Best Unit Rate Analysis
Best Unit Rate Analysis
Birr
#NAME?
BILL OF QUANTITIES AND COST
Item
No. Description of work Unit Qty
1 WORKS
1.1 labor, etc) Ls 1.00
1.2 project activities Ls 1.00
1.3
office of size 4.4m*4.4m from CIS (G-32) for roof &
external wall from Cl sheet (G-32), internally painted chip
wood wall,and founded on a 25cm thick hardcore , 8cm Ls 1.00
C10(1:3:6) lean concrete and 2cm screed floor. The room
should be well ventilated thus equipped with window and
door of
1.4
of size 9.65m*3m from CIS(G-32) for roof & external
wall(G-32) and internally painted chip wood wall &
founded on a 25cm thick hardcore , 8cm C10(1:3:6) lean Ls 1.00
concrete and 2cm screed floor. Two rooms each has size of
3m*3m and are well ventilated equipping them with
windows and
1.5
is constructed from ClS (G-32) wall and roof (G-32) with
door and window, founded on a 25cm thick hardcore , 8cm Ls 1.00
G10(1:3:6) lean concrete and 2cm screed floor as per
drawing
1.6
6m*4m, constructed from CIS(G-32) wall and roof(G-32)
with door and window, founded on a 25cm thick hardcore, Ls 1.00
Scm C10 (1:3:6) lean concrete and 2cm screed floor as per
drawing
1.7
size 4m*2m, constructed from CIS(G-32) wall and roof(G-
32); ventilated separate with door and window, founded on Ls 1.00
a 10cm thick hardcore , Scm C10(1:3:6) lean concrete as
per drawing
1.8
constructed from CIS wall and roof with door and window', Ls 1.00
founded on a 25cm thick hardcore, Scm C10(1:3:6) lean
concrete and 2cm screed floor as per drawing
1.9
50m*30m, 2.0m height and 15cm diamter treated timber
post/eucluptus poles with barbed wire at 20cm vertical Ls 1.00
interval & posted in a minimum of 0.6m depth backfiiled
with lean concrtete,
1.10 Preparation of as-built drawings and site plan including Ls 1.00
operation and maintenance manual
1.11
Dimension of 1.0m*1.5m of 3mm thick with 0.3m*0.3m of
2.5m angle Iron pole, 0.4m*0.4m founded on C10(1:3:6) No 2.00
mass concrete of 0.5m
Total of Bill 1 carried to summary
2 ACCESS ROAD CONSTRUCTION
average thickness of 150mm on the alignment of road and m2 1,467.04
2.1 disposal of soil free haul 100m away
distance 2km and place as compacted fill in layer 200mm
to form access road embankment including trimming and m3 5,555.69
2.2 shaping
Total Carried Summary Birr
3 HEAD WORK
3.1 Coffer dam excavation River Training (Dozing) fnJ 150.00
3.2 Dewatering (pumping) &J 30.00
Sub Total
3.3 Weir
3.3.1 Excavation of normafsoil to the levels, width and grade as
m3 126.00
shown on. the drawings
3.3.2 Excavation in Hard Rock m3 54.00
3.3.3 Excavation in Soft Rock(if any) IT)3
3.3.4 Cyclopean concrete 40% boulder+60% C20 (1:2:4) m3 134.44
3.3.6 C-10 Concrete m3 11.42
Sub Total
4 POND
Pond and related structures (1 in No)
4.1 Site clearing m2 1,639.00
4.2 Excavation of ordinary soil m3 1,681.80
4.3 Fill and compaction with excavated or surrounding m3 121.97
4.4 30cm thick compacted clay material m3 385.00
4.5 Cart away to a distance up to 1 Km ra3 1,559.83
4.6 Geomembrane 2 mm Thick m 2
1,506
4.7 Pond inlet
a. Excavation on ordinary soil m3 3.00
b. Hard core blinded with 1:3 mortar in'1 4.55
c. Masonry bedded in 1:4 mortar m3 ! 8.40
d. Concrete C20 (1:2:4) m 3
0.60
e. Plastering in 1:3 mortar - m2 28.30
f. Clay back fill and compaction 3m 6.50
4.S Pond spillway
a. Excavation of ordinary soil 3 in 5.50
b. Hard core blinded with 1:3 mortar m3 6.50
c. Masonry bedded in 1:4 mortar m3 5.50
d. Plastering in 1:3 mortar m‘ 28.00
e. Clay back fill and compaction m3 7.00
4.9 Pond outlet
a. Excavation of ordinary soil m3 120.00
b. Hard core blinded with 1:3 mortar 3m 15.90
c. Masonry bedded in 1:4 mortar m3 60.30
C-20 of drawing m3 0.30
e.Supply and fix 40 cm diameter concrete pipe Pcs 20.00
f. Gate of size 500x500x5mm operated with spindle and
50mm square threaded shaft as per drawing and lps 1.00
g. Plastering in 1 : 3 mortar m2 44.50
h. Red clay back fill and compaction m3 105.80
Total Carried Summary Birr
S ON FARM WORK
5.1 Canal) Km 1.19
5.1.1 average thickness of 150mm on the alignment of canal and
disposal of soil free haul 100m away m2 3,592.50
5.1.2 Canal excavation of common material open to the lines and
grades as shown in the drawing and disposal of surplus to m3 1,275.55
spoil pits and spreading, free haul 500m
5.1.3 Hard Rock Excavation(if any) m3
5.1.4 Soft Rock Excavation(if any) m3
• 5.1.5 distance 7.5km and place as compacted fill til iayer 250mm
to form canal embankment including trimming tutd shaping m3 1,218.66
compaction and proctor test as directed
5.1.6 thick to the level m3 127.56
5.1.7 Construction of Stone masonry to the lined canal with 30
m3 608.94
cm thick bedded on cement mortar 1:4,
5.1.8 Plastering and cement screed all external faces of the lined
-/ m“ 2,029.80
canal with cement mortar 1:3, 3 coat.
Sub Total
5.1.7 Turnouts
On M.C NO 7.00
5.1.7. Foundation Excavation m3 22.40
mortar 1:4 at right and left side to the canal bed and on the m3 8.40
5.1.7. 2 inlet .outlet side of the Structure
2 coat of Plastering and cement screed the third, all external 1TI2 72.80
5.1.7. 3 faces of the wall with cement mortar 1:3,
5.1.7. pipes(0 10cm) pcs 30.80
5.1.7. Fixing Wooden Gates at pipe inlet pcs 7.00
5.1.7. Cemented stone piching with ratio 1:3 in2 3.00
Sub Total
5.1.8 DROPS
On M.C NO 6.00
5.1.8. Foundation Excavation m3 39.00
mortar 1:4 at right and left side to the canal bed and on the
5.1.8. 2 m5 22.00
inlet .outlet side of the structure.
