DOCUMENT HCC-KEC/CMRL/C4-ECV02/MS/QC/74
NUMBER: Revision: 00
P20C4ECV02PRW-HCKC-QMSWMS-0074(0)
DOC STATUS: P P-Preliminary, D-Definitive, C-Construction Reference, W-Working Drawing,
B-As Built, M-As Manufactured Drawing, E- Employer's Drawing
DATE OF FIRST
21-08-2023 No of sheets: 18
ISSUE:
Environmental
Mr. Saurabh pundy 21-08-2023
Reviewed by;
Page | 1
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
METHOD STATEMENT FOR
PORTAL BEAM ERECTION
TABLE OF CONTENT
PAGE
SL. NO. CONTENTS
NO.
1.0 Introduction 3
2.0 Objective 3
4.0 Abbreviations 3
6.0 Materials 4
12.0 Annexure 15
Page | 2
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
METHOD STATEMENT FOR
PORTAL BEAM ERECTION
1. INTRODUCTION
2. OBJECTIVE
The object of this Method Statement is to lay down a procedure for carrying out the portal
beam erection work for Chennai metro rail CMRL C4-ECV-02 (As per the approved drawings
& relevant technical specifications).
This basic activities described under this method statement are transportation of portal
beam, lifting & erection of Portal beam, levelling of portal beam using hydraulic jacks,
preparation & concreting of pier-portal beam connection portion & stressing of portal beam
4. ABBREVATIONS
CMRL : Chennai Metro Rail Limited
GC : General Consultant
GFC : Good For Construction
IRS : Indian Railway Standard Codes and Specifications
IRC : Indian Road Congress
IS : Indian Standard
ASTM : American Society for Testing and Materials
MS : Method statement
PQP : Project Quality Plan
ITP : Inspection & Test Plan
QC : Quality Control
5. REFERENCE DOCUMENT:
6. MATERIALS
Reinforcement
2 Fe 500D SAIL, RINL, JSW IS 1786
steel
Mechanical
3 Approved source Approved source BS 8110 & ACI 318
Couplers
Hyper-plasticizers &
5 Admixture Approved brand IS:9103
expanding
15.2mm diameter,
6 HT Strands stress relieved, low Approved source As per IS:14268 Class-2
relaxation
As per technical
8 Epoxy mortar Approved source Approved source
specifications & MTC
As per technical
9 Shuttering Oil Approved brand Approved brand
specifications & MTC
S No Description Nos
1 Gantry Girder- 100/150MT 02
3 Heavy duty Multi-axle trailer (Capacity not less than 200MT) As required
Page | 4
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
METHOD STATEMENT FOR
PORTAL BEAM ERECTION
12 Dumpers As required
13 Power Generator 01
31 Cribs 06 nos
Page | 5
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
METHOD STATEMENT FOR
PORTAL BEAM ERECTION
33 MS plate 06 nos
Page | 6
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
METHOD STATEMENT FOR
PORTAL BEAM ERECTION
9. WORKING METHODOLOGY
allowed only after overhead clearance is made and wind speed is normal.
Any unauthorized entry will be strictly prohibited by clearly demarcating work zone.
9.2 Cutting & bending of reinforcement for Pier – Portal beam connection portion
Fe 500D grade reinforcement of approved source shall be used.
Reinforcement cutting and bending shall be done at pre-cast yard and shall be shifted to
desired location as per the construction program.
Bar bending schedule (BBS) shall be prepared & get approved as per approved drawing.
For each bar type total length of the bar (calculated) shall be cut with the help of mechanical
reinforcement cutting machine.
All the cut pieces of steel shall be stacked diameter wise at designated platform free from
moisture. Scrap pieces of steel shall be shifted to scrap yard.
The cut pieces of steel shall be suitable marked & bend to suitable dimension & angle as per
approved BBS.
The bending of steel reinforcement steel shall be done with the help of bending machine
consisting of mandrel & number of holes for the adjustment of bending angle of steel as per
approved Bar Bending Schedule.
The bent-pieces of steel shall be stacked at different locations free from moisture.
9.3 Lifting of Portal beam from stacking yard & loading on trailer
Survey axis of both faces of portal beam shall be suitably marked before lifting.
Lifting frame for portal beam shall be fabricated as per approved drawing.
Lifting of portal beam from the stacking yard shall be done with gantry girder attached with
portal lifting frame as per approved lifting arrangement drawing.
All necessary safety checks for the trailer shall be done before lifting of portal beam as per
attached checklist.
Portal beam shall be loaded on multi-axle trailer of capacity not less than 70MT & is secured
in position properly with necessary tools & tackles.
9.4 Transportation of Portal from loading point to erection point
The route of transportation shall be pre-decided and all approvals from the concerned
authorities, field erection team shall be taken prior to the transportation of portal beam from
precast yard up to the erection point. Safety checklist for the lashing & other arrangements
has been attached.
The transportation of the portal beam will commence only after getting confirmation from
erection location that the site is ready for erection.
During transportation on public roads, each trailer shall be accompanied by escort vehicle.
Portal beam transportation Permit shall be taken before transportation from casting yard.
Trailer inspection checklist should be verified by P&M and ESHS staff before its use.
9.5 Erection and aligning of Portal Beam
The erection crane & trailer shall be moved to the pre-marked location for erection of portal
beam.
