Guideline 7th Module
Guideline 7th Module
LABWORK SUBSTANCE
Determining the layout of floor production and additional facilities.
LABWORK OBJECTIVES
1. Students are able to analyze the relationship between each process in a factory.
2. Students are able to determine the position of each department in accordance with the
relationship between activity and material flow.
3. Students are able to determine the position of each department according to the number
of floors needed and the number of floors available.
LABWORK TOOLS
Microsoft Excel
LABWORK REQUIREMENT
Guideline
STUDY CASE
CV FRI company has 20 production facilities in the floor production from receiving
until shipping and additional facilities. The company wants to identify the relation between
departments. This was done in order to achieve a good work flow, production lines smoothly,
until the good relations between each facility and minimize any disruption close together
facilities.
1
LABWORK STEPS
1. Finding out the number of A, E, I, O, U and X in combination with the total
number of pairs departments.
Table 1 Production Floor Result of Combine
RESULT OF COMBINE
A 9
E 19
Combine 190
I 28
O 38
U 87
X 9
2
3. Analysis of a single department to department in accordance with the other
table relationship reasons of production, personnel and information.
Table 3 Production Floor Reasons Relation
3
Table 4 Sorted Production Floor Reasons Relation
20 L M v v v v v 5 E
21 L GBBU v v v v v 5 E
22 M N v v v v v 5 E
23 M GBBP v v v v v 5 E
24 N O v v v v v 5 E
25 O GBBP v v v v v 5 E
26 O W v v v v v 5 E
27 W SHIP v v v v v 5 E
28 A B v v v v v 4 E
4
Table 5 Sorted Production Floor Reasons Relation (Cont.)
29 A C v v 2 I
30 A E v v 2 I
31 A G v v 2 I
32 B D v v 2 I
33 B F v v 2 I
34 C E v v 2 I
35 C G v v 2 I
36 D G v v 2 I
37 E G v v 2 I
38 H J v v 2 I
39 I J v v 2 I
40 REC A v 1 I
41 REC B v 1 I
42 REC C v 1 I
43 REC D v 1 I
44 REC E v 1 I
45 REC F v 1 I
46 REC G v 1 I
47 REC H v 1 I
48 REC I v 1 I
49 REC J v 1 I
50 REC K v 1 I
51 REC L v 1 I
52 REC M v 1 I
53 REC N v 1 I
54 REC O v 1 I
55 REC W v 1 I
56 REC SHIP v 1 I
5
Table 7 Sorted Production Floor Reasons Relation (Cont.)
95 C SHIP v 1 U
96 D E v 1 U
97 D F v 1 U
98 D H v 1 U
99 D I v 1 U
100 D J v 1 U
101 D L v 1 U
102 D M v 1 U
103 D N v 1 U
104 D O v 1 U
105 D GBBP v 1 U
106 D GBBU v 1 U
107 D W v 1 U
108 D SHIP v 1 U
109 E H v 1 U
110 E I v 1 U
111 E J v 1 U
112 E K v 1 U
113 E L v 1 U
114 E M v 1 U
115 E N v 1 U
116 E O v 1 U
117 E GBBP v 1 U
118 E W v 1 U
119 E SHIP v 1 U
120 F G v 1 U
121 F H v 1 U
122 F I v 1 U
123 F J v 1 U
124 F L v 1 U
125 F M v 1 U
126 F N v 1 U
127 F O v 1 U
128 F GBBP v 1 U
129 F GBBU v 1 U
130 F W v 1 U
131 F SHIP v 1 U
132 G H v 1 U
133 G I v 1 U
134 G J v 1 U
135 G L v 1 U
136 G M v 1 U
137 G N v 1 U
138 G O v 1 U
139 G GBBP v 1 U
140 G W v 1 U
141 G SHIP v 1 U
142 H K v 1 U
143 H M v 1 U
144 H O v 1 U
145 H GBBP v 1 U
146 H W v 1 U
147 H SHIP v 1 U
148 I M v 1 U
149 I O v 1 U
150 I GBBP v 1 U
151 I GBBU v 1 U
152 I W v 1 U
153 I SHIP v 1 U
154 J M v 1 U
155 J O v 1 U
156 J GBBP v 1 U
157 J W v 1 U
158 J SHIP v 1 U
159 K L v 1 U
160 K N v 1 U
161 K O v 1 U
162 K GBBU v 1 U
6
Table 8 Sorted Production Floor Reasons Relation (Cont.)