5.1.8. 3 2 coat of Plastering and cement screed the third, all external
m2 111.89
faces of the wall with cement mortar 1:3,
Sub Total
6 SOCIAL STRUCTURES
6.1 drawing) LS 2.00
6.2 Washing Basin (2 in number as per drawing) LS 2.00
6.3 Foot Bridge (4 in number as per drawing) LS 4.00
Total Carried Summary Birr
30,000.00 30,000.00
30,000.00 30,000.00
36,000.00 36,000.00
43,200.00 43,200.00
40,000.00 40,000.00
43,200.00 43,200.00
14,400.00 14,400.00
7,200.00 7,200.00
25,000.00 25,000.00
28,000.00 28,000.00
10,000.00 20,000.00
317,000.00 317,000.00
10.00 14,670.40
92.40 513,345.76
528,016.16 525,082.08
#NAME? #NAME?
1,600.00 48,000.00
#NAME? 55,186.50 #NAME?
50.00 6,300.00
296.14 15,991.57
340.82 -
1,462.04 196,556.94
2,037.95 23,273.33
242,121.84 367,749.41 (125,627.57)
2,725.07 12,262.80
2,725.07 327.01
-
29.80 694.45 38-40
29.80 7,749.22
21,033.48 27,176.83 (6,143.35)
42.75 4,350.74
624.82 15,895.39
1,200.14 328,838.94
125.33 17,545.59
125.33 11,492.36
119.99 6,719.54
624.82 48,298.50
433,141.06 506,701.86 (73,560.80)
-
#NAME? #NAME?
1,249.61 4,998.45
450.00 4,500.00
119.99 1,799.88
4,306.07 4,306.07 4,306.07
100,000.38 100,000.38 100,000.38
1,000.00 31,000.00 104,306.46
#NAME? 74,195.58
#NAME? #NAME?
260.00 18,200.00
624.82 103,095.12
624.82 34,365.04
#NAME? 192,869.48 #NAME?
59.84 2,393.54
119.99 59,995.91
624.82 6,248.19
68,637.64 60,719.50 7,918.14
#NAME? 1,284,599.16
59.84 98,075.14
#NAME? #NAME?
119.99 14,635.40
119.99 46,196.85
42.75 66,690.35
152.30 229,363.80
-
#NAME? #NAME?
624.82 2,842.93
1,200.14 10,081.19
1,249.61 749.77
125.33 3,546.71
119.99 779.95
-
#NAME? #NAME?
624.82 4,061.32
1,200.14 6,600.78
125.33 3,509.12
119.99 839.94
#NAME? #NAME?
624.82 9,934.62
1,200.14 72,368.57
1,249.61 374.88
500.00 10,000.00
4,306.07 4,306.07
125.33 5,576.99
119.99 12,695.14
#NAME? 577,372.20 #NAME?
-
59.84 214,969.46
#NAME? #NAME?
624.82 -
340.82 -
119.99 146,229.24
119.99 15,306.16
1,200.14 730,814.54
125.33 254,385.93
-
#NAME? #NAME?
1,200.14 10,081.19
125.33 9,123.70
35.00 1,078.00
30.00 210.00
6.50 19.50
#NAME? 21,586.95 #NAME?
-
#NAME? #NAME?
1,200.14 26,403.13
-
125.33 14,022.68
#NAME? #NAME?
1,200.14 38,968.61
125.33 5,758.71
-
1,249.61 4,973.46
2,725.07 109,002.69
#NAME? 169,757.63 #NAME?
#NAME? 1,438,729.49 #NAME?
5,000.00 10,000.00
20,000.00 40,000.00
13,000.00 52,000.00
102,000.00 102,000.00
#NAME? 4,244,783.09
10000
15000
25000
79,306.46
Construction Materials
S.№ Items Unit Rate · Weight of Reinforcem
1 Cement Quintal 220.00
CI Sheet G-28 Pcs 250.00 181.16
CI Sheet G-30 Pcs 200.00 144.93
CI Sheet G-32 Pcs 200.00 144.93 · Weight of Re
CI Sheet G-35 Pcs 200.00 144.93
Ø6 bar kg 25.00 6 0.2220 2.6645
Ø8 bar Pcs 120.00 25.33 8 0.3947 4.7369
Ø10 bar Pcs 200.00 27.02 10 0.6168 7.4014
Ø12 bar Pcs 300.00 28.15 12 0.8882 10.6581
Ø14 bar Pcs 400.00 27.57 191.97 14 1.2089 14.5068
Ø16 bar Pcs 500.00 26.39 27.42 16 1.5790 18.9477
Ø20 bar Pcs 650.00 27.11 18 1.9984 23.9806
Ø24 bar Pcs 900.00 30.40 20 2.4671 29.6057
Paint № 111 galon 136.15 22 2.9852 35.8229
Paint № 122 galon 111.65 24 3.5527 42.6322
Paint № 117 galon 109.20 26 4.1695 50.0337
Brush 3x14 Pcs 40.00
Brush 4x14 Pcs 60.00
Brush 2 Pcs 4.00
Brush 3 Pcs 6.00
Brush 5 Pcs 15.00
Pipe
Roof nail kg 28.00
· Weight of Reinforcement per m is given by: , Where , W= weight in Kg/m and d= diameter in mm
2
d
W * * 0.785
10 4
· Weight of Reinforcement per Pcs is given by: , Where , W= weight in Kg/Pcs and d= diameter in mm
d 2 * 12
Kg W * 0.222
36
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
d 2 * 12
W * 0.222
36
meter in mm
WAGE INDEX
AVERAGE
MONTHLY FOOD AVERAGE ESTIMATED
SALARY ALLOWANCE(br SEVERANCE ANNUAL
NO MAN POWER (birr/month) ./month) PAY(br./month) WORKING hrs.
