EVP-003-CL2 Vaporizer Piping - Gas Pressure Feed
EVP-003-CL2 Vaporizer Piping - Gas Pressure Feed
Vaporizers are used for high capacity chemical feed applications when direct gas withdrawal systems are
impractical. This document will provide a generalized overview of vaporizer operation and general design
information for chlorine liquid manifolds. Throughout the document reference will be made to chlorine
(Cl2), but the information also applies to sulfur dioxide (SO 2) and ammonia (NH3). This document should
be used only as a reference and only after proper engineering consideration has been given to all aspects
of the relevant system design. For additional information refer to the Hydro Instruments Chlorine
Handling Manual and the Chlorine Institute, Inc. Pamphlet 6.
Vaporizer Overview
The vaporizer pressure chamber is submerged in a hot water bath at approximately 180°F (82°C). Water
bath temperature can be adjusted depending on feed rate requirements and also can be set lower during
standby usage. As the liquid chlorine flows into the pressure chamber it is vaporized on contact with the
hot walls of the chamber. The resultant gas chlorine is then superheated as it travels out of the vaporizer
before flowing downstream to the process (See Figure 2). The rate at which chlorine passes through the
chamber is dictated by the chemical feed rate of the system. Initially the liquid chlorine level in the
pressure chamber will rise until the heat transfer rate from the pressure chamber walls to the liquid
chlorine is sufficient to balance the chemical feed rate of the system. If the liquid chlorine level rises
above this equilibrium level (or if feed rate demand of the system is reduced) then chlorine gas pressure
inside the chamber will build up and push the liquid chlorine level back until a new equilibrium level is
reached. As the chlorine feed rate is increased, gas pressure will fall causing the liquid level to rise, and
as the liquid chlorine level rises the heat transfer surface area increases between the liquid chlorine and
the pressure chamber walls until an equilibrium level is reached. Therefore, the size of the inner chamber
and its ability to transfer heat to the liquid chlorine determines the feed rate capacity of the vaporizer.
IMPORTANT: Exceeding this feed rate capacity risks the liquid level rising above the height of the
chlorine pressure chamber and flooding liquid chlorine past the vaporizer.
FIGURE 1
Expansion Chamber
Actuated Pressure Reducing Valve
VENT TO SCRUBBER
INTAKE DUCT
Pressure Relief Valve
EMERGENCY SCALE
GAS ALARM
SHUTOFF SYSTEM INDICATOR
Pressurized Pipe
(gas) FILTER
Ton Container
Vaporizer
SCALE
Flexible Connector
Pressurized Pipe
(liquid)
600 Emlen Way, Telford, PA 18969 Telephone: (215) 799-0980 Fax: (215) 799-0984
US Toll Free: (888) 38-HYDRO www.hydroinstruments.com [email protected]
Pressurized Piping
Pressurized piping should be 1” schedule 80 seamless carbon steel. Fittings must be 3000 pound forged
steel, A-105.
Note: Threaded joints must be sealed with Teflon tape or other approved sealant.
Chlorine Liquid Manifold
The liquid manifold can be placed above or below the liquid cylinder valve (e.g. the bottom valve) on the
ton container. However, to prevent liquid traps it is recommended it be placed above. If placed above the
ton container then the pipe should be pitched back toward the ton containers at approximately 2° to 3°.
Flexible connectors are used to connect the manifold piping to the ton containers. Auxiliary valves (e.g.
isolation valves) should be used on all flexible connectors at the ton container.
Pressure Equalization Manifold
The use of a pressure equalization manifold is recommended when utilizing more than one ton container
in order to equalize the pressure within the ton containers. This will help to prevent overfilling of the ton
containers when liquid chlorine is pushed back into them. The pressure equalization manifold must be
placed above the liquid manifold. Pipe size should be 1” schedule 80 seamless carbon steel and fittings
must be 3000 pound forged steel, A-105. If adding a secondary gas discharge line, the pipe size should
be sized appropriately for the flow rate and it must be tilted back toward the containers and installed with
liquid traps and heaters to allow use during times of vaporizer maintenance.
Gas Feed Line (optional)
This piping arrangement can be used for gas feed during times of vaporizer maintenance or as a means
to evacuate the gas piping line.
The gas feed line piping should pitch back (approximately 2° to 3°) toward the ton containers and the gas
outlet of the vaporizer must be higher than the containers. The valves in the optional gas evacuation pipe
line must remain closed during normal operation.
600 Emlen Way, Telford, PA 18969 Telephone: (215) 799-0980 Fax: (215) 799-0984
US Toll Free: (888) 38-HYDRO www.hydroinstruments.com [email protected]
600 Emlen Way, Telford, PA 18969 Telephone: (215) 799-0980 Fax: (215) 799-0984
US Toll Free: (888) 38-HYDRO www.hydroinstruments.com [email protected]
Therefore, the chamber size determines maximum capacity and the water temperature is the only variable
the vaporizer can adjust under operating conditions.
As illustrated in Figure 2 below, the superheat is an indication of how high the liquid level is in the
chamber. If the superheat falls to zero then this means that liquid has reached the top of the pressure
chamber and will flood past the vaporizer. The Hydro Instruments Vaporizer monitors the superheat and
has a superheat alarm feature that will stop liquid chlorine flow by cutting power to the actuated pressure
reducing valve in the gas outlet line should the superheat fall below the alarm set point. This is critically
important because if liquid chlorine passes through the vaporizer it could enter equipment downstream of
the vaporizer or reach the process, which could cause a chlorine release or downstream process
malfunction.
FIGURE 2
T2
Superheat = T2 – T1
T1
600 Emlen Way, Telford, PA 18969 Telephone: (215) 799-0980 Fax: (215) 799-0984
US Toll Free: (888) 38-HYDRO www.hydroinstruments.com [email protected]
Page 5 of 5
E1. Expansion chamber 662 m3 volume K. Chlorine gas filter E
E2. Testing tee with plug L. Manifold union J2 VENT TO SCRUBBER
J1 INTAKE DUCT H
0
10
80 0
14
40 0
18
F F F
L H1
N
PLUG
P Q
D D D
M
B
VENT TO SCRUBBER
O INTAKE DUCT 0
10
H
G 80 0
14
40 0
18
0
20
E1
H
C
P1 VENT TO SCRUBBER
INTAKE DUCT L L
E3 E2
I1
I2
F F F
100
E5 80 140
40 180
200
E4
F F F
L H1
PLUG
D D D N
B
O M
VENT TO SCRUBBER
INTAKE DUCT 0
10
H
80 0
14
E1 40 0
18
0
20
C
G
www.hydroinstruments.com
P1 H
VENT TO SCRUBBER
E3 E2 INTAKE DUCT L L
40 180
200
E4