163 K W v 1 U
164 K SHIP v 1 U
165 L N v 1 U
166 L O v 1 U
167 L GBBP v 1 U
168 L W v 1 U
169 L SHIP v 1 U
170 M O v 1 U
171 M GBBU v 1 U
172 M W v 1 U
173 M SHIP v 1 U
174 N GBBP v 1 U
175 N GBBU v 1 U
176 N W v 1 U
177 N SHIP v 1 U
178 O GBBU v 1 U
179 O SHIP v 1 U
180 W GBBP v 1 U
181 W GBBU v 1 U
182 GBBP GBBU v 1 X
183 GBBP SHIP v 1 X
184 GBBU SHIP v 1 X
185 H L v v -4 X
186 H N v v -4 X
187 I L v v -4 X
188 I N v v -4 X
189 J L v v -4 X
190 J N v v -4 X
7
5. Make diagrams in Microsoft Visio ARC Tables ARC based on a case study sheet.
8
6. Further the normalization of ARC. Make an normalization table of the ARC based on the ARC and the value of normalization.
9
7. Input the rectilinear distance of each other facilities from the data on MHC Design sheet.
Table 10 Production Floor Rectilinear Distance Table 11 Production Floor Rectilinear Distance
(Cont.)
10
8. Input data required in this module is the From-To Chart (FTC) Cost divided by the rectilinear distance.
11
Table 13 Production Floor From To Chart (Cont.)
12
9. Counting UFD (UFD multiplication and normalization of data for ARC).
13
Table 15 Production Floor Unit Flow Distribution (Cont.)
14
10. Make a worksheet, fill the relationship column of each facility with the number of the facility on the worksheet sheet that have a relation
between each other facility.
Relation Degree
No Initial Facility Name
A (1) E (0.8) I (0.6) O (0.4) U (0.2) X (0)
