Project Planning and Management_27 Nov. 2024
Project Planning and Management_27 Nov. 2024
contract administration
team building
2. Final exam………………………………………40%
4
Course Assessment
Individual Term Paper: Article Review (a maximum of 10 pages): This
requires critically reviewing a journal article on topics related Project
Management. The following sections could be included in the review:
Research Problem/Research Questions and/hypotheses
Conceptual Framework Used
Research Methods
Results/Findings and Discussions
Contributions of the article
General Critique
In this section you should state your opinions of how well (or
poorly) the authors did their research, and presented the
research results in the article.
Your critique can contain both positive and negative
comments.
Justify and explain in detail each of your critique points in a
separate paragraph. 5
Course Assessment-Cont’d
Writing format!
6
Risk?
An uncertain event or condition that, if
it occurs, has a negative or positive effect
on the project objectives.
Examples on threats: bad weather, inflation,
high project team turnover.
It’s common to think that all risks are threats, but the term
Inherent
Uncertainty
Financial risk
Technology risk
People risk
Structure/process risk
14
Risk Assessment/Analysis
2. 1. Performing Qualitative Risk Analysis
2.2. Performing Quantitative Risk Analysis
(probability/impact matrix )
Evaluation of Impact
Scale of Probability
Example
• Note that the zones are not symmetrical across the matrix
– High impact low probability events much more important than likely low
impact events
Performing Quantitative Risk Analysis
18
Expected Monetary Value (EMV)..Cont’d
Examples include:
Completing more tests on the project work before
implementation
Developing prototypes, simulations, and limited
releases
Managing the Positive Risk and Opportunities
Enhancing: Example 1
Suppose you’re constructing a school building, and suddenly
the client tells you that if you complete the job two months
earlier than planned, the client will give a monetary reward.
Therefore, you take several measures to realize the opportunity.
You utilize crashing.
You’re only trying to complete the project early to gain the
opportunity; i.e. you are only increasing the
probability of completing the project early;
There is no guarantee you will realize the
opportunity.
Managing the Positive Risk and Opportunities__ Cont’d
Enhancing: Example 2
For example, let’s say your project will be completed in three
months. You find out that the government is about to float a
similar type of project in two months. Therefore, if you are able
to complete your project in two months, you can bid for a new
project.
warranted.
Monitoring and Controlling Project Risks
project.
project participants.
team meeting.
Group exercise
Identify one viable project idea (give a name for this
project)
Generate a list of possible risks (about 5 risk events)
through brainstorming
Prioritize these risks by “probability*impact” index
By using your own hypothetical figures
Prepare a project risk severity matrix, and
Compute EMV
44
The responsibility for implementing
the project is usually entrusted with
an implementation team.
50
PROJECTS – PITFALLS AND LESSONS OF
EXPERIENCE
Why Projects Fail
Projects particularly construction Projects, in many
instances, face problems owing to:
cost overruns or schedule slippages; and
ended with below their standards in terms of quality &
performance.
Project Organization
Advantages Disadvantages
1. No Structural Change 1. Lack of Focus
2. Flexibility (for 2. Poor Integration
utilization of experts
and resources) 3. Slow decision
3. In-Depth Expertise
making
5. Easy Post-Project
Transition
Pure Project Organization/projectized organization
Characteristics
is a specialized organization for executing projects.
with a strong focus on the project.
The organization’s lifespan is equal to the lifespan of the
project.
a small, self-sufficient and full-time team is set up.
The team leader is like an entrepreneur.
Leader has full responsibility over the project.
Functional units are stable, provide support to
project teams.
One functional unit (transport, finance, HRM…) for all
projects or one functional unit for each of the projects.
The Project Organization
Advantages of pure project
Clear authority & responsibility: PM with full project
authority
Disadvantages
High bureaucratic costs
High costs (time and money) for building relationships
Higher potential for conflict :Two-boss employee’s role
conflict
Different Matrix Forms
Weak Form
The authority of the functional manager predominates
and the project manager has indirect authority.
Strong Form
The project manager has broader control and
functional departments act as subcontractors to the
project.
Balanced Form
The project manager sets the overall plan and the
functional manager determines how work to be done.
Exercise
Group 1: Identify the strengths & weaknesses of functional form of project
organization
GROUP 4:
Share your experiences about the ‘dominant form of a project organization’ in the
work place
Show by organogram (organizational chart)
Mention some considerations in choosing the appropriate project structure.
GROUP 5:
Share your experiences about the ‘dominant form of a project organization’ in the
work place
Show by organogram (organizational chart)
Mention some considerations in choosing the appropriate project structure.
Project Implementation Plans
Project plans are considered to consist of three
fundamental “dimensions”:
scope: what is to be done
time: how long it will take to execute
work—individually and as a total project
cost: how much money that will be spent
and how it’s budgeted over time
Project Planning and Scheduling
Work-breakdown structure
What activities do we need to do?
Gantt chart
Network Techniques
When will we do each activity?
