcement may be replaced by 15M hoops (circular ties) or discrete 20M hoops
with spacing 50% larger than 15M bars. In either any case, the spiral pitch or hoop spacing
cannot exceed 6 times the diameter of the longitudinal reinforcement, nor 150mm.

3.3.1.1 Permanent Steel Casing

Permanent casing is usually steel pipe having the same nominal diameter as the
completed shaft. The permanent casing becomes a form to contain the concrete between
the top of the shaft and the rock socket. Permanent casing is left in place after concrete
placement. Sealing the permanent casing within the rock socket is important during
concrete placement because concrete may leak through any gaps.

3.3.1.2 Temporary Steel Liner

Temporary liners are heavy-walled pipes that are usually driven, screwed, or vibrated into
the earth. Drilling may occur either before or after the casing is in place. Temporary liners
of a larger diameter and partial length may be used in additional to permanent casings, to
reduce the friction of soil when the permanent casing is installed.

March 2024 Page 12 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

3.3.1.3 Concrete Placement

The method used to place the concrete falls into one of two categories, wet pour, or dry
pour. The location of the water table and the type of materials that make up the underlying
geology control whether the excavation is considered a "wet" shaft or a "dry" shaft. For
wet shafts, the concrete must be placed through a tremie or pump extension so that the
groundwater and contaminated concrete is pushed up by a head of concrete inside the
tremie as it is being placed in the excavation.. A wet pour requires the use of a casing.

3.3.1.4 Rebar Cages

A drilled shaft rebar cage is comprised of longitudinal bars that are normally arranged in
a uniform spacing circumferentially to form a cylinder that is concentric with the drilled
shaft. Transverse reinforcing is placed around and attached to the longitudinal bars.

The most common types of transverse reinforcement in drilled shafts are spirals. 15M
spirals are typically used for caisson piles and readily available from rebar fabricators.
The tight pitch spacing on spiral reinforcement can often result in constructability issues
with concrete flow through the rebar cage. When a design pitch spacing of 15M spirals is
less than 80 mm, use of circular ties or hoops with either same bar size and/or larger bar
size can allow an increase in the bar spacing as shown in Figure 3.3.1. Welded hoops
shall not be permitted. Another solution is to detail 20M spirals with spacing 50% larger
than 15M spirals. The designer shall confirm the availability of 20M spiral reinforcement
from the rebar fabricators, as they are generally not available in Ontario. In any case, the
spiral pitch cannot exceed 6 times the diameter of the longitudinal reinforcement, nor
150mm. Mixing of spirals and hoops within the same section is not permitted.

FIGURE 3.3.1 – TRANSVERSE REINFORCING DETAILS FOR CAISSON PILE

For long cages and cages with large diameter, bracing elements are normally provided by
the Contractor to prevent permanent distortion of the cage as a result of stresses induced
by lifting and placing, and for safety.

March 2024 Page 13 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 3 - DEEP FOUNDATIONS

3.3.2 Materials

Normal 30 MPa concrete is used for caisson piles. Reinforcing steel for rebar cages shall
be grade 500W.

3.3.3 Drawings

Standards notes for drilled shafts shall be listed on the drawings. The following are typical
drilled shaft notes for various conditions.

1. CAISSONS ARE …. mm NORMINAL DIAMETER AS SHOWN AND SHALL BE


DRILLED AND SOCKETED INTO BEDROCK.

2. MAXMUM COMBINED FACTORED LOADS:


SLS …. kN PER CAISSON
ULS …. kN PER CAISSON

3. STEEL CASINGS FOR CAISSONS SHALL CONFORM TO ASTM A252 GRADE


3 MODIFIED (345 MPa). WELDED CASING SHALL COMFORM WITH THE
REQUIREMENTS OF CSA W59.

4. CAISSON LENGTHS SHOWN ARE THEORETICAL LENGTH BELOW TOP OF


CAISSON AND ARE BASED ON ESTIMATED TIP ELEVATION. FINAL
LENGTHS SHALL BE DETERMINED ON SITE FROM DRILLING REPORTS.

5. CAISSON SPACING IS MEASURED AT THE UNDERSIDE OF FOOTINGS.

3.4 Pile Caps

The thickness of the pile cap is typically established to resist shear without need for shear
reinforcement and should be sufficient for the bars projecting from the piles and the dowel
bars for the columns to be developed.

Where a pile cap meets the definition of a deep beam according to the CHBDC, the pile
cap shall be designed using a strut-and-tie model.

March 2024 Page 14 of 14 SM-D2-S03


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 4 - SHALLOW FOUNDATIONS

Table of Contents

4 SHALLOW FOUNDATIONS ................................................................................. 2


4.1 General ........................................................................................................................ 2
4.2 Design Criteria ............................................................................................................. 2
4.2.1 Working Slabs/Mass Concrete or Granular Pads .................................................. 2
4.2.2 Foundations in Rock ............................................................................................. 2
4.2.3 Minimum Frost Protection to Footings ................................................................... 3
4.2.4 Scour Protection ................................................................................................... 4

March 2024 Page 1 of 4 SM-D2-S04


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 4 - SHALLOW FOUNDATIONS

4 SHALLOW FOUNDATIONS

4.1 General

A spread footing is a type of shallow foundation which may be a more suitable option than
any deep foundations for specific project circumstances.

Prior to the initiation of the foundation engineering investigation, the structural Engineer
shall provide the geotechnical Engineer with a conceptual layout of the proposed structure
foundations.

The subsequent Foundation Investigation and Design Report (FIDR) produced by the
geotechnical Engineer shall contain information and recommendations with respect to
shallow foundations. When spread footings are selected, the final design shall be
developed through consultation between the structural Engineer and the geotechnical
Engineer.

In the Foundation Investigation and Design Report, the geotechnical Engineer shall
provide recommendations for:

i) Type of material supports and founding elevations for spread footings, e.g., spread
footings can be founded on bedrock, on mass concrete placed on either subsoil or
bedrock, or granular pad placed on subsoil.

ii) Factored axial and horizontal resistances at ULS where the resistances are based
on the geotechnical resistance of the footings.

iii) Axial and horizontal resistances at SLS for identified settlements or displacements
and corresponding subgrade reactions.

4.2 Design Criteria

4.2.1 Working Slabs/Mass Concrete or Granular Pads

If required, recommendations for using working slab/mass concrete or granular pad shall
be stated in the Foundation Investigation and Design Report. When the founding soils
must be covered with the mass concrete within a limited time after exposure to prevent
deterioration, the time limit should be noted on the footing drawing.

4.2.2 Foundations in Rock

Without special rock excavation procedures, over excavation may occur periodically. The
over excavation can result in either approximately vertical side surfaces or sloping side
surfaces.

When footing stability is a concern, the designers shall satisfy themselves about the
provision of adequate sliding resistance on rock so that the footing will perform as
intended, i.e., resistance against sliding shall be provided by bearing against

March 2024 Page 2 of 4 SM-D2-S04


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 4 - SHALLOW FOUNDATIONS

approximately vertical side rock surface, or by using steel reinforcement dowels between
the rock and the footing or by the rough sloping rock surface provided that:

a) In the case of over excavation with approximately vertical side surfaces, the over
excavation is replaced with concrete of the same Specified 28-day Compressive
Strength as the footing concrete;

b) In the case of over excavation with sloping (greater than about 30° to the vertical) side
surfaces, the sloping surfaces are rough (25 mm + deep depressions with jagged
edges evenly spaced over about 50% of the sloping surface area) or if they are
artificially roughened to the same roughness as above and the over excavation is
replaced with concrete of the same Specified 28-day Compressive Strength as the
footing concrete.

Since OPSS 902 currently states that over excavation is to be replaced by "a material
suitable for the particular application and approved by the Contract Administrator", it is
essential that the drawings state that over excavation of rock be replaced by the footing
concrete.

Where it is necessary to key the footings into rock the footing drawing shall contain the
following notes:

i. FOOTING(S) SHALL BE SET …mm INTO SOUND BEDROCK;

ii. ROCK SURFACES IN OVER EXCAVATED AREAS SHALL BE SUBJECT TO


APPROVAL BY THE CONTRACT ADMINISTRATOR;

iii. OVER EXCAVATION SHALL BE REPLACED WITH CONCRETE OF SAME


SPECIFIED 28-DAY COMPRESSIVE STRENGTH AS FOOTING CONCRETE.

4.2.3 Minimum Frost Protection to Footings

The frost protection depth to the underside of structure footings shall be according to the
recommendations of the Foundation Investigation and Design Report. Where this in not
available the following shall be used:

• OPSD 3090.100 - Contours of frost depths for Northern Ontario;

• OPSD 3090.101 - Contours of frost depths for Southern Ontario.

Rock fill and rock protection shall count for half of their thickness in determining the depth
of cover provided.

Footings bearing on sound rock or well drained rock fill on sound rock do not require frost
protection; but if the rock fill is on soil, the minimum frost protection depth applies to the
soil.

RSS (MSE) wall concrete leveling pads require embedment to provide stability and
protection from surface drainage scour as per CHBDC and RSS Design Guidelines.

March 2024 Page 3 of 4 SM-D2-S04


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 4 - SHALLOW FOUNDATIONS

4.2.4 Scour Protection

When scour of footings is a concern, the designer shall consider and show on design
drawings the scour protection requirements of the footings as recommended by the
Hydrology Report and/or Foundation Investigation and Design Report.

The minimum depth of embedment in soil or soft rock, e.g., weathered shale, should be
1.2 m. This depth is provided only as a general guide for minor structures where a
Hydrology Report is not considered necessary by the hydrologist and where scour is not
likely to be a problem.

March 2024 Page 4 of 4 SM-D2-S04


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

Table of Contents

5 ABUTMENTS AND EARTH RETAINING SUBSTRUCTURES............................. 2


5.1 General ........................................................................................................................ 2
5.1.1 Integral Abutments ................................................................................................ 2
5.1.2 Semi-Integral Abutments ...................................................................................... 2
5.1.3 Conventional Abutments ....................................................................................... 3
5.2 Abutment Design.......................................................................................................... 3
5.2.1 Abutment Wall and Retaining Wall ........................................................................ 3
5.2.1.1 Earth Pressure on Abutment Wall and Retaining Wall ................................................ 3
5.2.1.2 Abutment Wall and Retaining Wall Drainage Design .................................................. 3
5.2.1.3 Abutment Wall Stem Thickness ................................................................................... 4
5.2.1.4 Abutment Wall Vertical Construction Joint .................................................................. 4
5.2.1.5 Abutments to Approach Slabs Dowels ........................................................................ 5
5.2.1.6 Staining of Concrete Abutments by Weathering Steel ................................................ 5
5.2.1.7 Traffic Barrier in Front of Abutment or Retaining Walls ............................................... 5
5.2.2 Abutment Seats and Provision for Jacking ............................................................ 5
5.2.2.1 Bearing Pedestals on Abutment Seats ........................................................................ 6
5.2.2.2 Rust Stain Control for Steel Girder Bridges ................................................................. 6
5.2.3 Ballast Walls ......................................................................................................... 7
5.2.3.1 Ballast Wall Dimensions and Elevations ..................................................................... 7
5.2.3.2 Ballast Wall Construction Joints .................................................................................. 8
5.2.4 Wingwalls ............................................................................................................. 8
5.2.4.1 Wingwalls Length ......................................................................................................... 8
5.2.4.2 Height of the Wingwall ............................................................................................... 10
5.2.4.3 Loads on Wingwall ..................................................................................................... 10
5.2.4.4 Calculation of Forces in the Cantilever Wingwall ...................................................... 11
5.2.4.5 Standard Design Aids for Wingwall ........................................................................... 11
5.2.4.6 Standard Structural Drawing (SSD) for Wingwall ...................................................... 11
5.2.4.7 Wingwall Extensions .................................................................................................. 11
5.3 Mechanically Stabilized Earth (MSE) Systems (RSS)..................................................12
5.3.1 General ................................................................................................................12
5.4 The Use of MSE (RSS) Walls Adjacent to Structures ..................................................12
5.4.1 MSE (RSS) Wall Design History ..........................................................................12
5.4.2 Design Requirements ..........................................................................................13
5.5 Approach Slabs ...........................................................................................................14

March 2024 Page 1 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

5 ABUTMENTS AND EARTH RETAINING SUBSTRUCTURES

5.1 General

MTO has a strong preference to use rigid frame bridges or integral abutment bridges due
to improved long term durability and having fewer components to inspect and maintain in
the future (e.g., no bearings). Integral abutments shall be used when possible. If not
possible, semi-integral abutment bridges are the next preferred since leakage of the
expansion joint does not lead to deterioration of the abutments.

5.1.1 Integral Abutments

Integral abutment bridges are single span or multi-span bridges with a movement system
composed primarily of abutments on flexible integral pile foundations and approach slabs,
in lieu of movable deck expansion joints and bearings at abutments. The effect of the
longitudinal forces in the structure due to temperature, shrinkage and creep is minimised
by making the abutment foundations flexible and less resistant to longitudinal movements.

Integral abutment bridges are well-suited for the concrete slab-on-girder type of
superstructures for total bridge length of 150 m with thermal movements of a maximum of
75 m length going to one side, and skew angle of less than or equal to 20 degrees. To
minimise the effect of soil pressure and resistance to abutment movements, the total
height of the abutment wall and length of wingwall should not exceed 6 m and 7 m
respectively. The abutment should be supported on relatively flexible piles such as H-
piles. Where the load-bearing strata is near the surface or where the use of short piles
less than 5 m in length is planned, the site may not be suitable for integral abutment
bridges. Integral abutments may be constructed on concrete filled-tube piles, concrete
caissons, or on columns supported on spread footings (e.g., spill-through abutments)
where these systems can provide the flexibility needed to accommodate the movements
from the superstructure.

Short span bridges have been designed with integral abutments supported on narrow
spread footings capable of providing a small amount of rotation, similar to the abutments
of a cast-in-place rigid frame, and shall be designed as rigid frames. The behaviour of the
structure and its durability is greatly influenced by the movement required and detail of the
footing.

Bridges shall have integral abutments as required by Section 2.1.2. The structure length
and skew limitations can be exceeded subject to approval by the Structural Section.
Reference should be made to the Structural Office Report # SO-96-01, "Integral Abutment
Bridges".

5.1.2 Semi-Integral Abutments

Semi-integral abutment bridges are single span or multi-span continuous deck type
bridges with rigid, non-integral foundations and movement system composed primarily of
reinforced concrete end diaphragms, approach slabs, movement-accommodating
bearings and horizontal joints at the superstructure and abutment interface. This

March 2024 Page 2 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

arrangement shall only be considered where an integral abutment arrangement cannot be


used.

Reference should be made to Bridge Office Report BO-99-03, “Semi-Integral Abutment


Bridges”.

5.1.3 Conventional Abutments

Conventional abutments are built with deck expansion joints which are suitable for bridges
with large longitudinal movements and where use of Integral or semi-integral abutments
is restricted by design constraints. Conventional abutments shall be detailed with
sufficient space between the ballast wall and the deck end for inspection and maintenance
of joints and bearings, as required by Section 13.

5.2 Abutment Design

Beneficial effects of compression in reinforced concrete abutment components shall not


be taken into account in the design.

5.2.1 Abutment Wall and Retaining Wall

5.2.1.1 Earth Pressure on Abutment Wall and Retaining Wall

Backfill arrangements for abutment and retaining walls shall be according to


OPSD 3101.150 or OPSD 3101.200.

Conventional abutments and retaining walls should normally be designed for the active
earth pressure. This, of course, is contingent on the use of free draining granular backfill
and on the type of compaction equipment used within the restricted zone behind the wall.
Abutments and retaining walls founded on unyielding material or on short piles may
generate earth pressures exceeding the active earth pressure. Integral abutment bridges
shall be designed for earth pressure commensurate with the movement of the abutments
into the soil from thermal movements of the superstructure.

The 0.8 m height equivalent live load surcharge of does not need to be applied to most
abutments, with approach slab supported on the abutment ballast wall. Where the length
of the approach slab carrying live loads is less than the height of the abutment, the live
load surcharge effects shall be considered.

When earth pressure is acting as a resistance, the effects shall be neglected when there
is a possibly of the soil being removed, or when the soil is within the frost penetration
depth.

5.2.1.2 Abutment Wall and Retaining Wall Drainage Design

Drainage of the granular fill behind retaining walls and abutments should be provided as
follows:

March 2024 Page 3 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

a) For perched abutments "150 mm diameter perforated subdrains" behind abutments


and within the granular limits;

b) For other types of abutments and for retaining walls “150 mm perforated sub-drains
and/or wall drains”;

c) Where there is a sidewalk in front of an abutment or retaining wall, drainage should be


provided by some means (e.g., sheet drain such as Miradrain) other than wall drains
if possible;

d) Wall drains shall be shown on the drawings by reference to OPSD 3190.100 or, if this
is not appropriate, as "75 mm dia. non-metallic wall drains at 3000 mm c/c, elevation
to be determined by the Engineer";

The part of the note above concerning the elevation should be used only if the drain
elevations are not shown on the drawings. They should be shown if possible.
Generally, elevations should be set as low as possible, but at least 300 mm above the
level of the ground or normal water level in front of the wall.

A pocket of "open graded 19.0 mm clear stone in accordance with OPSS 1004" should
always be shown 0.05 m3 in volume around the inlet to each drain. The drains should
be shown level;

e) Perforated subdrains must be shown on the preliminary and final versions of the
general arrangement, on the elevation only. The length, outlets and connections
should not be shown.

It is not generally necessary to drain the back of a wall below the elevation of soil or water
in front of the wall. Backfill which is not free draining requires additional considerations
and requires approval by the Structural Section.

5.2.1.3 Abutment Wall Stem Thickness

In some cases, the required gap between ballast walls and superstructures, and minimum
ballast wall thicknesses, leads to excessively thick abutment stems. Where the abutment
stem of a tall abutment exceeds 1.2 m in thickness, the back face of the abutment shall
be corbelled below the bearing seat ledge to reduce the thickness of the lower portion of
the abutment wall.

5.2.1.4 Abutment Wall Vertical Construction Joint

Relatively long and thick abutment walls are prone to vertical cracking due to restrained
shrinkage and thermal effects. For abutment walls placed on spread footings or pile caps
and when the length of the abutment wall exceeds 12 m, vertical construction joints shall
be specified to construct the wall in shorter lengths to control cracking due to restrained
shrinkage. Smaller diameter reinforcing steel at tighter spacing is more effective to control
cracking than equivalent quantity of steel with larger bars at larger spacing. The
reinforcing horizontal steel at the front face of the abutment shall have a spacing of not
more than 150 mm. Concrete with a shrinkage reducing admixture may be specified for
massive walls.

March 2024 Page 4 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

Walls which are placed in one pour and not subject to restraint from adjacent concrete
members, as is typically the case with integral abutments, construction joints are usually
unnecessary.

5.2.1.5 Abutments to Approach Slabs Dowels

It is important that the stainless steel dowels used to tie approach slabs to abutment ballast
walls should be in line with the bottom steel of the approach slabs. If the dowels are near
the top of the slab, settlement of the slab could cause a tension crack at the top of the slab
that could precipitate a shear failure. In addition, dowels should be hooked so that they
do not project beyond the back face of the abutment and obstruct backfill compaction.

The dowels provided shall be S15M @ 150.

5.2.1.6 Staining of Concrete Abutments by Weathering Steel

Where aesthetics is important, the Structural Section may recommend a sealer to prevent
rust staining of concrete abutments from exposed steel beams during construction. This
may occur during prolonged construction delays, such as a winter shutdown, before
placing the deck and expansion joints.

All exposed faces of the abutments encompassing the bearing seats, front and side faces
below the bearing seat should be treated before the erection of the structural steel.
Preceding the application of the sealer, surface preparation should be carried out as per
the manufacturer’s instructions. As an alternative to a sealer, a clear curing compound
may be applied after the concrete has been cured. Some rust stains may be inevitable,
and provision should be made for washing the stains from the concrete after the deck has
been cast.

MTO had successfully used "Dekguard system sealer" manufactured by Fosroc


Construction Chemicals of Guelph, Ontario as a suitable sealer on several projects.

5.2.1.7 Traffic Barrier in Front of Abutment or Retaining Walls

When abutments or retaining walls are close to travelled lanes, a traffic barrier should be
provided in front of the wall face. Possible applications of this treatment should be
identified at the preliminary planning stage and discussed and decided by the Project
Delivery Section, as it could affect the structure span. Where the wall is within the Clear
Recovery Zone and not able to withstand the Vehicle collision load of CHBDC Clause
3.15, the wall should be located outside of the Zone of Intrusion (see Section 2.5.1 for
further information).

5.2.2 Abutment Seats and Provision for Jacking

Abutment seats shall be detailed with discrete pedestals for each bearing location. The
concrete surface between the pedestals must slope at 5% min. and shall be detailed to
avoid potential leakage from draining onto the front face of the abutment.

March 2024 Page 5 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

All bridges supported on bearings shall have provision for jacking. It is feasible to jack
from a 5% slope, using shims. The gap provided for jacks should be 250 mm minimum in
height.

The unfactored dead load and live load reactions (for jacking purposes) and the
permissible location for jacking points should be shown on the drawings. MTO’s Bearing
Replacement and Jacking Guidelines (BRO-062; ISBN 978-1-4868-2356-7) should be
referenced for further details.

5.2.2.1 Bearing Pedestals on Abutment Seats

Bearings should be supported on concrete pedestals that are at least 150 mm above the
top surface of the abutment wall except for side-by-side concrete boxes with integral
abutment bridges, this should be at least 250 mm to allow integral abutment concrete to
flow under the boxes.

5.2.2.2 Rust Stain Control for Steel Girder Bridges

Structural steel bridges require special treatment to prevent rust staining of piers and
abutments. For a standard detail on abutments, see Figure 5.2.1.

March 2024 Page 6 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

FIGURE 5.2.1 – STANDARD DETAIL FOR RUST STAIN CONTROL AT ABUTMENT

5.2.3 Ballast Walls

5.2.3.1 Ballast Wall Dimensions and Elevations

Unless required otherwise by design, ballast walls which are not more than 1200 mm high,
measured above the bearing seat ledge, shall have a minimum thickness of 380 mm. For
greater heights, a minimum thickness of 450 mm shall apply. It is essential however that
sufficient space be available between the superstructure end block-out and the ballast wall
block-out to accommodate the expansion joint armouring on both sides (see Section
13.2.1). The desirable width of the concrete block-out at each side of the expansion joint
is 500 mm to provide space for placing the concrete and for the bent "hairpin" rebars.

There has been some confusion regarding the calculation of elevations to be shown on
the top of ballast wall on contract drawings. Standards, such as the OPSD 3370.100 for

March 2024 Page 7 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

bridge deck waterproofing, show a 5 mm dimension from the top of ballast wall to the top
of adjacent asphalt. The 5 mm represents a local increase in asphalt thickness to account
for subsequent compaction by traffic and should not be taken into account when
calculating the elevations to be shown on the top of ballast wall on contract drawings.

5.2.3.2 Ballast Wall Construction Joints

a) For steel and precast concrete girder bridges, the horizontal construction joint between
the abutment and the ballast wall should be shown level with the bottom of the bearing
seats. Dowels from the abutment will then project up above the bearing seat.

b) For post tensioned bridges, dowels may interfere with the stressing operation and the
joint must generally be stepped down below the bearing seat. This may not be
necessary if the anchorages are more than a lap length above the bearing seat.

5.2.4 Wingwalls

Wingwalls are provided to retain the roadway embankment at the approach of a bridge.
The length and the height of the bridge wingwall should be adequate to retain the roadway
embankment with an allowable slope and to eliminate the risk of spill through of the
abutment backfill. The Ministry allows alignment of the bridge wingwalls either parallel to
the roadway or at any angle to the abutment. Wingwalls aligned parallel to the roadway
are very common because they confine the approach roadway effectively and reduce the
risk of approach settlement. This alignment is also suitable for integral abutment bridges
and can be used for supporting the traffic barriers over the wingwalls.

The Ministry had implemented design aids for cantilever type wingwall design in the
Structural Manual in 2008. These design aids demonstrate all the applicable loads for the
wing wall design for Ministry bridges, however barrier loading was limited to TL-4.
Additionally, the Ministry developed and made available one standard structural drawing,
SS105-2, for wingwall design with non-integral bridges.

The Ministry has implemented a policy to specify 500W steel reinforcement for new
structures and all future designs shall be based on steel reinforcement yield strength of
500 MPa. Therefore, the current design aids have been updated with 500W steel
reinforcement and include traffic impact loading on both TL4 and TL5 barriers. Also, the
previous standard structural drawing was renumbered as SS105-11, and a new standard
structural drawing SS105-12 for wingwall with integral abutment bridges has been
developed.

5.2.4.1 Wingwalls Length

The length of a wingwall, Lw, as illustrated in Figure 5.2.2 is measured from the front face
of the abutment to its end. The length of the wingwall must be sufficient so that the slope
of the approach embankment along the wingwall meets the back face of the abutment
below the elevation of the bridge bearing seats. The length of the wingwall shall be
rounded up in 500mm increments. When the wingwalls are aligned parallel to the roadway
(U shape), an additional 500mm length must be provided so that the top of the approach
slope meets 500mm away from the end of the wingwall to protect against erosion. The

March 2024 Page 8 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

Ministry recommends using cleats at the interface of abutment and wingwalls with a
minimum dimension of 500mm along the abutment and 1000mm along the wingwalls to
minimise concrete shrinkage cracking due to the rapid change in the wall thickness, and
to facilitate placement of concrete. The design length of a wingwall with cleat, L is
measured from the end of the cleat to the end of the wingwall. Typical wingwalls aligned
parallel to the roadway are illustrated in Figure 5.2.2.

The following equations in combination with Figure 5.2.2 can be used to calculate the
minimum length of the wingwalls aligned parallel to the roadway:

Length of wingwalls from the front face of the abutment for non-skew bridges,
𝑳𝑳𝒘𝒘 = (𝐸𝐸𝑇𝑇 − 𝐸𝐸𝐿𝐿 )𝑆𝑆 + 500𝑚𝑚𝑚𝑚

Length of wingwall from the front face of the abutment for skew bridges,
(𝐸𝐸 −𝐸𝐸 )𝑆𝑆
𝑳𝑳𝒘𝒘 = 𝑇𝑇 𝐿𝐿 + 500𝑚𝑚𝑚𝑚 at the abutment acute corner
𝐶𝐶𝐶𝐶𝐶𝐶 𝜃𝜃
𝑳𝑳𝒘𝒘 = (𝐸𝐸𝑇𝑇 − 𝐸𝐸𝐿𝐿 )𝑆𝑆 + 500𝑚𝑚𝑚𝑚 at the abutment obtuse corner

Design Length of Wingwalls


L = Lw – D – Length of the cleat along the wingwall

Here,
Lw, L, ET, EL, D and θ are illustrated in Figure 1.
S = Longitudinal slope of approach embankment along the wingwall as shown in
Figure 5.2.2

March 2024 Page 9 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

FIGURE 5.2.2 – GEOMETRY OF WINGWALLS ALIGNED PARALLEL TO ROADWAY

5.2.4.2 Height of the Wingwall

The wingwalls must have enough height above the ground level to retain the approach
embankment and enough height below the ground level to ensure they are founded below
the frost depth. Cantilever wingwalls are not susceptible to frost action provided they are
supported over free draining fill above the normal water level. However, Ministry
recommends providing a minimum wingwall height of 1500mm for a wingwall as illustrated in
Figure 5.2.2 to retain the abutment backfill and provide sufficient height to transfer the
collision load from the traffic barrier supported on it.

5.2.4.3 Loads on Wingwall

Wingwalls are designed for lateral active earth pressure, live load surcharge and compaction
surcharge. When the bridge traffic barrier is supported on the wingwall, an equivalent static
lateral live traffic load on the barrier as specified in CSA S6, must be included in the wingwall
design. Lateral earth pressure for the wingwall design shall be calculated using soil
parameters provided in the Foundation Investigation Design Report. Where the soil
parameters are not available, the Ministry recommends using an equivalent fluid pressure,

March 2024 Page 10 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

Ka γ = 7.0 kPa in the lateral earth pressure calculation. Figure 5.2.3 illustrates design loads
on a wingwall.

5.2.4.4 Calculation of Forces in the Cantilever Wingwall

A cantilever type wingwall shall be analysed as a free cantilever wall suspended from the
abutment. The maximum moment and shear in the cantilever wall occur at the interface
of the wall to the cleat. The equations provided in the Design Aids can be used to calculate
the maximum moment and shear for cantilever wingwall design for applicable loads.
Caution must be exercised when determining the force in intensity when wingwalls do not
extend for the full height.

FIGURE 5.2.3 – DESIGN LOADS APPLIED ON WINGWALLS

5.2.4.5 Standard Design Aids for Wingwall

Design Aids are provided in Division 3. The design values provided in the design aids are
only applicable for the particular shape of wingwall shown in the design aids.

5.2.4.6 Standard Structural Drawing (SSD) for Wingwall

Two Structural Standard Drawings exist for wingwall. One with integral abutment bridges
(SS105-12) and one for wingwall with non-integral bridges (SS105-11).

5.2.4.7 Wingwall Extensions

For self standing structures independent of the abutment (e.g., MSE (RSS) wingwalls,
separate retaining walls), the frost cover shall be as specified in Section 4.2.3. The above
criteria for length, height and loads shall apply.

March 2024 Page 11 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

5.3 Mechanically Stabilized Earth (MSE) Systems (RSS)

5.3.1 General

Mechanically Stabilized Earth (MSE) Systems (as known as Retained Soil System, RSS)
are structural systems that retain generally horizontal soil loads. They may employ either
strip or grid-type, metallic or polymeric tensile reinforcements in the soil mass, and a
discrete modular precast concrete facing, which is either vertical or nearly vertical. There
are also other forms including interlocking soil-filled timber, reinforced concrete or steel
modules that do not contain strip or grid reinforcement, but these are rarely used adjacent
to structures and thus the terms MSE and RSS are used interchangeably in this manual.

MSE may be considered for use where conventional gravity, cantilever, or concrete
retaining walls with counterfort are considered, and particularly where substantial total and
differential settlements are anticipated. Economic and foundation conditions determine
the most suitable type for a particular location.

The contract documents should include a Foundation Investigation Report, and


constraints for the retaining structure, consisting of alignment, profile, and cross-sectional
space constraints. MSE are categorised in terms of three attributes, application,
performance, and appearance.

• For application, the categories are: true abutment, false abutment, wall/slope, road
base embankment.

• For performance, the categories are: high, medium, low.

• For appearance, the categories are: high, medium, low.

These requirements are more fully detailed in the MTO RSS Design Guidelines (2008).

The MSE systems approved for use are listed in the Designated Sources of Materials
(DSM) Listing, DSM #9.70.52, #9.70.53, #9.70.56 and #9.70.59. All design, construction
and fabrication drawings and specifications required to complete this work are obtained
by the contractor from the supplier of the proprietary MSE system (RSS) listed on the
DSM.

5.4 The Use of MSE (RSS) Walls Adjacent to Structures

5.4.1 MSE (RSS) Wall Design History

Early MSE (RRS) walls were generally separate from bridge structures until the
introduction of integral abutment and semi-integral abutment bridges in the mid-1990s.
MSE design was left entirely to the contractor’s MSE suppliers, and MSE walls were often
specified in locations that were not ideal. MSE (RSS) Design Guidelines were developed
to capture previous experience and require that the foundation specialist engineer do
adequate investigations to ensure that MSE is suitable for the site. The guidelines provide
direction and details on the use of MSE in false abutments, wingwalls, and some other

March 2024 Page 12 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

common uses including walls separated from the structure. MSE (RSS) under water or in
flood plain applications requires approval from the Foundation Section.

The RSS Design Guidelines limit the maximum SLS settlement to 25mm for walls that are
abutting a rigid bridge structure. Despite the 2008 Guidelines, settlement continues to be
a problem. The magnitude of this settlement depends on consolidation of the underlying
soil and of the MSE fill, both of which depend largely on the height of the embankment.
For false abutments, excessive settlement can lead to unsightly gaps, as well as potential
exposure of the piles. For wingwalls and retaining walls, settlement can lead to noticeable
differences in traffic barriers ‘on bridge vs. on MSE wing walls’ top elevation problems with
utilities in barrier conduits, roadway settlement, drainage problems and leaking, as well as
cracks caused by concrete surfaces leaning against each other. For barriers on MSE
walls with moment slabs (see Section 10.5.2), settlement of the barrier causes geometric
discontinuity and a potential snag hazard between this barrier and the barrier on the
bridge. This detail has also caused voids to open between the approach slab and the
moment slab, leading to undermining and drainage issues.

In conventional bridges, it is relatively easy to build up the approach pavement if


settlement occurs. With MSE walls and integral abutments, the movement of the walls
makes settlement difficult to control and correct and creates the need for extensive
maintenance or rehabilitation prior to the first planned rehabilitation.

As stated in the RSS Design Guidelines, consideration should be given to whether there
are adequate quantities of MSE walls to justify their use, along with the need for a separate
sub-contractor to do the work. In situations where there is minimal opportunity for cost
savings, the potential settlement problems will outweigh cost savings. Another
consideration is to move the MSE walls away from the structure so that the differential
settlements can be tolerated. If this is done, the abutment would have conventional cast-
in-place cantilever wingwalls, plus MSE walls away from the bridge substructure - either
parallel to the abutment, curved, or flared at an angle. MSE walls under the front of the
abutment, and/or used as wingwalls with the barrier and moment slab on MSE walls,
should only be used where potential for settlement is very small, or where absolutely
required for property or other reasons.

This following policy (March 2019) was developed to specify a preference for the MSE
walls being separated from the structure, thus reducing the consequences of settlement
on the performance, behaviour, and aesthetics of the bridge.

5.4.2 Design Requirements

The suitability of the site for MSE walls shall be determined with adequate investigations
by the foundation specialist engineer.

When MSE is suitable:

1. The MSE wall shall be separated from the structure, both in front and to the sides, like
what is shown in Figure 5.5.1 for integral abutment bridges or Figure 5.5.2 for bridges
with bearings at abutments.

March 2024 Page 13 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

a) If the bridge has bearings, consideration shall be made for inspection of the
bearings. If the bearings are accessible from a lift (cherry picker, scissor lift) below,
the MSE wall may be kept tight to the abutment as shown in the RSS Design
Guidelines. However, if the inspector is expected to access the bearings by foot,
a 1.2 m wide platform is required, along with potential inspector safety railings
depending on the MSE height.

b) If the MSE wall extends roughly parallel to the bridge, there shall be adequate
slope and clear zone between the roadside barrier (concrete or steel beam
guiderail) and the MSE wall to accommodate barrier deflection. Consideration
shall also be given to preventing de-icing salts from reaching and causing
deterioration of the steel straps within the MSE backfill by the use of curbs, or
barriers to lead the drainage longitudinally away from the MSE wall.

2. The MSE wall under the front of the abutment, and/or used as wingwalls with the
barrier with moment slab on MSE, may only be used when approved by the Structural
Section, and with consultation with the RSS Committee. The following situations
generally should be satisfied to be considered for approval:

a) The anticipated settlement is very minimal (less than 10 mm); or,

b) The backfill and MSE fill is less than 5 m height; or,

c) The barrier on MSE begins beyond the approach slab or the barrier wall is
supported directly on the approach slab; or,

d) If a unique situation dictates the need to minimize the MSE backfill mass.

5.5 Approach Slabs

a) 6000 mm approach slab with 90 mm asphalt and waterproofing shall be used on


structures on all paved roads and on roads that are to be paved in the near future.

b) For locations with sleeper slabs, the length of approach slab should be extended so
that the sleeper slab drainage is beyond the end of the wingwalls. The approach slab
reinforcement may need to be increased.

c) Approach slabs waterproofing is shown on Structural Standard Drawing SS 105-15 &


SS 105-16, SS105-17, and OPSD 3370.100.

d) Based on historical performance and considering MTO compaction practices, it is


acceptable to design the approach slab as a simply supported structure over 60% of
the length of the slab, instead of the 75% suggested in CHBDC Clause C1.7.2.

e) If the approach slabs are not to be included in the bridge contract, the approach slab
drawing should still be included in the contract drawings but must not bear the W.P.
nor contract no. The general arrangement drawing must also carry the note:
"THE APPROACH SLABS ARE NOT PART OF THIS CONTRACT".

March 2024 Page 14 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

FIGURE 5.5.1 – MSE (RSS) FALSE ABUTMENT (IN FRONT OF INTEGRAL


ABUTMENT STEM) WITH FLARED MSE WALLS

(From Figure 4.5 RSS Design Guidelines, 2008)

March 2024 Page 15 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

FIGURE 5.5.2 – RIGID PILED BRIDGE WITH MSE (RSS) FALSE ABUTMENT AND
FLARED MSE WALLS

(From Figure 4.10 RSS Design Guidelines, 2008)

March 2024 Page 16 of 16 SM-D2-S05


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 6 - PIERS

Table of Contents

6 PIERS ................................................................................................................... 2
6.1 Design .......................................................................................................................... 2
6.1.1 Round Column Diameters ..................................................................................... 2
6.1.2 Expansion Piers .................................................................................................... 2
6.1.3 Pier Column Reinforcing Details in Earthquake Zones .......................................... 2
6.1.4 Protection of Bridge Pier Columns from Collision Loads ....................................... 4
6.2 Miscellaneous Details .................................................................................................. 5
6.2.1 Pier Nosing for River Piers .................................................................................... 5
6.2.2 Pier Bearing Seats ................................................................................................ 5
6.2.3 Rust Stain Control for Steel Girder Bridges ........................................................... 6

March 2024 Page 1 of 8 SM-D2-S06


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 6 - PIERS

6 PIERS

6.1 Design

Preference is to provide integral piers for prestressed girder bridges in lieu of shallow
bearings. These bridges require cast-in-place concrete in the pier, so this adds no
additional construction operations, it improves structural redundancy and reduces the
number of elements requiring future inspection and maintenance. For more than 2 spans,
multiple integral piers are possible, however the piers must be able to accommodate the
superstructure thermal movements.

Steel girders bridges typically are not made continuous with piers, although they may be
designed that way with careful attention to details at the pier.

6.1.1 Round Column Diameters

Contractors traditionally rent their steel, round column forms as listed below for basic
series of metric sizes of round column forms.

• 1000 mm, 1200 mm, 1350 mm, 1500 mm, 1800 mm, 2100 mm, 2400 mm.

These traditional steel forms can be used for both new and rehabilitation design. However,
currently Sonotube forms are readily available for any metric sizes of columns for new
design. Sizes other than above listed may be considered with a confirmation of Sonotube
size availability.

6.1.2 Expansion Piers

Expansion piers shall be proportioned based on the appropriate shear rate when
laminated elastomeric bearings are used and based on a sliding coefficient of friction
according to CHBDC Table 11.4 when spherical or pot bearings are specified. Fixed
supports, both piers and abutments, shall be designed to resist cumulative forces from
expansion location, as required.

6.1.3 Pier Column Reinforcing Details in Earthquake Zones

Pier column reinforcing details in earthquake zones shall be in accordance with the
provisions contained in CHBDC Section 4.7.

Reinforcing details shown in Figure 6.1.1 are to be used in seismic performance category
1. They provide sufficient flexibility to construct and do not compromise the integrity of the
column at the interface of the footing.

Figure 6.1.2 shows the reinforcing details to be used for seismic performance categories
2 and 3 to prevent buckling of the longitudinal steel and to provide confinement for the
core of the column. A continuous spiral with continuous longitudinal reinforcement is
preferable. A break in spiral at locations 1, 2 and 3 is optional. The column reinforcing
should be supported during the placement of the footing, splicing of longitudinal reinforcing
or spiral outside the middle half of the column is not allowed.

March 2024 Page 2 of 8 SM-D2-S06


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 6 - PIERS

The spiral embedment shall be the greater of D/2 or 400 mm. The plastic hinge zone shall
be the greater of H/6, D or 500 mm or the length over which the moment exceeds 80% of
the maximum moment (see Figure 6.2.1(b)).

FIGURE 6.1.1 – PIER COLUMN REINFORCING DETAILS – SEISMIC PERFORMANCE


CATEGORY 1

March 2024 Page 3 of 8 SM-D2-S06


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 6 - PIERS

The details on Figure 6.1.1 or Figure 6.1.2, adapted to the specific bridge, shall be shown
on the contract drawings to avoid debate during construction.

FIGURE 6.1.2 – PIER COLUMN REINFORCING DETAILS – SEISMIC PERFORMANCE


CATEGORY 2 & 3

6.1.4 Protection of Bridge Pier Columns from Collision Loads

a) New bridge pier columns located within 10.0 m of the nearest travelled lane (measured
from the face of the column) shall be designed for the collision loading as specified in
the CHBDC, regardless of whether they are protected by a roadside barrier.

b) New Bridge piers with only one or two columns shall be designed for the CHBDC
Collision load regardless of their distance from the edge of the travelled lane.

March 2024 Page 4 of 8 SM-D2-S06


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 6 - PIERS

c) Existing Piers: When new traffic lanes are added around an existing pier that encroach
within 10m of an existing bridge pier, or a bridge is rehabilitated where the existing
lanes are already within 10m of the pier, the Regional Structural Section shall assess
the structural adequacy of the pier columns to withstand the collision loading according
to the CHBDC. The Regional Structural Section shall consider factors including pier
vulnerability, pier structural capacity, and remaining life of the bridge to determine
whether strengthening of the pier, and/or protection of the pier columns is required.

d) All piers accessible to impact at higher speeds should be protected by a barrier to


reduce loading and damage to the pier, and to protect the vehicle occupant of the
roadside hazard.

e) Piers and some abutments, adjacent to railways, also have requirements for crash
protection walls and for crash load. These vary by railway owner and must be
confirmed during bridge planning phase.

For existing pier columns that were not designed for collision loads, effective measures
for protecting the pier columns from collision loads include the following:

a) An embankment; or,

b) A structurally independent 1370 mm high barrier meeting the requirements of TL-5 as


specified in CHBDC Clause 12.4.3.4.2; or,

c) A structurally independent 1050 mm high barrier meeting the requirements of TL-5 as


specified in CHBDC Clause 12.4.3.4.2 provided the barrier is a minimum of 3 meters
from the component being protected.

If none of these measures is feasible to implement at a bridge site, the Regional Structural
Section may choose to do a site specific detailed study considering site-specific truck
traffic volumes, highway speed, highway alignment and grade, separation distance to the
existing pier, structure redundancy, consequences of failure, acceptable probability of
failure consistent with the requirements of CHBDC Clause 3.5.1, etc., in order to come up
with an alternative measure of protection in terms of barrier type, shape, height or
separation distance to the structure’s components being protected.

6.2 Miscellaneous Details

6.2.1 Pier Nosing for River Piers

Steel nosing should not be provided unless approved by the Head of Structural Section
for angular piers in rivers with heavy ice floes.

6.2.2 Pier Bearing Seats

If the bridge deck over a pier is not continuous, the requirements of Section 6.2.3 apply.

The requirements of Section 5.2.2 concerning provisions for jacking also apply to piers.

March 2024 Page 5 of 8 SM-D2-S06


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 6 - PIERS

6.2.3 Rust Stain Control for Steel Girder Bridges

Piers below steel girders shall be detailed with dams to avoid leakage onto the piers and
drained off at discrete vertical drain grooves. Rust dams should be at least 75 mm wide,
and the trough shall be at least 75 mm. The bearing seats shall be detailed above the
dams. The slope should match the deck crossfall. Add a counter slope to direct staining
away from the ends. This slope should be of equal magnitude (max. 4%) but opposite
direction to the deck cross-fall.