1 REC RECEIVING 2,3 - 4,5,6,7,8,9,10,11,12,13,14,15,16,17,18,19,20 - - -
2 GBBU Warehouse of Direct Material 1,4,6 8,10,11,13,15 - 5 7,9,12,14,6,17,18,19 3,2
3 GBBP Warehouse of Indirect Material 1 14,16,18 - 4,5,6 7,8,9,10,11,12,13,15,17,19 2,20
4 A Milling Machine 1 2 5 1,6,8,10 3,7,9,11,12,13,14,15,16,17,18,19,20 - -
5 B Milling Machine 2 16 4 1,7,9 2,3,6,8,10,11,12,13,14,15,17,18,19,20 - -
6 C Milling Machine 3 2,7 - 1,4,8,10 3,5,9,11,12,13,14,15,16,17,18,19 20 -
7 D Milling Machine 4 6,14 - 1,5,10 4 2,3,8,9,11,12,13,15,16,17,18,19,20 -
8 E Milling Machine 5 9 2 1,4,6,10 5 3,7,11,12,13,14,15,16,17,18,19,20 -
9 F Milling Machine 6 8 14 1,5 4,6 2,3,7,10,11,12,13,15,16,17,18,19,20 -
10 G Milling Machine 7 - 2,14 1,4,6,7,8 5 3,9,11,12,13,15,16,17,18,19,20 -
11 H Turning Machine 1 12 2 1,13 4,5,6 3,7,8,9,10,14,16,18,19,20 15,17
12 I Turning Machine 2 11 14 1,13 4,5,6 2,3,7,8,9,10,16,18,19,20 15,17
13 J Turning Machine 3 - 2,14 1,11,12 4,5,6 3,7,8,9,10,16,18,19,20 15,17
14 K Assembly Table 1 7 3,9,10,12,13,16 1 4,5,6 2,8,11,15,17,18,19,20 -
15 L Inspection Table 1 - 2.16 1 4,5,6 3,7,8,9,10,14,17,18,19,20 11,12,13
16 M Assembly Table 2 5 3,14,15,17 1 4,6 2,7,8,9,10,11,12,13,18,19,20 -
17 N Inspection Table 2 - 16.18 1 4,5,6 2,3,7,8,9,10,14,15,19,20 11,12,13
18 O Packaging Table - 3,17,19 1 4,5,6 2,7,8,9,10,11,12,13,14,15,16,20 -
19 W WAREHOUSE - 18,2 1 4,5,6 2,3,7,8,9,10,11,12,13,14,15,16,17 -
20 SHIP SHIPPING - 19 1 4,5 6,7,8,9,10,11,12,13,14,15,16,17,18 2,3
15
11. Make Area Allocation Diagram (AAD) based on the worksheet sheet.
16 M 17 N 18 O
2,7,8,9,10,11,12,1 2,3,7,8,9,10,14,15 2,7,8,9,10,11,12,1
4,6 - 4,5,6 11,12,13 4,5,6 -
3,18,19,20 ,19,20 3,14,15,16,20
- 18,2 1 - 19 1
19 W 20 SHIP
2,3,7,8,9,10,11,12 6,7,8,9,10,11,12,1
4,5,6 - 4,5 2,3
,13,14,15,16,17 3,14,15,16,17,18
16
12. Input Area Allocation Diagram of manufacture is a worksheet. In this AAD proximity to the appropriate level of interest seen in color.
Result AAD
17
13. Input the production floor area the size of each facility based on initial layout sheet.
B Milling Machine 2 1 6 6 36
C Milling Machine 3 1 6 6 36
D Milling Machine 4 1 6 6 36
E Milling Machine 5 1 6 6 36
F Milling Machine 6 1 6 6 36
G Milling Machine 7 1 6 6 36
H Turning Machine 1 1 7 5 35
I Turning Machine 2 1 7 5 35
J Turning Machine 3 1 7 5 35
K Assembly Table 1 1 7 6 42
L Inspection Table 1 1 6 5 30
M Assembly Table 2 1 7 6 42
N Inspection Table 2 1 7 6 42
O Packaging Table 1 1 7 6 42
REC Receiving - - - 2
GBBU GBBU - - - 2
GBBP GBBP - - - 2
W Warehouse - - - 5
SHIP Shipping - - - 2
TOTAL 568
18
14. Make Initial layout that has been adapted to Area Allocation Diagram (AAD).
m2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
1 GBBU REC GBBP
2
4 H
C E A
5 K
6
9 I
10
11
D F B
12 M
13
14 J
15
16 L
17
G
18
19 N
20
21
22
23
24
25
26 O
27
28
29
30 W
31 S
32
19
15. Calculate on the Initial Layout coordinates that have been made and make a
decision which location of facility will be fixed. The facilities that can be
consider as “fixed location” are the facilities which have a major effect if
they’re moved, such as change the IN or OUT way of the material TO or FROM
the factory. The coordinate of the facility is determined by the starting from
starting edge of ‘x’ and ‘y’ axis and ended on finish edge of ‘x’ and ‘y’ axis,
the ‘x’ axis starting from the left to the right, and the ‘y’ axis starting from the
top to the down of the edges.
Table 18 Production Floor Facilities Table 19 Production Floor Facilities Fixed Location
Coordinate
20
16. Finding out the number of A, E, I, O, U and X in combination with the total
number of pairs departments by adding additional facilities for examples
offices, toilets, rooms, meeting rooms, parking area, and others with the rest of
your land area.