Identifying How Long It Will Take to Do
Everything (Time Management)
Work breakdown structure (WBS)
Each project is complex:
many gradual steps and its objective is achieved by means
of a number of outputs delivered by the project team.
The WBS tool is used to decompose the whole into
smaller parts that will be easier for the team to plan and
manage.
A Work Breakdown Structure (WBS) is a simple, tool used
to quickly and concisely define the activities required to
complete a project.
A visual depiction of work to be performed.
Work breakdown structure (WBS)-
Cont’d
A work breakdown structure describes the components
and subcomponents of the project’s various work
products as a “family tree.”
It represents a systematic and logical breakdown of the
project into its component parts.
House
project
Layout Concrete
Excavation
topography pour
Establishing Project Implementation Schedule
Implementing even the simplest project requires
completing a number of tasks that have to be
undertaken in a particular sequence and with a
particular set of inter-relations.
Milestones
A. Clear Site
B. Level Site
C. Excavate Foundation
D. Lay Reinforcement
E. Pour Concrete
F. Order Re-Bars
G. Cut & Bend Re-Bars
H. Order Cement
I. Order Aggregates
The advantages of the a Gantt chart are:
It is simple to understand
activities Y and Z have to wait until the task X is ready. In this case
activity Y and activity Z can be done in parallel (to save time).
The activity X is called burst activity because more than one arrow
bursts from its node.
Activity On Node Network Techniques
Task A Task K
Task B Task L
Errors in Logic
Looping
Due to a mistake in drawing or to errors in
identifying dependent activities
P Q
R
Errors in Logic
Dangling
Usually occur when activities are added as an
afterthought
Can be avoided by using a single finish node
K
K LL Finish
M M
Dummy activity: an activity that
does not consume time or
resources.
It shows merely the dependencies
or proper relationship between
activities.
A dotted arrow represents
dummy.
Upper left….
To answer:
What is the total time to complete the project?
What are the scheduled start and finish dates for
each specific activity?
Which activities are critical and must be completed
exactly as scheduled to keep the project on
schedule?
How long can noncritical activities be delayed
before they cause an increase in the project
completion time?
Basic steps in Network diagram----CPM
Step 1: Define activities
The project & all of its significant activities or tasks
Efficient tool: WBS
The WBS represents a logical decomposition of the work to be
performed
(Example: What are the activities that are needed to
build a house? to conduct a research?)
Finding these activities is a brainstorming activity
Key questions:
what is the expected duration of the project?
What are the earliest start and finish dates for each activity?
What are the latest start and finish dates for each activity that does
not interfere with the project completion time?
Critical Path –
– The series of activities all of which must
finish on time for the whole project to finish
on time
– Sometimes described as the longest path
through a network, hence the shortest
project time
Computing Critical Path
Calculate the Forward Pass by adding the
durations along each path in your network:
to establish the earliest start (ES) and finish (EF) dates
for each activity
4 F 7
0 A 2 2 C 4 10 3 13 EF
0 2 2 2 2 4
ES
13 H 15
4 E 8
B 13 2 15
0 3 3 D 7 4 4 8
1 LS
3 4 4 4 8
LF
8 G 13
critical path
8 5 13
122
Exercise 2: Cables By M company is bringing a new product on line to be manufactured in
their current facility in some existing space. The owners have identified 11 activities and
their precedence relationships. Develop an AON for the project & determine project
123
completion time
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
Feedback
124
Calculate the Path Completion Times
….Reading Assignment…
Managing Your Projects with Software
The best project management tool in the world can
never replace your good judgment.
However, the tool can and should help you accomplish
the following:
Track all the information you gather about the work,
duration, costs, and resource requirements for your project.
Visualize and present your project plan in standard, well-
defined formats.
Schedule tasks and resources consistently and effectively.
128
Contents of a contract
Name and address of both the parties,
Subject of the agreement,
Deadlines for the different stages of fulfillment of
the agreement,
Financial aspects and other necessary conditions
such as violation of contract etc.
129
Approaches to contracting:
Contracting total responsibility for one
contractor
Dividing the project and contracting it to suitable
suppliers and contractors.
130
Contracting procedures:
Governments and different institiutions have
their own procedures with clear
objectives to acheive:
To elicit competitive bids
To provide equal opportunity and
equal treatment to all eligible
tenderers
To accept the tender at the lowest
cost
131
Steps in contracting :
1. Work packaging and scheduling
Specialized Activity Packages like
construction, civil engineering works,
painting etc.
Unit packages like administration building,
by - product plant, steel melting shop etc.
