Mprm April
Mprm April
REPORT - FEBRUARY
DATE OF
REPROT NO.
SUBMISSION 1-May-18
01 A PROJECT DATA
Constuction of Imaging Investigation Complex and Ward Complex for Cancer
PROJECT NAME
Unit at Tellipalai, Jaffna - Stage 1
Contac
t
CLIENT Ministry of Health Person
T.P
Contac
Director General of Buildings Department of Buildings, t Mr.Thirukumar
CONSULTANT Chief Engineer's Office, (Zone 2), Department of Person
Buildings T.P
Name PROJECT Name
PROJECT DIRECTOR
T.P COORDINATOR T.P
Name PROJECT Name Mr.K.Aingaran
PROJECT MANAGER
T.P ENGINEER T.P 077-3144971
Name Mr.K.Kajendran Name Mrss.Neeruya
PROJECT QS - Site PROJECT QS - HO
T.P 077-0613347 T.P 076-9128899
Scope of Project
01 B CONTRACT DATA
Remaining Dates 0
01 D. FINANCIAL DATA
BUDGET As AT EXPECTED at END
DESCRIPTION ACTUAL
PLAN REVISED PLAN REVISED
% 13.42% 0.00%
Reasons/Requirements
0.00
1 Cement bags 2746 2746.00 2707 30 2737.00 9.00
2 Plaster Sand Cube 0 0.00 0 0.00 0.00 Not Required
3 River Sand Cube 92.9 92.90 89.76 89.76 3.14
4 Sea sand Cube 0 0.00 0 0.00 0.00 Not Required
5 3/4" Metal Cube 61.5 61.50 61.3 61.30 0.20
6 1" Metal Cube 0 0.00 0 0.00 0.00 Not Required
7 1 1/2" Metal Cube 0 0.00 0 0.00 0.00 Not Required
8 Chip Metal Cube 0 0.00 0 0.00 0.00 Not Required
9 6" x 9" Rubble Cube 78.75 3 81.75 78 3 81.00 0.75
10 Gravel Cube 0 0.00 0 0.00 0.00
11 Quarry Dust Cube 6 6.00 5.5 5.50 0.50 Not Required
12 Bricks Nos 0 0.00 0 0.00 0.00 Not Required
13 100mm thk Solid Blocks Nos 0 0.00 0 0.00 0.00 Not Required
14 100mm thk Hollow Blocks Nos 0 0.00 0 0.00 0.00 Not Required
15 150mm thk Solid Blocks Nos 0 0.00 0 0.00 0.00 Not Required
16 150mm thk Hollow Blocks Nos 0 0.00 0 0.00 0.00 Not Required
17 200mm thk Solid Blocks Nos 0 0.00 0 0.00 0.00 Not Required
18 200mm thk Hollow Blocks Nos 0 0.00 0 0.00 0.00 Not Required
T 8 - Bars - 6m Bars 422.30 422.30 422.30 422.30 0.00
19 T 10 - Bars - 6m Bars 270.27 270.27 270.27 270.27 0.00
20 T 12 - Bars - 6m Bars 563.06 563.06 563.06 563.06 0.00
21 T 16 - Bars - 6m Bars 844.59 844.59 844.59 844.59 0.00
22 T 20 - Bars - 6m Bars 202.70 202.70 130.70 130.70 72.00
23 T 25 - Bars - 6m Bars 172.97 172.97 172.97 172.97 0.00
24 T 32 - Bars - 6m Bars 0.00 0.00 0.00 0.00 0.00 Not Required
T 8 - Bars - 12m Bars 211.15 211.15 110.00 101.15 211.15 0.00
25 T 10 - Bars - 12m Bars 6789.12 135.00 6924.12 5256.83 1467.72 6724.55 199.57
26 T 12 - Bars - 12m Bars 2395.36 2395.36 2203.21 152.53 2355.74 39.62
27 T 16 - Bars - 12m Bars 1265.91 1265.91 862.97 150.92 1013.89 252.02
28 T 20 - Bars - 12m Bars 236.42 236.42 221.82 29.12 250.94 -14.52
29 T 25 - Bars - 12m Bars 1438.94 21.60 1460.54 1219.02 207.31 1426.33 34.21
30 T 32 - Bars - 12m Bars 0 0.00 0 0.00 0.00 Not Required
31 R 06 bars Kg 778.39 778.39 496.56 120.35 616.91 161.48
32 Binding Wire Kg 870 870.00 645.00 225 870.00 0.00
33 12mm Plywood sheet Nos 0 0.00 0.00 0.00 0.00 Not Required
34 15mm Plywood sheet Nos 1010 1010.00 1007.00 3 1010.00 0.00
35 18mm Plywood sheet Nos 0 0.00 0.00 0.00 0.00 Not Required
36 5mm Plywood sheet Nos 30 30.00 0.00 0.00 30.00
37 2"x2" Timber Ft 28852 28852.00 28452.00 400 28852.00 0.00
38 2"x4" Timber Ft 18500 18500.00 16100.00 2400 18500.00 0.00
39 4"x4" Timber Ft 0 0.00 0.00 0.00 0.00 Not Required
40 Ready Mix Concrete - Gr 15 m3 18.5 18.50 18.5 18.50 0.00
41 Ready Mix Concrete - Gr 20 m3 0 0.00 0 0.00 0.00
42 Ready Mix Concrete - Gr 25 m3 773 286 1059.00 773 286 1059.00 0.00
43 Ready Mix Concrete - Gr 30 m3 0 0.00 0 0.00 0.00
Note.
