408 GT 2020
408 GT 2020
NEW DELHI
Coram:
Shri P.K. Pujari, Chairperson
Shri I.S. Jha, Member
Shri Arun Goyal, Member
In the matter of
Petition for truing-up of tariff for the 2014-19 Tariff Period and for determination of
tariff for the 2019-24 Tariff Period in respect of Maithon Right Bank Thermal Power
Project (1050 MW) of Maithon Power Limited.
And
In the matter of
ORDER
The Petitioner, Maithon Power Ltd (in short ‘MPL’) is a public limited company
incorporated on 26.7.2000 under the provisions of the Companies Act, 1956. MPL is
a joint venture between Tata Power Trading Company Ltd. (TPTCL) with an equity
participation of the remaining 26%. Maithon Right Bank Power Project (1050 MW)
Project in terms of the Ministry of Finance, Govt. of India Notification No. 63/99 dated
commercial operation (COD) of Unit-I of the generating station is 1.9.2011 and the
Background
2. Petition No. 274/2010 was filed by the Petitioner for determination of tariff of
the generating station from COD of Unit-I (1.9.2011) and Unit-II (24.7.2012) till
31.3.2014 and the Commission vide its order dated 19.11.2014 determined the tariff
for the said period, based on the capital cost of Rs.244839 lakh (as on 1.9.2011) and
Rs.137002 lakh (as on 24.7.2012). Against this order dated 19.11.2014, the
Petitioner filed Appeal No. 48/2015 before the Appellate Tribunal for Electricity
(APTEL) and the same was disposed of by judgment dated 10.5.2016. Against this
judgment, the Petitioner filed Review Petition (RP No. 16/2016) before APTEL and
by order dated 10.10.2017, the APTEL upheld its judgment dated 10.5.2016 in
152/GT/2015 was filed by the Petitioner for truing-up of tariff for the 2009-14 tariff
period and for determination of tariff of the generating station for the 2014-19 tariff
period. Meanwhile, Petition No. 72/MP/2016 was also filed by the Petitioner seeking
Environment, Forest and Climate Change (in short ‘MOEF & CC’) dated 7.12.2015
and the Commission vide its order dated 20.3.2017 in Petition No. 72/MP/2016
“10. Since, the 2014 Tariff Regulations do not provide for the grant of in-principle
approval for the capital expenditure, the prayer of the petitioner for in-principle approval
of the Abstract scheme of capital expenditure by relaxing the provisions of the tariff
regulations through invoking Regulation 54 of 2014 Tariff Regulations, is not
maintainable. In our view, since, the implementation of new norms in the existing and
under construction thermal generating stations would require modification of their
existing system and installation of new systems such as Retro-fitting of additional fields
in ESP/replacement of ESP, etc. to meet Suspended Particulate Matter norms,
installation of FGD system to control SOx and Selective Catalytic Reduction (SCR)
systems for DeNox, the petitioner is directed to approach the Central Electricity
Authority to decide specific optimum technology, associated cost and major issues to
be faced in installation of different system like SCR, etc. The petitioner is also directed
to take up the matter with the Ministry of Environment and Forest for phasing of the
implementation of the different environmental measures. Accordingly, the petitioner is
granted liberty to file appropriate petition at an appropriate stage based on approval of
CEA and direction of MoEF which shall be dealt with in accordance with law.”
No.152/GT/2015, trued up the tariff of the generating station for the 2009-14 tariff
period and determined tariff for the 2014-19 tariff period. In the said order, an
amount of Rs.160 crore towards Liquidated Damages (LD) was deducted from the
capital cost, till such time the Petitioner furnished details of LD settlement. Against
this order, the Petitioner filed Review Petition (Petition No.16/RP/2018) on the
following issues:
“a) Disallowance of 1% of additional interest rate for computing the Interest During
Construction and Interest on Loan for the period 2011-14 to recover fully the
interest cost with actual weighted average;
4. Thereafter, the Commission vide its order dated 25.4.2019, disposed of the
review petition (Petition No.16/RP/2018) rejecting the prayer (a) above, while
allowing the other prayers (b) to (e) above. However, while allowing prayers (b) and
(d), the Commission in the said order dated 25.4.2019 observed that these issues
would be considered at the time of truing-up of tariff for the 2014-19 tariff period.
Petitioner has filed appeal (Appeal No. 405/2019) before APTEL and the same is
pending.
5. The Petitioner had also filed Petition No. 285/MP/2018 for inclusion of LD
amount of Rs.160 crore deducted from the capital cost (in terms of Commission’s
order dated 26.12.2017 in Petition No. 152/GT/2015) and for re-computation of tariff
for the tariff periods 2009-14 and 2014-19 and the Commission by order dated
“22. In view of the above, the total expected LD amount of `160 crore which was
deducted from the capital cost vide Commission’s order dated 26.12.2017 in Petition
No. 152/GT/2015 is allowed to be included in the capital cost of the generating station.
Consequently, the impact due to inclusion of the said LD amount in the capital cost
shall be worked out and tariff of the generating station for the period 2011-14 and
2014-19 shall be revised by a separate order in Petition No. 152/GT/2015. We decide
accordingly”
Petition No.152/GT/2015, revised the annual fixed charges of the generating station
7. Thereafter, the Petitioner, based on the response of CEA and MOEF&CC and
in terms of the liberty granted by the order dated 20.3.2017 in Petition No.
amongst others, a declaration that the MOEF&CC Notification dated 7.12.2015 and
its letter dated 11.12.2017 are ‘change in law’ events and also for the grant of ‘in-
principle’ approval of the expenditure towards installation of FGD system for meeting
the revised emission norms of SO2. By order dated 11.11.2019, the Commission
“16……..Considering the fact that the expenditure shall be incurred during next tariff
period commencing from 1.4.2019, prayer of the petitioner is to be dealt under the
provisions of 2019, Tariff Regulations pertaining to additional capital expenditure. As per
29. In view of the above, the Commission accords In-principle approval to the petitioner
for following cost:
xxx
The Commission allows the petitioner to claim IDC, IEDC, Taxes and opportunity cost at
actuals which may be allowed after prudence check in accordance with the 2019, Tariff
Regulations.
30. Accordingly, prayer (c) and (d) of the petitioner are disposed in terms of above
35. The norms for additional O&M expenses would be finalized by CERC. Accordingly,
the claim of the petitioner for allowing O&M expenditure is not being considered at this
stage. We direct the petitioner to submit the O&M expenses relating to FGD system on
actual basis at the time of filling the petition for determination of tariff on commissioning
of the FGD system.
38. As regards the exclusion of the shutdown period for calculation of availability for
recovery of fixed charges, Commission has already taken a view that the generator in
consultation with beneficiaries would plan to synchronize the interconnection of FGD
with the annual overhaul so as to minimize the additional downtime required for FGD
interconnection. Accordingly, Petitioner is directed to schedule the shutdown period
prudently to avoid the impact on availability. However, if shutdown period for FGD
integration exceeds the period of annual overhauling, the petitioner has liberty to claim
the same at the time of tariff determination. Accordingly, prayer (e) and (f) of the
petitioner is disposed in terms of above.
xxx
40. As per Clause (2) of the Regulation 14 of the 2019 Tariff Regulations, the
Commission has already specified the regulatory framework for determination of
supplementary tariff inter-alia provides supplementary capacity charges and
supplementary energy charges. This regulation is effective for 2019-24 tariff period. The
Commission will determine this supplementary tariff on submission of application by the
petitioner after installation of FGD. As such, state/beneficiaries may decide merit order
dispatch while scheduling the plants. Accordingly, prayer (g) of the petitioner is
disposed in terms of above.
41…………..Further, in Petition no. 92/MP/2015 dated 08.03.2019, the Commission has
clarified as under:
“xxxxx
In view of the above, the Petitioner may seek appropriate remedy in case the
Petitioner relinquishes LTA due to additional APC. Accordingly, prayer (h) of the
petitioner is disposed in terms of above.”
allowed vide order dated 1.10.2019 in Petition No. 152/GT/2015. In this regard, the
capital cost was considered as opening capital cost as on 1.4.2014 for determination
of tariff for the 2014-19 tariff period), approved vide order dated 1.10.2019 in Petition
2012-13 and 2013-14, which the Petitioner had failed to furnish at the time of truing
up of tariff for the 2009-14 tariff period. Since the Petitioner, in the present petition,
has submitted that there is de-capitalization of Rs.450.81 lakh for 2012-13 and 2013-
14, the opening capital cost for the 2014-19 period stands revised to Rs.432039.88
1.10.2019 in Petition No. 152/GT/2015. Here, we would like to point out that even
though tariff for the 2009-14 tariff period has been trued up earlier for the generating
station, the downward revision (on account of decapitalization of Rs. 450.81 lakh) in
the capital cost is allowed, keeping in view the interest of consumers and tariff is
modified accordingly.
2013-14 has been allowed and based on the downward revision in capital cost, the
(Rs. in lakh)
1.9.2011 to 1.4.2012 to 24.7.2012 to 2013-14
31.3.2012 23.7.2012 31.3.2013
Total annual fixed charges 33660.10 18522.83 68213.37 108896.58
allowed in order dated
1.10.2019
Total annual fixed charges 33660.10 18522.83 68199.83 108896.58
allowed in this order
11. The difference between the annual fixed charges recovered by the Petitioner
in terms of the order dated 26.12.2017 read with order dated 1.10.2019 in Petition
No.152/GT/2015 and the annual fixed charges determined by this order shall be
12. The present petition has been filed by the Petitioner for truing-up of tariff of
the generating station for the 2014-19 tariff period, in terms of Regulation 8 of the
2014 Tariff Regulations and for determination of tariff of the generating station for the
2019-24 tariff period, in accordance with the provisions of the 2019 Tariff
13. The capital cost allowed vide order dated 1.10.2019 in Petition No.
15. The Respondent No.3, Kerala State Electricity Board Limited (KSEBL) has
filed its reply vide affidavit dated 17.6.2020 and the Petitioner has filed its rejoinder to
the Commission vide Record of the Proceedings (ROP) directed the Petitioner to
submit certain additional information and reserved its order. In response, the
Petitioner vide affidavit dated 3.7.2020 has filed the additional information and has
served copies of the same on the Respondents. Taking into consideration the
submissions of the parties and the documents available on record, we examine the
claims of the Petitioner for the 2014-19 tariff period, on prudence check, as stated in
Capital Cost
“9 (3) The Capital cost of an existing project shall include the following:
(a) the capital cost admitted by the Commission prior to 1.4.2014 duly trued up by
excluding liability, if any, as on 1.4.2014;
(b) additional capitalization and de-capitalization for the respective year of tariff as
determined in accordance with Regulation 14; and
(c) expenditure on account of renovation and modernization as admitted by this
Commission in accordance with Regulation 15.”
17. We have, in paragraph 9 of this order, allowed the revision of the capital cost
Accordingly, in terms of Regulation 9(3)(a) of the 2014 Tariff Regulations, the closing
18. Regulations 14(1) and 14(3) of the 2014 Tariff Regulations provide as under:
19. The projected additional capital expenditure allowed vide order dated
(Rs.in lakh)
Sl. Package Name 2014-15 2015-16 2016-17 2017-18 2018-19
No
1 BTG Package- Station (-) 416.00 0.00 0.00 0.00 0.00
2 Cost of Land & Site 19505.00 0.00 0.00 0.00 0.00
3 General Civil Works (GCW) 9793.00 0.00 0.00 0.00 0.00
4 Plant Water System (PWS) 214.00 0.00 0.00 0.00 0.00
5 Ash Handling System (AHS) (-) 413.00 716.00 0.00 0.00 0.00
6 Coal Handling System (-) 502.00 0.00 0.00 0.00 0.00
7 Reverse Osmosis (RO)System 0.00 8400.00 0.00 0.00 0.00
8 BOP Electrical 45.00 0.00 0.00 0.00 0.00
9 Township & Colony 57.00 0.00 0.00 0.00 0.00
Design, Engineering & 787.00 0.00 0.00 0.00 0.00
10
Project Management
11 Pre-Operative Expenses 1836.00 0.00 0.00 0.00 0.00
12 IT System for Software 414.00 0.00 0.00 0.00 0.00
13 Interest During Construction 145.00 - 0.00 0.00 0.00
Total (on net basis) including 31465.00 9116.00 0.00 0.00 0.00
de-capitalization
14 Cash expenses towards land (-) 5507.00 0.00 0.00 0.00 0.00
Total additional capital 25958.00 9116.00 0.00 0.00 0.00
expenditure (projected)
152/GT/2015 to furnish the calculation of IDC along with basis of IDC allocation
towards additional capital expenditure and the reconciliation of the same with books
of accounts.
21. The Petitioner in Form 9Bi and Form-9C of the petition, has furnished the
under:
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Additional capitalization as per 34679.91 14992.72 1087.48 2267.78 4390.74
books (a)
Less: Exclusions (items not 0.00 0.00 58.34 53.53 10.44
allowable / not claimed)
Additional capitalization claimed 34679.91 14992.72 1029.14 2214.25 4380.30
De-capitalization as per books of 3214.56 131.14 69.61 132.63 81.37
accounts
2014-15
22. The additional capitalisation of Rs.31465.35 lakh (after adjustment of the de-
(Rs in lakh)
Head of Work/Equipment Projected additional Additional
capitalization allowed capital
vide Commission’s order expenditure
dated 26.12.2017 in claimed in
Petition No.152/GT/2015 this petition
Ash Handling System (AHS) (-) 413.00 48.65
BOP 45.00 18.21
BTG Package – Station (-) 416.00 730.69
Coal Handling System (CHS) (-)502.00 1042.53
Cost of Land & Site 19505.00 21142.23
General Civil Works 9793.00 10577.92
IT System for Software 414.00 457.52
Plant Water System 214.00 252.36
Pre-Operative expenses 1836.00 207.87
Design, Engineering & Project Management 787.00 0.00
Township & Colony 57.00 57.12
24. The Petitioner has submitted that the actual additional capital expenditure
incurred for 2014-15 is in respect of assets which form part of the original scope of
work of the project and is up to the cut-off date of the generating station. COD of the
generating station is 24.7.2012 and, accordingly, the cut-off date of the generating
station, in terms of the 2009 Tariff Regulations is 31.3.2015. It is observed that the
claim of the Petitioner for net additional capital expenditure of Rs.31465.35 lakh in
assets which form part of the original scope of work of the project and is up to the
cut-off date, the net additional capital expenditure of Rs.31464.35 lakh (Rs.34679.91
Tariff Regulations.
2015-19
capital expenditure in respect of certain assets/ works, which form part of the original
scope of work of the project, namely, Railway System, Township & Colony, General
Coal Handling System, BOP Electrical, BTG Package, Design Engineering and
period 2015-18 with a prayer for extension of cut-off date of the generating station till
31.3.2019, due to the delay in execution of these works. Though the prayer of the
Petitioner for extension of cut-off date of the generating station till 31.3.2019 was
rejected by order dated 26.12.2017, the Commission had allowed the projected
additional capitalization in 2015-16 only towards works namely, RO system and Ash
the time of truing-up of tariff of the generating station. However, in respect of other
assets/ works like Railway System, Township & Colony, General Civil Works and
Ash Conveying Pipeline, the projected additional capitalization for the period 2015-
18 was disallowed, but liberty was granted to the Petitioner to approach the
and in accordance with the provisions of the applicable Tariff Regulations. The
“91..In view of this submission and considering the fact that capitalization of projected
additional expenditure of these assets/ expenditure before 31.3.2019 is uncertain, the
consideration of the prayer of the petitioner for extension of cut-off date of the generating
station till 31.3.2019 would not serve any useful purpose. In this background, the prayer of
the petitioner for projected capitalization of the expenditure is not allowed. However, the
petitioner is granted liberty to approach the Commission for additional capitalization based
on the actual expenditure incurred for these assets and the same will be considered after
due diligence and prudence as per the regulation in vogue at that time. In view of this, the
projected additional capitalization claimed in respect of Railways System (`31100.00 lakh in
2016-17 and `9400.00 lakh in 2017-18), Township & Colony (`2000.00 lakh in 2015-16,
`3000.00 lakh in 2016-17 and `1442.00 lakh in 2017-18) and General Civil Works
for`6255.00 lakh in 2015-16 has not been allowed at this stage.”
