0% found this document useful (0 votes)
5 views

New Microsoft Word Document

Uploaded by

ishfaqdirvi0313
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

New Microsoft Word Document

Uploaded by

ishfaqdirvi0313
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Building Work Items Description

Grey Work
1. Excavation and Earthwork
o Site clearance and leveling
o Excavating trenches for foundations
o Earth backfilling and compaction
2. Termite Proofing
o Under Footings (strip, raft, isolated, combined)
o All Wood Work
3. Foundation Work
o Footings (strip, raft, isolated, combined)
o Concrete for foundation walls and slab
o Damp-proofing membrane
4. RCC (Reinforced Cement Concrete) Work
o Concrete pouring for beams, columns, and slabs
o Reinforcement (steel bars)
o Formwork for casting concrete structures
5. Masonry Work
o Brickwork or blockwork for walls (both load-bearing and partition walls)
o Stone masonry work
o Pointing and jointing of walls
6. Plinth and Flooring
o Base floor slab (ground floor)
o Concrete flooring (temporary or rough)
7. Structural Steelwork
o Steel beams, columns, and girders
8. Water Proofing
o Waterproofing (if part of the structural work)
9. Shuttering/Formwork and Scaffolding
o Shuttering for casting concrete (walls, slabs, beams)
o Scaffolding for safe working at heights during construction
10. Drainage and Sewage Lines
o Installation of main sewage and pipes
o Trenches for underground pipelines
11. Electrical & Plumbing Rough-In
o Laying of electrical conduits
o Plumbing and drainage pipes embedded within walls or floors
Finishing Work
1. Plastering and Rendering
o Internal wall plastering (cement or gypsum)
o External wall rendering (with smooth or textured finish)
o False ceiling installation (gypsum board, POP, etc.)
2. Flooring and Tiling
o Floor tiles (ceramic, porcelain, marble, etc.)
o Wall tiles (bathrooms, kitchen backsplashes)
o Hardwood flooring or laminate or Vinyl flooring
o Polishing of concrete floors
3. Painting and Polishing
o Wall painting (distemper, emulsion, enamel)
o External surface painting (weatherproof)
o Wood polishing for doors, windows, and furniture
o Metalwork painting (railings, gates)
4. Window and Door Installation
o Fitting of doors (wooden, UPVC, or metal)
o Fitting of windows (wood, aluminum, or UPVC)
o Door hardware (handles, locks, hinges)
5. False Ceiling & Acoustics
o Installation of false ceilings (gypsum, metal, or acoustic panels)
o Acoustic treatments (soundproofing)
6. Joinery and Carpentry
o Woodwork for windows, doors, and cupboards
o Custom carpentry for wardrobes, shelves, and furniture
7. Sanitary Fittings
o Installation of toilets, sinks, bathtubs, showers, and faucets
o Installation of mirrors, shower doors, and other bathroom accessories
8. Electrical Work (Final)
o Wiring of lights, fans, and other electrical fixtures
o Switchboards, sockets, and plugs
o Installation of light fittings, chandeliers, and ceiling fans
o Installation of air-conditioning systems
9. Plumbing Fittings (Final)
o Fitting of water tanks, taps, and valves
o Connection of sewer lines to the main network
o Installation of water meters and filtration systems
10. Exterior Works
o Landscaping (gardens, lawns, flower beds)
o Paving for pathways, driveways, and external flooring
o Fencing or boundary walls
11. Glass and Glazing
o Installation of glass windows, doors, and curtain walls
o Glazing for external facades and skylights
o 1. Gray Work (Structural Work / Rough Construction)
o 1.1 Site Preparation
o Site Survey and Layout: Survey the land, mark the boundaries, and set out
the foundation lines.
o Site Clearing: Remove trees, shrubs, rocks, and other obstructions from the
site.
o Excavation: Dig the site for foundations, trenches for utilities, septic tanks,
and other structures.
o 1.2 Foundation Work
o Excavation for Foundation: Digging trenches for foundation footings or pits
for deeper foundations.
o Pouring of Concrete for Footings: Laying a concrete base for foundation
walls or footings.
o Reinforcement of Foundation: Placing reinforcement steel bars (rebar) in
foundation footings.
o Damp Proofing: Applying a damp-proof membrane to prevent water
penetration into the foundation.
o Curing: Allowing the concrete foundation to set and cure before proceeding
to the next step.
o 1.3 Sub-Structure and Basement Work
o Basement Excavation: Digging for basement construction if required.
o Basement Slab & Wall Construction: Pouring concrete for the basement
floor and walls.
o Waterproofing Basement Walls: Applying waterproofing materials to
basement walls to prevent moisture.
o 1.4 Superstructure Construction
o Plinth Beam Construction: Laying beams at plinth level to provide support
to the walls above.
o Column and Beam Work: Constructing reinforced concrete columns and
beams.
o Slab Casting: Pouring concrete slabs for floors, typically using
shuttering/formwork.
o Wall Construction: Building load-bearing or partition walls using masonry
(brickwork or blockwork).
o Reinforced Concrete Slabs and Beams: Construction of additional floors by
casting RCC (Reinforced Cement Concrete) slabs and beams.
o Structural Steel Framework (if applicable): Installing steel beams,
columns, and structural trusses.
o 1.5 Roofing Work
o Roof Structure Installation: Constructing or installing roof trusses, rafters,
or steel supports.
o Roof Slab or Decking: Casting the roof slab or decking material if it's a solid
roof.
o Waterproofing Roof: Applying a waterproof membrane on the roof to
prevent water leakage.
o Roof Covering Installation: Installing roofing materials (tiles, metal sheets,
or concrete roofing slabs).
o 1.6 Rough Electrical and Plumbing Work
o Electrical Conduit Laying: Installing PVC or metal conduits for electrical
wiring inside walls.
o Plumbing Pipes Laying: Laying water supply and drainage pipes within
walls and floors.
o Sewer and Stormwater Drainage: Installing sewer lines, stormwater drains,
and waste pipes.
o Ventilation Ducts: Laying ducting for ventilation systems (if applicable).
o 1.7 Drainage and Sewage System
o Trenching and Laying Piping: Excavating trenches for laying sewage and
stormwater pipes.
o Manhole Construction: Building manholes for access to underground
drainage systems.
o 1.8 Finishing Structural Work
o Shuttering and Formwork Removal: Removing the temporary formwork
used for pouring concrete once the concrete is set.
o Backfilling: Filling the trenches and foundation with earth or other materials.
o Compaction of Soil: Compacting soil to ensure proper stability and support
for walls and floors.
o