Aligning of crane shall be done with steel plates will be put at the out-riggers location to
Page | 9
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
METHOD STATEMENT FOR
PORTAL BEAM ERECTION
Concrete shall be transported to casting location in transit mixer & conveyed to the pouring
location with the boom placer/static pump as per site condition with uniform rate of pour.
Concrete shall be poured in individual layers of maximum 300mm thick & shall be compacted
uniformly with high frequency electrical needle vibrator of 60mm/40mm size vibrator.
Concrete shall be placed into the form gently and shall not drop from a height of 1.5m
Special care shall be taken to fill the concrete at corner & joint locations.
Concrete shall be poured in one stage & no construction joint is allowed.
The concrete at top surface shall be finished to required level.
9.8 Curing of Concrete
Immediately after completion of concreting, concrete shall be cured by covering it with wet
hessian cloth till concrete attains its final setting.
After final setting of concrete, curing of exposed concrete surface shall be done by
continuously wetting the surface with water soaked hessian cloth for a period of 14 days
9.9 Threading of Strands
HT Strands selected for use shall be from approved source
Strands shall be accurately located & maintained inside the duct as per approved drawing.
Tendons shall be so arranged that they have a smooth profile without sudden bends or kinks.
Extra length of Tendon shall be kept beyond the anchorages as per drawing to facilitate
stressing.
All necessary site precautions shall be adopted to avoid any wear & tear, physical damage in
tendons while threading.
9.10 Post tensioning of Portal Beam
After erection the prefabricated steel working platform shall be used for post tensioning
activities such as threading of strands, wedge plate fixing stressing, grouting and recess filling
as per site conditions.
Post tensioning of portal beam shall be done after Cast-In-Situ concreting of Pier-Portal beam
connection portion as per the sequence.
Second stage stressing the Cable T7 & T10, T5 & T6, simultaneously after 28 days of stitch
concreting.
After erection of all U-Girders on Portal beam third stage stressing the Cable T8 & T9. The
stressing sequence may be adjusted after finalization of launching scheme.
Post tensioning shall be done with Multi-strand pull calibrated pressure jacks with concentric
scale type pressure gauges accurate to within 2% of their full capacity
Pressure gauge shall be so selected that when the tendon is stressed to 75% of its breaking
load, the gauge is reading between 50-80% of its full capacity
Stressing of the tendons are carried out simultaneously from both ends after concrete
achieves the required strength.
Before stressing, following are to be checked and recorded in the stressing format:
Stressing force required at jacking end & stages of stresses at 50Kg/cm2 interval till we reach
Page | 11
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
METHOD STATEMENT FOR
PORTAL BEAM ERECTION
While stressing from one end only, the slip at the end remote from the jack shall be measured
& an appropriate allowance shall be made in the measured extension at the jacking end.
All grout components shall be mixed in grout mixer & to keep the grout in homogeneous state
& of uniform consistency, the mixer should have an additional storage device with agitator to
keep the grout moving continuously before it is pumped into the duct.
Grouting shall be done with mechanical operated calibrated grout pump fitted with a pressure
gauge to enable pressure of injection to be controlled.
At the time of grouting density of grout shall be checked with hydrometer to ascertain that it
should be in line with the design density. Temperature shall not be exceed 25 degree Celsius
Injection of grout must be continuous & shall not be interrupted till the completion of
grouting.
Page | 13
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
METHOD STATEMENT FOR
PORTAL BEAM ERECTION
Grouting shall be done initially with a low pressure of 0.3 Mpa increasing it until the grout
comes out at the other end. The grout shall be made to free flow from the outer end until the
consistency of grout at the outer end is the same as that of injection end. When consistency
of grout becomes same at both ends, the outer end shall be closed off & building up of
pressure shall be commenced.
Samples of grout shall be collected in cubes of 100x100x100mm size from the outer end
during the grouting.
Minimum 02 sample (6 Number of cubes) shall be collected.
Full injection pressure of 0.5 Mpa shall be maintained for at least one minutes before closing
the injection pipe.
If in any case, there is a buildup pressure much in excess of 1.0 Mpa without flowing of grout
at the outer end, the grouting shall be discontinued & the entire duct shall be flushed with
high pressure water.
Grout shall be used within 30 minutes of its mixing.
After the completion of grouting, the projecting portion of the vents shall be cut off.
9.13 Concreting of anchorage recess portion
The entire recess area shall be cleaned with wire brush to remove all surface laitance,
unevenness or irregularities.
Reinforcements shall be fixed in the recess portion as per drawing.
Bonding agent should be applied on the old concrete surface to new concrete.
Shutters shall be installed at required anchorage location leaving a suitable gap in the
formwork for the pouring of required material
Entire recess area shall be filled with concrete as mentioned in the drawing.
All shutters of recess filling shall be removed after 24 hours of concreting.
Curing of recess filling shall be done by continuously wetting the surface with water soaked
hessian cloth for a period of minimum 14 days or curing compound shall be applied after de-
shuttering
10.QUALITY ASSURANCE AND QUALITY CONTROL
Quality Assurance and Quality Control shall be strictly followed as per approved ITP and
Method Statement and attached formats.
Vest etc.
