explain the basics of MRP area

Uploaded by

RP Tech
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views

explain the basics of MRP area

Uploaded by

RP Tech
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 13

The purpose of this document is to explain the basics of MRP area, steps involved in activating MRP area and

to use
it in different possible ways.

As we know MRP runs at plant level (centralized), but as per business need we may have to plan MRP for individual &
independent planning areas (decentralized). This can be achieved by activating MRP areas. These MRP areas are
fully configurable organizational units within ECC where MRP can be run individually. So we can broadly classify
running MRP in 2 major ways.

 MRP at plant level: The system adds together stocks from all of the individual storage locations to
determine total plant stock. The requirements are combined in the planning run and procurement elements
are created for these pegged requirements with unknown sources. Individual storage locations can be
planned separately or be excluded from planning.

Illustration:

 MRP area level: Only the stocks from the storage locations or subcontractor assigned to the respective
MRP area are taken into account. The requirements in this particular MRP area are combined and
procurement elements are created for them. This enables us to plan material requirements specifically for
certain areas (MRP areas).

Illustration:

You can define MRP areas within a plant and carry out MRP specifically for that particular area, for
example in above illustration, for MRP area M0001 can be planned independently without running
MRP for plant FP01.

In each MRP area you can control staging and procurement of parts that are produced in house or
externally. All MRP procedures are supported by MRP areas and one can display the result of
MRP run for each MRP area.
MRP Area (definition):

As per SAP, “MRP Area represents an organizational unit for which material requirements
planning is carried out independently”

MRP Area is functionality for special planning process that enables you to carry out planning not
only at plant level but also at different planning levels (eg, storage location & sub-contractors).
There are 3 types of MRP areas in SAP

 Plant MRP Area


 MRP Areas for storage location
 MRP Areas for Subcontractors
Plant MRP area:

MRP area can be created at plant level. On doing so, system combines all its storage locations and stock with
subcontractors under that MRP area. When you define MRP areas for storage locations and for subcontractors and
assign material to newly created MRP areas with in plant then the plant MRP area gets reduced by exactly the
numbers of subcontractors and storage locations. This is because they will now be planned separately in new MRP
areas.

MRP area for storage location:

MRP area can also be defined for storage location or multiple storage locations. Material requirements for this storage
location are then planned separately from the rest of the plant. Important point to note here is that you can assign 1
storage location to only 1 MRP area but you can have multiple storage locations under single MRP area. It’s a N to 1
relationship.

MRP Areas for Subcontractors:

You can also define an MRP area for each subcontractor. Important point to note here is that a subcontractor can be
assigned to only one MRP area in a plant. An MRP area of the subcontractor type can only contain one subcontractor.
It’s a 1 to 1 relationship.

How to setup MRP area in SAP

There are 2 aspects of setting up MRP area. First one is to activate it in customizing and second
part it to set up master data (i.e. adding materials to that particular MRP area in material master).

MRP with MRP area is not operational until you assign MRP area to a particular material in
material master or in order words create a MRP area segment. If you have not assigned a material
to an MRP area, that is, you have not created an MRP area segment in the material master, the
material will continue to be planned in the plant MRP area only.
Step 1 - Converting Planning file entries
Path: SPRO > Production > Material Requirement Planning > Master Data > MRP Areas >
Convert Planning file entries for MRP areas – OM0F or SE38 program RMDBVM00

When we convert planning file entries for MRP area, system creates plant MRP area for each plant. Following entries
from below tables are converted. Planning file entries are maintained in MRP file which are converted to MRP area file
in below tables.

Planning file entries in MDVM are converted to DBVM

Planning file entries in MDVL are converted to DBVL

Planning file entries in KDVM are converted to KBVM

Planning file entries in KDVL are converted to KBVL

If you are running converting planning files for the first time then system will automatically create
plant MRP areas. These new entries can be seen in OMIZ under plant MRP area with area type
"01".