FIGURE 6.2.1 – RUST STAIN CONTROL – PIER SHAFTS

The vertical groove should clear any radius of shaft ends by at least 300 mm in pier shafts
(see Figure 6.2.1) and clear the column by at least 300 mm in pier caps on columns (see
Figure 6.2.2). Pier shapes vary; those shown are for guidance purposes only. Place

March 2024 Page 6 of 8 SM-D2-S06


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 6 - PIERS

scuppers and vertical grooves at all low points. Position the scupper to take advantage of
any damming action from the outside bearing seat.

FIGURE 6.2.2 – RUST STAIN CONTROL – PIER CAPS ON COLUMNS

March 2024 Page 7 of 8 SM-D2-S06


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 6 - PIERS

This page is intentionally left blank.

March 2024 Page 8 of 8 SM-D2-S06


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

Table of Contents

7 PRESTRESSED CONCRETE .............................................................................. 2


7.1 General ........................................................................................................................ 2
7.1.1 Background .......................................................................................................... 2
7.2 Precast, Prestressed Girders ....................................................................................... 3
7.2.1 General ................................................................................................................. 3
7.2.2 Precast Prestressed Girder Sizes ......................................................................... 5
7.2.3 Debonded Strands ................................................................................................ 5
7.2.4 Precast, Prestressed Solid Slabs (Precast Planks) and Voided Girders ................ 5
7.2.5 Temporary Bracing ............................................................................................... 5
7.2.6 Side by Side Precast Prestressed Concrete Box Girders Type Bridge .................. 6
7.2.7 Establishing Screed Elevations ............................................................................. 6
7.2.8 Establishing the Required Undercut and Stirrup Projection ................................... 7
7.2.9 Prestressed Girders Notes .................................................................................... 8
7.3 Post-Tensioned Concrete Decks .................................................................................. 8
7.3.1 General ................................................................................................................. 8
7.3.2 Circular Voided Decks .........................................................................................10
7.3.3 Box Girder Voids and Access Locations ..............................................................10
7.3.4 Post-Tensioning Tendons, Ducts, Strands, Detailing ...........................................11
7.3.5 Anchorage Slip for Post-Tensioning Systems ......................................................11
7.3.6 Post-Tensioning Tendons and Duct Sizes ...........................................................11
7.3.7 Post-Tensioning Tendon Duct and Web Details ...................................................12
7.3.8 Additional Reinforcing in Exterior Webs Adjacent to Tapered Voids.....................12
7.3.9 Post-Tensioned Deck Notes ................................................................................13

March 2024 Page 1 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

7 PRESTRESSED CONCRETE

7.1 General

This section on prestressed concrete describes the requirements for pretensioned girders
(Subsection 7.2) and post-tensioned decks (Subsection 7.3).

7.1.1 Background

The design and construction of precast prestressed concrete girders has evolved over
time due to advancements in material quality, precasting production methods, and
prestressing and concrete technologies. The Ministry first used prestressed girders in
bridges in the mid to late 1950’s, before the use of prestressing beds, meaning the first
generation of girders where post-tensioned. In the early 1960s, the American Association
of State Highway and Transportation Officials (AASHTO) girder sections with concrete
strength of about 35 MPa were introduced. Prestressed concrete box girders, typically
separated with a thin deck spanning between girders, was also introduced at that time. In
the mid to late 1970s, the Ministry switched from AASHTO girders to Canadian Precast
Prestressed Concrete Institute (CPCI) girders with concrete strength of 40-50 MPa and
prestressing strands of 13 mm (0.5”) diameter. Most recently, in the early 2010s, the
Ministry introduced the Nebraska University (NU) girder shapes for use in bridge designs
while still maintaining the use of CPCI girders. Since 2019, NU girders have been used
exclusively, with CPCI being retaining only for widening of existing bridges.

Nu Girders are advantageous because:

• The constant size top and bottom flange and standard bottom flange configurations
allow for easier reuse of forms in various size girders for easier fabrication;

• The wide top flange allows for shorter deck slab spans and hence less deck
formwork between girder top flanges;

• The wide and thick bottom flange allows for more efficient placement of strands
and increased strand capacity as well as increased stability during transportation
and post installation;

• The ability to achieve longer spans (>45 m); and,

• The ability to have fewer numbers of girder lines at larger spacing with
approximately the same girder depth, or shallower girders placed at approximately
the same spacing.

All concrete I-girders on MTO projects shall be NU girders shapes. CPCI can only be
used for special cases with approval of the Structural Section (such as widening of existing
bridges or replacement of a damaged CPCI girder). Prestressed Box girders may also be
used, although currently, side-by-side box girders which minimize forming requirements,
are preferred over separated boxes.

March 2024 Page 2 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

7.2 Precast, Prestressed Girders

7.2.1 General

a) Girders should be pretensioned rather than post tensioned, unless transportation


problems dictate post-tensioning (see Section 16.2), or the girders are to be spliced.

b) Capacity of all girders in the cross-section shall be identical. Side-by-side box girders,
and girders carrying any unusual additional dead loads, may be designed differently
with approval of the Structural Section

c) The design of prestressed concrete members shall be based on a 50 MPa Specified


28-day Compressive Strength for Box girders and solid slabs, and 60 MPa for NU
girders, respectively.

Based on past Ministry experience, girder compressive concrete strength of 50 MPa


or more should provide adequate durability for most exposures and situations. This
assumes cover requirements are met, temperature limits are observed, and other
specification requirements are complied with.

d) The minimum concrete strength required at transfer of prestress, f’ci, shall be specified
to the nearest 0.5 MPa. It is very important for the production cycle of precast and
prestressed components that the designer specifies the minimum value of strength at
transfer that the CHBDC’s SLS design requirements at transfer will permit. For NU
girders, the concrete strength specified at transfer should be kept to 40 MPa or less
and shall not exceed 45 MPa. The concrete strength at transfer shall not be greater
than 38 MPa for concrete box girders and 35MPa for solid slabs.

Note: The availability of GU and HE cement will be severely restricted in late 2024 as
the cement industry in Canada moves exclusively towards GUL and HEL Portland-
limestone cements to reduce environmental impacts. Therefore, it will no longer be
possible to achieve 45 MPa transfer strength with a single day with HEL because the
limestone does not contribute to accelerated strength gain.

e) Deflected strands shall be fanned out at the ends of the girders to obtain the most
uniform stress distribution. The designer should keep the centroid of the deflected
strands as low as design parameters will allow, while attempting to spread the strands
uniformly at girder ends throughout the web.

Typically, precast, pre-stressed girders are designed with both deflected and straight
strands. However, to facilitate production, all precast, pre-stressed concrete box
girders 900 mm deep or shallower shall be designed with straight strands only.

f) In calculating stresses, the transformed area of the strands may be used to compute
section properties.

g) Single hold-down forces greater than 80 kN (18 kips) should be avoided since this is
the limit for some precasting beds. Generally, an individual strand should not be
deflected steeper than a slope of 1 to 6.

March 2024 Page 3 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

The design of precast, prestressed girders may require the debonding of a number of
straight strands at girder ends. In this case, they shall be grouped according to
CHBDC provisions and rigid debonding sleeves shall be specified on drawings.

The strands to be deflected shall be designated into groups with the hold-down
location of each group clearly indicated on the drawings. A 1.0 m spacing between
hold-down points of different groups of deflected strands is normally used.

h) At the ends of the girders, the deflected strands are usually flared vertically in the web
in multiples of 100 mm to avoid stress concentration and hence longitudinal cracking
in webs at girder ends.

i) The CHBDC prestressing stress limit for prestressing stress immediately prior to
transfer of 0.75 fpu does not account for stresses added by the fabricator to
compensate for chuck sitting, form shortening, bulkhead rotations, friction at hold-
downs, ambient temperatures, thermal effects, or relaxation which occurs between the
time of stressing and when the strands are cut to release the force into the girder.

Precasters are reluctant to stress the strands above 0.80 fpu due to the risk of
breakage. This risk is higher for deflected strands. Consequently, the designer shall
limit the specified prestressing stress prior to transfer to 0.74 fpu.

j) Details of the positive moment connection over piers are given on SS107-15 and
SS107-24. In integral and semi-integral abutment situations, the connection of the
girder to the abutment, is achieved by the use of projected L-shaped reinforcement
bars or by bent projected strands from the girder.

k) All diaphragms shall be cast integrally with the deck slab pour, without construction
joints. Diaphragms shall completely encase strands at the ends of girders to achieve
the minimum cover required by the CHBDC.

l) The girders’ ‘stirrups’ projection above the top of girder must be calculated and
specified so that it accounts for girder hogging (upward deflection) and the vertical
curve of the roadway profile. It shall be verified and revised, if necessary, to ensure
that the girder stirrups are projecting a minimum of 25 mm above the bottom
reinforcement mat of the deck slab. The stirrups at the girder ends shall have a
minimum spacing of 75 mm to avoid reinforcement congestion. Particular attention
shall be given to the spacing and arrangement of stirrups at the vicinity of the
rectangular dowel holes. In the case of skewed bridges, a plan detailing the
arrangement of the stirrups and the dowel holes shall be included on the drawings.

m) The distance from the end of the bearing to the end of the girder shall be specified as
100 mm.

n) Shear design shall assume 13 mm size of aggregate. OPSS 909 requires that 19.0
mm aggregate be used for precast girders but the precaster may request the use of
13.2 mm aggregate size for girders with congested reinforcement.

March 2024 Page 4 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

o) When premium reinforcement is required for stirrups in precast girders, it shall be of


stainless steel according to Section 12 of this manual. GFRP stirrups shall not be
used.

7.2.2 Precast Prestressed Girder Sizes

The available metric girder sizes that the ministry currently uses are:

a) NU Girders 900, 1200, 1400, 1600, 1800, 1900, 2000, 2400.

b) Box Girders 700, 800, 900, 1000.

c) Solid Slabs 300, 400, 500.

7.2.3 Debonded Strands

Debonding of strands shall be accomplished with rigid polymer sheathing with a wall
thickness of not less than 1 mm.

As it is possible for moisture to penetrate around debonded strands from the ends of
girders, debonded strands shall not be used at the ends of girders at expansion joints.

7.2.4 Precast, Prestressed Solid Slabs (Precast Planks) and Voided Girders

Precast sections of less than 700 mm depth shall not have voids. The addition of voids
adds greatly to the complexity and saves relatively minimal dead load on the girder.

When used with spaces between the units, these members shall be regarded as precast
girders and the deck slab shall be designed in accordance with normal composite deck
slab requirements.

CHBDC Clause 8.21 gives requirements for interconnection of units placed side by side
in contact.

Non-standard precast sections may be used in the construction of cast-in-place bridges


with an approval of Structures Office (e.g., for the deck of a rigid frame bridge over
railway). Precast sections with a span of greater than 10 m shall be prestressed.

7.2.5 Temporary Bracing

In order to ensure that prestressed precast concrete NU girders are provided with
adequate safety and stability provisions at the time of installation, the ministry has created
minimum bracing requirements to prevent any possible movements, overturning or tipping
of the installed girders until the time when the contractor can implement their formwork
design. As a minimum, contractors are required to brace the girders by attaching the
girder ends at each support location to the faces of abutments and piers and also provide
in-span bracings within each span.

March 2024 Page 5 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

The ministry has created a Structural Standard Drawing (SSD) SS 107-9 for this purpose.
Designers of bridges that have prestressed precast concrete NU girders are required to
include Structural Standard Drawing SS 107-9 in the structural drawings package.

The deck formwork designer must not rely solely on the temporary restraints provided by
these temporary bracing that are used solely for the stability of the girder. Additional or
different temporary struts; bracing, tie bars/cables and other devices shall be used for
temporary restraint, as required by formwork design, in order to carry all loads imposed
during each stage of construction. When working platforms are provided between the
bottom flanges of the girders they should be stabilized together appropriately.

Temporary struts, bracing, tie bars/cables and other devices used for temporary restraint
shall be removed upon completion of the structure.

7.2.6 Side by Side Precast Prestressed Concrete Box Girders Type Bridge

Bridge decks made of side-by-side precast prestressed concrete box girders with an
integral 150 mm topping cast in place concrete slab do not require shear keys between
adjacent boxes nor transverse stressing. Such units shall have a steel plate welded
connection tying them together following erection as shown on Structural Standard
drawings to:

a) Ensure their stability during construction;

b) Prevent differential deflection during placement of the concrete deck, which would
cause cracking of partially setup concrete; and,

c) Prevent exterior girders from differentially deflecting and/or separating from the
adjacent girders when they are loaded in torsion during the deck placement due to the
deck cantilever overhang, or sidewalk that is detailed to be poured at the same time
as the deck slab, or if the bridge is on a large skew.

For side-by-side box girder bridges that are designed without a topping slab, the designer
shall design and detail shear keys between neighbouring boxes to fully carry the shear
between the boxes. In this case, the thickness of the top slab of the box itself is usually
much thicker than that of a standard box used with a topping slab. Waterproofing and
paving are usually applied directly over the shear-keyed side-by-side boxes.

7.2.7 Establishing Screed Elevations

CHBDC Clause 8.13.3.4 allows designers to estimate long-term deflections by multiplying


instantaneous deflections by appropriate factors. These factors, or “multipliers” are given
in the code commentary Clause C8.13.3.

This Multipliers method originated from many documents published by the


Precast/Prestressed Concrete Institute (PCI) and the Canadian Precast prestressed
Concrete Institute (CPCI). However, they do caution the reader regarding the applicability
of these multipliers when it comes to bridge girders where a large cast-in-place deck slab
is made composite with them, as is usually the case in Ontario.

March 2024 Page 6 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

Screed elevations shall not be established using long-term deflections. The designers
shall establish the screed elevations by including allowances for the roadway profile and
the deflection due to the weight of the wet concrete slab and superimposed dead loads.
The deflection due to the weight of the wet concrete slab and superimposed dead load
shall be multiplied by a factor of 1.10.

7.2.8 Establishing the Required Undercut and Stirrup Projection

Although the “final” deflection multipliers specified in Table C8.8 of the commentary to the
CHBDC should not be used in calculating the long-term deflections for precast prestressed
girder type bridges, the deflections and rotations at the time of erection correlate closely
to the use of the “at erection” multipliers specified in the commentary table referenced
above. This can be explained by the fact that, at this stage, the time dependant effects
are acting on the prestressed member alone and not on the composite section. As a
result, the “at erection” multipliers are providing accurate predictions of deflections and
rotations due to prestress and self-weight of the girder. At the erection stage, the
deflections and rotations due to the weight of the wet concrete are instantaneous and do
not require a multiplier (i.e., the multiplier is 1.0).

For composite action, according to the code, the stirrups must extend sufficiently into the
deck to engage the bottom mat of reinforcing steel. The top of the stirrups must also be
at least 100 mm below the top of the deck if black steel reinforcing bars are specified. The
projection of the stirrups above the top of the girder shall be established for the erection
stage. Stirrups along the length of the member can have different projection lengths
specified when required by the design.

The purpose of the bearing soffit undercut is to ensure proper contact between the girder
and the elastomeric bearing when all the dead loads have been applied. In calculating
the undercut, the structure grade ‘G’, camber due to prestress ‘C’ as well as deflections
due to the girder self weight and the wet concrete ‘D’ should be considered (camber and
deflections in this case refer to the resulting rotations). At the low end, dimension ‘b’
shown on the Structural Standard Drawing containing the girder details, is a function of
+G-D+C. At the high end, dimension ‘c’ is a function of +G+D-C. Therefore ‘b’ and ‘c’
may differ.

The maximum undercut dimension (‘b’ or ‘c’) that is allowed, in order to maintain proper
cover to the reinforcing steel, is 18 mm. When the undercut dimensions ‘b’ or ‘c’ exceed
18 mm, the embedded bearing plate detail shown on the MTO Standard drawings should
be used.

Requirements

1. The multipliers specified in Table C8.8 of the commentary to the CHBDC shall be used
when calculating the deflections and rotations for the girder erection stage.

2. The projection of the stirrups above the top of the girder shall be established for the
erection stage. Stirrups along the length of the member can have different projection
lengths specified w hen required by the design.

March 2024 Page 7 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

3. The bearing soffit undercut shall be established using the “at erection” multipliers when
calculating the rotations due to prestress and girder self weight and a multiplier of 1.0
when calculating the rotation due to the weight of the wet concrete.

7.2.9 Prestressed Girders Notes

Precast beams are generally detailed on Structural Standard Drawings which have the
notes pre-printed. If Structural Standard Drawings cannot be used, copy the appropriate
notes from them.

A) NOTES (On DECK DETAILS drawing, prestressed girder superstructure.)

1. SCREED ELEVATIONS ARE TO TOP OF CONCRETE DECK.

2. SCREED ELEVATIONS SHOWN IN TABLE INCLUDE AN ALLOWANCE FOR


VERTICAL CURVE, WEIGHT OF DECK SLAB AND SUPERIMPOSED DEAD LOAD.

3. CONCRETE IN DECK SLABS AND DIAPHRAGMS SHALL BE RETARDED USING


A TYPE B OR D ADMIXTURE TO ENSURE THAT THE CONCRETE REMAINS
PLASTIC FOR THE DURATION OF EACH PLACEMENT.

4. CONCRETE IN BARRIER WALLS OR SIDEWALK SHALL NOT BE PLACED UNTIL


ALL CONCRETE IN DECK SLAB HAS REACHED A STRENGTH OF 20 MPa.

5. FALSEWORK FOR THE CANTILEVER PORTIONS OF THE DECK SLAB (FOR A


LENGTH OF 2.0 m) SHALL NOT BE REMOVED UNTIL THE CONCRETE AROUND
THE INSTALLED EXPANSION JOINT HAS REACHED A STRENGTH OF 20 MPa
(TYP. AT ALL FOUR CORNERS OF THE BRIDGE).

6. ALL DIAPHRAGMS SHALL BE CAST INTEGRAL WITH DECK SLAB, AND


CONCRETE IN DIAPHRAGMS SHALL BE VIBRATED THOROUGHLY.

7.3 Post-Tensioned Concrete Decks

7.3.1 General

a) Post-tensioned superstructures, which are solid or voided by means of round tubes,


must be transversely prestressed throughout their length with reinforcing steel reduced
to a minimum. Transverse stressing is not mandatory for box section decks except as
required by (c) and (d) below.

b) For skew angles in excess of 20º, transverse prestressing cables and reinforcing steel
should be square to the deck except over skewed supports.

c) Transverse moments over piers and abutments shall be resisted by transverse


prestressing rather than reinforcing steel.

March 2024 Page 8 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

d) Wherever possible, the cantilever portion of cast-in-place, post-tensioned cross-


section shall be greater than 1.6 m. Deck cantilever overhangs exceeding 3.2 m in
length shall be prestressed.

e) For decks with circular voids, the length of the solid section at the anchorages shall be
at least equal to the distance from the centreline of the outside anchorage to the edge
of the deck measured perpendicular to the longitudinal centreline of the deck.

f) Post-tensioned decks shall be designed using 35 MPa concrete except, unless a


higher strength is needed for web crushing in rectangular voided sections or
compressive resistance of the bottom slab at piers.

g) To control internal concrete temperature during casting without supplementary cooling


measures, the thickness of solid slabs shall be limited to 1.0 m for 35 MPa concrete
and 0.7 m for 50 MPa concrete. This limit does not apply to solid end zones of voided
slabs or box sections.

h) The location of the outlets for cable duct vents and drains shall not be shown on the
drawings.

i) The location and limits of construction joints in box girders (e.g., between slabs and
webs) shall be clearly defined. This often requires that the joints be shown in plan or
elevation as well as in cross-section.

j) Chamfer strips shall be detailed around the perimeter of the concrete that constitutes
the bottom slab of rectangular voided post-tensioned decks.

k) In order to limit and contain spalling-type stresses, resulting from the shear caused by
bearing reactions, the distance from deck end to centreline of bearing shall not be less
than 0.8 m. This end distance for longitudinal cables may need to be even greater,
depending on skew of bridge, size of tendon, size of bearing, and depth of section.

l) Dead-end and live-end anchorages (including local zone components such as


anchorage plates, spirals, etc.) are to be fully detailed and supplied by the post-
tensioning supplier. Dead-end anchorages shall be detailed the same as live end
anchorages on design drawings. Bond-head anchorages shall not be used unless
approved the Head of Structure Section.

m) Anchorage recesses should be detailed based on the largest available anchorage


devices from listed suppliers.

n) The spacing of stirrups should be such that, wherever possible, a stirrup or row of
stirrups is located at each tendon ordinate location.

o) For box girders, longitudinal tendons in the webs, at their lowest point, shall be detailed
to above the top reinforcement of the bottom slab.

p) Post-tensioning couplers should be avoided. Instead, construction joints in long post-


tensioned bridges should be detailed with tendons lapped across blisters in the web.

March 2024 Page 9 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

If couplers are subjected to net tensile fatigue stresses, dynamic testing of the couplers
shall be specified.

q) Tendon curvature shall be limited to a 10 m radius for 19 strand tendons and larger,
except for loop tendons where smooth steel duct is required. Round tendons ducts,
excluding loops, shall have a minimum radius of 10 m.

r) Clearances around tendon anchorage shall be designed to allow stressing with multi-
strand jacks except for transverse tendons in flat ducts. Tendons should be designed
to be stressed horizontally, and preferably at deck level.

s) The diameter of a duct, or an equivalent diameter of a non-circular duct, shall not


exceed 40% of the least gross concrete section thickness at the location of the duct.

7.3.2 Circular Voided Decks

For spans of 28 to 43 m, the span-to-depth ratio of circular voided decks shall be no


greater than 26. A solid section may be more appropriate for spans less than 30 m, and
rectangular voids are more appropriate above 40 m.

Corrugated metal pipe void forms shall be used to form all round voids. Corrugated metal
pipe is available in any size over 150 mm diameter; but the following standard diameters
should be used in specifying the void sizes (mm): 600, 700, 800, 900, 1000, 1200, 1400,
1500.

The arrangement of void forms and longitudinal tendons must provide, between all void
forms, one unobstructed vertical passage of at least 100 mm in width as recommended in
the CHBDC Commentary to Section 8.

Standard Drawings showing void drainage (OPSD 3333 series) and hold down details
(OPSD 3332.100) shall be included in the design. Stirrups should be shaped so that void
forms can be lowered into place after the longitudinal cables have been placed.

7.3.3 Box Girder Voids and Access Locations

Access openings for the inspection and maintenance of concrete box sections shall be
provided where the cross-sectional depth is 1.8 m or greater. Box girders deeper than
2.4m shall have access openings through diaphragms between spans. The minimum
clearance for walking through intermediate or support diaphragms inside box girders shall
be 600 mm horizontally and 1200 mm vertically.

The number of access openings and their locations shall be as follows:

a) For concrete box girders with solid diaphragms: One opening per box cell;

b) For concrete box girders with walk-through diaphragms: Two openings per box girder,
one located adjacent to each end diaphragm.

March 2024 Page 10 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

The access openings shall be located to avoid or minimise interference with traffic during
inspection and should be easily accessible to inspectors.

7.3.4 Post-Tensioning Tendons, Ducts, Strands, Detailing

Grade 1860, Size Designation 15 (15.2 mm or 0.60" diameter), low relaxation strand shall
be specified for all tendons. The nominal area of size designation 15 strand is 140 mm².

Solid slab and circular voided post-tensioned structures do not require tendons larger than
size designation 19/15 (containing 19, Size 15 strands). In the case of trapezoidal voided
and box girder post-tensioned structures, large tendons are beneficial to reduce the width
of the web and/or increase the eccentricity of the strand and tendons up to size designation
37/15 may be used. Tendons anchored and stressed from within a box girder shall be no
larger than 19/15 to limit the size and weight of jacks.

Rigid ducts shall be detailed for the full length of longitudinal tendons in all cast-in-place
post-tensioned concrete bridges.

High strength bars may be used for vertical and transverse post-tensioning. Cold rolled
high strength threaded bears larger than 46 mm are not permitted.

7.3.5 Anchorage Slip for Post-Tensioning Systems

The CHBDC requires the magnitude of the anchorage slip to be either as required to
control the stress in the prestressing steel at transfer, or as recommended by the
manufacturer of the anchorage, whichever is greater. Stressing from two ends shall not
be specified when the calculated elongation is less than the length of the wedge grip.

The anchorage slip specified on the plans for strand post-tensioning systems shall not be
less than 8 mm for anchorages with up to 7 strands, 10 mm for anchorages with 8 to 12
strands, and 12 mm for anchorages with more than 12 strands. For post-tensioning bars,
the slip allowed for in design shall not be less than 1.5 mm.

On short tendons when anchorage slips losses are a major contributor to the total
prestress loss of the tendon, the designer may consider specifying power seating and lowe
slip values upon consultation with suppliers.

7.3.6 Post-Tensioning Tendons and Duct Sizes

Design of post-tensioning shall be done with commonly stocked tendon sizes, and
standard plastic duct sizes as shown in Table 7.3.1. Duct sizes are established to ensure
the inside cross-sectional area of the duct is at least 2.5 times the net area of the strand.
Duct diameters given are nominal and actual diameters can vary by ± 3 mm. OPSS 910
requires the use of plastic ducts and steel duct dimensions are provided for reference.

March 2024 Page 11 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

TABLE 7.3.1

No. of 15 mm Strands Plastic Duct I.D./O.D. Steel Duct I.D./O.D. (mm)


5 48/59 55/60
7 59/73 65/70
12 76/91 85/90
19 100/116 105/110
27 115/135 125/130
37 130/151 135/140

Tendons for transverse post-tensioning of deck slabs may use flat anchorages with up to
four strands and flat duct. Where flat ducts are used for transverse tendons in deck slabs,
internal dimensions area 25 x 76 mm and outer dimensions are 40 x 90 mm.

7.3.7 Post-Tensioning Tendon Duct and Web Details

Duct arrangements and corresponding reinforcement layout and web dimensions are
shown in Figure 7.3.1. Dimensions are based on 27/15 tendons.

FIGURE 7.3.1 – DUCT ARRANGEMENT FOR RECTANGULAR VOIDS

7.3.8 Additional Reinforcing in Exterior Webs Adjacent to Tapered Voids

In order to prevent tendons breaking into the tapered voids, additional reinforcing is
required to resist the radial forces caused by horizontally curved tendons. A detailed plan
and cross-section through tapered portions of the voided section must be shown on
contract drawings. No splices of duct sheathing shall be allowed along the tapered portion
of void, and within one metre from either end of it, to reduce the risk of tendon kinking.

March 2024 Page 12 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

7.3.9 Post-Tensioned Deck Notes

The following are standard notes of the type shown below the title block on the appropriate
drawing. The notes must be worded to cover the requirements specific to the project and
should only be used if applicable. Other notes may be required in special circumstances.
In specifying the 28-day Compressive Strength of concrete, different components may be
itemised together if the Specified 28-day Compressive Strengths are the same. For clarity
the wording of the notes is shown in upper case (capital) lettering. Explanations shown in
brackets in lower case lettering are not part of the notes.

A) General Notes

1. ALL TENDON ANCHORAGES SHALL BE INTERNAL TYPE AS SHOWN ON THE


DRAWINGS.

2. DUCT GROUTING VENTS SHALL BE PROVIDED AT HIGH POINTS AND AT BOTH


ENDS OF ALL TENDONS. DRAINS SHALL BE PROVIDED AT LOW POINTS.

3. MIN. CLEAR COVER TO TENDONS DUCTS:

TOP ± … LONGIT.
± … TRANSV.

ELSEWHERE 80 ± 10

4. WELDING IS NOT PERMITTED WITHIN 3000 mm OF ANY TENDON OR TENDON


DUCT.

5. ALL TENDONS SHALL BE STRESSED IN THE NUMERICAL ORDER SHOWN ON


THE DRAWINGS.

6. SPECIFIED 28-DAY COMPRESSIVE STRENGTH: 35 MPa.

7. CONCRETE STRENGTH BEFORE STRESSING: 25 MPa.

8. ALL ANCHORAGE RECESSES SHALL BE ABRASIVE BLASTED AND COATED


WITH AN APPROVED CEMENT PASTE PRIOR TO CASTING OF 35 MPa
CONCRETE IN THE RECESSES. CONCRETE IN RECESSES SHALL BE COLOUR
MATCHED WITH ADJACENT CONCRETE.

9. THE POST-TENSIONING SUPPLIER SHALL DETAIL AND SUPPLY LIVE-END AND


DEAD-END ANCHORAGES INCLUDING SPIRALS, THE METHOD OF SUPPORT
AND ASSOCIATED REINFORCEMENT.

10. PRESTRESSING TENDONS SHALL HAVE THE NUMBER OF STRANDS AS


INDICATED IN THE TABLE(S).

11. PRESTRESSING STEEL SHALL BE LOW RELAXATION SEVEN WIRE STRAND,


SIZE DESIGNATION 15, GRADE 1860, AND SHALL MEET THE REQUIREMENTS

March 2024 Page 13 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

OF ASTM A416/A416M. MINIMUM BREAKING STRENGTH SHALL BE 260 kN PER


STRAND.

12. SHEATHS FOR POST-TENSIONING DUCTS SHALL BE CORRUGATED PLASTIC.

B) Longitudinal Tendons

1. TENDON SIZE, REQUIRED ELONGATION, AND JACKING FORCE SHALL BE AS


SHOWN IN THE TABLE BELOW. (Use "STAGE" column in table if superstructure is
staged construction.)

ELONGATIONS SHOWN ARE APPROXIMATE AND MAY BE ADJUSTED BY MTO


AFTER THE ACTUAL STRESS-STRAIN PROPERTIES OF THE STRAND TO BE
USED ARE AVAILABLE.

ASSUMED Ep=200 000 MPa, K=0.001, μ=0.14

TENDON DUCT JACKED JACKING ELONGATION REQUIRED


STAGE LOCATION TYPE
SIZE OD (mm) FROM FORCE (kN) (mm) SLIP (mm)

(Jacking data should be given for simultaneous jacking from both ends and also for
jacking at one end followed by final take up jacking at the other.)

2. DUCTS FOR PRESTRESSING STEEL SHALL BE SECURELY FASTENED IN


PLACE TO PREVENT MOVEMENT UNTIL CONCRETE IS PLACED AND
HARDENED. DUCTS SHALL BE SUPPORTED AT INTERVALS NOT EXCEEDING
600 mm OR AS SHOWN ON THE DRAWINGS.

C) Transverse Tendons

1. TENDON SIZE, REQUIRED ELONGATION, AND JACKING FORCE SHALL BE AS


SHOWN IN THE TABLE BELOW.

ELONGATIONS SHOWN ARE APPROXIMATE AND MAY BE ADJUSTED BY MTO


AFTER THE ACTUAL STRESS-STRAIN PROPERTIES OF THE STRAND TO BE
USED ARE AVAILABLE.

ASSUMED Ep=200 000 MPa, K=0.001, μ=0.14

TENDON DUCT OD JACKED JACKING ELONGATION REQUIRED


LOCATION TYPE
SIZE (mm) FROM FORCE (kN) (mm) SLIP (mm)

March 2024 Page 14 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

(Jacking data should be given for simultaneous jacking from both ends and also for
jacking at one end followed by final take up jacking at the other).

2. DUCTS FOR PRESTRESSING STEEL SHALL BE SECURELY FASTENED IN


PLACE TO PREVENT MOVEMENT UNTIL CONCRETE IS PLACED AND
HARDENED. DUCTS SHALL BE SUPPORTED AT INTERVALS NOT EXCEEDING
500 mm OR AS SHOWN ON THE DRAWINGS.

3. FOR GENERAL NOTES, SEE DWG. …

D) NOTES (On DECK DETAILS drawing, post-tensioned superstructure.)

1. NO ALLOWANCE IS REQUIRED FOR DEAD LOAD DEFLECTION.

2. THE SCREED ELEVATIONS SHOWN ARE TO BE ADJUSTED FOR FALSEWORK


DEFLECTION ONLY, BEFORE THEY ARE USED FOR SETTING SCREEDS.

3. ALL ELEVATIONS ARE TO TOP OF CONCRETE AS SHOWN.

The following notes are applicable only to trapezoidal-voided post-tensioned


box-girders:

4. DRAINAGE TUBES TO BE LOCATED AT LOW POINT OF VOID CROSS-SECTION.

5. FORMWORK USED TO FORM VOIDS SHALL BE REMOVED AFTER CONCRETE


STRENGTH HAS REACHED 20 MPa.

6. FOR ACCESS HATCH DETAILS, SEE DWG. …

The following note shall be included on the Deck Detail drawing for post-tensioned
deck bridges constructed in stages:

THE CALCULATED APPROXIMATE VERTICAL DEFLECTION BETWEEN THE TIP OF


THE CANTILEVER AND SUBSEQUENT STAGE, IS AS FOLLOWS:

STAGE 1: …
STAGE 2: … etc.

THE CONTRACTOR SHALL VERIFY THE DEFLECTION AND ADJUST THE SOFFIT
FORMS, AND/OR FALSEWORK, TO PROVIDE A SMOOTH TRANSITION FOR A
MINIMUM DISTANCE OF 1.2 m FROM THE END OF THE PREVIOUS STAGE.

E) Sequence of Deck Construction (On DECK DETAILS drawing, for solid or


circular -voided post-tensioned superstructure.)

1. PLACE CONCRETE IN DECK EXCEPT AT (SIDEWALKS, MEDIAN, CURBS AND


BARRIER WALLS) PRESTRESSING ANCHORAGE RECESSES, AND EXPANSION
JOINTS.

March 2024 Page 15 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 7 - PRESTRESSED CONCRETE

2. STRESS ALL TRANSVERSE TENDONS AT PIERS AND ABUTMENTS, THEN IN


SPANS, WHEN CONCRETE IN DECK HAS REACHED A STRENGTH OF 30 MPa.

3. STRESS ALL LONGITUDINAL TENDONS AFTER CONCRETE IN TRANSVERSE


ANCHORAGE RECESSES HAS REACHED A STRENGTH OF 30 MPa.

4. GROUT ALL TRANSVERSE AND LONGITUDINAL TENDON DUCTS.

5. PLACE 35 MPa CONCRETE AT RECESSES FOR ALL LONGITUDINAL AND


TRANSVERSE TENDONS.

6. PLACE CONCRETE IN SIDEWALKS, MEDIAN, CURBS AND BARRIER WALLS.

F) Sequence of Deck Construction (On DECK DETAILS drawing, for


trapezoidal -voided post-tensioned superstructure.)

1. PLACE CONCRETE IN BOTTOM SLAB (ACCESS HATCH IN POSITION).

2. PLACE REMAINING CONCRETE IN DECK EXCEPT AT (SIDEWALKS, MEDIAN,


CURBS AND BARRIER WALLS) PRESTRESSING ANCHORAGE RECESSES AND
EXPANSION JOINTS.

3. STRESS ALL TRANSVERSE TENDONS AT PIER(S) AND ABUTMENTS WHEN


CONCRETE IN DECK HAS REACHED A STRENGTH OF 30 MPa.

4. PLACE CONCRETE AT TRANSVERSE ANCHORAGE RECESSES.

5. STRESS ALL LONGITUDINAL TENDONS AFTER CONCRETE IN TRANSVERSE


ANCHORAGE RECESSES HAS REACHED A STRENGTH OF 30 MPa.

6. PLACE 35 MPa CONCRETE AT RECESSES FOR ALL LONGITUDINAL TENDONS.

7. GROUT ALL TRANSVERSE AND LONGITUDINAL TENDON DUCTS.

8. PLACE CONCRETE IN SIDEWALKS, MEDIAN, CURBS AND BARRIER WALLS.

(The notes above apply to single stage construction. If the deck is cast and stressed in
multiple stages, the order of steps 6 and 7 should be reversed).

March 2024 Page 16 of 16 SM-D2-S07


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

Table of Contents

8 STRUCTURAL STEEL ......................................................................................... 3


8.1 Design .......................................................................................................................... 3
8.1.1 General ................................................................................................................. 3
8.1.2 Structural Steel Design Requirements .................................................................. 3
8.1.3 Protection of Steel ................................................................................................ 5
8.1.4 Use of Steel I-Girders Over Roadways ................................................................. 6
8.1.5 Tunnelling Effects ................................................................................................. 8
8.1.6 Use of ACR Steel Girders Over Water Crossings ................................................. 9
8.1.7 Vegetation ............................................................................................................ 9
8.1.8 Standardised Nomenclature for Structural Steel Shapes .....................................10
8.1.9 Structural Steel Box Girders Temporary Bracing..................................................10
8.1.10 Identification of Tension Zones ............................................................................10
8.1.11 Construction Stage Design Requirements ...........................................................11
8.1.12 Concrete Cantilever Overhang .............................................................................11
8.1.13 Girder Flange Widths Between Splices ................................................................12
8.1.14 Transitions of Box Girder Flange and Web Thicknesses ......................................12
8.1.15 Bolt Grid...............................................................................................................12
8.2 Structural Steel Girders Profile ....................................................................................13
8.2.1 Camber ................................................................................................................13
8.2.2 Elevations ............................................................................................................14
8.2.3 Example: 2-Span Steel Box Girder ......................................................................14
8.3 Details .........................................................................................................................15
8.3.1 Structural Steel Box Girders Bottom Flanges .......................................................16
8.3.2 Box Girder Drainage and Ventilation ....................................................................16
8.3.3 Access to Box Girder Voids .................................................................................17
8.3.4 Drip Tab Details ...................................................................................................18
8.3.5 Girder Web Spacing.............................................................................................19
8.4 Stiffeners and Connection Plates ................................................................................20
8.4.1 Coping of Stiffeners and Gusset Plates................................................................20
8.4.2 Fillet Weld Terminations ......................................................................................21
8.4.3 Lateral Bracing.....................................................................................................22
8.4.4 Vertical Stiffeners .................................................................................................22
8.4.5 Bearing Stiffener to Flange Connection................................................................23

March 2024 Page 1 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

8.4.6 Intermediate Stiffener to Flange Connection ........................................................24


8.4.7 Stiffener to Web Connection ................................................................................24
8.4.8 Intersecting Longitudinal and Transverse Stiffeners .............................................25
8.4.9 Box Girder Web Stiffeners ...................................................................................25
8.4.10 Transition Radius for Longitudinal Stiffeners and Gusset Plates ..........................26
8.4.11 Bottom Flange Stiffener Details ...........................................................................27
8.4.12 Clipping Connection Plates ..................................................................................28
8.5 Frames, Bracing and Diaphragms ...............................................................................28
8.5.1 Frames for Intermediate Bracing ..........................................................................28
8.5.2 Box Girder Bracing...............................................................................................29
8.5.3 Intermediate Diaphragms in Shallow Girders .......................................................29
8.5.4 Box Girder Diaphragms at Piers and Abutments ..................................................29
8.6 Weld Details ................................................................................................................30
8.6.1 Transition of Web Thickness ................................................................................30
8.6.2 Transition of Flange at Butt Welds .......................................................................31
8.6.3 Grinding of Butt Welds .........................................................................................32
8.6.4 Bearing Shoe Plate Welds ...................................................................................33
8.7 Structural Steel Notes .................................................................................................33
8.8 Steel Truss and Arch Design .......................................................................................37

March 2024 Page 2 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

8 STRUCTURAL STEEL

8.1 Design

8.1.1 General

The Structural Manual builds on current design and detailing requirements of the CHBDC.
Since the 1960s, MTO has moved towards atmospheric corrosion resistant (ACR) steel to
reduce long-term maintenance costs of steel bridges.

The design of an uncoated ACR steel bridge needs to consider the general geography in
which the bridge is located (macro-climate), as well as the local, site-specific
characteristics of its location (micro-climate). To achieve the performance expected of
uncoated ACR steel, prolonged exposure to wetness without opportunity to dry, and
exposure to high levels of chlorides (Cl-) need to be prevented.

Time of wetness may be a quantitative measure of the amount of time the relative humidity
is greater than 80% and the temperature is above freezing, expressed in hours per year.
Prolonged wetness may occur when there is:

• High humidity due to either the general climate or local effects such as surface
water or vegetation growing against the bridge;

• Roadway or marine salts which slow the drying process and accelerate corrosion;
and,

• Debris that traps moisture.

The goal of design and detailing is to prevent the conditions above from occurring.
Generally, the structure details should be approached with the mindset of promoting self-
cleaning and easy discharge of water to the extent possible. The requirements of Section
8 will permit the use of uncoated ACR steel for girders on most highway bridges in Ontario.

For locations with past performance deficiencies of ACR steel (a stable patina has not
developed, and the corrosion product flakes off), replacement with uncoated ACR steel is
not recommended. For these locations, enhanced corrosion protection (i.e., metalized or
A1010 trapezoidal box girders) may be specified by the Structural Section.

8.1.2 Structural Steel Design Requirements

a) All structural steel used in highway structures shall be weldable and notch-tough steel.
Steel shall conform to CSA standard G40.20/G40.21 Type AT or WT and shall be
specified on the contract drawings. The notch-tough requirements for fracture critical
and primary tension members shall be 27 Joules and the test temperature shall be
dependent on the service temperature and as specified in Table 10.14 and
Table 10.15 of the CHBDC.

Rolled sections shall conform to CSA Standard G40.20/G40.21, ASTM specification


A588 or A709. ASTM A709 atmospheric corrosion resistant steel grades shall be
designated with a W suffix.

March 2024 Page 3 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

(Note: ASTM A588 may be substituted for G40.21 Grade 350AT steel when the notch-
toughness requirements are verified by the submission of test documentation.)

b) Section 10 of CHBDC defines primary tension members as members, or portions of


members, including attachments, other than fracture-critical members and secondary
components, that are subject to tensile stress. Girders and attachments fabricated
from plate material shall be made from notch-tough grade steel.

c) All primary members as well as secondary members designed for the forces they
attract, as would be the case for curved or highly skewed bridges, shall be Type AT or
WT.

d) Secondary members of straight bridges or bridges with a skew less than 20 degrees
may be specified as Type A or W.

e) Secondary members of curved bridges or highly skewed bridges shall be designed for
the forces they are subjected to and shall have the same notch-toughness
requirements as the primary members.

f) All girders shall have the same cross-section. Exterior longitudinal girders not have
less capacity than interior girders.

g) The availability of the required widths and thicknesses of steel plates should be
confirmed before finalising the design. Available lengths are sometimes of importance
in relation to the positioning of field splices. Longitudinal splices in web plates are not
permitted when depths are less than 3.8 m.

h) Plate girders shall be specified rather than specifying welded wide flange (WWF) and
welded reduced flange (WRF) designations.

i) ASTM F3125, Grade A325M, Type 1 galvanized bolts shall be used on coated steel
and Type 3 shall be used for all connections of uncoated ACR steel. Bolts shall be
22 mm diameter, except that where large numbers are required, in restricted spaces,
1” diameter may be used. For bridges with spans greater than 50 m, bolts shall be 1”
diameter.

(Note: ASTM A490M Type 3 bolts may be substituted for ASTM F3125, Grade A325M
Type 3 bolts on atmospheric corrosion resistant steel, but galvanized A490 Type 1
bolts are not permitted because of delayed fracture due to hydrogen embrittlement.)

j) Shear stud connectors shall be 22 mm diameter, not larger, due to limitations of the
welding equipment used by fabricators.

k) Any temporary or permanent field welding on all primary and secondary members is
not permitted except at the bearing shoe plate connection and for field shear connector
installation. If field welding is unavoidable, a written approval from the Head, Structural
Section is required. All field splices shall be designed with bolted connections.

l) Jacking points and loads must be shown.

March 2024 Page 4 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

m) Uncoated exterior girders shall be checked for structural adequacy assuming a


1.5 mm loss of steel section for:

1. Girder webs and bottom flanges adjacent to longitudinal median joints, which are
not protected from splashing from the roadway above by a solid barrier as shown
in Figure 8.1.1(a). Narrow, longitudinal joints are not preferred from a durability
perspective, see 9.2.1.

2. Girder webs adjacent to open railings for bridges with steel box-girders as shown
in Figure 8.1.1(b);

3. Girder webs and bottom flanges adjacent to open railings for bridges with steel I-
girders as shown in Figure 8.1.1(c).