Work Permit System shall be followed for the medium and high risk activities as per laid down
procedure.
Safety Harness while working at height and Face Shield with suitable dark glass for welding
work shall be used.
The work area shall be properly barricaded as laid down in the lift/construction depot plan.
Working platform of adequate strength with handrail shall be provided for work at height as
per IS 3696: 1991
Access Control shall be exercised to check the un-authorized person within construction area.
First aid box & fire extinguishers shall be kept at site.
Operator, Workmen and Foreman shall have adequate knowledge and experience.
Traffic marshals shall be deployed to assist the movement of trailers for smooth traffic flow.
Trailers and Lifting Devices (Cranes & Tackles etc.) shall be inspected before operations to
ensure safe working condition.
Safe transportation shall be ensured by deploying suitable capacity trailer with safe and easy
maneuverability during radial turnings in curved roads.
Trailers shall be fitted with side lamps, tail lamps, audible alarms for safe transportation and
warning to general public using the roads.
Lifting Equipment’s, Gantries, Tools and tackles shall have third party load test certificates
from Competent Person.
Approach roads must be cleared and traffic diversion plans shall be strictly adhered to, while
transportation of Precast Elements.
Persons shall not be allowed under the suspended load while lifting load.
Environmental aspects/impact shall be identified and appropriate mitigation measures shall
be taken during execution of work as per Project Safety, Health & Environment Plan.
Utilization of water and non-renewable sources like materials, fuel and energy shall be
optimized during work.
Spillage of oil & other shall be controlled from all pertinent operations.
Hazardous waste generated during work shall be managed, stored, and disposed as per rule
& condition of authorization.
12.ANNEXURES
Inspection Test Plan
Site Preparation
Tool Box Talk on Pre Cast Element Lifting
Pre-Lift Checklist
Checklist for Trailor Erection
Lift Evaluation Form
EIC Pre-Lift
Transport Permit
Post Concrete Checklist
Trailor erection
Page | 15
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
METHOD STATEMENT FOR
PORTAL BEAM ERECTION
Dispatch Checklist
Safety Checklist
Reinforcement Checklist
Grouting Record
Post pour inspection
Recess Checklist
Stressing Record
HIRA
Page | 16
HCC-KEC/CMRL/C4-ECV02/MS/QC/74
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot,
Katupakkam, Kumanan Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee Bypass & Associated Viaduct from
Chainage 17982.240 to Chainage 25928.186 and Approach to Depot at Poonamallee & All Associated works
Engineer
Engineer
Incharge
REFERENCE DOCUMENTS /
QA/QC
Section
CMRL
Sl No ACTIVITY DESCRIPTION ACCEPTANCE CRITERIA FREQUENCY VERIFYING DOCUMENTS EVALUATIO Remarks
Site
STANDARDS
N SOURCE
Prior to commencement
Contract Specifications / or any Notice of no objection certificate from Notice of no objection
1.4 Source of materials of work / Change of HCC-KEC NA H H R
additional approved vendor CMRL / GC / Approved status certificate from CMRL / GC
source
Once for each grade and
type of
Notice of no objection
1.5 Concrete mix design Technical specifications / IS Code Approved concrete mix design concrete and Prior to HCC-KEC R H P R
certificate from CMRL / GC
production
commencement
Approved method statement / Prior arrangements to be made Prior to commencement
1.6 Plant and equipment Visual inspection HCC-KEC R P H R
Contract specifications berfore start of production of work
Calibration of batching plant / Notice of Approval from CMRL/GC for RMC plants /
Approval of batching plant / RMC Prior to commencement
1.7 IS:4925 no objection certificate from CMRL / Trial run of the CMRL plant with clearance HCC-KEC R R P/H R
plant of work
GC certificate
Once prior to start and
Calibration certificates for
subsequent periodical Site laboratory plan / External laboratory HCC-KEC /
1.8 Measuring equipment / Load test Contract specifications To be made available R P H R
calibration as per calibration / Manufacturer laboratory External lab
certificate
calibration plan
2.0 MATERIAL RECEIPT, STORAGE, HANDLING AND DELIVERY
2.1.2 Sampling and testing Refer to ITP of reinforcement bars Sampling record / Test report HCC-KEC R R H W/R
Page 1 of 4
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot,
Katupakkam, Kumanan Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee Bypass & Associated Viaduct from
Chainage 17982.240 to Chainage 25928.186 and Approach to Depot at Poonamallee & All Associated works
Engineer
Engineer
Incharge
REFERENCE DOCUMENTS /
QA/QC
Section
CMRL
Sl No ACTIVITY DESCRIPTION ACCEPTANCE CRITERIA FREQUENCY VERIFYING DOCUMENTS EVALUATIO Remarks
Site
STANDARDS
N SOURCE
Compaction and levelling of ground Method Statement / Technical Ground shall be firmly compacted before Before commencement of
3.1.1 Visual inspection HCC-KEC P R R W
surface Specification positioning of crane work
Approved method statement / Item 3.1 to 3.3 is properly implemented, Pre-Pour Checklist
3.2.1 Final inspection prior to concrete Each Portal Beam HCC-KEC P R P H/W
Construction drawings recorded and accepted
3.4.1 HT Strands Technical specifications / IS Code Approved HT Strands / MTC Every Lot MTC / Delivery challan / Inspection report HCC-KEC P R R W/R
3.3.2 Physical Check Technical specifications / IS Code Packed properly free from rust Every Lot MTC / Delivery challan / Inspection report HCC-KEC P R R W
Page 2 of 4
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot,
Katupakkam, Kumanan Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee Bypass & Associated Viaduct from
Chainage 17982.240 to Chainage 25928.186 and Approach to Depot at Poonamallee & All Associated works
Engineer
Engineer
Incharge
REFERENCE DOCUMENTS /
QA/QC
Section
CMRL
Sl No ACTIVITY DESCRIPTION ACCEPTANCE CRITERIA FREQUENCY VERIFYING DOCUMENTS EVALUATIO Remarks
Site
STANDARDS
N SOURCE
3.3.3 Sampling and testing Refer to ITP of HT Strands HCC-KEC/CMRL/ECV02/ITP/11 Revision:R-00 HCC-KEC R R H W/R
3.4 Grouting
3.4.1 Grout Material Technical specifications / IS Code Approved Material / MTC Every Lot P R R W/R
Approved method statement / Mix should be homogeneous and uniform Grot record checklist HCC-KEC
3.4.2 Grout Mix Every new mix P R R H
Construction drawings / IS Code consistency
Page 3 of 4
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot,
Katupakkam, Kumanan Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee Bypass & Associated Viaduct from
Chainage 17982.240 to Chainage 25928.186 and Approach to Depot at Poonamallee & All Associated works
Engineer
Engineer
Incharge
REFERENCE DOCUMENTS /
QA/QC
Section
CMRL
Sl No ACTIVITY DESCRIPTION ACCEPTANCE CRITERIA FREQUENCY VERIFYING DOCUMENTS EVALUATIO Remarks
Site
STANDARDS
N SOURCE
Legend: H= Hold, R = Review, W= Witness, P = Perform, S= Submit, RW= Random Witness, HCC-KEC CONSORTIUM = CONSORTIUM of HCC & KEC, CMRL = Chennai Metro Rail Ltd.
Critical Category is Hold Point This activity requires inspection / verification and acceptance by CMRL Responsible for the stage before further processing is permitted.
This activity requires inspection / verification, and acceptance by the CMRL responsible for this stage before any further processing is permitted.
Major Category is Wittness Point
HCC-KEC CONSORTIUM / Sub-Contractor shall not process activity beyond a witness point without written approval by CMRL. The related quality records shall be submitted to CMRL for their review.
Page 4 of 4
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass
Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam, Kumanan
Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee
Bypass & Associated Viaduct from Chainage 17982.240 to Chainage 25928.186 and
Approach to Depot at Poonamallee & All Associated works
Doc no: HCC-KEC/CMRL/C4-ECV02/MS74/CL/ 01
CMRL Doc No. P20C4ECV02PRW-HCKC-QMSCHS-0074(1)
Employer : Chennai Metro Rail Limited
Contractor : HCC-KEC Consortium
Project : CMRL C4 ECV02
Portal beam Date of checking:
identification: Date of casting:
CHECKLIST FOR SITE PREPARATION
Observation
S No Description Remarks
Yes No
Sign
Name
Designation
Date
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass Crossing,
Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam, Kumanan Chavadi, Karayan
Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee Bypass & Associated Viaduct
from Chainage 17982.240 to Chainage 25928.186 and Approach to Depot at Poonamallee & All
Associated works
Doc no: HCC-KEC/CMRL/C4-ECV02/MS74/CL/ 02
CMRL Doc No. P20C4ECV02PRW-HCKC-QMSCHS-0074(2)
Project: CMRL C4 ECV03
Client: Chennai Metro Rail Limited (CMRL)
Contractor: HCC-KEC Consortium
Tool Box Talk on Pre Cast Element Lifting & Erection
Location Details Name & Chainage S.No.
Activity Date:
AA.Useful General Topics (Please tick " " the topic covered in tool box or write it)
Overhead Power
1 House keeping 8 15Illumination
transmission
2 Hand tools 9 Crane Operation 16.Personnel
Transit Mixture/Concrete
3 Power tools 10 17.Working at Height
Pump
4 Excavation 11 Trailer Operation 18.Diversions
5 Loading/Unloading 12 Mobile Equipments 19.Traffic
6 Lifting & Shifting 13 Permit to work 20. Others (Pl specify)
7 Life Line 14 Working Platform 21) Edge Protection
4 Trailor 8.JCB
CC:Critical Hazard & its control (To be written by concerned exexcution supervisor/Engineer)
DD.Attendance of persons participating on tool box (includes all staffs,workmen & subcontractor employee)
14 Spare tyres
B Driver Requirements
Name
Designation
Date
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass
Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam, Kumanan Chavadi,
Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee Bypass & Associated
Viaduct from Chainage 17982.240 to Chainage 25928.186 and Approach to Depot at Poonamallee &
All Associated works
PORTAL BEAM TRANSPORT PERMIT FROM PCY
Doc no: HCC-KEC/CMRL/C4-ECV02/MS74/CL/ 07
CMRL Doc No. P20C4ECV02PRW-HCKC-QMSCHS-0074(7)
Date: Vehicle type and Reg. No:
Time of dispatch:
Whether Brakes, Main horn, Back horn, all lights and wipers are
3
working?
