002 QA& QC Procedure
002 QA& QC Procedure
REV
W153-8543-OK-QA/QC-002 0
PT. ADHI KARYA (Persero)
Tbk
DATE 20-11-09 SHEET 1 OF 10
QA/QC PROCEDURE
Bona Sitompul
1. GENERAL......................................................................................................……........ 3
1.1. Scope........................................................................................................................ 3
1.2. Reference.................................................................................................................. 3
1.3. Terminology.............................................................................................................. 3
1.4. Conflicting Requirements …………………………………………………………….…. 4
2. QUALITY ASSURANCE.............................................................................................. 5
2.1. Quality Assurance Requirements .............................................................................. 5
2.2. Quality Records......................................................................................................... 5
2.3. Internal Quality Audit............................................................................................... 5
2.4.Training..............................................................................................................…... 6
3. QUALITY CONTROL..........................................................................................….... 6
3.1. Quality Control Requirements................................................................................... 6
6. ATTACHMENT............................................................................................................. 10
1.1. Scope
1.2.Reference
ASME :
American Society of Mechanical Engineering
API :
American Petroleum Institute
AWS :
American Welding Society
ASTM :
American Society for Testing and Materials
ISA :Instrument Society of America
NEC :
National Electric Code
AASHTO :
American Association State Highway and Transportation
officials
Related CPI Specification
1.2. Terminology
In this specification, the following words and terms shall have the meanings hereby
assigned to them, unless noted otherwise.
1.2.1. Company
1.3.2. Contractor
1.3.3. Vendor
1.3.4. Migas
1.3.6. Inspector
1.3.1. In case of conflict between this Specification and its associated Specifications and
the above Codes and Standards, the Vendor shall bring the matter to the
company’s attention for resolution and approval in writing. However, the most
stringent requirement shall apply.
1.3.2. Should conflicts exist between this specification and other documents, the
following order of precedence shall govern:
Scope of Work
Data Sheets.
This Specification
Other company Specifications
2. QUALITY ASSURANCE
2.1.3. Contractor/Vendor shall develop and implement the project quality assurance
plan. COMPANY will monitor and audit all aspects of quality assurance to
ensure that the project quality assurance plan is being correctly used and
effectively implemented.
2.1.4. Contractor’s/Vendor’s project quality assurance plan shall include about all
phases of a project activity from establishing functional capability to operation of
the facilities.
2.1.5. Contractor shall responsible for the quality of Vendor’s/Subcontractors works and
materials in accordance with company specification (Contract) and statutory
requirements.
2.2.2. The system shall be able to ensure all quality records are legible, identifiable,
stored, maintained, and retrievable.
2.3.1. Contractor shall carry out planned audits to ensure the adequacy of the quality
assurance, quality control, inspection, and testing activities in order to ensure
2.3.2. The audit results shall be documented and company reserves the right to be
represented during these audits and have access to all pertinent documents.
2.3.3. Company shall have the right to conduct periodic audits on contractor pertaining
to QA/QC activities related to the Works. Company shall notify contractor two
weeks in advance prior to the audits.
2.3.4. All irregularities or non-conformances revealed by the audit and during on going
QA/QC review shall be corrected by contractor in a timely manner so that the
contractual completion can be fulfilled.
2.4. Training
2.4.1. Contractor shall describe the system for identifying the training needs and
provision of training to all personnel involved in the Work.
2.4.2. The system shall be able to provide guidelines to all personnel to perform specific
assignments that conform to the Contract requirements. Detail explanations of the
project quality assurance plan will be described on the PP-QCGG- 001 Project
Quality Assurance Plan.
3. QUALITY CONTROL
3.1.2. Contractor has policy to assign some personnel to perform the quality control of
the whole of project. Organization chart of quality control is shown in.
Attachment-1 of this procedure.
3.1.4. Company (or his Inspector) and contractor shall have the right to witness/review
Vendor and/or Subcontractor’s quality control, testing, inspection and review
3.1.5. Company and contractor shall sign the inspection sheet upon completion of
successful inspection/testing activities.
3.1.6. MIGAS inspection attendance and review/approval shall include in the items that
already stated in the inspection and test plan document. MIGAS attendance under
responsible of contractor’s Third Party or Vendor’s Third Party.
4.1. Policy
The following items are the project policy about Quality Control personnel assignment
activities as required by Contract, or Scope of Work:
4.1.1. Quality Control Manager under the direction of the Project Manager is
responsible for all quality control work.
4.1.2. Each discipline engineer under the supervision of Engineering Manager shall be
responsible for quality control of his discipline works through close monitoring of
the Vendor/ Subcontractors work. Responsible for inspection activities of his
discipline when requested by QC Manager.
4.2. Organization
Quality Control Manager shall give reports to the Project Manager about his/her
responsibilities for supervision of all quality control activities and coordinates
project quality assurance / quality control efforts to ensure the intended results.
He/She has right to attend the pre inspection meeting, inspection meeting and
inspection of testing and holding the inspection activity in coordination with the
Project Manager and company’s Quality Control Coordination, and/or MIGAS/
Discipline Inspector has responsibility to report the result of each attend the
testing and inspection of their each discipline to the Quality Control Engineer.
The Discipline Inspector has right to inspect at any time according their
determined schedule and can give notification that the work is release or rejected.
Inspection and testing items, level definitions and co-ordinations are shown in the
documents: PPQC-GG-003 Inspection and Test Plan at Shop and PP-QC-GG-004 Inspection
and Test Plan at Field.
Contractor / Vendor shall perform this meeting for any major equipment, before
start fabrication. The detail explanation of this meeting will describe in PP-QC-
GG-008 Fabrication Quality Control Plan.
5.3.2. Upon completion of all inspection/test, contractor shall submit to company a copy
of the original set (quantity of copies as per the contract). These records will form
part of the mechanical completion turnover packages.
5.4.1. Contractor shall describe the method used to ensure the measurement equipment
for examination, test and inspection are properly controlled, calibrated, and
maintained. All information about the inspection equipment including the
periodic calibration for accuracy and any adjustment shall be documented.
5.4.2. Contractor shall ensure the effective monitoring of the accuracy of the inspection
equipment with respect to the specified requirements and standards.
6. ATTACHMENT