IMP note: After the conversion, contents of MDVM/MDVL/ KDVM/KDVL are deleted and entries
are created in DBVM/ DBVL/ KBVM/ KBVL.
Step 2 - Define MRP area in SPRO - OMIZ

Path: SPRO > Production > Material Requirement Planning > Master Data > MRP Areas >
Define MRP areas

MRP area has 3 types (01, 02 & 03) and system will allow you to have MRP areas in below types only (Plant, Storage
location or Sub Contractor)

Plant MRP area should have same name as plant so you can have only one entry for plant MRP
area. For example plant 1000 will have plant MRP area as 1000.

In order to maintain consistency and uniformity, only MRP areas of the type 'plant' are allowed to
have 1-4 digits key. Sloc MRP area should have minimum of 5 digits. Example M0001 etc…
You can only have 1 sub-contractor vendor assigned to 1 MRP area. Multiple vendors cannot be
grouped together in a single MRP area.

You can have multiple storage locations combined together in a single MRP area.

You can only one entry for plant in plant MRP area. Multiple plants cannot be grouped together in
a single MRP area.

Once MRP area is defined, next step is to Activate MTP area

Step 3 - Activating MRP Areas – OM01

Path: SPRO > Production > Material Requirement Planning > Master Data > MRP Areas >
Activate MRP for MRP areas

NOTE: MRP areas are activated at client level. Once you activate it, it will be available for all plants and MRP areas
features would be available to use.

This sums up setting up MRP area configuration in SAP customizing.


You can find following changes due to activation of MRP area. These are just few for example

MD61 – PlR creation

MRP

Material Master

Stock Requirement list


Step 4: Master data for MRP area

The material will not be considered in MRP area planning until it’s extended to MRP area. Following steps shows how
to extend a material in MRP area. You can extend a material to multiple MRP areas based on the need.

Go to change material master under MRP 1 screen and assign MRP area as shown below:

You will have additional views for MRP 1, MRP 2, Forecast & Consumption values. You need to fill required fields as
per your need.
When you assign a material to a new MRP area, a new record for this assignment gets added in
the planning file. You have an option to define individual MRP and forecast parameters for each
MRP area that you assign to a material. These parameters can differ from those defined in the
material master at plant level. As an example, you can have different MRP controllers, lot size or
MRP type for each individual MRP areas that is assigned to a material.

Users can set up different forecast model and consumption values in MAR area tabs. Once MRP
with MRP area is activated, ATP check is also activated at MRP area level.
Scope of planning with MRP area

You can create scope of planning run if you want to carry out total planning for limited MRP areas.
In case you do not give any MRP area in total planning run, system will consider all MRP areas
under a plant and plan for them in total planning.

For single item planning system, in MD02 & MD03 system plans a material only in the specified
MRP area.

Sample Scenario:

Let’s consider a material Assembly maintained in plant ZSY1 under 2 storage locations (ZSY3 & ZSY4)

Sloc ZSY3 maintained in MRP area MA001. Assembly is extended to MA001 with following stock situation

ZSY3 – 100 (under storage location MRP area MA001)

ZSY4 – 150 (under Plant MRP area ZSY1)

Lot size for same material is maintained as FX (fixed lot size) in MA001 MRP area and EX in plant MRP area ZSY1
Total stock MMBE
MD04 - MRP Area ZSY1

MD04 - MRP Area MA001

Let’s have requirement from a Sales order for plant ZSY1, it will come under plant MRP area ZSY1

For testing, we can also have PIR created for specific MRP area MA001

Here is the stock situation of MD04 with sales order in Plant MRP area

Stock requirement for MRP area MA001:


If we run MD02 for plant ZSY1, system will only consider plant MRP area and will not plan for
MRP area MA001 as it’s a separate planning area

MRP area MA001 is untouched:

After running MRP for MA001 system creates planned order for 200 quantities
Material Assembly was maintained as EX lot size in plant MRP area and with fixed lot size 200 in
MA001 hence planned order of 200 Qty created in MA001. In this way separate planning
parameters can be maintained to run requirement planning using MRP areas.