“95…In view of this Submission and considering the fact that the capitalization of projected
additional expenditure of the asset/ expenditure before 31.3.2019 is uncertain, the
consideration of the prayer of the petitioner for extension of cut-off date of the generating
station till 31.3.2019 would not serve any useful purpose. In this background, the prayer of
the petitioner for projected capitalization of the expenditure is not allowed. However, the
26. Also, the Petitioner, in the Petition No.152/GT/2015, had claimed projected
which were not part of the original scope of work of project, namely, Building and
Civil Engineering works, Transformer and Sub-station equipment, Plant & Machinery,
such claims in its order dated 26.12.2017, granted liberty to the Petitioner to
approach the Commission at the time of truing-up of tariff with detailed justification,
including the provisions of the relevant regulations under which the said expenditure
“110. It is observed that petitioner has not filed any details regarding the break-up of the
“Plant and Machinery‟ Building & Civil works‟ and “Other un-classified assets‟ along with
justification and the relevant provisions of the regulations under which each asset/work has
been claimed for 2014-19. In this background, we are not inclined to allow the projected
additional capital expenditure in respect of items/assets which are not in the original scope
of work as shown in the above table. However, the petitioner is granted liberty to approach
the Commission at the time of truing-up of tariff along with the detailed justification and the
provisions of relevant regulations under which the expenditure has been claimed”.
in the present petition, for the period 2015-19, are summarized below:
(Rs. in lakh)
Assets/Works 2015-16 2016-17 2017-18 2018-19
Reverse Osmosis (RO) System 7798.20 (-) 28.04 57.38 -
IDC- RO system 349.53 - - -
Ash Handling System (AHS) 26.23 - - -
Balance of Plant (BOP) 445.57 5.82 - -
BTG 837.40 1.78 - -
Spare GT 846.76 35.73 - -
Coal Handling System (spares) 367.53 - - -
Cost of Land and Site 69.98 0.40 - 2112.86
General Civil Works 791.99 184.39 154.47 147.49
Railway System 2412.62 - - -
IDC- Railway System 448.94 - - -
Town Ship & Colony 43.38 - - -
New Schemes 554.59 829.06 2002.40 2119.96
Total additional capital expenditure 14992.72 1029.14 2214.25 4380.30
claimed
De-capitalization 131.14 69.61 132.63 81.37
Net additional capital expenditure 14861.58 959.53 2081.62 4298.93
claimed
28. The Petitioner has submitted that the capitalization of these packages that
form part of the original scope of work of the project could not be completed till the
cut-off date (31.3.2015) on account of various factors which were beyond the control
of the Petitioner and due to ‘Force Majeure’ reasons. The Petitioner has also
submitted that after the cut-off date, most of the project packages were completed in
2015-16, except for Railway System, General Civil Works (GCW) and Land & Site,
some assets in these packages have been put to use during the 2014-19 tariff period
and, accordingly, part capitalization of these packages falls in the said period and the
balance within the 2019-24 tariff period. The Petitioner has added that in majority of
cases where additional capitalization within the original scope of work of the project
has been delayed beyond the cut-off date (31.3.2015), the same has been on
account of reasons beyond the control of the Petitioner. The Petitioner has,
therefore, submitted that in respect of the additional capitalization during the period
Regulation 8(3) and Regulation 54 of the 2014 Tariff Regulations (Power to relax) to
consider the delays faced by the Petitioner due to ‘Force Majeure’ events and to
approve the additional capitalization, within the original scope of work. In addition to
this, the Petitioner has submitted that as the generating company is not entitled to
for minor capital assets for construction or procurement under the said allowance
was not available to the Petitioner. Therefore, for such expenditure on capital assets,
the Petitioner has sought invocation of Regulation 54 of the 2014 Tariff Regulations
Regulation 8(3) and Regulation 14(3) read with the principles laid down under
29. The Respondent, KSEBL has submitted that Regulation 14 of the 2014 Tariff
Regulations allows additional capitalization limited to works within the original scope
of work of the project. It has also stated that the additional capital expenditure
claimed in respect of assets/ works beyond the original scope of work, such as Fire
tender with shed & fixed foam system, NABL accredited lab, Yard sprinkling and fire
detection system in CHP, Re-heater modification & MTM installation, Coal pit run-off
redundancy and re-arrangement at BOP area, Gate house near junction tower & E-
store area and MAX DCS Version up-gradation, do not fall within the scope of
‘Change in law’ and these claims ought to be carried out from the O&M expenses
allowed to the generating station in terms of the 2014 Tariff Regulations. Based on
31. The Commission vide order dated 26.12.2017 in Petition No.152/GT/2015 had
allowed the projected additional capital expenditure of Rs.8400 lakh for Reverse
information, namely the (i) audited actual expenditure incurred for the asset; (ii) LD
amount, if any, recovered from the contractor; (iii) reasons for the delay including
IDC, if any; (iv) Cost-Benefit analysis; and (v) Technical capacity assessment at the
2014 Tariff Regulations. In compliance with this direction, the Petitioner has claimed
the actual additional capital expenditure of Rs.8147.73 lakh [Rs 7798.20 +349.53
lakh (IDC)] in 2015-16, (-) Rs.28.04 lakh in 2016-17 and Rs.57.38 lakh in 2017-18
towards RO System, duly supported by Auditor’s certificate. The Petitioner has also
submitted that there was no occasion for recovery of Liquidated Damages (LD) from
the contractor and since the RO plant was not delayed, there was no impact on
increase in IDC. As regards Cost-benefit analysis, the Petitioner has submitted the
following:
(b) Due to particularity and water quality of the boiler water supply, the cost
and optimization of desalination cannot be directly applied in the RO
treatment process in power plant. RO technology is known as the most
32. It is observed from the above that the Petitioner, in order to ensure
compliance with the directions of JSPCB (Jharkhand State Pollution Control Board)
and in order to reduce the make-up water consumption, had taken up the installation
of RO system and had obtained Board’s approval for the expenditure in 2013, but
the fact that the additional capital expenditure incurred is within the approved limit of
Rs.8400 lakh allowed vide order dated 26.12.2017 in Petition No. 152/GT/2015, the
16 and Rs.57.38 lakh in 2017-18 is allowed under Regulation 14(3)(ii) of the 2014
Tariff Regulations. Also, the negative adjustment of (-) Rs 28.04 lakh for RO system
in 2016-17, which is in respect of the expenditure claimed for this asset in 2015-16,
had allowed the projected additional capital expenditure of Rs.716.00 lakh in 2015-
16 for ‘Ash Handling System’ under Regulation 14(3)(iv) of the 2014 Tariff
Regulations, subject to the Petitioner submitting relevant details regarding the work
executed, at the time of truing-up of tariff in terms of Regulation 8 of the 2014 Tariff
Regulations. The Petitioner, in this petition, has claimed actual additional capital
expenditure of Rs.26.23 lakh in 2015-16 for this asset and has submitted that most
of the works have been completed by the cut-off date. It has, however, submitted
that initial spares amounting to Rs.26.23 lakh, for which procurement was
initiated before the cut-off date, was delivered and capitalised in 2015-16.
Therefore, the Petitioner has submitted that the Commission may permit
Regulations. Since the work of ‘Ash Handling System’ is continuous in nature and
is carried out in phases, during the lifetime of the project and is within the original
scope of work of the project, we allow the actual additional capital expenditure of
Rs.26.23 lakh in 2015-16 under Regulations 14(3)(iv) of the 2014 Tariff Regulations.
based on the actual expenditure incurred for the said asset/ work, for consideration
this petition, has claimed actual additional capital expenditure of Rs.2861.56 lakh
[2412.62+448.94 (IDC)] in 2015-16 towards ‘Railway System’ which form part of the
original scope of work of the project, but after the cut-off date. In justification of the
b) In case, capitalisation of these civil assets is not allowed till the completion
of Railway Infrastructure Package as Railway Infrastructure has not been put
to use, capitalisation (along with corresponding additional IDC) of the same
may be allowed along with remaining Railway Package and to allow such
capitalisation along with corresponding additional IDC or in the alternative, the
Petitioner may be allowed to amend its proposal to this effect. The decision of
the Commission in its order dated 4.12.2014 in Petition No. 17/GT/2013 and
order dated 9.10.2018 in Petition No. 38/MP/2018 is applicable in this case.
sought extension of cut-off date of the generating station till 31.3.2019 stating that
some of the works of ‘Railway System’ may not even be completed before
31.3.2019, with liberty to approach the Commission after completion of the said
works. From the submissions of the Petitioner, in this petition, it is evident that the
asset has not been put to use. Only some civil work like roads, over-bridges and
under-passes for smooth movement of public transport have been constructed and
Petitioner, under this head. In other words, the additional capitalisation claimed by
the Petitioner, is not in respect of the completion of the Railway System, but only for
few civil works which have been completed. Without the completion of the Railway
System, the construction of these civil assets for public transport has no nexus with
the generation of power from the plant. In our view, the additional capitalisation of
these civil assets cannot be permitted, unless the Railway System is completed and
put to use for generation and supply of power. The Petitioner’s reference to order
relaxation has no relevance in the present case and is, therefore, not considered. In
view of this, the prayer of the Petitioner for additional capitalisation of Rs.2861.56
lakh in 2015-16 is not allowed. The Petitioner may approach the Commission after
36. The Petitioner, in Petition No. 152/GT/2015 had claimed projected additional
capital expenditure of Rs. 2000.00 lakh in 2015-16, Rs.3000.00 lakh in 2016-17 and
Rs.1442.00 lakh in 2017-18 for ‘Township & Colony’ and the same was disallowed
by order dated 26.12.2017, with liberty to approach the Commission for additional
capitalization based on the actual expenditure incurred for the said asset/ work and
for consideration as per regulations in vogue. The Petitioner, in this petition, has
claimed actual additional capital expenditure of Rs. 43.38 lakh in 2015-16 for
‘Township & Colony’ which form part of the original scope of work, but after the cut-
off date. The Petitioner has submitted that while the expenditure of Rs.57.00 lakh
an expenditure of Rs.43.38 lakh was capitalised in 2015-16 for this work, which form
part of the original scope, but was deferred. The additional capitalisation claimed for
‘Township & Colony’ work in 2015-16 is on account of the same being deferred from
2014-15. The works pertaining to the township and colony, which are within the
original scope of work, are spilled over works which had started prior to the cut-off
date and, hence, the Petitioner was granted liberty vide order dated 26.12.2017 in
37. The Petitioner, in Petition No.152/GT/2015, had not claimed any projected
additional capital expenditure towards ‘Cost of Land & Site’ during the period 2015-
19. However, the Petitioner, in the said petition, had also claimed projected
additional capital expenditure of Rs.6255 lakh in 2015-16 for ‘General Civil Works’
with a prayer for extension of the cut-off date till 31.3.2019 and the same was
disallowed vide order dated 26.12.2017. However, liberty was granted to the
accordance with the regulations in vogue. The Petitioner has submitted justifications
for claim towards Cost of Land & Site and General Civil Works as stated below.
38. The Petitioner, in this petition, has claimed the actual additional capital
expenditure of Rs.69.98 lakh in 2015-16, Rs. 0.40 lakh in 2016-17 and Rs.2112.86
lakh in 2018-19 towards ‘Cost of Land & Site’ which form part of the original scope of
2014 Tariff Regulations. As regards ‘land acquisition’ issues and consequent time
and cost overrun, the Petitioner has mainly submitted the following:
(a) Acquisition of land for setting up of land-intensive projects like that for a
thermal power plant is a humongous and time-consuming task. The task
involved becomes even more complicated when the Project Proponent/
Developer has to deal with vast and multiple land parcels, in an area that has
the environment of socio-cultural disturbances with a history of fragile
industrial relations in and around that area;
(a) MPL has made earnest efforts in coordinating with various stakeholders
involved, such as its equity partner – DVC (which is a statutory entity of the
Central Government), the land owners, the State Government, various
Government departments and other multitude of associated entities, for timely
completion of the thermal power project, which today benefits Distribution
Licensees in New Delhi, West Bengal, Jharkhand and Kerala;
(b) Despite serious planning and prudence, various extraneous factors that
are out of bound of the project developer’s control have delayed the project
completion timelines. The said delay is due to ‘Force Majeure’ conditions and,
therefore, such reasons cannot in any manner be attributable to MPL.
(c) While the zero date of the Project was 25.10.2007, possession of land
and, hence, construction activity could not be started until R&R Policy was
approved by Government of Jharkhand and a settlement reached with Project
Affected People (“PAP”) only on 31.03.2008. There is incremental cost
associated with time delay/ time overrun which has ultimately led to increase
in Project Cost;
(d) This following summary of events highlights some of the key facts w.r.t.
land acquisition for the Project of the relevant period in the past and several
associated issues in a chronological manner:
(i) The land earmarked for the project comprises land of various natures
viz. Rayati (Private), Gair Majruah (GM) or State Government owned and
Forest land;
(ii) The land earmarked for the project was acquired (Rayati) by DVC or
leased (GM and Forest land) to DVC between the period from 2002 to
2009, but in phases, and was not transferred to MPL, either on paper or
physically till 31.3.2008. Some part of project land is yet to be transferred
in favour of MPL, although its possession has been given to MPL;
(iii) In the absence of R&R policy in the State, MPL had to take initiatives
in the R&R activities associated with the Project;
(ix) There was change in the policy clarity on whether land could be sub-
leased for long period in the name of private entities like MPL.
(x) Therefore, even though DVC was a 26% equity partner for the Project,
the land transferred to DVC by the Government of Jharkhand was finally
permitted to be transferred and made available to MPL in 2018 i.e. after
delay of almost 10 years.
(xi) MPL made relevant payments with respect to the acquisition/ sub-
lease of land within reasonable timelines against the original/ amended
fees/ lease to the respective department.
(xii) GoJ, which permitted MPL physical possession of GM land and its
transfer under sub-lease in 2010, had later gone back on their permission,
citing provisions of the (new) amendments in the land policy of 2011/14 in
the State, which made the process carried out till then redundant, thereby
leading to additional associated cost and loss of time. The Change in
Policy of GoJ fall within the scope of ‘Change in law’.
(xiii) GoJ was fully aware of the shareholding pattern of MPL at the time
of granting permission and despite the same, revoked the permission for
sub-leasing of the land granted to it on the grounds that MPL is not a
Government entity.
The Petitioner has furnished in detail, the justification for time and cost overrun
39. The Petitioner has submitted that in order dated 26.12.2017 in Petition
No.152/GT/2015, a total of Rs.19505 lakh was approved towards Cost of Land &
Site expenses in 2014-15. It has stated that the actual capitalisation under Land &
Site head had increased to Rs.21142 lakh as compared to initially approved amount
Rs.1628 lakh between two heads viz. “Cost of Land & Site” and “Pre-Operative
expenses”. The Petitioner has also submitted that the capitalization approved by the
the actual additional capitalization towards Pre-operative expenses was Rs. 208 lakh
in 2014-15 and the remaining amount of Rs.1628 lakh initially approved under Pre-
operative expenses was capitalised under “Cost of Land & Site” owing to the nature
of expense as the statutory auditor changed the category of lease hold land due to
which the amount of Rs.1628 lakh was shifted from pre-operative expenses to cost
of land and is, thus, claimed as part of capitalisation under the head ‘Cost of Land &
Site in 2014-15’. The Petitioner has further submitted that there has been inter-se
there is no increase in the overall actual capitalisation under these heads put
together in 2014-15. In addition to the above, the Petitioner has submitted that it had
(i) Purchase of private land in Mugma Village for Railway Corridor (Rs.0.70 crore in
2015-16, Rs.0.004 crore in 2016-17 and Rs.1.72 crore in 2018-19);
(ii) Payment of fresh demand for un-notified Forest land admeasuring 191.67 acre
(Rs.11.61 crore in 2018-19);
(iii) Payment of demand for GM land acquired for Railway Corridor and Payment of
License fee for Railway land acquired for Railway Corridor (Rs.6.47 crore in
2018-19);
(iv) Payment of fresh demand of GM Land (114.95 acre) for the Project (2019-24);
40. The details of additional capitalization towards Land & Site for 2015-19, as
(Rs. in crore)
Category 2015-16 2016-17 2017-18 2018-19
Main Plant Land
Raiyati Freehold land-Main Plant - - - -
Forest
Forest Land- Main project - - - 11.61
Land
GM land GM land - - - -
Railway Land
Raiyati Freehold Land- Railway 0.7 0 - -
Freehold Land- Railway-
- - - 1.72
Mugma
GM Land GM land Railway-I - - - -
GM Land- Railway-II - - - 6.47
Eastern Railway Land-II - - - 1.04
Eastern Railway Land-I - - - 0.3
Krishi Farm and tribal land - - - -
Contingency - - - -
Total 0.7 0 - 21.13
41. Accordingly, the Petitioner has submitted that due to changes in policies and
the stand of ‘GoJ’ on transfer of land, the land transfer to the Petitioner for the
Project had been delayed. The Petitioner had been asked to pay additional amount
42. The Petitioner has claimed actual additional capital expenditure of Rs.791.99
Rs.147.49 lakh in 2018-19 towards ‘General Civil Works’ which form part of the
original scope of work, under Regulation 3(25) and Regulation 8(3) read with
Regulation 54 of the 2014 Tariff Regulations. The Petitioner has submitted that delay
in execution of ‘General Civil Works’ package capitalised during the period 2015-19
is on account of the various ‘Force Majeure’ reasons which were beyond the control
of the Petitioner. As regards General Civil Works (GCW), the Petitioner has
submitted that in terms of the liberty granted vide order dated 26.12.2017, the
Petitioner has claimed actual capital expenditure of Rs.10578 lakh in 2014-15 for
General Civil Works against the approved cost of Rs.9793 lakh. It has also submitted
that an amount of Rs.787 lakh allowed in 2014-15 towards Design, Engineering and
Project Management has been capitalized under ‘General Civil Works’ in 2014-15 as
‘Engineering and Project Management’ were provided for ‘General Civil Works’
package. Thus, a total amount of Rs.10578 lakh in 2014-15 has been claimed under
this head, taking both the heads together. According to the Petitioner, there has
been inter-se adjustment between these two heads of capitalization owing to re-
capitalization under these heads put together. The details of the expenditure and the
(i) Boundary Wall and Peripheral Road inside Plant along Boundary Wall:
Boundary wall work was delayed due to various land related disputes and other
problems which were beyond the control of the Petitioner. The contract for boundary
(b) Field Hostel (part of work got delayed): The Commission in its order dated
19.11.2014 (in Petition No.274/2010) had acknowledged that there is a need of field
hostel within the boundaries of the plant for smooth, intervention free operation of the
plant, considering the difficult remote location of the plant, accessibility at odd hours
and frequent blockages and agitation by local villagers backed by factional politicians.
