MPR July Updated 20233

Uploaded by

Nani Sai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
37 views65 pages

MPR July Updated 20233

Uploaded by

Nani Sai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 65

Consultancy Services for Authority's Engineer for Supervision of Rehabilitation and

Upgradation of NH-565 from km.86.057 to 132.920 Nagarjuna Sagar Dam to


Davulapally Section to two Lane with paved Shoulder in the State of Andhra Pradesh
through EPC Mode

Authority’s Engineer
M/s. Dhruv Consultancy Services Limited Associate with
Kaius Consulting Pvt. Ltd.

MONTHLY PROGRESS REPORT FOR THE MONTH OF JULY,


2023
1
Table of Contents

SL. No Particulars Page No.


1.0 Executive Summary 4-4
1.1 Construction Progress in Current Month 4-4
1.2 Current Issues and Recommended Action by IE/AE 5-5
1.3 Strip Plan (Summary) 6-6
1.4 Strip Plan (Details) 7-17
1.4.1 Physical Progress status of Structures 18-18
2.0 Project Overview 19-19
2.1 Sailent Features of Projects 19-19
2.2 Project Milestone 20-20
2.3 Location Map 21-21
2.4 Key Plan 22-22
3.0 Critical Issues & Action Log 23-23
3.1 Pending Issues & Action Log 23-23
3.2 Obligations As Per Contract 23-23
4.0 Physical Progress 24-24
Detailed Scope of Work & Physical Progress by
4.1
Component 25-26
5.0 Land Acquisition and Clearance 27-27
5.1 LA Summary 27-27
5.2 LA Detail by CALA 28-28
5.3 LA Detail by Village for Each CALA 28-28
5.4 Manpower details of CALA 29-29
5.5 Clearance Summary 30-30
5.6 Status of Utilities Shifting 31-31
6.0 Change of Scope 32-32
7.0 Mobilization of Resources 33-35
8.0 Financial Progress Details (For PPP Projects) 36-36
2
8.1 Pen Pictures -Escrow 36-36
8.2 Escrow Details 37-38
9.0 Summary of Quality Control Tests 39-41
9.1 Test Witnessed by IE/AE 39-41
9.2 Test Conducted by IE/AE 39-41
Monitoring of Maintenance Obligations During
10.0
Construction Phase 42-42
10.1 Critical Issues & Action Log 42-42
10.2 Summary of Repair Works 42-42
10.3 Status of Damage 42-42
11.0 Safety Features 43-43
11.1 Pen Pictures of safety Features 43-43
11.2 Accident Report 44-44
12.0 Annexures 45-48
13.0 Annex 49-49
13.6 Weather Report 50-51
Organizational Chart of Concessionaire / Contractor
13,13.7.1
and IE / AE 52-52
13.7.2 Contractor Organization Chart 53-53
13.8 List Of Lab Equipment 54-56
14.0 Camp & Plant Establishment 57-57
14.1 Project Photographs 58-65

3
1. Executive summary
Total length of project (Design Length 46.863 Km) from Design Ch 86.057 to Design Ch
132.920 with total cost of Rs. 225.73 Cr. Appointed Date was declared as 25/05/2022 and
scheduled date of completion of construction is 04/05/2024 (with 730 days construction
period).
Cumulative physical progress is 62.36% (Rs. 140.76 Crores) against scheduled progress of Rs.
145.63Crore (i.e., 64.5%). Financial progress is Rs. 138.33 Crores (i.e., 61.28 %). The
appointed date has been declared as 25 May,2022. Contractor has mobilised manpower,
machinery and established its site camp office along with erection of stone crusher unit 1 no.
and Batching Plant 1 no. 1 No. Wet Mix Plant and 1 no. Hot Mix Plant.
Shifting of electrical utilities and water pipe lines under RWS&S Department work is in
progress.
Land acquisition is under progress mainly for Curve Improvement / Realignment locations.
Also, land required for construction of Toll Plaza. Demolition of existing structures
(Hindrances in ROW) are under progress with the help of NH Division / Local Administration.
Now, 46.863 Km (i.e., 100%) of project highway is encumbrance free and available for
execution of works.
1.1 Construction Progress in Current Month
Key reporting Metrics Value % Amount
Scheduled Physical Progress % 4.47%
Cumulative Physical Progress up to Current Month % 62.36%
Physical Progress During Current Month % 5.27%
Financial Progress (%) 61.29%
Cumulative Expenditure till date (Cr) 138.34
Tests Passed as % of total tests Witnessed by AE 75%
Tests Passed as % of total tests Conducted by AE 75%
Number of Pending COS proposals 3.0
Amount for pending COS (Rs Cr) 22.88 Crs, (Negative scope 2.83 Cr)