FIGURE 8.1.1 – STEEL GIRDERS BELOW LONGITUDINAL JOINT AND OPEN


RAILINGS

8.1.3 Protection of Steel

An approved shop applied coating is required to protect structural steel at abutments and
deck expansion joints from salt laden water run off. The coatings should be applied as
follows:

• Except for integral and semi-integral abutment bridges, all structural steel surfaces
including diaphragms and bracing, but excluding surfaces in contact with concrete and

March 2024 Page 5 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

the contact surfaces of bolted joints shall be coated for a distance of 3000 mm from
the ends of the girders.

• For integral abutment bridges all structural steel surfaces, except diaphragms buried
in concrete, shall be coated for a distance of 700 mm as follows: from the face of the
abutment 100 mm towards the ends of girders and 600 mm towards the centre of
girders. The colour of the finish coat shall be indicated on the drawings (see Section
8.7).

• For semi-integral bridges all structural steel surfaces, except the areas of girders and
diaphragms encased in concrete, shall be coated as follows: from the ends of the
girders to 600 mm beyond the front face of the abutment. The colour of the finish coat
shall be indicated on the drawings (see Section 8.7).

• Field splices, at the outside face of exterior girders of I-girder bridges, are susceptible
to deterioration at the bottom flange where debris accumulate and trap moisture from
wind-driven rain and runoff. Field splices of exterior I-girders shall be coated per
Section 8.7. This phenomenon does not occur with box girders, and they shall not be
coated at field splices.

• Lapped surfaces of sign and light posts are susceptible to crevice corrosion. Contact
surfaces at lap joints shall be coated.

8.1.4 Use of Steel I-Girders Over Roadways

Uncoated ACR steel I-girders shall only be used for the ranges of posted speeds and
vertical clearances shown in Figure 8.1.2, along with the protection specified in this
manual. Where I-girders are not permitted, trapezoidal box girders shall be used.

Partially coated ACR steel I-girders may be used where metallizing is permitted within
Figure 8.1.2.

Fully coated steel I-girders (hot dip galvanized, metallized with a DSM seal coating, or a
paint coating system) are permitted within the coated and uncoated range of Figure 8.1.2.

March 2024 Page 6 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.1.2 – USE OF ACR I-GIRDERS OVER HIGHWAYS

Notes:
1. ACR steel girders may be uncoated except as required by Section 8.1.3 at girder ends
and Section 8.7 at splices of exterior girders.
2. Coated ACR steel I-girders shall have a paint coating of at least the following limits
(although a greater extent may be specified for convenience):
• Exterior girders for the entire length of the bridge with protection of the exterior
top flange, exterior web, entire bottom flange, and 500 mm up the inside face
of the web (Figure 8.1.3a); and,
• Interior girders, over travelled lane(s) for a length 10m beyond the edge of any
future travelled lane(s), with protection of the bottom flange and 500 mm up
each face of the web (Figure 8.1.3b); and,
• As required by Section 8.1.3 at girder ends and Section 8.7 at splices of
exterior girders.

March 2024 Page 7 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.1.3 – PAINT COATING MINIMUM LIMITS

Steel I-girders which are not fabricated from ACR steel shall be Type WT, and shall be
coated for the full section and length with:

a) Hot dip galvanizing; or,

b) Metallizing with a DSM seal coat.

Even where I-girders are permitted, steel trapezoidal box girders are preferred because
they have a much lower exposed surface area. Box girders are also less likely to enable
bird nesting and entrap salt and debris and are easier to inspect. I-girders are appropriate
for most railway and water crossings. Connecticut Department of Transportation findings
suggest that stray current from electrified rail line crossings may affect the corrosion rate
in existing bridges so proper electrical insulation from electrified rail is recommended.

In recent years, MTO has built a few bridges using ASTM A1010 steel (now included in
ASTM A709 as Grade 50CR). This steel has a high (11%) chromium content (which is
just below the threshold to be considered a stainless steel) and could also be considered
acceptable for locations where ACR I-girders are not permitted. Approval is required from
the Structural Section for the use of A1010 steel until standard material and fabrication
specifications are developed.

Deviations from the policy above require approval from the Structures Office.

8.1.5 Tunnelling Effects

Vertical clearance requirements were introduced to prevent the splash and spray of traffic
from increasing local corrosion rates in the structure. However, sites with limited
horizontal and vertical clearances can produce a micro-climate often referred to as a
tunnel effect. Steel girder bridges that are determined to be subject to tunnelling effects
shall be fully coated. Increased local corrosion is frequently observed on the bottom flange
of girders directly over travel lanes of grade separation structures, and the fascia of the

March 2024 Page 8 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

inbound girder. Sheets of unbonded patina often develop in these locations which may
fall off the structure and pose a risk to traffic below.

Factors and their values resulting in a tunnel effect have not been definitively identified
and research is ongoing. Factors hypothesized to influence tunnelling effects include a
combination of:

• Vertical and horizontal clearance, combined with variation in roadway elevation


(smaller clearance is worse);

• Width of overpassing structure (wider is worse);

• Proximity of the abutment/pier to the travel lane (closer is worse);

• Average daily traffic (related to quantity of de-icing agents; higher is worse);

• Local wind conditions.

In the absence of high amounts of de-icing agents, low clearances do not generally appear
to be detrimental to the performance of uncoated ACR steel. However, the designer
should consider the possibility of tunnelling effects when there is a combination of the
factors above. The structure’s micro-climate may be assessed by referencing the National
Steel Bridge Alliance (NSBA) Uncoated Weathering Steel Reference Guide, 2022.

8.1.6 Use of ACR Steel Girders Over Water Crossings

Uncoated ACR steel girders shall not be used over water crossings where prohibited by
Table 10.1 of the CHBDC.

Higher humidity areas result in condensation on the structure that accelerates corrosion
and doesn’t permit the protective patina to develop. Limited vertical clearance over water
can cause a localized increase in time of wetness relative to the surrounding macro-
climate.

If the macro-climate of the site does not contain a high time of wetness (i.e., does not
exceed 2500 hours/year at greater than 60% relative humidity), and minimal vegetation
is present within 3m of the structure, there are no concerns with using uncoated ACR
steel.

8.1.7 Vegetation

Vegetation in, or nearly in, contact with uncoated ACR steel shall be prevented where
doing so is not detrimental to the surrounding environment and environmental regulations
permit doing so. Growth of vegetation may be considered during the maintenance of a
bridge, but the design should provide a suitable environment. A 3 m clear zone of rock fill
or scrub/grasses shall be provided at each side of the wingwalls to permit sunlight to shine
on the superstructure.

March 2024 Page 9 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

8.1.8 Standardised Nomenclature for Structural Steel Shapes

The designations for various structural sections are standardised as listed below.

TABLE 8.1.1 – DESIGNATIONS FOR VARIOUS STRUCTURAL SECTIONS

Shape Designation Structural Section Example


C Standard Channels C230x30
HP H-Pile Sections HP310x79
HSS Hollow Structural Sections HSS101.6x50.8x3.18
Angles
L L203x102x13
(Give nominal leg x leg x thickness.)
M Miscellaneous Shapes M250x13.4
MC Miscellaneous Channels MC250x37
MT Structural Tees. Cut from M Shapes. MT100x24.3
S American Standard Beams S460x104
ST Structural Tees. Cut from S. Shapes. ST 150x37.3
Wide Flange.
W W410x67
(Give nominal depth x mass per unit length.)
WT Structural Tees. Cut from W Shapes. WT305x108.5
Z Zeds Z130x17.3

Standard designation for steel plate is thickness x width x length, e.g., PL14 x 510 x 3050.
Specify all dimensions in mm.

8.1.9 Structural Steel Box Girders Temporary Bracing

For concrete deck slabs on steel girder bridges to be designed using the empirical method,
the CHBDC requires that cross frames or diaphragms, at a maximum spacing of 8.0 m c/c,
be provided throughout the full cross section width of the bridge, inside and between box
girders.

When such diaphragms or cross frames are not provided, temporary bracing to prevent
displacement or twisting of the girders may be required, particularly when the deck is
placed. The designer shall check the stability of the girders during the deck placement,
and if temporary bracing is required, the requirements shall be indicated on the contract
drawing. Tack welding the reinforcing steel to the studs is not allowed.

8.1.10 Identification of Tension Zones

To ensure that tension zones in structural steel girders are properly identified so that they
can receive the required level of testing during fabrication, the designer shall identify the
tension zones for weld testing for the top and bottom flanges on the girder elevation view
of the structural steel drawing. See Figure 8.1.4 for example.

March 2024 Page 10 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.1.4 – DRAWING SHOWING TENSION ZONES FOR WELD TESTING

8.1.11 Construction Stage Design Requirements

The designer shall design the structure considering the non-composite structural steel
construction stage (loads due to structural steel, formwork, cantilever brackets, wet
concrete and construction live loads such as screed machine, equipment, personnel, etc.)
as well as the subsequent stages and their contributions to the final stresses in the girder.
Intermediate diaphragms and bracing shall be provided to ensure structural adequacy for
all construction stages and, except for bridges over freeways, shall remain in place even
if some can theoretically be removed after the concrete deck has attained its full 28-day
specified strength.

The flanges of exterior girders shall be designed for the combined effect of longitudinal
loading and transverse loading due to the wet deck, live load, and the curvature of the
girders (if present). Intermediate bracing and connections shall be designed to resist the
torsional and transverse moments on the exterior girder due to the cantilever overhang.

OPSS 919 requires screed rails be placed directly over the flange of the exterior girders
within 0.1 m of the centreline of the web. In staged construction of the deck of steel girder
bridge where only a single lane width of the bridge is constructed, this requirement is at
odds with the requirement of OPSS 904 to use a mechanical screed machine to finish the
deck, and it is necessary to place the screed rails at the outside of the deck cantilever
overhang. When this is the case, the flanges shall also be designed for the transverse
loading due to the screed loads acting on the cantilever overhang and if additional
temporary bracing is required for the deck pour, the requirements shall be clearly noted in
the Contract.

8.1.12 Concrete Cantilever Overhang

For girder depths ≤ 2 m, the overhang of the bridge deck over the steel girder shall be at
least equal to the depth of the girder to avoid direct wetting by rain (Figure 8.1.5).

March 2024 Page 11 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.1.5 – MINIMUM CANTILEVER OVERHANG

8.1.13 Girder Flange Widths Between Splices

The plate width used for any one flange should be kept constant between field splices.

Flanges for girders are purchased in economical multi-width plates. Where a change in
flange thickness occurs, the mill plates are butt welded together. If the flange width is
constant for a given shipping length, the plates can be stripped into multiple flanges in one
continuous operation.

8.1.14 Transitions of Box Girder Flange and Web Thicknesses

Except when the bridge is to be erected by launching, flange thickness transitions should
be made so that a constant depth web plate is maintained. Flange thickness transitions
made so that a constant web depth is maintained simplifies fabrication and results in
economy.

Web thickness transitions should be made to maintain a flush outer box girder face. Web
thickness transitions made so that a flush outer face is maintained, facilitates web splice
details. If a horizontal web stiffener is required by design, a flush outer face makes
fabrication easier. Note that eccentric transitions produce small local bending effects
which can be significant where elastic instability is possible, e.g., in tension plates
temporarily subject to compression during construction.

8.1.15 Bolt Grid

Bolt holes should be set on an 80 mm x 80 mm grid, or multiples of 80 mm, to facilitate


the use of multi spindle drills (see Figure 8.1.6).
The use of a standard grid pattern simplifies fabrication and results in economies. The
spacing shall be sufficiently for sealing of the plies to avoid crevice corrosion.

March 2024 Page 12 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.1.6 – POSSIBLE BOLT LAYOUT IN A FIELD SPLICE

8.2 Structural Steel Girders Profile

8.2.1 Camber

Camber is defined as the built-in deviation of a bridge member from straight, when viewed
in elevation. It is intended to compensate for deflections due to all dead loads and usually
includes the roadway profile.

Relaxed camber is the camber which compensates for deflection due to all dead loads,
including girder + slab + superimposed dead loads, plus the roadway profile. This is
necessary since in the process of fabrication, the self-weight of girders is not acting due
to the method of girder support. The contract drawings must show the relaxed camber
diagram. Girders are cambered to the values shown in the relaxed camber diagram. The
camber cutting diagram, used by the fabricator to cut the web plates to shape for girder
segments, is calculated by them based on the relaxed camber diagram, and shown only

March 2024 Page 13 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

on the shop drawings. Unless the span length(s) is very short, relaxed camber diagram
ordinates are given at the 10th point of the span. According to Section 10.7.4 of the
CHBDC, for spans less than 25 m the girders need not be cambered. Variations in
concrete haunch thickness can be used, in lieu of providing a camber, to achieve the
required screed elevations. Where haunching in lieu of camber is used, variable shear
stud lengths might be required.

Steel Plate Girders

Plate girders are fabricated with the web in a horizontal position. For plate girders, the
relaxed camber diagram shown on the contract drawings is used to check that the required
camber in the shop has been achieved within the allowable tolerances. Deflections for
girder segments resulting from self-weight of girders are not required to be shown on the
contract drawings.

Steel Box Girders

Box girders are generally fabricated with the webs in an upright position. Both webs are
supported at close intervals during fabrication. For box girders, in addition to giving the
relaxed camber diagram, it is necessary to show on the contract drawings the girder self-
weight deflections for girder segments when simply supported at the field splice locations.
This allows verification in the plant that the girder segments have been fabricated to the
required camber (by subtracting ordinates for deflections for girder segments from the
relaxed camber diagram ordinates).

8.2.2 Elevations

Structural Steel contract drawings shall show girder erection elevations at the top of
girders with only the weight of the completely erected structural steel acting. These
elevations are given at splice points, mid-span points, piers, and abutments. The
elevations should always be given to the top surface of the girders, which will be to top of
flange or top of splice plate. This must be clearly indicated on the drawings.

Top of girder elevations are required in order to verify that the girders have been erected
within acceptable tolerances to the elevations given on the contract drawings. Prior to
placing the deck, the height of the concrete deck haunches are set in order that the screed
elevations shown on the contract drawings can be achieved. The as-constructed girder
elevations, at the time the erection of all the girders is completed and accepted by the
contractor, are permanently recorded.

8.2.3 Example: 2-Span Steel Box Girder

The sketches in Figure 8.2.1 illustrate the various diagrams required for steel box girders,
to be shown on the structural steel contract drawings.

March 2024 Page 14 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

Note: If the top flanges at any point are at different elevations due to geometry (horizontal
curve of structure or skew of bridge) or different web heights (large deck crossfall),
two girder erection elevations will have to be given, one at the top of each flange.

FIGURE 8.2.1 – STRUCTURAL STEEL GIRDERS PROFILE EXAMPLE FOR 2-SPAN


STEEL BOX GIRDER

8.3 Details

A steel structure should not be permanently wet or damp. Even if the general environment
is satisfactory, it is important to ensure good detailing to provide a natural drying process
and prevent accumulation of moisture and debris.

March 2024 Page 15 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

Water ponds and debris accumulate on horizontal surfaces and in corners formed by
horizontal and vertical plates (re-entrant corners), fostering excessive corrosion.

Avoid detailing which creates pockets and crevices. The most susceptible locations are
bottom flanges, gusset plates for horizontal bracing, longitudinal stiffeners, bolted splices
of horizontal and sloped members, and intersections of bearing and intermediate stiffeners
with flanges and gusset plates.

8.3.1 Structural Steel Box Girders Bottom Flanges

The weld joining the bottom flange and the web should be detailed so that any projection
of the flange outside of the web plate where salt could collect is minimized. A projection
of 25 to 40 mm beyond the edge the web is sufficient.

Pier and abutment diaphragms shall be coped to clear continuous welding of the web-to-
flange joint. At abutments, the copes shall have a mesh caulked over the copes to prevent
the entry of rodents or birds into the girders (see Figure 8.3.1).

FIGURE 8.3.1 – BOTTOM FLANGE WELDING DETAILS

8.3.2 Box Girder Drainage and Ventilation

Drains are required through the bottom flanges of box girders wherever water can collect.
These should be detailed to prevent water from running along the soffit and to keep out
birds. As a minimum, drains should be located at each end of every span and at low
spots. Drains shall project 50 mm below the bottom of the bottom flange. Cut outs in
longitudinal stiffeners shall be detailed at drains as necessary. Drains shall be located to
avoid staining of the substructure.

Adequate ventilation of the interior of box girders must be ensured to allow a draft. Two
vent holes per span shall be provided on the interior web of each girder in each span.
Vents shall be provided with screens attached with silicone caulking. Vent holes and
drains shall be 40 mm diameter.

March 2024 Page 16 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

Note: Multiple drain holes could be provided, or copes could be provided in stiffeners to
channel runoff to one drain hole.

FIGURE 8.3.2 – BOX GIRDER DRAINAGE AND VENTILATION

8.3.3 Access to Box Girder Voids

CHBDC Clause 1.8.3.1.5 requires access openings for the inspection and maintenance
of steel box sections having inside vertical dimensions of 1.20 m or greater.

March 2024 Page 17 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

Box girders with access openings shall have a minimum inside clear height of 1200 mm.
The minimum clearance, both vertically and horizontally, for walking through intermediate
cross bracing and diaphragms inside box girders shall be preferably 600 mm and not less
than 500 mm.

The number of access openings and their locations shall be as follows:

a) Simple span steel box girders with walk through cross bracing shall have two access
openings per box girder, one located near each end;

b) Continuous steel box girders with walk through cross bracing shall have pier
diaphragms with openings and shall have two access openings per box girder, one
located near each end. For exceptionally long girders, the need for additional
intermediate access openings should be determined by the Structural Section and
stated in the Structural Design Report.

The access openings shall be located to avoid or minimise interference with traffic during
inspection and should be easily accessible to inspectors, but not to the general public. In
Ontario, the access openings are usually located in the web near abutments. This would
reduce the shear resistance of the web. Therefore, the access openings should not be
located in the steel box area subjected to high shear forces and torsional moments. Web
access hole should be added in the space between stiffeners. Access openings shall not
be located on the exterior web of the girder where they may be directly exposed to the
elements.

Details of hatch for the access opening shall be as per OPSD 3311.900. The shear
resistance of the web at the access openings shall be designed along with transverse and
longitudinal stiffeners around the opening, as required.

8.3.4 Drip Tab Details

Drip tabs shall be used on steel beams and girders to prevent water along girders from
being deposited on abutments and piers. Drip tabs divert water and debris from collection
points, and to reduce or eliminate objectionable staining of the concrete substructure when
the steel is ACR. When required, drip tabs shall be attached to all steel beams or girders
in the shop, since staining may occur prior to slab placement.

Drip tabs should be shown both in plan and in elevation. They should be located such
that the ends of the tabs are 1.0 m in front of the front face of the abutment wall, and 1.0
m to the side of a pier when the girder slopes upwards away from the pier.

Structures on crest curves shall have tabs in front of both abutments. Structures on a
grade shall have tabs in front on the abutment on the low side of the bridge only.
Structures with a sag curve, where the low point is away from the abutments, generally do
not need drip tabs.

Where water/debris may collect, such as when splice plates cannot be tapered or
stiffeners cannot be provided with a cope (snipe/clip) according to Section 8.4.1, additional
drip tabs should be provided.

March 2024 Page 18 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

Steel drip tabs falling within the coated zone specified in Section 8.7 note 13 shall also be
coated.

FIGURE 8.3.3 – DRIP TAB DETAILS FOR I-GIRDERS AND BOX GIRDERS

8.3.5 Girder Web Spacing

The spacing of girder webs between girders shall be no closer than the larger of 1.8 m or
the depth of girder (Figure 8.3.4). Avoiding closely spaced girders provides adequate
ventilation for drying.

FIGURE 8.3.4 – GIRDER SPACING

March 2024 Page 19 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

8.4 Stiffeners and Connection Plates

8.4.1 Coping of Stiffeners and Gusset Plates

Copes on transverse stiffeners shall inverted J-clips, with at least the minimum dimensions
shown in Figure 8.4.1. Copes on other details, such as longitudinal stiffeners and gusset
plates, shall be quarter-round, not less than 50mm in radius (see Figure 8.4.2).

FIGURE 8.4.1 – COPE DETAILS

These larger copes are desirable for the following reasons:

1) They prevent the possibility of intersecting welds;

2) They reduce the high weld shrinkage strains associated with smaller copes; and,

3) They allow drainage without the buildup of debris.

At end diaphragms of box girders, copes shall be filled with weld or caulking to prevent
entry of rodents or birds. This generally dictates a drain at the diaphragm.

March 2024 Page 20 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.4.2 – COPING OF STIFFENERS AND LOCATION OF GUSSET PLATES

8.4.2 Fillet Weld Terminations

Fillet welds shall be detailed in such a way that the introduction of notch type deficiencies
into the base metal is minimized. Due to the risk of creating notch type deficiencies if fillet
welds are continued to the end of the joint or wrapped around the end of the joint, it is
preferable to stop the weld short. An accepted practice is to stop welds short of the edge
of the base metal by a distance equal to the designed fillet weld leg length +/- 3mm for
shorter welds, such as those joining vertical stiffeners to flanges, and by 15mm +/- 5mm
for longer welds, such as those joining stiffeners to webs. A weld termination detail shall
be included in the structural steel drawings.

Fillet weld hold backs shall be indicated on the contract documents.

FIGURE 8.4.3 – WELD TERMINATION DETAILS

March 2024 Page 21 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

Design details shall avoid the need to extend fillet welds to the edge of the base metal. In
cases where fillet welds must reach the edge of the base metal and the joint will not be
cut to length after welding, runoff tabs shall be used.

8.4.3 Lateral Bracing

Lateral bracing shall be provided only where required and shall be connected directly to
the flange where feasible. When it is not feasible, lateral bracing may be connected to
lateral gusset plates.

All gusset plates for lateral bracing should be fillet welded and be located a distance as
required by the CHBDC and practical situations. The outer corners of the gusset plates
should be left square unless fatigue design requires a radiused gusset plate. "Bridge
Fatigue Guide, Design and Details" by J. W. Fisher should be consulted when determining
the location of bolt holes. See also Figure 8.4.2.

Several factors should be taken into consideration in determining the position of lateral
bracing gusset plates.

1) Access for fabricating and inspecting the gusset plate to web connection; and,
2) The fatigue performance; lateral bracing bolted directly to the flanges has superior
fatigue performance, whereas gusset plates can be moved away from the flange into
a lower stress region. For girders with a depth of up to 2.4 m, the bracing shall be
connected to the top flange or connected to gusset plates installed close to the fop
flange.

3) Ability to form the deck. If precast panels are used, the bracing shall be connected
directly to the flange.

8.4.4 Vertical Stiffeners


Bearing Stiffeners on plate girder bridges shall be true vertical under full dead load with
the requirement noted on the contract documents (see 8.7(a)(7)). Intermediate stiffeners
may be either true vertical, or perpendicular to fabrication work lines, depending on the
fabricator's practice.
The recommendation for bearing stiffeners to be true vertical under full dead load is
primarily for aesthetics with the normal pier and abutment designs. Vertical diaphragms
would also result at the bearing points, which will facilitate the jacking arrangement for
bearing maintenance. Some fabricators choose to work from a horizontal work line on the
webs of girders and install intermediate stiffeners perpendicular to these work lines with
the girder in a relaxed condition. When the dead load acts, the intermediate stiffeners are
not vertical, but the difference is slight with no functional loss.
Stiffeners should be detailed to avoid trapping water and debris (Figure 8.4.4) and shall
be coped. Stiffeners consisting of closed sections such as a half pipe shall have copes
filled with weld.

March 2024 Page 22 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.4.4 – CHOICE OF VERTICAL STIFFENERS

8.4.5 Bearing Stiffener to Flange Connection

Bearing stiffeners, irrespective of thickness, shall be fitted to bear and welded to both
flanges at abutment locations as well as at interior supports, as shown in Figure 8.4.5.
The size of the weld shall be specified on the contract drawings.

Because the load being transferred through the stiffeners may be too large to be
transferred through the welds alone, bearing stiffeners are required to be fitted to bear in
their contact to the inner surface of the flanges.

OPSS 906 describes the contact tolerance of “fitted” and “fitted to bear”.

March 2024 Page 23 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.4.5 – BEARING STIFFENER TO FLANGE CONNECTION

8.4.6 Intermediate Stiffener to Flange Connection

Intermediate stiffeners that are used as connection plates on I-girders and on the inside
of box girders shall be welded or bolted to both the tension and compression flanges
depending on fatigue requirements.

Intermediate stiffeners that are not used as connection plates on I-girders and on the
inside of box girders shall be welded to the compression flange and snug fit or welded to
the tension flange depending on fatigue requirements.

8.4.7 Stiffener to Web Connection

All stiffeners shall be welded to the webs of the girders by continuous fillet welds which
shall not be returned around the end of the stiffener. The size of these welds shall be the
larger of the “minimum size” given on the contract drawings and the size which
corresponds to a shear force of 0.0001 hFy1.5 (N/mm) as given in the CHBDC.

Continuous welding improves the fatigue performance in a girder by reducing the number
of stress raisers. The minimum weld size is specified to reduce residual stresses and web
deformations. The weld return about the end of the stiffener is undesirable as it
aggravates the fatigue problem in the web between the stiffener and girder flange.

Longitudinal web stiffeners shall be plate to avoid trapping water/debris.

March 2024 Page 24 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

8.4.8 Intersecting Longitudinal and Transverse Stiffeners

Where possible, longitudinal stiffeners shall be located on the opposite side of the girder
web to intermediate transverse stiffeners. Locating longitudinal and transverse stiffeners
on opposite sides of girder webs facilitates fabrication and reduces the number of stress
raisers in the web of the girder.

Intersection of stiffeners is sometimes unavoidable. Where longitudinal and transverse


stiffeners intersect, the longitudinal stiffener should be cut short of the transverse stiffener.
Cutting the longitudinal stiffener in tension regions results in a category E detail. This
detail may be improved by providing a radiused transition, if this category is too severe,
or by making the longitudinal stiffener continuous and welding the transverse stiffener to
it, resulting in a category C detail. Alternately, in tension regions, where fatigue is a
governing design criterion, and where longitudinal and transverse stiffeners intersect, the
longitudinal stiffener may be made continuous, and the transverse stiffener welded to it at
the intersection.

8.4.9 Box Girder Web Stiffeners

Web stiffeners on the inner and outer faces of box girders should be cut short of the bottom
flange as shown in Figure 8.4.6 in order to allow use of automatic welding of the web-to-
flange joint. This is necessary because the process of fabricating the box girders calls for
the web stiffeners to be welded prior to welding the web to the flanges. The stiffener is
then extended to the bottom flange by the attachment of a plate as shown in Figure 8.4.6.
This plate shall be welded, bolted, or fitted to the bottom flange depending on its location
(i.e., used or not used as connection plate) and fatigue requirements. The plate shall be
welded to the flange where fatigue stress range permits. The connection of bracing to the
outer faces of box girders shall be as shown in Figure 8.4.6 and should be opposed by an
interior stiffener welded to the bottom flange.

March 2024 Page 25 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.4.6 – BOX GIRDER WEB STIFFENERS

8.4.10 Transition Radius for Longitudinal Stiffeners and Gusset Plates

The ends of the transition radius for radiused gusset plates and longitudinal stiffeners shall
be ground smooth (see Figure 8.4.7). The minimum radius (R) shall be based on the
target fatigue category required in accordance with Clause 10.17 of the CHBDC. The
radius should be 600 mm for Category B and at least 150 mm for Category C.

March 2024 Page 26 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.4.7 – TRANSITION RADIUS FOR GUSSET PLATES AND LONGITUDINAL


STIFFENERS

8.4.11 Bottom Flange Stiffener Details

In terms of their structural function, wide flange "W" or "WT" sections are preferred for longitudinal
bottom flange stiffeners. The sections should be spaced a minimum of 305 mm between flanges
to allow the use of automatic welding equipment. For box girders fabricated from ACR, plate
section should be used for longitudinal bottom flange stiffeners where practical due to better
availability of ‘AT’ steel plate than rolled sections. Channel sections, welded to the top of the wide
flange longitudinal stiffeners, and to the inner web stiffeners, are preferred as transverse bottom
flange stiffeners (see Figure 8.4.8).

March 2024 Page 27 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.4.8 – BOTTOM FLANGE STIFFENER DETAILS

8.4.12 Clipping Connection Plates

Flange splice plates within a bolted field splice are a common water trap. If the girder is
on a vertical grade, water flowing down the flange will get trapped by the flange splice
plates. The bottom flange splice plates may be sniped at their leading and trailing ends
to combine the function of a drip tab and facilitate water shedding. Where splice plates
are clipped, it should be at an angle between 30 and 45 degrees (see Figure 8.1.6).

Clipping is not necessary for top flange splice plates embedded in a concrete deck.

8.5 Frames, Bracing and Diaphragms

8.5.1 Frames for Intermediate Bracing

Prefabricated frames should be used for intermediate bracing, in lieu of angle sections
shipped loose to the site, and should be designed for shipping and erection as a single
unit. All frames should be designed and detailed for fabrication from one side, eliminating
the need for "turning over" during fabrication. A "K" brace angle system is preferred over
“X” bracing when the girder spacing exceeds the girder depth, as it allows more space for
workers and inspectors to pass through. Bracing connections need to be bolted
connections with rectangular gusset plates. Oversized holes in the gusset plates are
permitted when required.

Except for bridges over freeways, the preferred "K" brace system for use between girders
consists of angles shop welded to one side of gusset plates which would be field bolted to
the girder stiffeners. It results in more economical fabrication and erection procedures
when all frames are produced in one jig without the need to turn the frame, and when
fewer pieces are handled in the field.

For bridges over freeways, intermediate bracing between tub girders shall be avoided
altogether. Where absolutely necessary, frames consisting of angles shall be bolted or
welded all around to gusset plates to seal the interface between angle and gusset plate to
minimize crevice corrosion.

If “X” bracing is used, it shall be detailed with tightly fitting filler plates at the intersection
of angles to minimize crevice corrosion.

March 2024 Page 28 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

8.5.2 Box Girder Bracing

Unless required otherwise by design, L 102 x 102 x 9.5 should be used as a standard
angle size for box girder bracing. If additional interior bracing is required for handling of
the girders, in excess of what the contract drawings call for, the fabricator shall show this
on the shop drawings and the additional attachments shall be subject to approval by the
Ministry. The designer should ensure that the interior bracing can be welded to the web
stiffeners (see Figure 8.5.1). In the case of X bracing if acceptable structurally, the
intersection of the two bracing elements need not be connected.

The size chosen is adequate for the typical range of bridge spans built in Ontario.

FIGURE 8.5.1 – BOX GIRDER BRACING

8.5.3 Intermediate Diaphragms in Shallow Girders

Constant depth intermediate diaphragms, in lieu of frame bracing, are preferred in I-girder
bridges with a web depth of up to 1200 mm.

Diaphragms fabricated from channel, bent plate, or beam sections are preferred in shallow
girder bridges over welded plate sections.

8.5.4 Box Girder Diaphragms at Piers and Abutments

Diaphragms at piers should be detailed so that the box girder and diaphragm flanges are
not connected (see Figure 8.5.2(a)). Two possible solutions are shown.

Diaphragms at abutments are normally of a shallower depth to allow for deck end
thickening details. In this case, the box girder flanges should be stabilised against rotation
(see Figure 8.5.2(b)).

Diaphragms between box girders at piers and at abutments should be of constant depth
and bolted to box girder web stiffeners (see Figure 8.5.2(c)). Oversized holes in
diaphragms or stiffeners are permitted.

At piers and abutments with bearings, provisions for jacking within the width of the bottom
flange should be provided for by design.

March 2024 Page 29 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

The details as shown in Figure 8.5.2 were developed to meet design and fabrication
needs.

FIGURE 8.5.2 – BOX GIRDER DIAPHRAGMS

8.6 Weld Details

8.6.1 Transition of Web Thickness

Web splice details indicating a CJP weld shall be included in the structural steel drawings
according to Figure 8.6.1. The plate preparation and specific weld details are provided by the
fabricator according to their approved welding procedures.

March 2024 Page 30 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

FIGURE 8.6.1 – WEB SPLICE DETAIL

8.6.2 Transition of Flange at Butt Welds

Transition of flange thickness at butt welds should be made in accordance with CSA W59
with a slope through the transition zone not greater than 1 in 2.5.

A slope of 1 in 2.5 can be produced by burning. Research indicates that this detail
achieves the required fatigue categories. Less steep slopes require more expensive
fabrication methods with no significant compensating improvement in fatigue
classification.

FIGURE 8.6.2 – FLANGE SPLICE DETAIL ELEVATION

Flange width transitions at butt welds shall be avoided. If absolutely necessary, they shall
be detailed according to Figure 8.6.2.

FIGURE 8.6.3 – FLANGE WIDTH TRANSITION PLAN

March 2024 Page 31 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

8.6.3 Grinding of Butt Welds

In the following, "Flush" is defined as: the condition in which there is a smooth gradual
transition between base and weld metal, involving grinding where necessary to remove all
surface lines and to permit radiographic testing (RT) or ultrasonic testing (UT)
examination. Weld reinforcement not exceeding 1 mm in height may remain on each
surface, unless the weld is part of a faying surface, in which case all reinforcement shall
be removed.

"Smooth" is defined as: the condition in which the surface finish of weld reinforcement has
a sufficiently smooth gradual transition, involving grinding where necessary to remove all
surface lines and to permit RT or UT examination. Weld reinforcement not exceeding the
following limits may remain on each surface.

• For plate thicknesses < 50 mm, 2 mm

• For plate thicknesses > 50 mm, 3 mm

(a) Butt welds in webs of girders designed for tension in category B shall be "flush" for a
distance of 1/3 the web depth from the tension flange.

(b) All other butt welds designed for tension in category B shall be "flush".

(c) Butt welds designed for compression only or for stresses in category C shall be at least
“smooth”.

These recommendations are in line with the latest fatigue rules. For welds specified to be
ground "flush", weld reinforcement of 1 mm is allowed (except in the case of faying
surfaces) reducing the possibility of over-grinding and repair.

In webs of girders, butt welds more than 1/3 the girder depth from the tension flange are
in a lower stress range. This results in a less severe fatigue category not requiring the
"flush" condition.

Where the contour of the weld is to be "smooth" grinding may be required to permit RT or
UT examination of the tension welds. Compression welds may require grinding if the weld
reinforcement limits are not met.

In I-girders, the top surface of bottom flange butt welds shall be “flush”. The designer shall
consider grinding other butt welds where water may collect (Figure 8.6.4).

FIGURE 8.6.4 – GRINDING FLUSH OF WELDS WHICH OTHERWISE FORM WATER


TRAPS

March 2024 Page 32 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

8.6.4 Bearing Shoe Plate Welds

Bearing shoe plates should preferably be welded only longitudinally to plate girder flanges.
If the shoe plates are to be welded in the field, they should be wider than the girder flanges
to facilitate welding in the downwards horizontal position.

For box girders, unless design requirements dictate otherwise (e.g., skew), double
bearings should be used at both piers and abutments. Where the bearing shoe plates are
to be welded in the field, they should be positioned to allow longitudinal welds in the
horizontal position between flange and shoe plate. In addition, short transverse welds,
between flange and shoe plate, of approximately 150 mm in length, should be provided
(see Figure 8.6.5). Sufficient access should be provided to execute these transverse
welds.

FIGURE 8.6.5 – BEARINGS AT PIERS AND ABUTMENTS

8.7 Structural Steel Notes

The following are standard notes to be shown below the title block on the appropriate
drawing. The notes must be worded to cover the requirements specific to the particular
project and should only be used if applicable. Other notes may be required in special
circumstances.

For clarity the wording of the notes is shown in upper case (CAPITAL) lettering.
Explanations shown in brackets in lower case lettering are not part of the notes.

A. General Notes

1. ALL STRUCTURAL STEEL SHALL CONFORM TO CSA G40.20/G40.21 GRADE


350AT. THE CHARPY IMPACT ENERGY REQUIREMENTS SHALL BE 27
JOULES AND THE TEST TEMPERATURE SHALL BE … °C.

(Note: For fully coated structural steel, Type AT shall be replaced with Type WT in
the note above. Obtain the test temperature requirements from the appropriate table
of CSA S6 for the service temperature given for the location).

March 2024 Page 33 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

ROLLED SECTIONS SHALL CONFORM TO CSA G40.20/G40.21, ASTM


A588/A588M OR ASTM A709/A709M.

(Note: Add Charpy impact test requirements for primary tension members)

2. BOLTS ON ATMOSPHERIC CORROSION RESISTANT STEEL SHALL BE


ASTM F3125/F3125M, GRADE A325M TYPE 3, M22. BOLTS ON COATED STEEL
SHALL BE GALVANIZED GRADE A325M TYPE 1, M22. BOLT THREADS SHALL
BE EXCLUDED FROM THE SHEAR PLANES.

(Note: ASTM F3125/F3125M, GRADE A490M Type 3 bolts may be substituted for
ASTM F3125/F3125M, GRADE A325M Type 3 bolts on ACR steel, but galvanized
A490 Type 1 bolts on coated steel are not permitted because of delayed fracture
due to hydrogen embrittlement.).

3. STUD SHEAR CONNECTORS SHALL BE 22 mm DIA. AND CONFORM TO ASTM


A108 AND CSA W59.

4. ALL LENGTHS SHOWN ARE IN THE HORIZONTAL PLANE AND MEASURED AT


20 °C.

5. GIRDERS SHALL BE CAMBERED TO VALUES SHOWN IN THE RELAXED


CAMBER DIAGRAM.

6. RELAXED CAMBER ORDINATES INCLUDE AN ALLOWANCE FOR GIRDER


SELF-WEIGHT, CONCRETE DECK, SUPERIMPOSED DEAD LOADS AND
PROFILE OF HIGHWAY.

(Note: If the bridge is a multi-span steel box-girder structure, the following note
should be included.)

ADJUSTMENTS SHALL BE MADE TO THE RELAXED CAMBER DIAGRAM TO


COMPENSATE FOR THE DEFLECTION OF THE INDIVIDUAL GIRDER
SEGMENTS.

7. THE ENDS OF GIRDERS AND BEARING STIFFENERS SHALL BE TRULY


VERTICAL UNDER FULL DEAD LOAD.

8. ALL BUTT WELDS IN FLANGE AND WEB SHOP SPLICES SHALL BE FINISHED
FLUSH OR SMOOTH AS INDICATED. MARKS LEFT BY GRINDING TO BE IN
THE DIRECTION OF APPLIED STRESS. IF SHOP SPLICES ARE REQUIRED IN
LOCATIONS OTHER THAN THOSE WHERE PLATE SIZES HAVE TRANSITIONS,
THEIR LOCATION SHALL BE APPROVED BY THE ENGINEER.

(Note: The weld finishes to be indicated on the drawing using the appropriate
standard symbol (see Section 8.6.3)).

9. UNLESS OTHERWISE NOTED THE MINIMUM FILLET WELD SHALL BE AS


FOLLOWS:

March 2024 Page 34 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

MATERIAL THICKNESS OF MINIMUM SIZE OF


THICKER PART JOINED SINGLE PASS FILLET WELD
(mm) (mm)
TO 12 INCLUSIVE 5
OVER 12 TO 20 6
OVER 20 TO 40 8
OVER 40 TO 60 10
OVER 60 TO 120 12

10. FILLET WELDS BETWEEN STIFFENERS AND WEBS SHALL STOP SHORT OF
THE EDGE OF THE BASE METAL BY 15 +/- 5 mm. ALL OTHER FILLET WELDS
SHALL STOP SHORT OF THE EDGE OF THE BASE METAL BY A DISTANCE
EQUAL TO THE DESIGNED FILLET WELD LEG LENGTH +/- 3 mm.

11. UNLESS OTHERWISE NOTED, LONGITUDINAL WEB STIFENERS SHALL BE


CUT 25 mm SHORT OF THE TRANSVERSE WEB STIFFENERS.

12. BOLT HEADS IN FIELD SPLICES FOR BOX GIRDERS SHALL BE LOCATED ON
THE EXTERIOR SURFACES.

13. ALL STRUCTURAL STEEL SURFACES, INCLUDING DIAPHRAGMS AND


BRACING, BUT EXCLUDING SURFACES IN CONTACT WITH CONCRETE AND
THE CONTACT SURFACES OF BOLTED JOINTS SHALL BE COATED FOR A
DISTANCE OF 3000 mm FROM THE ENDS OF GIRDERS AT EXPANSION
JOINTS. THE COLOUR OF THE TOPCOAT SHALL BE …

(The colour of the topcoat or finishing coat to be inserted by the designer as follows:

• 10045 brown According to Federal Standard 595C Colours (for ACR steel
girder bridges); or,

• 16307 grey According to Federal Standard 595B Colours (for all other steel
including any ACR steel used in the rehabilitation of carbon steel structures).

14. If the bridge is integral the following note shall be added:

ALL STRUCTURAL STEEL SURFACES SHALL BE COATED FOR A DISTANCE


OF 700 mm AS FOLLOWS: FROM THE FRONT FACE OF THE ABUTMENT
100 mm TOWARD THE ENDS OF GIRDERS AND 600 mm TOWARDS THE
CENTRE OF GIRDERS. THE COLOUR OF THE TOPCOAT SHALL BE …

(The colour of the topcoat or finishing coat to be inserted by the designer should be
as shown in note 12.)

If the bridge is semi-integral the following note shall be added:

March 2024 Page 35 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

ALL STRUCTURAL STEEL SURFACES, EXCEPT DIAPHRAGMS, SHALL BE


COATED AS FOLLOWS: FROM THE ENDS OF THE GIRDERS TO 600 mm
BEYOND THE FRONT FACE OF THE ABUTMENT. THE COLOUR OF THE
TOPCOAT SHALL BE …

(The colour of the topcoat or finishing coat to be inserted by the designer should be
as shown in note 12.)

15. CONTRACTOR SHALL ENSURE THE STABILITY OF ALL COMPONENTS


DURING HANDLING, TRANSPORTATION AND ERECTION AND UNTIL THE
STRUCTURAL STEEL IS IN ITS FINAL LOCATION WITH ALL PERMANENT
BRACING, CONNECTIONS AND SUPPORTS IN PLACE AND THE CONCRETE
IN THE DECK HAS REACHED 75% OF ITS SPECIFIED STRENGTH.

16. If the bridge is a multi-span steel box-girder structure, the following note 15 should
be included:

ADJUSTMENTS SHALL BE MADE TO THE RELAXED CAMBER DIAGRAM TO


COMPENSATE FOR THE DEFLECTION OF THE INDIVIDUAL GIRDER
SEGMENTS.

17. The designer shall add the following note to the structural steel drawings at exterior
field splice locations of I-girders, unless the entire exterior I-girder is coated:

ALL STRUCTURAL STEEL SURFACES OF EXTERIOR I-GIRDERS, INCLUDING


SPLICE PLATES, BUT EXCLUDING SURFACES IN CONTACT WITH CONCRETE
AND THE CONTACT SURFACES OF BOLTS JOINTS, SHALL BE COATED FOR
A DISTANCE OF 2000 mm ON EITHER SIDE OF THE CENTRELINE OF A FIELD
SPLICE.

B. Notes (on DECK DETAILS drawing, structural steel girder superstructure)

1. SCREED ELEVATIONS ARE TO TOP OF CONCRETE.

2. SCREED ELEVATIONS SHOWN IN TABLE INCLUDE AN ALLOWANCE FOR


ROADWAY PROFILE, WEIGHT OF DECK SLAB AND SUPERIMPOSED DEAD
LOAD.

3. CONCRETE IN DECK SLABS AND DIAPHRAGMS SHALL BE RETARDED USING


A TYPE B OR D ADMIXTURE TO ENSURE THAT THE CONCRETE REMAINS
PLASTIC FOR THE DURATION OF EACH PLACEMENT.

