Adl-DS.02-Method of Statement For Static Load Test-Rev.00-10.10.2024
Adl-DS.02-Method of Statement For Static Load Test-Rev.00-10.10.2024
3-10
DOCUMENTS SUBMISSION
Project : Residential Building – Al Khobar. Client: Trouq Al Ammar Real Estate Development Co.
Consultant:
Description
Received By:
PM Signature:
10.10.2024
Attached Documents:
Comments Status
DVC
R.E DATE :
Static load test – Method Statement
Consultant
1
Static load test – Method Statement
1. Purpose
The aim of this Method Statement is to describe the tests procedure that will be
performed on bored cast-in-situ pile. The type and frequency of the tests will be as
follows:
* Compression load test for non-working piles, details of test piles are clarified in
(Attachment-1).
2.1 Scope
This test method covers the procedure for Compression Load Test of Piles to determine
the maximum settlement of pile to an impact static load applied axially by a Kentledge
method at the head of the pile.
➢ The pile will be tested when the strength of the tested cubes taken from the pile
concrete mix achieves the required compressive strength .
➢ The pile head shall be formed to give a plane surface which is normal to the axis of
the pile.
➢ The top level of pile head should be at a minimum height equal to the pile diameter
above the cut-off level.
➢ The top of the pile head will be trimmed to the cutoff level.
➢ Cast the test pile cap with dimension 1.2x1.24x1m (reinforced with steel) or casted during pile casting
considering pile reinforcement should reach up to the top level of pile head.
2
Static load test – Method Statement
B. Kentledge Method
➢ The platform supporting the Kentledge foundations, beams and other supporting
structures shall not experience any differential settlement and has to be verified.
➢ The Kentledge consists mainly of concrete cubes that are 1 x 1 x 1m (2.5 ton) or 1 x 2
x 1m (5 ton) in size, steel girders and beams.
➢ Two rows of cubes will be placed to support the main girders where the steel beams
are then place on top of it.
➢ On top of the steel beams concrete cubes will be loaded then stacked.
➢ The total weight of the cubes and the beams will be equivalent to the axial loading
required.
➢ The clear distance from the edge of the test pile to the nearest part of the main girder
supporting the Kentledge stack in contact with the ground shall be greater than
1.3m.
➢ Movement regular checks (minimum one at every change of load) will be carried by
mean of level instrument based on a benchmark remote.
➢ Indicative sketches for the sake of illustration are attached in (Fig.– 1).
➢ The equipment used for applying load shall consist of hydraulic jacks with total
capacity of 1500 tones, will be fixed against the main girders to deliver the axial load
to the test pile & four nos. of dial gauges which measure the settlement.
➢ Main Contractor will give Engineer 24 hours’ notice before the commencement of any
test.
➢ The test load will be applied by hydraulically jacking against Kentledge load, the load
being measured by tested and certified pressure gauge.
➢ Testing will not commence until it is confirmed that there is no settlement of the
frame and Kentledge.
3
Static load test – Method Statement
➢ The pile settlement will be recorded by means of 4 dial gauges registering against a
reference beam, bearing on prepared flat surfaces fixed to the pile head and normal
to the pile axis.
➢ The support of reference beam shall be at least the greater of three test pile diameters
or 2 meter from the center of test pile.
➢ The dial gauges shall be placed equidistant from the pile axis and from each other.
➢ The dial gauges shall enable readings to be made to an accuracy of at least 0.1 mm.
➢ The hydraulic jacks, pump, hoses, pipes, couplings and other apparatus to be
operated under hydraulic pressure shall be capable of withdrawing a pressure of 1.5
times the maximum pressure used in the test without leaking.
➢ Other construction activities and persons who are not involved in the testing process
shall stay at a sufficient distance from the test to avoid disturbance to the measuring
apparatus.
E. Test Procedure
4
Static load test – Method Statement
Table 1 – Loading & Un-Loading stages for Preliminary piles (200% working load)
5
Static load test – Method Statement
Attachments Table:
Item Discretion
01 Test Piles Details.
02 Pile Load Test Figure (Fig.-1).
03 Loading Procedures and Pressure Calibration Sheet.
04 Site record table.
05 Risk Assessment.
06 Reference: ASTM D-1143.
07 Certificate of calibration
08 Site Photos.
6
Static load test – Method Statement
Attachment 01
7
Static load test – Method Statement
Consultant
8
Static load test – Method Statement
Attachment 02
9
Static load test – Method Statement
Attachment 03
10
Load Vs. Hydraulic
Stress
25 80 36 510
50 160 72 1020
Attachment 04
11
Pile Load Test Record Sheet
Project:
Consultant:
MainContractor:
PillingContractor: DeltaValleys Contracting Co.(DVC)
STATICLOADTESTRECORDSHEETFIRSTCYCLE
Pileno.: Location:
PileDia.: MainSteel:
Pilelength: StartTime:
CastingDate: TestDate:
WorkingLoad: TestLoad:
30
25%
45
60
120
0
15
120min
30
50%
45
60
120
0
15
120min
30
75%
45
60
120
Sheet1
2/20/20199:58AM 1/4
Pile Load Test Record Sheet
Project:
Consultant:
MainContractor:
PillingContractor: Delta Valleys Contracting Co. (DVC)
15
30
45
360min
60
100%
120
180
240
300
360
0
15
120min
30
125%
45
60
120
0
15
120min
30
150%
45
60
120
0
15
120min
30
175%
45
60
120
Sheet1
2/20/20199:58AM 2/4
Pile Load Test Record Sheet
Project:
Consultant:
MainContractor:
PillingContractor: Delta Valleys Contracting Co. (DVC)
0
15
30
45
60
120
180
720min
200% 240
300
360
420
480
540
640
720
0
5
60min
175% 15
30
60
0
5
60min
150% 15
30
60
0
5
60min
125% 15
30
60
Sheet1
2/20/20199:58AM 3/4
Pile Load Test Record Sheet
Project:
Consultant:
MainContractor:
PillingContractor: Delta Valleys Contracting Co. (DVC)
0
5
60min
125% 15
30
60
0
5
60min
100% 15
30
60
0
5
60min
75% 15
30
60
0
5
60min
50% 15
30
60
0
5
60min
25% 15
30
60
0
15
120min
0% 0 0 30
45
60
120
Sheet1
2/20/20199:58AM 3/3
Static load test – Method Statement
Attachment 05
Risk Assessment
12
RISK ASSESSMENT FOR PILE TEST
Crane not operating in Crane lose control Workers, Property Ensure crane operator follows the
accordance with and hit surrounding Supervisors, damage and manufacturer’s instructions
manufacturer’s instruction building and hit Engineers injury to worker 4 3 12
surrounding
workers
Rod may slip & fall Workers Fall on leg Safe handling
on the leg Provide safety shoe
3 3 9 Place the rod safety
Wear leather gloves
While placing the Cut injury
finger may caught
in b/w the rod 2 3 6 Provide proper PPE .
Steel rod fall due to Workers Injury to the Tying should be 3 winding in 3
improper bundling underneath 2 3 6 places in equal distance evenly
Workers person
Crane Steel rod may fall Workers Material damage Two leg slinging should be provided
due to improper & injury to 2 3 6
sling human
Hook may hit on Workers Hook may Proper signal to be given to crane
the wall damage operator
Hit the person 2 3 6
underneath
Steel rod may fall Workers Rod fall down & Provide a latch in the hook
Sling may get hit the person 2 3 6 Check properly
damage
Bundle may loosen Workers Hit the person Check whether the steel rods are
and rod may fall oscillation or not.
due to oscillation 2 3 6 Make sure that it should not fall one
side
Finger may entrap Finger may Finger get injury Tying a rope in a correct location &
in the bundle or de entrap in the proper manner Counter weight
shackle bundle or de should be loaded
Entangled of load shackle 2 3 6
by structure Entangled of
load by
structure
Page 2
RISK ASSESSMENT FOR PILE TEST
Improper way of Workers Person death Barricade working area and posted
concrete block 5 5 25 proper signboard
erection
Rope may snap & Material damage Proper signal to crane operator
steel rod fall down 2 3 6 Slow lifting
due to over load
Heat, Radiation Welders Person injury Aprons shall be worn to reduce the
Effect heat / radiation effect. The
2 3 6 assistance worker of the welder
must wear goggles
Electric Shock All users Fatality, electric It will be ensured that working lead
shock, and return lead are provided without
impartment any break and welding cables holder
damage to and earthing holder shall be in good
materials, heart condition.
fibrillation 5 5 25
Power circuit shall be maintained
proper
Welding
The job should be grounded to the
main earth
Fire Hazard workers Fire may lead to All electrical connections shall be
death of enrouted through ELCB’s and shall
workers, cause be kept away from Gas cylinder
burns storage area
Page 3
RISK ASSESSMENT FOR PILE TEST
High Pressure Hydraulic Oil – Fatality Workers Death Visual check of equipment. Regular
leaks inspection by competent person &
5 5 25 regular maintenance
Ejection of Components under Failure of Structure All users Personal Injury Checks for cap rotation for reaction
load frame stability during test. Minimal
3 3 9 packing to be used, all of suitable
size & quality, positioned between
jack and load cell
Structural failure because of Failure of Structure All users Fatality/ Use only components with
frame parts, couplers, Personal Injury/ calculated SWL within capacity. Do
washers, nuts Material 5 5 25 not load test beyond planned peak
Damage test load. Check actual loads
applied using pressure gauge
Workers or working All user Serious injury or Ensure sufficient lighting in and
machines may be death of workers around works area. High visibility
hit by vehicular and third party clothes tube worn by workers
traffic due to poor damage to 4 4 16
visibility. vehicle
/equipment
Working at night Clearing shrubs Security Injury to person, First aid services are provide
and bushes around May be fatal ,ensure PPE usage, alert the other
sites and during sometimes Security personnel
night round by 5 3 15
security personnel
Heat, Radiation Welder/Helper Skin burning Aprons shall be worn to reduce the
Effect heat / radiation effect. The
Acetylene Cutting 2 2 4 assistance worker of the welder
must wear goggles
Page 4
Static load test – Method Statement
Attachment 06
ASTM D-1143
13
Static load test – Method Statement
Attachment 07
Calibration certificate
14
Static load test – Method Statement
Attachment 08
Site Photos
15