4
1.2 Critical Issues & Recommendation action by AE:

1. Slow Progress of Structure: Nill


a) Recommendation: Nill
2. Status of Change of Scope Proposals: AUP & RCC drain EPC Contractor had Submitted
Positive Scope 17.54 Crs.
a) Recommendation: Authority Engineer had recommended 14.24 Crs
3. Electrical Utility shifting contractor had submitted Rs 2.52 Cr
a) Recommendation: Authority Engineer had reviewed and commented
4. Descope of Rigid Pavement (Negative scope) contractor had submitted Rs 2.83 Cr
a) Authority's Engineer had reviewed and commented

5
1.3 Strip Plan (Summary):

1.Work Front Unavailable & Reason for Unavailability 2. Length Completed by Layer (MCW)

% Total Pending % Total Pending


Length (km) Length (km)
Length Length
Total length 46.863 Total length 46.863
Total Length Completed (Till
Total Work front Unavailable 0 0.00% 36.031 77.00%
DBM)
Pending Land Acq. 0 0.00% BC 0.000 100.00%
Pending Clearances 0 0.00% DBM 36.031 77.00%
Encumbrances 0 0.00% WMM 38.318 81.77%
GSB 38.468 82.09%
SUBGRADE 39.078 83.39%
C&G 41.310 88.15%

Status of Clear Front Availability as on 31st July 2023 is given below :-

Sl. no. Description Unit Scope %age Remarks


1 Total Project Length Km 46.863
2 Work front available Km. 46.863 100.00%
3 Land Acquisition Km. 0.000 0.00%
Availability of clear Work front
The location wise details of stretch affected due to land acquisition is given below: -

S. No. Description Length affected Reason


NILL NILL NILL NILL NILL NILL
NILL NILL NILL NILL NILL NILL
NILL NILL NILL NILL NILL NILL
Total Length (Km.): 0.000

6
1.4 Strip Plan Details

7
8
9
10
11
12
13
14
15
16
17
1.4.1 Physical Progress status of Structures

Nagarjuna Sagar Dam to Davulapally Section of NH -565


Progress Status of Structure Works as on 31-07-2023

Physical Progress status of Structures

Reconstruction New Construction Widening GRAND TOTAL

S
Balance to Start

Balance to Start

Balance to Start
Work Taken Up

Work Taken Up

Work Taken Up
Traffic open on

Traffic open on

Traffic open on
Type of Traffi
N
Completed

Completed

Completed
Structure Work Balanc c
o
Scope

Scope

Scope
Scop Complete

road

road

road
Take e to open
e d
n up Start on
road

Hume Pipe
1 23 9 - - - -
Culverts 20 3 20 6 1 2 6 - 32 26 1 5 26
Box/Slab
2 4 - 4 1 - 1 -
Culverts 4 4 2 1 1 2 - 9 6 1 2 6
Minor
3 10 - 6 - - - - -
Bridges 8 2 8 4 2 4 - 16 12 4 - 12
Major
4 bridges - 2 - - - - - - - - - -
2 2 - 2 - -
New
Animal
5 Underpasse 2 - - - - - - - - - - -
2 2 - - 2 -
s (AUP)
Total: 41 19 1 - 1 -
32 4 5 32 12 4 3 12 - 61 44 8 9 44
100 78 10 12 78 100 63 21 16 63 100 0 0 100 100
0% 72% 13% 15%
% % % % % % % % % % % % % % %

18
2.Project Overview:
2.1 Salient Features of Project:

Rehabilitation and Upgradation of NH-565 from Km


86.057 to 132.920 Nagarjuna Sagar Dam to
Project Name
Davullapally Section to Two Lane with Paved Shoulders
in the state of Andhra Pradesh through EPC Mode.

NH No. (New/Old) NH-565


Scheme/ Phase NH (O)
Mode of the Execution (BOT Toll/BOT Annuity
/EPC/HAM/ Item Rate/Others)
EPC MODE
No. of Lanes /Configuration 2 Lane with Paved Shoulder
Length of the Project (in KM) 46.863 kms

Tender Amount Rs 225.73 Cr, L.S.C. E NO: 06/2021-22


Total Project Cost (in Cr)
(Estimated cost 385.97 Cr Job No. NH-565-AP-2020-21-
709, Dt.31.03.2021)
No. of Bypasses (Name of Town, Length) Nill
No. Of Major Bridges (Number and Location) 2 No's (km.96+310 & km.109+735)
No. of Toll Plazas (Number and Location) 1 No (km.94+970)
No. of Fly overs (Number and Locations) Nill
DPR Authority 's Engineer Name M/s KDM ENGINEERS INDIA PVT LTD
Lead & Consortium Members of Banks -

