0% found this document useful (0 votes)
42 views

Keywords

Uploaded by

engomar84.oo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views

Keywords

Uploaded by

engomar84.oo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 23

PMP

Project Management
Professional
Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®)

1
PMP Keywords
•If the communication styles are changed:
•Action: Update the communication management plan.
•If the SPI is 0.5 and the CPI is 1.25:
•Assessment: The project is behind schedule.
•Action: Additional experienced resources can be added.
•If a planned activity becomes more complex:
•Action: Cross-functional team members work together to complete the activity.
•Two options to initially address an obstacle:
•Actions: Conduct a root cause analysis and schedule a retrospective.
•If a team member is unhappy with the complexity of tasks:
•Action: Set up team-building activities to reduce tension.
•A focus group and brainstorming sessions:
•Purpose: Used to gather more details about the project scope.
•If the Product Owner (PO) is confused about how to start delivering functionalities:
•Action: The PM coaches the PO on how to create a product backlog.
•If the project involves different countries:
•Action: Conduct a stakeholder analysis to identify how regional policies may influence needs.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
• WBS Dictionary:
•Definition: Provides detailed information about each component in the Work Breakdown Structure (WBS).
• Variance Analysis:
•Purpose: Compares the baseline to the actual results.
• Trend Analysis:
•Purpose: Examines project performance over time.
• WBS (Work Breakdown Structure):
•Definition: Hierarchical decomposition of the total scope of work.
• Verified Deliverables:
•Responsibility: Verified by the Quality Control Team.
• Accepted Deliverables:
•Responsibility: Accepted by the customer or sponsor.
• Analogous Estimate:
•Definition: Uses historical data; suited for limited information; less accurate.
• Parametric Estimating:
•Definition: Uses historical data combined with project parameters.
• Bottom-up Estimating:
•Definition: Estimates cost by using the WBS components.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
• Critical Path Method:
•Purpose: Determines the minimum project duration.
•Key Feature: Longest path with zero total float.
• Resource Leveling:
•Definition: Adjusts start and finish dates based on resource constraints.
•Impact: May change the original critical path.
• Resource Smoothing:
•Definition: Adjusts activities in the schedule model without changing the critical path.
• Fast Tracking:
•Definition: Activities are performed in parallel to reduce project duration.
• To make the sprint planning meeting more productive, you need two pieces of
information:
•Information: Product backlog and sprint goal.
• Tools the PM can use to influence clients' decision to keep the project active:
•Tools: Cost-benefit analysis and multi-criteria decision making.
•During daily meetings, if a team member wants to express issues:
•Action: The PM should have a confidential discussion with the team member to identify
the root cause.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
• If the PM wants to motivate the project team's performance:
•Action: Award certificates of appreciation to encourage the team.
• If a junior staff member is unfamiliar with what is expected of them:
•Action: Instruct the new team member to review the RACI matrix.
• SWOT Analysis:
•Purpose: Used to identify the risks.
• To keep delivering value:
•Action: Prioritize the product backlog, focusing on high business value and low effort items.
• If stakeholders disagree on the project objectives:
•Action: Break down the situation to identify the root causes of the disagreement.
• If a new team member is unable to complete the deliverables on time:
•Action: Address the lack of performance by coaching the new team member.
• If a key team member lacks the required skills for key tasks:
•Action: Update the issue log to account for the lack of qualifications.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
