0% found this document useful (0 votes)
17 views39 pages

DPR 14 Nov 24

Uploaded by

noidatcs94
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views39 pages

DPR 14 Nov 24

Uploaded by

noidatcs94
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 39

Project Name: TCS NOIDA IT Park Progress as on 14/Nov/24

A Weather
Fog (31°)
B Site Progress :-

#NAME? Activity Target Date Unit of Measurement Scope Achieved till previous day Achieved for the day Cummulative Achieved

1 Piling 2752 2752 2752

2-Dec-2023
A SDB1 5-Feb-2024 NOS 780 780 0 780

26-Dec-2023
B SDB2 10-Feb-2024 NOS 687 687 0 687

C PARKING BLOCK 28/Feb/24 NOS 748 748 0 748

D CAFÉ 28/Feb/24 NOS 260 260 0 260

E UTILITY 10/Mar/24 NOS 277 277 0 277

2 Secant Piles NOS 122 122 0 122

3 Pile Cap NOS 442 442 0 442

A SDB1 NOS 119 119 0 119

B SDB2 NOS 51 51 0 51

C PARKING BLOCK NOS 201 201 0 201

D CAFÉ NOS 71 71 0 71

E UTILITY NOS 95 0 0 0

4 PIT NOS 2752 2553 0 2553

5 Excavation ( incl utility & pile caps) CUM 73912 37425 0 37425

6 GSB CUM 3521 2639.233 0 2639.2

7 PCC CUM 1300 1187.593 0 1187.6

8 Backfilling CUM 275000 76176 120 76296.0

Resources :

1 Manpower-828 nos., Staff :- 275 Nos.


Daily Site Progress Report
A) Labour Report -
Planned Manpower FTM
Work Total
Skilled 358
Unskilled 470
Total 828
B) Plant & Machinery Available
JCB 3 Nos
Dumper 3 Nos
Rig Machine 0 Nos
Tower Crane 6 Nos
Hydra 3 Nos
Road Roller 1 Nos
Bar Cutting Machine 9 Nos
Excavator 1 Nos
Concrete (T.M) 9 Nos
Boom Placer 1 Nos
Concrete Pump 3 Nos
Bar Bending Machine 10 Nos

Activity Target Date

1 Piling

2-Dec-2023
A SDB1
5-Feb-2024

26-Dec-2023
B SDB2
10-Feb-2024

C PARKING BLOCK 28/Feb/24


D CAFÉ 28/Feb/24

E UTILITY 10/Mar/24

2 Secant Piles

3 Pile Cap

A SDB1

B SDB2

C PARKING BLOCK

D CAFÉ

E UTILITY

4 PIT

5 Excavation ( incl utility & pile caps)

6 GSB

7 PCC

8 Backfilling

Resources :

1 Manpower-828 nos., Staff :- 275 Nos.


P&M :
JCB - 3 Nos.
Dumper - 3 Nos
Rig Machine - 0 nos
Tower Crane - 6 nos
Hydra - 3 nos
2 Road roller - 1 nos
Bar cutting machine - 9 nos
Bar bending machine - 10 no
Excavator - 1 nos
Concrete (T.M) - 9 nos
Boom Placer - 1 nos
Concrete Pump -3 nos

Safe Manhours

1 3220958 Till 10th Nov'24


Staff Deployment (TPL)
Staff deployed at site
Weather
Managers / Engineer
Supervisor/ Foreman
Fog (31°)
Operator/Electrician/Plumber etc

Operational
3
3
0
6
3
1
7
1
9
1
3
8

Unit of Measurement Scope Achieved till previous


day

2752 2752

NOS 780 780

NOS 687 687

NOS 748 748


NOS 260 260

NOS 277 277

NOS 122 122

NOS 442 442

NOS 119 119

NOS 51 51

NOS 201 201

NOS 71 71

NOS 95 0

NOS 2752 2553

CUM 73912 37425

CUM 3521 2639.2

CUM 1300 1188

CUM 275000 76176


14-Nov-24

Total
73
108
94

Achieved for the Cummulative % Achieved


day Achieved

0 2752 100%

0 780 100%

0 687 100%

0 748 100%
0 260 100%

0 277 100%

0 122 100%

0 442 100%

0 119 100%

0 51 100%

0 201 100%

0 71 100%

0 0 0%

0 2553 93%

0 37425 51%

0 2639.2 75%

0 1188 91%

120 76296 28%


Hinderences/Delays/Notifications

Date
10/14/2024
10/21/2024
11/1/2024
11/1/2024
11/13/2024
11/14/2024
11/14/2024
Hinderences/Delays/Notifications

Event
GRAP-I Notification issued by CAQM, communicated via email on 15-Oct-24
GRAP-II Notification issued by CAQM, communicated via email on 21-Oct-24
Supply of external soil impacted due to NGT Grap -2 in place and inspections from NGT Authorities
Decrease in Manpower due to Festival
Heavy Fog and AQI > 350
Heavy Fog and AQI > 350
GRAP-III Notification issued by CAQM, communicated via email on 15-Nov-24, Concreting, Backfilling and other works Imp
Date 14-Nov-24

Scope Completed
Building Floor Nos Nos
Café Below Plinth 126.00 121.00
Café GF to 1st Floor 123.00 74.00
Parking 1st Floor to 2nd Floor 227.00 86.00
Parking 2nd Floor to 3rd Floor 226.00 37.00
Parking Below Plinth 249.00 226.00
Parking GF to 1st Floor 247.00 181.00
SDB-02 1st Floor to 2nd Floor 156.00 97.00
SDB-02 2nd Floor to 3rd Floor 158.00 97.00
SDB-02 3rd Floor to 4th Floor 153.00 87.00
SDB-02 4th Floor to 5th Floor 153.00 58.00
SDB-02 Below Plinth 180.00 180.00
SDB-02 GF to UGF 173.00 173.00
SDB-02 UGF to 1st Floor 162.00 148.00
SDB-01 Below Plinth 233.00 233.00
SDB-01 GF to Pod. 1st Floor 108.00 106.00
SDB-01 GF to 201.7 28.00 26.00
SDB-01 GF to Welcome 1st floor 88.00 88.00
SDB-01 Pod. 1st Floor to Pod 2nd Floor 108.00 106.00
SDB-01 201.7 to 205 28.00 21.00
SDB-01 Welcome 1st floor to Welcome 2nd Floor 88.00 75.00
SDB-01 Pod. 2nd Floor to Pod 3rd Floor 107.00 105.00
SDB-01 205 to 208.3 28.00 18.00
SDB-01 Pod. 3rd Floor to SDB1 1st Floor 86.00 84.00
SDB-01 208.3 to SDB1 1st floor 34.00 16.00
SDB-01 1st Floor to 2nd Floor 179.00 53.00
FLOOR- WISE POUR DETAILS AS ON 14-11-2024