Table 20 Prod. Floor + Add. Facilities Result of Combine
Combine 21
17. Creating relation analysis of production, employee association and information
selected in order to determine the position of each department in accordance
with the activities and the flow of material.
Table 21 Prod. Floor + Add. Facilities Relevance Motive Table
21
18. Analysis of a single department to department in accordance with the other
table relationship reasons of production, personnel and information.
22
19. ARC table is sorted by the number of A, E, I, O, U and X in accordance with
the number previously counted.
Table 24 Sorted Prod. Floor + Add. Facilities Reasons Relation
Relation Between Reason Relation
No.
Facility 1 Facility 2 1 2 3 4 5 6 7 Total code
1 P Q v v v v v v 6 A
2 P S v v v v v v 6 E
3 Q R v v v v v v 6 E
4 P R v v v v 4 I
5 P U v v v v 4 I
6 P V v v v v 4 I
7 Q S v v v 3 O
8 Q U v v v 3 O
9 U V v v v 3 O
10 Q V v v 2 O
11 R S v v 2 U
12 P T v 1 U
13 Q T v 1 U
14 R T v 1 U
15 R U v 1 U
16 R V v 1 U
17 S T v 1 U
18 S U v 1 U
19 S V v 1 U
20 T U v 1 U
21 T V v -5 X
20. Make diagrams in Microsoft Visio ARC Tables ARC based on a case study sheet.
23
21. Further the normalization of ARC
Normalization
From\To 1 2 3 4 5 6 7
P Q R S T U V
1 P 1 0.6 0.8 0.2 0.6 0.6
2 Q 1 0.8 0.4 0.2 0.4 0.4
3 R 0.6 0.8 0.2 0.2 0.2 0.2
4 S 0.8 0.4 0.2 0.2 0.2 0.2
5 T 0.2 0.2 0.2 0.2 0.2 0
6 U 0.6 0.4 0.2 0.2 0.2 0.4
7 V 0.6 0.4 0.2 0.2 0 0.4
Table 25 Prod. Floor + Add. Facilities ARC
Normalization
24
22. Make a worksheet, fill the relationship column of each facility with the number of the facility on the worksheet sheet that have a relation
between each other facility.
Table 26 Prod. Floor + Add. Facilities Worksheet
Relation Degree
No Initial Facility
A (1) E (0.8) I (0.6) O (0.4) U (0.2) X (0)
1 P Office 2 4 3,6,7 - 5 -
2 Q Toilet 1 3 - 4,6,7 5 -
3 R Mosque - 2 1 - 4,5,6,7 -
4 S Employee Parking - 1 - 2 3,5,6,7 -
5 T Smoking area - - - - 1,2,3,4,6 7
6 U Security Pos - - 1 2,7 3,4,5 -
7 V Production Floor - - 1 2,6 3,4 5
- - - - - 1 - - 1
25
24. Input Area Allocation Diagram of manufacture is a worksheet. In this AAD proximity to the appropriate level of interest seen in
color.
Result AAD
- - 1
Production
7 V Floor
2,6 3,4 5
1 3 - 2 4 3,6,7
- 2 1
- 4,5,6,7 - 4,6,7 5 - - 5 -
- - - - - 1 - 1 -
Employee
5 T Smoking area 6 U Security Pos 4 S Parking
- 1,2,3,4,6 7 2,7 3,4,5 - 2 3,5,6,7 -
26
25. Make the list of facilities including production floor and additional facilities, then make
an Initial layout that has been adapted to Area Allocation Diagram (AAD).
Table 27 Prod. Floor + Add. Facilities Detail
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
1 GBBU REC GBBP
2
3
4 H
5 C E A
K
6
7
8
9 I
10
11
D F B
12 M
13
14 J
15
16 L
17 G
18
19 N
Q
20
21
P
22
23
U
24 R
25
26 O
27
28
29
30 W
31 Ship
32
33
34 T
35
S
36
37
38
27
26. Finding out the number of A, E, I, O, U and X in combination with the total number of
pairs departments by adding facilities in the office, such as table, chair, and storage.