• The project escalation policy:
• Definition: It is a part of the communications management plan.
• If a team member's performance is continuously improving:
• Action: Appreciate this team member's performance throughout the project life cycle (PLC).
• If five agile teams are working together on a product:
• Action: Perform a Scrum of Scrums on a regular basis.
• The project manager should always:
• Action: Promote collaboration to help remove obstacles for the team.
• If a new technology will be implemented in the organization:
• Action: The project manager should start a SWOT analysis.
• Execute as a Scrum project when:
• Condition: The requirements are evolving, and the scope is kept flexible.
• If a project team member increases the scope without approval:
• Action: The PM should evaluate the impacts of the changes.
• If the vendor informs that a core component cannot be shipped on time:
• Action: The PM should review and update the issue log.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
• Examples of impediments:
• A team member discussing a user story not on the Scrum board.
• Lack of team empowerment.
• A technology blocking agile capabilities.
• Ishikawa diagram and Five Whys:
• Purpose: Used to determine the underlying reasons that lead to a problem.
•Cause-and-effect diagrams:
•Purpose: Identify the main or root cause of a problem.
•Scope creep:
•Definition: Uncontrolled expansion to product or project scope without proper
approval.
•SWOT Analysis:
•Components: Strengths, Weaknesses, Opportunities, and Threats.
•Prompt List:
•Purpose: Used to identify potential risks.
•Tornado Diagram:
•Purpose: Identifies risks with the most potential impact on project outcomes.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Escalate:
•Action: Used when a threat is outside the project manager’s authority and scope.
•Escalation Levels: Program or portfolio level.
•Avoid:
•Action: Eliminate the threat by changing project strategies (e.g., extending schedules or reducing scope).
•Transfer:
•Action: Shift the impact of a risk to a third party.
•Examples: Insurance or contracts (e.g., fixed-price contracts).
•Mitigate:
•Action: Reduce the probability of occurrence or impact of a risk.
•Examples: Conduct additional tests or develop prototypes.
•Accept:
•Action: Acknowledge the risk and monitor it periodically without immediate action.
•Crashing:
•Definition: Shortening the schedule by adding additional resources or working overtime.
•Changes in Agile:
•Definition: Incorporated in real time during delivery.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Leadership:
•Definition: The project manager communicates the vision to the team and inspires them.
•Emotional Intelligence:
•Definition: The PM manages team emotions and encourages individuals to manage their own emotions.
•Conflict Management:
•Scenario: When two team members disagree, the PM steps in to mediate.
•Problem Solving:
•Purpose: Focuses on finding a long-term resolution to an issue.
•Power/Interest Grid:
•Purpose: Used for classifying identified stakeholders based on their level of power and interest.
•Business Case:
•Purpose: Provides the reasoning and justification for authorizing the project.
•Stakeholder Register:
•Contents: Includes stakeholders' roles and contact details.
•Stakeholder Engagement Plan:
•Focus: Addresses relationship problems with stakeholders.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Communication Management Plan (Information Problems):
•Purpose: Deals with challenges related to communication.
•Communication Management Plan (Escalation/Confidential Information):
•Purpose: Details escalation policies and how to manage confidential
information.
•Fixed Price Contracts:
•Risk: Placed on the seller.
•Cost-Plus Contracts:
•Risk: Placed on the buyer.
•Cost Plus Incentive Fee (CPIF) Contracts:
•Feature: Includes a sharing ratio between buyer and seller.
•Develop Team:
•Components: Recognition and rewards, training.
•Corrective Action:
•Purpose: Realigns performance to bring it in line with the plan.
•Preventive Action:
•Purpose: Ensures future performance is aligned with the project
management plan (PMP).