Cumm. Target Pours for


Nov’24 Month Cummulative
Completed
Description of Floor Completed
Total number of pours Nos. of Pour in a floor number of Schedule Status
building Description pours as of 14-
pours till d pours Current 11-2024
Oct’24 for Status
Nov’24
Podium First Floor 6 6 0 6 All pours casted
Podium Second Pour 4: Slab casted on 09-11-2024
6 3 3 1 4
Floor Pour 5 & 6: Vertical casting in progress
SDB1 55 Podium Third Floor 3 3 0 3 All pours casted
First Floor 8 2 1 1 3 Pour 1, 2 & 3 slab casted
Second Floor 8 0 3 1 1 Pour 1: Slab casted on 14-11-24
POUR 2 & 4 : Vertical casting in progress
UGF 4 4 0 4 All pours casted
First Floor 6 4 1 4 Pour 5: All verticals casted, slab reinforcement in progress
Pour 6: Vertical reinforcement in progress
Second Floor 6 4 0 4 Pour 1,2,3 & 4 casted
SDB2 82 Third Floor 6 4 0 4 Pour 1,2,3 & 4 casted
Forth Floor 6 2 2 2 Pour 3: Slab reinforcement in progress
Pour 4: Vertical casting in progress
Fifth Floor 6 0 2 0 Pour 1: Slab reinforcement in progress
Pour 2: Slab shuttering in progress
Podium First Floor 12 5 2 5 Pour 5 & 6 :All verticals casted, Slab reinforcement in progress.
Parking 48 Podium Second Pour 3: All verticals casted, slab shuttering in progress
12 3 2 3
Floor Pour 4: Vertical casting in progress
Café 11 First Floor 5 0 1 1 1 Pour 2 : Slab casted on 13-11-2024
Utility 5 - 0 0 0 Raft completed on 27-10-2024
Total 201 40 17 4 44
*17 Pours scheduled subject to mobilisation of manpower and No impact of NGT Ban
Description of
Cummulative Completed
building, Total floors & Floor Description Nos. of Pours
pours as of 14-11-2024
Total pours
SDB1 Podium First Floor 6 6
(8 floors & 55 pours) Podium Second Floor 6 4
Podium Third Floor 3 3
First Floor 8 3
Second Floor 8 1
SDB2 UGF 4 4
(13 floors & 82 pours) First Floor 6 4
Second Floor 6 4
Third Floor 6 4
Forth Floor 6 2
Fifth Floor 6 0
Parking First Floor 12 5
(4 floors & 48 pours) Second Floor 12 3
Café
First Floor 5 1
(3 floors & 11 pours)
Utility
- 0 0
(2 floors & 5 pours)
Total
44
(201 pours)

Slab Casting Details


Sn. Area Level Pour Casting Date

1 SDB1 Podium 1st Floor Pour 1 08/06/2024


2 SDB1 Podium 1st Floor Pour 2 7/19/2024
3 SDB1 Podium 1st Floor Pour 3 7/27/2024
4 SDB1 Podium 2nd Floor Pour 1 06/08/2024
5 SDB1 Podium 2nd Floor Pour 2 27/08/2024
6 SDB1 Podium 2nd Floor Pour 3 30/08/2024
7 SDB1 Podium 3rd Floor Pour 1 09/09/2024
8 SDB1 Podium 3rd Floor Pour 2 27/09/2024
9 SDB1 Podium 3rd Floor Pour 3 30/09/2024
10 SDB1 Welcome Block 1st Floor Pour 4 20/09/2024
11 SDB1 Welcome Block 1st Floor Pour 5 08/10/2024
12 SDB1 Welcome Block 1st Floor Pour 6 22/10/2024
13 SDB1 Welcome Block 2nd Floor Pour 4 09/11/2024
14 SDB1 Ist Floor Pour 1 12/10/2024
15 SDB1 Ist Floor Pour 2 29/10/2024
16 SDB1 Ist Floor Pour 3 02/11/2024
17 SDB1 2nd Floor Pour 1 14/11/2024

1 SDB2 UGF Pour 1 5/24/2024


2 SDB2 UGF Pour 2 6/15/2024
3 SDB2 UGF Pour 3 7/9/2024
4 SDB2 UGF Pour 6 9/24/2024
5 SDB2 1st Floor Pour 1 7/16/2024
6 SDB2 1st Floor Pour 2 7/31/2024
7 SDB2 1st Floor Pour 3 8/17/2024
8 SDB2 1st Floor Pour 4 8/31/2024
9 SDB2 2nd Floor Pour 1 8/24/2024
10 SDB2 2nd Floor Pour 2 9/5/2024
11 SDB2 2nd Floor Pour 3 9/15/2024
12 SDB2 2nd Floor Pour 4 9/28/2024
13 SDB2 3rd Floor Pour 1 9/26/2024
14 SDB2 3rd Floor Pour 2 10/4/2024
15 SDB2 3rd Floor Pour 3 10/15/2024
16 SDB2 3rd Floor Pour 4 10/28/2024
17 SDB2 4th Floor Pour 1 10/21/2024
18 SDB2 4th Floor Pour 2 10/28/2024