M/S KCVR Infra Projects Pvt.Ltd (Job No. NH-565-AP-


concessionaire Name (SPV& Parent Company)
2020-21-709, Dt.31.03.2021)

Date of Award (LOA Date) 03-03-2022


Appointed Date 25-05-2022
Concession Period -
Construction Period 730 Days
O&M Period (in Days) 1825 Days
Scheduled Date of Completion 23-05-2024

M/s. Dhruv Consultancy Services Limited Associate with


Authority Engineer
Kaius Consulting Pvt. Ltd.

08-01-2022 (Job No. NH-565-AP-2020-21-709,


IE/AE Agreement Date
Dt.31.03.2021)
IE/AE Mobilization Date 01-09-2022

19
2.2 Project Milestone:

Planned
Description (Days
Financial Amount Current
Project Milestone from Appointed Remarks
(Cr.) Financial Scheduled Status
Date)
Progress Date

M-I, achieved during


Milestone I 256 Days 22.57 10% 04-02-23 the month of Oct.'22

M-II, achieved during


Milestone II 438 Days 79.01 35% 05-08-23 the month of Feb.'23

Milestone III 621 Days 158.01 70% 04-02-24 61.29%

Scheduled Completion 730 Days 225.73 100% 23-05-24

20
2.3. Project Location Map:

Project Start
Km 86+057

Project End
km 132+920

Project Length - 46.863 KMs

District Covered - palnadu (Andhra Pradesh)

21
2.4 Key Plan

22
3. Critical Issues and Action Log:
3.1 Pending Issues & Action Log:
Expected
Chainage Length Action Action(s) Date / Actual
Issue Ongoing /New Concerned
Sl.NO Type Affected Due Affected Taken till Suggested by Date of
Description issue/Resolved Authority
to the issue (Km) now AE Resolving
issue
1 Nill NA NA NA NA NA NA NA NA
2 Nill NA NA NA NA NA NA NA NA

3.2 Obligations As per Contract:

Expected Contents & Structure


a) Critical Obligations and Constraints of Concessionaire as per Contract: Nill
b) Critical Obligations of Authority as per Contract: Nill
c) Critical Obligations of Authority as per Contract: Nill
d) Critical Pending Obligations of IE/AE as Per Contract: Nill

23
4.0 physical Progress:

Physical Progress
Component % Weightage
(During Current (Upto Previous (Cumulative,
Month) Month) Upto Current Month)

Road works including culverts, Minor Bridges,


under passes, over passes approaches to 73.10% 4.24% 49.00% 53.24%
ROB / RUB / Major Bridges / Structures

Minor Bridge Works 5.32% 0.22% 2.57% 2.80%

Major Bridge Works 1.59% 0.29% 0.64% 0.93%

Other Engineering works 17.50% 0.51% 4.12% 4.63%

Shifting of Utilities (Electrical and RWS water


2.49% 0.00% 0.77% 0.77%
Pipe line)

Total Physical Progress 100.00% 5.27% 57.09% 62.36%

24
4.1 Detailed Scope of Work & Physical Progress by Component:

25
26
5.0 Land Acquisition and Clearance:
5.1 LA Summary

Total Required Total in Possession in Total To be


Description
(ha) start (ha) Acquired (ha)

Existing ROW 28.034 28.034 0.000

Pvt Land to be Acquired 12.145 12.145 0.000

Public Land To be Acquired 121.816 121.816 0.000


Grand Total 161.995 161.995 0.000

27
5.2 LA Detail by CALA
Total Land Amount
3G 3G 3A Amount Amount Pending
to be 3H Pending 3H Done 3D Done Disbursed by
CALA Pending Pending Pending Awarded Deposited Amount
Acquired (Ha) (Ha) (Ha) CALA (Crore
(Ha) (Ha) (Ha) (Crore Rs.) (Crore RS.) (Crore Rs.)
(Ha) Rs.)
CALA 4.13 0.00 0.00 0.00 0.00 0.00 0.00 1.56 1.56 1.55 0.01

