Format of Work Completion Report
Format of Work Completion Report
To
The Manager (CO-ORDINATION),
CESC Limited
This is in reference to my above application for installation of SPGS system I / We hereby confirm you that
I / we have completed the work of installation of the SPGS system of capacity ...................... and submit
the following basic information for your perusal and request you to inspect and commission the system.
4. No. of Modules 46
5. Total Capacity (kWp) 20KWP
6. Date of Installation 4th SEP 2023
7. Applicable Standard (BIS/IEC) IEC 61215/IEC61730
(PART I &II) IEC 62804
B. Details of the Inverter
GOODWE TECHNOLOGIES co.
8. Name and address of the inverter manufacturer ltd. SUZHU,215011.CHAINA)
Certification:
I / We certify that the above said SPGS system is installed and the equipment used in the system comply
the Technical and Safety Standards as specified in the regulations notified by the MNRE / CEA / WBERC
for the SPGS systems.
Enclosures:
N.B: Online Applicant should provide above documents during Connectivity Inspection