1 Parking Block Podium 1st Floor Pour 1 8/3/2024


2 Parking Block Podium 1st Floor Pour 2 9/4/2024
3 Parking Block Podium 1st Floor Pour 3 10/14/2024
4 Parking Block Podium 1st Floor Pour 12 9/4/2024
5 Parking Block Podium 1st Floor Pour 4 10/27/2024
5 Parking Block Podium 2nd Floor Pour 1 9/23/2024
6 Parking Block Podium 2nd Floor Pour 2 10/19/2024
7 Parking Block Podium 2nd Floor Pour 12 10/19/2024

1 Café 1st Floor Pour 2 11/13/2024


Approved
Description of Delivered Quantity
Rate Validity Quantity by
Materials till 15-11-2024
CFT Team

Cement 12/31/2024 57,324 34,511


Steel (8mm) 9/30/2024 3121.7 2745
Steel (10mm) 9/30/2024 1043.37 1053
Steel (12mm) 9/30/2024 973.9 968
Steel (16mm) 9/30/2024 3609 3595
Steel (20mm) 9/30/2024 2407.6 2029
Steel (25mm) 9/30/2024 1949.97 1820
Steel (32mm) 9/30/2024 1897.48 1817
Total Steel 15003.02 14027
PT 9/30/2024 580 576

* For Delivered Stock Quantity, Please refer the BPV Tracker


Requirement of
Available Stock
Materials for
as on 14-11-
the Month of
2024
Nov'24

520 3400
700.985
177.299
301.776
520.903 915
562.673
411.182
522.2
3197.0 915
259 86
Bulk Material Status
S. No. Material UOM Balance Stock
1 Cement Mt 520
2 Flyash Mt 46
3 Admixture Mt 14.05
4 Sand Mt 3000
5 10mm Aggregate Mt 2500
6 20mm Aggregate Mt 3500
7 Stagging Material MT 4400
8 Plywood Nos 20698
9 H-Beam Rmt 142775
10 Timber 2''*3"*8' Cft 27410

S. No. Concrete Grade Cumm. Till 31-Oct-24 Nov Till date


1 M7.5 53.5 0
2 M10 1150.5 5
3 M15 1169.093 18.5
4 M25 598 0
5 M30 for piles 39136.15 0
6 M30 10554.937 534.5
7 M40 19854.45 1511.75
8 M45 3820.53 23
9 M50 82 233.5
10 M60 1702.89 83
Total 78122.05 2409.25
Remarks

Updated as of
15th Nov'24

Total 11/1/2024 11/2/2024 11/3/2024 11/4/2024 11/5/2024


54 0 0 0 0
1156 0.0 0.0 0 0
1188 0.0 0.0 0 0
598 0.0 0.0 0 0
39136 0.0 0.0 0 0
11089 42.0 0.0 0 0
21366 35.8 464.8 25.5 64
3844 0.0 14.0 0 0
316 50.0 0.0 51 11.5
1786 0.0 4.5 2 5.5
80531.30 127.75 483.25 78.5 81
Concrete Production
11/6/2024 11/7/2024 11/8/2024 11/9/2024 11/10/2024 11/11/2024
0 0 0 0 0
0 0 0 0 0
12 0 0 0 6.5
0 0 0 0 0
0 0 0 0 0
0 41 0 451.5 0
23 61.25 23.5 0 52.5
0 0 9 0 0
17 46 0 0 36
0 4 16.5 32 6.5
52 152.25 49 483.5 101.5
Concrete Production
11/12/2024 11/13/2024 11/14/2024 11/15/2024 11/16/2024 11/17/2024 11/18/2024
0 0 0
5 0 0
0 0 0
0 0 0
0 0 0
0 0 0
27.25 314.25 420
0 0 0
22 0 0
12 0 0
66.25 314.25 420 0 0 0 0
11/19/2024 11/20/2024 11/21/2024 11/22/2024 11/23/2024 11/24/2024 11/25/2024