2 PROJECT MANAGER 30,000.00 1500.00 7,500.00 2,080.00
3 SITE ENGINNER 15,000.00 1500.00 3,750.00 2,080.00
4 SURVEYOR 15,000.00 1500.00 3,750.00 2,080.00
6 STORE KEEPER 1,800.00 1200.00 450.00 2,080.00
1 FORMAN 3,000.00 1500.00 750.00 2,080.00
Operator 6,000.00 1500.00 1,500.00
Driver 6,000.00 1500.00 1,500.00
GENERATOR
7 OPERATOR/ELECERICIAN 1,800.00 1200.00 450.00 2,080.00
9 DATA COLLECTOR 1,800.00 2,080.00
10 Mason 4,290.00 2,080.00
11 Assis. Mason 2,600.00 2,080.00
12 Carpenter 4,290.00 2,080.00
13 Assis.Carpentar 2,600.00 2,080.00
14 Gang Chief 3,900.00 2,080.00
15 Bar Bender 4,290.00 2,080.00
16 Assis. Bare bender 2,600.00 2,080.00
17 D/LABOURER 1,950.00 2,080.00
18 CHAIN MAN 2,600.00 2,080.00
19 TIME KEEPER 3,000.00 2,080.00
20 COOKER 1,800.00 2,080.00
21 CAMP CLEANER 1,800.00 2,080.00
22 GUARD 1,800.00 2,080.00
TOTAL
NB:-
Leave payment considering 34 days annaul
Bounes considering one month salery per y
Medical expense considering 0.9% of monthl
Average severance pay. Considering three m
DEX
ESTIMATED
ANNUAL HOURLY MAN ESTIMATED COST
TOTAL MONTHLY COST(br./yr.or 12 POWER Duration through duration of
COST(br./month) months) COST(br./hr.) (month) project
56,290.00 675,480.00 324.75 3 168,870.00
30,690.00 368,280.00 177.06 3 92,070.00
30,690.00 368,280.00 177.06 3 92,070.00
8,115.85 97,390.20 46.82 3 24,347.55
11,110.00 133,320.00 64.10 3 33,330.00 512.77
72,000.00 28.85 4 288,000.00
72,000.00 28.85 5 2,076,923.08
2,843,863.18
Make Model or Oil Grease
Item Equipment Type Supplier consumption Consumption
I. Earth Work Equipment
1 Dozer D9N CAT - D9N
2 Dozer D8R CAT - D8R
3 Dozer D7R CAT - D74
4 Grader 14 H CAT - 14G
5 Grader 140 H CAT - 140G
6 Track Type Loader 210 HP
7 Wheel Loader 250 HP
8 Wheel Loader 200 HP
9 Dumper 1 m3
10 Track Type Excavator 200 HP
Track Type Excavator with
11 rock breaker 200 HP
12 Backhoe Excavator 120 Hp
13 Vibratory Compactor 8-10 ton
14 Vibratory Compactor 10-12 ton
15 Hand Tamper
16 Crushing plant 75 ton
17 Crushing plant 120 ton
18 Generator 90 kw
19 Generator 45 kw
20 Driller
21 Jack Hammer
22 Sand Washing Machine
23 Air Compressor
24 Pneumatic tyred roller Estimate
25 Sheep's foot roller, 14Ton Estimate
II. Hauling Equipment
1 Dump Truck 14m3 Nissan
2 Dump Truck 9m3 Nissan
3 Water Truck 13,000 Lit. Nissan
4 Truck with trailer 20t. Volvo
5 Lowbed, 40 ton .-
6 Station wagon 4 WD Toyota
7 Pick up 4 WD Toyota
8 Mobile Crane Estimate
III. Concrete Machine
1 Concrete mixer 750/500 lts Estimate
2 Concrete mixer 300lt lts Estimate
3 Concrete vibrator Estimate
4 Concrete vibrator (small) Estimate
5 Bar bend. & Cutting Estimate
6 Hand Tools
IV. Other Equipments
1 Hand drill Estimate
2 Centrifugal W/Pump Estimate
3 Water Tanker
V. Pavement Equipment
1 Asphalt Plant
2 Asphalt Kittle
3 Power Broom
4 Aspalt Paver
5 Asphalt Distributer
6 Aggregate Spreader
7 Stationary Asphalt Heater
8 Generator
9 Concrete Plant
Consider
Fuel Price 18.55
Benzene 20.47
Current Current
Fuel Market w/out Market with
consumption Fuel Cost fuel fuel Remark
3 48.6 45 93.6
2 38.88 30 68.88
1 17.36 25 42.36
1 19.44 20 39.44
15 15
2.01 2.01
25 25
3 52.08 25 77.08
100 100 12.5
3,500.00 3,500.00
23 434 250 684
5 86.8 50 136.8
5 86.8 4,000.00 4,086.80
22 416.64 280 696.64
22 416.64 2,500.00 2,916.64
9 173.6 800 973.6
75 1,388.80 1,200.00 2,588.80
1,200.00 1,200.00
Item Selling price w/t
No Type of material Unit VAT
Sheet Metal
Sheet Metal 1x2mx3m Pcs 939.13
Sheet Metal 3x1.5mx6m Pcs 4956.52
Sheet Metal 2mm thick Pcs 6800
Chipwood
8mm thick Pcs 164.08
19mm thick Pcs 345
Wire mesh
Wire mesh Mt 25
Angle iron
Angle Iron 30x30x2 Pcs 210
Angle Iron 40x40x2.5mm ml 45
Angle Iron 40x40x3.0mm ml 50.67
Angle Iron 30x30x3.0mm ml 41.67
Form work
4x30x2.5 Pcs 258.26
4x20x2.5 Pcs 172.17
4x25x2.5 Pcs 215.21
REINFORCEMENT
14 Dai 6 kg 21.5
15 Dai 8 kg 19.46
16 Dai 10 kg 18.45
17 Dai 12 kg 20.97
18 Dai 14 kg 19.01
19 Dai 16 kg 20.98
20 Dai 20 kg 19.1
21 Dai 24 kg 19.58
22 Tie wire 1.5mm kg 29
23 Tie wire 2.5mm kg 29
Nails
Nails Kg 26.27
Roof Nails Kg 63.25
WOODEN PRODUCTS
24 Wooden door m2 2,674.04
Purlin 5x7cm austria Pc 150.00
25 Plywood 1220*2440*8mm PC 117.4
26 Plywood 1220*2440*8mm PC 347.83
27 Plywood Formwork 1220*2440*12mm PC 460.87
28 Eucalyptus diameter 8-10mm Ml. 40
29 Eucalyptus diameter 10-12mm Ml. 60
PAINT
50 Plastic Paint Gal 129.14
51 Quartiz Paint 16lit 375
HOLLOW CONCRETE BLOCK
52 20cm thick PC 12.08
53 15cm thick PC 10.35
54 10cm thick PC 10.35
55 Bricks PC 2.5
Marble
Wolega Marble
56 a) 1cm. thick m2 550
57 b) 2cm. thick m2 750
58 c) 3cm. thick m2 1,050.00
GLAZING MATERIALS
59 Clear Glass 3mm thick m2 160
60 Clear Glass 4mm thick m 2
220
Clear Glass 5mm thick m2 350
Clear Glass 6mm thick m2 608.7
Clear Glass 10mm thick m2 746
Temperd Glass 5mm thick m2 700
Temperd Glass 6mm thick m2 750
Temperd Glass 10mm thick m2 1250
ALUMINUM MATERIALS
61 Aluminum normal hand rail m2 2,200.00
62 Aluminum partition wall m2 1,750.00
63 Aluminum suspended ceiling m2 1,750.00
64 Aluminum Door and Windows m2 1,750.00
SANITARY FITTINGS
68 Hand Wash No 1,800.00
69 Turkishi WC No 2,595.65
70 Kitchen Sink No 950
71 Shower Tray Size 700x700mm No 600
72 Shower Try No 1,939.13
73 Litre Water Heater No 3,820.00
74 Water Heater 80 litter No
75 Water Heater 50 litter No
76 Soap holder No 186.96
77 Toilet paper holder No 186.96
78 Towel hanger No 186.96
79 Floor drain 10 x10cm No 95
80 Water Tanker 25,000 lit No 47,600.00
81 Water Tanker 10,000 lit No 18,000.00
82 Water Tanker 5,000 lit No 9,700.00
83 Water Tanker 7,000 lit No 12,000.00
84 Water Tanker 4,000 lit No 8,500.00
85 Water Tanker 3,000 lit No 6,600.00
86 GS-Pipes 50mm No 826.09
PP-R pipes
ELECTRICAL WIRE
Insulated Copper Wire
102 1x2.5mm2 (Differnet Color) Roll 615.5
103 1x4mm2 (Differnet Color) Roll 965
104 2x4mm2 (Differnet Color) Ml. 27.75
105 4x4mm2 (Differnet Color) Ml. 48.14
106 4x10mm2 (Differnet Color) Ml. 119.74
107 1x25mm2 STANDARD (1x1000) Ml. 241.54
Others
300.00
217.99
333.50
264.50
340.40
241.50
264.50
215.00
503.12
414.00
40.25
69.00
97.75
368.00
414.00
39675.00
38525.00
38525.00
2.01
104.37
120.86
176.30
243.24
276.75
324.30
610.25
787.35
1080.00
5700.00
7820.00
188.69
396.75
28.75
0.00
241.50
51.75
58.27
47.92
297.00
198.00
25
22
21
24
22
24
22
23
33
33
30
73
3,075.15
172.50
135.01
400.00
530.00
46.00
69.00
215.00
264.99
10,100.00
9,065.00
324.00
161.00
135.00
230.00
287.5
253
230
218.5
477
456
830
125
1,050.00
830
1,050.00
164.98
161
17.25
148.51
431.25
10.35
9.2
8.05
2.88
632.5
862.5
1,207.50
184
230
2,530.00
2,012.50
2,012.50
2,012.50
2,070.00
2,985.00
1,092.50
690
2,230.00
4,393.00
215
215
215
109.25
54,740.00
20,700.00
11,155.00
13,800.00
9,775.00
7,590.00
950
345
667
977.5
437
690
1,033.85
2,208.00
155.25
178.25
225.4
189.75
1,092.50
8,970.00
223.1
155.25
707.83
1,109.75
31.91
55.36
137.7
277.77
13,018.00
14,375.00
9,142.50
5,301.50
5,301.50
Equipment Qty Unit price total
Damp truck 1 500 500
Creshur 1 2000 2000
Concrete mixer 1 300 300
Hand Compactor 1 300 300
Service Vehicle 1 500 500
Dozer D7 and above 1 74000 74000
Loader 1 74000 74000
Vibrator 1 300 300
Dewatering pump 1 300 300
Set of Surveying equipment
(Leveling) 1 500 500
Excavatpr 1 0
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
- D/L 1 1 11.25 11.25 Tool 1 2.01 2.01
- G.Chief 1 0.25 22.50 5.63 -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
Total (1:-01) - Total (1:02) 16.88 Total (1:03) 2.01
A= Materials Unit 0 Birr/m2 B= Manpower Unit Cost 42.78 Birr/m2 C= Equipment Unit Cost 5.10 Birr/m2
Total of (1:02) 1.44 Total of (1:03)
Hourly Output: 0.89 Hourly output: ______________
Direct Cost of Work Item = A+B+C = 47.87 Birr/m2
Over head cost : 20% 9.57 "
Profit Cost: 5% 2.39 "
Total Unit Cost : 60 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-2-
2.34375 2.4
PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: 0.3 m3/hr.
WORK ITEM: ( 1.Excavation on Normal soil EQUIPEMENT: Tool
TOTAL QANTITY OF WORK 1 m3 RESULT: 341 Birr/m3
A= Materials Unit 0 Birr/m3 B= Manpower Unit Cost 258.65 Birr/m3 C= Equipment Unit Cost 14.00 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ______________
Direct Cost of Work Item = A+B+C = 272.65 Birr/m3
Over head cost : 20% 54.53 "
Profit Cost: 5% 13.63 "
Total Unit Cost : 341 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-3 -
1.1
PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: 0.1375 m3/hr.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
A= Materials Unit 0 Birr/m3 B= Manpower Unit Cost 114.73 Birr/m3 C= Equipment Unit Cost 122.18 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
Direct Cost of Work Item = A+B+C = 236.91 Birr/m3
Over head cost : 20% 47.38 "
Profit Cost: 5% 11.85 "
Total Unit Cost : 296.14 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1 -
1.271
PROJECT: Back fill AND EARTH WORK. LABOUR HOURLY OUTPUT: 0.158875 m3/hr.
WORK ITEM:
Back fill and Compaction EQUIPEMENT: Tool
TOTAL QANTITY OF W 1m 3
RESULT: 120.0 Birr/m3
** Indexed
Type of Cost per Labour by Hourly Hourly Type of Hourly Hourly
Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
- foreman 1 0.01 64.10 0.64 tool 1 2.01 2.01
- DL 1 1 11.25 11.25 -
- G.CHIEF 1 0.06 22.50 1.35 -
- - -
- - -
- - -
- - -
- - -
- - -
Total (1:-01) - Total (1:02) 13.24 Total (1:03) 2.01
A= Material 0 Birr/m3 B= Manpower Unit Cost 83.34 Birr/m3 C= Equipment Unit Cost 12.65 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: ______________
Direct Cost of Work Item = A+B+C = 95.99 Birr/m3
Over head cost : 20% 19.20 "
Profit Cost: 5% 4.80 "
Total Unit Cost : 120 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-1-
6
PROJECT:Cart Away of Excavation Material LABOUR HOURLY OUTPUT: 0.75 m3/hr
Cartaway surplus soil material,1m
WORK ITEM: 3
EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM 1m 3
RESULT: 43 Birr/m3
A= Material 0.00 Birr/m3 B= Manpower Unit Cost 32.65 Birr/m3 C= Equipment Unit Cost 2.68 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output: _________________ Hourly output: __________________
Direct Cost of Work Item = A+B+C = 35
Over head cost : 20% 7.07
Profit cost : 5% 0.35
Total unit cost : 43 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1-
PROJECT: Hard core Placement LABOUR HOURLY OUTPUT: 18
WORK ITEM
25cm
: thick hard core EQUIPEMENT: 2.25 m2/hr.