4. CONCRETE SHALL REMAIN PLASTIC IN POURING OF SEGMENTS WITH THE


SAME SEQUENCE NUMBER.

5. MINIMUM CONCRETE STRENGTH OF PREVIOUS DECK PLACEMENT SHALL BE


20 MPa BEFORE PROCEEDING WITH THE PLACEMENT.

March 2024 Page 36 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

6. CONCRETE IN BARRIER WALLS (AND SIDEWALK(S)) SHALL NOT BE PLACED


UNTIL ALL CONCRETE IN DECK SLAB HAS REACHED A STRENGTH OF 20 MPa.

7. FALSEWORK FOR THE CANTILEVER PORTIONS OF THE DECK SLAB (FOR A


LENGTH OF 2.0 m) SHALL NOT BE REMOVED UNTIL THE CONCRETE AROUND
THE INSTALLED EXPANSION JOINT HAS REACHED A STRENGTH OF 20 MPa
(TYP. AT ALL FOUR CORNERS OF THE BRIDGE).

8.8 Steel Truss and Arch Design

In the design and evaluation of steel trusses and arch structures, connections are
assumed to be typically pinned. However, the effects of connection rigidity or seized pins
shall also be considered during analysis to determine whether resulting bending stresses
are acceptable and fatigue will not be an issue.

March 2024 Page 37 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 8 - STRUCTURAL STEEL

This page is intentionally left blank.

March 2024 Page 38 of 38 SM-D2-S08


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

Table of Contents

9 BRIDGE DECKS .................................................................................................. 2


9.1 General ........................................................................................................................ 2
9.2 Deck Geometry ............................................................................................................ 2
9.2.1 Bridge Deck Width ................................................................................................ 2
9.2.2 Sidewalk Widths on Bridges.................................................................................. 3
9.2.3 Deck Fascia Details .............................................................................................. 4
9.3 Deck Slab Design......................................................................................................... 5
9.3.1 Concrete in Deck Slabs ........................................................................................ 6
9.3.2 Minimum Thickness of Deck Slabs ....................................................................... 6
9.3.3 Reinforcing Steel Below Barrier Walls ................................................................... 6
9.3.4 Haunches ............................................................................................................. 7
9.3.5 Stay-in-place Forms .............................................................................................. 8
9.3.6 Partial Depth Precast Deck Panels ....................................................................... 8
9.3.7 Additional Reinforcement in Skewed Decks .......................................................... 9
9.4 Construction ................................................................................................................10
9.4.1 Deck Construction Joints .....................................................................................10
9.4.2 Sequence of Deck Placements for Slab-on-Girder Bridges ..................................10
9.4.3 Screed Elevations on Bridge Decks .....................................................................11
9.4.3.1 Slab on Girder Decks ................................................................................................. 11
9.4.3.2 Post Tensioned Concrete Decks ............................................................................... 11
9.4.4 Construction Loading from Deck Cantilever Overhangs .......................................11
9.4.5 As-Constructed Elevations ...................................................................................12
9.5 Durability .....................................................................................................................12
9.5.1 Bridge Deck Waterproofing ..................................................................................12
9.5.2 Future Wearing Surface .......................................................................................12
9.5.3 Waterproofing of Deck Cantilever of Steel Box-Girder Bridges ............................12
9.5.4 Structure Deck Drainage ......................................................................................13
9.5.5 Drip Grooves........................................................................................................14

March 2024 Page 1 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

9 BRIDGE DECKS

9.1 General

This section covers requirements for bridge decks, including sidewalks and curbs.

9.2 Deck Geometry

The travelled width of the bridge deck typically matches that of the approach roadway,
although some exceptions are possible depending on roadway class. Consideration is
also made to future rehabilitation of the bridge. Requirements can be found in the MTO
Design Supplement for TAC Geometric Design Guide (GDG) for Canadians Roads.

9.2.1 Bridge Deck Width

When traffic on a wide bridge is separated by a median curb or barrier, the bridge may be
designed as a single wide bridge, or as twin bridges with longitudinal separation at the
median. Closely spaced bridges lead to run-off and deicing salts on the cantilever
overhangs between them and may promote a microclimate with high time of wetness.
From the perspectives of durability and structural stiffness, for bridge deck widths up to 35
m, the preferred approach is to have a transversely continuous structure, see Figure 9.2.1.

Where twin bridges are used, they shall be separated by less than 50 mm or more than 2
m apart. The 2 m minimum permits inspection with the Bridgemaster. Bridges carrying
bidirectional traffic with a deck width less than 35 m shall be designed without longitudinal
joints. Decks wider than 35 m and twin parallel bridges (typically with high skew or
curvature) with cumulative width less than 35 m, require approval of the Structural Section.

As the bridge deck gets wider, transverse restraint due to thermal loads and shrinkage
must be considered. The deck may require additional transverse reinforcement to control
cracking.

March 2024 Page 2 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

FIGURE 9.2.1 – CLOSELY SPACED PARALLEL BRIDGES VS. CONTINUOUS SPAN


CARRYING BOTH DIRECTIONS OF TRAVEL

9.2.2 Sidewalk Widths on Bridges

Sidewalk widths on bridges shall comply with the Accessibility for Ontarians with
Disabilities Act, S.O. 2005, c.11, and the Transportation Association of Canada.
Geometric Design Guide for Canadian Roads: 2017, in conjunction with the MTO Design
Supplement. For designs of new bridges with sidewalks or bridge rehabilitations where
the sidewalks are rehabilitated, unless otherwise permitted in section 80.31 of O. Reg.
413/12, the minimum clear sidewalk width shall be 1500 mm. In addition, the minimum
clear sidewalk width shall:

• Be maintained over the entire length of the bridge and transition smoothly to the
approaches;

• Not be reduced below 1500 mm by appurtenances such as guiderail connections to


the bridge;

• Apply to the clear surface of the sidewalk excluding surfaces of other elements such
as curbs or tops of walls that are separated from the sidewalk by longitudinal joints.

The requirements above are illustrated in Figure 9.2.2 for greater clarity. These
requirements are typically met using an 1800 mm wide sidewalk (measured at asphalt
level and with the standard curb face slope of 50 mm horizontal to 150 mm vertical) using
standard MTO details on the bridge approaches.

March 2024 Page 3 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

FIGURE 9.2.2 – SIDEWALK WIDTH

9.2.3 Deck Fascia Details

Fascia treatment is categorised by deck type and the presence or absence of a sidewalk
as shown in Figure 9.2.3. Slab on girder decks with a sidewalk or curbs supporting open
railings shall have a 500 mm high fascia. Decks without a sidewalk shall have a 350 mm
high fascia with concrete barriers. Cast in place post-tensioned decks shall have fasciae
from 350 to 600 mm high.

March 2024 Page 4 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

FIGURE 9.2.3 – DECK FASCIA DETAILS

9.3 Deck Slab Design

The ministry developed the empirical method of bridge design in the 1970’s and it has
been used for deck design since the introduction of the first Ontario Highway Bridge
Design Code (OHBDC) in 1979. This has been used continually since that time, with
similar provisions being adopted by Section 8 of the CHBDC since the year 2000.
Generally, for regular shape decks, all interior portions of decks use the empirical design
method, which results in a 225 mm thick deck with a top and bottom mat of 15M
reinforcement at 300 mm spacing in each layer in each direction.

March 2024 Page 5 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

9.3.1 Concrete in Deck Slabs

To ensure adequate durability, the Specified 28-day Compressive Strength for decks shall
be a minimum of 30 MPa.

9.3.2 Minimum Thickness of Deck Slabs

In order to permit placing four layers of reinforcing steel with the required cover and
associated tolerances, the minimum thickness of deck slabs shall be 225 mm. Such slabs
should be detailed so that the bars in the positive two layers of distribution (longitudinal)
reinforcement are not vertically in line with one another. If possible, size 15M bars shall
be used except for negative moment regions over piers or at deck cantilevers where larger
diameter reinforcing steel bars would be required.

For deck slab made with full-depth precast deck panels, the minimum thickness of the
panels shall be 200 mm.

9.3.3 Reinforcing Steel Below Barrier Walls

Cantilever portions of deck slabs tend to develop transverse cracks at barrier wall
construction joint locations.

To control the cracks, 15M at 200 mm top and bottom longitudinal reinforcement shall be
provided in cantilever slabs under barrier walls starting from the outside end of the slab
and extending inward 500 mm from the inside face of the barrier wall (or to the outside
girder flange, if it is closer than the 500 mm). See Figure 9.3.1.

FIGURE 9.3.1 – LONGITUDINAL REINFORCEMENT BELOW BARRIER WALL

Cantilever portions of deck slabs with sidewalks do not require this additional crack-control
reinforcement.

March 2024 Page 6 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

9.3.4 Haunches

Concrete haunches of varying thickness may be used to fit the top of girders to a deck
slab of constant thickness to achieve the proper screed elevation. The haunches shall be
the same width as the top flange and shall not cover the sides of the top flange as shown
in Figure 9.3.2(a). For deep haunches, the detail shown in Figure 9.3.2(b) is also
acceptable but not preferred.

a) Typical Haunches b) Deep and Narrow Haunches

FIGURE 9.3.2 – HAUNCH DETAILING

Shear stud height in a steel girder shall project into the deck slab above the bottom
transverse bars as required by the code. Stirrup projection in a concrete girder shall extend
to develop the strength of the bar across the interface between the top of the girder and
the cast-in-place slab, unless a reduced strength of the bar is assumed in the calculation
of interface shear. Nevertheless, the stirrups shall project a minimum of 25 mm above the
bottom mat of bars. . Haunches shall not be reinforced unless the haunch depth above
the flange exceeds 100 mm. Stirrup projections and shear stud height shall be designed
as necessary to avoid additional flange reinforcement except when stirrup projections or
shear stud length exceeds 300 mm, in which case haunches shall be reinforced to extend
the bottom mat of reinforcing steel downwards into the haunch.

Typically, steel girders are fabricated to follow the roadway profile through built-in camber
and a uniform haunch thickness is achieved along the girder length and in transverse
direction, whereas concrete girders require a variable haunch to make up the difference
between the highway profile and the deformed shape of the girder prior to casting the
deck. Nevertheless, the actual haunch on site could vary from estimated haunch which
may affect the stirrup projection in the deck. When stirrup projection turns out be less than

March 2024 Page 7 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

required by design, the haunch is required to be reinforced with transverse bars, usually
in this shape with standard hooks, to interlock with the girder stirrups or studs.
Where stirrup projections or shear studs are too long and impede cover to the top of deck,
consideration can be given to bending them to achieve the cover.

Additionally, it is important to ensure that the girders do not penetrate more than 25 mm
into the nominal thickness of the deck slab. This may happen if an insufficient allowance
has been made at mid span for the upward prestress camber of precast girders and also
if the deck has a sag vertical curve. As a general rule, to achieve all of the criteria above,
it is necessary to provide haunches raising the bottom of the deck above the top of precast
beams or the top of steel beam flanges, with haunch heights at the supports as shown in
Table 9.3.1. For steel beams spanning 80 m and above, a thicker haunch may be
necessary.

TABLE 9.3.1 – TYPICAL HAUNCH HEIGHTS

Haunch Height (mm) Concrete Girder Steel Girder


Spaced box beams and Steel girders with web depth
50
NU 900, 1200 < 1400 mm
Steel girders with web depth
75 NU 1400 or larger
≥ 1400 m

9.3.5 Stay-in-place Forms

Steel forms are considered to have many disadvantages and are therefore not to be used.
They are or may become unsightly. They may cause maintenance problems and at the
very least impede inspection. It does not appear that there is any economic advantage to
their use. Stay-in-place Forms of any material shall not be used without approval of the
Ministry.

9.3.6 Partial Depth Precast Deck Panels

As a result of research by MTO and others, precast, usually prestressed, concrete deck
panels were introduced to Ontario in the 1990s as a means of accelerating bridge
construction. The deck cantilevers are still formed conventionally, so the benefits of the
panels diminish for narrow bridges with few girders, as well as for bridges constructed
using staged construction where there are two additional temporary deck cantilevers. The
use of the panels has been found to be advantageous for steel box girder bridges, or at
least for the slab span within the steel box, to eliminate the difficult task of removing
conventional formwork. The thickness of the deck panels shall be according to SS109-42
and SS109-44, and are topped with 135 mm of concrete. Tests have shown that stirrups
connecting the topping slab to the panel are not required, although a few are added to the
standard drawing to facilitate tying of the reinforcement for the topping slab. The design
of partial depth deck panel deck is provided in the CHBDC, while details are contained in
drawings SS109-42 and SS109-44.

March 2024 Page 8 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

This deck system requires continuity between the reinforcement in the deck panels. This
is achieved, for the longitudinal reinforcement, by placing continuous reinforcement along
the top of the panel. For bottom transverse reinforcement, strands or regular rebars must
be developed over the girders. For NU girders, with their wide top flanges, lapping is
easily achieved, while for steel girders the strands must be crossed over the adjacent
panel.

For large spans with large negative moments in the deck, or bridges with large overhangs,
adequate space between reinforcement may be difficult to achieve. For these
aforementioned situations, a deck thicker than 225 mm may be required. For bridges on
skew, the panels span perpendicular to the girders, and the triangular portions of deck
near supports are formed conventionally with cast-in-place concrete.

9.3.7 Additional Reinforcement in Skewed Decks

The following detail (Figure 9.3.3), along with Table 9.3.2, shows the additional
reinforcement required, unless analysis dictates otherwise, for the cantilevered portion of
thin slab bridge decks with skews exceeding 20° but less than 45°, and with the cantilever
span not exceeding 1.6 m. Skewed decks with cantilever spans less than 0.6 m do not
require this additional reinforcement.

TABLE 9.3.2 – ADDITIONAL DECK REINFORCEMENT FOR DIFFERENT SKEWS

SKEW CANTILEVER ADDITIONAL REINFORCEMENT


20° - 35° 0.6 m - 1.2 m 6 - 20M
20° - 35° 1.2 m - 1.6 m 6 - 25M
35° - 45° 0.6 m - 1.2 m 8 - 20M
35° - 45° 1.2 m - 1.6 m 8 - 25M

March 2024 Page 9 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

FIGURE 9.3.3 – ADDITIONAL REINFORCEMENT IN SKEWED DECKS

The additional reinforcement shall be placed directly under the top layer of deck
reinforcement.

No additional radial reinforcement is required at the obtuse-angle corners of the bridge


deck.

9.4 Construction

9.4.1 Deck Construction Joints

Construction joints across which force effects are assumed to be transmitted or which
must resist leakage, require special treatment. Introduction of construction joints that are
not shown on contract drawings is not allowed without approval.

It should be noted that waterstops in deck construction joints shall not be used.

9.4.2 Sequence of Deck Placements for Slab-on-Girder Bridges

No deck placing sequence should be specified when the deck can be cast in one
continuous operation from one abutment to the other unless there are specific reasons,
such as when the deck pour could exceed 12 hours in duration or where the structure type
or structural articulation dictates otherwise (i.e., arch bridges, continuous multi-span
girders with short end spans that could lead to lift off the abutment bearings when concrete
is placed in the adjacent span, etc.).

When necessary, the deck placing sequence shall be shown on the drawings. Each deck
placement should be as large as practical, taking into account structural considerations

March 2024 Page 10 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

and the availability and volume of concrete. The following notes concerning strength of
the previous placement before allowing the next placement should be given on the deck
drawing:

CONCRETE STRENGTH OF PREVIOUS DECK PLACEMENT SHALL BE AT LEAST


20 MPa BEFORE PROCEEDING WITH THE NEXT PLACEMENT.

CONCRETE IN DECK SLABS AND DIAPHRAGMS SHALL BE RETARDED USING


TYPE “B” OR “D” ADMIXTURE TO ENSURE THAT THE CONCRETE REMAINS
PLASTIC FOR THE DURATION OF EACH PLACEMENT.

The deck placing sequence should be shown in numerical order.

NOTE: Simultaneous concrete placements should not be specified unless absolutely


necessary, in which case the intent should be clarified on the deck slab drawing.

9.4.3 Screed Elevations on Bridge Decks

Screed elevations are the elevation to which the deck needs to be placed to achieve the
final vertical profile after all dead load deflections occur. Screed elevations are achieved
by the contractor by adjusting the height of the haunches as required.

9.4.3.1 Slab on Girder Decks

Screed elevations shall be given at the centreline of all exterior girders, the break points
in the deck, and on the deck at the faces of curbs and barrier walls. Screed elevations
shall be given at intervals not exceeding 3 m.

9.4.3.2 Post Tensioned Concrete Decks

Screed elevations shall be given at break points in the deck, and on the deck at the face
of curbs or barrier walls. The screed elevations shall be given at intervals not exceeding
3 m. No allowance is required normally for dead load deflections provided that prestress
and dead load are more or less balanced.

9.4.4 Construction Loading from Deck Cantilever Overhangs

Girders shall be designed to account for the load effects of the deck cantilever overhang
during the deck pour.

OPSS 919 requires the screed rail to be placed above the centre of the web. In cases
where this is not feasible based on the need to screed the deck to the full width (i.e.,
staged construction of a two-lane bridge), the girder design shall account for the load of
the screed machine acting on the screed rail located 0.1 m outside of the deck fascia, and
an NSSP shall be included to permit this condition.

March 2024 Page 11 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

9.4.5 As-Constructed Elevations

Steel pins used to record as-constructed elevations of bridges shall be installed when
called for in the Structural Design Report. The decision to install steel pins shall be made
by the Head, Structural Section in consultation with the Design Section Head of the
Structures Office. Structural Standard drawing SS116-40 shall be included in the contract
when steel pins are to be used.

Steel pins shall only be required where long term settlement can be expected due to
specific site conditions and on superstructures that are sensitive to long term creep effect,
such as bridges of segmental construction, or cast in place post tensioned bridges of
staged construction.

9.5 Durability

9.5.1 Bridge Deck Waterproofing

Bridge decks detailed with an asphalt wearing surface must also be shown as being
waterproofed. The drawings should state only "Asphalt and Waterproofing System,
90 mm total." (See Section 2.6.6).

9.5.2 Future Wearing Surface

All structures detailed with an exposed concrete surface shall be designed for 90 mm
future asphalt wearing surface and waterproofing. To allow for wear of exposed surface,
the cover to the reinforcing steel from the top surface shall be increased by 10 mm.

The heights of curbs and barrier walls should not be increased to accommodate the future
wearing surface.

9.5.3 Waterproofing of Deck Cantilever of Steel Box-Girder Bridges

For steel box-girder bridges, the face of curb/sidewalk, if any, should preferably start
beyond the exterior flange of the exterior girder. If this is not practical, hot poured
rubberized asphalt waterproofing system shall be used to prevent salt-laden deck run-off
from invading the joint between the slab and the sidewalk, filtering through the deck and
into the unprotected steel box-girder, causing serious internal corrosion. This damaging
potential is intensified on wide-deck bridges, and especially in the vicinity of piers, where
the concrete decks may have numerous flexural cracks in the negative moment region.
Hot poured rubberized waterproofing system shall be according to OPSS 914 except that
protection board shall not be used. The concrete sidewalk shall be placed directly on the
waterproofing membrane, a minimum of 1 day after the waterproofing has been placed.

This waterproofing should start at 150 mm in front of the face of the sidewalk, continue
along the top of the deck/sidewalk construction joint to the vertical joint face under the
barrier wall. The waterproofing system should extend the full length of the bridge.

Whenever this requirement is used, additional dowels should be added between the
deck/sidewalk interface to ensure continuity and the integrity of the deck cantilever to

March 2024 Page 12 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

resist the traffic barrier loads given in Clause 3.8.8.1 of the CHBDC. The total area of
dowels between the top of the deck and the sidewalk shall not e less than 2000 mm² per
m along the length of the bridge.

9.5.4 Structure Deck Drainage

Requirements for deck drainage inlets must be established as part of the overall drainage
design of the crossing. The size and number of drains shall meet the requirements of
MTO’s Highway Drainage Design Standards. Bridge deck drains shall be provided only
where necessary. Structures having one or two lanes draining to one side, built with
normal crossfall on a vertical crest curve not more than 120 m long, normally do not require
deck drainage inlets.

For bridges on grades or sag curves, the roadway surface runoff shall be intercepted by
catch basins or other means located on the approaches to prevent flow into the expansion
joints or onto the bridge deck.

When bridge deck drainage inlets are required, they shall be used with an airdrop
discharge. Water may not be discharged onto railway property, pavements, sidewalks,
unprotected embankment slopes or waterways if environmental concerns prevail. When
water is discharged onto other surfaces, where stability or appearance is a consideration,
provision shall be made to prevent scour. The position and length of the discharge pipes
shall be such that water falling at an angle of 45° to the vertical does not touch any part of
the structure. Discharge pipes should project 400 mm below the bottom flange of adjacent
girders to prevent splash. Consideration, however, must also be given to minimum vertical
clearance requirements and aesthetics. Pipes need not be attached to adjacent girders if
overall length is less than 2.5 m.

OPSD 3340.100 deck drainage inlets do not collect a significant quantity of water and
should be used only to prevent local ponding. This is sometimes necessary when flat
grades are unavoidable, or structures are subject to substantial permanent deflections
that cannot be accurately predicted.

Catch basins are normally necessary just beyond the structure limits to intercept runoff
from bridge decks. A continuous length of curb or gutter is provided to connect the bridge
curb or barrier to the catch basin to prevent wash outs around the ends of wing walls.
Detailing of the wing wall or approach slab should be such as to permit straight vertical
junctions with approach curbs. The final grading drawings should be reviewed in
conjunction with the structure drawings to ensure that this or an equally acceptable
arrangement has been adopted.

Deck drainpipes shall be located outside of the tub or box girders and shall not cross
through tub or box girders. Drainage analysis shall be performed at preliminary design
stage to determine if deck drains can be avoided. If deck drains are required, the designer
shall select a structural type and configure the cross-section accordingly.

March 2024 Page 13 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

9.5.5 Drip Grooves

Continuous drip grooves are required along the soffit on both sides of all concrete decks.
They should be provided on each side of the joint between abutting twin bridges, even if
the joint is sealed.

The dimensions are shown in Figure 9.5.1.

LOCATION OF THE CONSTRUCTION


JOINT WHEN COMBINED WITH DRIP
GROOVE

FIGURE 9.5.1 – DRIP GROOVES

For practical and aesthetic reasons, it may be desirable to combine the drip with
construction joints that result from transverse prestress anchorage recesses, or decks with
curbs or sidewalks. For this case the drip should not be located greater than 250 mm from
the fascia (see OPSD 3390.100).

March 2024 Page 14 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 9 – DECKS AND CURBS

This page is intentionally left blank.

March 2024 Page 15 of 15 SM-D2-S09


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

Table of Contents

10 BARRIERS AND RAILING SYSTEMS ................................................................. 2


10.1 General ........................................................................................................................ 2
10.2 Approved Traffic Barriers ............................................................................................. 3
10.2.1 Test Level 2 (TL-2)................................................................................................ 3
10.2.2 Test Level 4 (TL-4)................................................................................................ 5
10.2.3 Test Level 5 (TL-5)................................................................................................ 9
10.3 Combination Traffic/Bicycle Rail ..................................................................................10
10.4 Separation Barriers for Bridges with Multi use Pathways (MUPs)................................12
10.5 Barrier Walls Beyond the Bridge Structure ..................................................................14
10.5.1 Barrier Walls in Fill Piles ......................................................................................14
10.5.2 Barrier Walls on MSE Structure ...........................................................................15
10.6 Other Barrier Types.....................................................................................................16
10.6.1 Noise Barriers ......................................................................................................16
10.6.1.1 Highway Noise Barriers ........................................................................................... 17
10.6.1.2 Noise Barrier on Bridges .......................................................................................... 17
10.6.1.3 Noise Barrier Design ................................................................................................ 18
10.6.2 Inspector Guards .................................................................................................18
10.6.3 Unreinforced Concrete Median Barriers and Shoulder Barriers ............................20
10.7 Miscellaneous Details of Barriers ................................................................................21
10.7.1 Architectural Finish on Barrier Walls ....................................................................21
10.7.2 Detailing of Standard Steel Tube Railing..............................................................21
10.7.3 Reinforcement Detail of Concrete Barrier Walls on Structures .............................22
10.7.4 Ducts in Concrete Barrier Walls ...........................................................................22
10.8 Barrier Design Aid .......................................................................................................23

March 2024 Page 1 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

10 BARRIERS AND RAILING SYSTEMS

10.1 General

a) Bridge railing shall be selected in accordance with the requirements of Section 12 of


the CHBDC; that is, conforming to TL-2, TL-4, or TL-5, meeting the crash test
requirements specified in the NCHRP Report 350, or the AASHTO Manual for
Assessing Safety Hardware (MASH).

Only the railing appropriate for the test level of the bridge site should be used.

All bridge barriers adopted for use by the Ministry originate from the crash-testing
programs carried out in the United States. The current standards used by the Ministry
are based on crash tests carried out in accordance with the crash test procedures of:

• Michie, J. D. (1981). NCHRP Report 230: Recommended Procedures for the


Safety Performance Evaluation of Highway Appurtenances. Washington:
Transportation Research Board.; and/or,

• Ross, H. E., Sicking, J. L., Zimmer, R. A., & Michie, J. D. (1993). NCHRP
Report 350: Recommended Procedures for the Safety Performance Evaluation
of Highway Features. Washington: Transportation Research Board.; and/or,

• AASHTO. (2009). Manual for Assessing Safety Hardware (1st ed.). American
Association of State and Highway Transportation Officials., or deemed
equivalent.

MTO is in the process of moving towards the use of MASH 2016 barriers. Further
information about crash tested barrier systems can be found in AASHTO publications,
NHCRP reports, Transportation Research Record, and FHWA memorandums. The
reference subsection of the commentary to Section 12 of the CHBDC gives a
comprehensive listing of pertinent documents, and the following FHWA web site also
gives actual details of approved railing systems and memorandums:

https://safety.fhwa.dot.gov/roadway_dept/countermeasures/reduce_crash_severity/li
sting.cfm?code=long

Some of the accepted bridge rail designs may also be found in the 1995 AASHTO
AGC-ARTBA Joint Committee publication “A Guide to Standardized Highway Barrier
Hardware”.

b) Slip forming of concrete barriers on structures is not permitted.

c) When curbs are required, for sidewalks, raised medians etc., they shall be 150 mm
high.

March 2024 Page 2 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

10.2 Approved Traffic Barriers

In this section the various test levels and corresponding bridge railing types that have been
successfully crash tested and used by the Ministry are described. Note that the railing
systems identified in italics refer to the name of the railing system that has been crash
tested and approved by the FHWA.

For bridges on low volume roads with an AADT, in both directions, of 400 or less, a Test
Level lower than TL-2 is acceptable. MTO's criteria for selecting a lower test level for local
low volume roads is provided in Division 1.

10.2.1 Test Level 2 (TL-2)

As none of the available crash tested TL-2 systems meet the minimum pedestrian height
and other geometric requirements, none are suitable for sites where pedestrian protection
is warranted. The barriers were crash tested to NCHRP 230, or AASHTO Guide
Specifications for Bridge Rails, and were found to be NCHRP 350 compliant for TL-2 as
per a 1997 FHWA memorandum.

The following barrier types are standards used by the Ministry for TL-2:

a) Box Beam Guide Rail – Side Mount (Structural Standard Drawing SS110-2)

The system in Figure 10.2.1 is based on the crash tested California Type 115 Bridge
Railing. Its standard structural “W” and “HSS” shapes provide a relatively inexpensive,
easy to fabricate and erect railing suitable for vehicular only warrants on low speed
and/or low volume highways.

Its open configuration offers a low profile, see-through rail for maximum visibility, which
is desirable in scenic and rural sites.

b) Thrie Beam Guide Rail – Side Mount (Structural Standard Drawing SS110-5)

The system in Figure 10.2.2 is based on the crash tested Oregon Side Mounted Thrie-
Beam Bridge Railing. The Oregon side mounted system consists of standard “Thrie
Beam” elements mounted on standard structural steel posts. It is ideally suited for
cast in place and precast slab superstructures with at least 400 minimum slab depth.
It should be noted that the “W” shape steel beam guide rail used in Ontario is not the
same as the “thrie” beam section. Currently there are no crash tested bridge rail
systems available incorporating the “W” shape steel beam.

March 2024 Page 3 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

FIGURE 10.2.1 – BOX BEAM GUIDE RAIL – SIDE MOUNT (TL-2)

FIGURE 10.2.2 – THRIE BEAM GUIDE RAIL – SIDE MOUNT (TL-2)

March 2024 Page 4 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

c) Thrie Beam Guide Rail – Timber Deck (Structural Standard Drawing SS110-
7)

The system in Figure 10.2.3, for longitudinal timber bridge decks, is based on the
Steel System-Thrie Beam on Steel Posts bridge railing crash tested for the US
Department of Agriculture Forest Service. This in turn is an adaptation of the
California Thrie Beam Bridge Rail modified for timber bridge decks. It consists of
a thrie beam connected to standard structural steel “W” shape posts and spacer
blocks side mounted on the bridge deck. The steel system is connected to the
deck with high strength bars. Material costs are more economical than longitudinal
glulam and timber post alternatives.

FIGURE 10.2.3 – THRIE BEAM GUIDE RAIL – TIMBER DECK (TL-2)

10.2.2 Test Level 4 (TL-4)

The following barrier types are standards used by the Ministry for TL-4, each of which is
based on an NCHRP 350 crash tested barrier:

a) Barrier Wall with Railing (Structural Standard Drawings SS 110-54/58/91)

The system in Figure 10.2.4 is based on the crash tested 32-inch (813 mm) F-Shape
Bridge Railing. It is constructed of reinforced concrete and this type is the most

March 2024 Page 5 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

common rigid traffic barrier in use today on both roadways and bridges. F-shape does
not refer to the shape of the barrier but merely to the crash test designation. Its
popularity is based on its generally effective performance as a barrier, particularly with
its re-directional capabilities, and its low maintenance costs. The concrete barrier
requires virtually no maintenance for most hits. The lower sloped face redirects
vehicles without damage under low-impact conditions. During moderate to severe
impacts, some energy is dissipated when the vehicle is lifted off the pavement. The
loss of tire contact with the pavement also aids redirection. In crash tests, the F-shape
has proven to be more successful than the New Jersey shape in preventing rollover
for small vehicles. The barrier may redirect or contain heavy vehicles, but it was not
designed for this purpose. Therefore, it is most suitable for highways carrying traffic
with low heavy truck volumes.

A handrail is mounted on top to provide a combination railing for maintenance workers


and occasional pedestrians on bridges without sidewalks. The handrail also provides
some aesthetic benefit. The barrier wall is not to be used on bridges with sidewalks,
as it provides no extra advantage when compared to a concrete parapet.

FIGURE 10.2.4 – BARRIER WALL WITH RAILING (TL-4)

b) Parapet Wall with Railing


(Structural Standard Drawings SS 110-56/57/59/90/97/98/104/105)

The system in Figure 10.2.5 is based on the crash tested 32-in (813-mm) vertical
concrete parapet. It offers a simple to build reinforced concrete alternative to the F-
shape railing. Vertical concrete walls do not have the energy management feature of

March 2024 Page 6 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

the F-shape, but crash test have demonstrated that they perform acceptably as traffic
barriers. Because vehicles are not lifted or tilted, all four wheels tend to stay on the
ground and all the energy absorption upon impact goes into the crushing of the vehicle.
Therefore, damage to a vehicle on impact with the parapet is likely to be more severe
compared to the F-shape and redirection not as smooth. Potential rollover is
minimised, however, with a vertical face.

A handrail is mounted on the top to provide a combination railing for maintenance


workers and for bridges with sidewalks.

Where width is a premium on bridge decks such as on rehabilitations the narrower


width of the parapet provides an advantage over the F-shape.

FIGURE 10.2.5 – PARAPET WALL WITH RAILING (TL-4)

c) Box Beam Guide Rail on Curb (Structural Standard Drawings SS 110-37/39)

The system in Figure 10.2.6 is based on the crash tested Massachusetts Type S3
Curb Mounted Bridge Rail. This system is constructed of standard structural steel W
section posts and three HSS rails and offer a good performing lightweight and open
(“see through”) rail alternative to the concrete barriers outlined above. Even though
these rails are acceptable in most applications they are not recommended for use on
high speed and limited access highways. For these cases the F-shape is
recommended, as it is better at redirecting errant vehicles and requires less
maintenance. The systems are usually used with concrete end posts for connection
to the approach railing system. An alternative end connection between the box beams

March 2024 Page 7 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

and approach steel thrie beam guide rail has been developed to accommodate user
needs.

In general, these systems are suitable for vehicular applications, however, the
Massachusetts system may be used for vehicular/pedestrian applications if pickets are
included.

Because it offers one of the most open railings at this test level, it is most suitable for
scenic and rural sites.

FIGURE 10.2.6 – THREE TUBE RAILING ON CURB (TL-4)

(d) Box beam railing on sidewalk (Structural Standard drawings SS110-46/49)

The system in Figure 10.2.7 is based on the crash tested New England Transportation
Consortium 4-Bar Sidewalk Mounted Bridge Rail. It is constructed of standard
structural steel W section posts and four HSS rails and offers a good performing
lightweight and open (“see through”) rail alternative to the concrete parapet wall on
sidewalk with railing outlined previously.

This system is suitable for vehicular/pedestrian applications. Because it offers one of


the most open railings at this test level, it is most suitable for scenic and rural sites.

Although this railing satisfies all the current requirements of the CHBDC with regard to
clear spacing between the rails, the ladder like orientation of the horizontal rails make
it more inviting to climb for little children. Consequently, a different system should be
used when the structure is located near public schools and where the anticipated
pedestrian traffic includes little children.

March 2024 Page 8 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

FIGURE 10.2.7 – FOUR TUBE RAILING ON SIDEWALK (TL-4)

10.2.3 Test Level 5 (TL-5)

The Ministry currently has two barrier/railing systems that satisfy the TL-5 requirements.
An F-shape barrier without railing and a system consisting of box beam railing on a
concrete parapet wall.

These railing systems provide the maximum level of protection, in the event of a collision,
for which the Ministry has a standard. Barriers crash tested to NHCRP 350 or MASH or
for special cases such as for heavy trucks are available, and details of these may be found
on the FHWA web site.

a) Barrier wall without railing (Structural Standard drawings SS110-61/92/94/109)

The system in Figure 10.2.8 is based on the crash tested 42-inch (1.07 m) F-Shape
Bridge Railing. This railing system is very similar to the F-shape TL-4 concrete barrier
in that the front surfaces and its construction are identical except for its height. The
crash test characteristics are similar to the F-shape TL-4 barrier except that the extra
height reduces potential rollover for impacting vehicles.

This railing system is not for use on sidewalks even though it meets the code
requirements for pedestrians.

The system in Structural Standard Drawing SS110-92 is based on the crash test done
by Ryerson University in 2011 at TTI on F-shape TL-5 barrier incorporating GFRP bars
with anchor head. The crash test was performed in accordance with MASH TL-5.

March 2024 Page 9 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

The system in Structural Standard Drawing SS110-94 is based on the crash test done
by Ryerson University in 2016 at TTI on F-shape TL-5 barrier incorporating GFRP bars
with hook bar. The crash test was performed in accordance with MASH TL-5.

FIGURE 10.2.8 – BARRIER FIGURE 10.2.9 – PARAPET WALL WITH


WALL WITHOUT RAILING (TL- TWO TUBE RAILING (TL-5)
5)

b) Parapet wall with two tube railing (Structural Standard drawing SS110-96)

The system in Figure 10.2.9 is based on the PA Bridge Barrier from Pennsylvania
DOT. It was accepted by FHWA as a TL-5 barrier designation. It consists of a
concrete parapet with metal railings mounted on top. The parapet facilitates transfer
of post loads into the deck and the metal railings portion permit visibility through the
railing. It offers a semi-open system alternative to the solid concrete barrier mentioned
above.

10.3 Combination Traffic/Bicycle Rail

This railing provides protection to both bicycles and vehicles when bicycles are travelling
along the roadway. It shall be located on the outside face of bridges. The system shown
in Figure 10.3.1 (Structural Standard Drawings SS 110-82/83/84/85) is developed based
on the flush mounted combination traffic/bicycle rail system from Oregon DOT that was
accepted by FHWA as a TL-4 barrier. It consists of a concrete parapet with two metal
railings mounted on top.

March 2024 Page 10 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

FIGURE 10.3.1 – PARAPET WALL WITH TWO TUBE COMBINATION


TRAFFIC/BICYCLE RAIL (TL-4)

Another system shown in Figure 10.3.2 (Structural Standard drawings SS110-34/36) is a


TL-4 open railing which is developed based on a Maine DOT system. It consists of a steel
post with 4 HSS metal railings mounted on a 225 mm curb. The overall height of both
systems is 1370 mm. It meets the CHBDC requirements for bicycle barrier.

March 2024 Page 11 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

FIGURE 10.3.2 – FOUR TUBE COMBINATION TRAFFIC/BICYCLE RAIL (TL-4)

10.4 Separation Barriers for Bridges with Multi use Pathways (MUPs)

A sidewalk is a raise platform for the passage of pedestrians and typically less than 2 m
wide, while a Multi-Use Path (MUP) is intended for the joint use by pedestrians and
bicyclists and are typically 3 m or in width or greater. When sidewalks or MUPs are used
with a curb, the barrier on the outside edge non-traffic side of the sidewalk/MUP shall be
a crash tested combination traffic/pedestrian or traffic/bicycle barriers respectively. These
barriers should have a handrail at a minimum height of 1050 mm above the top of sidewalk
and 1370 mm above the top of MUP. This handrail provides a safety “grip” for pedestrians
in case they slip, makes it difficult for people to walk on top and adds some aesthetic
value. The following is also noted:

• The Barrier Wall Without Railing TL-5 railing system is not for use on sidewalks even
though it meets the code requirements for pedestrians.

• The Four Tube Railing on Sidewalk (Structural Standard Drawings SS110-46/49) and
Parapet Wall with Railing on Sidewalk (Structural Standard Drawings SS110-
57/97/98/105) are the MTO railing systems, currently available, for use on sidewalks.

• Currently no Structural Standard drawing exists for combination barriers (without


separation barrier) on MUPs meeting bicycle height requirements.

March 2024 Page 12 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

For high-speed applications, as specified in CHBDC, a separation barrier is required


between traffic and pedestrians/bicyclists. In lower speed application with very high
pedestrian or multi-use usage, it may also be prudent to provide a separation barrier. This
results in the following configuration:

roadway – separation barrier – sidewalk/MUP – pedestrian/bicycle barrier

The separation barrier shall satisfy the crash test and geometric requirements for the
traffic, with the barrier height from the pedestrian or bicyclist side satisfying the minimum
600mm requirement of CHBDC. The barrier at the outside of the bridge is protected by
the traffic separation barrier and must only be meeting loading and geometric design
requirements for pedestrian or bicycle barrier for sidewalks and MUPs respectively.
Structural Standard Drawing SS110-110 and SS110-111 show the design and details for
the TL-4 and TL-5 separation barrier respectively (see Figure 10.4.1). Both separation
barriers satisfy height requirements of CHBDC on the traffic side for the protection of the
MUP user. No modification should be made to the separation barrier to increase the height
or change the change the geometry. A TL-5 barrier is taller than TL-4, and it could be
used where enhanced pedestrian/MUP user comfort is desired.

FIGURE 10.4.1 – SEPARATION BARRIER FOR TL-4 AND TL-5

Drawing SS110-22 shows the design of a bicycle barrier on the outside edge of the bridge
(see Figure 10.4.2). Due to the high likelihood of the presence of bicycles on an MUP or
sidewalk separated from traffic by a separation barrier, only a bicycle height barrier should
be used in these circumstances.

March 2024 Page 13 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

FIGURE 10.4.2 – BICYCLE BARRIER

10.5 Barrier Walls Beyond the Bridge Structure

10.5.1 Barrier Walls in Fill Piles

Because of the high cost of supporting barrier walls on piles in back fill, especially to
withstand higher test level loads, the designer should investigate all possible alternatives,
such as carrying the normal two-sided concrete highway barrier up to the end of the
structure or retaining wall, with the standard transition, where required. If approach
barriers are required to be supported on piles, the length of piles for barrier walls on fill
shall be determined as follows:

a) Piles located between the structure and first pavement expansion joint from the
structure: Piles 1 m into existing ground, or minimum overall length 3 m and maximum
overall length 6 m;

b) Other piles under barrier walls: Piles 0.5 m into existing ground or minimum overall
length 3 m, maximum overall length 5 m.

March 2024 Page 14 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

10.5.2 Barrier Walls on MSE Structure

The CHBDC does not provide design details or guidelines for traffic barriers mounted on
mechanically stabilized earth (MSE) System (RSS). Furthermore, the CHBDC has
increased the traffic rail impact load requirements for all test levels compared to the earlier
OHBDC. Designing for these new loadings, and in particular at the TL-5 level, without
knowledge of their distribution through the barrier and transfer to a structural slab and wall
system can result in costly or over conservative designs using conventional design
methods. This problem has been recognised in the USA, and the Transportation
Research Board has carried out a NCHRP project “Design of Roadside Barrier Systems
Placed on MSE Retaining Walls” in 2010 (NCHRP 663). Design guidelines for the barrier
system were developed based on finite element simulation, bogie vehicle tests and full-
scale Test Level TL-3 crash test.

In Ontario the design of the current barriers on MSE walls has been based on the impact
loads given in OHBDC. To avoid severe wall damage during vehicle impact, top mounted
traffic barriers are connected integrally to continuous footings (normally called anchor slab
or moment slab) that are independent of the MSE retaining walls (see Figure 10.5.1). So
far, no unsafe performance or damage, in over 30 years of use on Ministry Highways, has
been reported. Given that the TL-4 loadings in CHBDC are just marginally higher than the
loading given in OHBDC, it was decided to use the CHBDC TL-4 loading, on an interim
basis, for the design of both TL-4 and TL-5 traffic barriers on MSE retaining walls.
Furthermore, in the USA, AASHTO generally accepts TL-4 loading for the majority of its
applications on highways and freeways with a normal mixture of trucks and passenger
vehicles and this also seems appropriate in Ontario for the majority of its highways.
Therefore, the current Structural Standard Drawings (SS110-64/65/68/69/75) may
continue to be used for barriers on MSE retaining walls.

March 2024 Page 15 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

FIGURE 10.5.1 – TYPICAL BARRIER WALL ON MSE (RSS) WALL WITH MOMENT
SLAB

The following requirements apply for traffic barriers on MSE retaining walls.

1. For a TL-5 traffic barrier the loading used shall be equivalent to the TL-4 loading as
given in Table 3.7 of the CHBDC and it shall be applied as indicated in Figure 12.2 of
the CHBDC for the TL-4 barrier.

2. For a TL-2 and TL-4 barrier the appropriate loads given in Table 3.7 of the CHBDC
and applied as indicated in Figure 12.2 of the CHBDC shall be used.

3. Top mounted traffic barriers shall be connected integrally to continuous footings (i.e.,
anchor slab, moment slab, see Figure 10.5.1 and shall be independent of the MSE
wall. The loading stipulated in (1) above shall be used for the design of the barrier
footing.

4. A traffic barrier integral with the MSE crash tested to NCHRP 350 or MASH for the test
level required, is acceptable as an alternative.

5. Consideration shall be given, where practical, to locating the MSE wall away from the
traffic barrier. (See Section 5.4).

10.6 Other Barrier Types

10.6.1 Noise Barriers

March 2024 Page 16 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

10.6.1.1 Highway Noise Barriers

The current practice for erecting noise barriers in the Ministry’s Right-of-Way is as follows:

1. When noise barriers are required on roadways and are located beyond the clear
recovery zone, then the noise barriers are erected simply between steel posts.

2. When noise barriers are required on roadways and are located within the clear
recovery zone, then the noise barriers are erected either on top of or behind traffic
barrier walls.

