Project Execuation Plan
Project Execuation Plan
Document Approval
Prepared by Reviewed by Approved by
• Temporary access roads & site facilities area preparation as per approved TMP
• Boreholes
• Excavation work (General excavation, rib able & non-rip able rocks)
• Demobilization.
(Fig:1 Mirage Visitor Centre)
2 REFERENCES
2.1 NEOM Document
Document Number Document
NEOM-NEV- PRC 016; Full set of documentation and associated forms and tools
PRC501; PRC 601; PRC 701
and PRC 801.
2.2 PPCO Document
Document Number Document
2.3 Other
Document
SEC Guidelines
SWCC Guidelines
Environmental Accord
Term Definition
4 Organization Chart.
5 Site & Office Layout Plan.
Phase 3: Tree & Wildlife Preparation access for Boreholes & Translocation
Translocation of Trees and Spiny Lizards.
Phase 6: MSE Wall Installation, MSE Wall bed preparation & Precast concrete
Rock Material Crushing & block installation Rock material crushing, hydraulic
Backfilling backfilling with crushed material.
• Topographical Survey: Perform a detailed survey of the site, including mapping the terrain
and identifying features relevant for the construction.
• Ecology Survey: Conduct a survey of the ecological environment and heritage aspects within
the project boundary to ensure no protected species or structures are disturbed.
• Project LUP Boundary Marking: Mark the limits of the land use plan (LUP) boundary as per
project requirements.
Key Deliverables:
• Ground Preparation for Site Facilities: After NEOM approval Marking & preparation the
area for the site offices, welfare facilities, and storage areas for materials and equipment.
Mobilization & Installation of site offices & welfare.
• Temporary Access Roads Preparation: Prepare the access roads and internal pathways, in
accordance with the traffic management plan, ensuring proper road quality and safety.
• Equipment’s Mobilization: Prepared the parking area for equipment’s and mobilize all
equipment’s to parking area for site work operation.
Key Deliverables:
Resources Required:
• backhoes (JCB)
• Bulldozer
• Water Tanker
• Loader
• Grader
• Boom Truck
Survey Equipment’s:
• GPS station,
• Total station
• Leveling instrument
• Hand Shovel
• Spray Paint
• Hammer
• Translocation of Trees: Safely remove and transplant trees that may be in the construction
area, as per environmental and ecological guidelines.
• Translocation of Spiny Lizards: Relocate any spiny lizards identified in the ecological
survey to safe, pre-designated areas.
Key Deliverables:
Resources Required:
Phase 4: Boreholes
Boreholes: Preparation access for remaining boreholes 69 nos. The purpose of this geotechnical
investigation is to obtain information on the physical properties of the subsurface conditions and to
determine the rock mass parameters below the proposed structures, and foundations.
Fig: Bore Satellite Image
• General Excavation: After NEOM inspection and approval for Site facilities Carry out
excavation across the site, including both general soil excavation and excavation in rock
areas (rip-able and non-rip-able rock). Material category will be as per quality team and
consultant inspection with third party testing. This phase will involve heavy machinery for
digging and transporting material.
• Blasting: For the rocky area prepare for the blasting, make sure before this blasting method
of statement and blasting plan approved from NEOM & PMC.
• The blasting process must be handled and managed in a way that minimizes the risk of
the unplanned detonation of explosives, and associated undesired outcomes, and
uncontrolled blast behavior at the time of firing.
Key Deliverables:
• Excavation of the required volumes completed to as per project specification & quantities.
Resources Required:
• Drilling rigs
• Skilled labor for manual excavation operations & charging for blasting.
• MSE Wall: Preparation bed as per approved drawings for MSE wall, after approval of MSE
wall design, mobilize the MSE wall concrete block required areas as per approved project
drawings, Installation of pre-cast wall approved lifting plan.
• Rock Material Crushing for Backfilling: Use crushers to break down the excavated rock
material into usable sizes as per project specification for backfilling purposes.
• Hydraulic Backfilling: Backfill required areas as per approved project drawings with the
crushed rock material which produced on site mobile crusher, additional required backfill
materil will be haulage after NEOM approval from LAJV stock or outsource, compacted as per
project specifications. Hydraulic backfilling requires careful layering and compaction to ensure
the stability of the backfilled areas.
Key Deliverables:
Resources Required:
• Rock Bolting: As per geotechnical recommendation and consultant approval Install rock
bolts to further stabilize the ground, including drilling holes and inserting bolts, followed by
grouting and securing.
Key Deliverables:
Resources Required:
Environmental Considerations
• Ensure that the earth work activities do not cause environmental damage, such as soil
erosion or disruption to local habitats.
• Minimize waste and ensure proper disposal of any excess material or debris.
• Use dust suppression techniques, especially during dry conditions (Loading / unloading).
• Ensure and proper arrangement for waste removal of toilets septic tank before
• Final Inspection & Project Handover: Perform a thorough inspection of the site, ensuring all
work is completed to specifications. Hand over the completed project to the client, including
all documentation (e.g., reports, certifications).
Key Deliverables:
Resources Required:
• Removal of Temporary Facilities: Dismantle all temporary site offices, welfare facilities, and
other infrastructure.
• Site Cleanup: Clean up the site, removing any leftover materials, equipment, and waste from
the project.
• Demobilization: Ensure that all equipment is removed from the site, and the site is left in a
safe and clean condition.
Key Deliverables:
Resources Required:
• Excavation: The excavation s of material is a critical path item. Rocky & hilly area delays
here will impact the entire project schedule.
• Backfilling & Rock Crushing: Timely crushing of rock and backfilling is necessary to
maintain progress for ground support installation and other activities.
• Tree & Wildlife Translocation: Delays in this activity can affect the overall schedule, as it
must be completed before other activities (excavation, etc.) begin.
• Shotcrete & Rock Bolting: Timely apply of shotcrete and rock bolts installation after
Geotechnical engineer recommendation and reports & consultant approval is essential for the
safety of the site and to ensure excavation can proceed.
• Safety: Implement strict safety measures for all excavation, construction, and ground support
activities.
• Quality Assurance: Ongoing inspections and testing will ensure that each phase meets
required NEOM standards & Project specification.
Environmental Compliance: Special attention will be given to ecological impacts, especially during
the tree and wildlife translocation and ground support activities.
Conclusion:
This 120-day project execution plan outlines all critical activities and phases required to
complete the site preparation, excavation, backfilling, ground support installation, and
handover. Timely execution, resource management, and coordination between the different
phases are key to meeting the project goals.
7 Project TimeLine: