Earned Value As A Tool For Control
Earned Value As A Tool For Control
Cost
SPI CPI Performance
Schedule Index
Performance SPI=EV/PV • CPI=EV/AC • A measure of
Index how close the
A measure of project is to
how close the spending on the
project is to work performed
Index Values
performing work to what was
< 1: over budget or behind schedule
as it was actually planned to have
>1: under budget or ahead of schedule
scheduled been spent
How to Measure Earned Value
Earned Value Management Terms
• EV: Earned Value
• AC: Actual Cost
• PV: Planned Value
• BAC: Budget At Completion
• EAC: Estimation At Completion
• VAC: Variance At Completion
• SV: Schedule Variance
• CV: Cost Variance
• SPI: Schedule Performance Index
• CPI: Cost Performance Index
• To determine Budget of remaining work =BAC-EV
• To determine remaining Funds= BAC-AC
• Note that we Use SPI and SV to see if the project within the schedule or not
whereas we use CPI and CV to see if project within budget or not
Cost Performance
1. Cost Variance (CV) = BCWP ACWP
+ve Under Budget (cost)
Cost Variance 0 Within Budget (on cost)
- ve Over Budget (cost)
5 C 8
7 3 10
0 A 2 2 B 5 10 10
FINISH
0 2 2 0 3 7 10 10
5 D 7 7 E 10
0 2 7 7 3 10
E 0 0 0 - - - -