The starting and finishing time of each
individual package
132
2. Preparation of Tender Documents
Instruction to tenderers
Model Form of tender
Drawings and specifications
Schedule of Rates
General conditions of contract
Special conditions of contract
Specimen of Bank guarantee
133
3. Determination of Contractor's Qualifications
World Bank's criteria :
Factors Points
Organization and Planning 10
Management Structure
General Implementation programme
Plans for subcontracting
History of Default
134
Personnel 15
Experience/ qualification of key personnel
Adequacy of specialized staffing
135
Experience
30
Technical references
Value of completed contracts of similar type
Average percent of work under subcontractor
Financial Condition 30
Bank reference
Average annual turnover
Working capital
Quick Ratio
Value of contracts completed in last 5 years
136
4.Tender Invitation
Sending equerry letters for short lists or
Advertising openly
5.Tender submission
Tender is usually submitted in sealed
envelops
The required number of copies together with
documents will be submitted by tenderers on or
before the last date for submission
137
6.Tender Opening
Tenders should be opened in the
presence of tenderers or their
authorized representatives unless
required
7. Evaluation and recommendation
Costs, quality, quantity and other
technical specification
138
8. Award of contract
Technical capacity
Lowest price
Negotation
139
Team Building and Conflict Management
Goal-setting
Role-clarification/definition
Interpersonal processes
Problem solving
Team building techniques _ cont’d
Goal-setting
clarifying for the team members the general goals and
specific objectives of the project,
establishing timetables.
***********************************
The result of good leadership & good team building is
teamwork.
Team building-Cont’d: Conclusion
The result of good leadership & good team
building is teamwork.
Question for reflection
For example:
was equipment available as planned, are activities on time (as
mapped in the work plan),
are the outputs produced on schedule?
153
EVALUATION
• Assessing whether a project is achieving
its intended objectives
• Conducted periodically
• Internal or external
• Focuses on outcomes and impacts
• It makes comparison of the outcomes
of the project with planned ones.
What’s the difference?
Monitoring Evaluation
Timing Continuous, throughout Periodically at significant points
the project in the project: mid-term or end
of project are most common
Scope Day to day activities Assess overall delivery of
activities and progress towards
achieving aim and objectives
Main participants Project staff and project External evaluators/facilitators,
users project users, project staff,
donors
Reporting formats Regular reports and Written report with
updates to project users, recommendations for changes to
management and donors project
160
Project close-out
What is close out?
future projects
169
Key Elements in a Project Closure-Cont’d
Verify acceptance of final project deliverables
This means that the project product or output has been delivered and
transitioned (handed over) to the appropriate party.
this step signifies that the customer agrees that the scope
of the project and its deliverables are complete and were
delivered as agreed upon by all parties (customer, the
project sponsor, the project steering committee, etc.).
Acceptance is based upon the success criteria defined in
the initiating and planning phases of the project.
should be formal:
physical sign-offs should be obtained by the customer, the
project sponsor, the project steering committee, as appropriate.
170
Key Elements in a Project Closure-Cont’d
Conduct post-project assessment and lessons
learned
Lessons learned should draw on both positive experiences
& negative experiences
The lessons learned session is typically a meeting that
includes:
Project team
Stakeholders representation including external oversight,
auditors,..
Executive management
Project support staff
171
Key Elements in a Project Closure-Cont’d
Conduct post-project assessment and lessons learned-Cont’d
discussion questions in the lessons learned session should include:
Did the delivered product meet the specified requirements and goals of
the project?
Was the customer satisfied with the end product(s)? If not, why not?
Was budget pan meet? If not, why not?
Was the schedule meet? If not, why not?
Were risks identified and mitigated? If not, why not?
Did the project management methodology work? If not, why not?
What bottlenecks or challenges were experienced?
What can be done in future projects to facilitate success?
Lessons learned and comments regarding project assessment
should be documented, presented, and openly discussed with
the intent of eliminating the occurrence of avoidable issues on
future projects.
172
Key Elements in a Project Closure-Cont’d
Conduct post-project assessment and lessons learned-
Cont’d
In summary:
what aspects of the project went right,
What went wrong and ,
173
Key Elements in a Project Closure-Cont’d
Conduct post-project review and evaluation
this provides a record of the history of a project
provides a written documentation of the planned and actual
budget, the baseline and actual schedule, documents
recommendations for other projects of similar size and scope.
Should include the following items:
project organization including staffing and skills
WBS, schedules
Successful risk assessment and mitigation techniques, e.g. what risks
occurred and what techniques were used to mitigate these risks.
General techniques for project communication
General techniques for managing customer expectations
Financial data
Project environment/culture
Lessons learned
Recommendations to future project managers
Final project report
174
Key Elements in a Project Closure-Cont’d
Recognize and celebrate outstanding project work
provide some positive reinforcement to the teams and
individuals when a project is completed successfully.
EX. By praising the team at a key meeting or a large
gathering of staff.
Such recognition is a motivation to other projects to be
successful.
175
Key Elements in a Project Closure-Cont’d
Disburse project resources-staff, facilities & automated
systems
Staffing decisions
Retain and reassign to different projects
Terminate – benefits, severance
Return borrowed equipments
176
Key Elements in a Project Closure-Cont’d
Complete and archive final project records
Historic project data is an important sources of information to
help improve future projects.
All records (both soft copy and hard copies) should be stored.
177
Key Elements in a Project Closure-Cont’d
178
Key Points _ Summary
Thank you