0 0 0 0 0 0 0
11/26/2024 11/27/2024 11/28/2024 11/29/2024 11/30/2024

0 0 0 0 0
S.no. 11/1/2024 11/2/2024 11/3/2024 11/4/2024
1 Carpenter+Helper 195 238 263
2 Fitter +Helper 162 224 239
3 Mason +Helper 34 33 48
DAY 4 Welder+Helper 5 12 17
5 Rigger & Khalasi 116 152 182
6 Supervisor/Skilled 42 54 66
7 Unskilled 13 35 18
8 PT Vendor 26 31 31
Total 593 779 0 864

S.no. 11/1/2024 11/2/2024 11/3/2024 11/4/2024


1 Carpenter+Helper 0 0 10
2 Fitter +Helper 0 0 0
NIGHT 3 Mason +Helper 4 2 37
4 Welder+Helper 0 0 0
5 Rigger & Khalasi 0 4 1
6 Supervisor/Skilled 1 0 2
7 Unskilled 1 5 1
8 PT Vendor 8 7 9
Total 14 18 0 60

Daily Manpower Report-Day 15-11-2024

PARKING UTILITY &


S.no. SDB-1 SDB-2
BLOCK cafeteria

1 Carpenter+Helper 132 99 30 3
2 Fitter +Helper 57 44 24 20
3 Mason +Helper 34 30 22 1
DAY
4 Welder+Helper 5 2 1 0
5 Rigger & Khalasi 49 53 19 2
6 Supervisor/Skilled 28 21 10 1
7 Unskilled 0 0 0 24
8 PT Vendor 0 18 4 3
Total 305 267 110 54

Daily Manpower Report-Night 15-11-2024

PARKING UTILITY &


S.no. SDB-1 SDB-2
BLOCK cafeteria

NIGHT
1 Carpenter+Helper 0 0 0 0
2 Fitter +Helper 0 0 0 0
3 Mason +Helper 0 6 0 0
NIGHT
4 Welder+Helper 0 0 0 0
5 Rigger & Khalasi 0 0 0 0
6 Supervisor/Skilled 0 1 0 1
7 Unskilled 0 0 0 4
8 PT Vendor 4 0 0 0
Total 4 7 0 5

TCS NOIDA:
Week-wise
Average Week 3(Oct Week 4 (Oct
Manpower 2024) 2024)
count
Day 1258 1203
Night 115 83
Total in Nos 1373 1285
11/5/2024 11/6/2024 11/7/2024 11/8/2024 11/9/2024 11/10/2024
228 242 243 251 247
200 227 215 176 185
42 73 76 78 85
8 8 9 11 10
177 178 162 166 156
54 60 57 58 60
18 24 31 29 32
34 38 37 36 35
761 850 830 805 810 0

11/5/2024 11/6/2024 11/7/2024 11/8/2024 11/9/2024 11/10/2024


0 2 2 0 0
0 0 0 0 0
16 21 14 17 16
0 0 0 0 0
17 6 5 3 6
1 2 1 0 3
5 1 1 5 10
8 9 9 10 10
47 41 32 35 45 0

ay 15-11-2024
Infra
Labour Camp Works+Transit Other Total
Hub
0 0 4 268 268
0 6 0 151 151
1 1 4 93 102
0 0 0 8 8
0 0 7 130 130
0 3 5 68 70
0 8 22 54 64
0 0 4 29 35
1 18 46
Total 801

ght 15-11-2024
Infra
Labour Camp Works+Transit Other Total
Hub
0 0 0 0
0 0 0 0
0 0 3 9
0 0 0 0
0 0 0 0
0 0 0 2
0 0 6 10
0 0 2 6
0 0 11
Total 27

Grand Total 828

TCS NOIDA:WEEK WISE WORKMEN REPORT

Week 5 (Oct Week 1 (Nov Week 2 (Nov Week 3(Nov Week 4 (Nov Week 5 (Nov
2024) 2024) 2024) 2024) 2024) 2024)

