Sch B Offshor
Sch B Offshor
Tender Details
IFB / Tender Notice No. : Tender Notice No-1 of 2011-12 Tender ID : 69914
Constructing canal earth work, lining, structures
and service roads including maintenance &
Name of Work : repair works (for five (5) years) for distributaries ECV(INR) : 286,436,847.76
(D-13 to D-17) and its minors of Morbi branch
canal from Ch. 44 to 65 km.
Last Date & Time For Submission of Bid: 24/01/2012 18:00:00
Earthwork in
embankment by pad
method using selected
soil, soft & hard
murrum excavated
from approved borrow
area / village tanks
https://ssnnl.nprocure.com/asp/tmsv2/worldbankworks/ViewSupplierBOQRate.asp 17-02-2012
Welcome to (n)Procure Tender Management System Page 2 of 9
https://ssnnl.nprocure.com/asp/tmsv2/worldbankworks/ViewSupplierBOQRate.asp 17-02-2012
Welcome to (n)Procure Tender Management System Page 3 of 9
smooth finishing,
curing including
dewatering where
required as directed
etc. complete.
L-3 three hundred
12. (manually with 2,313.7500 m2 403.6500 316.0000 7,31,145.0000
(a) sixteen
conventional mixer)
Cement level 240 kg.
(a) 12.5 cm thick
lining in bed with
water curing
(b) 12.5 cm thick
L-3 three hundred
13. lining in slope with 11,271.4300 m2 426.1500 325.0000 36,63,214.7500
(b) twenty five
membrane curing
Providing and filling
the bituminous sealing
compound of approved
make in the expansion
and contraction joints
14. L-4 80,211.0000 m 33.6500 50.0000 fifty 40,10,550.0000
in cement concrete
lining work including
clearing the joints with
air water jet etc.
complete.
Providing and laying
M15 grade plain
concrete of cement,
sand and crushed
metal for 0.75 m wide
step on the canal
slopes with 0.10 m
wide side wall
two hundred
15. L-5 including dressing the 720.0000 No. 146.9000 234.0000 1,68,480.0000
thirty four
sub grade to correct
profile, mixing,
placing, vibrating form
work, finishing and
curing the concrete
etc, complete as per
drawing with all leads
and lift.
Providing and placing
in position
reinforcement bars
including cutting,
sixty one
16. L-6 bending, welding joints 49.5700 MT 46,680.3000 61,000.0000 30,23,770.0000
thousand
where necessary,
hooking etc. complete
as per drawing for all
leads and lifts. (B) TMT
Excavation for
foundation in all sorts
of soil including yellow
sandy & gravelly soils,
soft and hard murrum
etc. including
S-1 depositing the
17. 27,262.0900 m3 61.2000 54.0000 fifty four 14,72,152.8600
(a) excavated stuff in
uniform layers in
banks or as and where
directed etc. complete
for lead upto 1 km and
all lift (By machinery)
(a) Above water table.
Excavation for
foundation in SOFT
ROCK including
depositing the
S-1 excavated stuff as and one hundred
18. 3,205.4800 m3 120.9000 120.0000 3,84,657.6000
(b) where directed etc. twenty
complete for lead up to
1.0 Km and all lift( By
machinery) (a) Above
water table
Excavation for
foundation in HARD
ROCK including
blasting and chiseling
S-1 if necessary sorting two hundred
19. 1,603.7600 m3 216.3000 250.0000 4,00,940.0000
(c) out and stacking fifty
seperately the usable
rubble, depositing the
excavated stuff etc.
complete for lead upto
https://ssnnl.nprocure.com/asp/tmsv2/worldbankworks/ViewSupplierBOQRate.asp 17-02-2012
Welcome to (n)Procure Tender Management System Page 4 of 9
https://ssnnl.nprocure.com/asp/tmsv2/worldbankworks/ViewSupplierBOQRate.asp 17-02-2012
Welcome to (n)Procure Tender Management System Page 5 of 9
https://ssnnl.nprocure.com/asp/tmsv2/worldbankworks/ViewSupplierBOQRate.asp 17-02-2012
Welcome to (n)Procure Tender Management System Page 6 of 9
fabrication, fixing in
position, and applying
two coats of red oxide
37. S-14 tagged by chain to 25.3100 m2 1,585.5000 2,000.0000 two thousand 50,620.0000
anchor bar embedded
in cement block etc. as
directed.