The contract for construction of field hostel was awarded to M/s Kanwar
Enterprises (P) Ltd in 2014. However, while carrying out the construction work, the
contractor faced several hindrances from the local people. Therefore, M/s Kanwar
addressed letter dated 13.5.2015 to the Petitioner, citing the reason for delay of field
hostel and requested for time extension for the work. When the contractor started
the work by making burgees for the layout and by installation of borewell, the locals
damaged the burgees and borewell claiming to be owners of the land. This problem
took around 2 months to be sorted out. Again, after starting the work, it was
stopped by the locals demanding that work should be executed through them
only. The contractor was ready, but the rates were very high and it took almost one
month to convince them and make them ready to work at genuine rates. But the
villagers could not deliver the required number of labour and the work was
stopped. After resuming the work with available labour, it was again stopped by
local vendors for about 45 days due to land dispute. Work was also stopped for 15
43. We have examined the claims and justifications given by the Petitioner.
According to the Petitioner, the cost of land had increased on account of changes in
the policies of the Government of Jharkhand. Also, the works of Boundary wall and
the peripheral road inside Plant along Boundary Wall and Field Hostel got delayed
due to various force majeure events. Based on this, the Petitioner has prayed for
44. It is observed from submissions of the Petitioner that the land payments are
mainly due to (i) payment of fresh demand for un-notified Forest land, payment of
demand for GM land acquired for Railway Corridor and (ii) payment of license fee for
Railway land acquired for Railway Corridor etc. The payment delays were mainly
private land in Mugma Village for Railway Corridor (for Rs.70 lakh in 2015-16, Rs.40
lakh in 2016-17 and Rs.172 lakh in 2018-19) and the Payment of fresh demand for
un-notified Forest land measuring 191.67 acre (for Rs.1161 lakh in 2018-19) pertains
to Railway corridor and the delay is attributable to the dispute which had arisen due
resulted in Writ Petition No. 5084 of 2016 being filed by the Petitioner before the
High Court of Jharkhand, wherein, directions were issued by the High Court on
issues. As the matter could not be fully resolved, the Petitioner again filed Writ
Petition No. 5242 of 2017 before the High Court of Jharkhand and the High Court in
its judgement dated 22.2.2018, directed the State Government (GoJ) to cancel the
prepare fresh awards in favour of genuine persons within four months. The High
Court’s order dated 22.2.2018 has been enclosed as Annexure P6/H to the petition.
In respect of (i) Payment of demand for GM land acquired for Railway Corridor and
payment of license fee for Railway land acquired for Railway Corridor (for Rs.647
lakh in 2018-19) and (ii) Payment of fresh demand of GM Land (114.95 acre) for the
due to change in the policy of State Government (GoJ) for leasing the land. The
Petitioner, it is observed that the delay in payment towards land and site was due to
furnished indicates that ‘land issues’ had prolonged till 24.11.2018, i.e. even after the
cut-off date. Though the said work form part of the original scope of work of the
project, the Petitioner had to continue the execution of these works even after the
cut-off date on account of the delay in the availability of land and site. Similarly, the
delay in the development of Railway Corridor was cleared when Hon’ble High Court
of Jharkhand vide its judgment dated 22.2.2018 had directed the State Government
accordance with law. The Petitioner had made all payments mandated due to
basis. Similarly, in the case of General Civil Works (Boundary wall and Field hostel),
the delay in execution of these works is consequent upon the delay in the availability
of land and are for reasons not attributable to the Petitioner. As regards the prayer of
the Petitioner for extension of cut-off date till 31.3.2019, the Commission in its order
“In view of this submission and considering the fact that capitalization of projected
additional expenditure of these assets/ expenditure before 31.3.2019 is uncertain, the
consideration of the prayer of the petitioner for extension of cut-off date of the
generating station till 31.3.2019 would not serve any useful purpose. In this
background, the prayer of the petitioner for projected capitalization of the expenditure
is not allowed. However, the petitioner is granted liberty to approach the Commission
for additional capitalization based on the actual expenditure incurred for these assets
and the same will be considered after due diligence and prudence as per the
regulation in vogue at that time…”
46. As already observed, the delay in the availability of land & site was due to
Railway Corridor after payment of compensation. Also, the delay due to non-
availability of land had caused the delay in execution of the General Civil Works by
the Petitioner and the same cannot be attributable to the Petitioner. From the
documents enclosed by the Petitioner, it is noticed that the Petitioner has been
coordinating with the local administration for speedy resolution of the land issues and
has been taking steps to mitigate the delay. Accordingly, actual additional
lakh in 2018-19 towards Land & Site is allowed under Regulation 14(3(i) of the 2014
Tariff Regulations. Consequently, as the General Civil Works were also delayed due
to delay in the possession of land, for which reasons and justifications have been
towards ‘Coal Handling System’ under Regulation 14(3) of the 2014 Tariff
Regulations. By order dated 26.12.2017, the said claim was rejected as under:
“In response to the Commission’s directions vide ROP of hearing dated 12.1.2016, the
petitioner has not furnished any details of the works to be executed, the
reasons/justification for the delay in the execution of ‘Coal Handling System’ beyond
the cut-off date of the project. In this background, the projected additional capital
expenditure for Coal Handling System claimed by the petitioner after the cut-off date is
not allowed”
48. The Petitioner, in the present petition, has claimed actual additional capital
towards ‘Coal Handling System’ (which form part of the original scope of work of the
project, but after the cut-off date) under Regulation 3(25) read with Regulation 8(3)
and Regulation 54 of the 2014 Tariff Regulations. The balance amount of Rs.84.81
lakh (Rs.367.53 lakh - Rs.282.72 lakh) is towards Stone Picking shed (for Rs.42.79
lakh), Fire Detection system (for Rs.21.04 lakh) and ‘Others’ (Rs.20.98 lakh). In
justification of the same, the Petitioner has submitted that the actual additional
2014-15 and Rs. 367.53 lakh in 2015-16. It has submitted that Rs.367.53 lakh
which was initiated and procured prior to the cut-off date (31.3.2015), while the
accordance with the provisions of Regulation 13 of the 2014 Tariff Regulations (4%
Rs.282.72 lakh towards initial spares pertains to initial spares which form part of the
original scope of the Plant and Machinery. It is evident from the submissions of the
Petitioner, that the procurement of spares was initiated even before the cut-off date
(31.3.2015), but spares were received only during 2015-16. Since the claim of the
spares for ‘Coal Handling System’ after the cut-off date, the same is allowed in
amount of Rs.84.81 lakh (Rs.42.79 lakh for Stone Picking shed, Rs.21.04 lakh for
Fire Detection system and Rs.20.98 lakh towards ‘Others’) have not been allowed as
the items do not form part of initial spares and no justification has also been
capital expenditure of Rs.1616 lakh in 2015-16 towards BTG Package and the same
was not allowed by the Commission in its order dated 26.12.2017. The Petitioner, in
the present petition, has claimed actual additional capital expenditure of Rs.837.40
lakh for BTG package (including spares for Rs.777.30 lakh) and Rs.846.76 lakh for
Spare GT in 2015-16, Rs.1.78 lakh for BTG and Rs.35.73 lakh for Spare GT in 2016-
17, which are within the original scope of work of the project, but after the cut-off
date. The balance amount of Rs.60.10 lakh (₹837.40 - ₹777.30) under BTG package
apart from Spares is towards ‘Workshop equipment’ (Rs.23.83 lakh), ‘Mill hoist’
(Rs.15.23 lakh) and ‘Others’ (Rs.21.05 lakh). The Petitioner, in justification of the
said claim has submitted that the expenditure mainly relates to mandatory ‘Initial
capital spares’, which were required to be procured before the cut-off date
(31.3.2015). It has, however, submitted that due to their non-critical requirement for
cut-off date from M/s BHEL, but their procurement was concluded in 2015-16.
Accordingly, the Petitioner has submitted that the additional capital expenditure falls
within the scope and ambit of Regulation 54 read with Regulation 8(3) and
50. The Respondent, KSEBL has submitted that the Petitioner has not furnished
any details and justification for the claim and the same is not in line with Regulation
14(3) of the 2014 Tariff Regulations. It has further submitted that the BTG package
was capitalized after the cut-off date and is not allowable in terms of the regulations,
as the Petitioner has not furnished any valid reason for extension of procurement of
the same beyond the cut-off date. Accordingly, KSEBL has submitted that the claim
of the Petitioner may be disallowed. In response, the Petitioner has submitted that
the cut-off date of the generating station is 31.3.2015, which is within the first year
(2014-15) of the 2014-19 tariff period. The Petitioner has stated that the claim under
Regulation 14(3) is inadvertent and the same may be read as Regulation 14(2) of the
2014 Tariff Regulations. Accordingly, it has submitted that the claim is within the
original scope of work of the project. The Petitioner has further submitted that the
contractual liability was created in 2014-15, but was reflected in 2015-16 only after
after material is received along with bills. The Petitioner has also furnished the
details in Annexure P/12 of the petition. The Petitioner has contended that due to
force majeure condition, arising on account of multiple failures, the Petitioner had to
procure the assets, the process for which had started in 2014-15. It has also added
that initial spare GTs under contingency budget for deferred initial spares was
procured to sustain the unit operation during any future eventuality. Therefore, the
scope of Regulations 14(3)(iii) and 14(3)(v) read with Regulation 54 of the 2014
Tariff Regulations.
51. In addition, the Petitioner has submitted that for key initial spares, such as
BCW pump, journal shaft, workshop, IA compressor spare, High energy drain valve,
HP plunger pump, Mill hoist for Unit-2, Instrumentation capital spares and Spare GT,
the procurement of these spares were initiated prior to the cut-off date, but the OEM
could deliver these items only after the cut-off date. It has been stated that these
items are urgently required for the operation of the generating station and by
procurement of these spares after the cut-off date, no extra cost had occurred to the
beneficiaries. The Petitioner has further stated that in terms of Regulation 13 of the
2014 Tariff Regulations, the capitalisation of initial spares is limited to 4.0% of Plant
& Machinery cost up to cut-off date for coal-based/ lignite-fired thermal generating
stations. It has submitted that the total Plant & Machinery cost up to cut-off date is
Rs.2821.82 crore and in terms of Regulation 13 of the 2014 Tariff Regulations, the
Rs.2821.82 crore). The Petitioner has pointed out that initial spares of Rs.71.64
crore, capitalised till 2013-14, were approved in the order dated 26.12.2017 in
Petition No. 152/GT/2015 and further, initial spares of Rs.14.83 crore and Rs.21.53
crore have been procured and capitalized under various packages during the years
(Rs. in crore)
Initial Spares Amount
Initial Spares supplied till 31.3.2014 (A) 71.64
Initial Spares supplied during 2014-15 (B) 14.83
Initial Spares supplied during 2015-16/ 2016-17 (C) *21.53
Total (A+B+C) 108.00
4% of P&M cost 112.87
52. Thus, the total value of Initial spares procured till 2015-16 is Rs.108 crore
which is within the ceiling of Rs.112.87 crore i.e. (4% of Rs.2821.82 crore), specified
under Regulation 13 of the 2014 Tariff Regulations. The Petitioner has submitted
that it has procured initial spares as and when it was required and some spares were
procured in 2015-16, after cut-off date. Regulation 14(1)(3) of the 2014 Tariff
accordance with Regulation 13 of the 2014 Tariff Regulations (i.e. 4% of Plant &
Machinery cost as on the cut-off date). It is evident from the submissions of the
Petitioner that the initial spares form part of the original initial cost of the plant and
machinery. The procurement of spares was initiated before the cut-off date
(31.3.2015) but the OEM had delayed the delivery of the same. Since the Petitioner
is entitled for initial spares up to 4% of Plant and Machinery cost, we allow Rs.777.30
lakh towards initial spares of BTG package in exercise of the power to relax under
Regulation 54 of the 2014 Tariff Regulations. However, the amount of Rs.60.10 lakh
(Rs.23.83 lakh), Mill hoist (Rs.15.23 lakh) and for Others (Rs.21.05 lakh) during
2015-16 and Rs.1.78 lakh in 2016-17 have not been allowed as the capitalization
has occurred after the cut-off date and reasons furnished by the Petitioner do not
lakh in 2015-16 and Rs 35.73 lakh in 2016-17 towards Spare GT, the Petitioner has
submitted that the same may be allowed as ‘replacement’ as the original Generator
Transformer (GT) procured prior to COD had failed and has been de-capitalized at
its gross value of Rs.1147.14 lakh in 2014-15. This submission of the Petitioner has
been verified from the list of assets de-capitalized in 2014-15 and it is noticed that
lakh in 2015-16 and Rs.35.73 lakh in 2016-17 towards Spare GT is allowed for the
purpose of tariff as ‘replacement’ since the gross value of the old asset has been de-
Regulations.
54. The Petitioner has claimed actual additional capital expenditure of Rs.445.57
lakh in 2015-16 and Rs.5.82 lakh in 2016-17 towards ‘BOP’ which form part of the
original scope of work of the project, but after the cut-off date. The claim of the
Petitioner for Rs.5.82 lakh in 2016-17 is under the head ‘Others’. In justification of
the said claim, the Petitioner has categorised the capitalization of this package in
2015-16, as under:
(Rs. in lakh)
Asset Description 2015-16
Condition Monitoring Instruments 207.20
Initial mandatory spares 185.10
Electrical System for Plant facilities 53.27
Total 445.57
55. The Respondent, KSEBL has submitted that the additional capitalization
claimed after the cut-off date may not be allowed. In response, the Petitioner has
submitted that the capitalization claimed under BOP package, beyond the cut-off
instruments and initial spares. It has submitted that the procurement process was
initiated within the cut-off date and order was placed in March 2015/ early April 2015,
but the supply got concluded in 2015-16. The Petitioner has stated that the delay
was on account of multiple failure of the units during the years 2013-14 and 2014-15,
thereby delaying the initial stabilization of the units. It has added that on account of
Regulation 14(3)(v) read with Regulation 54 of the 2014 Tariff Regulations (Power to
relax). The Petitioner has further submitted that the additional capitalization for
assets which form part of the original scope of the project, but also have life of more
than one accounting period and is an integral part of the existing assets. Hence,
such expenditure incurred are capital in nature and are not charged to O&M
57. The Petitioner has submitted that Regulation 46 of the Central Electricity
equipment. It has submitted that the procurement process of testing instruments was
initiated on 13.8.2014 (within the cut-off date) after finalizing the specifications and
the bidding process was initiated and Purchase order was issued to qualified
supplier on 6.4.2015. The equipment was procured in batches in order to lessen the
burden of cost in one year. The Petitioner has also submitted that major procurement
was done in 2015-16 for Rs.207.20 lakh and the remaining equipment were
purchased in 2016-17. The Petitioner has submitted that since the said expenditure
expenditure incurred squarely falls within the scope of Regulation 14(3)(ii) of the
58. We have considered the submissions of the Petitioner. Since the additional
equipment has been incurred in compliance with the CEA (Technical Standards for
59. The Petitioner has claimed initial mandatory spares for Rs.185.10 lakh and
has stated that these mandatory spares were procured as and when they were
required and some spares were procured in 2015-16 i.e. after cut-off date. The
Petitioner has stated that the same is within the ceiling of initial spares as per the
60. We have considered the submissions. The claim of the Petitioner for
Rs.185.10 lakh towards mandatory spares pertain to initial spares which form part of
the original scope of the Plant and Machinery. It is evident from the submissions of
the Petitioner that the procurement of the spares was initiated before the cut-off date
(31.3.2015), but were received only during 2015-16. Accordingly, the claim of the
spares for ‘BOP spares’ after the cut-off date is allowed under Regulation 14(1)(3) of
61. The Petitioner has submitted that facilities like field hostel, gate house and
canteen were delayed due to land issues and local agitation as explained under
“General Civil Works” package. Hence, the capitalization of electrical system was
carried out in 2015-16 when these facilities where commissioned and an amount of
Rs.53.27 lakh was capitalized in 2015-16. The Petitioner has submitted that these
assets are within the original scope of work, but due to various force majeure
conditions faced by the Petitioner, the commissioning of such assets were delayed
house and canteen, is consequential to ‘General Civil Works’ which were delayed
due to land non-availability and the same are for reasons beyond the control of the
support of the claim for Rs.5.82 lakh during 2016-17, the Petitioner has submitted
that the amount corresponds to “Others” but has not mentioned the nature of items
63. The Petitioner has also claimed additional capital expenditure for ‘New
Schemes’ in 2015-19, as follows, which do not form part of the original scope of work
of the project and which were taken up after the cut-off date:
(Rs in lakh)
Assets/Works 2015-16 2016-17 2017-18 2018-19
Fire Tender with shed 61.53 0.60 14.47 1.30
Fixed Foam system for LDO & HFO 60.74 - - -
NABL Accredited Lab 70.52 112.96 5.62 55.18
Online Effluent Monitoring System 13.95 - - -
IT & Others 10.97 61.01 125.62 134.55
Augmentation of Track Hopper shed 268.36 - -
MAX DCS version up-gradation (XP) 67.52 - 438.86
Unit-1
Construction of road in Ash area - 80.29 18.15 -
Installation of CAAQMS - 67.58 - -
Power supply redundancy and Re- - 401.59 - -
arrangement at BOP area
Gate house near JNT/security infra/e- - 45.07 98.58 257.66
security
Ash Bagging - 27.21 -
Augmentation of Store area - 31.74 7.58 171.16
Safety related expenditure - - 67.09 103.67
Augmentation of Fire detection system - - 80.41 -
Drinking Water System - - 10.07 13.16
Augmentation of Ash handling system - - 700.13 848.07
Fabrication of expansion bellow - - 49.69 23.34
64. The Petitioner has claimed additional capitalization of Rs.61.53 lakh in 2015-
16, Rs.0.60 lakh in 2016-17, Rs.14.47 lakh in 2017-18 and Rs.1.30 lakh in 2018-19
for Fire tender with shed under Regulation 14(3)(ii) of the 2014 Tariff Regulations. In
justification for the same, the Petitioner has submitted that a fire station has been
commissioned near the DM plant with intent to cover the entire plant premises in the
65. The Respondent, KSEBL has submitted that IS 3034 Standards were to be
followed by the Petitioner at the time of design of the generating station and should
have formed part of the original scope of work. The Respondent has stated that the
expenditure does not fall under ‘change in law’ and, therefore, should not be allowed
stabilization issues of the units, which was of utmost priority, the Petitioner had
initially conducted audit/ review/ mock drills of the existing firefighting systems and
their compliance with IS standards/ CEA Regulations, 2010. After review of the
firefighting systems, it was observed that with the existing location of Fire Tender, it
was not possible to meet the response time of 5 minutes in case of fire at the Coal
Handling Plant area. The Petitioner has pointed out that the claim of NTPC towards
firefighting system was allowed by the Commission in its order dated 29.7.2016 in
period) subject to the report of CEA. Accordingly, the Petitioner has submitted that
66. IS:3034 standard which deals with fire stations in Super Thermal Power
generating stations having installed capacity exceeding 1000 MW, stipulate the
following:
“(a) As per clause no 10.3.5 “Considering the large area of Super Thermal Power
Stations (Super Thermal/Power Stations Having Installed Capacity Exceeding 1 000
MW), facilitate quick turn out it may be necessary to deploy the operational
manpower at two Fire Stations — a Main Fire Station and a Sub Fire Station, both
having up-to-date communication facilities to help easy
mobilization in case of emergency.”
(b) As per clause no 10.4.1 “Power Stations authorized for full time Fire Brigades with
major firefighting appliances shall have well designed Fire Stations for housing
appliances and firefighting staff. They shall be so located that the response times for
fire appliances are kept to a minimum not to exceed 5 minutes.”
67. Thus, as per IS:3034 standard, the response time for reaching a fire prone
area should be limited to less than 5 minutes and, if necessary, an additional sub-fire
station is required to be made operational. The Petitioner has submitted that during
various mock drills conducted (as per the Factories Act, 1948), it took more than five
minutes to reach the premises of Coal Handling Plant (CHP) of the Petitioner, which
is a critical area to be protected from fire, as it is situated far away from the DM Plant
area. Hence, the need was felt by the Petitioner to set up another sub-fire station
near CHP area to be compliant with IS:3034 standard in order to avoid any
eventuality. Keeping in view that the expenditure incurred was in compliance with the
IS:3034 standard (which deals with “Fire Stations in Industrial Buildings’) and as the
same is required for the safety and security of the plant, the additional capital
Regulations.
68. The Petitioner has claimed additional capitalization of Rs.70.52 lakh in 2015-
16, Rs.112.96 lakh in 2016-17, Rs.5.62 lakh in 2017-18 and Rs.55.18 lakh in 2018-
19 for NABL accredited lab. It has also claimed additional capitalization of Rs.13.95
lakh for ‘Online Effluent monitoring system’ in 2015-16. The Petitioner has claimed
for Construction of road in Ash area and Rs.67.58 lakh for ‘Installation of CAAQMS’
in 2016-17. Also, additional capital expenditure of Rs.29.90 lakh for ‘Wind barrier in
Ash pond’ and Rs.18.91 lakh for ‘Yard sprinkling and Fire detection system’ in CHP
in 2018-19 has been claimed by the Petitioner. The Petitioner has submitted that
these expenditures have been incurred for various schemes which were to be
complied by the Petitioner based on the directions of the Jharkhand State Pollution
Control Board (JSPCB) and is, therefore, covered under Regulation 14(3)(ii) of the
2014 Tariff Regulations. It has stated that the sitting arrangement of the lab
technicians/ department was initially arranged in the adjoining space which was not
arrangement was made to comply with the requirements of ISO-17025 for the lab
and to comply with the mandate of Jharkhand State Pollution Control Board (JSPCB)
scope and meaning of Regulation 14(3)(ii) of the 2014 Tariff Regulations i.e. change
in law or compliance of existing law. The Respondent, KSEBL has submitted that the
justification on perusal of the ‘Consent to Operate’ order and the same is not in line
with JSPCB with regard to the said schemes. The schemes executed by the
Petitioner are mainly to comply with the Pollution control norms and for maintaining
incurred the aforesaid additional expenditure in respect of these assets/ works for
compliance with the directions of JSPCB, the same are allowed under Regulation
70. The Petitioner has claimed additional capitalization of Rs.10.97 lakh in 2015-
16, Rs. 61.01 lakh in 2016-17, Rs.125.62 lakh in 2017-18 and Rs.134.55 lakh in
2018-19 for IT & others. The Petitioner, in justification of the same, has submitted
that it has incurred the expenditure for replacement of IT equipment, namely laptops,
computers, servers, printers, etc. and some other ‘minor assets’ which have been
fully depreciated in the books of accounts. The Petitioner has stated that in case the
generating station would have completed more than 10 years, the expenses on such
items would have been managed from the Compensation Allowance eligible in terms
of the 2014 Tariff Regulations. It has stated that the life of IT equipment is much less
than 10 years and needs to be replaced within the said period. Therefore, there is no
other means available with the Petitioner for meeting expenditure on these assets.
Regulation 54 of the 2014 Tariff Regulations and has submitted that the expenditure
Act, 2003. The Respondent, KSEBL has submitted that the additional capital
expenditure falls under R&M expenses and, therefore, the same may be disallowed.
claimed by the Petitioner is beyond the original scope of work of the project and is
after the cut-off date. In this regard, the proviso to Regulation 14(3) of the 2014 Tariff
“Provided that any expenditure on acquiring the minor items or the assets including
tools and tackles, furniture, air-conditioners, voltage stabilizers, refrigerators, coolers,
computers, fans, washing machines, heat convectors, mattresses, carpets etc. brought
after the cut-off date shall not be considered for additional capitalization for
determination of tariff w.e.f. 1.4.2014.”
nature of ‘minor assets’ which has been incurred after the cut-off date. Hence, in
terms of the proviso to Regulation 14(3) of the 2014 Tariff Regulations, the additional
73. The Petitioner has claimed additional capitalization of Rs.60.74 lakh in 2015-
16 for ‘Fixed foam system for LDO and HFO’ under Regulation 14(3)(ii) of the 2014
Tariff Regulations. The Petitioner has submitted that Foam flooding system at HFO
and LDO Tank is required as per clause no 5.3.5.2 of IS 3034 standards, which
stipulate as follows:
“5.3.5.2 The oil storage tanks should also have fixed foam fire extinguishing system in
conformity with IS 12835 (Part 1): 1989.”
74. The Petitioner has referred to IS 3034:1993 and IS 12835 (Part 1): 1989 and
has submitted that the additional expenditure incurred is for compliance with the
provisions of the said IS standards. Though these IS standards were in place at the
is for compliance with the existing law, we allow the additional capitalization of Rs.
60.74 lakh for ‘Fixed Foam system for LDO and HFO’ in 2015-16 under Regulation
Petitioner has submitted that originally, Track hopper was designed for direct
unloading of coal from BOBR (Bogie Open Bottom Rapid discharge Railway Wagon)
into track hopper. It has submitted that the track hopper shed was erected in 2012
with dimensions as per BOBR unloading requirements, but in the absence of rail
connectivity, coal is transported through road by Hyva (a vehicle by Tata Motors) and
is unloaded at coal bed/ ramp area or track hopper as per need and, thereafter,
excavators/ bulldozers push the coal into track hopper. The Petitioner has stated that
continuous movement of heavy vehicles for feeding coal into track hopper, coupled
with impact of large size stones in coal had considerably damaged the structure of
the Track hopper, which endangered the safety of personnel working there. It has
submitted that additional capital expenditure under this scheme was required to be
incurred due to unforeseen circumstances beyond the control of the Petitioner and
could not have been anticipated or avoided, through prudent utility practices.
Accordingly, the Petitioner has prayed that the Commission may allow the additional
capital expenditure under this scheme, in exercise of the power under Regulation 54
(Power to relax) read with Regulation 3(25) and Regulation 8(3) of the 2014 Tariff
Regulations. Alternatively, the Petitioner has submitted that the said expenditure is
76. The matter has been examined. Admittedly, the additional capital expenditure
claimed by the Petitioner is beyond the original scope of work of the project and is
after the cut-off date. The Petitioner’s submission that the additional capitalization
incurred is on account of ‘Force Majeure’ events and the same may be allowed in
Alternatively, the prayer of the Petitioner to allow the said claim under Regulation
14(3)(iii) of the 2014 Tariff Regulations is also not acceptable, as the Petitioner has
not furnished any documentary evidence indicating that the expenditure has been
incurred for higher security or safety of plant as advised or based on directions of the
internal security. In view of this, the additional capitalization claimed by the Petitioner
(f) MAX DCS Version up-gradation (XP) Unit-1 (New schemes required on account
of obsolescence)
77. The Petitioner has claimed additional capitalization of Rs.67.52 lakh in 2015-
16 and Rs.438.86 lakh in 2017-18 for ‘MAX DCS version Up-gradation (XP) Unit-1’ in
exercise of the power to relax under Regulation 54 of the 2014 Tariff Regulations. In
(a) Digital Control System (DCS) is the automated intelligence of any thermal power
generating station. Windows XP operating system was the most popular and reliable
Windows platform provided by all leading industrial automation companies for their
control system. However, from 8.4.2014, Microsoft has completely withdrawn the
support for Windows XP Operating System. With end of support by Microsoft on
Windows XP operating system, it stopped developing Security Patches for Windows
XP, non-security hot fixes, online technical content updates and telephone support.
Hence, system was more vulnerable for malware attack and had become out-dated.
(b) The Petitioner managed the system with existing inventories and support from
BHEL till mid of 2016. However, after mid of 2016, M/s BHEL expressed its inability to
provide further support and recommended for complete up-gradation of existing DCS
to higher version of Windows Operating System with upgraded version of MAX DNA
DCS for Maithon Units to ensure services and necessary spares. Accordingly, MAX
DCS up-gradation for Unit-1 was taken up in 2017-18.
78. The Respondent, KSEBL has submitted that the additional capital expenditure
incurred is in the nature of R&M expenses and, hence, may not be allowed. In
response, the Petitioner has submitted that the expenditure has been incurred on
control of the Petitioner. It has stated that though Microsoft had withdrawn its support
for Windows XP Operating System on 8.4.2014, the Petitioner with all its efforts and
existing inventory managed to maintain the system till 2016-17, but had to undertake
such replacements when M/s BHEL stopped extending its support after mid of 2016
and strongly recommended to upgrade to higher versions. The Petitioner has stated
that the same could not have been avoided and due to such uncontrollable factors, it
79. The matter has been examined. The Petitioner has submitted that the Digital
Control System (DCS) has become obsolete as Microsoft had completely withdrawn
its support for Windows XP Operating System. Max DNA version 6.x.x on Windows 7
was envisaged to replace the earlier version i.e. Max DNA version 4.x.x on Windows
XP. The Petitioner has furnished the recommendations of OEM (M/s BHEL)
confirming that further sustenance of the system was not possible. Considering the
submissions of the Petitioner and the documents furnished and keeping in view that
the additional expenditure was incurred by the Petitioner under circumstances which
were beyond its control (on account of obsolescence of Windows XP for DCS), the
80. The Petitioner has claimed additional capital expenditure of Rs.45.07 lakh in
2016-17, Rs.98.58 lakh in 2017-18 and Rs.257.66 lakh in 2018-19 under Regulation
54 (Power to relax) read with Regulation 14(3)(iii) of the 2014 Tariff Regulations for
construction of gate house near JNT equipped with turnstile gate and strengthening
justification of the said claim, the Petitioner has submitted that these works were
strikes, dharna and increasing instances of theft etc.. The Petitioner has also
submitted that the turnstile gates have dual authentication with access card as the
first and biometric as the other. It has further stated that Boom barriers, one for entry
road and one for exit road have been constructed and also RFID system has been
81. The Respondent, KSEBL has submitted that expenditure claimed is covered
under the security expenses allowed to the Petitioner, over and above the normative
O&M expenses. In response, the Petitioner has submitted that the plant is spread
over 1116 acres of land and is situated in a region having less employment and is a
stronghold of Maoists, which poses a high security threat to the installations and
workforce of the plant. It has further submitted that since inception, it is continuously
facing a lot of law and order problems like agitation, gate jams, trespassing, thefts by
displaced persons, supported by political outfits and such facts had been observed
by the Intelligence Bureau, GOI in its report dated 10.1.2019. The Petitioner has
added that due to delay in the commissioning of Railway project, owing to Force
Majeure conditions, coal is transported through trucks (about 1200-1600 per day)
and the security staff had to oversee all these along with patrolling and monitoring
which was difficult for them and was prone to human error, due to fatigue.