Noise Barriers adjacent to roadways are approved by Highway Design Office of MTO and
follow DSM 5.50 and roadside safety requirements.

10.6.1.2 Noise Barrier on Bridges

On bridges and retaining walls, the noise barriers are usually located within the clear
recovery zone and are generally attached either on top of or to the back face of barrier
walls. According to the CHBDC, when the noise barrier is located within the zone of
intrusion of the traffic barrier, the noise barrier in combination with the traffic barrier must
meet the crash test requirements of NCHRP 350 or MASH. Alternatively, in lieu of crash
testing, a noise barrier system meeting the requirements of CHBDC Clauses 12.4.7.1 to
12.4.7.4 may be used. Only noise barriers specified in DSM 5.50.40 shall be used on
MTO bridges. Due to the limited number of crash-tested noise barriers available, MTO
allows the use of a MASH tested TL-4 noise barrier, on TL-5 barrier wall, to be used for
TL-5 conditions. For all other test levels, the noise barrier shall satisfy the crash-test
requirements for the specific test level.

Recommendations

1. Before a noise barrier is considered for use on a bridge, a cost benefit analysis should
be carried out. This study should consider, but not be limited to, the following:
• That the noise reduction is significant enough to warrant the use of a noise barrier;
• That there are a reasonable number of residents that are expected to benefit from
the reduction in noise level as determined by MTO Environmental Guide for Noise
Oct 2006;
• Stopping the noise wall at the bridge and turning it obliquely (flanking) away from
the highway towards the residential area. In effect avoiding noise barrier walls
being erected on the bridge itself;
• The effect of increased loading to the structure (from vertical, wind, torsion loads
etc.). These effects may create the need for additional girders and cross bracing,
and a refined structural analysis for verification;
• Access for inspection of the bridge and the noise barrier components;
• Cost of an approved traffic/noise barrier wall system and additional costs to the
structure;
• Possible snow accumulation; and,
• Aesthetics.

March 2024 Page 17 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

2. Where it has been assessed that it will be beneficial to install a noise barrier wall on
bridges and retaining walls or portions thereof, the design shall satisfy CHBDC,
including requirements to contain or otherwise prevent debris that could endanger
public safety, from falling.

10.6.1.3 Noise Barrier Design

Noise barriers shall be designed in accordance with the CHBDC as light slender structures
not unusually sensitive to wind action, and CSA-Z107.9, Standard for Certification of Noise
Barriers. Wind loads and ice accretion loads on all the noise wall elements shall be
considered in the design as per the CHBDC. Reference wind pressures for a 25-year
return period shall be used.

In the calculation of section properties and strength for cold formed steel members, for
which the provisions of the CHBDC are not applicable, the requirements of CSA-S136 for
ultimate limit state design shall apply.

In evaluating or designing a structure on which a noise barrier is to be mounted, the above


criteria shall apply, except that the local reference wind pressure shall always be used and
a gust factor of 2.0 is sufficient for the relatively rigid structures (e.g., retaining walls), to
which noise barriers are generally attached.

10.6.2 Inspector Guards

Some areas exist where bridge inspectors and other maintenance staff are expected to
approach a location where a fall hazard exists. This hazard can be mitigated by wearing
appropriate PPE, or more preferably, by the use a railing. Site specific considerations
shall be reviewed to assess whether there is a need for an Inspector Guard to protect
against this, with the final decision made by the Head of the Structural Section. Installation
of guards should be planned as part of the major capital program when work is planned
on the structure. In some unique situations, guards may be provided as standalone
installations.

If guards were found to be needed in the review of fall hazard risk assessment, the
following policies shall apply:

1. Retaining walls within MTO’s right-of-way in areas with no pedestrian access where
the height of the wall exceeds 2.4 m shall be equipped with a guard or guardrail on top
of the wall as shown in Figure 10.6.1. For sloped walls where the height tapers from
zero to the full height of the embankment, the guard shall be placed starting from a
height of 1.0 m as shown in Figure 10.6.1. Guards shall be designed to meet the
requirements for guardrails of Industrial Requirements, R.R.O. 1990, Reg. 851, s.14.
Those requirements include a top and middle rail, but do not require a kick plate.
According to R.R.O. 1990, Reg. 851, section 14. (2) the loading and structural design
shall be in accordance with O. Reg. 332/12: Building Code.

2. At bridges and culverts, where the fall hazard from the obvert exceeds 2.4 m, the
headwall or top slab of the culvert shall be equipped with a guard on top of the wall

March 2024 Page 18 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

conforming to Section 1 of this memo. Figure 10.6.2 illustrates the schematic locations
of inspector guards in two typical culvert scenarios.

FIGURE 10.6.1 – GUARD REQUIREMENTS WITHIN MTO’S RIGHT-OF-WAY


WITHOUT PEDESTRIAN ACCESS

FIGURE 10.6.2 – GUARD REQUIREMENTS AT CULVERTS WHERE FALL HAZARD


EXCEEDS 2.4M

March 2024 Page 19 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

The guards shall be detailed as follows:

1. The guards shall be detailed on the structural drawings within a Contract and shall
include:
a. an elevation or plan to denote the limits of the guards;
b. details at expansion joints in the railings;
c. mounting details, and,
d. details of anchorage at base plates.

2. The guard shall be mounted on the wall, within 300 mm of the exterior face of the wall.

3. Posts shall be installed vertically.

4. Posts shall be mounted to the retaining wall with base plates and anchors designed to
resist the loads imposed on the guard. Anchors shall be embedded into the retaining
wall or anchored with epoxy. Given their history of problematic maintenance, posts
shall not be embedded directly into the concrete.

5. Guards shall be designed to avoid the accumulation of standing water at posts and
connections, with positive drainage to the fill side of the wall where practical.

6. Guards shall be galvanized, and pipe shall have a wall thickness no less than 3.5 mm.

7. Pickets, when required, shall be solid bar, round, or plate.

8. Connections shall be designed by the structural engineer. The structural engineer


shall ensure that the underlying surface and component to which the guard is mounted,
is adequate to resist the force applied to it from the post.

9. Drawings of guards shall be sealed per the requirements of the Structural Manual
Division 1.

Structural Standard Drawings SS110-33, Inspector Guard Details, is designed to meet the
design requirements above. Other Guards, meeting the requirements of the Industrial
Regulations or Building Code, as needed, may be used for longer applications or other
unique cases, where approved by the Head of the Structural Section. For Corrugated
Metal Culverts the details shown on SS110-33 will require modifications to suit the
placement and attachment to corrugated metal.

For locations that are more accessible to pedestrians, and with fall hazards as low as
600mm, a taller railing and/or one satisfying Ontario Building Code, O. Reg. 332/12,
s.3.3.1.17, with loading as specified in s.4.1.5.14 may be required.

10.6.3 Unreinforced Concrete Median Barriers and Shoulder Barriers

Unreinforced barrier walls are no longer used on Ministry bridges. The justification for the
use of unreinforced concrete median barriers was based entirely on testing and a history
of acceptable performance, rather than on their being able to meet structural design

March 2024 Page 20 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

requirements. Outside barriers on structures have always had to meet structural design
requirements.

Barrier walls are not permitted to be slip-formed on structures because the horizontal
reinforcement may produce voids beneath themselves during the slip-forming process.
Moisture could collect in these voids and cause problems when the moisture would freeze.
Concrete median barriers on structures must be cast-in-place and shall not be placed
directly on waterproofing membranes and must be provided with lateral restraint to prevent
movement. If the membrane is stopped at the barrier, it must be turned up the vertical
face at the barrier base and into a groove. With this arrangement, the barrier must be
dowelled to the deck so that small relative movement does not rupture the membrane.
Median barrier details shown on Structural Standard Drawings SS 110-62/63 meet these
requirements and that of the CHBDC.

10.7 Miscellaneous Details of Barriers

10.7.1 Architectural Finish on Barrier Walls

Bridge barriers are usually located where they are frequently seen by the public. An
architectural finish on the wall surface provides a pleasant aesthetic while maintaining the
proper structural function of the barrier.

A TL-5 concrete barrier wall with an architectural finish added to the outside face is shown
in SS110-70/93/99. The surface finish can be selected from the four standard patterns
given in Structural Standard Drawings SS110-71/72/73/74.

10.7.2 Detailing of Standard Steel Tube Railing

The Structural Standard Drawings permit detailing using either of two methods:

a) For structures on which the exact length of parapet or barrier railing can be readily
established, e.g., individual structures on tangent, the spacing of the posts shall be
shown on the drawings.

b) For other structures, e.g., structures on horizontal curves; structures or retaining walls
in groups connected by railing, on which the exact rail length may not be readily
established, the post spacing shall be determined by the contractor and should not be
shown on the plans. A note to this effect should be given on the drawings.

Unless otherwise specified in the standards, the post spacing with single tube hand
railings shall not exceed 2.5 m or 3.5 m for aluminum and steel rails respectively. For
other HSS steel railings, post spacing shall not exceed values specified on the respective
standard drawings. The rail shall be supplied in length to be attached to a minimum of
three rail posts and the rail splice shall be located within 600 mm from the post. The rail
should be ordered in standard lengths satisfying the criteria mentioned above plus pieces
for each side of the bridge of such a length as to give the exact rail length required.

March 2024 Page 21 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

If the curvature of the rail in position is sharper than 150 m radius, at least the first and
last sections of the rails should be pre bent and a note to this effect should be given on
the drawings.

10.7.3 Reinforcement Detail of Concrete Barrier Walls on Structures

The following requirements apply:

a) Longitudinal reinforcement in concrete barrier walls must be continuous through


construction joints;

b) Unsupported ends of barrier walls (including those at expansion joints) must, for a
distance of 1 m from the unsupported end, be provided with double the amount of
reinforcement required for moment for the remainder of the wall. This is normally done
by doubling up the number of bars at the unsupported end thereby reducing the
spacing to one half of the normal spacing.

10.7.4 Ducts in Concrete Barrier Walls

The following must be considered for all bridges with ducts in the concrete barrier walls:

a) A maximum of two ducts are permitted in a barrier;

b) For all new bridges when electrical duct is required, the duct diameter shall follow
electrical OPSD standards. Parapet walls shall be 300 mm wide to permit use of
75mm diameter ducts;

c) Ducts shall be no larger than 50 mm in parapet walls of 250 mm width. For existing
bridges where a 300 mm width of parapet wall is not feasible, use of 50 mm diameter
ducts in 250 mm wide parapet walls can be considered, with consultation with the
project’s electrical engineers to determine if the 50 mm diameter duct is adequate for
the project-specific needs;

d) Ducts shall be positioned to be tied to the reinforcement in the back face of the parapet
or barrier, with the lower duct at 200 mm above the asphalt. Duct positioning shall
allow concrete to flow around tension reinforcement and shall not impede the
anchorage of the tension reinforcement;

d) Junction boxes should not be located within 1 m from expansion joints, where the
vertical steel is at 110 mm spacing;

e) The deflection cavity for the duct (located at bridge expansion joints) is 143 mm dia. x
150 mm deep. This would interfere with reinforcement if the cover were at the
maximum tolerance of 70 ± 20 mm (90 mm). A note should be added stating:

"ADJUST END BAR SPACING TO ACCOMMODATE DUCT DEFLECTION CAVITY


FORMER.";

March 2024 Page 22 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

f) On structures with expansion joint assemblies, especially joints such as modular joints
(DSM 9.40.20), where the armouring is carried to the top of the barrier wall, provision
must be made to allow the ducts and duct deflection cavity former to be placed.

10.8 Barrier Design Aid

Dead loads of standard permanent barriers and temporary barriers are provided in
Division 3 in Design Aid 10-1 and Design Aid 10-2 respectively. For permanent barriers
the dead load is tabulated for typical barrier sections to be used for the design of
superstructure elements.

The temporary Barrier design Aid 10-2 contains the MTO’s standard Precast temporary
barriers along with proprietary steel barriers. Information of these proprietary barriers can
be obtained from MTO’s Roadside Design Manual.

March 2024 Page 23 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 10 - BARRIERS AND RAILING SYSTEMS

This page is intentionally left blank.

March 2024 Page 24 of 24 SM-D2-S10


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 11 - RIGID FRAMES

Table of Contents

11 RIGID FRAMES.................................................................................................... 2
11.1 General ........................................................................................................................ 2
11.1.1 Backfill .................................................................................................................. 2
11.1.2 Earth Pressure ...................................................................................................... 3
11.1.3 Drainage ............................................................................................................... 3

March 2024 Page 1 of 3 SM-D2-S11


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 11 - RIGID FRAMES

11 RIGID FRAMES

11.1 General

Rigid frame structures are ideal for short to medium span bridges. The high degree of
structural indeterminacy allows redistribution of forces between the deck and the
substructure contributing to resilience in the face of extreme events. The jointless nature
of a rigid frame structure offers a sustainable structure with low maintenance efforts during
the service life of the bridge.

The following sections provide discussion of key design parameters of rigid frame
structures.

11.1.1 Backfill

Unless the abutment walls have been designed to withstand earth pressure without the
deck in place, backfill should not be placed behind them until the deck is constructed.
Therefore, in most cases a note stating this should be shown on the contract drawings. A
standard note to be shown on the general arrangement drawing is given in Section 2.6.6.

The footings of rigid frame bridges exert a horizontal thrust upon the foundation, as well
as a vertical thrust. If the footings are free to rotate the frame is said to have hinged
supports. When the rotation of the footing is prevented, the supports are said to be fixed.
The supports are actually rarely hinged or fixed, but the foundation conditions lie
somewhere in the range between these two extremes: that is, the supports are restrained.

If the summation of the horizontal forces at the footing is not equal to zero (i.e., there is
insufficient resistance against sliding) the remaining unbalanced horizontal force will
cause a moment at the top of the rigid frame that should be accounted for in the design.

Normally, rigid frame structures are to be designed assuming simultaneous earth pressure
on both sides. It is essential in such cases that the general arrangement should bear the
standard note (given in Section 2.6.6) under "Construction Notes", on the right-hand side
of the drawing.

The standard note, or a shorter note, e.g., from "Backfill" to "abutment", in the note above,
must also appear on the preliminary version of the general arrangement.

When essential due to site access problems, a structure may be designed for earth
pressure on one side. This must be stated as a requirement in the Structural Design
Report. When a structure is designed for earth pressure on one side, the general
arrangement shall bear the following note under "Construction Notes" instead of the
standard note:

"BACKFILL BEHIND (designate, e.g., "the north", "either", etc.) ABUTMENT MAY BE
COMPLETED BEFORE BACKFILLING BEHIND THE OTHER ABUTMENT".

March 2024 Page 2 of 3 SM-D2-S11


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 11 - RIGID FRAMES

If the design of the abutment wall requires that it be supported during construction (e.g.,
for stability) a note to this effect should be shown on the general arrangement drawing
under “Construction Notes”.

11.1.2 Earth Pressure

Earth pressure distributions shall correspond to the anticipated movement at nominal


temperature loads. Nevertheless, rigid frames with spans up to 30 m, and other structures
where the deflection of the abutment is prevented by the propping action of the deck, may
be designed for the at-rest earth pressure.

11.1.3 Drainage

The provisions of Section 5.2.1.2. (b) to (e) inclusive apply to the legs of rigid frame
structures.

March 2024 Page 3 of 3 SM-D2-S11


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

Table of Contents

12 REINFORCING .................................................................................................... 2
12.1 General ........................................................................................................................ 2
12.1.1 Reinforcing Steel Bar - Identification ..................................................................... 2
12.1.2 Premium Reinforcing - Identification ..................................................................... 3
12.2 Premium Reinforcing – Where Required ...................................................................... 4
12.2.1 Reinforcing Steel for Concrete Culverts ...............................................................10
12.3 Reinforcing Geometry .................................................................................................10
12.3.1 Reinforcing – Dimensional and Shape Limitations ...............................................10
12.3.2 Use of Size 10M Reinforcing Bars .......................................................................11
12.3.3 Availability of 45M and 55M Reinforcing Steel .....................................................12
12.4 Reinforcement Details .................................................................................................12
12.4.1 Reinforcing Schedules .........................................................................................12
12.4.2 Detailing Reinforcing on Contract Drawings .........................................................12
12.4.3 Hooks and Bar Bends ..........................................................................................13
12.4.4 Spiral Reinforcement ...........................................................................................13
12.4.5 Splicing of Reinforcing Bars .................................................................................13
12.4.6 Anchor Headed GFRP Bars .................................................................................15
12.5 Anchors in Concrete....................................................................................................15
12.5.1 Post-installed Adhesive Dowels in Concrete ........................................................15

March 2024 Page 1 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

12 REINFORCING

12.1 General

Reinforcing steel in structures shall be CSA G30.18 Grade 500W. Premium reinforcing
steel shall be stainless steel according to OPSS 1440 or GFRP according to OPSS 1640.
Designs shall use a yield strength of 500 MPa in proportioning size and spacing of all
reinforcing steel in all components.

Structures shall be designed with a combination of black carbon reinforcement and


premium reinforcement, as required by Section 12.2. Steel reinforcement and GFRP shall
not be used in different orthogonal directions within the mat of reinforcement in a given
area. At locations where a mat transitions from steel to GFRP reinforcement, the designer
shall consider the implications for the structural behaviour (since the sectional behaviour
may change from being tensioned controlled to compression controlled).

Examples of how to approach design with GFRP reinforcing bar include:

• ISIS Design Manual, No. 3, Reinforcing Concrete Structures with Fibre


Reinforced Polymers, September 2007;

• ISIS Design Manual, No. 4, FRP Rehabilitation of Reinforced Concrete


Structures, March 2008;

• Bank, Lawrence C. Composites for Construction: Structural Design with FRP


Materials. 1st Ed. Hoboken: John Wiley & Sons, Inc., 2006;

• Nanni, Antonio, De Luca, Antonio, Jawaheri Zadeh, Hany. Reinforced


Concrete with FRP Bars: Mechanics and Design. 1st Ed. London: CRC Press,
2014.

However, these examples shall not be considered authoritative for MTO work. MTO
published documents and the CHBDC shall govern.

For bridges with decks that are waterproofed, black (carbon) reinforcing bars shall be used
in the deck except in the locations identified in Section 12.2, where Premium Reinforcing
materials (see Section 2.4.8) shall be used.

12.1.1 Reinforcing Steel Bar - Identification

Reinforcing bars shall be designated as illustrated in the following example pertaining to


black steel reinforcing:

15M @ 300

which denotes size 15 metric bars spaced at 300 mm, centre-to-centre, with the indicated
shape. M is the metric bar size identifier.

March 2024 Page 2 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

Some examples of bar designation for black steel reinforcing, illustrating the above, are
as follows:

15M

15M @ 300

20 - 15M @ 300

When the required bar shape is clear on the plan or section, the shape need not be given.

The bar size must always be given, but the bar spacing is not required to be given if they
are specified as "equally spaced" within a clearly defined length or width on the contract
drawings.

Where the length over which they apply can be calculated, or the distance is given, the
number of bars is not required to be shown.

The quantity, size and spacing of bars should be given in situations when the extent of the
bars is unclear, or it is simpler to do so.

The reinforcing schedules and placing drawings, which are prepared by the contractor,
will contain bar marks for identification purposes.

12.1.2 Premium Reinforcing - Identification

Prefix identifiers, as specified below, shall be used with Premium Reinforcing bar
designations. A prefix identifier shall be regarded as an inseparable part of the bar
identification.

Stainless Reinforcing Steel:

Stainless steel reinforcing shall be prefixed by the letter S. For example, a metric, 15
mm diameter, stainless steel reinforcing bar would be denoted as S15M. The General
Notes on the drawings shall indicate the Type of Stainless Steel (2205 Duplex or 316LN,
or 2304 Duplex) to be used.

GFRP Reinforcing:

Only Grade III GFRP reinforcement shall be used in the design. The bars shall be
identified by “G” for GFRP along with the nominal diameter (for example, a metric 15 mm
nominal diameter, GFRP reinforcing bar would be denoted as G15). The suffix M is
omitted from GFRP bar identifiers as the bar sizes do not conform to those of Canadian,
metric steel reinforcement. Bar diameter designators and nominal bar areas are defined
in CSA S807. Note that the nominal area values are not based on the designated
diameter. Nominal area values from CSA S807 shall be used in design.

GFRP reinforcement (bar sizes and areas as per CSA S807) is available in nominal
metric bars which are equivalent in area to the imperial sizes (e.g., size 15 has area of

March 2024 Page 3 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

199 mm2, size 25 has area of 509 mm2). For MTO projects, nominal diameters of 13,
15, 20, and 25 shall be used. The 10 mm nominal diameter is susceptible to damage
during construction, and 30 mm diameter is difficult for performing QC and QA testing,
and these sizes shall only be used with approval of the Structural Section.

12.2 Premium Reinforcing – Where Required

Premium Reinforcing shall be used in locations vulnerable to salt induced corrosion (as
defined in Table 12.2.1). In those locations, bars that are within 100 mm (e.g., cover
specified as 125 ± 25 mm) of the surfaces shall be of Premium Reinforcing unless:

a) The surface is permanently covered by water; or,

b) Footings permanently covered with at least 500 mm of soil and the concrete cover is
specified as minimum of 75 mm (i.e., 100 ± 25); or,

c) Buried structures where the surface is waterproofed.

Even for bridge decks that are waterproofed, those on busy highways have additional
wear of the waterproofing due to heavy traffic while simultaneously tending to have
rehabilitation and waterproofing replacement delayed due to the desire to avoid traffic
disruptions. For these bridges, there are benefits to using Premium Reinforcement in the
deck. Table 12.2.1 identifies bridge decks that require Premium Reinforcement.

For bridge rehabilitation:

• Where stainless steel is used, 2304 Duplex shall be specified. It is expected that Type
2304, with its lower Nickel content will be less expensive, but still adequate for the
rehabilitation service life;

• Where the remaining service life of the bridge is less than 35 years, conventional
concrete and black steel shall be used;

• Where the remaining service life of the bridge is between 35 and 45 years, Premium
Reinforcement is only required in exposed surfaces being replaced as part of
rehabilitation;

• Where the remaining service life of the bridge is longer than 45 years, the extent of
Premium Reinforcement, for components which require replacement, shall be the
same as for a new bridge.

Where bridges are being widened, the reinforcement requirements shall be as specified
by the Structural Section, with consideration to the remaining life of the widened portion,
and whether it will survive beyond the remaining life of the existing components of the
bridge. Premium Reinforcing is not required for selected components or structures that
are covered by specific standards and that have a design service life less than 50 years,
such as footings of sign support structures and footings of high mast pole structures.

March 2024 Page 4 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

TABLE 12.2.1 – REINFORCING REQUIREMENTS FOR SURFACES WITHIN SPLASH


ZONE

Component Surface Reinforcement6


Stainless or
GFRP on
Deck Slab Top Mat
freeways with
AADT > 50,000
Stainless or
Deck GFRP on
Closure pours between CIP deck stages
Top freeways with
AADT > 50,000
Stainless or
Deck Closure pours between Precast components.
GFRP
Deck Top within 1.5 m of expansion joint gap. Stainless
Topping Slab within 1.5 m of expansion joint. Stainless
Stainless or
Sidewalks Barrier and parapet walls. GFRP1
and
Barriers Sidewalks, medians, and curbs. Stainless or
GFRP
Stainless or
See Figure 12.2.1, Figure 12.2.2 and Figure 12.2.3.
GFRP
Deck soffit within 1.5 m of expansion joint gap. Stainless
Deck
Soffit Soffit of Post-tensioned Bridges with AADT > 50,000 Stainless or
under bridge8. GFRP
Same as CIP
Precast deck.
deck.
Stirrups and perimeter bars from precast component (i.e.,
Girders Stainless2
NU, CPCI, box) within 1.5 m of expansion joints.
Front surface of ballast wall and top surfaces of bearing
seats and pedestals exposed to roadway drainage or Stainless2
possible dripping3.
Surfaces of abutments, wingwalls, retaining and
Abutment Stainless or
MSE(RSS) walls5 that are exposed to roadway drainage
Areas GFRP
or possible dripping3.
Exposed faces of abutment walls, wingwalls, tunnels,
Stainless or
retaining and MSE (RSS) walls5 within 7 m horizontally
GFRP
and 5 m vertically of an existing or future roadway4.
Pier caps, bearing seats and sides of pier shafts and
Piers7 columns exposed to roadway drainage or possible Stainless
dripping3.

March 2024 Page 5 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

Side and end surfaces of pier shafts and columns within


10 m horizontally and 5 m vertically above an existing or
Stainless
future roadway6. All reinforcement in the column should
be considered, including dowels from the footing.
Pier shafts and columns exposed to roadway drainage or
Stainless
possible dripping.
Top surfaces of expansion joint end dams including those
Stainless2
at sleeper slabs supporting the end of the approach slabs.
Bars connecting approach slab to bridge and at approach
Stainless2
slab end.
Misc. For semi-integral abutment bridges: All surfaces at and
within 750 mm of the joint between the deck and wingwall. Stainless2
(See Figure 12.2.4 for examples).
Top and side surfaces of bases for lighting poles that are
Stainless2
attached to bridges.
Notes:

1. Where specified by the Structural Section, stainless steel may be required for TL-5
barriers on bridges with AADT > 100,000 and where deck/shoulder width is narrow,
precluding a safe work zone if repair to the barrier wall is required. For other situations,
use either Stainless Steel or GFRP.

2. GFRP shall not be used due to the excessive bend requirements of bars in these
locations.

3. This includes surfaces below joints (sealed or unsealed), deck drain outlets, and
overhanging features from which dripping may occur. “Below” should be taken to
mean within a vertical cone of height 5m (measured from the bearing seat or drainage
discharge) and having an apex angle of 45 degrees or likely to receive run-off from a
surface within such a cone.

4. Distance measured from the edge of the nearest travelled lane.

5. The designer shall specify which MSE walls in the contract fall within these limits and
require Premium Reinforcing in their facings. Premium reinforcing shall not be
specified on contract drawings and shall be supplied according to approved DSM
product drawings.

6. When AADT both on and under the bridge (if applicable) are between 400 and 2,000,
Premium Reinforcement is only required in the barrier walls, curbs and sidewalks, with
Black steel elsewhere. Where AADT < 400 both on and under the bridge (if
applicable), Premium Reinforcement is not required, and Black steel shall be used
throughout.

7. Although pier caps are within 5 meters vertically of the roadway surface, they are on
the outer periphery of the splash zone and historically have performed well with black
steel.

March 2024 Page 6 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

8. The requirement for Premium Reinforcing applies only to portions of the soffit within 6
m of top of the roadway surface. For the purpose of evaluation and design, post-
tensioned bridges have a design service life of 100 years.

FIGURE 12.2.1 – PREMIUM REINFORCEMENT BELOW JOINTS AND RAILINGS

March 2024 Page 7 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

FIGURE 12.2.2 – PREMIUM REINFORCEMENT BELOW JOINTS AND RAILINGS

March 2024 Page 8 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

FIGURE 12.2.3 – PREMIUM REINFORCEMENT BELOW JOINTS AND RAILINGS

March 2024 Page 9 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

DIAPHRAGM OVERHANG

*
*

*
*

*
*
*
*
JOINT BETWEEN JOINT BETWEEN
DECK AND WINGWALL DECK AND WINGWALL

1 2

BARRIER WALL JOINT BARRIER WALL BARRIER WALL JOINT BARRIER WALL
ON DECK ON WINGWALL ON DECK ON WINGWALL

CONCRETE CONCRETE
DECK DECK
1
JOINT BETWEEN
DECK AND WINGWALL JOINT BETWEEN 2
DECK AND WINGWALL
CONCRETE
GIRDER
STEEL
GIRDER

ABUTMENT WINGWALL
ABUTMENT WINGWALL

ELEVATION ELEVATION

LEGEND:

*
*
*

FIGURE 12.2.4 – PREMIUM REINFORCEMENT BELOW JOINTS AND RAILING

12.2.1 Reinforcing Steel for Concrete Culverts

Reinforcing steel quantities for all cast-in-place concrete culverts in a contract are
combined and included in a separate lump sum tender item for each culvert. However,
when the total quantity of reinforcing steel for all concrete culverts in a contract is less
than 5 tonnes, the reinforcing steel will be included in the concrete item "Concrete in
Culverts" and there will be no separate tender item for reinforcing steel.

12.3 Reinforcing Geometry

12.3.1 Reinforcing – Dimensional and Shape Limitations

12.3.1.1 Steel Reinforcing

The normal mill length for reinforcing steel bar stock is 12 m for size 10M, and 18 m for
all other bar sizes. These lengths should never be exceeded for straight bars.

March 2024 Page 10 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

The shipment by truck of bars longer than 15 m requires an uncommon type of vehicle
and should be avoided unless there is an economic advantage.

Bent bars, when laid flat, should fit into a rectangle having dimensions not greater than
20 m by 2.4 m.

12.3.1.2 GFRP Reinforcing

Length and shipment limitations for straight GFRP reinforcing bars are similar to those
of steel reinforcing bars. The process for forming and curing bent GFRP bars means
there are general limitations on the types of bent bar shapes that can be manufactured,
either by total length or effective plan area of shape. Due to differences in the
manufacturing process, the longest leg length of bent bars varies between DSM listed
suppliers. Consult DSM listed supplier documentation for further information.

In order to provide a GFRP design which all DSM suppliers are able to supply, the
following detailing limits should be respected:

• For components detailed with bent bars, the bars should be the smallest practical
size (13, 15 or 20).

• For 90° bends, the length of the sum of each leg should be less than 3 m.

• Stirrups should be designed with any assembly of shapes satisfying S6, each of them
designed to fit within a 1.1 m by 2.2 m rectangle. If these cannot be met, stirrups
and bent shapes should be detailed to fit within a 2.5 by 2 m rectangle.

• Shapes should have all bends in a single direction (i.e., all bends moving in clockwise
direction)

• Spirals or hoops should be detailed with extra turns or laps for anchorage and are to
be used only for structures classified in seismic performance category 1 per S6.
Spirals are available for columns up to 1.2 m in diameter. Spirals with bends into the
core of the column are not commercially available. Hoops may be used instead of
spirals in the drilled shaft foundations when the pitch spacing of spiral becomes tight
for concrete placement.

These limitations should be discussed with manufacturers if they affect the design.

Mechanical splices of GFRP reinforcing bar are not available, only lap splices shall be
permitted.

12.3.2 Use of Size 10M Reinforcing Bars

Size 10M bars are too flexible for most applications, particularly in deck slabs and where
they may be walked on. Size 10M bars shall not be used in cast-in place deck slabs;
their use should be restricted to small sections, such as barrier walls and precast units,
where supporting stirrups are close together.

March 2024 Page 11 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

12.3.3 Availability of 45M and 55M Reinforcing Steel

Size 45M and 55M reinforcing steel bars are not commonly required within the reinforcing
steel industry. Fabricators cannot economically justify stocking these bars for which
there is a low demand. As a result, a premium may be paid, and delays are possible if
these bars are specified. It is recommended that these bar sizes be avoided wherever
possible.

12.4 Reinforcement Details

12.4.1 Reinforcing Schedules

Rebar schedules shall not be prepared or provided by the designer in the contract
documents. Contractors are expected to produce the rebar schedules and working
drawings. The designer shall prepare the contract drawings so that there are sufficient
rebar details and other relevant information to facilitate the preparation of rebar
schedules and working drawings by the fabricator.

12.4.2 Detailing Reinforcing on Contract Drawings

1. The designer shall ensure that the contract drawings clearly show all required
detailing information.

2. Reinforcing bars shall be identified according to Sections 12.1.1 and 12.1.2.

3. Reinforcement details shall include the size, shape, spacing and placing limits for
individual bars, and if necessary, the number of bars. Detailing shall be adequate to
eliminate ambiguity and misinterpretation. Dimensioned sketches of bars should be
provided as required.

4. Where multiple layers of reinforcement exist, the bar sizes in the outer layer shall not
be less than any inner layer, and the bar spacing (linear for rectangular sections and
angular for circular columns) shall not be greater than in any inner layer.

5. Lap lengths for reinforcing steel, not indicated on the contract drawings, shall be
Class B as per CHBDC. Other lap lengths, where required, shall be indicated on the
drawings. For GFRP, these lap lengths shall be as modified according to the
requirements of CHBDC.

6. Reinforcing steel bar hooks shall be as per Structural Standard Drawing SS112-1
unless indicated otherwise.

7. Reinforcing steel stirrups shall have hooks as per Structural Standard Drawing
SS112-1, unless indicated otherwise.

8. Bent or curved GFRP reinforcing shall be fabricated with radii specified by the
manufacturer. Designers should be aware of manufacturers’ recommendations and
ensure that they are accounted for in the design, uncommon bend radii may increase
the cost of bent reinforcement as manufacturer’s may need to purchase components

March 2024 Page 12 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

for their bend forming apparatus.

Because of instances of poor quality GFRP reinforcing and code strength limitations
at “bend” locations, straight bars should be specified where possible.

9. Reinforcing tender items are lump sum bid items and the quantity shall not be listed
on the contract “Quantities-Structure” drawing.

10. The designer shall forward the quantities of reinforcing items for black steel
reinforcing, stainless reinforcing steel and GFRP reinforcing to the Project Delivery
Section for Ministry internal use.

11. The requirements of the notes 5 to 7 above should be given as part of the general
notes on the general arrangement drawing of all projects.

12. Structural reinforcement shown on the contract drawings shall not be used for any
electrical grounding purposes. Any electrical grounding, if required, shall be done
using independent insulated grounding cables that could be buried in/through
concrete, if preferred, and exiting the structural component to be connected outside
to a copper grounding rod.

12.4.3 Hooks and Bar Bends

Structural Standard Drawing SS112-1 shall be attached to the full-size Structural


Standard Drawings in a contract. It is intended for the contractor’s use, in order to
produce consistently accurate hooks and bar bends in black and stainless reinforcing
steel.

The GFRP industry has standardized bent shapes using a bend-radius-to-bar-diameter


ratio (r/d) of 4.0 and may not be able to readily manufacture bends with other r/d ratios.
The bend strength of GFRP reinforcing bar is strongly correlated with the r/d ratio,
which means that while the CHBDC (2019) permits the use of bars with a bend-radius-
to-bar diameter ratio of 3.0, most of the MTO’s DSM listed suppliers were qualified for
bends a r/d = 4.0 as meeting bend strength requirements. As such, both the minimum
r/d and standard r/d used on MTO projects shall be 4.0.

12.4.4 Spiral Reinforcement

Ontario reinforcement fabricators are only able to bend spirals of size 15M or smaller. If
larger transverse reinforcement is required, it may be possible to use bundled spirals
(2 nested 15M spirals that are touching, and then with a spiral pitch somewhat larger
than what could be achieved with a single spiral. Hoops of size 20M or 25M are also
possible.

12.4.5 Splicing of Reinforcing Bars

Design drawings shall clearly define splice type(s), locations, and force requirements.
For example, lapped versus mechanical splices; Type 1 versus Type 2 mechanical
splice.

March 2024 Page 13 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

Lap splices are preferred for splicing of reinforcing bars due to their reliability and ease
of inspection/verification during construction. Mechanical splices require material testing
and assembly verification during construction and should be used where geometry
necessitates, or where they provide benefits of reduced congestion of reinforcement or
cost savings from materials reduction, such as:

a) When the location of construction joints and provision for future construction dictates
the use of mechanical splices to provide tensile continuity, e.g., staged replacement
of bridge decks when projecting bars are not feasible.

b) Splicing bars greater than 35M.

c) Where spacing of rebar is insufficient to permit lapping of bars, or large amounts of


reinforcement or larger bars may obstruct concrete flow. This situation is common in
columns and caissons.

d) Forming openings in tub girders to facilitate formwork removal for cast-in-place decks.

OPSS 905 lists and describes the following six groups of mechanical connectors (subject
to DSM lists) for reinforcing steel bars:

a. Filled Sleeve Type b. Sleeve Swaged Coupler Type

c. Threaded Coupler Type d. Hot Rolled Thread Bar Coupler Type

e. Forged Bar Coupler Type f. Form Saver Type

The MTO groups of mechanical connectors is descriptive and a historical practice for the
DSM. The categorization of all DSM mechanical connectors is tension-compression
mechanical splices that can resist both tensile and compressive forces. The type of DSM
mechanical connector may be Type 1 or Type 2.

Mechanical connectors of black steel and stainless steel shall be supplied in accordance
with the latest active DSM at the time of contract awarded. Black steel bars shall not be
coupled with stainless steel connectors, and vice versa.

Mechanical connectors are not available or acceptable for splicing of GFRP reinforcing.

Minimum cover requirements apply to the splices and mechanical connectors. The
designer shall also consider geometric and clearance requirements for couplers (e.g.,
adequate access for swaged connectors, space between non-staggered couplers for
concrete flow, etc.).

Where required, mechanical connectors and splices shall be designed for their specified
fatigue loading.

March 2024 Page 14 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 12 - REINFORCING

12.4.6 Anchor Headed GFRP Bars

Anchor heads are only permitted on GFRP reinforcing bars of size 15 and may be
assumed to develop 100 kN of bar strength.

12.5 Anchors in Concrete

Anchors post-installed into concrete shall be adhesive bonded dowels. Mechanical,


grouted bonded and screw types shall not be used.

12.5.1 Post-installed Adhesive Dowels in Concrete

Adhesive dowels into concrete shall not be used in new structures, except for
reinforcement installed through steel or precast concrete girders at integral abutments and
piers, and for the connection of precast headwalls to precast culverts.

Dowels shall be detailed with holes drilled in downward, downward inclined, and horizontal
orientations. Adhesive anchors upwardly inclined, including vertically overhead shall not
be allowed. DSM List # 9.30.25 does not include any adhesives for use in overhead
applications, and for these applications, the industry is moving towards a requirement that
dowels be installed by personnel certified by an applicable certification program. The
collapse of the suspended ceiling system of the I-90 connector tunnel in Boston on July
10, 2006, prompted significant research and advancements in epoxy technology and
dowel installation requirements, explained in the FHWA publication T5140.34, NCHRP
Report 639, NCHRP Report 757, and the ACI/CRSI “Adhesive Anchor Installer”
certification program. Until approved products are included in the DSM and
installer/inspector programs become more accessible in Ontario, to ensure public safety
and long-term performance of the infrastructure, upwardly inclined dowels are not allowed.

Dowels into concrete shall not be larger than 25M.

Installation and acceptance testing shall be according to the relevant OPSS and SSP
specification.

For all applications other than anchorage of barriers and expansion joint end dams, epoxy
dowels shall not be relied on to provide more than 25% of the total required tensile
resistance at the critical section, and epoxy dowels shall not be used for applications
where sustained tensile load exceeds 25% of the allowable tensile capacity of the dowel
based on bond. If a higher capacity is required, the design of post-installed adhesive
dowels may be completed according to most recent edition of CSA A23.3 Annex D.

March 2024 Page 15 of 15 SM-D2-S12


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

Table of Contents

13 EXPANSION JOINTS AND BEARING ASSEMBLIES.......................................... 2


13.1 General ........................................................................................................................ 2
13.2 Expansion Joints .......................................................................................................... 2
13.2.1 Expansion Joints in Decks .................................................................................... 2
13.2.2 Approved Expansion Joint Assemblies ................................................................. 4
13.2.3 Expansion Joint Assemblies in Skewed Bridges ................................................... 5
13.2.4 Expansion Joint Drainage System ........................................................................ 5
13.2.5 Expansion Joints at the End of the Approach Slab of Integral and Semi-Integral
Bridges 6
13.2.6 Longitudinal Joints and Gaps ................................................................................ 6
13.2.7 Completion of Structural Standard Drawings ........................................................ 7
13.2.8 Force Due to Movement of Modular Joints............................................................ 7
13.2.9 Strip Seal Joints Anchored in Concrete ................................................................. 8
13.2.10 Sliding Plate Joints ............................................................................................ 9
13.2.11 Modular Joints ..................................................................................................10
13.3 Bridge Bearings...........................................................................................................13
13.3.1 Bearing Selection .................................................................................................14
13.3.2 Rotational Bridge Bearings ..................................................................................15
13.3.3 Elastomeric Bearings ...........................................................................................22
13.3.4 Provision for Future Bearing Replacement...........................................................26

March 2024 Page 1 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

13 EXPANSION JOINTS AND BEARING ASSEMBLIES

13.1 General

This section describes the types of deck expansion joints and bearings used on MTO’s
bridges. The design and detailing requirements for both components are discussed
throughout the section.

13.2 Expansion Joints

13.2.1 Expansion Joints in Decks

Bridge expansion joints are designed to allow for continuous traffic across structures while
accommodating movements due temperature variations of the structure, long-term effects
of creep and shrinkage of concrete, and differential settlement of substructures.
Expansion joints shall allow sufficient vertical movement to permit bearing replacement
without the need to dismantle the bridge expansion joint.

The designer should make every effort to minimise the number of expansion joints along
the length of structure and to locate expansion joints behind the abutments through
integral or semi-integral abutment configurations.

In all cases, the expansion gap shall be detailed parallel to the skew of the deck, for the
full width of the deck. In skewed bridges, the resulting exposed acute angled concrete
edges shall be provided with 50 mm chamfers. Designers should avoid skew angles of
32 to 38 degrees, inclusive, to minimise the chances of snagging snow plough blades
which are usually set at approximately 35 degrees.

In addition to longitudinal movement of the superstructure, displacements due to rotation


of the structure under transient loads shall be considered.

The gap between the end of a deck and the ballast wall face must meet the requirements
of the CHBDC. The gap between the underside of the deck and the bearing seat shall be
large enough and accessible for cleaning. The drawings must show the gaps free of any
material used to form them in construction.

When specifying an expansion joint movement rating, only those movements which can
occur after the joint has been installed shall be considered. Thus, when specifying
expansion joint movement ratings for rehabilitation projects, elastic shortening, hydration,
shrinkage, and creep effects should be neglected. Likewise, for new prestressed concrete
bridges, creep and shrinkage effects occurring prior to joint installation should be
neglected. In prestressed concrete bridges, joint installation should occur as long after
the completion of prestressing operations as the schedule permits and shall be indicated
on the expansion joint standard.

Proper installation is critical in achieving the expected long-term performance of expansion


joints. Important elements of the installation include proper alignment, installation after
paving, and epoxy injection under the armouring. Proper installation of expansion joint

March 2024 Page 2 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

assemblies accounts for compaction of the asphalt wearing surface, by traffic, adjacent to
the concrete end dams.

Expansion joints may be installed prior to or after paving. The Ministry’s preference has
historically been to install deck joint assemblies after paving because this method provides
a superior ride for vehicles, resulting in lower impact on the joint and its anchorage, and
superior durability. Installing deck joint assemblies after paving often places the operation
on the critical path of the construction schedule. Projects have the potential to be delayed
and incur cost overruns if the designer and/or contractor does not fully account for this. It
has been found that there are some instances where installation prior to paving is
acceptable, such as when a reduced durability is acceptable over the remaining service
life of the bridge.

The designer shall specify the method of deck joint assembly installation in all new bridge
construction or bridge rehabilitation projects which require new deck joint assemblies as
follows:

1. The designer may choose to specify installation prior to paving when all the following
criteria are met:

a) The bridge is being rehabilitated;

b) The bridge is not skewed;

c) Average Annual Daily Traffic (AADT) is less than 2000;

d) The estimated working days for structure work, with installation prior to paving, is
at least 10% less than with installation after paving.

The designer shall specify installation after paving for all other scenarios, unless
written Approval is obtained by the designer from the Head, Structural Section.

2. The designer shall include Structural Standard Drawing SS113-38 in the Contract
Documents and modify it to reflect the actual bridge and to show the specified method
of installation.

3. The designer shall include fill-in standard special provision SP 920F03 in the Contract
Documents, amending OPSS 920 to clearly specify the method of deck joint assembly
installation for each bridge.

The designer shall consider that installation prior to paving reduces the durability and
longevity of the expansion joint. A service life of 20 years shall be assumed for financial
analysis.

