WMS for (Road work)
WMS for (Road work)
530000024
FACTORY PROJECT,
GE-DLF-CBRE-SPCPL-QA-QC MARHOWRAH, BIHAR WMS –GSB(Road Work)
WMS-015 (Rev-0)
APPROVAL STATUS
Sign:
Prabhakar Mudgal Manas Kumar Samal Ananyo Maitra
Name:
Date:
Sign:
SPCPL Page 1 0f 6
Document No. GE- DIESEL LOCOMOTIVE Contract No. 530000024
FACTORY PROJECT,
GE-DLF-CBRE-SPCPL-QA-QC MARHOWRAH, BIHAR WMS –GSB(Road Work)
WMS-015 (Rev-0)
Name:
Date:
CONTENTS
1. SCOPE
2. PURPOSE
3. REFERENCES
6. MATERIALS
7. SUBGRADE PREPARATION
9. SAFETY
SPCPL Page 2 0f 6
Document No. GE- DIESEL LOCOMOTIVE Contract No. 530000024
FACTORY PROJECT,
GE-DLF-CBRE-SPCPL-QA-QC MARHOWRAH, BIHAR WMS –GSB(Road Work)
WMS-015 (Rev-0)
10 . ANNEXURE
SPCPL Page 3 0f 6
Document No. GE- DIESEL LOCOMOTIVE Contract No. 530000024
FACTORY PROJECT,
GE-DLF-CBRE-SPCPL-QA-QC MARHOWRAH, BIHAR WMS –GSB(Road Work)
WMS-015 (Rev-0)
1.0 SCOPE
This work will follow all requirements, specifications, local codes or any
other governing regulatory agency or body after getting employer’s
approval.
2.0 PURPOSE
3.0 REFERENCES
SPCPL Page 4 0f 6
Document No. GE- DIESEL LOCOMOTIVE Contract No. 530000024
FACTORY PROJECT,
GE-DLF-CBRE-SPCPL-QA-QC MARHOWRAH, BIHAR WMS –GSB(Road Work)
WMS-015 (Rev-0)
QA/QC Engineer: He shall be responsible to inspect and perform test as per ITP
Site Engineer: He shall be responsible to perform the job accordingly to the WMS
and daily job schedule. He is also responsible to ensure safety, quality and other
Poclain
JCB
Dozer
Grader/Dozer
Vibro Roller /Smooth Wheel Roller
Hywa (Tipper)
Water Tanker
Auto Level
Total Station
6.0 Materials:
The Material to be used for GSB work shall consist of 20mm,10mm and crusher dust of
suitable proportion and fulfilling grading requirement of Morth Table 400-1( Grading-III).
SPCPL Page 5 0f 6
Document No. GE- DIESEL LOCOMOTIVE Contract No. 530000024
FACTORY PROJECT,
GE-DLF-CBRE-SPCPL-QA-QC MARHOWRAH, BIHAR WMS –GSB(Road Work)
WMS-015 (Rev-0)
Proportion of said material shall be finalized based on mix design. Similarly material
should be confirmed the physical requirement specified in Morth Table-400-2.
Profile and level of sub grade should meet the approved road drawing requirement.
97 %( Min) compaction shall be ensured for sub grade prior to GSB laying.
Rolling shall commence at the lower edge and proceed towards upper
edge longitudinally for portions having unidirectional cross fall or on
super elevation.
Each pass of roller shall uniformly overlap not less than one third of the
track made in the preceding pass.
SPCPL Page 6 0f 6
Document No. GE- DIESEL LOCOMOTIVE Contract No. 530000024
FACTORY PROJECT,
GE-DLF-CBRE-SPCPL-QA-QC MARHOWRAH, BIHAR WMS –GSB(Road Work)
WMS-015 (Rev-0)
During rolling, the grade and cross fall shall be checked and any high
spots or depressions which become apparent, corrected by removing or
adding fresh materials.
Rolling shall be continued till the density achieved is at least 98% of Lab
MDD.
9.0 SAFETY:
SPCPL Site Engineer and Safety Supervisor shall carry out the safety
site inspections to ensure that safety requirements laid out in the safe
work plan are followed before, during and after the work. SPCPL Safety
Engineer / Supervisor shall review HSE Plan and secure Work Permit
shall be obtained prior to start of block work.
During the Period of construction, arrangement for the traffic shall be
provided and maintained.
Wherever necessary barricading and signages will be provided for GSB
work area. The checks shall be conducted prior to commencement of
GSB work.
Work will be started only after getting the work permit from the concerned
department of the project. All equipment’s will have access in site
premise after inspection and verification of documents as well as physical
check by HSE Department.
SPCPL Page 7 0f 6
Document No. GE- DIESEL LOCOMOTIVE Contract No. 530000024
FACTORY PROJECT,
GE-DLF-CBRE-SPCPL-QA-QC MARHOWRAH, BIHAR WMS –GSB(Road Work)
WMS-015 (Rev-0)
10.0 ANNEXURE:
SPCPL Page 8 0f 6