Capital Budgeting
Capital Budgeting
P1.An investor issues a deep discount Bond for Rs.5,000 today and will mature in 15 years for Rs.20,000. Advise an
investor whose opportunity rate of return 11%?
Solution:
Bond's issue price today Year Cash Flow
Redemption Value 0
Tenure (Years) 1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
IRR on Bonds Rate
P2.A firm is evaluating a proposal costing Rs.1,60,000 and expected to generate cash flows of Rs.
40,000, Rs.60,000, Rs.50,000, Rs.50,000 and Rs. 40,000. there is no salvage value there after.
Find out the IRR of the proposal.
Should it be taken up if the hurdle rate of the firm is 12%?
Solution:
Year Cash Flows
0 -160000
1 40000
2 60000
3 50000
4 50000
5 40000
IRR 15%
P3.Hunny Projects Ltd. Is evaluating two mutually exclusive investment proposals X and Y, The company's required rate
of return from such projects is 10%. The cash flows pattern of both the proposals are given. Evaluate the proposals as
per NPV and IRR methods:
Solution:
Year X Y
0 60000 60000 Rate 10%
1 50000 5000 year x y
2 25000 30000 0 -60000 -60000
3 5000 55000 1 50000 5000
2 25000 30000
NPV 3 5000 55000
PV $69,872.28 $70,661.16
IRR
Npv Pv of cash inflow - Pv of cash outflow
$9,872.28 $10,661.16
Solution:
Project A Project B
Rate 12% 12%
Cash Invested -150000 -300000
CF1 40000 80000
CF2 56000 112000
CF3 60000 120000
CF4 45000 90000
CF5 65000 130000
Solution:
Initial Investment 100000 Year CFAT
1 60000
Life 5 2 50000
3 40000
4 10000
5 5000
Total Cash inflows 165000
Cumulative CFAT
60000
110000
150000
160000
165000
N 1
I 100000
Ccn 60000
Cn+1 50000
P6.
GIVEN:
You are required to find the most profitable investment based on “Payback Period”.
30%
P7. Xerox Ltd. Is considering two additional mutually exclusive projects. The after tax cash flows associated with these
projects are given in the table. The required rate of return on these projects is 11%:
Advise as to which project will be chosen by way of: NPV and IRR?
Which project should be accepted? Why?
Solution:
Calculation of NPV and IRR
Year Project A Project B
0 -100000 -100000
1 32,000 0
2 20,000 0
3 32,000 0
4 35,000 0
5 45,000 200000
IRR 17.46% 14.87% Project A should be selected due to higher irr as compared to Project B
rr as compared to Project B
P8. The ABC Ltd is in the process of selecting a capital project. The details of 2 Capital projects A and B identifie
Project A Project B
Rate of Interest 12% 12%
Cost of Project 500000 550000
Cash Inflows Year 1 400000 20000
Year 2 60000 500000
Year 3 50000 60000
Year 4 70000 70000
Year 5 80000 80000
You are required to evaluate the above capital budgeting projects and recommend the project to be implemented
the basis of:
a) IRR Method
b) NPV Method using 12% Interest Rate
Calculate the value of NPV of “Project A” at the rate of interest of 10% to 15%
Draw a suitable chart for NPV of “Project A” at the rate of interest of 10% to 15%
Solution:
Project A
Rate 12%
Cost -500000
CF1 400000
CF2 60000
CF3 50000
CF4 70000
CF5 80000
Project A Project B
NPV 30443.92 -958.69
ommend the project to be implemented so that the company earns maximum profit on
15%
to 15%
Project B
12%
-550000
20000
500000
60000
70000
80000
Project to be selected
Project ?
Project A should be selected to positive npv and higher irr
Project ?
Project ?
Solution: Solution:
Values Occurrence
-35000 1-Jan-17
6000 1-Mar-17
8000 30-Oct-17
7000 1-Apr-18
19000 15-Dec-18