Chapter 4 - Network diagram scheduling
Chapter 4 - Network diagram scheduling
1 Introduction
2 Activity on node
3 Activity on arrow
4 Thiết kế sơ đồ mạng
2
4.1 Introduction
• Activity on arrow - AOA
• Activity on node - AON
3
4.1 Introduction
Task dependency
Removing Excavation
Pouring tank installation
formwork tank installation
concrete Pipe installation
Pouring concrete Pipe installation Excavation
Removing formwork
4
4.1 Introduction
Task dependency
• Finish - start
6
4.1 Introduction
• Finish – finish (FF) • Start – finish (SF)
i
i
j
j
8
4.2 Activity on node
Basic Rules:
9
4.2 Activity on node
10
4.2 Activity on node
A
D
C
F
B E
11
4.2 Activity on node
Precedence Duration
No Activity
relationship (days)
1 A - 2
2 B - 3
3 C A 2
4 D B; C(SS/+1) x
5 E D 3
6 F B 2
7 G F 1
8 H C; E 3
12
4.3 Activity on arrow
13
4.3 Activity on arrow
a) Numerical methods (Table)
Early Late Slack Critical
task task
14
4.3 Activity on arrow
15
4.3 Activity on arrow
16
4.3 Activity on arrow
17
4.3 Activity on arrow
18
4.3 Activity on arrow
19
4.3 Activity on arrow
Time axis
20
4.3 Activity on arrow
Gantt chart
task time
21
4.3 Activity on arrow
Resource graph
22
4.4 PERT
26
4.4 PERT
27
4.4 PERT
28
4.4 PERT
a) Determine the critical path and project completion time with the CPM
method.
b) Determine the probability that the project will be completed in 16 weeks.
c) Determine the time to complete the project with a probability of 90%.
30