TOTAL QANTITY OF
WORK ITEM: 1 m2 RESULT 625 Birr/m2
** Indexed
Type of Cost per Labour by Hourly Hourly Type of Hourly Hourly
Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
Stone m2 1.3 360.00 468 Foreman 1 0.25 64.10 16.02 Tools 4 2.1 8.4
Masone 1 1 24.75 24.75
D/L 2 1 11.25 22.50
A= Material 468.00 Birr/m2 B=Manpower Unit Cost 28.12 Birr/m2 C=Equipment Unit Cost 3.73 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: __________________
Direct Cost of work item = A + B + C = 499.86
Over head cost : 20% 99.97
Profit cost : 5% 24.99
Total unit cost : 625 Birr/m2
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-1-
0.708
PROJECT: MASONRY WORKS LABOUR HOURLY OUTPUT: 0.0885 m2/hr.
WORK ITEM : ( 2.4Masonary work 1.69 EQUIPEMENT:
TOTAL QANTITY OF WORK I 1m 2
RESULT : 1200 Birr/m2
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
Cement Qnt. 0.41 260.00 106.60 Forman 1 0.01 64.10 0.64 tools 2 2.1 4.2
Sand m3 0.08 250.00 20.00 Mason 1 0.5 24.75 12.38 0
Stone m 3
1.2 250.00 300.00 Chisler 1 0.5 15.00 7.50 0
- D/L 2 1 11.25 22.50 0
- - 0
- - 0
- - 0
- - 0
- - 0
Total (1:-01) 426.60 Total (1:02) 43.02 Total (1:03) 4.2
A= Material unit cost 426.60 Birr/m2 B=Manpower Unit Cost 486.06 Birr/m2 C=Equipment Unit Cost 47.4576271186 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: _________________
Direct Cost of work item = A + B + C = 960.11 Birr/m2
Overhead Cost : 15% 144.02 "
Profit Cost: 10% 96.01 "
Total Unit Cost : 1200 Birr/m2
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
5
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
PROJECT: MASONRY WORKS LABOUR HOURLY OUTPUT: 0.625 m2/hr.
WORK ITEM : ( 2.340cm. thick elevation wall (One side dressed) . EQUIPEMENT:
TOTAL QANTITY OF WORK I 1 m2 RESULT 753 Birr/m2
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
Cement Qnt. 0.41 260.00 106.60 Foreman 0.25 1 64.10 16.02 0
Sand m 3
0.08 250.00 20.00 Masone 2 1 24.75 49.50 0
Stone m 3
1.1 250.00 275.00 Chisler 1 1 15.00 15.00 0
- D/L 4 1 11.25 45.00 0
- - 0
- - 0
- - 0
- - 0
- - 0
Total (1:-01) 401.60 Total (1:02) 125.52 Total (1:03) 0
A= Material unit cost 401.60 Birr/m2 B=Manpower Unit Cost 200.84 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: _________________
Direct Cost of work item = A + B + C = 602.44 Birr/m2
Overhead Cost : 10% 60.24 "
Profit Cost: 15% 90.37 "
Total Unit Cost : 753 Birr/m2
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-3-
6
PROJECT: MASONRY WORKS LABOUR HOURLY OUTPUT: 0.75 m3/hr.
WORK ITEM : ( 2.250cm. thick masonry foundation (A.G.L). EQUIPEMENT:
TOTAL QANTITY OF WORK I 1 m3 RESULT 1,304 Birr/m3
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
Cement Qnt. 1.50 260.00 390.00 Foreman 1 0.17 64.10 10.90 tools 2 1 2
Sand m 3
0.42 250.00 105.00 Masone 2 1 24.75 49.50
Stone m 3
1.50 250.00 375.00 D/L 6 1 11.25 67.50
A= Material unit cost 870.00 Birr/m3 B=Manpower Unit Cost 170.53 Birr/m3 C=Equipment Unit Cost 2.66666666667 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: __________________
Direct Cost of work item = A + B + C = 1043.20 Birr/m3
Over head cost : 10% 104.32
Profit Cost: 15% 156.48
Total Unit Cost : 1,304
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
6
PROJECT: MASONRY WORKS LABOUR HOURLY OUTPUT: 0.75 m3/hr.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
WORK ITEM : ( 2.150cm. thick masonry foundation (B.G.L). EQUIPEMENT:
TOTAL QANTITY OF WORK I 1m 3
RESULT 1,184.62 Birr/m3
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
Cement Qnt. 1.50 260.00 390.00 Foreman 1 0.17 64.10 10.90 tools 2 1 2
Sand m 3
0.42 250.00 105.00 Masone 1 1.00 24.75 24.75
Stone m 3
1.25 250.00 312.50 D/L 6 1.00 11.25 67.50
A= Material unit cost 807.50 Birr/m3 B=Manpower Unit Cost 137.53 Birr/m3 C=Equipment Unit Cost 2.66666666667 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: __________________
Direct Cost of work item = A + B + C = 947.70
Over head cost : 15% 142.15
Profit Cost: 10% 94.77
Total Unit Cost : 1184.62 Birr/m3
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-5-
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
dressed stone m2 1.05 414.00 434.70 Foreman 1 0.25 64.10 16.02 tools 2 2.1 2
red ash m 3
1.05 69.00 72.45 masonii 1 1 24.75 24.75 0
selected material m 3
1.05 40.25 42.263 D/L 1 1 11.25 11.25 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Total (1:01) 549.41 Total (1:02) 52.02 Total (1:03) 2
A= Materials Unit Cos 549.41 Birr/m2 B= Manpower Unit Cost 13.01 Birr/m2 C= Equipment Unit Cost 0.50 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 562.92 Birr/m2
Over head cost : 20% 112.58 "
Profit Cost: 5% 28.15 "
Total Unit Cost : 704 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-1-
0.708
PROJECT: HCB BLOCK WORK LABOUR HOURLY OUTPUT: 0.0885 m2/hr.