Grand Total 4.13 0.00 0.00 0.00 0.00 0.00 0.00 1.56 1.56 1.55 0.01

5.3 LA Detail by Village for Each CALA


Amount
Amou
Deposited
3H 3G 3D nt
Total Land to 3A (Crore Ha) Pending
Pendi 3H Done Pendi 3G Done Pendi 3D Done 3 A Done Award
Village be Acquired Pending Amount Amount
ng (Ha) ng (Ha) ng (Ha) (Ha) ed
(Ha) (Ha) Disbursed (Rs. Cr)
(Ha) (Ha) (Ha) (Crore
by CALA (RS.
Rs.)
Cr)
Talla Palli Under Under
0.8660461 0.000 0.8660461 0.000 0.8660461 0.000 0.8660461
Village Progress Progress
Kothapalli Under Under
0.2630513 0.000 0.2630513 0.000 0.2630513 0.000 0.2630513
Village Progress Progress
Mandadi Under Under
0.7871307 0.000 0.7871307 0.000 0.7871307 0.000 0.7871307
Village Progress Progress
Uppalapadu Under Under
0.056819 0.000 0.0568190 0.000 0.0568190 0.000 0.0568190 1.56 1.55 0.01
Village Progress Progress
Veldurthi Under Under
0.9921487 0.000 0.9921487 0.000 0.9921487 0.000 0.9921487
Village Progress Progress
Sirigiripadu Under Under
1.3344791 0.000 1.3344791 0.000 1.3344791 0.000 1.3344791
Village Progress Progress
Under Under
Grand Total 4.2996749 0.000 4.2996749 0.000 4.2996749 0.000 4.2996749
Progress Progress

28
5.4 Manpower Details Of CALA

Provided
Revenue
by Amins/ Patwaries Tehsildars/D
Inspection Tehsildars/ Clerks/Sahayak Computer
CALA <Agency Surveyo /Village ep Accountants Peons Chairman Total
s Kanungo s Operators
> / State rs Accountant Tehsildars
/Kanungo
Govt

(CALA <Agency
1) >

(CALA State
1) Govt

(CALA <Agency
2) >

(CALA State
2) Govt

Grand
Total

29
5.5 Clearance Summary

Environment
Issues
Proposal Description Status Length Completed Current Stage
/Comments
NILL NILL NILL NILL NILL
Forest Land
Issues
Proposal Description Status Length Completed Current Stage
/Comments
NILL NILL NILL NILL NILL
Wild Life
Issues/
Proposal Description Status Length Impacted Current Stage
Comments

Work has been Land has been


7.04 Km NILL NILL
taken up cleared
Tree Cutting
Issues/
Proposal Description Status Length Impacted Current Stage
Comments
NILL NILL NILL NILL NILL
Railway (ROBs/RUBs)
Issues/
Proposal Description Status Length Impacted Current Stage
Comments
NILL NILL NILL NILL NILL

30
5.6 Status of Utilities Shifting
Date
When
Date of Date of
Estimat Date of
approva Deposi Progres
Length Date of Request e Was Certificatio Issue
Utility Departmen l by t of s of Estimate
Name Status Affecte by Authority for Receiv n of From /Comment
Category t Authorit Super Physical Amount
d Estimate ed from Agency for s
y RO/ Vision Shifting
Concer Completion
HQ Charge
ned
Dept
Sirigiripad
u To
Water In Progress 5.0km RWS
Veldhurth
y
Veldhurth
y to
In Progress 1.5km RWS 78.95% 10-12-2022 13309651.82
Sirigiripad
u
Veldhurth
y to
Completed 3.0km RWS
Uppalapa
du
Electricity
Spun Poles -
12.50 In Progress 704 APSPDCL
9.1 PSCC
Poles In Progress 137 APSPDCL
33 KV Completed 6.9 APSPDCL
11 KV In Progress 18 APSPDCL
22-05-
LT In Progress 14 APSPDCL 42896648.09 30.00% 42896648.09
2023
DTR's In Progress 70 APSPDCL
M+6 Tower
Erections In Progress 36 APSPDCL
M+9 Tower
Supply & In Progress 4 APSPDCL
Erection
Others NILL NILL NILL NILL NILL NILL NILL NILL NILL NILL NILL NILL

