The Lesson 7
The Lesson 7
Introduction
The purpose of lesson six is to study how network techniques could use for project
planning, monitoring and management. The session will explain basic characteristics
of network analysis and main network analytical tools such as Project Evaluation
and Review Techniques (PERT) and Critical Path Analysis (CPA) methods.
Due to some limitations of using Gantt charts in project scheduling i.e. not indicate
inter relationships between project tasks/activities and impacts of delaying tasks or
of shifting resources, network analysis is used as planning technique for project
management.
E H
150 180
Wake up A B C F I J
60 600 40 60 100 15
G
45
D
350
Construction
B
8 weeks
An Example
Both AON and AOA formats use as activity oriented networks to show (describe)
projects in terms of tasks or jobs in planning and implementation.
If you were given information about the project as shown in table7.2, you can
prepare a network either using AON method or AOA method.
Start Finish
A6
E6
C8
Note that AON networks construct without use of dummy and it is easier and
simple to construct. As shown in Dig. 7.4, nodes used to indicate activity and time,
and arrows used to indicate relationship between events and activities.
When use AOA method, node represents events and arrows shows the activity.
Each events were numbered including start and finish (Dig 7.5).
D4
3 5
B
7
1 A 2 9
6
6 8 C 8 4 E
AOA method is used often by project managers because it suit for PERT and CPM
procedures to indicate the relationship of project activities, duration and costs.
PERT was developed by U.S. Navy’s Polaris Missile System Program in 1958.
Though initially it was developed for defense projects, now it widely uses as
planning and controlling projects. It emphasis the uncertainty of project finish by
considering variation of project time in terms of three scenarios as follows.
Optimistic Time: Minimum Time required for an activity to complete, the situation
where everything goes well. (See point a in figure 7.1)
Most likely (Normal) Time: It is the normal time to complete the task. It assumes
that no extra time or personnel required. (See point m in figure 7.1)
Pessimistic Time: The maximum time that activity could take. It is the worst time
that could be expected if everything went wrong. (See point b in figure 7.1)
Fig. 7.1: Probability Distribution of Time
Activity
Optimistic ML Average Pessimistic
a m te b
Probability
3 5 6 13 month (Time)
te = ta+4tm+ tb
te = expected time
ta = Optimistic time
tm = Most likely time (ML)
tb = Pessimistic time
According to time distribution of fig 6.1, the average or expected time (te)is
= 3+4(5) + 13/6 = 6 days
The Variance also counted as follows;
V = (𝑏 − 𝑎 )2
A - 03 04 05 04
B A 01 02 03 02
C A 02 03 04 03
D C 01 02 03 02
E A 03 05 07 05
F C 04 05 12 05
G B,D 05 04 11 04
H E 92 04 06 04
I F,G 02 03 04 03
J H.I 04 06 08 06
4 6
5
B 2 D 2 F 6 3 I
A C J
1 2 3 7 8
4 3 6
E H
5
5 4
Cost
Cc=18……………..
cost slope=Cc-Cn
Cc = crash cost
Tn = Normal Time
Tc = crash time
According to above equation and the statistics in the figure 7.2, additional cost
requirement (Cc-Cn ) to reduce duration from Tn -Tc ( 8 - 5 weeks) is calculated as
follows.
Cc-Cn / Tn-Tc
= 18- 9 / 8 -5 = 9 / 3
= 3
Critical path
Critical path is the longest path in a network. It is the order of activities or task that
indicate maximum time to complete the project. It is important because it reflects
earliest start time and earliest finish time. So it helps to identify faults of the path
that would affect to delay the project. Therefore, both PERT and CPM methods
count critical path in the network analysis. Four type of durations are considered in
critical path analysis. It includes;
It is the time, which indicates earliest start time of activity without delaying the
total project time
It is the time, which indicates earliest finish time of activity without delaying the
total project time
The time, which indicates latest start time of activity without delaying the total
project time
4. Latest Finish Time (LFT):
It is the time, which indicates latest finish time of activity without delaying the
total project time
If we consider expected time calculated in table 7.4, EST and EFT for each task
could be calculated as follows;
For activity A, no early start work and therefore EFT is 04 days. For activity B, EST
is 4 because it start after activity and it require 2 days to finish. Thus EFT is 4+2 =6.
The activity C also start after activity A and hence EST is 4 and since activity C
require 3 days, its EFT is 4+3 = 7. Thus EFT for all activities can be calculated by
counting EST and time require for each activity. According to table 7.4 and diagram
7.6, EST for last activity J is 17 days and its EFT is 23 days. It indicates the longest
path of the projected to be completed. EST and EFT is mentioned above the arrow.
Since the last activity and the last event are considered as total time required to
complete project, LST and LFT of each and every activities counted by reducing
required time for each activity from EFT. For instance, EFT of the last activity is
23 and it consider as the LFT. Thus LST for activity J is counted by reducing
required time for activity J as follows (23-6 = 17). Similarly, LST and LFT for each
activity could be calculated. LST and LFT is mentioned below the arrow (Table 7.5).
Counting early and late perspectives indicates clearly critical path. Thus critical and
non-critical activities identify easily by counting slack, which reflects time period
for which an activity can be delayed without causing troubles in completion of
project. It may be positive or negative. When slack become negative it recognize as
critical activity and when it becomes positive it recognize as non-critical activity If
we consider the same example in accordance with slack, the diagram analysis could
be illustrated as follows (See diagram 7.7). The critical path is denoted by double
line or darker to distinguish it from non-critical activities.
Table 7.5: Counting Slack according to Network
E (4,9) H (9,11)
5 (8,13) 4 (13,17)
5
Critical Path 1 A 2 C 3 D 4 G 6 I 7 J 8
4 3 2 5 3 6
= 23 weeks