82. The matter has been considered. Admittedly, the additional capital
expenditures claimed by the Petitioner is beyond the original scope of work of the
project and is after the cut-off date. The Petitioner’s submission that the additional
capitalization has been incurred is on account of Force Majeure events and the
submissions made by the Petitioner do not demonstrate the existence of any force
majeure events. Alternatively, the prayer of the Petitioner to allow the said claim
under Regulation 14(3)(iii) of the 2014 Tariff Regulations is also not acceptable, as
the Petitioner has not furnished any documentary evidence indicating that the
responsible for national/ internal security. In view of this, the additional capitalization
(h) Power Supply redundancy and re-arrangement at BOP area and Augmentation of
Store area
83. The Petitioner has claimed additional capital expenditure of Rs.401.59 lakh in
2016-17 for ‘Power Supply redundancy and re-arrangement at BOP area’ and
Rs.31.74 lakh in 2016-17, Rs.7.58 lakh in 2017-18 and Rs.171.16 lakh in 2018-19
towards ‘Augmentation of Store area’ under Regulation 3(25) read with Regulation
54 of the 2014 Tariff Regulations. In justification of the same, the petitioner has
result of poor planning which is attributable to the Petitioner and, therefore, may not
be allowed and cannot also be classified as a force majeure event. In response, the
Petitioner has submitted that existing overhead line of 11 kV installed for the purpose
of construction supply was being utilized for supplying power to some of the
essential load like gate house complex, field hostel, site office, etc. It has stated that
with passage of time, tripping of these overhead lines had increased because of
movement of coal trucks, which was initially not envisaged and was beyond the
control of the Petitioner. Accordingly, the Petitioner has submitted that the
85. The submissions have been considered. The Petitioner’s submission that the
the same may be allowed in exercise of the power to relax is not acceptable, as the
submissions made by the Petitioner do not indicate the existence of any force
majeure events. In our view, the works executed by the Petitioner are only an
Alternatively, the prayer of the Petitioner to allow the said claim under Regulation
14(3)(iii) of the 2014 Tariff Regulations is also not acceptable, as the Petitioner has
for higher security or safety of plant as advised or is based on the directions of the
internal security. In view of this, the additional capitalization claimed by the Petitioner
86. The Petitioner has claimed additional capital expenditure of Rs.27.21 lakh in
2016-17 for ‘Ash Bagging system’ under Regulation 3(25) read with Regulation 8(3)
and Regulation 54 of the 2014 Tariff Regulations. The Petitioner has submitted that
‘Ash bagging system’ has been installed to facilitate dry fly ash to be packed in the
bags directly from silo discharge points and, thereafter, dry fly ash filled in bags are
transported through rail/ trucks, for onward transportation and utilization. It has
submitted that additional capital expenditure of Rs.27.21 lakh has been incurred in
2016-17 for installation of ‘Ash bagging system’ to optimally utilize the fly ash and
was in compliance of with the directions of JSPCB vide notice dated 17.5.2013.
Accordingly, it has submitted that the additional capitalization may be allowed under
Regulations 14(3)(ii) and 14(3)(iii) read with Regulation 54 of the 2014 Tariff
Regulations.
87. The matter has been considered. The notice dated 17.5.2013 of JSPCB
indicates that the Petitioner is required to comply with the direction of the Board
regarding usage of 100% fly ash. As the additional expenditure incurred was in
compliance with the directions of JSPCB, which is a statutory authority, we allow the
Regulations.
under Regulation 14(3)(ii) of the 2014 Tariff Regulations. In justification of the same,
“(a) That the matter for Upgradation/replacement of old Remote Terminal Unit (RTU) in
Eastern Region for reporting of old RTU/Substation Automation System (SAS) to back
up control center over IEC 60870-5-104 has been discussed in a special Project
review meeting held on 14.2.2017 at Eastern Reginal Power Committee (ERPC), 35th
TCC/ERPC meeting held on 24th / 25th February 2017 and also in 19th SCADA O&M
meeting held on 7.4.2017. As advised by ERPC in 35th TCC/ERPC meeting, detailed
report has been finalized and approved in 36th TCC/ERPC board meeting held on
13th/ 14th September 2017 at Bhubaneshwar. In view of above direction of
ERLDC/ERPC, the Petitioner was mandated to upgrade the RTU system and seek
additional license from OEM for enabling existing RTUs for reporting over IEC 104
protocol to Main as well as back-up Control Centre of ERLDC. Therefore, the
Petitioner prays to the Commission to consider the circumstances as under
compliance of existing law and allow capitalization under this head. The expenditure
incurred therefore squarely falls within the scope of Regulation 14 (3)(ii) of 2014 Tariff
Regulations.”
89. Since the total additional capitalization of Rs.48.75 lakh (Rs.1.45 lakh and
Rs.47.30 lakh) for up-gradation of RTU or protection system has been based on
discussions in various ERPC meetings and has been incurred by the Petitioner in
system, we allow the same under Regulation 14 (3)(ii) of 2014 Tariff Regulations.
90. The Petitioner has claimed additional capitalization of Rs.67.09 lakh in 2017-
18 and Rs.103.67 lakh in 2018-19 for ‘Safety related expenditure’ (i.e. scaffolding for
Regulations provides for admissibility of expenditure for higher security and safety,
responsible for national/ internal security. As the Petitioner has not demonstrated
91. The Petitioner has claimed additional capitalisation of Rs.321.88 lakh in 2018-
19 towards Coal Pit Run-off mechanised Drainage system, under Regulation 3(25)
read with Regulation 54 of the 2014 Tariff Regulations. In justification of the same,
(i) The three runoff pits near Stacker Reclaimer, track hopper and crusher house
are provided to store internal drainage. Any spill over from these pits are stored in
another runoff pit located near main entrance gate on the western side of the Plant.
Topography of the northern area outside and near the plant is such that runoff of this
area enters the plant campus, travels around 200 m inside plant and thereupon goes
outside the plant through western side of the Plant. During heavy rainy seasons, such
storm water enters the plant coal handling area carrying coal dust with it and gets
mixed with the runoff pit near gate. In an event of spill over due to flooding of pit, the
outflow of this pit crosses the Nirsa-Jamtara road through a culvert and finds its way to
Rani Talab due to natural slope of the area. The accumulation of the runoff water was
also causing failure of the wall. Many villagers started agitation on the belief that the
Petitioner is discharging contaminated process water from the plant to the outside
environment. Letter from village community leader to the Petitioner complaining
regarding discharge of contaminated water (which actually is rainwater) is annexed;
(ii) Based on the experience of flooding of the storm water drain with the coal
handling area runoff water during the monsoon season, the Petitioner reviewed the
existing drains to arrive at a long-term solution to avoid flooding under all rainfall
conditions. It was, therefore, decided that the storm water drains from outside plant
boundary be diverted along the northern boundary preventing mixing with the internal
drainage water or flooding the pit located near main entrance gate and ultimately to be
discharged into the culvert on Nirsa-Jamtara road beyond the boundary wall. This way
the excess water from outside the plant boundary will not flood the run-off pit 2 near
main gate and only clean water would be diverted outside the plant, which shall
address the concern raised by villagers as stated above. Accordingly, the scheme was
conceptualized and proper drainage system was constructed for its natural flow
without any contamination outside the plant. However, the construction work beyond
the Petitioner’s boundary was forcefully stopped by the local community and their
leaders as they were still of the belief that diverted water would be/may be
contaminated, through an agitation on 18.6.2018 disrupting plant operation and supply
of coal. A True Copy of newspaper cutting in this regard is annexed;
(iii) Though all the efforts have been made by the Petitioner to explain the local
community leaders, but the Petitioner was not permitted to carry out the work of
extending the drainage system into the culvert on Nirsa-Jamtara Road. Accordingly,
the Petitioner vide its Letter dated 17.8.2018 apprised Sub-Divisional Officer (SDO)
Dhanbad about the Scheme undertaken for addressing the concern raised by
neighbouring community, however, due to agitation by the community leaders on
18.6.2018 the same was stopped. In view of above developments, it was, therefore,
further decided to have alternative disposal methodology for the coal area runoff water
during the monsoon season. Under this Project, it has been decided to divert the
(a) Construction of the drainage system for natural flow of storm water entering
through northern area near the plant and preventing it from mixing with the
contaminated water;
(b) To divert Coal run off disposal into Ash pond (during monsoon season)
through a pumping and piping arrangement;
(c) To contain the coal dust mixed run off water within coal storage area.
92. The Petitioner has submitted that the additional capital expenditure claimed
was incurred due to circumstances, which were unforeseen and beyond the control
of the Petitioner and the same was neither anticipated nor could have been avoided
through any prudent utility practice. Accordingly, the Petitioner has prayed that the
Commission may allow the additional capital expenditure under this scheme in
exercise of the power under Regulation 54 of the 2014 Tariff Regulations. The
Petitioner has also submitted that in addition to the additional expenditure incurred
for 2018-19 as above, an expenditure of Rs.400 lakh for balance work is envisaged
93. The Respondent, KSEBL has submitted that the expenditure incurred by the
Petitioner is due to poor planning and is, therefore, attributable to the Petitioner. It
has also stated that claim is not in line with provisions of the 2014 Tariff Regulations
and is not on account of any force majeure event. The Petitioner in its rejoinder has
submitted that the storm water used to mix with coal dust and run-off pit near the
gate and in event of flooding of the pit, the outflow of this used to flow in the Rani
Talab due to natural slope of the area leading to widespread resistance from the
villagers along with their political leaders. Accordingly, the Petitioner has submitted
94. The matter has been examined. It is observed from the submissions and the
documents enclosed that the Petitioner was required to undertake the construction of
community as the contaminated storm water from the plant area during monsoon
season was overflowing to the natural reservoir (Rani Talab) located in a nearby
Petitioner indicate that the expenditure incurred was necessary due to unforeseen
conditions, which could not be apprehended during the construction stage of the
plant. We note that Regulation 3(25) of the 2014 Tariff Regulations defines ‘Force
Majeure’ conditions which prevent the timely completion of the project and as such,
the expenditure is not covered under Regulation 3(25) as the plant is in operational
stage. However, considering the fact that the said expenditure was necessitated to
95. The Petitioner has claimed additional capitalisation of Rs.700.13 lakh in 2017-
under Regulation 3(25) read with Regulation 54 of the 2014 Tariff Regulations. The
Petitioner has also submitted that the additional expenditure claimed is covered
within the scope of Regulation 14(3)(ii) of the 2014 Tariff Regulations. The Petitioner
has submitted that the additional capitalization claimed is beyond the original scope
of work of the project and has been incurred due to “force majeure” events which
a) The Petitioner has been facing acute operational and maintenance issues
in its ‘Ash handling system’, primarily on account of combined effect of (i)
significantly higher volume of ash generated than design capacity (ii) higher
ash particle size and bulk density compared to design and (iii) Lower GCV
leading to higher quantity of coal consumption and in turn increasing the
effect of (i) and (ii) above.
b) The problems are mainly attributable to the poor quality of the coal received
from various sources of Central Coalfield Limited and its subsidiaries. The
coal received at the plant contains much higher ash than anticipated since
its inception.
c) High quantity and coarser quality of ash posed pressure on the existing ash
disposal system in proper handling of both fly ash and bottom ash leading
to frequent leakages in ash conveying pipelines, thereby causing higher
dust in environment and faster filling of limited capacity ash pond. In fact,
there were specific directions from JSPCB for reduction of fugitive dust
around ash pond and fly ash silo area in their letter dated 5.07.2016.
96. In view of the above submissions and since the additional capital expenditure
incurred is based on the directions of JSPCB vide its letter dated 5.7.2016, the
97. The Petitioner has claimed additional capitalization of Rs.10.07 lakh in 2017-
18 and Rs.13.16 lakh in 2018-19 towards ‘Drinking water facility’ under Regulation
14(3)(ii) of the 2014 Tariff Regulations. In justification of the same, the Petitioner has
submitted that Chapter III Section 41(d) of the Bihar Factories Rules, 1950 read with
the Factories Act, 1948, as adopted by the State of Jharkhand, requires that ‘the
number of water centres to be provided shall be one ‘centre’ for every 150 persons
employed at any one time in the factory’. According to this Rule, the number of
drinking water centre should be one, for every 150 persons employed at any given
time in the factory. The Petitioner has submitted that since many of the worker’s
concentration areas were more than ‘150 per centre’ unless the workers travel to
farther water centres. Therefore, the Petitioner has submitted that in order to reduce
the overall travel time and in order to comply with the said Rule, it was decided to
add drinking water facilities in three additional locations of the plant area viz., CHP
area, Ash pond area and Coal weighbridge, which was concentrated with maximum
Regulations.
98. In consideration of the submissions of the Petitioner and keeping in view that
the said additional expenditure incurred is for compliance with the provisions of the
existing law i.e. the Bihar Factory Rules, 1950, we allow the additional capitalization
99. The Petitioner has also claimed additional capitalization of Rs.49.69 lakh in
Rs.192.79 lakh in 2017-18 and Rs.16.08 lakh in 2018-19 for Labour Colony,
Rs.160.29 lakh in 2017-18 and Rs.78.23 lakh in 2018-19 for Re-heater Modification
& MTM installation, Rs.80.41 lakh in 2017-18 for ‘Augmentation of Fire detection
system’ and Rs.31.98 lakh in 2017-18 for ‘Refurbishment of DM Plant Piping and
incurred on the ground of force majeure events and has accordingly prayed that the
claim may be allowed under Regulation 3(25) read with Regulation 54 of the 2014
Tariff Regulations.
additional capital expenditure is in respect of the assets/ works which do not form
part of the original scope of work of the project and is after the cut-off date. It is
observed that the works executed by the Petitioner are related to extension/ re-
Petitioner has also not justified the nature of the ‘force majeure’ events which
view of this, we find no reason to exercise the power to relax the provisions of the
101. In view of the above discussions, the actual additional capital expenditure
(Rs. in lakh)
Sl. Package Name 2014-15 2015-16 2016-17 2017-18 2018-19
No.
1 BTG 730.69 777.30 0.00 0.00 0.00
2 Cost of Land and Site 21142.23 69.98 0.40 0.00 2112.86
3 General Civil Works 10577.92 791.99 184.39 154.47 147.49
4 Plant Water System 252.36 0.00 0.00 0.00 0.00
5 Ash Handling System 48.65 26.23 0.00 0.00 0.00
6 Coal Handling System 1042.53 282.72 0.00 0.00 0.00
7 Balance of Plant 18.21 445.57 0.00 0.00 0.00
8 Township & Colony 57.12 43.38 0.00 0.00 0.00
9 Pre-Operative expenses 207.87 0.00 0.00 0.00 0.00
10 IT system for Software & 457.52 0.00 0.00 0.00 0.00
Hardware
11 RO system 0.00 7798.20 (-) 28.04 57.38 0.00
12 Fire Tender with shed 0.00 61.53 0.60 14.47 1.30
13 Fixed Foam System for LDO & 0.00 60.74 0.00 0.00 0.00
HFO
14 Construction of Road in Ash 0.00 0.00 80.29 18.15 0.00
area
15 NABL Accredited Lab 0.00 70.52 112.96 5.62 55.18
16 Yard Sprinkling & Fire 0.00 0.00 0.00 0.00 18.91
detection system in CHP
17 Up-gradation of Protection 0.00 0.00 0.00 1.45 47.30
System
102. The Petitioner has included IDC capitalized in books, excluding Railways, in
the additional capitalization as per Form 9A. However, the same has been deducted
by the Petitioner in Form 1(I) while claiming capital cost for tariff.
103. Accordingly, the net additional capitalization allowed after considering the de-
capitalization/ deduction and before adjustment of liabilities and IDC as per books, is
as under:
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
A Total additions allowed 34679.91 11705.92 481.12 1400.60 3596.05
B Less: De-capitalization allowed 3214.56 131.14 69.61 132.63 81.37
C Less: De- capitalization not 0.00 96.56 192.54 717.48 350.46
performed in books.