Name
Designation
Date
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass
Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam, Kumanan
Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee
Bypass & Associated Viaduct from Chainage 17982.240 to Chainage 25928.186 and
Approach to Depot at Poonamallee & All Associated works
Doc no: HCC-KEC/CMRL/C4-ECV02/MS74/CL/ 08
CMRL Doc No. P20C4ECV02PRW-HCKC-QMSCHS-0074(8)
Employer : Chennai Metro Rail Limited
Contractor : HCC-KEC Consortium
Project : CMRL C4 ECV02
1* Surface finish OK
All inserts Bearing Pedestal, shear key, Safety sleeves, earthing rod,
10
drainage pipe & drain sprout, and lifting hole etc, are in position
NOTE: DEVIATION DETAILS ("NO" IN CASE OF 1,2,4,7 & 8 AND "YES" FOR 5,6)
Sign
Name
Designation
Date
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass
Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam, Kumanan Chavadi,
Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee Bypass &
Associated Viaduct from Chainage 17982.240 to Chainage 25928.186 and Approach to Depot at
Poonamallee & All Associated works
Doc no: HCC-KEC/CMRL/C4-ECV02/MS74/CL/ 09
CMRL Doc No. P20C4ECV02PRW-HCKC-QMSCHS-0074(09)
Employer : Chennai Metro Rail Limited
Contractor : HCC-KEC Consortium
Project : CMRL C4 ECV02
Portal Beam Type: Date of checking:
Portal Beam identification: Date of casting:
CHECKLIST FOR PRECAST ELEMENT DISPATCH FROM PC YARD TO SITE
Observation
S No Description Remarks
Yes No
1 Any NCR / SOR's closing Pending?
2 All dimensions checked ( L*B*D) and found ok
Precast Element Nomenclature along with
3
direction is mentioned as per standard
Shear key, Bearing pedestal, Stitch concrete
4 dowels / coupler and stitch concrete ducts are
provided as per drawing
5 Curing period completed
6 Inhibitor Solution is applied in all the dowels
Surface Finishing has been done and there are no
7
Honeycombs over the surface of the Pier cap
Post Concrete Inspection Check list has been
8
approved?
Name
Designation
Date
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass
Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam, Kumanan
Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee
Bypass & Associated Viaduct from Chainage 17982.240 to Chainage 25928.186 and
Approach to Depot at Poonamallee & All Associated works
Doc no: HCC-KEC/CMRL/C4-ECV02/MS74/CL/ 10
CMRL Doc No. P20C4ECV02PRW-HCKC-QMSCHS-0074(10)
Employer : Chennai Metro Rail Limited
Contractor : HCC-KEC Consortium
Project : CMRL C4 ECV02
SAFETY CHECKLIST
Sign
Name
Designation
Date
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass
Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam, Kumanan
Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee
Bypass & Associated Viaduct from Chainage 17982.240 to Chainage 25928.186 and
Approach to Depot at Poonamallee & All Associated works
Name
Designation
Date
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai
Bypass Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam,
Kumanan Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus,
Poonamallee Bypass & Associated Viaduct from Chainage 17982.240 to Chainage
25928.186 and Approach to Depot at Poonamallee & All Associated works
Name
Designation
Date
Project: CMRL C4-ECV-02: Construction of Elevated Metro Stations at Chennai Bypass
Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam, Kumanan
Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus, Poonamallee
Bypass & Associated Viaduct from Chainage 17982.240 to Chainage 25928.186 and
Approach to Depot at Poonamallee & All Associated works
Cable No Cable No
Ram Ram
Pressure Difference Cumulative Dead End Pressure Difference Cumulative Dead End
reading Reading
(Kg/cm2) (mm) (mm) Reading (Kg/cm2) (mm) (mm) Reading
(mm) (mm)
Cumulative Elongation A= A=
Live End slip B= B=
Grip elongation C= C=
Dead End Slip D= D=
Total elongation E=A-B-C-D= E=A-B-C-D=
Pressure(%) Elongation(%) Pressure(%) Elongation(%)
Stressing Agency HCC-KEC Consortium CMRL / GC
Sign
Name
Designation
Date
HCC-KEC JV HAZARD IDENTIFICATION AND RISK
ASSESSMENT
Doc. No: CMRL/ECV02/ESHS/HIRAF/07
Chennai Metro -C4 Rev: 00
Package No.: ECV02
CONTRACTOR HCC KEC Consortium LOADING, TRANSPORTATION AND ERECTION OF Portal Beam
Activity
NAME:
Contract: CMRL /Phase II/ C4 ECV02 Date of Preparation 23/08/2023
L = Low priority to be implemented when resources allow. M = Medium priority to be H = High priority to be acted on immediately.
RISK RANKING:
scheduled as soon as practicable.
