Welding Control-Procedure (WCP)
Welding Control-Procedure (WCP)
TABLE OF CONTENTS
1.0 PURPOSE 3
2.0 SCOPE 3
4.0 DEFINITIONS 3
5.0 PROCEDURE 4
6.0 RECORD 7
Project No Unit Doc.Type Mat. Code Serial no Rev
A
LI. Job No LI. Doc. LILAMA 001 Page
69.1/WCP 3 of 7
1.0 PURPOSE
This procedure describes the general requirements for control of welding activities to
ensure all production welds are of good quality, meeting the relevant specifications and
Code requirements.
2.0 SCOPE
This procedure is applicable for welding control on fabrication of Steel Piles for 60m
Steel Wind Tower.
4.0 DEFINITIONS
UT : Ultrasonic Testing
5.0 PROCEDURE
All consumables shall be used within the primary classification limits specified by the
applicable consumable specification and the consumable manufacturer’s
recommendation.
Electrodes shall only be issued for use in portable electrode ovens capable of maintaining
a temperature of 70oC minimum. After use, any remaining electrodes shall be re dried in
accordance with the Manufacturer’s recommendation. Electrodes shall only be re-dried
twice before being discarded.
Welding consumable shall only be used wherein certificates has been approved by
Contractor/Client.
All material shall be inspected in accordance with latest approved Design Drawing and
Shop Drawing, mill certificate and cutting plan to ensure correct material specification,
dimension, cutting profile and piece mark free from any surface defects.
Contractor shall ensure that transferring of heat number, traceability No. of material is
done prior to cutting
Inspection and acceptance by Contractor may be required prior to cutting of any material.
After review the WPS, the test coupon shall be done for PQR, all test
required shall be done in accordance with ASME IX – 2007 requirements.
Project No Unit Doc.Type Mat. Code Serial no Rev
A
LI. Job No LI. Doc. LILAMA 001 Page
69.1/WCP 6 of 7
Welder and Welding performance shall be qualified in accordance with approved WPS
and ASME IX – 2007 requirements.
Base metal preparations may be cut, gouged or profiled by any mechanical or thermal
method. If thermal cutting is used a distance of 3mm from bevel edge shall be dressed
back by grinding or mechanical method
Before welding, a distance of 25mm from the weld edge shall be thoroughly cleaned of
any contaminants (e.g. dirt, oil, grease, NDE materials).
Following thermal cutting later dressing back by grinding.
The method of applying, checking and controlling preheat and inter pass temperatures
shall be stated on the approved WPS
Preheat may be applied by any suitable method. Where fuel gas or oil is used, the gas or
oil shall be sulfur free.
The preheat and inter pass temperature shall be checked by temperature indicating
crayons, thermocouples.
All welding joint shall be identified by a unique number and shall be identified on a weld
map and permanently marked adjacent to the weld joint using a method that is non
injurious to the material.
All welders, welding operators shall be qualified in accordance with code requirements.
All “Tack” welds or bridge welds shall be performed by qualified welders using a
qualified WPS.
Tack weld shall be removed or ground to a profile suitable for fusing into the finishing
weld.
Project No Unit Doc.Type Mat. Code Serial no Rev
A
LI. Job No LI. Doc. LILAMA 001 Page
69.1/WCP 7 of 7
Welders or welding operators shall be re-trained and re-tested when their repair rates
consistently exceed 5% over a period of three weeks.
1. All approved WPS shall be posted at site for welding supervisor and welder’s
reference.
2. Welding consumables to be used for welding shall be checked for the correct
classification, type and size as per approved WPS. Electrode shall be kept in a
heated quiver at all times maintaining temperature shall be at least 70oC.
3. Welder identification and qualification shall be checked and his identification
number shall be written with permanent marker adjacent to the joints.
4. All material or structures to be welded shall be earthed
5. Shelter and windbreaker shall be provided to give protection to the weld areas
from strong wind, rain, when welding at site and when deemed necessary.
Damage or failure on the gas cutting surface: Any damage or failure cannot be
acceptable
Burr or sharp edge: Burr or sharp edge cannot be acceptable.
NDT
All weld shall be completed join penetration groove weld.
Longitudinal and Circumferential Weld: refer to “Test / Inspection Specification”.
6.0 RECORD
All records shall be made and maintained in QC files as per ITP (Inspection/Test
Plan)