980 686 820 790


57 16 43 42
1037 702 863 832 0 0
Daily Manpower Report -Day
11/11/2024 11/12/2024 11/13/2024 11/14/2024 11/15/2024 11/16/2024
207 224 211 233
164 190 181 214
82 77 96 91
8 8 8 8
188 143 167 129
55 57 63 70
32 32 33 48
32 33 27 29
768 764 786 822 0 0

Daily Manpower Report -Night


11/11/2024 11/12/2024 11/13/2024 11/14/2024 11/15/2024 11/16/2024
0 0 0 0
0 0 0 0
21 30 13 12
0 0 0 0
10 6 6 4
1 2 2 1
2 1 17 14
10 10 11 9
44 49 49 40 0 0
11/17/2024 11/18/2024 11/19/2024 11/20/2024 11/21/2024 11/22/2024

0 0 0 0 0 0

11/17/2024 11/18/2024 11/19/2024 11/20/2024 11/21/2024 11/22/2024

0 0 0 0 0 0
11/23/2024 11/24/2024 11/25/2024 11/26/2024 11/27/2024 11/28/2024 11/29/2024

0 0 0 0 0 0 0

11/23/2024 11/24/2024 11/25/2024 11/26/2024 11/27/2024 11/28/2024 11/29/2024

0 0 0 0 0 0 0
11/30/2024

11/30/2024

0
Soil Dumping Trips

S.no Date Day

Till 12-Mar-23
From 04-Dec-24 to 10-Aug-24

67 10/4/2024 8
68 10/5/2024 13
69 10/6/2024 5
70 10/8/2024 6
71 10/9/2024 13
72 10/10/2024 7
73 10/11/2024 8
74 10/19/2024 19
75 10/20/2024 11
76 10/21/2024 19
77 10/22/2024 10
78 10/23/2024 30
79 10/24/2024 30
80 10/26/2024 26
81 10/27/2024 32
82 10/28/2024 13
83 10/30/2024 2
84 11/8/2024 32
85 11/9/2024 3
86 11/10/2024 22
87 11/11/2024 4
88 11/12/2024 2
89 11/13/2024 6
90 11/14/2024 0

*Supply of external soil impact

S. No Building Plan for Nov'24 in Cum

1 SDB-01 3381
2 SDB-02 4016
3 Parking 2500
4 Café -
External Roads/Transit
5 5131
Hub
Total 15028
Dumping Trips Trips Dumped Pe

Night Total Cum Area of dumping SDB-1 SDB2

915 Infra Works


5173

0 8 Road/Café
0 13 Road/Parking
0 5 Road
0 6 SDB-2
0 13 156 Café/SDB-2
0 7 84 Café/Parking
0 8 96 Road/SDB-1
19 38 456 SDB-1/SDB-2/Parking
0 11 132 SDB-1/SDB-2
0 19 228 SDB-1/SDB-2
0 10 120 SDB-1/Café
26 56 672 SDB-1/SDB-2/Café
0 30 360 SDB-1/SDB-2
0 26 312 SDB-1/SDB-2/Parking
20 52 624 SDB-1/SDB-2/Road/Parking
0 13 156 SDB-1/Parking
0 2 24 Parking
0 32 384 SDB-1/SDB-2/Parking 10 8
0 3 36 SDB-1 3
24 46 552 SDB-1/SDB-2/Parking/Road 10 8
5 9 108 SDB-1/SDB-2/Parking 4 2
0 2 24 Parking
0 6 72 SDB-1/SDB-2 4 2
10 10 120 SDB-2 10 0

Total 6497

*Supply of external soil impacted due to NGT Grap -3 in place

Achieved in
Nov’24 in
cum
492
240
408
-
156
1296
Trips Dumped Per Building

Road/External
Parking Café
Development/Transit Hub

14

15 13
3
2

0
Overall Site Progress
SDB-1-2nd Floor P-1 slab casted

SDB-2 - Pour 5 reinforcement in progress

Parking - Pour 6 Reinforcement in progress


Café - Slab 1st Floor Pour-2

Utility- Lower Portion pile chipping in progress

You might also like