WORK ITEM : ( 5.1) 200mm HCB Wall 1.69 EQUIPEMENT:
TOTAL QTY OF WORK ITEM 1 m 2
RESULT : 1200 Birr/m2
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
Cement Qnt. 0.41 260.00 106.60 Forman 1 0.01 64.10 0.64 tools 2 2.1 4.2
Sand m 3
0.08 250.00 20.00 Mason 1 0.5 24.75 12.38 0
Block m3 1.2 250.00 300.00 Chisler 1 0.5 15.00 7.50 0
- D/L 2 1 11.25 22.50 0
- - 0
- - 0
- - 0
- - 0
- - 0
Total (1:-01) 426.60 Total (1:02) 43.02 Total (1:03) 4.2
A= Material unit cost 426.60 Birr/m2 B=Manpower Unit Cost 486.06 Birr/m2 C=Equipment Unit Cost 47.4576271186 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: _________________
Direct Cost of work item = A + B + C = 960.11 Birr/m2
Overhead Cost : 15% 144.02 "
Profit Cost: 10% 96.01 "
Total Unit Cost : 1200 Birr/m2
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
5
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
PROJECT: MASONRY WORKS LABOUR HOURLY OUTPUT: 0.625 m2/hr.
WORK ITEM : ( 2.3 )40cm. thick elevation wall (One side dressed) . EQUIPEMENT:
TOTAL QANTITY OF WORK ITE 1 m2 RESULT 753 Birr/m2
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
Cement Qnt. 0.41 260.00 106.60 Foreman 0.25 1 64.10 16.02 0
Sand m3 0.08 250.00 20.00 Masone 2 1 24.75 49.50 0
Stone m 3
1.1 250.00 275.00 Chisler 1 1 15.00 15.00 0
- D/L 4 1 11.25 45.00 0
- - 0
- - 0
- - 0
- - 0
- - 0
Total (1:-01) 401.60 Total (1:02) 125.52 Total (1:03) 0
A= Material unit cost 401.60 Birr/m2 B=Manpower Unit Cost 200.84 Birr/m2 C=Equipment Unit Cost 0 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: _________________
Direct Cost of work item = A + B + C = 602.44 Birr/m2
Overhead Cost : 10% 60.24 "
Profit Cost: 15% 90.37 "
Total Unit Cost : 753 Birr/m2
Remark : ____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-3-
6
PROJECT: MASONRY WORKS LABOUR HOURLY OUTPUT: 0.75 m3/hr.
WORK ITEM : ( 2.2 )50cm. thick masonry foundation (A.G.L). EQUIPEMENT:
TOTAL QANTITY OF WORK IT 1 m3 RESULT 1,304 Birr/m3
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
Cement Qnt. 1.50 260.00 390.00 Foreman 1 0.17 64.10 10.90 tools 2 1 2
Sand m 3
0.42 250.00 105.00 Masone 2 1 24.75 49.50
Stone m3 1.50 250.00 375.00 D/L 6 1 11.25 67.50
A= Material unit cost 870.00 Birr/m3 B=Manpower Unit Cost 170.53 Birr/m3 C=Equipment Unit Cost 2.66666666667 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: __________________
Direct Cost of work item = A + B + C = 1043.20 Birr/m3
Over head cost : 10% 104.32
Profit Cost: 15% 156.48
Total Unit Cost : 1,304
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
6
PROJECT: MASONRY WORKS LABOUR HOURLY OUTPUT: 0.75 m3/hr.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
WORK ITEM : ( 2.1 )50cm. thick masonry foundation (B.G.L). EQUIPEMENT:
TOTAL QANTITY OF WORK ITE 1m 3
RESULT 1,184.62 Birr/m3
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
Cement Qnt. 1.50 260.00 390.00 Foreman 1 0.17 64.10 10.90 tools 2 1 2
Sand m3 0.42 250.00 105.00 Masone 1 1.00 24.75 24.75
Stone m3 1.25 250.00 312.50 D/L 6 1.00 11.25 67.50
A= Material unit cost 807.50 Birr/m3 B=Manpower Unit Cost 137.53 Birr/m3 C=Equipment Unit Cost 2.66666666667 Birr/m3
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: __________________
Direct Cost of work item = A + B + C = 947.70
Over head cost : 15% 142.15
Profit Cost: 10% 94.77
Total Unit Cost : 1184.62 Birr/m3
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-5-
** Indexed
Cost per Labour by Hourly Hourly Type of Hourly Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. Rental Cost
dressed stone m2 1.05 414.00 434.70 Foreman 1 0.25 64.10 16.02 tools 2 2.1 2
red ash m 3
1.05 69.00 72.45 masonii 1 1 24.75 24.75 0
selected material m 3
1.05 40.25 42.263 D/L 1 1 11.25 11.25 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Total (1:01) 549.41 Total (1:02) 52.02 Total (1:03) 2
A= Materials Unit Cost 549.41 Birr/m2 B= Manpower Unit Cost 13.01 Birr/m2 C= Equipment Unit Cost 0.50 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 562.92 Birr/m2
Over head cost : 20% 112.58 "
Profit Cost: 5% 28.15 "
Total Unit Cost : 704 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-1-
A= Materials Unit Cost 521.04 Birr/m2 B= Manpower Unit Cost 5.81 Birr/m2 C=Equipment Unit Cost - Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 526.86 Birr/m2
Over head cost : 20% 105.37 "
Profit Cost: 5% 26.34 "
Total Unit Cost : 659 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-2-
A= Materials Unit Cost 452.04 Birr/m2 B= Manpower Unit Cost 11.63 Birr/m2 C=Equipment Unit Cost - Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: ___________________
Direct Cost of Work Item = A+B+C = 463.67 Birr/m2
Over head cost : 20% 92.73 "
Profit Cost: 5% 23.18 "
Total Unit Cost : 580 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-1- 12.50
PROJECT: CONCRETE WORK LABOUR HOURLY OUTPUT: 1.56 m3 / hr.
WORK ITEM: ( 3.8 ) C-7 lean concrete EQUIPEMENT: Mixer & Vibrator
TOTAL QUANTITY OF WORK ITEM: 1.00 m3 RESULT: 137 Birr/m2
-
-
-
-
Total (1:-01) 1,009.07 Total (1:02) 98.66 Total (1:03) 41.61
A= Materials Unit Cost 1,009.07 Birr/m3 B=Manpower Unit Cost 63.14 Br./m3 C= Equipment Unit Cost 26.63 Br./m3
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: __________________
Direct Cost of work item = A+B+C = 1,098.85 Birr/m3
Overhead Cost: 20% 219.77 "
Profit Cost: 5% 54.94 "
Total Unit Cost : 1,373.56 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
5.50
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
A= Materials Unit Cost 1,385.76 Birr/m3 B=Manpower Unit Cost 184.07 Br./m3 C= Equipment Unit Cost 60.52
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: ________________
Direct Cost of work item = A+B+C = 1,630.36 Birr/m3
Overhead Cost: 20% 326.07 "
Profit Cost: 5% 81.52 "
Total Unit Cost : 2,037.95 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-3-
5.50
PROJECT: CONCRETE WORK LABOUR HOURLY OUTPUT: 0.69 m3 / hr.