Mr. Md. Naziruddin (Manager), Mr. Prem Kumar (Sr. Engineer), Mr. Irfan B (Sr. Manager ESHS), Mr.Mubarak (Sr. Manager ESHS)
TEAM:
Unauthorized Gantry rail hit Y Workmen/ 5 5 25 Proximity sensors shall be fixed on gantry crane all the four 1 5 5 A
person entry or run over Staff sides.
into the gantry the person Lifting area shall be cordoned off.
movement No unauthorized entry sign boards shall be displayed.
area/ All workmen shall be educated on tool box talks not to
unprotected stand under suspended loads.
lifting zone
No visibility of Load and Y Workmen/ 5 5 25 Minimum 55 Lux shall be ensured in the working area. 1 5 5 A
lifting zone to gantry struck Staff During adverse weather condition, gantry crane shall be
the operator with other stopped.
object and Lifting zone shall be maintained obstruction free without
person any hindrance to the activity.
Over speed and Derailing of Y Workmen/ 5 5 25 Maximum 5Km/hr speed allowed for gantry crane 1 5 5 A
defective railing gantry crane Staff operation.
arrangements Gantry crane shall be inspected in proper intervals and
of gantry recorded.
Synchronization shall be done for both the gantries in case
of tandem lifting.
Alcohol test shall be carried out for operators specially on
night shifts, weekends.
Transportation of Portal Beam Puller / Axle Y Workmen/ 5 5 25 Puller / Axle capacity shall be ensured with respect to the 1 5 5 A
Portal Beam loaded on structure may Staff/ weight of Portal Beam.
inadequate failure Public Portal Beam loading shall be done on the fabricated frame
capacity of fixed with Axle Bed
Puller / Axle Vehicle age criteria shall be considered while engaging
the trailer. i.e Own vehicles- 10 years, hired-5 years.
The route of transportation shall be pre-decided and all
approvals from the concerned authorities shall be taken
prior to the transportation of U-Girder from precast yard up
to the erection locations.
The transportation of Portal Beams shall commence only
after getting the confirmation from erection location that
the site is ready for erection.
Squad team with red flags shall be deployed while
transporting the Portal Beam throughout the length of
travel.
Trial run will be carried out with skeleton frame/structural
steel frame (max length of Portal Beam) once before the
commissioning of work
Inadequate or Toppling of Y Workmen/ 5 5 25 Portal Beam shall be secured on the Axle by using Chains 1 5 5 A
sub-standard Puller / Axle Staff/ /ratchet belts.
securing along with the Public Suitable fabricated frames shall be provided on the Axle
arrangements load bed
HCC-KEC JV HAZARD IDENTIFICATION AND RISK
ASSESSMENT
Doc. No: CMRL/ECV02/ESHS/HIRAF/07
Chennai Metro -C4 Rev: 00
Package No.: ECV02
Defective Chain latching & ratchet belts should not be
used.
Rash driving should not be allowed.
Road transport lashing checklist shall be followed.
Using of Vehicle Y Workmen/ 5 5 25 All Puller/Axle documents shall be submitted to P&M dept. 1 5 5 A
Defective Puller collision/ Staff/ & verified.
/ Axle person hit by Public Inspection tag shall be displayed on Puller/Axle
Puller/Axle Operator should check the vehicle condition on daily basis
due to brake and daily operator inspection checklist shall be followed.
failure, Tyre condition, tyre pressure should be ensured during daily
bursting of inspection.
tyres etc.,
Unauthorized Vehicle Y Workmen/ 5 5 25 Driver should possess valid driving license and competency 1 5 5 A
driver collision/ Staff/ certificate.
person hit by Public Do not leave the key during shift change.
Axle/Puller
Unmanned Vehicle Y Workmen/ 5 5 25 Reverse horn shall be ensured in the trailer. 1 5 5 A
reversing collision/ Staff/ Banksman/marshal shall be deployed to monitor the
person hit by Public reversing vehicle.
trailer
Positioning of Placing the Collapse of Y Workmen/ 5 5 25 Crane shall be positioned on firm ground and level surfaces 1 5 5 A
crane crane un- crane while Staff/ only.
compacted lifting the load Public If the area identified as backfilled, Steel/MS plate shall be
surface/ provided.
SWD/Drainage/ Crane outriggers shall be fully extended while placing the
Uneven surface crane.
Padding shall be provided where the ground level differs.
Drainages shall be marked and crane should not be
placed above drainages.
Outriggers Collapse of Y Workmen/ 5 5 25 Area shall be levelled to place the outriggers. 1 5 5 A
placed on crane due to Staff/ Padding shall be provided to place the outriggers.
ground without settling of Public Crane outriggers shall be fully extended while placing the
padding crane crane.
arrangements MS plate shall be used wherever required.
Crane placed Collision with Y Workmen/ 5 5 25 Live road shall be diverted with warning sign boards. 1 5 5 A
on live road outside Staff/ Water barriers, traffic cones shall be used for traffic
without vehicle, public Public diversion.
precautions Marshal shall be deployed with blinkers.
Adequate illumination shall be ensured.
Unauthorized person shall not be allowed in the working
area.
HCC-KEC JV HAZARD IDENTIFICATION AND RISK
ASSESSMENT
Doc. No: CMRL/ECV02/ESHS/HIRAF/07
Chennai Metro -C4 Rev: 00
Package No.: ECV02
Non availability Crane hit by Y Workmen/ 4 5 20 Crane swing area shall be barricaded minimum 6m from 1 5 5 A
of swing area person and Staff/ the crane.
barricade vehicle Public Barricades shall be readily available in the work area prior
to start the activity
No one should be allowed to work/move on crane swing
area.
Other vehicles shall not be allowed in the crane working
area.