31
6.0 Change of Scope

Date of First Submission to COS Actual Date of


Sl. No Proposal Details Current Status
AE Amount Approval
Committee Recommended KCVR/NS-D/NH- Authority Engineer had reviewed
1 Certain Stretches and Structures 565/2022/169, and commented verbally to 18.48 Crs Nill
are within the forest area Dated:04.04.2023 resubmit
Authority Engineer had reviewed
KCVR/NS-D/NH-
and recommended Rs 14.24 Cr by
2 2nd time Resubmission 565/2022/189, 17.54 Crs Nill
Letter No DCSL/AE/NH-565/2023-
Dated:18.05.2023
24/780 dated: 31.05.2023
Authority Engineer had reviewed
KCVR/NS-D/NH- and Commented vide Letter
1st Submission of Electrical
3 565/2023/163 dated DCSL/Associated 6.83 Crs Nill
Utility shifting
27.03.2023 with/KSPL/TL/ND/2023-24/AP/71
dated: 01.04.2023
Authority Engineer had reviewed
KCVR/NS-D/NH-
Descope Rigid pavement Km and Commented vide Letter No.
4 565/2023/206 dated 2.83 Crs Nill
86.57 to Km 86.88 DCSL/AE/NH-565/2022-
17.06.2023
2023/1151 dated 26.06.2023
Authority Engineer had reviewed
KCVR/NS-D/NH-
and Commented vide Letter No.
5 2nd time Resubmission 565/2023/209 dated 2.52 Crs Nill
DCSL/AE/NH-565/2022-
20.06.2023
2023/1152 dated 26.06.2023
Authority Engineer had reviewed
KCVR/NS-D/NH-
Descope Rigid pavement Km and Commented vide Letter No.
6 565/2023/206 dated 2.83 Crs Nill
86.57 to Km 86.88 DCSL/AE/NH-565/2022-
17.06.2023
2023/1151 dated 26.06.2023

32
7.0. Mobilization of Resources

Deployed Expected
Planned Reason for
Equipment Actual during Delay due to
Sl. No Make Model /Required Under/Over Remarks
Name Quantity The Under
Quantity Mobilization
Month Mobilization

BATCHING
1 Schwing setter CP45 1 1 May-22
PLANT

CRUSHING
2 Puzzulona 250 TPH 1 1 May-22
PLANT
3 WMM PLANT Vibrant 200 TPH 1 1 May-22
4 HOT MIX PLANT Vibrant 140 TPH 1 1 May-22
BITUMEN
5 Ashok Leyland 2516 1 1 May-22
SPRAYER

AIR Machines & Machinery


6 Moto Super 1 1 May-22
COMPRESURE manufactures Ltd

7 WEIGH BRIDGE Meco Digi Scale 100TN 1 1 May-22

Ex-70-1, EX-110-2,
8 EXCAVATOR TATA HITACHI 10 10 May-22
EX130-3 & EX200-4

9 EXCAVATOR Komatsu PC-71-1 & PC-210-1 2 2 May-22

Lui gong CLG414 &


10 MOTOR GRADER Lui gong, Cat 3 3 May-22
CAT 120 motor

33
TRACTOR
11 John Dheere 5210 4WD 2 2 May-22
GRADER

SOIL
12 Volvo, Hamm SD110 &HAMM 4 4 May-22
COMPACTOR
13 WHEEL LOADER Hindustan 2021E 2 2 May-22
14 SENSOR PAVOR Volvo P5320BABG 1 1 May-22
15 PTR IR RTR220 1 1 May-22
TANDEM
16 Volvo DD100 & DD90 3 3 May-22
ROLLER
17 WATER TANKER Ashok Leyland 2516 4 4 May-22
TRACTOR
18 Mahindra 475 & 275 3 3 May-22
TANKER
19 DIESEL TANKER TATA 407 1 1 May-22
Bharat Benz &
20 HYVA/TIPPER 2,52,31,61,62,516 45 45 May-22
Ashok Leyland
21 JCB JCB 3DX 1 1 May-22
22 Hydra Crane Hydra 15 2022 1 1 May-22
23 TRACTOR Mahindra 475 2 2 May-22

TRANSIT
24 Ashok Leyland 2516 10 10 May-22
MIXTURE

Splender plus & Star


25 BIKE Hero. TVS 35 35 May-22
City

KDI Hydraulic
26 BROOMER 2017 1 1 May-22
Broomer
27 Kerb Machine Siddivinayaka 2022 1 1 May-22
28 TRAILOR Ashok Leyland 2516 2 2 May-22
34
CAT, 30KV, 62.5 KV,
29 D.G.SET KIRLOSKAR, 725KV, 380KV & 5 5 May-22
Jackson Cumins 160KV

WEILDING
30 Toshan ARC 400 4 4 May-22
MACHINE

Mahindra &
31 BOLERO PICKUP 102015 1 1 May-22
Mahindra

RMC CONCRETE
32 Putzmister 2022 1 1 May-22
PUMP

Mahindra &
33 CAMPERS 2022-3 & 2018-2 6 6 May-22
Mahindra

Mahindra &
34 BOLERO 2022 & 2014 2 2 May-22
Mahindra

35
8.Financial Progress Details (For PPP Projects)