WORK ITEM: ( 3.3 ) C-20 Concrete (Mix Ratio:- 1:2:4) EQUIPEMENT: Mixer & Vibrator
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
- -
- - -
- - -
- - -
- - -
Total (1:-01) 941.00 Total (1:02) 20.35 Total (1:03) 20.00
A= Materials Unit Cost 941.00 Birr/m3 B=Manpower Unit Cost 29.60 Br./m3 C= Equipment Unit Cost 29.09 Br./m3
Total of (1:02) Total of (1:03)
Hourly Output Hourly output: __________________
Direct Cost of work item = A+B+C = 999.69 Birr/m3
Overhead Cost: 20% 199.94 "
Profit Cost: 5% 49.98 "
Total Unit Cost : 1,250 Birr/m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-4-
2.75
PROJECT: CONCRETE WORK LABOUR HOURLY OUTPUT: 0.34 m3 / hr.
WORK ITEM: ( 3.5 ) C-25 Concrete EQUIPEMENT: Mixer & Vibrator
TOTAL QUANTITY OF WORK ITEM: 1.00 m3 RESULT: 2,725.07 Birr/m3
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
- -
- - -
- - -
- - -
Total (1:-01) 1,773.53 Total (1:02) 92.89 Total (1:03) 46.85
A= Materials Unit Cos 1,773.53 Birr/m3 B=Manpower Unit Cost 270.23 Br./m3 C= Equipment Unit Cost : 136.29 Br./m3
Total of (1:02) Total of (1:03)
Hourly Output Hourly output:
Direct Cost of work item = A+B+C = 2,180.05 Birr/m3
Overhead Cost: 20% 436.01 "
Profit Cost: 5% 109.00 "
Total Unit Cost : 2,725.07 Birr/m3
Remark __10cm thick______________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1- 50.00
Cement Qnt. 0.90 300.00 270.00 Foreman 1.00 0.10 64.10 6.41 Mixer 1.00 36.37 36.37
Sand m3 0.42 503.12 211.31 Mason II 1.00 1.00 24.75 24.75 Vibrator 1.00 5.24 5.24
Gravel (02) m3 1.61 414.00 665.88 D/L 6.00 1.00 11.25 67.50
A= Materials Un 1,147.19 Birr/m3 B=Manpower Unit Cost 15.79 Br./m3 C= Equipment Unit Cost 6.66 Br./m3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-1-
PROJECT : REINFORCEMENT BARS LABOUR HOURLY OUTPUT: 50 kg/hr.
WORK ITEM: ( 4.1 ) Plain Bars EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 kg. RESULT: 2 Birr/kg.
A= Materials Unit Cost 11.55 Birr/kg. B= Manpower Unit Cost 6.75 Birr/kg. C= Equipment Unit Cost 5.54117647 Birr/kg.
Total of (1:02) Total of (1:03)
Hourly Output: _________________ 11.25/12.5=0.90 Hourly output: ___________
Direct Cost of Work Item = A+B+C = _ 23.84 Birr/kg.
Over head cost : 20% 4.769 "
Profit Cost: 5% 1.192 "
Total Unit Cost : 30 Birr/kg.
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-1-
PROJECT: FORM WORK LABOUR HOURLY OUTPUT: 5.00 m2/hr.
WORK ITEM: ( 5.3 For Elevation Column. EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM : 1.00 m2 RESULT: 87 Birr/m2
A= Materials Unit Cos 63.46 Birr/m2 B= Manpower Unit Cost 10.73 Birr/m2 C=Equipment Unit Cost 0.15 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _________________
Direct Cost of Work Item = A+B+C = 74.34
Over head cost : 0.15 11.15
Profit Cost: 0.10 1.12
Total Unit Cost : 87 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
A= Materials Unit Cost 65.54 Birr/m2 B= Manpower Unit Cost 115.91 Birr/m2 C=Equipment Unit Cost 20.10 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _________________
Direct Cost of Work Item = A+B+C = 201.55 Birr/m2
Over head cost : 20% 40.31 Birr/m2
Profit Cost: 5% 10.08 Birr/m2
Total Unit Cost : 252 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1-
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
PROJECT: ROOFING WORKS LABOUR HOURLY OUTPUT: 3.50 0.48 1.00
WORK ITEM: ( 7.1 ) G-32 CIS Roofing ( Including Truss & Purlins ) EQUIPEMENT: 0.08 1.18
TOTAL QANTITY OF WORK ITEM: 1.00 m2 = 1 Trusses =1ml. Purlin RESULT: 364 Birr/m2
A= Materials Unit Cost 290.90 Birr/m2 B= Manpower Unit Cost - - - - C= Equipment Unit Cost
A= Materials Unit Cost 60.13 Birr/m2 B= Manpower Unit Cost 38.87 Birr/m2 C= Equipment Unit Cost 1.27 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 100.26 Birr/m2
Over head cost : 20% 20.05 "
Profit Cost: 5% 5.01 "
Total Unit Cost : 125 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-2-
10.00
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 1.25 m2/hr
WORK ITEM: (11.2) 2 Coats of cement plastering to soffit celling. EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1.00 m2 RESULT : 139 Birr/m2
A= Materials Unit Cost 60.25 Birr/m2 B= Manpower Unit Cost 49.36 Birr/m2 C= Equipment Unit Cost 1.61 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 111.22 Birr/m2
Over head cost : 20% 22.24 "
Profit Cost: 5% 5.56 "
Total Unit Cost : 139 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-3-
25.00
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 3.13 m2/hr
WORK ITEM: (11.4) 1 coat (final coat) cement rendering. EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1.00 m2 RESULT : 50 Birr/m2
A= Materials Unit Cost 20.48 Birr/m2 B= Manpower Unit Cost 17.85 Birr/m2 C= Equipment Unit Cost 1.42 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 39.75 Birr/m2
Over head cost : 20% 7.95 "
Profit Cost: 5% 1.99 "
Total Unit Cost : 50 Birr/m2
Remark 3.Coats of rendering ( 3+4 ) #REF!