Work at height Unsafe access falling of Y Workmen/ 4 4 16 Access shall be provided by Cherry picker/Man lift. 1 4 4 A
person from Staff maximum two persons allowed to use the cherry
height picker/man lift in the same time.
Users shall be provided with full body harness and lanyard
shall be anchored with the handrails.
Cherry picker/man lift statutory documents shall be
submitted to P&M, EHS dept.
Third party inspection shall be done for Cherry picker/man
lift.
Operator should possess valid driving license with Identity
card, competency and training certificate.
Outriggers/Jacks shall be fully extended if applicable.
Inspection tag shall be provided to the vehicle.
User should be familiar with the hand signalling.
Inadequate falling of Y Workmen/ 5 5 25 Adequate width of the platform shall be ensured. 1 5 5 A
width of person, Staff Handrails, mid rails shall be provided firmly.
platform, edge materials from Gaps shall be checked to avoid man, material falling.
protection and height Toe guards shall be ensured in the platform.
fall protection
Inadequate Falling of Y Workmen/ 5 5 25 PPE rope will be tied end to end of girder flanges in 2 or 3 1 5 5 A
anchoring person from Staff layers for edge protection.
arrangements height Anchoring of safety harness will be done in the exposed
for fall protection steel of the shear key.
during Portal
Beam erection
Using of Vehicle Y Workmen/ 5 5 25 Crane shall be inspected by third party and certificate shall 1 5 5 A
defective crane collision/ Staff be obtained.
person hit by All crane documents shall be submitted to P&M dept. &
crane due to verified.
brake failure, Inspection tag shall be displayed on the crane.
bursting of tyres Operator should check the vehicle condition on daily basis
etc., and daily operator inspection checklist shall be followed.
Tyre condition, tyre pressure should be ensured during daily
inspection.
HCC-KEC JV HAZARD IDENTIFICATION AND RISK
ASSESSMENT
Doc. No: CMRL/ECV02/ESHS/HIRAF/07
Chennai Metro -C4 Rev: 00
Package No.: ECV02
Improper rigging Detachment Y Workmen/ 5 5 25 Competent riggers, signal man and lifting supervisor shall 1 5 5 A
arrangements of load, Staff be deployed.
while lifting the toppling of Safe rigging procedures shall be followed.
bearing & steel crane Load shall be secured firmly to avoid free falling.
plate. Crane working radius and SWL shall be ensured.
Capacity of the crane shall be always considered.
Lifting frame should be tested by approved third party.
Defective tools & tackles should not be used.
Walkie-talkie shall be used for signalling if required.
Using of Fall of load due Y Workmen/ 5 5 25 All lifting tools & tackles shall be inspected by approved 1 5 5 A
defective lifting to Failure/ Staff third party and TPI certificates shall be available.
tools damage of Visual inspection shall be carried out for tools & tackles for
tools and each lifting work by lifting supervisor/Riggers.
tackles Colour coding shall be ensured.
Defected tools and tackles shall be cut and removed from
site.
Make shift arrangements shall not be entertained.
Permit system shall be followed.
Lifting the Load hit with N Workmen/ 4 4 16 Guide rope shall be used with minimum 20mm dia. 1 4 4 A
bearing, steel other objects, Staff Sufficient length of guide rope shall be used.
plate without man and Guide rope shall be ensured prior to start the lifting activity.
using the tag line machinery Damaged guide rope shall not be used.
Improper Falling of Y Workmen/ 5 5 25 Bearing, steel plate shall be secured firmly before de- 1 5 5 A
installation bearing, steel Staff slinging.
method/ de- plate from Spanners and other tools shall be secured from falling.
slinging without height Only trained workforce shall be deployed.
securing against Illumination level shall be ensured.
fall of bearing, Toolbox talk shall ensure the same.
steel plate.
Fingers Caught Cut and N Workmen/ 5 5 25 Activity sequence shall be followed. 1 5 5 A
in between abrasion injury, Staff All workers shall be provided with cut resistance hand
bearing and Permanent gloves.
pedestal disability Only trained workforce shall be engaged in the activity.
Portal Beam Parking on live Vehicle hit to Y Workmen/ 5 5 25 Working area shall be cordoned off. 1 5 5 A
loaded Axle road without public/ Staff/ Traffic barriers, cones and traffic marshals shall be ensured
parking on barricade the pedestrians Public If required traffic diversion shall be done, alternative routes
erection spot to area and vehicle shall be identified.
unload collision Unauthorized entry sign boards shall be displayed.
HCC-KEC JV HAZARD IDENTIFICATION AND RISK
ASSESSMENT
Doc. No: CMRL/ECV02/ESHS/HIRAF/07
Chennai Metro -C4 Rev: 00
Package No.: ECV02
Inadequate Obstruct the Y Workmen/ 4 4 16 Minimum 55 lux shall be maintained at the working area. 1 4 4 A
visibility to the operator and Staff/ Backup DG shall be ensured to overcome power failures.
operator due to others visibility Public Dedicated electrician shall be deployed at the working
poor illumination in the work area.
area Activity shall not be carried out during power cut.