If There is any other material which is use for permanent construction please include it.
MONTHLY PROGRESS REVIEW MEETING REPORT - April Page - 04
04). EQUIPMENT / MACHINERY REQUIREMENT
Note.
If There is any other equipment / Machinery please include it.
MONTHLY PROGRESS REVIEW MEETING REPORT - April Page - 05
05). FINANCIAL PROGRESS
12,000,000.00 12,000,000.00
1 30-Jul-17 13,539,640.35 13,539,640.35 250,000.00 250,000.00 13,289,640.35 15,570,586.40 27,570,586.40 27,570,586.40
2 31-Jul-17 71,969.04 13,611,609.39 64,772.14 314,772.14 13,296,837.25 27,570,586.40 1,074,362.61 1,074,362.61 26,496,223.79
3 31-Aug-17 4,194,352.55 17,805,961.94 3,565,199.67 3,879,971.81 13,925,990.13 27,570,586.40 5,114,897.88 6,189,260.49 21,381,325.91
4 30-Sep-17 5,618,192.75 23,424,154.69 4,775,463.84 8,655,435.65 14,768,719.05 3,227,265.67 30,797,852.07 3,119,457.61 9,308,718.10 21,489,133.97
5 31-Oct-17 9,241,126.14 32,665,280.83 7,854,957.22 16,510,392.86 16,154,887.97 5,591,831.22 36,389,683.29 3,998,789.12 13,307,507.22 23,082,176.07
6 30-Nov-17 19,184,342.52 51,849,623.35 16,306,691.14 32,817,084.00 19,032,539.34 6,689,959.43 43,079,642.72 5,891,456.12 19,198,963.34 23,880,679.38
7 31-Dec-17 12,730,949.40 64,580,572.75 12,094,401.93 44,911,485.94 19,669,086.81 11,854,807.69 54,934,450.41 7,314,644.91 26,513,608.25 28,420,842.16
8 31-Jan-18 6,229,636.05 70,810,208.80 5,606,672.45 50,518,158.38 20,292,050.42 54,934,450.41 5,075,467.54 31,589,075.79 23,345,374.62
9 28-Feb-18 1,863,426.55 72,673,635.35 1,677,083.89 52,195,242.28 20,478,393.07 54,934,450.41 10,100,149.88 41,689,225.67 13,245,224.75
10 31-Mar-18 1,863,426.55 74,537,061.90 1,677,083.89 53,872,326.17 20,664,735.73 4,329,258.49 59,263,708.90 7,269,287.82 48,958,513.48 10,305,195.42
30-Apr-18 6,912,069.75 66,175,778.65 8,335,217.95 57,293,731.43 8,882,047.22
FINANCIAL PROGRESS
80,000,000.00
70,000,000.00
60,000,000.00
50,000,000.00
Planed Income
40,000,000.00 Planed Expenses
Actual Income
Actual Expenses
30,000,000.00
20,000,000.00
10,000,000.00
-
1 2 3 4 5 6 7 8 9 10
MONTHLY PROGRESS REVIEW MEETING REPORT - April Page - 06
PHYSICAL PROGRESS
80,000,000.00
70,000,000.00
60,000,000.00
50,000,000.00
30,000,000.00
20,000,000.00
10,000,000.00
-
1 2 3 4 5 6 7 8 9 10 11 12 13 14
MONTHLY PROGRESS REVIEW MEETING REPORT - April - 2018
Total
Item Total Qty Total Total Ready Ready Cement Sand 3/4 Metal
1 1/2''
Reinforcem 6x9 Rubble Bricks in Tiles in Nos
Description Unit from IPC for Qty for Mix Gr 25 Mix Gr 15 Metal
No. (Bags) (Cube) (Cube) ent in MT (Cube) Nos (Size)
the reporting Temp. (m3) (Cube)
(m3)
month work
1 Ready Mix Gr 25 (m3) m3 1122.7 1068.34
2 Ready Mix Gr 15 (m3) m3 64.6 17.39
3 Site Mix Gr 25 (m3) m3 54.36 441.80 8.07 15.75
4 Site Mix Gr 15 (m3) m3 47.21 216.87 8.84 15.01
5 Reinforcement MT 180.08 180.08
6 RR Masonry m3 218.35 385.78 23.15 100.30
7 Brick work 225 mm
8 Brick work 110 mm
9 Ct Rendering
10 Plastering
11 Tiling
12
13
14
Total Material Qty. as standard or Logical 1,068.34 17.39 1,044.44 40.06 30.76 180.08 100.30 - -
Total Delivered Qty to the Site 1,059.00 18.50 2,746.00 92.90 61.50 196.49 81.75
Material At Site 0.00 0.00 9.00 3.14 0.20 8.90 0.75
Transfer to other site 489.00 10.59
Material used for work (cell 22 - cell 23) 1059.00 18.50 2248.00 89.76 61.30 177.00 81.00
Qty. Used excess (cell 24-cell 21) (9.34) 1.11 1203.56 49.70 30.54 (3.08) (19.30)
Qty. Used excess in % (cell 25/cell 21) -0.9% 6.4% 115.2% 124.1% 99.3% -1.7% -19.2%
Column D - Cumulative figure of the IPC for the reporting month
Raw No: 21, Total Material Qty. as standard or Logical means As per the BSR or based on other norms, material requirement for the work cumulatively
MONTHLY PROGRESS REVIEW MEETING REPORT - DECEMBER
08. VARIATION
Date of
Item No. Description of work Amount Claimed up to last IPC Date of Completion Payment
Commencement