Table 28 Office Result of Combine
Relationship Activity Percentage A 4
A 5% E 9
E 10% I 13
I 15% O 18
O 20% U 43
U The rest of the total combination X 4
X 5%
Combine 91
29
Table 32 Office Facilities Reasons Relation (Cont.)
AD BB V V V V V 5
AD BC V V V V V 5
AD BD V V V V V 5
AD BE V V V V V 5
AD BF V V V V V 5
AD CA V V V V 4
AD CB V V V V 4
AE AF V V V V V 5
AE BA V V V V V 5
AE BB V V V V V 5
AE BC V V V V V 5
AE BD V V V V V 5
AE BE V V V V V 5
AE BF V V V V V 5
AE CA V V V V 4
AE CB V V V V 4
AF BA V V V V V 5
AF BB V V V V V 5
AF BC V V V V V 5
AF BD V V V V V 5
AF BE V V V V V 5
AF BF V V V V V 5
AF CA V V V V 4
AF CB V V V V 4
BA BB V V V V V 5
BA BC V V V V V 5
BA BD V V V V V 5
BA BE V V V V V 5
BA BF V V V V V 5
BA CA V V V V 4
BA CB V V V V 4
BB BC V V V V V 5
BB BD V V V V V 5
BB BE V V V V V 5
BB BF V V V V V 5
BB CA V V V V 4
BB CB V V V V 4
BC BD V V V V V 5
BC BE V V V V V 5
BC BF V V V V V 5
BC CA V V V V 4
BC CB V V V V 4
BD BE V V V V V 5
BD BF V V V V V 5
BD CA V V V V 4
BD CB V V V V 4
BE BF V V V V V 5
BE CA V V V V 4
BE CB V V V V 4
BF CA V V V V 4
BF CB V V V V 4
CA CB V V V V V 5
30
29. ARC table is sorted by the number of A, E, I, O, U and X in accordance with
the number previously counted.
31
Table 34 Sorted Office Facilities Reasons Relation (Cont.)
