Business introduction and Typical design
2023
Modular Substation
01. Business introduction
02. Typical project
03. Typical design
Key benefits
15~25days
3~5 days
Equipment installation,
Inland
transportation commissioning
at site
30~60 days
2~3months
Factory
production for establish
10~30 days For Construccion in the field
Save 100~200 days of
site construction
period
Prefabricated Land Investment Production &
cabin saving saving Installation
The cabinet will be Compare with the Compare with the time
prefabricated, traditional substation, traditional substation, Only 120 days, including
including the positive it can save about 30% it can save about assembly and installation time.
pressure dust removal of the land. 20% of the total cost. Production 90 days and
etc. installation 30 days.
The main design principles
Pre
assembly
Safet
y • Pre assembly and debugging in
Desig factory
n • Meet the earthquake intensity of nine degrees(0.5g), With
the earthquake report issued by the National Seismological
Bureau.
• The cabinet can be used for 60 years.
• The GIS cabinet wide is 3.4m, Convenient for road transportation.
• Can be customized design according to the actual situation of the project site.
110kV prefabricated cabin
Three-layer
damping
tecnology
Straight line
form
Completely
Maintenance-
free
SF6
detection
alarm
Construction process
Land acquisition Foundation Module assembly
Module connection Cable connection Commissioning
Intelligent enviromental control
Micro-positive pressure dust-
proof
intelligent control system
Air-conditioning system regulates the
Micro positive air Internal External
pressure pressure
constant temperature and humidity in
pressure the cabin
Cold/Warm air
105%
Standard
Positive pressure system creates
atmospheric positive pressure in the tank
Fres pressure
Air
h Air Air flows out from the gap and dust
Entry
Standard can't enter
atmospher
ic
pressure
The most advanced and smallest
External Constant micro-positive pressure system in
circulation temperature and China
system humidity, dust-
free Perfectly eliminates the effects of
dew condensation and dust on
electrical equipment
High weather resistant anticorrosion technology
Shot blasting + Blowing dust
Thermal spray zinc
Zinc spray and primer
Epoxy with micaceous iron coating
Decorative hammer finish
Top cover and siding cladding material which made of magnesium aluminum alloy and non-
metallic material, could eliminate the potencial corrosion
Examples
Prefabricated cabin in high salt spray and high corrosion
environment operation
Technical details
Vertical maintenance station and escape
platform
Fully considered test, maintenance and expansion
Technical details
Equip potential connection Pipe busbar crossing eddy
Grouded cabin Anti-falling ladder
between compartments current and grounding
SF6 Leak Basic External SF6 leak alarm Internal environmental
sensor ventilation and ventilation system monitoring device
Typical project
01. Mongolia Ulan Bator Coal Mine 110kV Substation
02. Delingha Sunshine 10MW Photovoltaic Power Generation Project, Qinghai
03. Laoheishan 50MWp (Phase 1) Photovoltaic Power Station Project, Guizhou
04. Tajikistan Khorog Pamir Energy Group 110kV Substation
05. Lianghuai Photovoltaic Power Generation Project
06. Kyrgyzstan 110kV substation
07. Paraguay 220kV, 69kV Mobile substation
Mongolia Ulan Bator Coal Mine 110kV Substation
Full line operation on Nov. 25th, 2014 with success.
Experienced heavy rain and snow condition,
security and reliable
Experienced the lowest temperature of -27 ℃ ,
security and reliable
Experienced the coal dust, sand and other harsh
environments, security and reliable
Delingha Sunshine 10MW Photovoltaic Power
Generation Project, Qinghai
It covers only 400 square meters
The construction period is 45 days
Use the 5G technology for
communication
Laoheishan 50MWp (Phase 1) Photovoltaic Power Station
Project, Guizhou
Solved the problem of
transportation in mountainous
areas
90 days factory production, 30
days site construction
Main transformer three winding,
50MVA capacity
Tajikistan Khorog Pamir Energy Group 110kV Substation
High altitude mountain substation, altitude
is 3,500 meters
Solve the difficult problem of high
investment and difficulty in construction
All use plateau type electrical equipment
Main transformer 2×80MVA
Lianghuai 21MW (Phase 1) Photovoltaic Power Generation
Project
Main transformer 21MVA, step-up
substation
Highly integrated design, to solve
the landscape problem.
The construction period is 60
days
Kyrgyzstan 110kV substation
Main transformer 25MVA, step-up substation
Located in permafrost area all year round,
only simple ground foundation is made
Ground cable bracket is adopted for cable
laying, installation is easy and quick
The construction period is 100 days
Egypt 220kV, 50MVA Mobile substation
Main transformer 50MVA
The chassis of the fully powered hydraulic
lifting truck is adopted, which meets the
transportation requirements and has a
minimum turning radius of 8.4 meters
Paraguay 220kV, 69kV Mobile substation
Main transformer 41.67MVA and 30MVA
HV GIS 220kV and HGIS 66kV with Rotatable bushing
Hydraulic trailer
Typical Design
01. 110kV –T1 Three main transformers design
02. 110kV –T2 Two main transformers design
03. 110kV –T3 Single main transformer design
04. 110kV –T4 Single main transformer irregular terrain design
Typical design
Typical design
Typical design
Typical design
Typical design
Typical design
Typical design
Typical design
Thank you