The guidelines included above may also be used to assist the designer in evaluating a
contractor’s request to install deck joint assemblies prior to paving.

Concrete end dams detailed between an asphalt wearing surface and an expansion joint
seal shall be wide enough to permit the placing of concrete through the gap between joint

March 2024 Page 3 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

armouring and concrete dam armouring. Concrete end dams should not be less than
500 mm in width, either side of the joint seal. Weep holes through the deck are required
at low points at these dams. Refer to OPSD 3349.100.

Straight reinforcing bars shall be placed parallel to expansion joints in the concrete end
dams and shall consist of:

a) for modular joints: two shorter bars lapped between the support boxes; and,

b) for all joints: at least two shorter lapped bars which are to be weaved through anchor
loops and through other reinforcing steel.

Joints should be specified on the drawings by reference to the appropriate "Designated


Sources for Material List" number and, in the case of DSM 9.40 - Joints, by type.

When splicing of joint armouring is unavoidable, such as between construction stages,


permissible splice locations must be shown on the drawings. Such locations should be at
crown points, if possible, and in no case shall they be located near curbs, barrier walls,
wheel paths or at any point where water is likely to pond. On skew bridges, when the
approved splice is shown at a crown, the splice in the armouring should be shown parallel
to the centreline of the traffic lane and not perpendicular to centreline of joint.

The material for strip seals shall be polychloroprene (neoprene). Natural rubber is not
permitted because MTO lab tests have found that the effects of ozone and oil swell tests
were unacceptable.

13.2.2 Approved Expansion Joint Assemblies

The expansion joint systems approved for use on new and/or rehabilitated structures are
listed in Designated Sources for Materials List DSM 9.40 - Joints as follows:

DSM NO. DIVISION/APPLICATION/PRODUCT


DSM 9.40.18 Expansion, Injection Systems for Armouring
DSM 9.40.20 Expansion, Modular
DSM 9.40.24 Expansion, Strip Seals Anchored in Concrete, Type A
DSM 9.40.27 Expansion, Strip Seals Anchored in Concrete, Type C
DSM 9.40.33 Expansion, Strip Seals in Preformed Retainer

Guidelines for the application of these lists are given in 13.2.1 to 13.2.5. The selection of
the expansion joints for bridges shall be based on the total design movements at SLS and
other requirements of this section. During the design process, the designer shall select
which type should be used for each joint location on the bridge (see Table 13.2.1).

March 2024 Page 4 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

TABLE 13.2.1 – EXPANSION JOINT SELECTION

Design Integral and Semi-


Conventional
Movement at integral Abutment Note
Abutment Bridges
SLS (mm) Bridges
Section 16.6 or Section
0 to 10 - Type A or C
13.2.2
11 to 40 Type C* Type A or C * at Sleeper Slab
41 to 80 Type C* Type A or C * at Sleeper Slab
76 to 120 - Sliding Plate -
Field splicing of modular
81 to 400 - Modular
joints is not permitted

13.2.3 Expansion Joint Assemblies in Skewed Bridges

A plan and profile must be provided on the drawings for skewed expansion joints.

Joint assemblies in bridges with skews should be carried through sidewalks, medians, and
barrier walls without horizontal change in direction wherever possible. A 50 mm chamfer
shall be detailed on all exposed acute angled concrete deck edges on skewed bridges.

Where this is not possible the horizontal change in direction should be affected at a
location not less than 100 mm and not greater than 600 mm from the edge of the asphalt
at the barrier wall. The change in direction shall be affected by means of a 600 mm radius
bend. The exact location of the radius bend should appear on the plan view of the
structure on the contract drawings and on the contractor's shop drawings. Locating the
horizontal change as close as is practicable to the barrier wall reduces the modifications
necessary to the substructure.

A horizontal change in direction shall NOT be located within 100 mm of a vertical change
in direction since simultaneous bending of the seal in two planes is either physically
impossible or likely to lead to leakage between the seal and the clamping device.

Structures having a skew of up to 15 degrees or over 45 degrees shall have joint


armouring anchorage bars, on the deck side, detailed perpendicular to the expansion joint.
Structures skewed from over 15 degrees up to 45 degrees shall use joint armouring
anchorage bars, on the deck side, detailed 30 degrees offset from the perpendicular to
the expansion joint. Anchorages on the abutment side of the joint shall be placed at right
angles to the joint. The gap and blockout dimensions for the expansion joint on skewed
bridges should be detailed perpendicular to the joint.

13.2.4 Expansion Joint Drainage System

Strip seal expansion joints and the sliding plate expansion joint assembly are available
with a drainage system which allows runoff from the seal to be channeled through the
barrier and down to the ground through a scupper and downpipe according SS113-14.
The drainage system prevents local ponding where the joint seal is otherwise upturned
into the barrier and flushes the joint seal of debris. The flushing is particularly beneficial
for sliding plate joints where the strip seal is covered with steel plates. The use of the

March 2024 Page 5 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

drainage system is recommended when freezing and/or ponding of water is a concern,


specifically for bridges on flat profiles or close to a flat section of a vertical curve. The
drainage system shall not be used in aesthetically sensitive locations and underpasses.

13.2.5 Expansion Joints at the End of the Approach Slab of Integral and Semi-Integral
Bridges

Integral abutment bridges are single or multi-span bridges with the superstructure
integrally connected to the abutments. Both Integral and Semi-Integral bridge approach
slabs are integrally connected to and move together with the superstructure and the
abutment.

The movement demand is proportional to the expansion length of the superstructure.


Presently, a bridge can be made integral when the expansion length of the superstructure
does not exceed 75 m (i.e., total length of 150 m). The specified treatment at the end of
the approach slab should vary with the expected movement.

For integral and semi-integral abutment bridges where the expected movement at the end
of the approach slab does not exceed 10 mm, the movement end of the approach slab
shall be detailed as follows. Regardless of the movement calculated, the following detail
shall be used on integral bridges of up to 40 m in total length.

FIGURE 13.2.1 – EXPANSION JOINT DETAIL AT THE END OF APPROACH SLAB


FOR SPAN LENGTH < 40M

For integral and semi-integral abutment bridges where the expected movement at the end
of the approach slab is greater than 10 mm or for integral bridges longer than 40 m,
Structural Standard Drawing SS113-36 shall be used. The approach end of the approach
slab shall be supported on a sleeper slab and a Type C expansion joint shall be provided
between the approach slab and the sleeper slab.

13.2.6 Longitudinal Joints and Gaps

Longitudinal joints exposed to traffic shall be avoided unless approved by the Head of the
Structural Section. When used, they shall be Type C expansion joints to accommodate
movement demands from differential deflection and movement and have adequate
durability to withstand the traffic loads placed upon them.

March 2024 Page 6 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

Twin bridges separated by a narrow longitudinal gap shall be sealed to prevent the
accumulation and passage of debris, snow, water, and chlorides. These longitudinal gaps
(typically between raised medians or parallel barrier walls) shall be detailed with a
proprietary expansion joint seal according to MTO Policy Memo #SCB-SO-2021-02.

13.2.7 Completion of Structural Standard Drawings

The following note on the expansion joint Structural Standard Drawings must be
completed by the designer:

"EXPANSION JOINT SHALL BE IN ACCORDANCE WITH THE DESIGNATED


SOURCES FOR MATERIALS LIST DSM 9.40.[Note 1] AND SHALL HAVE A RATED TOTAL
MOVEMENT CAPACITY OF … mm." [Note 2]

Note 1: The designer shall insert the number of the appropriate DSM list or Lists which are
acceptable. Where DSM 9.40 - Joints are shown, the acceptable type or types must also
be given, except when all types are acceptable.

Note 2 The movement shown should be the required movement as determined by the Designer,
calculated at Serviceability Limit States; this movement shall not exceed the rated
movement of at least one of the joints in the type specified, and where possible, should not
exceed the rated movement of at least one joint from each supplier in the type specified.

The movement ratings given in Designated Sources for Materials List DSM 9.40 were
established from laboratory testing and to allow seal replacement at 25°C.

In completing the table of design requirements, the “J” dimension shall be determined by
setting the joint seal to be closed to the minimum opening at the hottest effective
temperature, increased by 5 mm where possible (i.e., when the full rated movement of the
joint is not fully utilised). This will have the effect of providing slightly more opening for
future replacement of the seal.

13.2.8 Force Due to Movement of Modular Joints

The force associated with the movement of modular joints shall be considered when
designing abutments.

When a bridge contracts in the longitudinal direction due to a decrease in Temperature


(as well as due to Creep and Shrinkage in prestressed concrete bridges), the modular
joint responds by opening further to accommodate this movement. As the joint opens, the
control springs which maintain equidistant openings across the seals are compressed,
causing a corresponding resistance to the opening movement, and thereby transferring
this resisting force as a horizontal load to the top of the ballast wall.

Assuming a control spring stiffness of 0.15 kN/mm, and supports beams spaced at 800
mm centre-to-centre, the resulting unfactored horizontal force would be approximately 8
kN per metre length of ballast wall.

March 2024 Page 7 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

13.2.9 Strip Seal Joints Anchored in Concrete

The joints in this list are for bridges having total deck joint movements calculated at SLS,
measured parallel to the centreline of the highway, and after joint assembly installation, of
80 mm or less but not greater than the rated movement of the joint specified.

DSM 9.40.24 and 9.40.27 is subdivided into several types based on the method of seal
retention used. General guidelines showing the characteristics of each type and the
applications for which it should be considered, are given on the following pages.

It is the responsibility of the designer to select the appropriate type or types of joint in
accordance with those general guidelines. All types of expansion joints on the DSM List
have been approved by the Ministry and should be considered for application on
structures. Where further guidance is required the Head, Structural Section should be
consulted.

Structural Standard Drawing SS113-11 covers anchorages and armouring for all types of
expansion joints listed in DSM 9.40.24 and 9.40.27.

Strip Seals - Type A Steel Plate Clamping Device

Clamping Plate Subject to Direct Wheel Load

FIGURE 13.2.2 – STRIP SEALS – TYPE A STEEL PLATE CLAMPING DEVICE

Characteristics
• Clamping plate directly supported.
• Few components.
• Excellent seal retention.
• Easy to install and replace seal.
• Direct access to clamping bolts and seal.

March 2024 Page 8 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

• Seal can be inspected completely and reused, if undamaged.


• Easy to modify for changes in elevation.
• Higher initial cost.

Strip Seals - Type C Retainers and Stop Bars

FIGURE 13.2.3 – STRIP SEALS – TYPE C RETAINERS AND STOP BARS

Characteristics

• Good seal retention.


• Can accommodate change in direction in plan.
• Seal cannot be inspected completely without removing the seal.
• Installation or replacement of seal may be difficult.
• Special tools and trained personnel required to install or replace seal for maintenance
purposes.
• No direct access to clamping device or retainer and seal.
• Difficult to replace bolted clamping device or damaged retainer.

Application

Type A joints as per DSM 9.40.24 should be considered for all bridges and particularly for
bridges which carry high volume freeway/arterial traffic (and especially when there is a
high proportion of heavy vehicles). For bridges which, as determined by the Head,
Structural Section, it is essential to minimise the frequency and duration of future lane
closures, only Type A joints shall be specified.

Type C joints as per DSM 9.40.27 shall be specified for all bridges except those where
only Type A joints are allowed. Expansion joints between sleeper slabs and approach
slabs shall be Type C.

13.2.10 Sliding Plate Joints

Sliding plate expansion joints (see Figure 13.2.4) and Structural Standard Drawings
SS113-30 to SS113-35) shall be used for joints where the SLS design movement is
greater than 75 mm and less than or equal to 120 mm. The sliding plate is designed to
behave as propped cantilever. It is essential that the sliding plate be installed with the

March 2024 Page 9 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

correct tolerance to the stop plate. During service, the joint is designed to function with
the sliding plate either directly bearing on the sliding plate or up to a maximum of 3 mm
above the sliding plate. At installation, the gap between the sliding plate and the stop
plate should be no more than 1 mm.

Sliding plate expansion joints shall only be used at abutments of post-tensioned deck
bridges and at abutments of girder type bridges. They shall not be used at pier locations.
Sliding plate joints shall not be installed in bridges when the slope of the roadway at the
joint exceeds 2% unless the bearings at that location are inclined to the same slope as
the highway. When the deck is sloped and the bearings are installed level, translation due
to expansion and contraction results in a change in the vertical gap between the sliding
plate and the stop plate.

FIGURE 13.2.4 – SLIDING PLATE EXPANSION JOINT

13.2.11 Modular Joints

13.2.11.1 Modular Joint Use

Modular joints shall be used when total deck joint movements, after joint assembly
installation and measured parallel to the centreline of the highway, are greater than
120 mm in one direction. With this type of expansion joint, wheels bear directly on the
separation beams between the seals. Seals and separation beams form a watertight joint
at the riding surface. Separation beams are supported by steel support bars each having
its own support box at both ends. One end of the support bar is fixed in a short support
box in the end dam, and the other end slides on engineered bearings inside a longer
support box. Modular joints are classified by the number of longitudinal support bars and
how they are connected to the transverse separation beams. In a multiple support bar
system, each separation beam is supported on an individual support bar. The number of

March 2024 Page 10 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

support bars therefore equals the number of separation beams and in a large movement
joint, the number of support bars leads to a joint that is not easily accessed from below for
maintenance. A single support bar system has all the separation beams supported on
one large support beam, and the separation beams slide on bearings on the top face of
the support beam. A single support bar system is therefore more accessible for
maintenance. Due to past performance, the Ministry has shifted towards single support
bar systems.

Modular joints shall not be field spliced.

In order to preserve the ride quality across a modular joint, the bearings supporting the
girder end shall be installed at the same slope as the highway vertical profile, to allow the
support bars to remain parallel to the highway at all range of movement.

Available Modular joints can have a minimum of 3 to a maximum of 8 seals. The maximum
movement of any one seal, measured parallel to the centreline of the highway, must not
exceed 60 mm.

The end dam over the ballast wall, the gap between the ballast wall and the deck end, and
the end dam at the deck end shall be detailed to permit installation of any modular joint
listed on DSM No. 9.40.20.

The absolute minimum distance between end dams, denoted F, is 250 mm at 15°C, to
permit access to the joint components for maintenance. The distance between the ballast
wall and the deck end, denoted L1 shall be as specified in Table 13.2.2 to permit
inspection and maintenance of the expansion joint from beneath. A corbel shall be
introduced on the ballast wall side with length D to support the end dam. The corbel shall
be detailed with a dimension D of 250 mm for 3 seals, 200 mm for 4 seals, and 150 mm
for 5 or more seals. The corbel shall be designed and detailed to be increased by up to
150 mm to accommodate the specific joint supplier. Dimensions F and D are shown Figure
13.2.5.

For post-tensioned concrete bridges, L1 should be calculated at 15°C for the required joint
size and movements due to creep, shrinkage and temperature fall occurring after time of
joint installation. In lieu of more accurate data, the designer may assume joint installation
occurs at 90 days after stressing of prestressed concrete bridges.

The width of blockout B1 and B2 depend on the number of seals in the joint, while the
depth of blockout H depends on the number of seals and on the supplier of the expansion
joint. Dimensions B1, B2 and H in Figure 13.2.6 shall be detailed according to Table
13.2.2.

The following note shall be added to the ABUTMENT drawing:

“THE CONTRACTOR SHALL ADJUST CORBEL DIMENSION ‘D’ AND REINFORCING


STEEL TO SUIT THE ACTUAL MODULAR EXPANSION JOINT FOR THE BRIDGE, UP
TO A MAXIMUM OF 150 mm.”

March 2024 Page 11 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

13.2.11.2 Modular Joint Selection

1. Calculate the Design Movement, due to the sum of Creep + Shrinkage + Temperature
Range.
Creep and Shrinkage movements are from time of joint installation (e.g., t = 90 days)
to joint replacement, assumed at a service life of 40 years.

Movements due to Temperature Range are from the sum of temperature fall to
temperature rise.

2. Obtain the Serviceability Limit States design movement which is 80% of the above
Design Movement.

If the SLS Design Movement < 120 mm, use strip seal (see Section 13.2.2 and Section
13.2.3 to Section 13.2.5) or sliding plate joints (see Section 13.2.6) as appropriate.

3. For Modular Joints, select the joint size (number of seals required) based on the SLS
Design Movement as provided in DSM 9.40.20.

4. Detail the abutment ballast wall and deck ends to accommodate dimensions "B1", “B2”
and "H".

TABLE 13.2.2 – MODULAR JOINT DETAILING TABLE

No. OF SEALS 2 3 4 5 6 7 8
B1 (mm) 590 675 760 835 915 995 1075
B2 (mm) 600 600 600 650 650 700 700
H (mm) MINIMUM 355 355 355 355 380 380 380
F @ 15°C (mm) 200 330 460 600 730 850 980
L1 @ 15°C (mm) 600 600 660 750 880 1000 1130

FIGURE 13.2.5 – MODULAR JOINT DETAIL – SECTION AT BOXES (SINGLE


SUPPORT BAR SYSTEM)

March 2024 Page 12 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

13.2.11.3 Modular Joint Setting

Having selected an expansion joint whose Range of gap rating (max. gap minus min. gap)
is greater than or equal to the SLS Design Movement, the "J" gap dimension must be
calculated at the assumed 15º C construction temperature.

For prestressed concrete structures, "J" at 15ºC equals 0.8 (CR + SH + Tfall), where Tfall is
the movement due to a temperature drop from 15°C to the Minimum Effective
Temperature used in design, and CR and SH correspond to the anticipated creep and
shrinkage of the bridge for 40 years after joint installation.

The maximum and minimum "J" dimensions shall be shown on the expansion joint
drawing.

13.2.11.4 Abutment Width

Since large movements are expected when modular joints are used, the abutment should
be proportioned based on the distances shown in Figure 13.2.6. The effect of skew and
minimum seating requirements for earthquake should also be considered. L1 shall be a
minimum of 600 mm for modular joints, to permit inspection and maintenance of the joint.
For post-tensioned bridges, the minimum lengths of L1 and L2 shall be satisfied at 90 days
after placing concrete.

L1 = Gap between ballast wall and end of deck

L2 = Distance between centreline of bearings and end of deck, as required to satisfy


minimum seating length requirements,

L3 = Distance between centreline of bearings and face of abutment

t= Thickness of ballast wall (see Section 5.2.3.1 for minimum thickness)

FIGURE 13.2.6 – MINIMUM WIDTH OF ABUTMENT

13.3 Bridge Bearings

March 2024 Page 13 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

13.3.1 Bearing Selection

MTO maintains standards for rotational bearings and for elastomeric bearings. The
selection of the bearings should be based on the articulation requirements of the structure.
The requirements of the bearings such as translations, rotations, vertical and lateral load
capacities and any special requirements must be established during the design process.
Design values provided in the tables on the drawings shall be the actual demands on the
bearings, from the structure, and shall not include additional tolerances. Tolerances are
added to the values specified in the design, as required by OPSS 1202 and 1203, which
include the tolerances required by the CHBDC.

For reactions of up to 3000 kN at SLS1, the designer shall specify elastomeric bearings
because of their long-term durability and cost-effectiveness, unless movement or rotation
demands preclude their use.

For high loads and/or long movements, rotational bearings shall be selected. For the
majority of bridges, all three types of rotational bearings will satisfy all the structural
requirements. However, there will be some bridges where, for reasons such as rotational
capacity or rotational stiffness, only one or two classes of bearings will be acceptable.

For bridges with more than one span, except for integral bridges where only plain
elastomeric bearings are used and for prestressed girder bridges with elastomeric
bearings, a bearing drawing shall be included in the design drawings for the bridge. The
bearing drawing shall contain a plan layout of the bearing locations at every support, along
with a symbol to indicate the bearing type and fixity. Figure 13.3.1 shows an example of
a bearing layout, along with the standard symbols to be used for rotational and elastomeric
bearings, and their associated restraints.

FIGURE 13.3.1 – BEARING LAYOUT AND LEGEND

March 2024 Page 14 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

Since the final bearing design is completed by the bearing supplier, the designer shall
provide a schematic section on the bearing drawing to convey the main components of
the bearing and the outer dimensions of the bearing assumed in the design. For
elastomeric bearings, the height of the bearing shall be shown along with any details of
positive attachment or plates above and below the bearing. For rotational bearings, a
typical section as shown in Figure 13.3.5 (bearing section). For most cases, a section
through the bearing transverse to the bridge profile is sufficient but a longitudinal section
may be required for bearings with longer movements or highways with steeper grades.

13.3.2 Rotational Bridge Bearings

This Section provides a summary of the features of rotational bearings which could affect
bearing selection and identify the bearing design data for rotational bearings that must be
shown on the plans. They do not apply to plain or laminated elastomeric bearings.

The Designated Sources for Materials List DSM 9.15.70 for Bridge Rotational Bearings
(except elastomeric bearings) will include three types of bearings divided into six classes:

• Class 1A – Pot Bearings Without Uplift Restraint Devices

• Class 2A – Disc Bearings Without Uplift Restraint Devices

• Class 3A – Spherical Bearings Without Uplift Restraint Devices

These bearings may be equipped with sliding surfaces for translation and guides for lateral
restraint.

Uplift restraint devices should be avoided and their use requires the approval of the
Structures Office Manager. Uplift-restraint devices shall not restrict the function of a
bearing and shall not limit the rotation capacity nor the displacement of the bearings under
any load combination. OPSS 1203 and 922 do not include provisions for design of uplift-
restraint bearings. When they are used, the contract shall include special provisions to
cover their design.

Columns supporting expansion bearings made of lubricated, unfilled PTFE surfaces shall
be proportioned based on a design coefficient of friction as given in the CHBDC.

13.3.2.1 Effect of Rotation on Eccentricity of Axial Load

When a bearing rotates about a horizontal axis there is a shift in the axial load from the
centre of bearing and the load becomes eccentric. The shift in the axial load depends on
the type of bearing.

For pot and disc bearings, the shift in the axial load from the centre of bearing depends
on the properties of the elastomer and is difficult to calculate. Creep of elastomer has a
beneficial effect in reducing the shift for disc bearings. Tests indicate that the shift can be
2% to 4% of the diameter of confined elastomer for pot bearings, and 2% to as much as
30% of the diameter of elastomer disc for disc bearings.

March 2024 Page 15 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

For spherical bearings, the shift "e", in the axial load, depends on the coefficient of friction
“μ”, and the spherical radius of curvature, "R", and is expressed by:

𝑒𝑒 = 𝜇𝜇𝜇𝜇

Given the values of coefficient of friction specified in the CHBDC, and that the spherical
radius of curvature "R" is generally between 1.0 and 2.8 times the plan diameter of the
PTFE curved surface, the shift in the axial load for spherical bearings can be 3% to 17%
of the diameter of the PTFE curved surface. At Serviceability Limit State Combination 1
loads and maximum rotation, CHBDC limits the shift in the axial load from the centre of
the bearing to the following values:

a) 4% of the diameter of the confined elastomer for pot bearings;

b) 10% of the diameter of the polyether urethane polymer compound for disc bearings;

c) 10% of the plan diameter of the curved PTFE surface for spherical bearings.

The effects of the maximum permitted shift in the axial load must be considered in the
design of the affected structural components above and below the bearing. Where it is
difficult or costly to provide for the 10% shift, the design may be restricted to pot bearings.

13.3.2.2 Translation and Rotation Capacity

Translational and rotational requirements about any horizontal axis and about the vertical
axis through the centre of the bearing provided in the bearing design data table shall be
as required by design.

13.3.2.3 Orientation of Guided Bearings on Curved Structures

The designer should minimise the number of guided sliding bearings at each support
(abutment or pier) location. One is usually adequate, and this should preferably be at the
centre of the support. If multiple guided bearings are required at a support, the alignment
should be the same for both and set to correspond to a point equidistant from each
bearing.

In horizontally curved structures, two concepts generally exist when designing for
horizontal movements. They are as follows:

a) The structure is guided to a Centre of Fixity by aligning guided sliding bearings parallel
to the chord drawn from the bearing to the theoretical point of fixity (see Figure 13.3.2).
The Centre of Fixity is the point of zero movement of the superstructure for internally
induced forces or movements due to temperature change, as well as creep and
shrinkage if applicable. It is calculated by taking into consideration the combined
stiffness of all supports including shear stiffness of bearings, flexural stiffness of
supports (abutment or pier) and rotation of footings due to strain of piles or subsoil.

Bearing Orientation A tends to accommodate the direction of the superstructure


movements without introducing horizontal forces to the substructure due to these

March 2024 Page 16 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

movements. However, for sharp or compound curves, this can introduce distortion at
the abutment expansion joint and misalignment of barrier walls. One way to avoid this
is to place the expansion joint perpendicular to the centroidal chord, but this is not
recommended since it will necessitate skewed abutments.

- Guided bearings aligned parallel to chord.

FIGURE 13.3.2 – BEARING ORIENTATION, A

b) The structure is guided tangentially by aligning guided sliding bearings tangent to the
radius of the structure at the support (abutment or pier) location (see Figure 13.3.3).

Bearing orientation B relies on the guided bearings to force the horizontal movement
in the direction of the longitudinal curved axis of the superstructure, resulting in
horizontal forces being transferred to the substructure through these bearings.

- Guided bearings aligned tangent to structure radius.

FIGURE 13.3.3 – BEARING ORIENTATION B

March 2024 Page 17 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

Both methods of bearing orientation have been used successfully in the past, each
with their attendant benefits and disadvantages. The choice of method to use is left
to the individual designer. However, since it is always better to minimise the
introduction of additional forces or deformations into a structural system, the guided
bearings at piers are recommended to be aligned as per Method A, while the guided
bearings at abutments are recommended to be aligned as per Method B (see Figure
13.3.4). As a result, because expansion joints at abutments are placed radially, they
will expand and contract parallel to the abutment guided bearings without distortion
and the abutments are generally better able to handle the lateral loads.

- At Abutments, guided bearings are aligned tangent to structure radius.


- At Piers, guided bearings are aligned parallel to chord.

FIGURE 13.3.4 – BEARING ORIENTATION C

Whichever method of bearing orientation is used in design, the designer is encouraged


to use a refined method of analysis to determine the resulting horizontal movements
and corresponding forces transferred to the substructure.

13.3.2.4 Lateral Load Capacity

Fixed and guided bearings shall be capable of resisting lateral loads in the restrained
direction as required by the design and as given in the CHBDC. All lateral loads shall be
resisted by a single bearing at a support line (pier or abutment line). However, for ULS-5
through ULS-8 (i.e., for Exceptional Loads), when more than one identical bearing with
guides for lateral restraint are provided at a pier or abutment, one bearing shall be
assumed to achieve its full lateral resistance while a second bearing shall be assumed to
resist 50% of its full lateral capacity and any subsequent guided bearings shall not
contribute to the lateral resistance. Other means of lateral restraint (i.e., a shear key)
should be used to provide lateral resistance to the bridge superstructure when the factored
lateral force exceeds 50% of the permanent reaction at the bearing.

March 2024 Page 18 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

13.3.2.5 Concrete Bearing Pressure

The average concrete bearing pressure used by the bearing manufacturer to proportion
the bearing shall be based on a Specified 28-day Compressive Strength of 30 MPa.

The concrete bearing surfaces above and below the bearing should be proportioned and
reinforced when necessary to withstand these pressures and lateral loads.

13.3.2.6 Installation

As the elevation at the top of bearings is critical especially for bolting diaphragms of steel
box girders, the tolerances for the elevation at the top of bearings as specified in
OPSS 922 are as follows:

Concrete deck or girders ±5 mm


Steel plate girders 0 to +3.0 mm
Steel box girders 0 to 2.0 mm

The Specification requires all bearings to be bedded over their entire area on an approved
grout to achieve the theoretical elevations within these tolerances. The thickness of the
bedding grout shall be 12 mm +/- 3 mm.

The height of bearing, ‘D’ (as shown in Figure 13.3.5) assumed in establishing the bearing
seat elevation should include 12 mm for grout bedding and the drawings should include
the following note:

"HEIGHTS OF BEARINGS INCLUDE 12 MM BEDDING GROUT AND EXCLUDE THE


SHOE PLATE THICKNESS. HEIGHTS OF BEARINGS ASSUMED IN ESTABLISHING
BEARING SEAT ELEVATIONS ARE AS FOLLOWS. THE CONTRACTOR SHALL
ADJUST BEARING SEAT ELEVATIONS AND REINFORCING STEEL TO SUIT ACTUAL
HEIGHTS OF BEARINGS.

ABUTMENTS … mm
PIERS … mm "

Precautions must be taken by the Designer, when there is the possibility of bearings being
installed under extreme cold or hot temperatures and not at 15ºC. Either the top plate of
a sliding bearing should be made sufficiently large to accommodate all of the maximum
expansion and contraction movements, or alternatively the Designer should specify a
temperature vs. setting table and corresponding details on the contract drawings.

March 2024 Page 19 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

plinth
50

shoe plate
75
50
40
100

bearing
height
40
including 75
40mm grout

FIGURE 13.3.5 – BEARING SECTION

13.3.2.7 Bearing Design Data

The bearing design data provided on the plans shall be as indicated below. Applied
horizontal loads shall be consistent with applied axial loads. Additional rows may be added
if necessary for atypical bridges where one of many ULS combinations may govern. Any
special requirements must also be specified.

ROTATIONAL BEARING DESIGN DATA


LOCATION TYPE LIMIT COMBINATION AXIAL MAX. MAX.
MAX.
STATE LOAD ROTATION TRANSLATION
HORIZ. LOAD (kN)
(kN) (radians) (mm)
ABOUT ABOUT
LONGIT TRANS HOR. VERT. LONGIT TRANS
AXIS AXIS
PERMANENT
directional or multi-

Serviceability

PERMANENT +
[Fixed or uni-

directional]

TRANSITORY
MAX.
PERMANENT +
TRANSITORY
MIN.
U

PERMANENT
l

March 2024 Page 20 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

PERMANENT +
TRANSITORY
MAX.
PERMANENT +
TRANSITORY
MIN.
PERMANENT +
EXCEPTIONAL
MAX.
PERMANENT +
EXCEPTIONAL
MIN.

The contract drawings shall include the following notes:

1. ROTATIONAL BEARINGS SHALL BE CLASS/CLASSES LISTED IN DSM 9.15.71,


9.15.75, and 9.15.80 UNDER THE HEADING "BEARINGS, BRIDGE
(ROTATIONAL)”.

2. THE CONTRACTOR SHALL ESTABLISH THE BEARING SIZE SUCH THAT


CONTACT PRESSURE UNDER PERMANENT LOADS AT SLS IS NOT LESS THAN
25 MPa.

3. BEARING SUPPLIERS ARE REQUIRED TO PROVIDE ADDITIONAL ROTATIONAL


CAPACITY OF 0.02 RADIANS ABOUT THE HORIZONTAL AXIS AND 0.02 RADIANS
ABOUT THE VERTICAL AXIS IN ACCORDANCE WITH OPSS 1203 AND AS
REQUIRED BY CHBDC.

4. THE CONTRACTOR SHALL COORDINATE WITH THE BEARING SUPPLIER THE


LOCATION OF THE BEARING ANCHORAGES IN THE PIERS AND/OR
ABUTMENTS. HOLES TO RECEIVE ANCHORS SHALL BE FORMED INTO THE
SUBSTRUCTURE. CORING IS NOT PERMITTED.

The additional rotations mentioned in note 3 shall not be included in the bearing design
table.

For bearings subject to uplift, the maximum permitted separation of the bearing
components must be specified.

The maximum required translation must be based on the assumption that, at the time of
installation, the longitudinal and transverse centrelines of the bearing sliding plate will be
set to coincide with the longitudinal and transverse centrelines of the bearing.

The coefficient of friction for PTFE sliding surfaces given in the CHBDC depends on
whether the PTFE resin is “filled” or “unfilled”. The type of PTFE resin assumed for design
must be included with the bearing design data given on the contract drawings, specifically
giving the following note: “UNFILLED PTFE, LUBRICATED DIMPLED SHEET HAS BEEN
USED IN THE DESIGN FOR ESTABLISHING THE BEARING COEFFICIENT OF
FRICTION.” This produces the minimum coefficient of friction. If for some reason the
designer wants to transfer a greater than minimum horizontal force to a particular sub-
structure, other sliding surface treatments given in the CHBDC may be considered.

March 2024 Page 21 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

13.3.3 Elastomeric Bearings

13.3.3.1 General

Elastomeric bearings, plain and laminated, shall be natural rubber supplied in accordance
with OPSS 1202. The following bearing sizes are recommended but other sizes may be
available.

TABLE 13.3.1 – STANDARD LAMINATED ELASTOMERIC BEARING SIZES

Size Minimum Target SLS1 Load


(mm x mm) Thickness (mm) (kN)
300 x 200 50 420
350 x 250 55 610
400 x 300 55 840
450 x 350 60 1100
500 x 400 65 1400
550 x 450 70 1730
600 x 500 80 2100
600 x 600 90 2520
600 x 700 90 2940
600 x 800 100 3360

S6-19 limits the total shear strain on the bearing but does not limit the bearing pressure.
OPSS 1202 further limits the compressive deformation of the bearing to approximately
0.07 of the effective elastomer thickness. Target SLS1 values correspond to a total
pressure of 7.0 MPa. The target SLS1 load values included in the table have proven
performance but may be exceeded provided the bearing is designed to satisfy S6-19 and
OPSS 1202.

Higher aspect ratio (width to length ratio) bearings may be preferable when thinner
bearings are required and rotation limitations are governing; they may be used when
approval is obtained by the designer from the Head, Structural Section.

The rotational capacity of any bearing is a function of the effective elastomer thickness
and is determined as per CHBDC.

13.3.3.2 Elastomeric Bearings Thickness

The thickness of plain elastomeric bearings specified on the contract drawings shall be
between 15 mm and 25 mm. Plain elastomeric bearings shall be used only for temporary
applications, for bedding of larger bearings, or in cases where they are encased in
concrete.

Bearing thickness shall be chosen to limit shear strain due to shear displacement to 0.5.

March 2024 Page 22 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

The minimum thickness of laminated elastomeric bearings shall be according to Table


13.3.1. The minimum thicknesses in the table were established to accommodate a
rotation of 0.002 rad due to transient loads in addition to the rotation tolerances in S6-19.
As long as bearing is specified with a thickness equal to or greater than the value in the
table, and loaded with at least 3 MPa under permanent loads, the bearing will meet the
strain requirements (S6-19 clauses 11.6.6.3.2 to 11.6.6.3.4), lift-off requirements (Clause
11.6.6.8), positive attachment (11.6.6.6) for service temperature Ts > -44ºC and
elastomer-to-concrete interfaces, as well as deformation limits required by OPSS 1202.

For post-tensioned concrete structures, the use of a thicker elastomeric bearing may be a
more economical choice than jacking the structure several months after stressing to
release the shear deformation in the bearing.

Thicker bearings do not add significant cost. A taller bearing may be preferable to reduce
the force transferred to the substructure, to avoid the need for positive attachment, or to
accommodate larger rotations.

13.3.3.3 Strip Bearings for Precast Side-by-side Box Girders and Precast Slabs

Strip plain elastomeric bearings may be used for precast side-by-side box girders or
precast slab bridges. The thickness of the strip bearing shall not exceed 25 mm.

13.3.3.4 Laminated Elastomeric Bearing with Slider Plate Assembly

For durability reasons, a slider plate shall not be used when a thicker bearing without a
slider plate is feasible and shall not be used for a movement range of less than 50 mm.
This type of bearing may be a reasonable choice for a long structure where the only other
solution would be a rotational bearing (pot, disc, or spherical bearing). OPSS 922 does
not cover the design provisions for laminated elastomeric bearings with sliding elements,
and if used, details of the sliding surfaces should be provided in the Contract Drawings
with appropriate NSSP’s to cover their design and fabrication.

13.3.3.5 Supply of Additional Sample Bearings for Testing

To ensure the quality of the bearings supplied, standard special provision 922F01 requires
that additional elastomeric bearings be supplied by the contractor for testing purposes.

The number of bearings requiring testing is based on the type of bearing, and the number
of bearings of each size. The fill-in special provision for bearings provides guidance to
the designer on the exact number of bearings to test. This special provision shall be
included in the contract. Each structure requires at least one bearing of each size for
testing. No samples for testing are required for bearings that are temporary and/or
subsequently encased in concrete (e.g., bearings located at the integral supports of
integral abutment type structures).

Additional bearings are not required to be supplied for all other approved bearings (i.e.,
disc, pot, spherical).

Twin structures shall be considered as separate structures.

March 2024 Page 23 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

13.3.3.6 Shear Rate of Elastomeric Bearings

When an elastomeric bearing undergoes shear deformation due to horizontal loading, a


horizontal force develops which is transferred to the substructure. The magnitude of this
force is a function of the shear stiffness (shear rate) of the bearing at the time of
displacement and the amount of bearing deformation.

The amount of deformation (due to superstructure movement) depends on the combined


effects of the following internally induced forces:

a) Heat of hydration (of concrete);

b) Elastic shortening (of concrete due to prestressing);

c) Shrinkage (of concrete);

d) Creep (of concrete under prestress and permanent loads);

e) Temperature effects.

Note: a) to d) are applicable to concrete structures only, and e) is applicable to all


structures.

The shear stiffness of any elastomeric bearing depends on the plan area and total
thickness of the rubber, and the shear modulus of the elastomer. The shear stiffness is
nearly constant for all temperatures above freezing but increases rapidly with decreasing
temperatures due to crystallization of the rubber. At -40°C, the shear rate can be two
times the stiffness at construction temperature.

In light of this, and since the various structure movements occur not only at its different
ages (important when considering creep and shrinkage) but also at a variety of
temperatures, the designer must use the bearing shear stiffnesses that correspond to
each condition in order to design the substructure.

For bearing design data given on the contract drawings, the designer should give the
shear stiffness rate that is assumed in the design of the substructure, at 20°C, denoted
K20. Bearing catalogues provide the shear rates for standard laminated elastomeric
bearings sizes.

The force that is transferred to the substructure for which it must be designed shall be
determined as follows.

For temperature drop, even though the bearing will experience a sustained shear
deformation over an extended period of time during cold temperatures, the bearing
stiffness starts at near K20 and increases at the lower temperatures after much of the
deformation has already occurred. The arithmetic mean of the full range of K values
should be used. For temperature drop, K = 1.35 * K20 should be used.

March 2024 Page 24 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

For temperature rise, since such bridge movements occur at a temperature above 15°C,
K20 should be used.

A) Shear Rate for Concrete Structures

Because shrinkage and creep occur throughout the year and gradually over many
seasons, it is expected that the bearing will undergo cycles of cooling and warming. Any
force that is induced during colder periods will be relieved to that calculated with K20 when
the temperature rises. Therefore, the horizontal force due to creep and shrinkage is
calculated assuming K20.

For post-tensioned bridge, the superstructure may be jacked up (at approximately three
months after construction) to relieve all horizontal shear deformation that has taken place
in the bearing pad until that time, returning the bearing to its originally undeformed
configuration. This relieves bearing movement due to heat of hydration, elastic shortening
and a portion of the total shrinkage and creep. After jacking, the bearing returns to vertical
at the assumed construction temperature and must be designed for the remaining portion
of shrinkage and creep, and all displacement due to temperature.

13.3.3.7 Elastomeric Bearing Design Data

For elastomeric bearings, the minimum design data provided on the contract drawings
shall be as indicated below. Any special requirements must also be specified.

ELASTOMERIC BEARING DATA


LOCATION ABUTMENTS PIERS
TYPE --- ---
SIZE (mm) __x__x__ __x__x__
NUMBER REQUIRED --- ---
SERVICEABILITY LIMIT STATES
PERMANENT LOAD (kN) --- ---
TOTAL LOAD (kN) --- ---
MOVEMENT (mm) ± ___ ± ___
ROTATION (radian) --- ---
SHEAR RATE at 20ºC (kN/mm) --- ---

The rotation value in the table shall be the imposed rotation required by the design, plus
the tolerances for rotations due to manufacturing and construction as required by the
CHBDC but shall be not less than ± 0.009 radians. Rotation in the bearing data table
corresponds to total load.

13.3.3.8 Installation of Elastomeric Bearings

Elastomeric bearings are to be installed directly on the bearing seats. No filler or grout is
to be shown on the drawings.

March 2024 Page 25 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

Precautions must be taken by the designer when there is the possibility of bearings being
installed below 0ºC or above 20 ºC. The translational capacity of the elastomeric bearing
shall be greater than the anticipated maximum movement.

Positive attachment shall be detailed on the contract drawings where required by S6-19.

Laminated elastomeric bearings supporting steel bridges shall be detailed with two pintles
between the shoe plate and the top lamina of the bearing. This prevents the structural
steel from unseating from the bearing during construction. This is especially important for
longer bridges where laminated elastomeric bearings cannot accommodate any
movements through shear deformation until a greater axial load form the deck concrete is
applied across the bearing to initiate frictional resistance to shear.

13.3.4 Provision for Future Bearing Replacement

Enough space, both vertically and horizontally, must be provided between the
superstructure and substructure to accommodate the required jacks for replacing the
bearings. The vertical clearance for jacks shall be no less than 200 mm. The designer
shall detail the jacking locations in the contract drawings based on the MTO Bearing
Replacement and Jacking Guidelines.

Connections (e.g., between bearings and shoe plates) must be bolted or make use of
accessible screws and should only be welded when future access and removability can
be guaranteed.

Requirements and guidance on bearing replacement procedures and bridge jacking


methods are provided in MTO document (BRO-062) – Bearing Replacement and Jacking
Guidelines.

March 2024 Page 26 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 13 - EXPANSION JOINTS AND BEARING ASSEMBLIES

This page is intentionally left blank.

March 2024 Page 27 of 27 SM-D2-S13


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 14 - CULVERTS

Table of Contents

14 CULVERTS .......................................................................................................... 2
14.1 General ........................................................................................................................ 2
14.2 Concrete Culverts ........................................................................................................ 2
14.2.1 Cast in Place Concrete Culverts ........................................................................... 2
14.2.2 Precast Concrete Culverts .................................................................................... 2
14.2.3 Waterproofing of Culverts ..................................................................................... 3
14.2.4 Earth Pressure ...................................................................................................... 4
14.2.5 Design of Concrete Culverts ................................................................................. 4
14.3 Metal Culverts .............................................................................................................. 4
14.3.1 Corrugated Metal Culverts .................................................................................... 4
14.3.2 Corrugated Steel Pipe (CSP) Products Dimensioning ........................................... 5
14.3.3 Length of Structural Plate Pipes and Pipe Arches ................................................. 5

March 2024 Page 1 of 6 SM-D2-S14


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 14 - CULVERTS

14 CULVERTS

14.1 General

This section shall apply to:

a) all culverts (buried structures) with spans 3m and greater; and,

b) all cast-in-place culverts detailed in the MTO Concrete Culvert Design and
Detailing Manual.

c) All culvert sizes specified in OPSS 1821,

d) all culverts contained in the future MTO Precast Concrete Box Culvert Manual.

On contract and working drawings the Culvert shall be identified as SPAN X RISE.

14.2 Concrete Culverts

14.2.1 Cast in Place Concrete Culverts

All cast in place concrete culverts should be designed and detailed in accordance with the
latest version of the Concrete Culvert Design and Detailing Manual. In this manual the
designs meet the requirements of the CHBDC and contains information necessary to
complete the standard drawings and quantities for concrete box and open footing culverts.
The following culvert types are covered:

a) Rigid frame open footing culverts with fill heights of 0.6 m to 6.0 m and sizes
2.0 m span x 1.25 m height to 6.0 m span x 4.0 m height;

b) Rigid frame box culverts with fill heights of 0.6 m to 6.0 m and sizes
2.0 m span x 1.25 m height to 6.0 m span x 4.0 m height; and,

c) Non-rigid frame box culverts with fill heights of 0.6 m to 5.0 m and sizes 1.25 m span
x 1.25 m height to 1.5 m span x 1.5 m height.

Reduced scale copies of the standard drawings for all of the above culvert types are
available in the “Concrete Culvert Design and Detailing Manual.”

14.2.2 Precast Concrete Culverts

Currently in MTO’s inventory, two categories of precast concrete culverts exist:

1. Culverts spanning 3m or less, which are fabricated and built according to OPSS 1821
“Material Specifications for Precast Reinforced Box Culverts and Box Sewers”, and
typically use Dry-Cast concrete. These culverts are generally used in drainage and
sewerage applications. The design of these culverts, in specific span and height
combinations to achieve maximum efficiency, is specified in the design tables which
are included in OPSS 1821.

March 2024 Page 2 of 6 SM-D2-S14


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 14 - CULVERTS

The culverts of this category are reinforced with welded wire fabric (WWF). The
material requirements are contained in OPSS 1340 for Concrete and OPSS 1440 for
WWF steel reinforcement. The construction specifications of these culverts are
covered in OPSS 422.

2. Culverts spanning greater than 3m are typically designed for larger scale application
for example high volume of stream flow or to act as a small bridge for multi-use (e.g.,
pedestrian, bicycle) traffic. Current practice is that the designer is required to perform
project specific analysis and design of the large culverts. These culverts are to be
reinforced either with black steel reinforcement or with WWF. Construction and
material requirements are specified in OPSS 912.

MTO has recently published construction specification OPSS 912 for Culverts with Spans
MTO has also issued design tables for this category of culverts in Memo # SCB-SO-2021-
01 which will enable designers to use the design information directly from the tables on
the contract drawings. Precast Concrete Box Culvert Manual containing design guidelines
will be published in the near future.

Irrespective of the categories, all precast box culverts shall be designed in accordance
with the CHBDC.

14.2.3 Waterproofing of Culverts

Concrete culverts with spans 3.0 m and greater shall be waterproofed irrespective of fill
height. Hot applied rubberized asphalt waterproofing system is the standard treatment for
the top surface of culverts with spans 3.0 m or greater. For precast concrete culverts, self-
adhering waterproofing membrane shall be applied at the joints prior to application of the
hot applied rubberized asphalt waterproofing on the top surface of the culvert. General
waterproofing and joint waterproofing shall extend a distance down from the top as
specified in SSP 599S30. Waterproofing need not be placed on areas beyond the limits
of embankment fill or under a distribution slab, as specified in the SSP. Protection board
is also added to protect the waterproofing from damage from backfill.

Waterproofing shall be specified for concrete culverts with a span 3.0 m or less for
following situations:

a) where a 75-year service life is required;

b) where additional durability is required;

c) under high volume roads where culvert rehabilitation or replacement would be


disruptive; or,

d) which are expected to be used by pedestrians or snowmobilers during the winter (where
icicles can pose a danger to the public).

Hot-applied rubberized asphalt waterproofing system is used by MTO for top surface
waterproofing of all types of culverts. However, the self-adhering waterproofing
membrane may also be used in special situations, such as in remote areas where labour

March 2024 Page 3 of 6 SM-D2-S14


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 14 - CULVERTS

and equipment to install hot- rubberized asphalt waterproofing membrane system


becomes unavailable or deemed uneconomical. Use of self-adhering waterproofing
system shall require the approval from the Structural Section in advance, prior to the start
of waterproofing operation on site.

14.2.4 Earth Pressure

Culverts and other structures where the deflection of the side walls is prevented by the
propping action of slabs shall be designed for the earth pressures specified in CHBDC.

14.2.5 Design of Concrete Culverts

Beneficial effects of compression in reinforced concrete culvert components should not be


taken into account in the design.

Cast-in-place culverts and precast culverts with fill height less than 600 mm shall require
reinforced concrete distribution slab above the culvert for distribution of live loads. The
distribution slab shall be designed as per the CHBDC.

Design of culvert appurtenances such as headwalls, retaining walls or wingwalls are to be


designed as per CHBDC. In the design, consideration should be given if the culvert
appurtenances are cast-in-place or precast. For precast elements, design should consider
ease of site installation of the element on the precast culvert with integral connection.
Culvert cut-off wall or apron wall is considered a non-structural component.

14.3 Metal Culverts

14.3.1 Corrugated Metal Culverts

Corrugated Steel Culvert (CSP) and Structural Plate Corrugated Steel Pipe (SPCSP)
terms are often used interchangeably. When used separately, the former is used typically
for the smaller sized made of a continuous helical corrugated plate, while the latter is used
for typically larger diameters made up of several plates around the circumference. Steel
is the most common material, although aluminum is also available, typically for more
severe environments.

Structural Plate Corrugated Steel Pipe Culverts (SPCSP) are fabricated by using hot-
rolled sheets or plates that are corrugated, curved to radius, custom hot-dip galvanized or
has a thermoplastic copolymer coating, assembled, and bolted together to form steel
culverts, pipes, arches, pipe-arches, and other shapes.

Environmental factors shall be considered while checking the suitability of site for using
SPCSP. The thickness of SPCSP and other steel components shall be determined
according to CHBDC to ensure the culvert is structurally sound until the end of the design
life. The design shall account for environmental conditions that exist at the site or are
likely to exist during the design life of the structure, and the anticipated steel material loss
during the design life. The MTO Gravity Pipe Design Guidelines and the CHBDC shall be
referenced for guidance. Notwithstanding the requirements above, the thickness of the
SPCSP shall not be less than 5 mm.

March 2024 Page 4 of 6 SM-D2-S14


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 14 - CULVERTS

All metal culverts irrespective of their span length must have adequate site preparation
and compacted backfill material around them.

The use of pipe arches is restricted to sites at which round pipes cannot be
accommodated. Other alternatives should also be considered. It is necessary that the
installation of pipe arches make provision for the necessary backfill volume of engineered
soils (granular ‘A’) on each side of the structure and that each installation have cut off
walls or headwalls on each end.

MTO is currently working to create standards for metal culverts material and construction
specifications. Until these standards are published designer must create non-standard
specifications and seek for Structural Office’s endorsement. For NSP preparation, MTO’s
Special Provision No. DBSP3271 could be referred to.

14.3.2 Corrugated Steel Pipe (CSP) Products Dimensioning

All dimensions of corrugated steel pipe products must be given in metric units, which are
generally conversions of dimensions set in imperial.

14.3.3 Length of Structural Plate Pipes and Pipe Arches

The overall length of structural plate pipe and pipe arches shall always be detailed on the
drawings and the dimension shown shall always be multiples of 610 mm, +100 mm.

e.g., 61,100 mm is acceptable.

This permits the use of an integral number of standard plate sizes, without cutting, and
ensures that the hook bolts in the cut off walls will be aligned with the standard
circumferential holes in the plates.

The spacing of hook bolts, if required, should be a multiple of 244 mm, to match the
spacing of standard holes in the plates.

14.3.4 Durability

Joints, including seams, shall be constructed and treated to prevent leakage and
infiltration. To prevent leakage through the culvert and associated passage of chloride
contaminated water leading to corrosion, the culvert shall be covered by a waterproofing
membrane. The membrane has a minimum thickness of 0.5 mm and is made of PVC,
HDPE, or some other polymer materials. It is draped over the culvert to take water away
from the culvert, with granular backfill between the liner and culvert to prevent punctures
from bolts or other edges.

Structural Plate Corrugated Steel Pipe (SPCSP) and Corrugated Steel Pipe (Culverts)
made of galvanized steel have shown signs of early corrosion in many environments in
Ontario. Polymer-coated pipe and metallic coated bolts have been used in newer culverts.
Structural Section and Structures Office shall be contacted to assist in determining the
suitability of the metal pipe for the given soil and water conditions, as well as for
requirements for the pipe system.

March 2024 Page 5 of 6 SM-D2-S14


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 14 - CULVERTS

This page is intentionally left blank.

March 2024 Page 6 of 6 SM-D2-S14


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Table of Contents

15 WOOD STRUCTURES ........................................................................................ 2


15.1 Material Properties of Softwood ................................................................................... 2
15.1.1 Structure of a Tree ................................................................................................ 2
15.1.2 Strength Properties ............................................................................................... 3
15.1.3 Moisture ................................................................................................................ 3
15.2 Design .......................................................................................................................... 4
15.2.1 Species ................................................................................................................. 5
15.2.2 Dimensions ........................................................................................................... 6
15.2.3 Pressure Preservative Treatment for Wood .......................................................... 7
15.2.4 Decks ................................................................................................................... 9
15.2.5 Traffic Barrier and Railing ..................................................................................... 9
15.3 Fabrication ................................................................................................................... 9
15.3.1 Shop Trial Assembly ............................................................................................. 9
15.3.2 Details..................................................................................................................10
15.3.3 Appearance .........................................................................................................11
15.3.4 Coatings ..............................................................................................................11
15.4 Wood Notes ................................................................................................................12
15.5 Maintenance Schedule ................................................................................................15
15.6 Sources of Information ................................................................................................16
15.6.1 Extra Design Information .....................................................................................16
15.6.2 Historical MTO Research References ..................................................................16
15.6.3 Other Information .................................................................................................17

March 2024 Page 1 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

15 WOOD STRUCTURES

15.1 Material Properties of Softwood

Properties of individual species are available, but for the purposes of design, some similar
species and varieties of sub-species are grouped together such as Southern Yellow Pine
(Pinus spp.), or the species combinations of CSA O86.

Hardwood is not commonly used for structural lumber but is very similar to softwood.

15.1.1 Structure of a Tree

Wood is an anisotropic, cellulosic, semicrystalline, cellular material. The material


complexity may be simplified by understanding that wood is a biological structure that
serves three functions in living plants:

1. To conduct water and nutrients from the roots to the leaves;

2. Mechanical support of the plant body;

3. Storage of biochemicals.

These functions have resulted in cells that are structured and interconnected in ways to
meet the needs of the plant, which has implications on the properties and design of
wood. The trunk is the useable portion of a tree for wood used in structures which may
be divided generally into heartwood and sapwood (Figure 15.1.1).

FIGURE 15.1.1 –
MACROSTRUCTURE OF FIGURE 15.1.2 – PRINCIPAL AXES OF
TRUNK (BOLE) WOOD

March 2024 Page 2 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Sapwood is the active conduction portion of the stem with live, metabolically active cells.
The pores are more open and there is a higher moisture content. The sapwood is more
prone to shrinkage and cracking, and is more susceptible to decay, but is easier to treat
with preservatives.

The heartwood functions as long-term storage of biochemicals (extractives) which


occludes pores and makes it more difficult to treat. The cells are dead, but it is more
naturally decay resistant than sapwood and is denser, dryer, and stronger than sapwood
(acts as the central, supporting pillar of the tree).

A review of the microstructure of the wood shows that discrete cells, typically many times
longer than they are wide, are interconnected in two separate systems of cells, i.e., an
axial system and a radial system. The axial system acts primarily as long-distance water
movement, so it has the most free water in the cell lumina and provides the bulk of
mechanical strength to the tree. The radial system provides lateral transport for
biochemicals and in many cases performs a large fraction of the storage function in wood.
More detail on the structure and properties of wood may be found elsewhere, such as
Forest Products Laboratory, Wood Handbook, Wood as an Engineering Material (FPL-
GTR-282).

The cell structure directly affects the properties of wood as a building material. As such,
the mechanical properties (elastic, strength, and rheologic) exhibit strong orientation
effects (axial and radial system) and are complicated by the addition of growth
irregularities (e.g., branches are seen as knots in sawn lumber). Mechanically, clear wood
obeys the laws of elastic orthotropic materials, and its failure characteristics are well
described by strain energy of distortion-type theory. Because cell structure is predictable,
wood may generally be described as orthotropic. The material properties vary according
to the longitudinal, radial, and tangential axes with respect to fibre direction (Figure
15.1.2).

15.1.2 Strength Properties

Common mechanical properties are measured and represented as strength properties for
species grades in CSA O86 and are represented as parallel, at an angle to, or
perpendicular to fibre direction (grain).

The reported properties reflect test mode and the gradation, shape, and size of test
specimen. Remanufacture (ripping, resawing or dressing) of graded dimension lumber
and timber should be avoided. Remanufacture can affect the rated properties of the
member, voids the NLGA grade stamp and contractors are generally not in a position to
re-grade the pieces. Specifically desired properties or shapes may be fabricated with
engineered wood products.

15.1.3 Moisture

Wood exchanges moisture with the surrounding environment. The water content depends
on the relative humidity and temperature of air and the current amount of water in the
wood.

March 2024 Page 3 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Shrinkage occurs when the water content drops below the fibre saturation point of the
wood species. Average values for shrinkage vary for different wood species when drying
from fibre saturation to service dry conditions, but there may also be a different percentage
of moisture movement in each fibre direction for the same species (longitudinal direction
of the stem / axial), radial direction (across annular rings) and tangential direction (along
annular rings).

The ratio of tangential to radial shrinkage generally represents the uniformity of shrinkage
of a species. The volumetric shrinkage indicates the magnitude of shrinkage. Longitudinal
shrinkage is effectively zero. Shrinkage is roughly twice as fast in the end grain as the
side grain.

At equilibrium moisture content, the wood is neither gaining nor losing moisture (or
swelling or shrinking). Service dry wood (19%) is about the typical moisture content
expected of in-service open decks (16-17%) and should shrink in a linear relationship to
moisture content. Higher moisture contents exhibit a non-linear relationship.

To accommodate movement, connections need to consider orientation of wood with


respect to adjoining wood, and the in-service moisture content expected at the site.

15.2 Design

Under suitable conditions, wood will give centuries of service. Unsuitable conditions
include abiotic and biotic factors and result in degradation. Wood must be protected
during processing, merchandising and in use.

In an unprotected environment, wood is susceptible to nonliving or physical agents such


as heat, abrasion, ultraviolet light, and strong chemicals, which generally act slowly to
decrease wood strength. However, the greatest hazard to timber bridges results from
living or biotic agents such as decay fungi, bacteria, insects, and marine borers. Most
biotic agents that enter and decay wood require four basic conditions for survival:

1. Free oxygen;

2. Suitable temperature (generally a range of 10-30 degrees Celsius. Decay


effectively stops at less than 2 and greater than 38 degrees);

3. Sufficient water (a moisture level in the wood above the fibre saturation point which
varies by wood species. On average, fibre saturation may be considered 25-30%
and 28% for Canadian softwood species); and,

4. A food source.

Elimination of any one condition above can prevent wood decay, however oxygen supply
and temperature cannot reasonably be controlled in the environment of a bridge structure.
The food source may be poisoned with wood preservative treatments. Preservative
treatment is the addition of a registered product to the wood and treatments come in two
primary varieties based upon their composition. Preservative treatments can be applied
through pressure-treatment, injection and surface coatings and affects a relatively shallow

March 2024 Page 4 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

depth of wood members. Since preservative treatment could fail during the life of a
structure, it should be combined with the elimination of as much water exposure as is
practical.

Durability and longevity of outdoor treated wood articles is dramatically impacted by


exposure of bright untreated wood by machining post treatment. Durability of wood is
dependent upon limiting exposure of bright untreated wood to the elements. A durable
wood design uses treated wood, deflects water from components, provides good
drainage, and facilitates member drying.

15.2.1 Species

The availability of wood species which may be used in design is practically limited by what
is available to post-treat wood after fabrication.

15.2.1.1 Permitted Species and Species Combinations for Sawn Wood

Only individual species and species combinations specified in CHBDC Table 9.15 are
permitted for sawn wood.

TABLE 15.2.1 – TREATMENT USE CATEGORY FOR WOOD SPECIES

Species Treatable Treatment 2


Combination Species 1 UC 4.1 UC 4.2
ACQ, ACZA, CA-B, CCA, ACZA, CCA, CR, CR-S,
Douglas Fir34 CR, CR-PS. CR-S, PCP-C PCP-C
Douglas Fir-Larch
ACZA, CCA, CR, CR-PS,
Western Larch3 CR-S, PCP-C
CR, CR-S, PCP-C
Western Hemlock3
Hem-Fir ACQ, ACZA, CA-B, CCA, ACQ-C, ACQ-D, ACZA,
Amabilis Fir3
CR, CR-PS, CR-S, MCA, CA-B, CCA, CR, CR-S,
Lodgepole Pine MCQ, PCP-C MCA, PCP-C
Jack Pine
White Spruce CR, CR-PS, CR-S, PCP-C No
ACQ-C, ACQ-D, CA-B, CR,
Engelmann Spruce CR-PS, CR-S, PCP-C
No
Spruce-Pine-Fir Black Spruce No
(SPF) CR, CR-PS, CR-S, PCP-C
Red Spruce No
ACQ-C, ACQ-D, CA-B, CR,
Alpine Fir CR-PS, CR-S, PCP-C
No

Balsam Fir CR, CR-PS, CR-S, PCP-C No

1 Bold species are specifically identified in CSA S6-19, Table 9.15 as treatable species for sawn wood.
Western Hemlock and Lodgepole Pine may be treated with some difficulty.
2 CSA O80 Series Sawn Product treatment options for the Use Category specified in OPSS 1601.
3 Coastal species are identified separately under NLGA Grading Rules but are not a separate species
combination for strength properties according to CSA O86. The differences between interior and coastal
species affect the ability to treat wood with preservative.
4 Preferred wood species for structural characteristics but interior species are difficult to treat. Consider
interior not treatable and only specify coastal Douglas Fir.

March 2024 Page 5 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Ponderosa Pine ACQ, ACZA, CA-B, CCA, ACQ-C, ACQ-D, ACZA,


CR, CR-PS, CR-S, MCA, CA-B, CCA, CR, CR-S,
Red Pine MCQ, PCP-C MCA, PCP-C
Western Red
No No
Cedar
White Cedar No No
Yellow Cedar No No
Northern Species
Grand Fir ACQ, ACZA, CA-B, CCA, ACQ-C, ACQ-D, ACZA,
Eastern Hemlock CR, CR-PS, CR-S, MCA, CA-B, CCA, CR, CR-S,
Eastern White Pine MCQ, PCP-C MCA, PCP-C
ACQ, CA-B, CR, CR-PS, ACQ-C, ACQ-D, ACZA,
Western White Pine CR-S, MCA, MCQ, PCP-C CA-B, CCA, MCA
Western White ACQ-C, ACQ-D, CA-B, CR,
No
Spruce CR-PS, CR-S, PCP-C

15.2.1.2 Permitted Species and Species Combinations for Glulam

Glulam is primarily produced in Canada as D.Fir-L or Spruce-Pine. Hem-Fir GLT may be


available in certain areas and local fabricators should be consulted for product availability.

The post-gluing treatment options with oil-based preservatives limits availability of GLT
products to Coastal Douglas Fir and Western Hemlock (Section 15.2.3.1 and Table
15.2.2).

15.2.2 Dimensions

Structural members can generally be fabricated to any size or shape. However, treatment
with preservatives practically limits members to that which can be handled and will fit in
the pressure treatment vessel, which varies by treatment plant. Weight of the treated
member may be a limiting factor for some treatment plants.

To be generally treatable, individual members should be:


• Less than 12m in length;
• Up to 1m in depth;
• Less than 8000 kg.

The designer shall contact treatment plants for treatment ability for all curved shapes or
when the dimensions or weight above are exceeded. (Note: the largest known member
dimensions which may be treated in Ontario are 15m length and ~1.5m depth).

15.2.2.1 Sawn Timber

There are many different nominal and actual dimensions of sawn timber depending on the
machining processes and moisture conditions. To avoid any ambiguity, all contract
drawing dimensions shall be actual dimensions, in millimetres (e.g., 191x191), and
standard sizes for sawn lumber or sawn timber.

Sawn timber shall not be specified as dressed.

March 2024 Page 6 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Sawn timber is generally available up to 4.85 m length in sections up to 241 x 241 mm.
For any CSA O86 sizes above these dimensions, the timber may be a special order and
the designer should first contact a mill or consider glulam. Custom sizes not listed in CSA
O86 should not be used.

15.2.2.2 Glulam

Beams are typically fabricated in standard finished widths of 80, 130, 175, 215, 265, 315
and 365 mm, corresponding with CSA O86 selection tables. Additional widths up to 515
mm are available according to CSA O122 but members wider than 365 mm are by special
order.

Glulam member depth shall be specified in 38 mm increments. Glulam member depth


may be specified in 19 mm increments for curved elements when permitted in CSA O86.

15.2.3 Pressure Preservative Treatment for Wood

All wood shall be pressure treated with preservatives according to CSA O80 Series and
the accompanying American Wood Protection Association (AWPA) preservation
standards in OPSS 1601.

Preservatives in CSA O80 are current at the time of publication and are subject to the
product label. The AWPA specification U1 is updated annually and may have more up-
to-date preservative treatments available than CSA O80. However, the production and
use of wood preservatives in Canada is regulated by the Pest Management Regulatory
Agency (PMRA) under the Pest Control Products Act (PCPA). Specific preservatives
listed in CSA O80 or AWPA U1 may be restricted or may not be available during design.
The designer shall check with preservative treatment suppliers about product availability
before specifying treatments in the contract documents.

Inorganic Boron (SBX), also known as Disodium Octoborate Tetrahydrate (DOT) requires
dual treatment where the SBX treated product is treated separately with an oil-borne
preservative (typically Creosote). The oil-borne treatment is required to seal in the SBX
which depletes and vapourizes when the moisture content exceeds about 22%.

Elements shall be specified in the drawing notes under the use category system. Each
element shall identify the wood species and size, use category, and type of preservative
(see Section 15.4).

15.2.3.1 Preservative Treatment of Glulam

Glulam shall be treated with an oil-based preservative (Table 15.2.2). The glulam
laminations are individually kiln-dried and are effectively sealed during gluing to a service-
dry moisture content. Adequately protected glulam can generally be considered to be in
service-dry condition. Incising and treatment with water-born preservatives increases the
moisture content of the product to a wet condition and may distort element dimensions
and any machined details, impacting fit-up.

March 2024 Page 7 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

TABLE 15.2.2 – GLT POST-GLUING PRESERVATIVE TREATMENTS

Treatment
Treatable Species Stamp Identification
UC 4.1 UC 4.2
Coastal Douglas Fir D FIR(N) CR, CR-PS, PCP-A, CR, CR-PS, PCP-
Western Hemlock W Hem(N) PCP-C A, PCP-C

There is currently an issue with procuring oil-based preservative treated glulam:

• The sole North American supplier of Pentachlorophenol (PCP) shut down production
in December 2021 and the PRMA product registration has ended, effectively banning
the use of PCP to treat any new products.

• There are three Creosote preservative treatment plants in Canada, limiting availability.
Wood may also be creosote treated in the USA.

• Creosote Petroleum Solution is not available in Canada. Wood may be treated in the
USA.

• Copper Naphthenate (CuN) in hydrocarbon solvent is currently specified to UC 4.1


only. The CuN supplier has submitted information to the CSA O80 technical
committee for review and may become a future alternative.

• 4,5-Dichloro-2n-Octyl-4-Isothiazolin-3-One (DCOI) is under review by PMRA as a


potential future alternative to PCP.

15.2.3.2 Component Treatment Use Category Designation

Components shall be specified to the Use Category in Table 15.2.3.

TABLE 15.2.3 – WOOD COMPONENT USE CATEGORY

Component CSA O80 Use Category


Foundation elements UC-4.2
Structure elements (except barrier) UC-4.2
Structure barrier UC-4.1
Guide Rail Posts UC-4.1
Guide Rail Blocks UC-4.1
Ground Mounted Sign Posts UC-4.1
Fence Posts UC-4.1

15.2.3.3 Fire Retardant Treated Wood

Pressure preservative treated processes are available in CSA O80 Series for fire-
retardant-treated lumber, timber, and plywood. It is not expected that fire retardance of
wood through chemical treatment will be required because:

• The occurrence of fires near or under bridges is relatively rare; and,

March 2024 Page 8 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

• Bridge members are generally large timbers that will have an inherent fire resistance
because of the slow burning rate of large timbers and the insulating effects of the char
layer.

Information about calculating fire resistance of wood members and assemblies may be
found in American Wood Council Technical Report No. 10.

15.2.4 Decks

Decks on wood girders shall be glulam unless approved by the Head of Structural Section.

Wood-concrete composite decks shall not be used unless approved by the Head of
Structural Section. MTO performance experience with wood-concrete decks has varied
but poorly performing ones all experience rot at the wood/concrete interface and can only
be ‘repaired’ by deck replacement. The detail in Figure 9.4 of CSA S6-19 shall not be
used; it contains angled shear key reinforcing nails installed top down at the
wood/concrete interface facilitating water penetration deeper into the wood laminates.

15.2.5 Traffic Barrier and Railing

TL-4 barrier crash tested to NCHRP Report 350 may be designed. References for design
of this timber TL-4 barrier are:

Faller, R. K., Ritter, M. A., Rosson, B. T., Fowler, M. D., & Duwadi, S. R. (2000, April 3-5).
Two Test Level 4 Bridge Railing and Transition Systems for Transverse Timber
Deck Bridges. Transportation Research Record, 1(1696), 19.

Duren, J. T., Yosef, T. Y., Rosenbaugh, S. K., Faller, R. K., Bielenberg, R. W., & Steelman,
J. S. (2023). Crash-Tested Bridge Railings and Transitions for Wood Bridges –
Phase IIA. Forest Products Laboratory. U.S. Department of Agriculture.

15.3 Fabrication

All structural components shall be designed to be prefabricated and post-treated with


preservatives. Machining and fastening post-treatment into bright wood is a significant
contributor to deterioration of wood bridges and reduces service life below a 75-year
target.

15.3.1 Shop Trial Assembly

The designer shall specify in the contract documents, girders and other main components
requiring shop trial assemblies before and, if required, after preservative treatment.

A typical single span simply supported girder bridge may not require a shop trial assembly
of fabricated elements prior to preservative treatment. However, wood bridges are not
regularly constructed on MTO highways so pre-assembly should be considered for all
glulam and dowel laminated (DLT) structures until there is general familiarity with them in
design and construction.

March 2024 Page 9 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Oil-based preservative treatments are more dimensionally stable and will typically not
need a second trial assembly after preservative treatment.

15.3.2 Details

15.3.2.1 Changes in Cross Section

Always provide taper cuts at notches to reduce abrupt differential stiffness change. Taper
cuts shall be slope cut not less than 1:12 to a maximum length of 300 mm or a maximum
depth of D/4, where D is the depth of the member being cut. Taper cuts in glulam shall
not be permitted in compression zones of the member.

Notches or abrupt changes in cross section introduce stress raisers which can promote
cracking to bright wood. Notches and abrupt changes in cross section shall not be
permitted unless a detailed assessment of the stress concentration effect has been made.
Notches on the tension side shall also be verified for fracture shear resistance at the notch
in accordance with CSA O86.

15.3.2.2 Accommodating Shrinkage and Expansion

Before fabrication of connector joints, members should be seasoned to a moisture content


corresponding as nearly as practical to that which they will attain in service. The moisture
content shall be indicated on the contract drawings.

15.3.2.3 Connections

The designer shall design all connections.

Connections of members and steel plates connecting members with their grain
perpendicular to each other shall be provided with slotted holes.

Connections should consider shrinkage and swelling, notching effects, decay prevention
and lateral restraint at supports. Examples of unacceptable connections that promote
cracking, and preferred alternatives, are provided in CSA O86 and American Institute of
Timber Construction (AITC) 104-2003, Typical Construction Details.

All holes should be pre-bored during fabrication so that they are effectively protected by
post-treatment with preservatives. Through holes shall be horizontal. Fastener and hole
information may be found in OPSS 907.

Vertical fasteners installed top down in structural elements or that penetrate or expose
bright wood shall not be permitted. Figure 15.3.1 shows an example of bottom-up deck
fastening that accommodates shrinkage. All through vertical fasteners should be avoided,
but where used shall be in pre-machined, treated holes.

Flat washers shall be installed between the timber surface and the nuts of bolts, or
between the timber surface and spring washers where spring washers are used.

Gauge lines for horizontal nailing shall be provided.

March 2024 Page 10 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Installation torque of lag screws shall be based on the specific fastener, diameter and
depth, and wood species specific gravity.

FIGURE 15.3.1 – GLULAM DECK FASTENING

Fasteners shall be the same material as the piece they are connecting and compatible
with the preservative treatment used. E.g., copper nails with copper flashing; stainless
steel nails with stainless steel flashing. Stainless steel type 304 or type 316 shall be used
when fasteners are driven into wood treated with ACQ, CA, CCA or MCA.

Electrolytic corrosion is most often considered where dissimilar metals are in direct
contact. However, the metals do not need to be in direct contact, they only need to be
electrically connected. While wood is generally a good electrical insulator, under certain
conditions wet wood may form an electrical connection between two dissimilar fasteners,
leading to an anode/cathode relationship. If the fasteners are embedded, acidic and basic
chemicals may accumulate at the node and cathode respectively. These chemicals may
degrade the wood surrounding the fasteners. Fasteners should be the same material as
embedded materials nearby.

15.3.3 Appearance

Appearance grade of glulam shall be industrial. Commercial grade glulam may be


considered for elements within 5 m of a pedestrian’s view and shall be clearly identified
on the contract drawings when used.

Note: CWC appearance grade designations are different from APA classifications. If
suppliers from the United States are anticipated because of species/treatment/size
requirements, the appearance grade should be industrial or framing. Architectural grade
may be considered for elements exposed to view.

15.3.4 Coatings

Wood with a minimum nominal dimension greater than 51 mm shall not be painted.
Coatings shall not contain more than 29% solids. Stains are preferred to paint.

March 2024 Page 11 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Coatings with greater than 29% solids have been historically used to protect rail elements
with added benefit of visual appeal. These high-solid paints tend to crack over time as
the wood expands and contracts, allowing moisture to infiltrate the member. The moisture
becomes trapped under the paint causing areas of high moisture content, and often
causing the paint to delaminate from the member. Thus, high solids coatings can often
promote rather than prevent decay.

15.4 Wood Notes

The following are standard notes of the type shown below the title block on the appropriate
drawing. The notes must be worded to cover the requirements specific to the particular
project and should only be used if applicable. Other notes may be required in special
circumstances.

For clarity the wording of the notes is shown in upper case (CAPITAL) lettering.
Explanations shown in brackets in lower case lettering are not part of the notes.

A. General Notes

1. ALL WOOD SHALL CONFORM TO CSA O86.

2. ALL SAWN LUMBER AND TIMBER SHALL CONFORM TO CSA O141. SAWN
LUMBER AND TIMBER SHALL CONFORM TO THE NLGA “STANDARD
GRADING RULES FOR CANADIAN LUMBER”.

3. If the bridge uses glued-laminated timber, the following note shall be added:

ALL GLUED-LAMINATED TIMBER (GLT OR GLULAM) SHALL CONFORM TO


CSA O122. GLUED-LAMINATED TIMBERS SHALL BE INDUSTRIAL
APPEARANCE GRADE UNLESS INDICATED OTHERWISE ON THE CONTRACT
DRAWINGS.

4. If the bridge uses mechanically laminated timber, the following note shall be added:

ALL MECHANICALLY LAMINATED TIMBER (MLT) SHALL BE DOWEL


LAMINATED TIMBER (DLT) AND SHALL CONFORM TO CSA O125.

5. MOISTURE CONTENT (BY WEIGHT) OF LUMBER AND TIMBER SHALL NOT


EXCEED 19% AND GLULAM SHALL NOT EXCEED 15% AT THE TIME OF
INSTALLATION. ALL WOOD SHALL BE ADEQUATELY PROTECTED DURING
ALL STAGES OF CONSTRUCTION TO ENSURE MOISTURE CONTENT
REMAINS BELOW THE SPECIFIED LIMIT.

(This note is about the maximum moisture content permissible of the wood product,
this does not represent the expected moisture content of the site.)

6. NO CHAINS, HOOKS OR PEAVIES SHALL BE USED IN HANDLING TREATED


WOOD.

March 2024 Page 12 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

7. FIELD DRILLING OR CUTTING NOT SHOWN IN THE CONTRACT DRAWINGS


SHALL NOT BE PERMITTED. FIELD MODIFICATIONS SHALL NOT BE
PERMITTED WITHOUT PRIOR APPROVAL FROM THE OWNER.

(Field drilling and cutting into bright wood is a significant contributor to deterioration
of a wood structure. If field drilling and cutting cannot be avoided, notes 8 and 9
shall always be included with note 7.)

8. ALL FIELD-DRILLED HOLES SHALL BE TREATED TO REFUSAL/SATURATION


WITH COPPER NAPHTHENATE PRESERVATIVE ACCORDING TO OPSS 1601.
TREAT HOLES AS SOON AS POSSIBLE AFTER DRILLING. ENSURE HOLES
ARE CLEAN AND FREE OF SAWDUST OR DEBRIS PRIOR TO TREATING.

9. FIELD-CUT SURFACES SHALL BE TREATED TO REFUSAL/SATURATION WITH


COPPER NAPHTHENATE PRESERVATIVE ACCORDING TO OPSS 1601. END
GRAIN SHALL BE COATED WITH ANCHORSEAL® PARAFFIN SEALANT.
TREAT BEAMS AS SOON AS POSSIBLE AFTER CUTTING. ENSURE CUTS ARE
CLEAN AND FREE OF SAWDUST OR DEBRIS PRIOR TO TREATING.

10. If the bridge uses prefabricated deck panels, the following note shall be added:

DECK PANELS MAY SHRINK OR EXPAND AFTER FABRICATION. DURING


INSTALLATION, PERIODICALLY CHECK THE CUMULATIVE DISTANCE FROM
THE END AND ADJUST GAP SIZE AS NEEDED. ORIENT ANY PANEL
CURVATURE IN THE SAME DIRECTION TO MINIMIZE GAPS.

B. Connection Notes

1. ALL STEEL CONNECTION HARDWARE SHALL BE HOT DIP GALVANIZED


ACCORDING TO ASTM A123. CONNECTOR PLATES SHALL BE FASTENED
ACCORDING TO THE MANUFACTURER’S RECOMMENDATIONS TO DEVELOP
THE FULL CAPACITY OF THE CONNECTOR.

(Fasteners used with hot-dip galvanized plates shall also be hot-dip galvanized. If
connector plates are stainless steel, fasteners shall also be stainless steel and the
note above shall be modified.)

2. NO CHECKING OR SPLITTING SHALL BE PERMITTED AT AREAS TO BE


BOLTED OR LAGGED.

3. A STANDARD FLAT WASHER SHALL BE PROVIDED WHERE A BOLT OR LAG


SCREW HEAD OR NUT BEARS DIRECTLY ON WOOD. WASHERS SHALL BE
HOT DIP GALVANIZED ACCORDING TO ASTM A123, OR STAINLESS STEEL
ALLOY 304 OR 316 ACCORDING TO ASTM F594.

4. BOLT HOLES SHALL BE ACCURATELY ALIGNED AND DRILLED 1-2mm


LARGER THAN THE BOLT DIAMETER. OVERSIZED HOLES SHALL NOT BE
PERMITTED UNLESS INDICATED ON THE CONTRACT DRAWINGS.

March 2024 Page 13 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

5. If the bridge uses bolted connections, the following note shall be added:

BOLTS FOR TIMBER CONNECTIONS SHALL BE TIGHTENED ONLY TO A


SNUG-TIGHT FIT. LOCK WASHERS SHOULD BE FLATTENED AND THE NUT
SHALL BE TURNED AN ADDITIONAL ¼ TO ½ TURN.

WOOD SHALL NOT BE DEFORMED UNDER WASHERS OR STEEL PLATES


DUE TO OVERTIGHTENING. UNLESS SPECIFIED OTHERWISE IN THE
CONTRACT DOCUMENTS, BOLTED CONNECTIONS SHALL HAVE A MAXIMUM
TORQUE OF 40 N-m.

AFTER BOLTS ARE TIGHTENED, BURR OR EPOXY 3-5 THREADS ON THE


CLEAN END OF THREADS. THE MINIMUM NUMBER OF CLEAR THREADS
PAST THE NUT SHALL BE 3.

6. If the bridge uses lag screw connections, the following note as well as note 7 and 8
below shall be added:

DRILL A PILOT HOLE TO A DEPTH EQUAL TO THE DISTANCE FROM THE


INSIDE OF THE LAG SCREW HEAD TO THE SHOULDER OF THREADS (DOES
NOT INCLUDE THE TIP).

FOR REDUCED-BODY DIAMETER LAG SCREWS, THE DIAMETER OF PILOT


HOLE ACCOMMODATING THE THREADED PORTION OF THE LAG SCREW
(E.G. PARENT WOOD SEGMENT) SHALL BE 90% OF SHANK DIAMETER IN
HARDWOODS OR 65% OF SHANK DIAMETER IN SOFTWOODS. THE
DIAMETER OF PILOT HOLE NOT ACCOMMODATING THE THREADED
PORTION (E.G. LAG SEGMENT) SHALL BE OVERSIZED BY 1.6mm OVER THE
SHANK DIAMETER.

FOR FULL DIAMETER LAG SCREWS, THE DIAMETER OF PILOT HOLE


ACCOMMODATING THE THREADED PORTION OF THE LAG SCREW SHALL BE
90% OF THREAD OUTER DIAMETER IN HARDWOODS OR 65% OF THREAD
OUTER DIAMETER IN SOFTWOODS. THE DIAMETER OF PILOT HOLE NOT
ACCOMMODATING THE THREADED PORTION SHALL BE OVERSIZED BY
1.6mm OVER THE THREAD OUTER DIAMETER.

7. SUITABILITY OF PILOT HOLE DIAMETER FOR LAG SCREWS SHALL BE


CONFIRMED ON SITE WITH A TRIAL HOLE. INSTALLATION SHALL NOT
RESULT IN CLEAVING.

8. LAG SCREWS SHALL BE INSTALLED BY TURNING WITH A WRENCH. DRIVING


WITH A HAMMER SHALL NOT BE PERMITTED. PETROLEUM-BASED
LUBRICANT SHALL BE USED TO FACILITATE INSERTION OF LAG SCERWS.
POWER-ASSISTED WRENCHES MAY BE USED FOR PRIMARY INSERTION OF
THE LAG SCREW, OR IF A CALIBRATED WRENCH IS SET TO THE TORQUE
VALUE SPECIFIED IN THE CONTRACT DOCUMENTS.

March 2024 Page 14 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

FINAL TORQUING OF LAG SCREWS SHALL BE TO … N-m, COMPLETED WITH


A TORQUE WRENCH OR SUITABLE TORQUE MEASURING DEVICE.

(Torque level is to be based on thread diameter, pitch, length, and species of wood.
Insert the required torque value for each fastener specified).

9. WHEN USING NAIL GUNS, INCREASE THE NAIL SIZE TO ACHIEVE THE
REQUIRED DIAMETER.

C. Wood Preservatives Notes

1. ALL STRUCTURAL WOOD ELEMENTS SHALL BE PRESSURE TREATED WITH


PRESERVATIVES ACCORDING TO OPSS 1601 AND CSA O80 SERIES TO THE
USE CATEGORY SPECIFIED IN OPSS 1601.

(If elements will be incised, modify the note as below)

ALL STRUCTURAL WOOD ELEMENTS SHALL BE INCISED AND PRESSURE


TREATED WITH PRESERVATIVES ACCORDING TO OPSS 1601 AND CSA O80
SERIES TO THE USE CATEGORY SPECIFIED IN OPSS 1601.

(If elements will be treated with products anticipated to only be available in the United
States, include references to AWPA standards, e.g.)

STRUCTURAL WOOD ELEMENTS PRESSURE TREATED WITH CREOSOTE


SHALL BE TREATED IN ACCORDANCE WITH CSA O80 OR AWPA U1 AND
AWPA T1 TO USE CATEGORY UC4.2 OR UC4B.

2. ALL MACHINING (E.G., CUTTING AND DRILLING) SHALL BE COMPLETED


PRIOR TO PRESERVATIVE TREATMENT.

3. WOOD COMPONENTS SHALL BE:

(List the unique wood components and specify their parameters. E.g., component,
element size, timber species, Use Category and treatment preservative)

DECKING – 38x140, LPP (LODGEPOLE PINE), UC4.2, PCP-C


GIRDERS – 315x1712 GLT, D FIR (COASTAL DOUGLAS FIR), UC4.2, PCP-C
POSTS – 140x140, RED PINE, UC4.1, CA-B

15.5 Maintenance Schedule

The designer shall prepare and submit a maintenance schedule that identifies:
• Required periodic maintenance;
• Inspection requirements;
• Component replacement.

March 2024 Page 15 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Required periodic maintenance may include, but is not limited to the following:
• Time of first maintenance of galvanized components;
• Fastener tightening intervals. There should be at least one interval during the time
units are coming to moisture equilibrium (normally during the first 2-3 years of
service life);
• Post-tensioning re-tightening intervals;
• Cleaning moisture-trapping dirt and debris;
• Component replacement.

15.6 Sources of Information

15.6.1 Extra Design Information

Extra design information may be found in the AASHTO LRFDBDS-9, LRFD Bridge Design
Specifications, 9th Edition and the American Wood Council ANSI/AWC National Design
Specification for Wood Construction.

15.6.2 Historical MTO Research References

The ministry directed its continuous bridge testing program towards wood structures in
1973 and produced research publications about wood structures until 1992. References
are provided for convenience below.

Bakht, B. 1986. Testing of Two Pin-Connected Truss Bridges. Report, Structures


Research Office, Ontario Ministry of Transportation, Downsview: Queen's Printer
for Ontario, 53.
Csagoly, P F, and R J Taylor. 1979. A Development Program for Wood Highway Bridges.
1979 RTAC Annual Conference, Structures Research Office, Ministry of
Transportation and Communications, Queen's Printer for Ontario, 65.
Csagoly, P F, and R J Taylor. 1986. A Structural Wood System for Highway Bridges.
Paper, Structures Research Office, Ontario Ministry of Transportation, Downsview:
Queen's Printer for Ontario, 31.
Doyle-Forintek, E, W Mortimer, H Walthert, R J Taylor, and J Wear. 1992. Pressure
Treated Wood in Canada: Task Force Report. Jurisdictional Review, Research and
Development Branch, Ontario Ministry of Transportation, Downsview: Queen's
Printer for Ontario, 125.
Jaeger, L G, and B Bakht. 1986. Analysis of Failure Loads of Timber Bridges. Paper,
Structures Research Office, Ontario Ministry of Transportation, Downsview:
Queen's Printer for Ontario, 48.
Jaeger, L G, and Baidar Bakht. 1985. Probabilistic Assessment of The Failure of Timber
Bridges. Presentation for 65th Annual Meeting of Transportation Research Board,
Research and Development Branch, Ministry of Transportation and
Communications, Downsview: Queen's Printer for Ontario, 21.
Maghsoudi, Akbar, and Baidar Bakht. 1982. Simulation of Timber Bridges for Statistical
Analysis. Paper, Research Development Branch, Ministry of Transportation and
Communications, Downsview: Queen's Printer for Ontario, 60.
Taylor, R J. 1987. Applications in Prestressed Wood. Report, Research and Development
Branch, Ontario Ministry of Transportation, Downsview: Queen's Printer for
Ontario, 29.