27 AC BC V V V V V 5 O
28 AC BD V V V V V 5 O
29 AC BE V V V V V 5 O
30 AC BF V V V V V 5 O
31 AD AE V V V V V 5 O
32 AD AF V V V V V 5 O
33 AD BA V V V V V 5 O
34 AD BB V V V V V 5 O
35 AD BC V V V V V 5 O
36 AD BD V V V V V 5 O
37 AD BE V V V V V 5 O
38 AD BF V V V V V 5 O
39 AE AF V V V V V 5 O
40 AE BA V V V V V 5 O
41 AE BB V V V V V 5 O
42 AE BC V V V V V 5 O
43 AE BD V V V V V 5 O
44 AE BE V V V V V 5 O
45 AE BF V V V V V 5 U
46 AF BA V V V V V 5 U
47 AF BB V V V V V 5 U
48 AF BC V V V V V 5 U
49 AF BD V V V V V 5 U
50 AF BE V V V V V 5 U
51 AF BF V V V V V 5 U
52 BA BB V V V V V 5 U
53 BA BC V V V V V 5 U
54 BA BD V V V V V 5 U
55 BA BE V V V V V 5 U
56 BA BF V V V V V 5 U
57 BB BC V V V V V 5 U
58 BB BD V V V V V 5 U
59 BB BE V V V V V 5 U
60 BB BF V V V V V 5 U
61 BC BD V V V V V 5 U
62 BC BE V V V V V 5 U
63 BC BF V V V V V 5 U
64 BD BE V V V V V 5 U
65 BD BF V V V V V 5 U
66 BE BF V V V V V 5 U
67 CA CB V V V V V 5 U
68 AA CA V V V V 4 U
69 AA CB V V V V 4 U
70 AB CA V V V V 4 U
71 AB CB V V V V 4 U
72 AC CA V V V V 4 U
73 AC CB V V V V 4 U
74 AD CA V V V V 4 U
75 AD CB V V V V 4 U
76 AE CA V V V V 4 U
77 AE CB V V V V 4 U
78 AF CA V V V V 4 U
79 AF CB V V V V 4 U
80 BA CA V V V V 4 U
81 BA CB V V V V 4 U
82 BB CA V V V V 4 U
83 BB CB V V V V 4 U
84 BC CA V V V V 4 U
85 BC CB V V V V 4 U
86 BD CA V V V V 4 U
87 BD CB V V V V 4 U
88 BE CA V V V V 4 X
89 BE CB V V V V 4 X
90 BF CA V V V V 4 X
91 BF CB V V V V 4 X
32
30. Make diagrams in Microsoft Visio ARC Tables ARC based on a case study sheet.
33
32. Make a worksheet, fill the relationship column of each facility with the number of the facility on the worksheet sheet that have a relation
between each other facility.
Table 36 Office Facilities Worksheet
Relation Degree
No Initial Facility
A (1) E (0.8) I (0.6) O (0.4) U (0.2) X (0)
1 AA Office Table 1 2,3,4,5 6,7,8,9,10,11,12 - - 13,14 -
2 AB Office Table 2 1 3,4 5,6,7,8,9,10,11,12 - 13,14 -
3 AC Office Table 3 1 2 4,5,6,7,8 9,10,11,12 13,14 -
4 AD Office Table 4 1 2 3 5,6,7,8,9,10,11,12 13,14 -
5 AE Office Table 5 1 - 2,3 4,6,7,8,9,10,11, 13,14 -
6 AF Office Table 6 - 1 2,3 4,5 7,8,9,10,11,12,13,14 -
7 BA Office Chair 1 - 1 2,3 4,5 6,8,9,10,11,12,13,14 -
8 BB Office Chair 2 - 1 2,3 4,5 6,7,9,10,11,12,13,14 -
9 BC Office Chair 3 - 1 2 3,4,5 6,7,8,10,11,12,13,14 -
10 BD Office Chair 4 - 1 2 3,4,5 6,7,8,9,11,12,13,14 -
11 BE Office Chair 5 - 1 2 3,4,5 6,7,8,9,10,12 13,14
12 BF Office Chair 6 - 1 2,3 3,4 5,6,7,8,9,10,11 13,14
13 CA Storage 1 - - - - 1,2,3,4,5,6,7,8,9,10,14 11,12
14 CB Storage 2 - - - - 1,2,3,4,5,6,7,8,9,10,13 11,12
34
33. Make Area Allocation Diagram (AAD)
6,7,8,9,10,11,1
2,3,4,5 - 1 3,4 5,6,7,8,9,10,11,12
2
- 13,14 - - 13,14 -
1 2 4,5,6,7,8 1 2 3
1 - 2,3 - 1 2,3
- 1 2,3 - 1 2,3
- 1 2 - 1 2
- 1 2 - 1 2,3
- - - - - -
13 CA Storage 1 14 CB Storage 2
1,2,3,4,5,6,7,8, 1,2,3,4,5,6,7,8,
- 11,12 - 11,12
9,10,14 9,10,13
35
34. Input Area Allocation Diagram of manufacture is a worksheet. In this AAD proximity to the appropriate level of interest seen in
color.
Result AAD
14
-
-
1,2,3,4,5,6,7,8,
9,10,13
CB
-
Storage 2
11,12
-
Figure 11 Office Facilities AAD Result
36
35. Make the list of facilities including production floor and additional facilities, then make
an Initial layout that has been adapted to Area Allocation Diagram (AAD).
37
References
Apple, J. M. (1990). Tata Letak Pabrik dan Pemindahan Bahan. Bandung: Penerbit ITB.
Muther, R. (1973). Systematic Layout Planning (Cahners Books ed.). Boston.
White, J. A. (1992). Facility Layout and Location .