D Less: Cash capitalization 5506.76 0.00 0.00 0.00 0.00
towards land
E Total Deductions 8721.32 227.70 262.15 850.11 431.83
F Net additional capitalization 25958.59 11478.22 218.97 550.49 3164.22
allowed before adjustment
of liabilities and IDC as per
books (A-E)
104. The net additional capital expenditure allowed after adjustment of un-
105. The Petitioner, vide Form-1 of the petition, has claimed the following amounts
of normative Interest during Construction (IDC) on excess equity and on actual loan
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19 Total
Normative IDC on excess 62.39 199.52 41.00 192.37 429.04 924.32
equity
Normative IDC on actual loan 2672.02 485.50 69.39 200.82 230.48 3658.21
provide as below:
the judgment of APTEL dated 3.10.2019 in Appeal No. 231/2017 (Power links
Transmission Limited V CERC & ors). The Petitioner has submitted that the entire
equity and no actual loan was/is proposed to be taken for such expenditure. Since
70% of such internal funds, which are in excess of 30% normative equity, are treated
as normative loan for the purpose of tariff determination under the 2014 and 2019
Tariff Regulations, interest on excess over 30% out of total internal funds before
108. It is observed that the Commission in its order dated 20.4.2017 in Petition No.
514/TT/2014 (Powerlinks Transmission Ltd v PGCIL & ors) had disallowed normative
disallowance of normative IDC, Powerlinks Transmission Ltd. had filed Appeal No.
231 of 2017 before the Appellate Tribunal for Electricity (in short ‘APTEL’) with the
prayer to allow normative IDC on normative loan, considered for funding the
additional capitalization for the 2014-19 tariff period. APTEL vide its judgment dated
“8 (ix) The Central Commission should have taken into consideration the aspect that
whatever be the types of funds it is never free of cost. There is always a cost of
funding. The argument that no actual loan for additional capital expenditure was
taken and therefore it is not admissible for any normative IDC is wrong. It is the
commercial decision of the Appellant whether to borrow the money from the market
for the purpose of additional capitalisation or use its internal accruals. In either case,
the capitalisation deserves to be given the Interest During Construction. For the
simple reasons that if the internal accruals were not to be used as additional capital
than it would have been invested in the market in any interest earning instrument.
Additional capitalisation is therefore entitled to be compensated in terms of normative
IDC. The Central Commission should have considered this aspect that no funds are
free funds.”
APTEL in Powerlinks case, has computed the normative IDC on 70% of the average
funds deployed during the year for the additional capitalization claimed. The
i. The Petitioner has first computed the opening and closing amounts of
Capital Works In Progress (CWIP) actually incurred in cash (cash CWIP)
by subtracting Un-discharged liabilities from CWIP amounts on
corresponding dates. Similarly, cash additional capitalization has been
simply referred to as additional capitalization for this purpose.
ii. Since the closing amount of CWIP during a financial year is obtained after
subtracting additional capitalisation during the year, CWIP schedule
during the year is considered as the sum of CWIP schedule obtained by
opening and closing amounts of CWIP and that for additional
capitalisation;
iii. While CWIP schedule obtained by opening and closing amounts of CWIP
is assumed to increase or decrease linearly from opening to closing
amounts, the CWIP schedule for additional capitalisation is assumed to
increase linearly from zero in the beginning to the amount of additional
capitalisation in the mid of the year;
iv. The said assumption is based on the fact that the Commission considers
average of opening and closing GFA i.e. additional capitalisation at the
mid of the year, for the purposes of computing equity, loan and
depreciation. Hence, for capitalisation to take place in mid of the year,
entire CWIP for that capitalisation must have been incurred up to mid of
the year.
i. Average CWIP has been obtained as sum of (a) average of opening and
closing CWIP for entire year (opening CWIP + closing CWIP)/2 and (b)
ii. The Petitioner has then considered excess equity of CWIP in a financial
year as the normative loan during that year and normative IDC has been
computed on average normative loan at Weighted Average Rate of
Interest on long term loan for that year;
iii. Therefore, total normative IDC has been computed as sum of IDC on
excess equity of average additional capitalisation and IDC on excess
equity of average of opening and closing amounts of CWIP.
iii. In case, the opening CWIP is more than additional capitalisation during
the year, additional capitalisation is done from the opening CWIP and
normative IDC to be capitalised for half year would be 70% x additional
capitalisation x 0.5:
110. The Petitioner has prayed for approval of the above methodology for
computation of normative IDC and to include the same in the additional capitalization
capitalized during the 2019-24 period. The Petitioner has also submitted the
CWIP.
Petitioner has neither submitted the normative IDC, duly certified by Auditors, nor the
interest rates etc. and their supporting documents, if any. Hence, in the absence of
the aforesaid information, we have worked out the normative IDC based on
assumptions as follows:
b. Date of capitalisation has been assumed to be at the mid of the year; and
c. Weighted Average Rate of Interest (WAROI) on actual loan of respective
years have been applied for calculation of normative IDC of respective years
112. The normative IDC on additional capital expenditure has been worked out by
applying WAROI on actual loan of the particular year on the average normative loan
for the respective year, applied for half of the year of the time span. Accordingly, the
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
760.89 221.46 9.60 24.59 55.34
Discharge of liabilities
113. The Petitioner has claimed discharge of liabilities for the 2014-19 tariff period
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
4589.39 319.17 (-) 107.27 179.21 0.00
114. In compliance to the directions of the Commission vide ROP of the hearing
dated 2.6.2020, the Petitioner vide affidavit dated 20.6.2020, has furnished the
statement of reconciliation, with regard to un-discharged liabilities for each year and
accrual basis, instead of cash basis. In Form 18 (Liability flow statement) also, the
since the additional capitalization is allowed on cash basis, the liabilities included in
the additional capital expenditure as per Form 9A, has been deducted from the
liabilities) have been worked out on the basis of the information furnished in Form 9A
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Opening un-discharged liabilities as
4980.50 391.10 71.03 162.07 0.00
per Form 1(I) and Form 18
Add: Additions as per Form-9A 391.10 71.03 163.06 0.00 0.00
Less: Closing un-discharged liabilities
391.10 71.03 162.07 0.00 0.00
as per Form 1(I) and Form 18
Discharge of liabilities allowed 4980.50 391.10 72.03 162.07 0.00
116. Based on the above, the capital cost allowed for the 2014-19 tariff period is
summarized as under.
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Opening capital cost 432039.88 463204.76 474874.98 475012.53 475749.68
Add: Net additional
capitalisation allowed 25567.49 11407.19 55.91 550.49 3164.22
on cash basis
Add: Discharges
4980.50 391.10 72.03 162.07 0.00
allowed
Normative IDC allowed 760.89 221.46 9.60 24.59 55.34
Less: IDC Capitalised
in Books excluding 144.00 349.53 0.00 0.00 0.00
Railways
Closing capital cost 463204.76 474874.98 475012.53 475749.68 478969.24
Debt-Equity Ratio
“(1) For a project declared under commercial operation on or after 1.4.2014 the debt
equity ratio would be considered as 70:30 as on COD. If the equity actually deployed
118. Accordingly, the debt-equity ratio of 70:30 has been considered for the
119. The Petitioner has also claimed additional tax arisen on account of
amendments in the Finance Act, 2017 to be recovered separately over and above
the annual fixed charges as per the ‘Change in law’ provisions. In this regard, the
The above enactments/ amendments in the Income Tax Act squarely fall under the
ambit of Change in Law as per Regulation 3 (9)(a) and (b) and are required to be
factored in the True-up of Annual Fixed Charges for the tariff period FY 2014-19 as per
Regulation 8(5)(ii) of CERC Tariff Regulations 2014 being a totally uncontrollable factor
and beyond the control of the Petitioner. Similar provisions also exist in CERC Tariff
Regulations 2019 and, hence, same relief is available to the Petitioner during the tariff
period 2019-24. In case of the Petitioner, MAT has been applicable during FY 2014-19
and is also expected to be applicable during FY 2019-24 and the book profit and tax
liability thereon has increased due to the said Change in Law. Thus, the Petitioner is
entitled to recovery of Additional Tax payable due to this Change in Law for the
applicable FYs 2016-17, 2017-18, 2018-19 in the tariff period FY 2014-19 and for FYs
2019-20 and 2020-21 in the tariff period FY 2019-24. Accordingly, it is humbly
submitted to the Hon’ble Commission to kindly consider the following
enactments/amendments as Change in Law under the CERC Tariff Regulations 2014:
a. the notification of Companies (Indian Accounting Standards) Rules, 2015 and
b. amendment of Section 115JB of the Income tax Act, 1961 under Finance Act, 2017
in order to incorporate provisions w.r.t Ind AS compliant companies
Further, as the basic principle of Change in Law is the principle of restitution i.e. to
bring back the Petitioner to same economic position as it would have been had
Change in Law not taken place, the Petitioner proposes to recover this additional tax
separately over and above the Annual Fixed Charges as per the provisions of the
regulations other than Change in Law provisions and not as part of Annual Fixed
Charges. This will also avoid unwarranted increase in Interest on Working Capital that
are linked to Annual Fixed Charges. However, since this additional tax recovery adds
to book profit and attracts further tax on it, the net recovery would not fully compensate
the Petitioner for increased tax. Therefore, in order to place the Petitioner back to the
same economic position, this additional tax recovery needs to be grossed up by the
applicable MAT rate for the relevant year and allowed to be recovered separately from
the beneficiaries.”
120. We have examined the matter. As regards the recovery of additional tax
Regulations provide for tax recovery by way of grossing up of Return on Equity with
the effective tax rate or Minimum Alternate Tax (MAT) in case of a generating
company or a transmission licensee, as the case may be, paying MAT of the
being allowed for grossing up with the MAT rate, as envisaged under the provisions
of the 2014 Tariff Regulations. It is further observed that the implementation of Ind-
AS has an accounting treatment implication and does not result in income from
generation business activity. Accordingly, the prayer of the Petitioner to allow the
Return on Equity
(3) The generating company or the transmission licensee as the case may be shall
true up the grossed up rate of return on equity at the end of every financial year
based on actual tax paid together with any additional tax demand including interest
thereon duly adjusted for any refund of tax including interest received from the
income tax authorities pertaining to the tariff period 2014-15 to 2018-19 on actual
gross income of any financial year. However, penalty if any arising on account of
delay in deposit or short deposit of tax amount shall not be claimed by the generating
company or the transmission licensee as the case may be. Any under-recovery or
over recovery of grossed up rate on return on equity after truing up shall be
recovered or refunded to beneficiaries or the long-term transmission customers/DICs
as the case may be on year to year basis.”
122. The Commission in its order dated 1.10.2019 in Petition No.152/GT/2015 had
only the capital cost of Rs.432039.88 lakh as on 1.4.2014 has been allowed as
against the capital cost of Rs.432490.69 lakh allowed vide Commission’s order dated
1.10.2019 in Petition No.152/GT/2015, the opening equity has also been adjusted to
Rs.129611.96 lakh for the 2014-19 tariff period. The Petitioner has claimed MAT
been considered for the purpose of tariff. Accordingly, ROE has been worked out
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Gross Notional Equity 129611.96 138961.43 142462.50 142503.76 142724.90
Addition due to
9349.47 3501.07 41.26 221.15 965.87
Additional Capitalization
Closing Equity 138961.43 142462.50 142503.76 142724.90 143690.77
Average Equity 134286.70 140711.96 142483.13 142614.33 143207.84
Return on Equity
15.500% 15.500% 15.500% 15.500% 15.500%
(Base Rate )
Tax rate for the year 20.9605% 21.3416% 21.3416% 21.3416% 21.5488%
Rate of Return on
19.610% 19.705% 19.705% 19.705% 19.758%
Equity (Pre Tax )
Return on Equity 26333.62 27727.29 28076.30 28102.15 28295.00
Interest on loan
124. The Petitioner has re-financed the long-term loan to reduce the interest
loan, the Petitioner has considered interest rate of original loan, and not the new rate
after refinancing. The Petitioner has submitted that in case of refinancing, the
application of Regulation 26(5) of the 2014 Tariff Regulations would require the
computation of ‘weighted average rate of interest’ using the actual loan portfolio/
schedule, along with interest rate that would have been applicable for original loan
term. In our view, Regulation 26(5) of the 2014 Tariff Regulations provides that the
weighted average rate should be calculated on the basis of actual loan portfolio,
which implies the consideration of the ‘existing loan’ portfolio. As such, the applicable
rate is the rate after such refinancing of loan. This was decided by the Commission
while working out the interest on normative loan in order dated 26.12.2017 in Petition
the Petitioner, is not allowed. The Petitioner, in compliance with the directions of the
Commission vide ROP dated 2.6.2020, has, vide affidavit dated 20.6.2020,
iii) Accordingly, the net normative opening loan as on 1.4.2014 works out to Rs.
255263.57 lakh;
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Gross Notional loan 302427.92 324243.34 332412.49 332508.77 333024.77
Cumulative Repayment of
47164.35 69464.84 93120.51 117005.07 140722.28
Loan up to previous year
Net Opening loan 255263.57 254778.50 239291.98 215503.70 192302.49
Addition due to additional
21815.42 8169.15 96.28 516.01 2253.69
capitalisation
Repayment of loan during 22785.93 23700.34 23949.17 23969.12 24160.20
the period
Less: Repayment
adjustment on account of 485.44 44.67 64.61 251.90 148.66
de-capitalization
Net Repayment 22300.49 23655.67 23884.56 23717.21 24011.55
Net Closing loan 254778.50 239291.98 215503.70 192302.49 170544.64
Average loan 255021.03 247035.24 227397.84 203903.10 181423.57
Weighted Average Rate of 10.96% 10.46% 9.92% 8.99% 8.79%
Interest on loan
Interest on loan 27957.86 25842.46 22561.92 18331.74 15953.23
126. The Petitioner has refinanced the loan which has resulted in substantial
benefits to the respondents on account of lower interest rates. The costs associated
refinancing shall be calculated and shared between the beneficiaries and petitioner
in the ratio of 2:1 in terms of Regulations 26(7), 26(8) and 26(9) of the 2014 Tariff
Regulations.
Depreciation
“27. Depreciation:
(1) Depreciation shall be computed from the date of commercial operation of a
generating station or unit thereof or a transmission system including communication
system or element thereof. In case of the tariff of all the units of a generating station
or all elements of a transmission system including communication system for which a
single tariff needs to be determined the depreciation shall be computed from the
effective date of commercial operation of the generating station or the transmission
system taking into consideration the depreciation of individual units or elements
thereof.
Provided that effective date of commercial operation shall be worked out by
considering the actual date of commercial operation and installed capacity of all the
units of the generating station or capital cost of all elements of the transmission
system for which single tariff needs to be determined.
(2) The value base for the purpose of depreciation shall be the capital cost of the
asset admitted by the Commission. In case of multiple units of a generating station or
multiple elements of transmission system weighted average life for the generating
station of the transmission system shall be applied. Depreciation shall be chargeable
from the first year of commercial operation. In case of commercial operation of the
asset for part of the year depreciation shall be charged on pro rata basis.
(3) The salvage value of the asset shall be considered as 10% and depreciation shall
be allowed up to maximum of 90% of the capital cost of the asset:
Provided that in case of hydro generating station the salvage value shall be as
provided in the agreement signed by the developers with the State Government for
development of the Plant:
Provided further that the capital cost of the assets of the hydro generating station for
the purpose of computation of depreciated value shall correspond to the percentage
of sale of electricity under long-term power purchase agreement at regulated tariff:
Provided also that any depreciation disallowed on account of lower availability of the
generating station or generating unit or transmission system as the case may be
shall not be allowed to be recovered at a later stage during the useful life and the
extended life.
(4) Land other than the land held under lease and the land for reservoir in case of
hydro generating station shall not be a depreciable asset and its cost shall be
excluded from the capital cost while computing depreciable value of the asset.
