1 mobilization 2 days Mon 11/11/24 Tue 11/12/24
2 excavation 2 days Wed 11/13/24 Thu 11/14/24 1
3 plane concrete 2 days Fri 11/15/24 Mon 11/18/24 2
4 foundation 2 days Tue 11/19/24 Wed 11/20/24 3
5 column neck and trench 3 days Thu 11/21/24 Mon 11/25/24 4
6 damproof 2 days Tue 11/26/24 Wed 11/27/24 5
7 backfill 5 days Thu 11/28/24 Wed 12/4/24 6
8 Grade beam 3 days Thu 12/5/24 Mon 12/9/24 7
9 slab on grade 2 days Tue 12/10/24 Wed 12/11/24 8
10 roof 3 days Thu 12/12/24 Mon 12/16/24 9
11 roof insullation 3 days Tue 12/17/24 Thu 12/19/24 10
12 rain drain piping work 2 days Fri 12/20/24 Mon 12/23/24 11
13 masonary work 2 days Tue 12/24/24 Wed 12/25/24 12
14 plaster 3 days Thu 12/26/24 Mon 12/30/24 13
15 door and window 3 days Tue 12/31/24 Thu 1/2/25 14
16 painting 3 days Fri 1/3/25 Tue 1/7/25 15
17 cleaning 4 days Wed 1/8/25 Mon 1/13/25 16