8.1 Pen Picture-Escrow

Cumulative inflow to Cumulative Outflow to Inflow to Escrow Outflow to Escrow


TPC (Cr) Escrow till Previous Escrow till Previous during the month during the month
Month (Cr) Month (Cr) (Cr) (Cr)
Nill Nill Nill Nill Nill
Nill Nill Nill Nill Nill
Nill Nill Nill Nill Nill

36
8.2 Escrow Details

MINISTRY OF ROAD TRANSPORT&HIGHWAYS


Rehabilitation and Upgradation of Nh-565 from km.86.057 to 132.920 Nagarjuna Sagar Dam to Davilapally Section to two
Lane with paved Shoulder in the State of Andhra Pradesh through EPC Mode

CASH FLOW (S- CURVE)

250.00

225.71
224.24
220.78
216.42
200.00

209.53
200.65
189.57
140.76

178.23
128.86
150.00

118.48

164.21
112.22

155.46
106.76

145.63
135.54
82.12

121.10
100.00
69.00

106.44 Cumulative
56.98

91.10

Target
44.09

75.85

Series2
29.45

50.00
61.39
16.50

46.37
9.26
1.22
0.00

0.00

33.94
24.38

0.00
15.46
9.22
3.30
0.00

0.01

37
wise
wise
wise
wise

Target
Target
Month

Amount
Amount
Amount
Amount

Monthly
Monthly
Monthly
Monthly

Achieved
Achieved
Achieved
Achieved

(in lakhs)
(in lakhs)
(in lakhs)
(in lakhs)

Mile Stone
Cumulative
Cumulative
Cumulative
Cumulative

Percentage
Percentage
Percentage
Percentage

Target Monthly
Target Monthly
0.0% 0.00% 0.0% 0.00% 0.00 0.00 0.00 0.00 May-22

0.0% 0.00% 0.0% 0.00% 0.01 0.01 0.00 0.00 Jun-22

1.5% 1.46% 0.5% 0.54% 3.30 3.29 1.22 1.22 Jul-22

4.1% 2.62% 4.1% 3.56% 9.22 5.92 9.26 8.04 Aug-22

6.8% 2.76% 7.3% 3.21% 15.46 6.24 16.50 7.24 Sep-22

10.8% 3.95% 13.0% 5.74% 24.38 8.92 29.45 12.95 Oct-22

15.0% 4.24% 19.5% 6.49% 33.94 9.56 44.09 14.64 Nov-22

Mile stone -I (256 Days) -04-02-2023-10%


20.5% 5.51% 25.2% 5.71% 46.37 12.43 56.98 12.89 Dec-22

27.2% 6.65% 30.6% 5.33% 61.39 15.02 69.00 12.02 Jan-23

33.6% 6.41% 36.4% 5.81% 75.85 14.46 82.12 13.12 Feb-23

40.4% 6.76% 47.3% 10.92% 91.10 15.25 106.76 24.64 Mar-23

47.2% 6.80% 49.7% 2.42% 106.44 15.34 112.22 5.46 Apr-23

38
35%
53.7% 6.50% 52.5% 2.77% 121.10 14.66 118.48 6.26 May-23

60.1% 6.40% 57.1% 4.60% 135.54 14.44 128.86 10.38 Jun-23

64.5% 4.47% 62.4% 5.27% 145.63 10.09 140.76 11.90 Jul-23

Mile stone II (438 Days) - 05-08-2023-


68.9% 4.36% 155.46 9.83 Aug-23

72.8% 3.88% 164.21 8.75 Sep-23

79.0% 6.21% 178.23 14.02 Oct-23


70%

84.0% 5.02% 189.57 11.34 Nov-23

88.9% 4.91% 200.65 11.08 Dec-23

92.8% 3.93% 209.53 8.88 Jan-24


Mile stone III (620 Days) - 03-02-2024-

95.9% 3.05% 216.42 6.89 Feb-24

97.8% 1.93% 220.78 4.36 Mar-24

99.3% 1.53% 224.24 3.46 Apr-24

100.0% 0.65% 225.71 1.47 May-24


730 days - 23-05-2024
Sch.Completion of Project:
9.0 Summary of Quality Control Tests

39
40
41
10.0 Monitoring of Operations and Maintenance Obligations

10.1 Maintenance Status during Construction Phase

This Month safety measures taken


1 - Safety Sign Boards erected on site.
2 - Gunny bags / Safety Ribbon with Bamboo Post provided on site

10.2 Maintenance Status during Operations & Maintenance Phase (If Applicable)

10.3 Status of Damage

42
11.0 Safety Features

11.1 Pen Picture on Safety Features


Details to be provided after assessment of the site requirement vis-à-vis provisions in the EPC Agreement

Additional Financial implications of


Location of Black Suggested Remedial Measures Remedial additional Remedial
Spots within provisions of Contract Measures Measures for Authority

(If any) (Cr.)

-NA- -NA- -NA- -NA-

-NA- -NA- -NA- -NA-

-NA- -NA- -NA- -NA-

43
11.2 Accident Data:
Nagarjuna Sagar dam to DavulaPally Section NH-565
Abstract of Accident Data for the month of July -2023
Date: 31-07-2023

Stretch (Existing/Design) Date of Accident

Existing/ Fatal No. of


SI. Accident
State NH. No. Design Length Accident Animals Remarks
No. (In No.)
(Km) (In No.) Fatalities Grievous Minor Injured Killed, if
From-(Km) To-(Km) (No. of (No. of (No. of (No. of
persons) persons) persons) persons)

Andhra
1 Pradesh NH 565 86+057 132+920 46.863 Nil Nil Nil Nil Nil Nil Nil

44
12 Annex 1: Detailed list of Physical Components as per Schedule H

Details to be Provided after assessments of the site requirements Vis -a-Vis Provisions in the EPC Agreement
Rehabilitation and Upgradation of Nh-565 from km.86.057 to 132.920 Nagarjuna Sagar Dam to Davilapally Section to
two Lane with paved Shoulder in the State of Andhra Pradesh through EPC Mode

Component Item Description

1 3
A - Widening and Strengthening of existing Road-2Lane
TCS - 1, 6, 7 & 8
Earth works up to top of the sub-grade.
Earth work in Shoulders
GSB
WMM
1.Road Works Including Bituminous Base Course (DBM)
Culverts, Widening & Wearing Coat (BC)
repair of Culvert B - Widening and Strengthening of existing Road-4Lane
TCS - 4 & 5
Earth works up to top of the sub-grade.
Sub Base Course (GSB)
Non-Bituminous Course (WMM)
Bituminous Base Course (DBM)
Wearing Coat (BC)

45
Paver Block including Sand Filling
C - Reconstruction/New 2-lane-Realignment/Bypass
TCS - 2 & 3
Earth works up to top of the sub-grade.
Earth work in Shoulders
GSB
WMM
Bituminous Base Course (DBM)
Wearing Coat (BC)

D - Reconstruction & New Culvert on existing road, realignments, bypasses.

Culverts (Length < 6m)


1. Minor Bridges
I) Foundation + Sub Structure
ii) Super-Structure
2. Minor Bridges, Over iii) Approaches
Passes/under passes 2. Animal Underpasses
I) Foundation + Sub Structure
ii) Super-Structure
iii) Approaches
3.Major Bridge Works and C - New Major Bridges
ROB/RUB/EUP Foundations.

46
Sub Structure
Super structure (including bearings)
Misc. Items like Crash Barriers, Wearing Coat, Expansion Joint, Drainage Spout, Stone
pitching & road marking etc.
Other Works
Service Roads
Toll Plaza
Road Side Drain / Footpath
Road signs, Markings, km stones, safety devices.
Project Facilities (Junctions, Bus Bay and Bus Shelter
4. Other Engineering works
Highway Electrical Lighting including Lighting in Toll Plaza etc.
Median Fill
Junctions
Protection works
Other Works - works to be executed as per MBWL Guide lines
Site Clearance, Jungle Clearance, tree cutting, dismantling etc.
Shifting of Utilities (Electrical and RWS water Pipe line)
Shifting of Electrical Poles
5.Shifting of Utilities Spun Poles - 12.50
(Electrical and RWS water
9.1 PSCC Poles
Pipe line)
33 KV
11 KV
47
LT
DTR's
M+6 Tower Errections
M+9 Tower Supply & Errection
Shifting of RWS water Pipe line
150 mm Día DI K7 Pipe
Uprooting of Existing 150mm Dia pipe incl. excav.
Provision of Anchor Blocks & Thrust Blocks
Air Valves with specials including valve chambers
Scour Valves with specials including valve chambers

48
Rehabilitation and Upgradation of NH-565 from Km 86.057 to 132.920 Nagarjuna
Sagar Dam to Davullapally Section to Two Lane with Paved Shoulders in the state of
Andhra Pradesh through EPC Mode.

49
13.6 Weather Report

Project Name: Rehabilitation and Upgradation of NH-565 from Km 86.057 to 132.920 Nagarjuna Sagar Dam to
Davulapally section to two lanes with paved shoulder in the State of Andhra Pradesh through EPC mode.