128. As regards the weighted average rate of depreciation used for the
computation of the depreciation claimed, the Petitioner has submitted that the same
accounts. The Petitioner has further submitted that as per accounting policy of the
Petitioner, depreciation on fixed assets is provided on pro rata basis from the month
in which the asset is available for use, on straight line method, at the rate and
applicable to Petitioner from 2016-17 with comparative period of one year viz. 2015-
16), the leasehold land, which was earlier considered as part of the gross block and
amortized over the license period. In this context, adjustment to this extent is made
in the books of accounts. The Petitioner has submitted that though the 2014 Tariff
Regulations provide for specific depreciation rate for lease-hold land, consequent
upon adoption of Ind-AS by the Petitioner, the treatment of leasehold land has
changed in the books of accounts. Therefore, the Petitioner, in the present petition,
has claimed depreciation against leasehold land, based on the actual amortization
130. The matter has been examined. It is observed that the Petitioner has claimed
depreciation based on the weighted average rate of depreciation, as per the books of
accounts. In terms of Regulation 27(5) of the 2014 Tariff Regulations, the rates
generating station are required to be used for arriving at the weighted average rate
by the Petitioner has not been considered and the rates specified in Appendix-II of
the 2014 Tariff Regulations have been considered for the computation of
131. Accordingly, depreciation allowed for the 2014-19 tariff period is as under:
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Opening Gross Block
432039.88 463204.76 474874.98 475012.53 475749.68
(A)
Addition due to
Additional 31164.88 11670.22 137.54 737.15 3219.56
Capitalisation (B)
132. The Petitioner has submitted that in the events where de-capitalization of
assets have to be carried out in the initial years of useful life of assets, there would
be significant loan outstanding on account of such assets which will necessarily have
to be serviced till end of loan tenure. It has stated that post de-capitalization, since
neither depreciation nor interest is available on such assets, the actual loan
outstanding for such assets will have to be serviced from revenue allowed for
and under-recovery, as it falls short of the revenue required for meeting expenses
which are already approved by the Commission. The Petitioner has also submitted
that the circumstances which lead to such shortfall are entirely beyond the control of
the Petitioner and for force majeure conditions. The Petitioner has further submitted
that as per Ind AS 16, along with de-recognition/ de-capitalization of replaced assets,
the Petitioner is required to book the gain or loss arising out of de-recognition in its
accounts. The Petitioner has added that while the 2014 Tariff Regulations and the
corresponding regulation for considering the gain or loss due to such replacement for
not recovering the normative depreciation @90%. In view of the above, the Petitioner
has requested that the Commission may allow the recovery of unrecovered
recovered till date of de-capitalization) to compensate for the losses which it may
incur in books of accounts, in exercise of the ‘Power to Relax’ and ‘Power to Remove
Difficulty’ under the 2014 Tariff Regulations. The Petitioner has also proposed to
depreciation, over and above the specified norms under the 2014 Tariff Regulations.
The claim of the Petitioner for unrecovered depreciation during the 2014-19 tariff
period is as under:
(Rs. in lakh)
2015 2016 2017 2018 2019 Total
160.00 137.00 158.00 482.00 213.00 1150.00
133. We have examined the matter. It is observed that the 2014 Tariff Regulations
provides for servicing of the funds infused in the admitted capitalised expenditure, by
way of allowing ROE and Interest on loan capital as components of the annual fixed
charges for the assets put in use. The equity and loan component for this purpose
Thus, the said regulation provides for servicing the debt capital in the form of
‘Interest on loan’ on the amount of loan arrived at, by applying the debt-equity ratio
on the capital cost allowed and not on the ‘actual loan’ being serviced through tariff.
The capital cost has been allowed after necessary adjustment for the
repayment of loan, instead of the ‘actual loan repayment’, the depreciation allowed
for the corresponding year/ period is considered as repayment of loan and the same
is in line with Regulation 26(3) of the 2014 Tariff Regulations, which is extracted
below:
“26(3) The repayment for each of the year of the tariff period 2014-19 shall be deemed
to be equal to the depreciation allowed for the corresponding year/ period.”
134. Accordingly, the prayer of the Petitioner to allow the recovery of unrecovered
depreciation (in respect of assets not in use) is not allowed as the same is not in
O & M Expenses
135. The total O&M expenses claimed by the Petitioner for the 2014-19 tariff period
is as under:
(Rs. in lakh)
Items / Heads 2014-15 2015-16 2016-17 2017-18 2018-19
Normative O&M expenses as 16800.00 17860.50 18984.00 20181.00 21451.50
per Regulation 29(1)(a) of the
2014 Tariff Regulations
Water charges as per 946.18 996.05 993.31 965.52 930.54
Regulation 29(2) of the
2014 Tariff Regulations
Capital spares as per 0.00 0.00 58.34 53.52 10.45
Regulation 29(2)
Rental &Conveyance 100.35 76.08 57.61 74.98 51.19
expenses in lieu of 2nd
township
Total O&M Expenses 17846.53 18932.63 20093.26 21275.02 22443.68
29(1)(a) of the 2014 Tariff Regulations are the same as allowed vide order dated
Regulations is allowed.
Water Charges
138. The Commission, in order dated 26.12.2017 in Petition No. 152/GT/2015, had
allowed Water charges under Regulation 29(2) of the 2014 Tariff Regulations, based
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
946.18 946.18 946.18 946.18 946.18
139. The Petitioner, in this petition, has claimed water charges based on the
audited actual water charges for the 2014-19 tariff period, in terms of Regulation
29(1)(b) of the 2014 Tariff Regulations. The Petitioner has furnished the details of
actual water consumption, water charge rates and water cess for each year. The
140. As stated, the Water charges allowed vide order dated 26.12.2017 in Petition
No.152/GT/2015 were based on the water charges incurred for 2014-15 and the
same was subject to revision, at the time of truing up of tariff, based on the actual
water charges paid by the Petitioner for the 2014-19 tariff period. The Petitioner has
Capital Spares
141. As regards the claim of the Petitioner for ‘capital spares’ in terms of
Regulation 29(2) of the 2014 Tariff Regulations, the Commission, in order dated
26.12.2017 in Petition No.152/GT/2015 had observed that the claim of the Petitioner,
tariff. The Petitioner, in the present petition, has claimed the following capital spares,
based on audited actual capital spares consumed during the 2014-19 tariff period:
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Spare Circuit Breaker for MV & 0.00 0.00 18.96 0.00 7.18
LV Switchgear (BTG & main)
Spare Motors for 0.00 0.00 39.38 16.36 0.90
(BTG, RWP & AHP)
TDBFP Recirculation valve 0.00 0.00 0.00 27.61 2.37
Boiler Tubes 0.00 0.00 0.00 9.55 0.00
Total 0.00 0.00 58.34 53.52 10.45
142. In support of the said claim, the Petitioner has submitted the following:
(a) Spare Circuit Breaker for MV & LV Switch gear (BTG & main)
Spare Circuit Breaker for MV & LV switch gear was needed to be procured for
running the plant without any generation loss or to minimize the duration of
generation loss in case of any breakdown. Since these circuit breakers have a lead
time of delivery, the same is needed to be procured and maintained as capital
spares. While procurement of these spares, it was found that GE has stopped
manufacturing these circuit breakers, hence, different make compatible circuit
breaker was procured as spare. The capital expenditure for Spare Circuit Breaker for
(b) Spare Motors (comprising of 500 KW Motor for Raw Water Pump, 500 KW
Motor for Conveying Air Compressor for Ash Handling Plant, 350 KW Motor for
Auxiliary Cooling Water pump):
As per existing configuration, 3 number of raw water pump motors, 6 number of
conveying air compressor motors for ash evacuation and 4 No of auxiliary cooling
water pump motors are in service. These are critical 6.6 KV motors and were not
having initial spares. Hence, new spare motors were procured and are used on
rotation basis to overhaul present motors in case of any breakdown. For overhauling,
these motors are required to be sent to vendor facilities as overhauling within the
Plant was not so effective. In view of foregoing, procurement of above motors was
carried out. The capital expenditure for these Spare Motors, therefore, may kindly be
approved by the Commission as Capital Spare in terms of the 2014 Tariff
Regulations.
143. In terms of Regulation 29(2) of the 2014 Tariff Regulations, the actual
expenses incurred by the Petitioner towards capital spares consumed are admissible
as additional O&M expenses. The Petitioner has certified that the capital spares
Allowance in terms of the 2014 Tariff Regulations or has been claimed as part of
Moreover, the cost of the capital spares claimed by the Petitioner has been excluded
from the ‘gross capital cost’ under the head ‘exclusion’ in the additional capitalization
of spares. It is pertinent to mention that the term ‘capital spares’ has not been
defined in the 2014 Tariff Regulations. The term capital spares, in our view, is a
for use in the event that a similar piece of critical equipment fails or must be rebuilt.
respect of earmarking and treatment of capital spares, the value of capital spares
exceeding Rs.1 (one) lakh, on prudence check of the details furnished by the
Petitioner in Form-17 of the petition, has been considered for the purpose of tariff.
Further, we are of the view that spares do have a salvage value. Accordingly, in line
with the practice of considering the salvage value, presumed to be recovered by the
value of 10% has been deducted from the cost of capital spares considered above,
for the 2014-19 tariff period. Therefore, on prudence check of the information
furnished by the Petitioner in Form-17 and on applying the said ceiling limit along
with deduction of the salvage value @10%, the net capital spares allowed in terms of
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Spare Circuit Breaker for MV & LV 0.00 0.00 18.96 0.00 7.18
Switchgear (BTG & main)
Spare Motors for (BTG, RWP & AHP) 0.00 0.00 39.38 16.36 0.00
TDBFP Recirculation valve 0.00 0.00 0.00 27.61 2.37
Boiler Tubes* 0.00 0.00 0.00 0.00 0.00
Total before salvage value 0.00 0.00 58.34 43.97 9.55
Less: Salvage value @10% 0.00 0.00 5.83 4.40 0.96
Total capital spares allowed 0.00 0.00 52.51 39.57 8.59
144. Accordingly, the total O&M expenses allowed in terms of the 2014 Tariff
(Rs in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Normative O&M Expenses 16800.00 17860.50 18984.00 20181.00 21451.50
as per Regulation 29(1)(a)
of the 2014 Tariff
Regulations
Water Charges as per 946.18 996.05 993.31 965.52 930.54
Regulation 29(2) of the
2014 Tariff Regulations
Capital Spares as per 0.00 0.00 52.51 39.57 8.59
Regulation 29(2) of the
2014 Tariff Regulations
Total O&M expenses 17746.18 18856.55 20029.82 21186.09 22390.63
allowed as per Regulation
29 of the 2014 Tariff
Regulations
145. The Petitioner has claimed the following additional O&M expenses in lieu of
2nd Township:
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Rental Charges (a) 123.40 90.88 54.27 74.15 67.52
HRA deduction from employee (b) 78.19 67.34 62.58 65.80 75.11
Conveyance Charges (c) 55.15 52.55 65.92 66.63 58.79
Total - (a-b+c) 100.35 76.08 57.61 74.98 51.19
146. In support of the aforesaid claims, the Petitioner has submitted the following:
(a) MPL had planned to construct the second phase of the Township to
accommodate the balance employees after phase I. Due to unavailability of land in
the adjoining area of the existing township, the Petitioner made efforts to locate
suitable Land in nearby location to facilitate the above purpose. Through letter dated
25.11.2011, it had approached DVC for additional allocation of 30000 m2 of land in
the plot adjacent to the phase-I of the Township. However, further transfer of land
from DVC was restricted by the Circular No. 93/2011-CDN dated 6.4.2011 of the
Ministry of Urban Development, GOI, wherein Government undertakings like DVC
have been directed to seek prior approval of the Cabinet for any transfer/alienation of
Land belonging to the Government. The Petitioner approached the district
administration to acquire land of approximately 30 acres. However, the land identified
by the district administration for the construction of Phase II of the township is owned
by the tribal community and GOJ. Accordingly, it again persuaded the district
(b) Presently, the employees of the Petitioner are accommodated in Dhanbad and
Asansol (approximately 40-50 km from the generating station) in rented
accommodation and bus service is provided to employee for conveyance for both
normal and shift duties. This has resulted into additional O&M cost which is not part
of Normative O&M Expenses. Total cost incurred by the Petitioner in absence of
phase II of “Township & Colony” is presented in table below;
(c) Had the Petitioner been able to come-up with the Phase-II of the Township and
Colony at the projected capital expenditure of ₹60 crores by 31.3.2014, the total
Annual Fixed Charges (AFC) recovery towards Phase-II of the Township in the
remaining years of the useful life of the Station would have been ₹223 crore whereas
if it pursues the current arrangement for employees as stated above it would require
additional O&M expenses towards rent and conveyance of about ₹23.15 crore over
the same period resulting into a net savings of ₹199.38 crore for the beneficiaries
which shall ultimately rests with them. Therefore, the Petitioner is seeking these
Rental and Conveyance Expenses over and above Normative O&M Expenses.
Going with existing arrangement and seeking additional O&M expenses in lieu of
Phase-II of the township and utilizing savings for other cost overrun is in no way
causing harm to the beneficiaries and shall be a fair approach to compensate the
costs incurred/to be incurred by the Petitioner. For arriving at savings, AFC has been
computed as per 2014 Tariff Regulations and assuming that the additional capital
expenditure was capitalized on 31.3.2014. Rent, HRA deduction and conveyance
charges have been considered at actual for 2014-15 to 2018-19 and thereafter
projected based on average of the previous five years with an annual escalation of
5% thereon until useful life of the generating station. Detailed workings of AFC and
additional O&M expenses and net savings on account of this annexed for kind
perusal of the Commission;
(d) In view of foregoing, Commission is, therefore, most humbly requested to allow
the expenses incurred by the Petitioner towards the Rental expenses adjusted with
HRA and conveyance charges at actuals for the period 2014-15 to 2018-19
separately as additional O&M Expenses over and above the Normative O&M
expenses and thereafter for the ensuing years on the projected basis subject to
truing up of tariff, based on actuals.
147. The Respondent, KSEBL has submitted that since the normative O&M
expenses is allowed for the project, the claim for additional O&M expenses in lieu of
2nd Township is not in line with the 2014 Tariff Regulations and may be rejected. In
response, the Petitioner has submitted that it had to drop the plan for 2nd township
employees in nearby cities and arrange transport facilities to office. It has also
covered under the normative O&M expenses. Accordingly, the Petitioner has
claimed such expenses over and above the normative O&M expenses allowed to the
generating station. The Petitioner has also contended that the 2014 Tariff
Regulations do not prohibit such claim of the Petitioner, arising due to force majeure
148. It is noticed that the Petitioner has claimed additional O&M expenses due to
availability of land. According to the Petitioner, this has resulted in savings in capital
burden on the consumer, as the claim of additional O&M expenses is against the
stated that due to non-availability of the land, the idea of Township colony was
dropped and thereby the projected capital expenditure of Rs.60 crore was not
incurred. As per submissions of the Petitioner, the total annual fixed charges
recovery towards the 2nd Township, in the remaining years of the useful life of the
generating station, would have been Rs.223 crore, whereas, in terms of the existing
arrangement for the employees, it would require additional O&M expenses towards
Rent and Conveyance of about Rs.23.15 crore over the same period, resulting into a
149. The admissibility of the claim of the Petitioner is examined in the light of the
provisions of the 2014 Tariff Regulations. The O&M expense norms for the 2014
expenses incurred by the generating stations for the period 2008-2013 and after
captures all components as stated by the Petitioner, the prayer of the Petitioner for
additional O&M expenses, if allowed, under this head, would, in our view, result in
re-opening of the O&M expense norms at this stage. For these reasons, the prayer
of the Petitioner for additional O&M expenses in lieu of 2nd Township is not allowed.
150. The Commission in its order dated 25.4.2019 in Review Petition No.
16/RP/2018 (in Petition No. 152/GT/2015) had allowed the projected ‘Ash disposal’
(Rs. in crore)
2014-15 2015-16 2016-17 2017-18 2018-19 Total
60.98 62.70 66.50 70.72 0.00 260.90
151. The Petitioner, in the present petition, has claimed audited actual ‘Ash
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19 Total
6098.44 3791.36 3647.73 3320.87 3340.46 20198.86
152. The Respondent, KSEBL has submitted that the claim towards ash disposal
expenses over and above the normative O&M expenses is not in line with the 2014
Tariff Regulations and, therefore, the claim may be disallowed. The Petitioner in its
rejoinder has submitted that issue is no more res integra as the Ash disposal
expenses over and above the normative O&M expenses had already been approved
by the Commission vide its order dated 26.12.2017 in Petition No. 152/GT/2015 and
by order dated 25.4.2019 in Petition No. 16/RP/2018 read with corrigendum order
dated 25.5.2019 subject to truing-up. The Petitioner has also stated that Ash
basis due to the limited capacity of ash pond and in compliance with the MOEF&CC
153. The submissions have been considered. The Commission in its order dated
allowed the ‘Ash disposal’ expenses, based on actuals of the year 2014-15 and
projected expenses for the period 2015-19, subject to revision, based on the actual
Ash disposal expenses incurred by the Petitioner, at the time of truing up of tariff.
The Petitioner has claimed actual expenses towards ash disposal, after adjustment
of the revenue earned and has submitted the break-up details, duly certified by
Auditor. Accordingly, the audited net ash disposal expenses, after adjustment of the
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19 Total
6098.44 3791.36 3647.73 3320.87 3340.46 20198.86
154. Considering the fact that reimbursement of the ash disposal expenses is
being allowed based on special circumstances (limited ash pond storage) for the
generating station, these expenses are not made part of the total O&M expenses
allowed and the consequent annual fixed charges determined in this order.