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT INDIRECT UNIT COST
-5-
16.00
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 2.00 m2/hr
WORK ITEM: (11.5) Cement pointing to masonry wall surface (1:3). EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1.00 m2 RESULT : 64 Birr/m2
A= Materials Unit Cost 19.01 Birr/m2 B= Manpower Unit Cost 30.85 Birr/m2 C= Equipment Unit Cost 1.01 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 50.87 Birr/m2
Over head cost : 20% 10.17 "
Profit Cost: 5% 2.54 "
Total Unit Cost : 64 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1-
0.25
Angle iron pcs 1.00 241.50 241.50 Foreman 1.00 0.17 64.10 10.70 Tools 1.00 2.01 2.01
Sheet metal m2 0.17 5,700.00 950.00 Welder 1.00 1.00 24.75 24.75 Welding Machine 0.13 15.00 1.88
Electrod PCS 10.00 0.60 6.00 D/L 1.00 1.00 11.25 11.25
- -
- -
- -
- -
- -
A= Materials Unit Cost 1,346.01 Birr/m2 B= Manpower Unit Cost 1,974.53 Birr/m2 C= Equipment Unit Cost 124.32 Birr/m2
Remark _____________________________________________________________________________
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
0.01
Angle iron pcs 1.00 5,000.00 5,000.00 Foreman 1.00 0.17 64.10 10.70 Tools 1.00 2.01 2.01
Sheet metal m2 1.00 50,000.00 13,000.00 Welder 1.00 1.00 24.75 24.75 Welding Machine 0.13 15.00 1.88
Electrod PCS 10.00 0.60 6.00 D/L 1.00 1.00 11.25 11.25
- -
- - -
- - -
- - -
A= Materials Unit Cost 18,506.00 Birr/m2 B= Manpower Unit Cost 57,851.85 Birr/m2 C= Equipment Unit Cost 3,642.46 Birr/m2
Remark _____________________________________________________________________________
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-1-
14.00
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 1.75 m2/hr
WORK ITEM: (11.1) Sogn post production EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1.00 m2 RESULT : 10,512 Birr/m2
A= Materials Unit Cost 8,373.05 Birr/m2 B= Manpower Unit Cost 35.26 Birr/m2 C= Equipment Unit Cos 1.15 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 8,409.45 Birr/m2
Over head cost : 20% 1,681.89 "
Profit Cost: 5% 420.47 "
Total Unit Cost : 10,512 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-2-
10.00
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 1.25 m2/hr
WORK ITEM: (11.2) 2 Coats of cement plastering to soffit celling. EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1.00 m2 RESULT : 471 Birr/m2
A= Materials Unit Cost 325.73 Birr/m2 B= Manpower Unit Cost 49.36 Birr/m2 C= Equipment Unit Cost 1.61 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 376.70 Birr/m2
Over head cost : 20% 75.34 "
Profit Cost: 5% 18.83 "
Total Unit Cost : 471 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-3-
25.00
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 3.13 m2/hr
WORK ITEM: (11.4) 1 coat (final coat) cement Rendering. EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1.00 m2 RESULT : 159 Birr/m2
A= Materials Unit Cost 108.40 Birr/m2 B= Manpower Unit Cost 17.85 Birr/m2 C= Equipment Unit Cost 0.64 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 126.89 Birr/m2
Over head cost : 20% 25.38 "
Profit Cost: 5% 6.34 "
Total Unit Cost : 159 Birr/m2
Remark 3.Coats of rendering ( 3+4 ) #REF!
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
-5-
16.00
PROJECT: FINISHING WORKS. LABOUR HOURLY OUTPUT: 2.00 m2/hr
WORK ITEM: (11.5) Cement pointing to masonry wall surface (1:3). EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1.00 m2 RESULT : 339 Birr/m2
A= Materials Unit Cost 239.22 Birr/m2 B= Manpower Unit Cost 30.85 Birr/m2 C= Equipment Unit Cost 1.01 Birr/m2
Total of (1:02) Total of (1:03)
Hourly Output: _______________________ Hourly output: _________________
Direct Cost of Work Item = A+B+C = 271.08 Birr/m2
Over head cost : 20% 54.22 "
Profit Cost: 5% 13.55 "
Total Unit Cost : 339 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
ANALYSIS SHEET FOR DIRECT UNIT COST
Project: Koga Irrigation Project Labour output:_______________________
Equipment:___________________________
Work Item: Ф30" Class III R.C.P. Production Resultant: 15 lm/spd 1.875 lm/hr
Cement Qt. 0.75 261 195.65 Mason Foreman - I 1 0.75 64.10 48.07 Concrete mixer 1/4m3 1 0.75 93.60 70.20
Sand m3
0.12 438 52.50 Mason 1 1.00 24.75 24.75 Concrete vibrator 2 0.75 42.36 63.54
Crushed agregate m3 0.15 360 54.00 Operator - I 1 0.75 15.00 11.25 Water tanker 1 1 100.00 100.00
Reinforcement kg 20 22 430.00 Helper 4 1.00 15.00 60.00 Pipe molde 15 1 300.00 4500.00
Tying wires kg 0.6 29 17.40 Labourers 10 1.00 11.25 112.50 Hand tools 10 1 2.01 20.10
Cement Qt. 1.2 261 313.04 Mason Foreman - I 1 0.75 64.10 48.07 Concrete mixer 1/4m3 1 0.75 93.60 70.20
Sand m3 0.16 438 70.00 Mason 2 1.00 24.75 49.50 Concrete vibrator 2 0.75 42.36 63.54
Crushed agregate m3 0.26 360 93.60 Operator - I 1 0.75 15.00 11.25 Water tanker 1 1 100.00 100.00
Reinforcement kg 40 22 860.00 Helper 4 1.00 15.00 60.00 Pipe molde 15 1 300.00 4500.00
Tying wires kg 0.6 29 17.40 Labourers 10 1.00 15.00 150.00 Hand tools 10 1 2.01 20.10
Cement Qt. 0.05 261 13.04 Mason Foreman - I 1 0.25 64.10 16.02 Mixer 0 0.25 93.60
Sand m3 0.12 438 52.50 Mason 2 1.00 24.75 49.50 Vibrator 1 0.25 42.36
30" R.C.P. prolm 1 2100 2100.00 Operator - II 1 0.25 15.00 3.75 Hand tools 5 1.00 2.01
Labourers 10 1.00 11.25 112.50
Cement Qt. 0.05 261 13.04 Mason Foreman - I 1 0.25 64.10 16.02 F.end laoder 1 0.25 93.60
Sand m3 0.12 438 52.50 Mason 2 1.00 24.75 49.50 Hand Tamper 1 0.25 42.36
36" R.C.P. prolm 1 2100 2100.00 Operator - II 1 0.25 15.00 3.75 Hand tools 5 1.00 2.01
Labourers 10 1.00 11.25 112.50
Cement Qt. 0.08 261 20.87 Mason Foreman - I 1 0.25 64.10 16.02 F.end laoder 1 0.25 93.60
Sand m3 0.15 438 65.63 Mason 2 1.00 24.75 49.50 Hand Tamper 1 0.25 42.36
36" R.C.P. prolm 1 2100 2100.00 Operator - II 1 0.25 15.00 3.75 Hand tools 5 1.00 2.01
Labourers 10 1.00 11.25 112.50
Total Cost
10.59
10.05
20.64
17
lm/hr
Total Cost
23.40
10.59
10.05
44.04
36
lm/hr
Total Cost
23.40
10.59
10.05
44.04
36