Contingency

planning evolution
By Shri Karve

The key to disaster recovery and business continuity today is operational resilience. As the relentless
application of technology continues we must attempt to create an arena in which we can protect these
technological advancements. Our reliance on 24/7/365 IT availability means that the success of any
Disaster Recovery Centre is measured in milliseconds.

Many Disaster Recovery Centre customers come from financial sectors who rely on backup centres
for their IT business continuity backbone. Events of 9/11 have focused the minds of the financial
services regulators to ensure that all major institutions have suitable contingency plans in operation.
In some major countries, especially the USA, CEOs are legally responsible for protecting their
organisation’s data. Companies that lose their data, for whatever reason, go into liquidation within 14
months of the loss, so the ability to recover data is vital.

However, the key to disaster recovery is not just redundancy; the resilience of the system or
the networks is critical. Resilience must be applied to technology at the design stage to
ensure continuity even during a cataclysmic event, which may be natural disasters, software
problems, cyber terrorism or latent design defects in the electrical and mechanical support
systems of the data centre.

Fault tolerance
Most of new multiple data
recovery centres are now being
built far away from main
financial hubs. According to
the SwissRE study, over 50%
of disasters are weather-
related but terrorism is getting
expensive too. In view of this,
infrastructure and electrical
system design needs to be
fault-tolerant. For example, a
short circuit should not stop the
functionality of the whole
building. A malfunction such
as that should clear itself
because of its fault tolerant
design which is part of the
operational resilience. Since
UPSs are at heart of any data
centre, a high degree of
attention must be paid to
resilience in UPS system
design.

We are all aware of recent


blackouts in London, New
York, Toronto, Copenhagen
and Rome. There were
different reasons for each
blackout - human error,
shortage of electricity,
deregulation, and so on. In
Europe, electricity utilities can
just about meet 99.9%, (i.e.
999) of availability. Percentage G-configuration S-07
Availability is measured as a
ratio of Meantime to repair
T H E U N I N T E R R U P T I B L E P O W E R P R O V I D E R
WHITE PAPER - Contingency planning evolution – By Shri Karve – Feb 2005
Contingency
planning evolution
By Shri Karve

(MTTR) and Meantime Between Failure (MTBF), i.e. Availability = (1- MTTR/MTBF) x 100. MTBF can
be increased by means of enhanced equipment reliability and using products that are independently
certified by recognised bodies e.g. TUV, KEMA and Veritas. It is important to make sure that both the
equipment and the installation as a whole shall be fault tolerant. In view of this, following factory
witness tests it is imperative to carry out system integrity (SI) testing that includes all the key
components of the Data Centre prior to hand over to client. During the SI testing one needs to
simulate faults at various levels within the electrical circuits and the mechanical items within the Data
Centre. This type of simulated testing can prove the robustness of the system design, equipment and
the installation. SI testing would bring to the fore any issues related to non-compatibility between
different packages or equipment.

Protection
MTTR can be reduced by use of
remote on-line diagnostics and G-configuration S-14
use of skilled experts carrying
out repairs within short space of
time. Correct range of spares
need to be available on 24/7
basis. Normal utility availability
of 99.9 % can result in 9 hours
of blackout or several short
blackouts and some brown
outs. As the utility companies
are not required to guarantee
continuity, organisations also
have to protect themselves
against these power losses.
Certainly, no financial institution
can accept this poor level of
availability, so it is essential,
therefore, to have data centres
backed up with UPS systems
and standby generation to
protect their core IT
infrastructure. It is known that
the cost of financial trading
system failure for one hour is 6
million euros (Source: IBID).

In order to achieve a high level


of resilience with a UPS system,
units which comply with dual
conversion design as per IEC
62040 must be used. In other
words, critical IT load is
protected against any power
quality issues at the input of the
UPS whether it is voltage or
frequency related. It is
important to note that some of
the rotary UPSs, and a small
percentage of static UPS may
not be of dual conversion
design.

T H E U N I N T E R R U P T I B L E P O W E R P R O V I D E R
WHITE PAPER - Contingency planning evolution – By Shri Karve – Feb 2005
Contingency
planning evolution
By Shri Karve

Static type UPS


Static type UPSs utilise battery banks to provide adequate back up time to provide cover during Mains
loss or poor quality from the utility supply. This allows enough time for the stand-by generators to fire
up and support the UPSs. For the large Data Centres it is worth using ten year design life batteries in
accordance with BS6290 Part 4 1997 standard. It is also necessary to install a battery monitoring
system that is based on Impedance-check technology. However it is very likely that in few years time
the battery banks will be replaced with Fuel Cell technology.
Battery autonomy can be based on requirements set by the client, but 10-15 minutes is the
common figure used in this type of industry. Standby generation is also essential to cover for
long outages and also to support non-essential loads, for example, air conditioning, lighting,
and so on.

It is good practice to have n+1 redundancy even at the standby generation level, whereas it is
critical for UPSs to go with n+n redundant design. (If n is the minimum requirement to support
the critical load, for example, 2 x 500 kva UPSs, then n+1 redundancy would mean 3 x 500kva
UPSs and n+n would mean 4 x 500kva UPS.) It is important to utilise an external centralised
static by-pass (CSB) per each parallel redundant UPS system. CSB provides a very high
degree of resilience when compared to simple modular parallel UPS systems. The reason
being that CSB static switch is rated for the system load whilst the modular type UPS system
depends on static switch that is rated only for the individual module rating i.e typically only 20
% of the load !

Blade servers
Since the growth of Blade servers it is good to have generator sets that have excellent compatibility
with leading power factor imposed by Blade servers. This will provide added resilience in the event of
the entire UPS system going into bypass mode during a mains loss situation. Since most of the IT
loads generate harmonics it is good practice to limit propagation of such pollution by using Active
Harmonic Filters. This helps to reduce the size of the neutral conductor, i.e., saves copper cost and
eliminates fire risk and nuisance tripping of circuit breakers. UPSs need to be provided with suitable
active harmonic filters to ensure that the current distortion (THDI) level is held at 5% or lower,
regardless of loading on the UPS system. This would help to meet the anti-pollution recommendation
G5/4.

In order to limit the damage caused due to a faulty source the static load transfer switches (STS) need
to be used at power distribution unit (PDU) level so that any fault is limited to that part of the circuit and
system resilience is not affected. These STS units are very fast acting (2-10 millisecond switching
time) hence they can switch the critical load from one source to the other without jeopardising
functionality of the servers.

In-built design
Each UPS system needs to have built-in redundancy and resilience at the design stage. Once the
design is checked for any dormant or hidden points of failure, it is good practice to carry out factory
witness tests for each individual item, i.e., UPS systems, switch gear, standby generator sets and so
on. Even during factory witness testing it is good practice to simulate short circuit on the load side to
help measure the fault tolerance level of the UPS system and its components. Also evaluate100%
load step performance of the UPS system and standby generators. It is recommended that suitable
critical component monitoring systems such as UPS battery banks monitoring are deployed, as this
type of monitoring would help the Facilities Management team to take proactive steps necessary to
avoid an internal disaster in a Data Recovery centre.

Before closing, there is no substitute for planned and regular maintenance which should also include
thermal imaging of critical components, for example, UPS, batteries during discharge, PDUs and
switch gear.

T H E U N I N T E R R U P T I B L E P O W E R P R O V I D E R
WHITE PAPER - Contingency planning evolution – By Shri Karve – Feb 2005