Unit Commitment
Unit Commitment
Chapter 5
Unit Commitment (UC)
Beyond spinning reserve, the unit commitment problem may involve various classes of
“scheduled reserves” or “off-line” reserves. These include quick-start diesel or gas-turbine units
as well as most hydro-units and pumped-storage hydro-units that can be brought on-line,
synchronized, and brought up to full capacity quickly. As such, these units can be “counted” in
the overall reserve assessment, as long as their time to come up to full capacity is taken into
account.
Reserves, finally, must be spread around the power system to avoid transmission system
limitations (often called “bottling” of reserves) and to allow various parts of the system to run
as “islands,” should they become electrically disconnected.
Example 5C
Constraints in UC
• Thermal Unit Constraints are:
• Minimum up time:
Once the unit is running, it should not be turned off immediately.
OR
This constraint state that once the unit is running must not shunt down
immediately due to technical limitation and mechanical characteristic of the
unit.
• Minimum down time:
Once the unit is decommitted, there is a minimum time before it can be
recommitted.
• Crew Constraints:
Constraints in UC
• Thermal Unit Constraints are:
• Crew Constraints
• Start-up cost
Constraints in UC
• Thermal Unit Constraints are:
• Crew Constraints
• Start-up cost
Constraints in UC
• Thermal Unit Constraints are:
• Other Constraints
• Hydro Constraints
• Must Run
• Fuel Constraints
Constraints in UC
• Thermal Unit Constraints are:
• Other Constraints
• Ramp Rates:
• To avoid damaging the turbine, the electrical output of a unit cannot
change by more than a certain amount over a period of time.
• Ramp-up rates:
• Start – up ramp rate: Unit cannot start immediately but taking time.
• Running – up ramp rate: Unit cannot immediate changing the power
up without taking time.
• Ramp-down rates:
• Shut down ramp rate: Unit take time to shut down.
• Running down ramp rate: Unit cannot immediate changing the power
down without taking time.
Constraints in UC
• Ramp Rate: The increase or
decrease in output (of
plant) per minute is called
ramp rate and expressed as
MW/min.
Unit Commitment Solution Methods
Unit Commitment Solution Methods
Priority-List Methods
Example 5D
Example 5D
Thank You