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Defect Repair:
•Purpose: Modifies a nonconforming product to meet requirements.
•Business Case:
•Purpose: Justifies the initiation of the project.
•Lessons Learned:
•Purpose: Documents reasons for project success and failure.
•Prototype:
•Purpose: Used for risk mitigation.
•Change Log:
•Purpose: Records all change requests, whether approved or rejected.
•Balanced Matrix:
•Definition: Power is shared between the project manager (PM) and the functional manager.
•PMO - Supportive:
•Degree of Control: Low.
•Purpose: Supplies templates, best practices, and training.
•PMO - Controlling:
•Degree of Control: Moderate.
•Purpose: Provides support and requires compliance.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•PMO - Directive:
•Degree of Control: High.
•Purpose: Directly manages projects.
•Stakeholder Engagement Assessment Matrix:
•Purpose: Compares the current and desired engagement levels of stakeholders.
•Responsibility Assignment Matrix (RAM):
•Purpose: Shows the connection between work packages or activities and team members.
• Video Conferencing:
•Purpose: Used for negotiations.
• Chat Rooms:
•Purpose: Used for team discussions.
• Online Boards:
•Purpose: Used to share routine information.
• Version Control System:
•Purpose: Used to manage project deliverables.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
• Political Awareness:
•Scenario: PM stays updated on government instability to address potential impacts.
• Cultural Awareness:
•Scenario: PM works in a rural area where people have different customs and adapts accordingly.
• Decision Making:
•Scenario: PM is given a chair position to reform government policies.
• Negotiations:
•Scenario: PM faces complaints from site workers but is unable to improve conditions due to
constraints.
• Forming Stage (Team Development):
•Behavior: Team members are independent and work in silos.
• Storming Stage (Team Development):
•Behavior: Team members argue and lack open collaboration.
• Norming Stage (Team Development):
•Behavior: Team members adjust their work habits and build trust.
• Performing Stage (Team Development):
•Behavior: Team members work independently and effectively.
• Adjourning Stage (Team Development):
•Behavior: Team members are reassigned to other projects after completion.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Sprint Planning:
•Purpose: Discuss the goal for the iteration.
•Daily Meeting/Standup:
•Purpose: Discuss the development flow.
•Iteration Review:
•Purpose: Determine whether backlog items are completed.
•Iteration Retrospective:
•Purpose: Identify what to continue, stop, or start doing.
•Product Owner:
•Role: Assign acceptance criteria and set goals.
•Scrum Master:
•Role: Discuss inter-dependencies with other projects.
•Servant Leader:
•Role: Assume leadership as needed to support the team.
•Requirements in Predictive:
•Definition: Defined upfront before the development team begins work.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Requirements in Agile:
•Definition: Elaborated frequently throughout delivery.
•Changes in Predictive:
•Management: Constrained as much as possible.
•Risk and Cost in Predictive:
•Control Mechanism: Managed through detailed planning.
•Risk and Cost in Agile:
•Control Mechanism: Managed as requirements and constraints emerge.
•Key Stakeholders in Predictive:
•Involvement: Participate at specific milestones.
•Key Stakeholders in Agile:
•Involvement: Continuously engaged throughout the project.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Work Breakdown Structure (WBS):
•Hierarchical decomposition of the total scope of work into smaller, manageable parts.
•WBS Dictionary:
•Provides detailed information about each WBS component.
•Scope Creep:
•Uncontrolled expansion to the project or product scope without proper approval.
•Risk Management Strategies:
•Avoid: Eliminate the risk.
•Mitigate: Reduce the probability or impact.
•Transfer: Shift the risk to a third party.
•Accept: Acknowledge the risk and monitor.
•Critical Path Method (CPM):
•Determines the minimum project duration and identifies the longest path with zero total float.
•SWOT Analysis:
•Evaluates Strengths, Weaknesses, Opportunities, and Threats.
•Stakeholder Engagement Assessment Matrix:
•Compares current engagement levels to desired levels for stakeholders.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Agile Principles:
•Focus on customer collaboration, responding to change, and delivering working software
iteratively.
•Burndown Chart:
•Tracks the remaining work in a sprint.
•Cost Management Techniques:
•Analogous Estimating: Uses historical data for estimates.
•Parametric Estimating: Uses historical data with parameters.
•Bottom-Up Estimating: Aggregates cost estimates of individual work packages.
•Communication Management Plan:
•Defines how information will be distributed, including escalation paths and managing
confidential information.
•Earned Value Management (EVM):
•Key Metrics:
•SPI (Schedule Performance Index): EV/PV.
•CPI (Cost Performance Index): EV/AC.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Lessons Learned Register:
•Documents reasons for success or failure to improve future projects.
•Five Process Groups:
•Initiating: Define the project.
•Planning: Establish scope, objectives, and procedures.
•Executing: Complete the work.
•Monitoring and Controlling: Track and manage progress.
•Closing: Finalize all activities.
•Servant Leadership:
•A leadership style focused on empowering the team to achieve project goals.
•Ishikawa Diagram (Fishbone Diagram):
•Identifies root causes of problems.
•Integrated Change Control:
•Evaluates and manages change requests throughout the project lifecycle.
•Earned Value Terms:
•EV (Earned Value): Value of work completed.
•PV (Planned Value): Planned budget by a specific time.
•AC (Actual Cost): Cost incurred by a specific time.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Types of Contracts:
•Fixed Price: Risk on seller.
•Cost Plus: Risk on buyer.
•CPIF (Cost Plus Incentive Fee): Includes a sharing ratio.
•Conflict Management Techniques:
•Collaborating: Win-win.
•Compromising: Partial satisfaction for all.
•Avoiding: Withdrawing temporarily.
•Forcing: Imposing a solution.
•Accommodating: Sacrificing own interests.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•PERT (Program Evaluation and Review Technique):
•Uses three-point estimates: Optimistic, Pessimistic, and Most Likely, with the formula:

•Monte Carlo Simulation:


•A quantitative risk analysis technique to assess impact and probability using computer models.
•Affinity Diagram:
•Organizes a large number of ideas into groups for analysis.
•Pareto Chart:
•A histogram that shows factors arranged by frequency, following the 80/20 rule (80% of problems are caused
by 20% of causes).
•Fishbone Diagram (Ishikawa Diagram):
•Visualizes root causes of a problem.
•Five Whys Technique:
•A tool to determine the root cause of an issue by asking "Why?" five times.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Responsibility Assignment Matrix (RAM):
•Defines who is responsible, accountable, consulted, and informed (RACI) for project tasks.
•Control Charts:
•A quality management tool to monitor process stability and performance over time.
•Flowcharts:
•Visual representations of processes to identify inefficiencies and risks.
•Scatter Diagrams:
•Display relationships between two variables to identify correlations.
•Histogram:
•Displays data distribution over a continuous interval, useful for identifying variations.
•Stakeholder Engagement Assessment Matrix:
•Compares the current vs. desired engagement levels of stakeholders.
•Tornado Diagram:
•A sensitivity analysis tool to identify risks with the greatest potential impact.
•Earned Value Management (EVM):
•Measures project performance using metrics like Schedule Variance (SV) and Cost Variance (CV).
•Gantt Chart:
•A bar chart for project scheduling that displays task dependencies and timelines.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
PMP Keywords
•Critical Path Analysis:
•Identifies the sequence of tasks that determines the project's minimum duration.
•Decomposition:
•Breaks down deliverables into smaller, manageable work components, used in WBS creation.
•Benchmarking:
•Compares project processes or performance with industry standards.
•Check Sheets:
•Used for data collection and analysis to ensure all required steps are completed.
•Context Diagrams:
•A tool used to visually depict the scope of a system, showing interactions between elements.

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share
‫ يوم فقط من هنا‬21 ‫•تقدر تطلع علي خطة المذاكرة واالعداد لالمتحان في‬
https://www.youtube.com/watch?v=yBPOEk7jCp0

‫ ايام فقط من هنا‬3 ‫•تقدر تشترك معانا في الكورس وتحصل علي خصم كبير لمدة‬
https://civilacademy.net/course/pmp-full-package/

‫• تقدر تدرب مجانا علي االمتحان من هنا‬


https://civilacademy.net/course/pmp-exams-examples-free/

‫• تقدر تنضم لجروبنا علي التليجرام من هنا‬


https://t.me/+y8im4uTVAYUzNGQ0

Dr.Abdallh Mostafa (MSc, PhD, PMP®, P3O®,PMO-CP,RMP) All Rights Reserved – Don’t Share

You might also like