Axle parked on Axle run over N Workmen/ 4 4 16 Axle shall not be parked on steep road. 1 4 4 A
steep road, the public, Staff/ Wedge stoppers shall be provided on trailer tyres.
failure to provide workers, Axle Public Axle driver shall be instructed about the risk involved.
stoppers on tyres hit with the
equipment.
Person taking Trailer run over Y Workmen/ 4 4 16 No one shall allowed to take rest at site, access and under 1 4 4 A
rest under the the workers Staff any vehicle.
trailer/ persons Workmen rest room shall be provided at site.
sleeping on All workers shall be instructed to take rest at workmen rest
vehicle access room only.
Lifting and Unauthorized Falling of Portal Y Workmen/ 4 4 16 Lifting area shall be cordoned off. 1 4 4 A
erection of Portal entry into the Beam on Staff/ No one shall be allowed to stand/work under the
Beam lifting zone public, Public suspended load.
workmen No unauthorized entry sign boards shall be displayed.
All workmen shall be instructed on tool box talks.
Traffic diversion plan shall be provided for each erection
work separately section wise and obtain approval before
commencement of activity
Inexperienced Fall of load, Y Workmen/ 5 5 25 Only authorized crane operators, riggers, signal man, lifting 1 5 5 A
lifting supervisor, toppling of Staff/ supervisors shall be engaged in the activity.
riggers and crane, struck Public Authorization card, identity card shall be used to the crane
signal man and onto other operators, riggers, signal man, lifting supervisors.
operator object Only signal man will give signal to the crane operator.
Permit system shall be followed.
Using of Fall of load due Y Workmen/ 5 5 25 All lifting tools & tackles shall be inspected by approved 1 5 5 A
defective lifting to Failure/ Staff third party and TPI certificates shall be available.
beam, tools and damage of Visual inspection shall be carried out for tools & tackles for
tackles tools and each lifting work by lifting supervisor/Riggers.
tackles Colour coding shall be ensured.
Defected tools and tackles shall be cut and removed from
site.
Make shift arrangements shall not be entertained.
Permit system shall be followed.
Failure of lifting Fall of load due Y Workmen/ 5 5 25 Lifting tools and tackles capacity shall be considered with 1 5 5 A
tools & Tackles to lifting tools & Staff respect to the lifting load.
tackles failure All lifting tools & tackles shall be inspected by third party.
Visual inspection shall be done for tools and tackles before
every lift.
Visual inspection shall be carried out for each lifting work
by lifting supervisor/Riggers.
HCC-KEC JV HAZARD IDENTIFICATION AND RISK
ASSESSMENT
Doc. No: CMRL/ECV02/ESHS/HIRAF/07
Chennai Metro -C4 Rev: 00
Package No.: ECV02
Colour coding shall be ensured.
Defected lifting tools and tackles shall be cut and removed
from site.
Make shift arrangements shall not be entertained.
Permit system shall be followed.
Erection area shall be barricaded and no unauthorized
entry sign boards shall be displayed.
Using of unfit Crane Y Workmen/ 5 5 25 Minimum each 400T / 450T capacity crane shall be 1 5 5 A
cranes collapse, Staff engaged in the Portal Beam erection work.
Toppling of All crane documents shall be submitted to P&M, EHS dept.
crane, Falling Crane inspection tag shall be ensured.
of loads. TPL Vehicle aging norms shall be considered.
Crane capacity shall be considered with respect to the
load and third party inspection shall be carried out.
Maintenance shall be carried for the crane as per
maintenance schedule.
Daily operator inspection checklist shall be followed.
Permit system shall be followed.
Overload the Crane Y Workmen/ 5 5 25 Tandem lifting shall be adopted for the Portal Beam 1 5 5 A
cranes collapse, Staff erection work.
Toppling of SWL shall be reduced at least 25% while load calculations
crane, Falling for tandem lifting.
of loads. Crane capacity shall be considered with respect to the
load and third party inspection shall be carried out.
Minimum each 400T capacity crane shall be engaged in
the Portal Beam erection work.
SWL and working radius shall be ensured as per the load
chart.
Pre lift checklist shall be prepared and Permit system shall
be followed.
Crane inspection tag shall be ensured.
Competent lifting team shall be engaged.
Extend the Crane boom Y Workmen/ 5 5 25 Boom limit switch & hoist limit switch shall be checked. 1 5 5 A
boom while collapse Staff Safe working load shall be checked as per the load chart
lifting for the particular boom length before extending the crane
boom.
Crane operator should aware of the load calculation and
load chart.
Unauthorized Vehicle Y Workmen/ 5 5 25 Crane operator should possess valid driving license, 1 5 5 A
person operate collision/ Staff/ operator competency certificate.
the crane person hit by Public Do not leave the key in cabin during shift change.
crane Unauthorized person should not be operate the crane
under any circumstance.
HCC-KEC JV HAZARD IDENTIFICATION AND RISK
ASSESSMENT
Doc. No: CMRL/ECV02/ESHS/HIRAF/07
Chennai Metro -C4 Rev: 00
Package No.: ECV02
Inadequate Obstruct the Y Workmen/ 4 4 16 Minimum 55 lux shall be maintained at the working area. 1 4 4 A
illumination on operator and Staff Backup DG shall be ensured to overcome power failures.
lifting zone others visibility Dedicated electrician shall be deployed at the working
in the lifting area.
zone Activity shall not be carried out during power cut.