Project BARARI AIN AL FAYDAH-PHASE-2- INFRASTRUCTURE WORK SECTOR B
Developer Q Holding
Consultant KN Consultants
Main Contractor ATGC LLC `
Sub Contractor M Power Equipment Rental
Survey and Setting Out for Storm Water Work
WIR No. Location: Date:
Checked by Checked by Checked by
SN Items to be checked Contractor QC Team Consultant Remarks
N/A
N/A
N/A
Yes
Yes
Yes
No
No
No
1 NOC / Permits
2 Use Instrument for surveying work it's calibrated
3 Setting out prior to excavation done and approved
4 All
work
bench mark and control point are confirmed before start excavation
5 Approved drawing / method statement available
6 Formation level is as per approved drawing
7 Pipe line alignment and level verified as per approved shop drawing
8 Verification
drawing
of Manhole/Chamber co-ordinates & level as per approved
Contractor Site Engineer Contractor QA/QC Inspector Consultant Representative
Name: Name: Name:
Signature: Signature: Signature:
Date: Date: Date:
TGC/QAQC/CHK/CVL/PNT/01 REV-00