March 2024 Page 16 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 15 - WOOD STRUCTURES

Taylor, R J. 1983. Design of Prestressed Wood Bridges Using the Ontario Highway Bridge
Design Code. Guide, Structures Research Office, Ministry of Transportation and
Communications, Downsview: Queen's Printer for Ontario, 27.
Taylor, R J. 1984. Design of Prestressed Wood Bridges Using the Ontario Highway Bridge
Design Code. Guide, Structures Research Office, Ontario Ministry of
Transportation, Downsview: Queen's Printer for Ontario, 35.
Taylor, R J. 1983. Design of Wood Bridges Using the Ontario Highway Bridge Design
Code. Paper, Structures Research Office, Ontario Ministry of Transportation,
Downsview: Queen's Printer for Ontario, 30.
Taylor, R J. 1983. Draft of OHBDC Section 13, Wood, Code and Commentary. Appendix
to SRR-83-02, Structures Research Office, Ontario Ministry of Transportation,
Downsview: Queen's Printer for Ontario, 123.
Taylor, R J. 1991. Testing & Analysis of Short Span Wood Decks. Paper, Structures
Research Office, Ontario Ministry of Transportation, Downsview: Queen's Printer
for Ontario, 60.
Taylor, R J. 1984. Wood Bridge Calibration Study for the OHBDC. Paper, Research and
Development Branch, Ministry of Transportation and Communications,
Downsview: Queen's Printer for Ontario, 44.
Taylor, R J, and H Walsh. 1983. A Prototype Prestressed Wood Bridge. Paper, Structures
Research Office, Ontario Ministry of Transportation, Downsview: Queen's Printer
for Ontario, 85.
Taylor, R J, and N Patel. 1986. Load Testing and Analysis of Wood Bridges Rehabilitated
by Transverse Post-Tensioning. Paper, Structures Research Office, Ontario
Ministry of Transportation, Downsview: Queen's Printer for Ontario, 37.
Taylor, R J, B deV Batchelor, and K van Dalen. 1983. Prestressed Wood Bridges. Paper,
Structures Research Office, Ontario Ministry of Transportation, Downsview:
Queen's Printer for Ontario, 23.
Tharmabala, T, and B Bakht. 1986. Steel-Wood Composite Bridges. Paper, Structures
Research Office, Ontario Ministry of Transportation, Downsview: Queen's Printer
for Ontario, 108.

15.6.3 Other Information

Other publications which have not been referenced above and may be informative, but
shall not be taken as authoritative for the purposes of design of wood for MTO contracts
may be found from the following sources:
• Ontario Wood Bridge Reference Guide (2017);
• The Canadian Wood Council;
• WoodWorks;
• The Engineered Wood Association;
• The American Wood Protection Association;
• The American Institute of Timber Construction;
• USDA Forest Products Laboratory.

March 2024 Page 17 of 17 SM-D2-S15


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

Table of Contents

16 MISCELLANEOUS ............................................................................................... 2
16.1 Utilities ......................................................................................................................... 2
16.1.1 Services Carried Through or Under Bridges ......................................................... 2
16.1.2 Electrical Grounding of Structures......................................................................... 5
16.2 Transportation and Fabricator Handling of Structural Components .............................. 5
16.3 Modular Bridges ........................................................................................................... 6
16.3.1 Temporary Modular Bridge (TMB)......................................................................... 6
16.3.2 MTO's TMB Policy for Municipalities and other Agencies ...................................... 6
16.3.3 Policy for Issuing Priorities of TMBs ...................................................................... 7
16.3.4 Emergency Needs Policy for TMB’s ...................................................................... 7
16.3.5 Policy for Detours and Non-Emergency Needs ..................................................... 8
16.3.6 Use of Bailey Bridges as TMB .............................................................................. 8
16.4 High Mast Lighting Poles.............................................................................................. 8
16.4.1 Design of High Mast Lighting Pole ........................................................................ 8
16.4.2 Foundations of High Mast Lighting Pole ................................................................ 9
16.5 Pedestrian, Bicycle and MUP Bridges .........................................................................10
16.5.1 Loads ...................................................................................................................10
16.6 Ethylene Vinyl Acetate (EVA) Foam ............................................................................10
16.6.1 Overview..............................................................................................................10
16.6.2 Material Properties and Classifications ................................................................10
16.6.3 MTO’s Best Practices and Preferences................................................................11
16.6.4 Design Considerations for EVA Foam in MTO’s Projects .....................................12
16.6.5 Presentation of EVA Foam on Contract Drawings ................................................13

March 2024 Page 1 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

16 MISCELLANEOUS

16.1 Utilities

16.1.1 Services Carried Through or Under Bridges

Fluid carrying pipelines are not normally allowed to be carried through or under bridges,
unless approved. This includes oil and gas pipelines, sanitary and storm sewers, and
water mains.

Electrical power lines may be carried through, under, or over bridges provided the voltage
does not exceed 44,000 volts.

The following details show approved details for the accommodation of non MTO utilities
on bridges. Bridges shall be used for this purpose only as a last resort and after the
proponent has carried out a cost benefit analysis. Schemes other than those shown below
may be considered, subject to the approval of MTO.

Utility plant is not allowed in sidewalks or to be directly suspended from thin deck slabs.
Also, utility hardware must not be placed in a location which prohibits routine inspection
of structural components. In any case, it must not be located below the underside of
girders for slab on girder bridges, or the underside of deck for slab type bridges.

Steel components that make up the duct support system for bridges having an all-concrete
superstructure or for bridges having painted steel girders, must be stainless steel,
galvanised, metallised, or painted. For bridges having ACR steel girders, all non-
embedded components may be fabricated of the same steel. Attachments shall not be
welded to flanges of superstructure girders.

Where necessary, the designer must also provide special details to allow the utility ducts
to pass through the abutment ballast walls and superstructure diaphragms. These details
must ensure:

1. That the ducts will be able to accommodate all prescribed structure movements
including deck jacking for bearing repairs;

2. That fill material behind the ballast walls is not washed out; and,

3. Any settlement that may occur in the fill material behind the ballast wall does not
impose undue stresses on the ducts. When the utilities are run through a steel
box girder, the designer must consider the location of intermediate cross braces,
vertical stiffeners in pier diaphragms, access openings in pier diaphragms, etc. All
utilities shall be designed with provisions to allow for future bridge maintenance.

Examples of how ducts could be accommodated through or carried by a structure may


include the following cases:

March 2024 Page 2 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

A. Duct location for structures with accessible cavities or spaces located within
the limits of the of the superstructure.

FIGURE 16.1.1 – SLAB ON CONCRETE/STEEL I TYPE GIRDERS

FIGURE 16.1.2 – SLAB ON CONCRETE/STEEL BOX GIRDERS

FIGURE 16.1.3 – TWINNED ROUND VOIDED POST TENSIONED DECKS

March 2024 Page 3 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

FIGURE16.1.1(D) POST TENSIONED DECKS WITH TRAPEZOIDAL VOIDS

B. Duct location in slab type structures, (superstructures without accessible


cavities).

Projects covered by this criterion require the construction of a non-structural utility corridor
outside of and adjacent to the barrier wall. Structure types included in this category include
rigid frames, culverts, and solid or round voided post tensioned concrete structures. This
scheme is best suited for structures without sidewalks or situated in non-urban locations
because of the possibility of pedestrians climbing up onto the utility corridor.

FIGURE 16.1.4 – CANTILEVERED UTILITY CORRIDOR

Electrical lighting ducts (including MTO utilities) shall not exceed 50 mm diameter, except
when installed in barrier walls, and shall be placed in accordance with the following criteria:

1. In abutments, ballast walls, slab piers and rigid frames, members must be greater than
500 mm in thickness and spacing of adjacent ducts shall be not less than 6 m.

2. In round columns:
• Maximum of one electrical duct, outside diameter not exceeding 50 mm, may be
placed at centre of columns having a diameter of 1000 mm or more.

March 2024 Page 4 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

• Junction boxes are not permitted in columns.


• Entrance/exit of duct at the bottom of columns to be through the footing.
• Entrance/exit of duct at the top of columns:
- for fixed-fixed columns (no bearings at top) the duct shall pass straight through
the deck column interface.
- for columns with bearings at top, duct may pass through side of column,
provided it does not interfere with reinforcement or bearing assembly and is
kept clear of the zone of high stress near the bearings.

3. In post tensioned decks:


• Ducts and junction boxes may be placed in post tensioned decks provided they
are located in solid portions of the deck adjacent to supports; they must be placed
above the bottom mat of reinforcement (and transverse post tensioning, when
present).
• Longitudinal ducts placed in post tensioned decks may be located inside deck
voids, but in any case, shall not be located in web portions of the deck.

When ducts are to be placed in such elements, positive drainage of the embedded duct
work must be assured, and the ducts must be located behind the steel reinforcement. The
structural Engineer shall also give consideration to the location of junction boxes
necessary in such installations and to the potential effects of duct bursting on the structural
integrity of the component(s). Electrical ducts left unused would need to be grouted as is
required with unused post tensioning ducts.

Other services may be provided for only as a result of specific approvals and agreements.
These, and approval for exemption from above restrictions, should be referred to the
Assistant Deputy Minister of Operations.

16.1.2 Electrical Grounding of Structures

Railings attached to a structure must be electrically grounded if the structure carries


electrical power conductors or provision for them. The Electrical Engineering Section
details the grounding.

Bridges having lighting ducts require grounding but those carrying only telephone ducts
or cables do not.

High level bridges may require lightning protection. Such structures should be referred to
the Traffic Management and Engineering Office, Electrical Engineering Section.

16.2 Transportation and Fabricator Handling of Structural Components

Prefabricated, indivisible structural components that exceed (including the vehicle) any of
the following limitations of:

Length ........................................ 19.0 m


Width .......................................... 3.5 m
Height ......................................... 2.6 m

March 2024 Page 5 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

Weight ........................................ 30,000 kg

shall require special oversize/overweight hauling permit(s) in order to be transported by


highway carrier over King’s highways.

For the following two categories: (A) Routine oversize/overweight loads, and (B) Non
routine oversize/overweight loads, pre-approval for King’s highways transportation is not
required. The length/width/height/weight limitations for both categories are detailed in
SSP No. 109F16, to which reference should be made.

Components exceeding the limitations of categories (A) or (B) require that the designer of
the load obtain transportation approvals from the Weight and Load Engineer, Carrier
safety and Enforcement Branch, MTO and other authorities, all as required by SSP
No. 109F16.
As early as possible in the design stage, written request for road transportation shall be
submitted to the Oversize / Overweight Permits Office for an in principle special permit
approval. The request shall indicate the number of components, dimensions, weights,
travel origin and destination, duration of transportation and required travel frequency. The
transportation approvals may take up to four (4) weeks and may not be granted if
transportation is deemed to be unsafe.

16.3 Modular Bridges

16.3.1 Temporary Modular Bridge (TMB)

The use of temporary modular bridge (TMB) (such as Acrow, Bailey, Mabey, AIL, etc.) is
primarily for installations as detours during new bridge construction or for emergency
situations with existing bridges. The use of a TMB as a permanent structure shall be
subject to the following:
• Consideration of the volume of traffic at the bridge site Fatigue design as per the
CHBDC; and,
• The required traffic barrier crash test level (e.g., TL-3, TL-4, etc.).

The responsibility and control of the supply, maintenance, and inventory of all TMB
components under the jurisdiction and ownership of MTO is governed by the following
Policy, Planning & Standards Directive PHM-B-22:

“Temporary Modular Bridges”: (A) Issuing Priorities


(B) Supply, Maintenance and Inventory Control
(C) Retrieval, Rental and Disposal

A summary of the contents of this document is given in this subsection.

16.3.2 MTO's TMB Policy for Municipalities and other Agencies

The Ministry will only supply TMB to municipalities when there is a real emergency. The
Ministry will not supply TMB to municipalities for detour purposes when new bridges are
being constructed or for bridge rehabilitations.

March 2024 Page 6 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

Municipalities that need TMB components in an emergency shall initially attempt to obtain
their requirements from the private sector. If the private sector is unable to supply the
components within one week from the date of the emergency, the municipality may
request them from the Ministry. When submitting a request to the Ministry, the municipality
must provide evidence that they were unable to obtain the TMB components in a timely
manner. The procedure to follow when making an emergency request and details of a
legal TMB rental/purchase agreement that must be entered into is given in Directive
PLNG–B-007.

The Ministry will not supply TMB to any other jurisdictions.

16.3.3 Policy for Issuing Priorities of TMBs

The Regional Director for the region in which the TMB is required is responsible for
approving the release of TMB. The Manager of Operations, Northern Region, North Bay
is responsible for issuing TMB. Issuing priorities will be in the following order of
precedence:

1. Emergency needs on the Ministry’s Provincial Highway System.

2. Emergency needs in municipalities.

3. Detour needs on the Ministry’s Provincial Highway System.

16.3.4 Emergency Needs Policy for TMB’s

To ensure a responsible supply of TMB components sufficient to meet most anticipated


emergencies, the Ministry maintains and services an emergency stock of TMB
components at a stockyard in Northern Region.

An emergency may exist due to failure of any bridge component or collapse of an existing
bridge that leads to a permanent closure of the bridge. An emergency requiring the issue
of TMB components is deemed to exist when one or more of the following conditions are
satisfied:

a) An existing structure has been damaged beyond immediate repair;


b) The road is completely closed to traffic due to damage to the bridge;
c) The shortest detour that exists exceeds what would normally be considered
reasonable for purposes of emergency response (i.e., fire, police, and ambulance);
d) The time required to make repairs to the existing structure is considered excessive;
e) Alternative solutions, other than the supply of TMB components are not viable.

The approval procedure for emergency requests at Ministry and municipality sites, prior
to the release of TMB components, shall be as detailed in Directive PLNG-B-007.

March 2024 Page 7 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

16.3.5 Policy for Detours and Non-Emergency Needs

At present, the Ministry maintains and services a portion of the existing inventory of TMB
components for use as detours at Ministry construction sites. This stock is kept separate
from that intended for emergency use. However, this detour stock may be depleted by
attrition with time and the supply of TMB components for operational needs will eventually
be obtained from the private sector.

The need for a TMB and sufficient information for design must be clearly stated in a
Structural Planning Report. This will be the Structural Planning Report for a structural
project for which a TMB detour is required or, if the TMB is not part of such a project, a
separate report.

TMB drawings, quantities, and appropriate tender items are to be prepared by the
Regional Structural Section responsible for the project. Site numbers should be assigned
according to Section 2.5.1, e.g., 34E-2221/B0 in the title block.

During the preliminary stages of design, the Regional Structural Section shall obtain
confirmation from the Manager of Operations, Northern Region that the required quantities
of TMB components will be available when needed. If this is not possible then
consideration shall be given to alternative designs from the private sector.

The approval procedure, bills of materials and requests for the release of TMB
components shall be as detailed in Directive PLNG-B-007.

16.3.6 Use of Bailey Bridges as TMB

Bailey Bridges have been used in Ontario for over a half century. Due to their modular
components, Bailey bridges can be assembled in numerous ways, with multiple truss
panels either adjacent or on top of each other. Similarly, the floor system is made up of a
number of adjacent stringer sets (depending on the width of bridge) and a number of
transverse floor transoms, usually 2 or 4 per 10 ft (3 m) bay.

For Bailey Bridges with two floor transoms per bay, an evaluation according to the CHBDC
found that the load carrying capacity of the floor system was deficient. Subsequent load
testing by the MTO Structures Office confirmed that the floor system was incapable of
carrying full CHBDC CL-625-Ont loading.

Consequently, all new Bailey Bridge installations shall be specified with four transverse
transoms per bay when load posting is not desirable and when two transverse transoms
are specified, the bridge shall have a triple load posting of 25 tonnes, 40 tonnes, and
55 tonnes for a single, two unit and multi-vehicle train respectively.

16.4 High Mast Lighting Poles

16.4.1 Design of High Mast Lighting Pole

The design of high mast lighting poles (HMLP) and their foundations shall be based on
the requirements of the CHBDC. A reference wind pressure for a 50-year return period

March 2024 Page 8 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

shall be used. AASHTO’s “Standard Specifications for Structural Supports for Highway
Signs, Luminaries and Traffic Signals” shall also be used for design requirements, for
example fatigue design, not specified by the CHBDC. However, where there is a conflict
the CHBDC shall govern.

On Ministry projects pole heights of 25, 30, 35, 40 and 45 m are currently used and the
design for these high mast lighting supporting structures has already been carried out.
MTO issued standard drawings showing details of these structures. General details are
shown on the following MTO standards:

• OPSD 2450.011 HMLP 25, 30 & 35 m 8-Sided Pole;


• OPSD 2450.021 HMLP 40 & 45 m 12-Sided Pole.

The installation of high mast poles is covered by OPSS 630 “Construction Specification
for the Installation of High Mast Poles” and related special provisions.

High mast lighting supports have fixed based support systems that do not yield or break
away upon impact. The large mass of the poles and the potential safety consequences
of them falling to the ground necessitate a fixed base design. Since fixed base systems
are rigid obstacles, they should not be used in the roadside clear zone unless protected
by a barrier or approved by the ministry.

16.4.2 Foundations of High Mast Lighting Pole

An anchorage assembly detailed on the following standards connects the high mast
lighting support to a concrete caisson foundation:

• OPSD 2218.010 HMP Anchorage Assembly Placement;


• OPSD 2456.011 HMLP Anchorage Assembly Details.

The design of foundations shall be based on the requirements stated in Section 16.4.1.

Foundations for high mast poles may be designed according to the Structures Office
publication BRO-009, “Guidelines for the Design of High Mast Pole Foundations, third
edition,” which is based on the requirements of Section 16.4.1. This guide presents the
design of concrete caisson type foundations in a variety of soil conditions including rock
and layered soils. The designs and design methods given in this document are modeled
on short piles with a rotational limit of 0.005 radians at the ground surface, and the
theoretical analyses given in papers by Bengt, Broms and others.

The following Structural Standard Drawings for high mast pole foundations that are ground
or median mounted are available for use:

• SS116-50 High Mast Lighting Pole Footing Ground Mounted;


• SS116-51 High Mast Lighting Pole Footing Median Tall Mounted (Symmetrical);
• SS116-52 High Mast Lighting Pole Footing Median Tall Mounted (Asymmetrical).

The construction of foundations for high mast poles is covered by OPSS 631 “Construction
Specification for Concrete Footings and Maintenance Platforms for High Mast Lighting

March 2024 Page 9 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

Poles” and related special provisions.

16.5 Pedestrian, Bicycle and MUP Bridges

This section provides guidelines for the design of pedestrian and bicycle bridges.
Pedestrian, Bicycle and MUP bridges shall be designed following CSA S7-23 –
Pedestrian, cycling, and multiuse bridge design guideline. CSA S7-23 relies heavily on
CSA S6 (CHBDC). In addition to those requirements, the requirements of Section 16.5.1
shall be followed.

16.5.1 Loads

Where the clear width of the bridge is ≥2.4 m and <3 m, the bridge shall be designed for
a load equal to 50% of the maintenance vehicle load specified in CSA S7, while for bridges
with clear width ≥3.0 m, they shall be designed for 100% of the maintenance vehicle load.

16.6 Ethylene Vinyl Acetate (EVA) Foam

16.6.1 Overview

EVA foam is a flexible cellular expanded rubber foam product, usually composed of
Ethylene-Vinyl Acetate/Polyethylene. It is typically used for providing a separation
between adjacent concrete elements.

OPSS 920 has historically classified EVA foam only as a joint seal in accordance with
ASTM D1056. It has been used as a joint seal between twin structures, but its use has
recently been more common in other bridge details such as semi-integral conversions.
ASTM D1056 allows for many different types, classes, and grades of EVA foam. There is
a need to better define the EVA foam material on MTO bridge projects to ensure it is
supplied and installed to meet the performance requirements of the design.

Designers shall include Standard Special Provision SSP 109S18 in MTO bridge projects.
The SSP amends OPSS 904 and provides material and construction requirements for
EVA foam.

Designers shall designate the type and grade of EVA foam according to guidance
described below.

16.6.2 Material Properties and Classifications

ASTM D1056-14 gives the requirements for EVA foam, and classifies the material based
on Type, Class, and Grade. There are two main Types of EVA foam which can be
specified. These include:

1. Type 1: Open-Cell Rubber - A product whose cells are not totally enclosed by its
walls and open to the surface, either directly or by interconnecting with other cells;

2. Type 2: Closed-Cell Rubber - A product whose cells are totally enclosed by its walls
and hence not interconnecting with other cells.

March 2024 Page 10 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

Both types are further classified into four different Classes of material. All Classes are
made from either natural, synthetic, reclaimed, or rubber-like materials, but each have
various oil and/or temperature interaction requirements. These Classes according to
ASTM D1056-14 are:

• Class A: Specific resistance to the action of petroleum base oils is not required.

• Class B: Specific requirements for oil resistance with low mass change.

• Class C: Specific requirements for oil resistance with medium mass change.

• Class D: Specific requirements for extreme temperature resistance (-75 to 175°C),


but specific requirements for petroleum-based oils is not required.

Types and Classes of EVA foam are then further divided into different Grades, which
specify the range of stiffness for the material based on compression of 25% of the
thickness. This is an important property of the material which the designer must consider
when calculating forces acting on the ballast wall due to thermal movements of a
semi-integral downturn. These Grades (according to ASTM D1056-14), as well as the
calculated unfactored elastic modulus values are:

Compression-Deflection Avg. Modulus of Max. Modulus of


Grade
Range (kPa) Elasticity, Eavg (kPa) Elasticity, Emax (kPa)
0 0 - 13.8 27.6 55.2
1 13.8 - 34.5 96.6 138
2 34.5 - 62.1 193 248
3 62.1 - 89.6 303 358
4 89.6 - 117.2 414 469
5 117.2 - 172.4 579 690

The average modulus of elasticity is based on the midrange value of the compression
deflection range, which is used for estimating deflections across the material. The
maximum modulus of elasticity is based on the upper bound value in the range, which is
used for determining design forces transferred to an adjacent element across the EVA
foam. Both values are based on 25% compression, since they are calculated from the
specified compression deflection ranges given in ASTM D105614.

16.6.3 MTO’s Best Practices and Preferences

MTO preference is to use Type 2 (Closed Cell) and Class A (no specific oil or temperature
requirements) EVA foam on bridge projects. When EVA foam is not explicitly classified,
Contract special provisions will require the Contractor to supply Type 2, Class A, and either
Grade 2 or 3 EVA foam by default. The designer may specify a different grade, but this
should be limited only to areas where a specific grade is required.

It is not economical to specify numerous types, classes, and grades of EVA foam on bridge
projects. Since Type 2 or 3 and Class A is preferred, designers should make an attempt

March 2024 Page 11 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

to limit the number of grades required.

It is preferred to use a single thickness of EVA foam rather than layering different sizes
together. There are many thicknesses available, but the most common are 20, 25, 30, 40,
50, 75, and 100 mm. If greater than 100 mm is required, the designer should specify a
total thickness that can be built up using multiple layers of one of the most common
thicknesses. The width and height are usually cut from sheets, so these dimensions can
be prescribed as required.

16.6.4 Design Considerations for EVA Foam in MTO’s Projects

EVA Foam Supporting Dead Loads

The designer should consider the stiffness of EVA foam when it is used to support dead
loads such as approach slabs resting on wingwalls.

The compressive deflection of EVA foam supporting dead loads should not exceed 10%
of its specified thickness as a best practice. The following table gives the maximum
amount of dead load that each grade of EVA foam can support, based on the calculated
average modulus of elasticity (Eavg) and a maximum strain of 0.1:

Grade Maximum Dead Load (kPa)


0 2.8
1 9.7
2 19.0
3 30.0
4 41.0
5 58.0

EVA Foam Accommodating Movements

Design forces transmitted to structural components through EVA foam need to be


considered in design. The maximum modulus of elasticity should be used in calculating
the applied forces as follows:

σ = Emax x (Δc/t)

Where:
Δc = Imposed displacement across the EVA foam
t = Thickness of EVA Foam

A sufficient thickness of EVA foam shall be provided such that the applied strain (Δc/t)
does not exceed 0.25 (25% of the specified thickness).

Design Example #1

A semi-integral abutment detail experiences 13.4 mm of thermal contraction. A total of


60 mm thickness of EVA Foam Grade 2A2 is provided with a height of 300 mm. Calculate

March 2024 Page 12 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 16 - MISCELLANEOUS

the unfactored applied force on the ballast wall as a result of this movement.

Solution:

σ = Emax x (Δc/t); σ = (248 kPa) x (13.4 mm / 60 mm); σ = 55.4 kPa

For a unit length of ballast wall: P = (55.4 kPa) x (300 mm); P = 16.6 kN/m

Design Example #2:

Re-calculate the result in Example #1 with 80 mm thickness of EVA Foam grade 2A1
provided instead.

Solution:

σ = Emax x (Δc/t); σ = (138 kPa) x (13.4 mm / 80 mm); σ = 23.1 kPa

For a unit length of ballast wall: P = (23.1 kPa) x (300 mm); P = 6.9 kN/m

16.6.5 Presentation of EVA Foam on Contract Drawings

When the default classification of EVA foam is appropriate (Type 2, Class A, Grade 2 or
3), the designer shall use the following notation in the contract drawings:

“X” mm EVA FOAM

Where:
X = Thickness of EVA Foam

The designer may specify a different classification of EVA foam where necessary. Type
2 and Class A EVA foam should always be specified, and only the Grade should be
changed. The designer shall use the following notation in the contract drawings when a
specific grade is required:

“X” mm EVA FOAM, GRADE “TCG”

Where:
X = Thickness of EVA Foam,
T = Type (2),
C = Class (A), and
G = Grade (0 through 5)

For example, for 40 mm thick of Grade 4 EVA Foam, the designer would show it on the
contract drawings as “40 mm EVA FOAM, GRADE 2A4”.

March 2024 Page 13 of 13 SM-D2-S16


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 17 - COMPUTER APPLICATIONS

17 COMPUTER APPLICATIONS - NOT USED

March 2024 Page 1 of 2 SM-D2-S17


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 17 - COMPUTER APPLICATIONS

This page is intentionally left blank.

March 2024 Page 2 of 2 SM-D2-S17


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 18 - SIGN SUPPORTS

Table of Contents

18 SIGN SUPPORTS ................................................................................................ 2


18.1 General ........................................................................................................................ 2
18.2 Overhead Sign Supports .............................................................................................. 2
18.2.1 Cantilever Static Sign Supports ............................................................................ 2
18.2.2 Tri-Chord Static Sign Supports ............................................................................. 2
18.2.3 Monotube Sign Supports ...................................................................................... 3
18.2.4 VMS Sign Supports............................................................................................... 3
18.2.5 Bridge Mounted Sign Supports ............................................................................. 3
18.3 Ground Mounted Sign Supports ................................................................................... 3

March 2024 Page 1 of 3 SM-D2-S18


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 18 - SIGN SUPPORTS

18 SIGN SUPPORTS

18.1 General

The design and detailing of standard overhead sign support structures is to be carried out
in accordance with the latest version of the Sign Support Manual (SSM). Roadside sign
supports are covered in Ontario Traffic Manual – Book 3, Ground-Mounted Sign Support
and Installation, 2022.

The SSM contains information needed to prepare the contract drawings, tender quantities
and special provisions for standard sign supports. The design of the cantilever, tri-chord,
monotube and variable message sign (VMS) support structures meets the requirements
of the CHBDC.

All non-standard sign support structures that do not meet the assumptions stated in the
SSM must be custom designed, sealed and signed by two engineers.

The standard sign support structures covered by the SSM are:

18.2 Overhead Sign Supports

18.2.1 Cantilever Static Sign Supports

A sign support that cantilevers from the roadside over the closest driving lane and shoulder
for static signs. Two types of cantilever sign supports, single cantilever and butterfly, are
currently available in the SSM. The butterfly sign support is suitable for total signboard
sizes up to and including 48 m2 and for single cantilever sign support signboard size
including and up to 32m2 is suitable, depending on the sign type, class, reference wind
pressure and the eccentricity of the centreline of the signboard. The static signs range in
depth from 1525 mm to 2745 mm inclusive. The structure is constructed of galvanised
structural steel and consists of an overhead truss supported on a single leg column with
a concrete caisson type foundation.

18.2.2 Tri-Chord Static Sign Supports

a) Simply Supported Type:

This is a sign support structure that crosses the highway with spans ranging from 14 m to
36 m inclusive. These sign supports are suitable for carrying total signboard areas of up
to and including 45 m2. The static signs range in depth from 1525 mm to 3965 mm
inclusive, depending on the structure type. The structure is constructed of galvanised
structural steel and consists of a three-chord overhead truss supported on a single leg
column on each side with concrete caisson type foundations.

b) Cantilever Type:

A sign support which cantilevers from the roadside over the closest driving lane and
shoulder. This sign support is suitable for total signboard sizes up to and including
26.7 m2. The static signs range in depth from 1525 mm to 2745 mm inclusive. The

March 2024 Page 2 of 3 SM-D2-S18


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 18 - SIGN SUPPORTS

structure is constructed of galvanised structural steel and consists of a three-chord


overhead truss supported on a single leg column with concrete caisson type foundation.

18.2.3 Monotube Sign Supports

A sign support that crosses the highway with spans ranging from 13.5 m to 24 m inclusive
for lane designation signs. This sign support is suitable for signboard sizes up to and
including 1200 mm by 1200 mm. The structure is constructed of galvanised structural
steel and consists of four tapered, octagonal monotubes with concrete caisson type
foundations.

18.2.4 VMS Sign Supports

a) Overhead truss:

A sign support that crosses the highway with spans ranging from 17.6 m to 34 m inclusive
for variable message sign systems. This sign support is suitable for sign systems up to
and including 40 m2. The structure is constructed of an overhead aluminum truss
supported on galvanised structural steel columns with concrete caisson type foundations.

b) Pole mounted:

This VMS sign support is fabricated from a galvanised structural steel pole with concrete
caisson type foundation. The pole is carrying the VMS digital panel. The maximum VMS
size is 3000 mm in depth by 5000 mm in width.

18.2.5 Bridge Mounted Sign Supports

A sign support mounted on bridges for static signs ranging in depth from 1525 mm to
2745 mm inclusive, and width as required. The structure is constructed of aluminium
struts and arms connected to the bridge by stainless steel anchors.

18.3 Ground Mounted Sign Supports

Ground mounted sign supports are available with break-away supports, or rigid supports
when located beyond the clear recovery zone or adequately behind a roadside barrier.
These sign supports are no longer contained in the MTO’s Sign Support Manual and are
in Ontario Traffic Manual - Book 3 (Ground-Mounted Sign Support and Installation).

March 2024 Page 3 of 3 SM-D2-S18


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 19 - BRIDGE REHABILITATION

Table of Contents

19 BRIDGE REHABILITATION ................................................................................. 2


19.1 Rehabilitation of Bridge Structures ............................................................................... 2
19.1.1 MTO’s Structure Rehabilitation Manual (SRM)...................................................... 2

March 2024 Page 1 of 2 SM-D2-S19


STRUCTURAL MANUAL DIVISION 2 - PROCEDURES

SECTION 19 - BRIDGE REHABILITATION

19 BRIDGE REHABILITATION

19.1 Rehabilitation of Bridge Structures

The overall structural design and detailing for the rehabilitation and repair of bridge
structures and components shall be according to the Structural Manual and CHBDC.
Methods, procedures, and detailed technical information related to bridge rehabilitation
are covered in the MTO Structure Rehabilitation Manual (SRM).

Additionally, other MTO manuals, guidelines, policies, and standards that are applicable
to bridge rehabilitation projects should also be referred to.

19.1.1 MTO’s Structure Rehabilitation Manual (SRM)

The SRM contains information on performing detailed site investigations, selecting the
appropriate methods and scope of rehabilitation, information on contract preparation, and
other guidance as it relates to bridge (and other structure) rehabilitation.

March 2024 Page 2 of 2 SM-D2-S19


STRUCTURAL MANUAL

DIVISION 3 - DESIGN AIDS

SM-D3-S00
STRUCTURAL MANUAL

This page is intentionally left blank.

SM-D3-S00
STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 1 - INDEX OF DESIGN AIDS

1 INDEX OF DESIGN AIDS

2 GENERAL DESIGN AND DRAFTING

Active Earth Pressure Without Surcharge ............................................................DA 2-10


Active Earth Pressure With 800 mm Surcharge ....................................................DA 2-11
Continuous Beams (Equal Spans) ........................................................................DA 2-12
Simple Beam Moment Coefficients (Uniform, Triangular, and Symmetrical
Parabolic Loads) ..................................................................................................DA 2-13
Simple Beam Moment Coefficients (Parabolic Load A and B) .............................. DA 2-14
Fixed End Moments for Prismatic Beams (Simply Supported / Fixed End ............ DA 2-15
Fixed End Moments for Prismatic Beams (Fixed End / Fixed End) ....................... DA 2-16

3 PILES

None.

4 FOOTINGS

None.

5 ABUTMENTS, WINGWALLS AND RETAINING WALLS

Wingwall Design Table (T = 400 mm) ....................................................................DA 5-1


Wingwall Design Table (T = 450 mm) .....................................................................DA 5-2
Wingwall Design Table (T = 500 mm) .....................................................................DA 5-3
Wingwall Design Table (T = 550 mm) .....................................................................DA 5-4
Wingwall Design Table (T = 600 mm) .....................................................................DA 5-5

6 PIERS

None.

7 PRESTRESSED CONCRETE

Precast NU Girders (Section Properties) ................................................................DA 7-1

8 STRUCTURAL STEEL

Standard Welding Symbols ....................................................................................DA 8-1

9 DECK AND CURBS

None.

10 BARRIERS AND RAILING SYSTEMS

Dead Load of Standard Barriers ...........................................................................DA 10-1

March 2024 Page 1 of 2 SM-D3-S01


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 1 - INDEX OF DESIGN AIDS

Dead Load of Temporary Barriers ........................................................................DA 10-2

11 RIGID FRAMES

None.

12 REINFORCING STEEL

Reinforcing Steel Bars ..........................................................................................DA 12-1

13 BEARING ASSEMBLIES AND EXPANSION JOINTS

None.

14 CULVERTS

None.

15 WOOD STRUCTURES

None.

16 MISCELLANEOUS

Imperial - S.I. Conversion Factors ........................................................................DA 16-5


Properties of a Parabolic Curve .......................................................................... DA 16-10

17 COMPUTER APPLICATIONS

None.

18 SIGN SUPPORTS

None.

March 2024 Page 2 of 2 SM-D3-S01


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 2 - GENERAL DESIGN AND DRAFTING

DESIGN AID 2-10


ACTIVE EARTH PRESSURE WITHOUT SURCHARGE

March 2024 Page 1 of 7 SM-D3-S02


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 2 - GENERAL DESIGN AND DRAFTING

DESIGN AID 2-11


ACTIVE EARTH PRESSURE WITH 800 mm SURCHARGE

March 2024 Page 2 of 7 SM-D3-S02


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 2 - GENERAL DESIGN AND DRAFTING

DESIGN AID 2-12


CONTINUOUS BEAMS (EQUAL SPANS)

March 2024 Page 3 of 7 SM-D3-S02


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 2 - GENERAL DESIGN AND DRAFTING

DESIGN AID 2-13


SIMPLE BEAM MOMENT COEFFICIENTS
(Uniform, Triangular, and Symmetrical Parabolic Loads)

March 2024 Page 4 of 7 SM-D3-S02


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 2 - GENERAL DESIGN AND DRAFTING

DESIGN AID 2-14


SIMPLE BEAM MOMENT COEFFICIENTS
(Parabolic Load A and B)

March 2024 Page 5 of 7 SM-D3-S02


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 2 - GENERAL DESIGN AND DRAFTING

DESIGN AID 2-15


FIXED END MOMENTS FOR PRISMATIC BEAMS
(Simply Supported / Fixed End)

March 2024 Page 6 of 7 SM-D3-S02


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 2 - GENERAL DESIGN AND DRAFTING

DESIGN AID 2-16


FIXED END MOMENTS FOR PRISMATIC BEAMS
(Fixed End / Fixed End)

March 2024 Page 7 of 7 SM-D3-S02


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

WINGWALL DESIGN AID


Moments and Lateral Thrust for Cantilever Wingwalls

March 2024 Page 1 of 8 SM-D3-S05


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

DESIGN AID 5-1


WINGWALL DESIGN TABLE (T = 400 mm)

March 2024 Page 2 of 8 SM-D3-S05


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

DESIGN AID 5-2


WINGWALL DESIGN TABLE (T = 450 mm)

March 2024 Page 3 of 8 SM-D3-S05


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

DESIGN AID 5-3


WINGWALL DESIGN TABLE (T = 475 mm)

March 2024 Page 4 of 8 SM-D3-S05


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

DESIGN AID 5-4


WINGWALL DESIGN TABLE (T = 500 mm)

March 2024 Page 5 of 8 SM-D3-S05


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

DESIGN AID 5-5


WINGWALL DESIGN TABLE (T = 550 mm)

March 2024 Page 6 of 8 SM-D3-S05


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

DESIGN AID 5-6


WINGWALL DESIGN TABLE (T = 600 mm)

March 2024 Page 7 of 8 SM-D3-S05


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 5 - ABUTMENTS, WINGWALLS AND RETAINING WALLS

This page is intentionally left blank.

March 2024 Page 8 of 8 SM-D3-S05


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 7 - PRESTRESSED CONCRETE

DESIGN AID 7-1


PRESTRESSED NU GIRDERS

March 2024 Page 1 of 1 SM-D3-S07


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 8 - STRUCTURAL STEEL

DESIGN AID 8-1


STANDARD WELDING SYMBOLS

March 2024 Page 1 of 1 SM-D3-S08


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 10 – BARRIERS AND RAILING SYSTEMS

DESIGN AID 10-1


PERMANENT BARRIERS DEAD LOAD

Note: Barrier Dead Load is based on barrier/curb concrete above the dashed line as marked
Total
DL of
DL of Weight
Related Structural Standard Barrier Concrete
Barrier Type Steel of
Drawing Shape Wall/curb
(kN/m) Barrier
(kN/m)
(kN/m)

Barrier Wall
SS110-21, SS110-
With Railing, 6.1 0.3 6.4
54,58,68,69,91
TL-4

Parapet Wall
SS110-21, SS110-
With Railing, 5.2 0.3 5.4
56,57,59,65,75,90,97,98,104,105
TL-4

Parapet Wall
for
Combination SS110-85, SS110-82,83,84 5.2 0.3 5.5
Traffic/Bicycle
Rail, TL-4

Four Tube
Combination
SS110-34,36 3.4 0.9 4.3
Traffic/Bicycle
Railing, TL-4

March 2024 Page 1 of 9 SM-D3-S10


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 10 – BARRIERS AND RAILING SYSTEMS

DESIGN AID 10-1


PERMANENT BARRIERS DEAD LOAD

Note: Barrier Dead Load is based on barrier/curb concrete above the dashed line as marked
Total
DL of
DL of Weight
Barrier Related Structural Concrete
Barrier Shape Steel of
Type Standard Drawing Wall/curb
(kN/m) Barrier
(kN/m)
(kN/m)

Three Tube
Railing on SS110-37,39 3.4 0.7 4.0
Curb, TL-4

Four Tube
Railing on
SS110-46,49 N/A 0.9 0.9
Sidewalk,
TL-4

Multi Use
Path (MUP)
Separation
SS110-110 5.5 N/A 5.5
Barrier
(Parapet),
TL-4

Barrier Wall
Without
SS110-92,94,109 7.9 N/A 7.9
Railing, TL-
5

March 2024 Page 2 of 9 SM-D3-S10


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 10 – BARRIERS AND RAILING SYSTEMS

DESIGN AID 10-1


PERMANENT BARRIERS DEAD LOAD

Note: Barrier Dead Load is based on barrier/curb concrete above the dashed line as marked
Total
DL of
DL of Weight
Barrier Related Structural Concrete
Barrier Shape Steel of
Type Standard Drawing Wall/curb
(kN/m) Barrier
(kN/m)
(kN/m)

Barrier Wall
With SS110-70,71,72, 73 and
8.7 N/A 8.7
Architectural 74,93,99
Finish, TL-5

Parapet
Wall for Two
S110-95,96 7.0 0.6 7.6
Tube
Railing, TL-
5

Multi-Use
Path (MUP),
Separation SS110-111 7.8 N/A 7.8
Barrier, TL-
5

Reinforced
Concrete
Median
Barrier Wall SS110-62 12.2 N/A 12.2
on
Structures -
Type I

March 2024 Page 3 of 9 SM-D3-S10


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 10 – BARRIERS AND RAILING SYSTEMS

DESIGN AID 10-1


PERMANENT BARRIERS DEAD LOAD

Note: Barrier Dead Load is based on barrier/curb concrete above the dashed line as marked
Total
DL of
DL of Weight
Barrier Related Structural Concrete
Barrier Shape Steel of
Type Standard Drawing Wall/curb
(kN/m) Barrier
(kN/m)
(kN/m)

Reinforced
Concrete
Median
Barrier Wall SS110-63 6.9 N/A 6.9
on
Structures -
Type II

Multi Use
Path (MUP)
SS0110.0022 3.5 0.8 4.2
Bicycle
Barrier

Inspector
Guard SS110-33 N/A 0.4 0.4
Details

Guide Rail
System,
Concrete
Barrier,
Type J OPSD 911.150 6.9 N/A 6.9
Connection,
4 m Length
Installation,
Temporary

March 2024 Page 4 of 9 SM-D3-S10


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 10 – BARRIERS AND RAILING SYSTEMS

DESIGN AID 10-1


PERMANENT BARRIERS DEAD LOAD

Note: Barrier Dead Load is based on barrier/curb concrete above the dashed line as marked
Total
DL of
DL of Weight
Barrier Related Structural Concrete
Barrier Shape Steel of
Type Standard Drawing Wall/curb
(kN/m) Barrier
(kN/m)
(kN/m)
Guide Rail
System,
Concrete
Barrier,
OPSD 911.16 6.8 N/A 6.8
Cast-In-
Place, Type
M,
Installation

March 2024 Page 5 of 9 SM-D3-S10


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 10 – BARRIERS AND RAILING SYSTEMS

This page is intentionally left blank.

March 2024 Page 6 of 9 SM-D3-S10


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 10 – BARRIERS AND RAILING SYSTEMS

DESIGN AID 10-2


TEMPORARY BARRIERS DEAD LOAD
Related
DL of
Structural
Barrier Type Barrier Shape/Photo Barrier
Standard
(kN/m)
Drawing
Guide Rail
System,
Concrete
Barrier Type
OPSD
T 6.8
0911.1800
Connection,
4.0m Length
Installation -
Temporary
Guide Rail
System,
Concrete
Barrier, Type
X MTOD
6.8
Connection, 911.194
4.0 m
Length,
Installation,
Temporary
Guide Rail
System,
Concrete
Barrier, Type MTOD
5.5
Z, 12.0 m 911.201
Length,
Installation,
Temporary
Guide Rail
System,
Concrete
Barrier,
OPSD
QuickChange 6.7
911.610
Moveable
Barrier,
Installation,
Temporary

March 2024 Page 7 of 9 SM-D3-S10


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 10 – BARRIERS AND RAILING SYSTEMS

DESIGN AID 10-2


TEMPORARY BARRIERS DEAD LOAD
Related
DL of
Barrier Structural
Barrier Shape/Photo Barrier
Type Standard
(kN/m)
Drawing

BarrierGua RDM
0.9
rd 800 5.1.4.1

ZoneGuar RDM
0.9
d 5.1.4.2

RDM
Defender 0.8
5.1.4.3

RDM
Safezone 0.8
5.1.4.4

March 2024 Page 8 of 9 SM-D3-S10


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 10 – BARRIERS AND RAILING SYSTEMS

DESIGN AID 10-2


TEMPORARY BARRIERS DEAD LOAD

HV2 RDM 5.1.4.5 3.5

Highway
RDM 5.1.4.6 0.9
Guard

March 2024 Page 9 of 9 SM-D3-S10


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 12 - REINFORCING STEEL

DESIGN AID 12-1


REINFORCING STEEL BARS

March 2024 Page 1 of 1 SM-D3-S12


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 16 - MISCELLANEOUS

DESIGN AID 16-5


IMPERIAL - S.I. CONVERSION FACTORS

March 2024 Page 1 of 2 SM-D3-S16


STRUCTURAL MANUAL DIVISION 3 - DESIGN AIDS

SECTION 16 - MISCELLANEOUS

DESIGN AID 16-10


PROPERTIES OF A PARABOLIC CURVE

March 2024 Page 2 of 2 SM-D3-S16