Earthwork in
embankment using
selected soil, soft &
hard murrum
excavated from
approved borrow
area / village tanks
38. S-15 etc. conveying, 3,203.1000 m3 71.8500 60.0000 sixty 1,92,186.0000
spreading in uniform
layers, breaking clods
and dressing to the
designed canal section
etc. with lead upto 3
km and all lift.
Excluding Royalty.
Compaction of
earthwork in
embankment in
uniform layers at
optimum moisture
39. S-16 content to required dry 3,203.1000 m3 7.5500 9.0000 nine 28,827.9000
density including
watering, rolling with
suitable type of roller
of specified capacity
etc. complete. )
Providing and fixing
guard stone of size 20
40. S-17 cm x 20 cm x 75 cm 214.0000 No. 68.6000 70.0000 seventy 14,980.0000
including white
washing in two coats.
Providing temporary
moterable service road
during construction
including cleaning the
seventeen
S-18 site in 7m width,
41. 11.2000 Km 19,013.0000 17,500.0000 thousand five 1,96,000.0000
(a) cutting undulations,
hundred
filling depressions,
watering & maintaining
the same etc.
complete (a) CTC
seventeen
S-18
42. (b) VRB 1.4000 Km 19,013.0000 17,500.0000 thousand five 24,500.0000
(b)
hundred
Providing and laying
wearing coat 100 mm
thick at center and 50
mm thick at ends of
compacted asphaltic
concrete with tack coat
of 0.50 Kg/m2 using
stone aggregates as
per gradation and
asphalt at 6.5% (which
will vary as per design
of mix in laboratory) to
43. S-19 51.6900 m2 711.2000 1,000.0000 one thousand 51,690.0000
have the required
specific gravity of the
compacted final mix by
weight of total mix per
binder by hot mix hot
laid process including
consolidation and
providing required
plant and machinery,
cost of fuel, oil,
lubricant, labour
charges etc. complete.
Dismentalling the
existing metal road
surface including
44. S-20 73.7600 m2 29.6000 25.0000 twenty five 1,844.0000
disposing off the
dismentalled material
as directed.
https://ssnnl.nprocure.com/asp/tmsv2/worldbankworks/ViewSupplierBOQRate.asp 17-02-2012
Welcome to (n)Procure Tender Management System Page 7 of 9
https://ssnnl.nprocure.com/asp/tmsv2/worldbankworks/ViewSupplierBOQRate.asp 17-02-2012
Welcome to (n)Procure Tender Management System Page 8 of 9
SubWork Details
S.No. SubWork Name SOR Total Est.Val Total Total
1. Schedule B- EARTH WORK 4,40,53,299.4230 4,40,53,299.4230 3,34,01,546.7700
2. Schedule B- LINING 9,12,99,308.6040 9,12,99,308.6040 8,81,61,071.5500
3. Schedule B- STRUCTURE and SERVICE ROAD 9,90,69,307.9030 9,90,69,307.9030 10,46,12,103.8100
4. Schedule B- WBM ROAD WORK 2,59,75,218.3600 2,59,75,218.3600 2,25,36,335.6400
5. Schedule B- MAINTANANCE and REPAIRS 2,60,39,713.5200 2,60,39,713.5200 1,20,00,000.0000
* 28,64,36,847.8100 28,64,36,847.8100 26,07,11,057.7700
Grand Total
Rebate (in %) NA NA 0.0000
Fixed Deduction Amount : NA NA NA
Net Amount
((Added Subwork Total * (1-Rebate/100)) -
28,64,36,847.8100 28,64,36,847.8100 26,07,11,057.7700
Deducted Subwork Total - Fixed Deduction
Amount) :
*
Added Subwork Total : (Sc+Sc+Sc+Sc+Sc)
Deducted Subwork Total : (dule B+ EARTH WORK +edule B+ LINING +edule B+ STRUCTURE and SERVICE ROAD+edule B+
WBM ROAD WORK +edule B+ MAINTANANCE and REPAIRS )
https://ssnnl.nprocure.com/asp/tmsv2/worldbankworks/ViewSupplierBOQRate.asp 17-02-2012
Welcome to (n)Procure Tender Management System Page 9 of 9
Notes
Schedule B- EARTH WORK
-
Schedule B- LINING
-
Schedule B- STRUCTURE and SERVICE ROAD
-
Schedule B- WBM ROAD WORK
-
Schedule B- MAINTANANCE and REPAIRS
-
https://ssnnl.nprocure.com/asp/tmsv2/worldbankworks/ViewSupplierBOQRate.asp 17-02-2012