Weather Report for the Month of July-2023


Cum
Temperature (oC) Humidity (%) .
S. Rainfall
Rain
N Date Remarks
fall
o.
(In
Max. Min. Max. Min. (In mm)
mm)
1 01-07-2023 40.8 29.9 58 30 0.0 0.0
2 02-07-2023 40.3 29.9 57 32 9.0 9.0
3 03-07-2023 40.2 29.5 73 33 0.0 9.0
4 04-07-2023 37.3 29.2 63 40 0.0 9.0
5 05-07-2023 35.0 28.4 69 45 0.0 9.0
6 06-07-2023 33.5 28.4 62 44 0.0 9.0
7 07-07-2023 34.7 28.4 61 43 0.0 9.0
8 08-07-2023 37.0 29.0 58 38 0.0 9.0
9 09-07-2023 39.3 29.1 69 33 1.0 10.0
1
10-07-2023 38.1 28.9 63 35 0.0 10.0
0
1
11-07-2023 39.2 28.5 71 33 3.0 13.0
1
1
12-07-2023 33.5 28.0 77 54 0.5 13.5
2
1
13-07-2023 35.5 28.2 71 42 0.0 13.5
3
1
14-07-2023 39.3 29.3 56 23 0.0 13.5
4
1
15-07-2023 35.1 29.1 61 41 0.0 13.5
5
1
16-07-2023 35.8 29.0 60 37 0.0 13.5
6
1
17-07-2023 34.7 27.3 69 40 0.0 13.5
7
1
18-07-2023 32.9 25.9 76 49 4.0 17.5
8
1
19-07-2023 28.4 27.1 77 69 7.4 24.9
9
2
20-07-2023 30.1 26.0 78 56 3.4 28.3
0
2
21-07-2023 32.1 26.3 78 57 1.1 29.4
1
2
22-07-2023 31.0 27.4 78 69 0.0 29.4
2
2
23-07-2023 30.7 28.5 79 60 0.0 29.4
3
2
24-07-2023 30.7 25.4 81 60 7.1 36.5
4

50
2
25-07-2023 29.5 25.3 83 68 26.7 63.2
5
2
26-07-2023 28.8 24.7 85 77 11.2 74.4
6
2
27-07-2023 32.1 26.5 73 55 0.0 74.4
7
2
28-07-2023 31.5 26.2 70 49 0.0 74.4
8
2
29-07-2023 30.2 25.2 68 50 5.0 79.4
9
3
30-07-2023 32.2 26.6 72 58 0.0 79.4
0
3
31-07-2023 31.2 26.7 63 55 0.0 79.4
1

EPC
Authority`s
Contactor
Engineer
`s
Represent Representati
ative ve

51
13.7 Organizational Chart of Concessionaire / Contractor and IE / AE
13.7.1 Organization Chart of Authority’s Engineer

52
13.7.2 Organizational Chart of Concessionaire / Contractor

53
13.8 List of Lab Equipment’s

54
55
56
14.0 Camp & Plant Establishment

57
14.1 Project Photographs

Checking of Reinforcement and shuttering for Slab at Ch km 129+565 Minor bridge

Casting of Cubes for M-30 Grade Concrete Raft at Ch km 103+457 Minor Bridge

58
Checking of Reinforcement and Shuttering for Raft at Ch km 103+457 Minor bridge

Checking of Reinforcement for RCC 2nd Girder at ch km 109+723 Major Bridge

59
Checking of Reinforcement and Shuttering for Slab at ch km 129+565 Minor Bridge

Checking of Reinforcement for RCC 12th Girder at Ch km 96+373 Major Bridge

60
Pouring of M-35 Grade Concrete for RCC 12th Girder at Ch km 96+373 Major Bridge

Checking of Reinforcement for RCC 11th Girder at Ch km 96+373 Major Bridge

61
Checking of Reinforcement and Shuttering for Slab at Ch km 129+692 Minor Bridge

Checking of PCC bottom level at Ch km 103+435 minor bridge


62
Checking of Reinforcement and shuttering for abutment A1 Cap at Ch km 96+373 Major bridge

Checking of Reinforcement and shuttering for abutment A2 Raft at Ch km 96+373 Major bridge
63
DBM Laying and rolling in Progress at Ch km 91+500 to 92+380 LHS

DBM Laying and rolling in Progress at Ch km 91+500 to 92+380 LHS

64
FDD Checking and Moisture for DLC at Ch km 94+970 to 95+000 RHS

Checking for Subgrade top Levels at Ch km 88+160 to 88+260 LHS

65