o 2. Finishing Work (Interior/Exterior Finishes)


o After the Gray Work is completed, the Finishing Work begins. This includes
adding aesthetic details and ensuring the building is livable and functional.
o 2.1 Plastering and Rendering
o Plastering of Walls and Ceilings (Internal): Applying a layer of plaster on
internal walls and ceilings to smoothen surfaces.
o External Rendering: Applying a cement-based render or stucco to the
exterior walls for a smooth, weather-resistant finish.
o Textured Wall Finish: Applying decorative textures on walls (if required).
o 2.2 Flooring and Tiling
o Sub-floor Preparation: Leveling and preparing the sub-floor surface for
tiling or flooring.
o Tile Installation: Laying ceramic, porcelain, or stone tiles for floors and
walls.
o Grouting: Filling the gaps between tiles with grout.
o Floor Finishes: Installing final flooring materials like vinyl, laminate, wood,
marble, or terrazzo.
o Polishing: Polishing of marble, granite, or terrazzo floors to give them a
smooth and glossy finish.
o 2.3 Painting and Polishing
o Wall Painting: Applying primer and finishing coats of paint (emulsion,
distemper, or acrylic) to internal walls.
o External Wall Painting: Painting the exterior with weatherproof paint.
o Wood Polishing: Polishing wooden elements like doors, windows, and
wooden paneling.
o Metalwork Painting: Priming and painting metal parts such as gates, railings,
and steel doors.
o 2.4 Door and Window Installation
o Door Frame Installation: Fixing wooden, aluminum, or UPVC door frames.
o Fitting Doors and Hardware: Installing doors and attaching hardware
(handles, locks, hinges).
o Window Frame Installation: Installing window frames (wooden, aluminum,
or UPVC).
o Fitting Glass in Windows: Installing glass panes or glazing in windows.
o Window Accessories: Installing window locks, handles, and other
accessories.
o 2.5 Ceiling Work
o False Ceiling Installation: Installing suspended ceilings made of materials
like gypsum boards, tiles, or metal panels.
o Acoustic Treatment (if required): Installing acoustic panels for
soundproofing, especially in areas like home theaters or offices.
o 2.6 Carpentry and Joinery Work
o Wooden Fixtures Installation: Installing custom-built woodwork such as
wardrobes, shelves, cabinets, and staircases.
o Fitting Wooden Panels and Trim: Installing wooden panels, skirting boards,
and trim around doors and windows.
o Furniture Making: Crafting and installing furniture items such as cabinets,
tables, and counters.
o 2.7 Sanitary Fittings
o Toilet Fittings Installation: Installing water closets, bidets, and urinals.
o Sink and Faucet Installation: Installing washbasins, kitchen sinks, faucets,
and shower systems.
o Shower Installation: Fitting shower heads, bath enclosures, and associated
accessories.
o 2.8 Final Electrical Work
o Electrical Wiring: Pulling and connecting final electrical wiring for lights,
fans, and outlets.
o Socket and Switch Installation: Installing electrical sockets, switches, and
circuit breakers.
o Lighting Fixtures: Fitting light fixtures, chandeliers, ceiling fans, and other
electrical appliances.
o 2.9 Final Plumbing Work
o Fitting Faucets and Showerheads: Installing faucets, taps, showerheads, and
related bathroom fixtures.
o Water Tank Installation: Fitting water tanks, pressure pumps, and
connection to the water supply.
o Final Plumbing Connections: Connecting the plumbing system to the main
water supply and sewage system.
o 2.10 Exterior and Landscaping
o External Wall Finishes: Final touch-ups for the external wall finishes
(painting, rendering).
o Landscaping: Creating gardens, lawns, and flower beds.
o Pathways and Driveways: Paving walkways, driveways, and external floors
with tiles, concrete, or stone.
o Fencing and Gates: Installing boundary walls, fencing, gates, and security
features.
o 2.11 Glass and Glazing
o Glass Installation: Installing glass for windows, skylights, and facades.
o Curtain Wall Glazing: Fitting glazing panels for large external window
systems or curtain walls.
o 2.12 Final Touches and Cleaning
o Cleaning Construction Debris: Cleaning up debris, dust, and leftover
materials from the site.
o Final Inspection: Inspecting the entire building for any defects or issues,
including finishes and installations.
o Handing Over: Final walkthrough with the client and handing over the
building.