155. Clauses (1) and (2) of Regulation 28 of the 2014 Tariff Regulations provide as
under:
(2) The cost of fuel in cases covered under sub-clauses (a) and (b) of clause (1) of
this regulation shall be based on the landed cost incurred (taking into account
normative transit and handling losses) by the generating company and gross calorific
value of the fuel as per actual for the three months preceding the first month for
which tariff is to be determined and no fuel price escalation shall be provided during
the tariff period.
had allowed interest on working capital based on ‘as billed GCV’ on provisional
basis, as follows:
“165. ………We however direct the Petitioner to place on record the GCV of coal for
the preceding three months on “as received” basis in terms of the directions
contained in order dated 25.1.2016, at the time of truing-up of tariff of the generating
station for 2014-19 in terms of Regulation 8 of the 2014 Tariff Regulations. The “as
received GCV” furnished by the Petitioner for the few days of the month of October,
2016 for which sample is taken from the track hopper cannot be considered “as
received‟ GCV of coal since the computation for fuel components in the working
capital is undertaken based on the preceding three months i.e. for the month of
January, 2014, February, 2014, and March, 2014. Also, the sample taken from track
hopper is not in compliance with the Commission order dated 25.1.2016 in Petition
No. 283/GT/2014, which specify that the measurement of GCV of coal on “as
received” basis shall be taken from the loaded wagons at the unloading point either
manually or through the Hydraulic Augur.”
allowed the fuel cost for computation of interest on working capital (IWC) based on
price and GCV on ‘as billed’ basis with adjustment formula as Petitioner did not
furnish the requisite “as received GCV”. The Petitioner has not furnished the details
of ‘as received’ GCV in the true-up petition also and has also not made any prayer
basis. In this background, we have considered the ‘as billed’ GCV to be ‘as received’
GCV, and the components of working capital i.e. the cost of coal for stock (30 days),
cost of coal for generation (30 days) and Energy charges (for two months) as
been considered for the purpose of tariff, in this order. Accordingly, the fuel
components in working capital have been allowed as per order dated 26.12.2017 in
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Cost of Coal towards stock - 30 10458.70 10487.35 10458.70 10710.71 10710.71
days
Cost of Coal for towards 10315.43 10315.43 10315.43 10563.99 10563.99
generation - 30 days
Cost of Secondary fuel oil 300.37 301.19 300.37 307.60 307.60
towards generation - 2 months
158. The Petitioner, in Form-13B of the petition, has claimed maintenance spares
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
3569.31 3786.53 4018.58 4255.10 4488.65
the 2014 Tariff Regulations. Therefore, in terms of Regulation 29(2) of the 2014
Tariff Regulations, the maintenance spares @20% of the O&M expenses, including
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
3549.24 3771.31 4005.96 4237.22 4478.13
160. O&M expenses for 1 month as claimed by the Petitioner in Form-13B for the
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
1487.21 1577.72 1674.41 1772.96 1870.27
161. Regulation 28(a)(vi) of the 2014 Tariff Regulations provides for O&M
expenses for one month towards Working Capital for coal-based generating stations.
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
1478.85 1571.38 1669.15 1765.51 1865.89
162. The difference in the O&M expenses for 1 month and the Maintenance spares
allowed as above, as against those claimed by the Petitioner, is due to the fact that
while the Petitioner had considered the O&M expenses in lieu of 2nd Township also
for calculation under these heads, the same has not been considered (since dis-
allowed in this order) in the calculations, while allowing the claims under these
heads.
163. Receivables equivalent to two months of capacity charges and two months of
energy charges towards Working Capital (as allowed in Commission’s order dated
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Fixed charges –
17253.62 17484.40 17233.33 16747.94 16621.10
for two months
Energy Charges – 21074.50 21103.97 21074.50 21582.30 21582.30
for two months
165. In terms of clause (3) of Regulation 28 of the 2014 Tariff Regulations, the rate
of interest on working capital has been considered as 13.50% (Bank rate 10.00 +
350 bps). Accordingly, Interest on working capital has been computed as under:
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Working Capital - Cost of coal 10458.70 10487.35 10458.70 10710.71 10710.71
for stock - 1 month
Working Capital - Cost of coal 10315.43 10315.43 10315.43 10563.99 10563.99
for generation - 1 month
Working Capital for O&M 1478.85 1571.38 1669.15 1765.51 1865.89
expenses - 1 month of O&M
Expenses
Working Capital - Cost of 300.37 301.19 300.37 307.60 307.60
secondary fuel oil - 2 months
Working Capital for Maintenance 3549.24 3771.31 4005.96 4237.22 4478.13
spares
Working Capital for Receivables 17253.62 17484.40 17233.33 16747.94 16621.10
(Fixed charges - 2 months)
Working Capital for Receivables 21074.50 21103.97 21074.50 21582.30 21582.30
(Variable charges - 2 months)
Total Working Capital 64430.71 65035.02 65057.44 65915.27 66129.71
Rate of Interest 13.50% 13.50% 13.50% 13.50% 13.50%
Interest on Working Capital 8698.15 8779.73 8782.75 8898.56 8927.51
166. Accordingly, the annual fixed charges approved for the generating station for
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
Return on Equity 26333.62 27727.29 28076.30 28102.15 28295.00
Interest on Loan 27957.86 25842.46 22561.92 18331.74 15953.23
Depreciation 22785.93 23700.34 23949.17 23969.12 24160.20
O&M Expenses 17746.18 18856.55 20029.82 21186.09 22390.63
Interest on Working 8698.15 8779.73 8782.75 8898.56 8927.51
Capital
Total 103521.74 104906.37 103399.96 100487.66 99726.57
167. As stated in paragraph 153 above, the Ash disposal expenses allowed is as
below:
168. The annual fixed charges allowed in order dated 1.10.2019 in Petition
(Rs. in lakh)
Total annual fixed 99154.50 106314.26 107868.34 106552.83 111287.93
charges allowed in
order dated 1.10.2019
Total annual fixed 103521.74 104906.37 103399.96 100487.66 99726.57
charges allowed in
this order
169. The difference between the annual fixed charges already recovered by the
Petitioner in terms of the order dated 26.12.2017 read with order dated 1.10.2019 in
Petition No.152/GT/2015 and the annual fixed charges determined by this order shall
170. The Petitioner has also sought determination of tariff of the generating station
for the 2019-24 tariff period in terms of the Central Electricity Regulatory
Commission (Terms and Conditions of Tariff) Regulations, 2019 (in short ‘the 2019
Tariff Regulations’). The capital cost and the annual fixed charges claimed by the
Capital Cost
171. Regulation 19 of the 2019 Tariff Regulations provides as under:
“19. Capital Cost: (1) The Capital cost of the generating station or the transmission
system, as the case may be, as determined by the Commission after prudence
check in accordance with these regulations shall form the basis for determination of
tariff for existing and new projects.
xxxx
(3) The Capital cost of an existing project shall include the following:
(a) Capital cost admitted by the Commission prior to 1.4.2019 duly trued up by
excluding liability, if any, as on 1.4.2019;
(b) Additional capitalization and de-capitalization for the respective year of tariff as
determined in accordance with these regulations;
(c) Capital expenditure on account of renovation and modernisation as admitted by
this Commission in accordance with these regulations;
(d) Capital expenditure on account of ash disposal and utilization including handling
and transportation facility;
(e) Capital expenditure incurred towards railway infrastructure and its augmentation
for transportation of coal up to the receiving end of generating station but does not
include the transportation cost and any other appurtenant cost paid to the railway;
and
(f) Capital cost incurred or projected to be incurred by a thermal generating station,
on account of implementation of the norms under Perform, Achieve and Trade
(PAT) scheme of Government of India shall be considered by the Commission
subject to sharing of benefits accrued under the PAT scheme with the beneficiaries.”
172. The Petitioner has claimed the opening capital cost of Rs.487912.60 lakh as
approved in this order, for the 2014-19 tariff period, has been considered as the
opening capital cost as on 1.4.2019, for determination of tariff for the 2019-24 tariff
period.
“25. Additional Capitalisation within the original scope and after the cut-off date:
(1) The additional capital expenditure incurred or projected to be incurred in
respect of an existing project or a new project on the following counts within the
original scope of work and after the cut-off date may be admitted by the
Commission, subject to prudence check:
(a) Liabilities to meet award of arbitration or for compliance of the directions or
order of any statutory authority, or order or decree of any court of law;
(b) Change in law or compliance of any existing law;
(c) Deferred works relating to ash pond or ash handling system in the original
scope of work;
(d) Liability for works executed prior to the cut-off date;
(e) Force Majeure events;
(f) Liability for works admitted by the Commission after the cut-off date to the
extent of discharge of such liabilities by actual payments; and
(g) Raising of ash dyke as a part of ash disposal system.
(2) In case of replacement of assets deployed under the original scope of the
existing project after cut-off date, the additional capitalization may be admitted by
the Commission, after making necessary adjustments in the gross fixed assets
and the cumulative depreciation, subject to prudence check on the following
grounds:
(a) The useful life of the assets is not commensurate with the useful life of the
project and such assets have been fully depreciated in accordance with the
provisions of these regulations;
(b) The replacement of the asset or equipment is necessary on account of change
in law or Force Majeure conditions;
(c) The replacement of such asset or equipment is necessary on account of
obsolescence of technology; and
(d) The replacement of such asset or equipment has otherwise been allowed by
the Commission.
174. The Petitioner has claimed additional capital expenditure in respect of assets/
works which form part of the original scope of work of the project, but after the cut-off
date, in terms of the provisions of Regulation 25 of the 2019 Tariff Regulations. It has
also claimed additional capital expenditure in respect of assets/ works which are
beyond the original scope of work of the project in terms of the provisions of
additional capital expenditure claimed by the Petitioner for the 2019-24 Tariff Period
(Rs. in lakh)
Sl. Head of work/Equipment Regulations 2019-20 2020-21 2021-22 2022-23 2023-24
No.
A Projected Additional Capitalisation within the original scope of work, but after the cut-off date
1 Cost of Land &Site 25(1)(e) 3881.64 - - - -
2 General Civil Works-Boundary 25(1)(e) 160.00 - - - -
Wall
3 Railway Package 25(1)(e) - 68506.24 - - -
(inclusive of IDC)
4 IT equipment 25(2)(b) 82.93 - - - -
5 2 Numbers Flat Top Freezers 25(2)(b) - - - - -
@ Aahar I
6 C.T.Fan Gearbox 25(2)(b) - 200.00 - - -
7 Centrifugal compressor and 25(2)(b) - 350.00 400.00 - -
motor for BTG
8 Centrifugal Compressors for 25(2)(b) - 300.00 300.00 300.00 300.00
Ash Plant
9 Coal Mill Internals 25(2)(b) - 100.00 200.00 200.00 -
176. The following additional capital expenditure has been claimed by the
Petitioner in respect of assets/ works which form part of the original scope of work of
the project, but after the cut-off date, under Regulation 25(1)(e) of the 2019 Tariff
Regulations:
(Rs. in lakh)
Head of work / Equipment 2019-20 2020-21
a. Railway Infrastructure Package (inclusive of - 68506.24
IDC)
b. Cost of Land & Site 3881.64 -
c. General Civil Works-Boundary wall 160.00 -
25(1)(e) of the 2019 Tariff Regulations and has submitted the following:
b) The land acquired for Phase I, Stage-1 by the Petitioner was 82.01 acres,
which comprises of 64.23 acres of Private land, 17.78 acres of Government
land (which includes 4.81 acres of Krishi land). Additionally, this Phase
included Railway land of 17 acres. The Private land and Government land is
spread over nine villages. The Petitioner earnestly started the work for
completion of the Railway Project immediately after Board approval and tying
up finance in 2008.
178. The Petitioner has submitted that the completion of Railway Infrastructure
Package was delayed due to reasons beyond the control of the Petitioner. The
No.152/GT/2015 for the delay in the Railway Infrastructure Package. The Petitioner
has further submitted that the execution of few Project packages including the
acquisition of requisite land parcels for this package, which are beyond the control of
the Petitioner and, therefore, the capitalization of these packages could not be
achieved within the cut-off date i.e. 31.3.2015. The summary of the reasons for the
179. The Petitioner in Annexure-P/6 of the petition has furnished the details of time
and cost overrun of the Railway Infrastructure Package along with justification. The
Petitioner has submitted that it made all efforts to expedite the possession of land
as and when the possession of these parcels were obtained, which at times needed
changes in design and scope due to actual site measurements being different from
estimates in design, when access was available for those parcels. The Petitioner has
submitted that with the present status and speed of resolution of disputes, it is
expected that the entire land related issues pertaining to Railway Infrastructure
Package would be resolved and possession of all land parcels would be obtained by
the end of June 2020 and accordingly the Railway Infrastructure Package would be
completed by 31.3.2021. It has stated that land acquisition has been categorized as
an ‘uncontrollable factor’ under the 2019 Tariff Regulations if the delay is for reasons
not attributable to the Petitioner. The Petitioner has added that the significance of
completing the Railway Infrastructure Package also arises from the fact that the
environmental concern and from fuel security point of view for ensuring supply to the
importance. The Petitioner has submitted that the delay in commissioning of Railway
Infrastructure Package is mainly due to land related issues which were totally out of
control of the Petitioner and the same is a ‘force majeure’ condition, which is to be
considered and allowed in terms of Regulation 3(25) read with Regulation 25 of the
180. As regards cost overrun of the Railway Infrastructure Package, the Petitioner
has submitted that the same was beyond the control of the Petitioner and the
increase in the Railway Infrastructure Package cost forced the Petitioner’s Board to
re-allocate the project cost. In addition, the Petitioner has stated that the Railway
Infrastructure Package contract which was initially awarded to M/s L&T had to be
split into three parts, on account of the unforeseen delays and was reallocated
Kanwar. The Petitioner’s Board in its meeting dated 16.3.2019 had approved the
cost and internal allocations under the ‘Railway Infrastructure cost’ for Rs.574.66
crore excluding IDC. It has further stated that during the execution of the packages
identified under Railway infrastructure, the cost allocation was changed and
approved by the Board for revised allocation, keeping the overall cost of Railway
Infrastructure package within the approved budget of Rs.574.66 crore in the Board
meeting dated 16.10.2019. The Petitioner has submitted that the total IDC is
Rs.152.75 crore on Railway Infrastructure Package. We note that the total Railway
Infrastructure Package cost approved by the Board works out to Rs.712.14 crore
(Rs.559.38 crore + Rs.152.75 crore) out of which the Petitioner has capitalized and
claimed Rs.28.13 crore (Rs.24.13 crore + Rs.4.49 crore of IDC) during 2015-16
which has not been allowed (as discussed in earlier part of this order) as the Railway
Rs.3881.64 lakh in 2019-20 towards the cost of ‘Land & Site’ and additional
Regulation 25(1)(e) of the 2019 Tariff Regulations and has submitted the following:
b) Even after continuous follow-up, the balance demand is yet to be received from the
Govt. of Jharkhand. The same is beyond the control of the Petitioner and ought to be
considered as an ‘uncontrollable factor’.
(b) Although the remaining work is related to Ash Pond and construction of wall, the
same is included under the ‘General Civil Works’ owing to the nature of the balance
scope of work. The completion of the boundary wall around the Ash Pond has been
delayed on account of land related issues, the resolution of which has taken much
longer time than envisaged earlier. Therefore, the balance work of the boundary wall is
expected to be completed by 2019-20.
(c) The detailed submissions justifying the delay in execution of General Civil Works
has been furnished in the truing-up of tariff petition in Annexure P/12 of the petition and
the same are not repeated herein for sake of brevity.
182. The Respondent, KSEBL has mainly submitted that the Petitioner is not
eligible to seek the additional capitalization of the expenditure towards cost of land &
site and for Railway Infrastructure Package, after the cut-off date. It has also
submitted that there has been lack of co-ordination on part of the Petitioner with the
local administration for resolution of disputes, which has led to the inordinate delay in
the execution of the work. Accordingly, the Respondent has prayed that the impact
of cost & time overrun for the aforesaid work may not be passed on to the
beneficiaries.
No.152/GT/2015, had furnished detailed reasons for the delay in the execution of the
Railway Infrastructure Package and submitted that the execution of few project
account of delay due to acquisition of requisite land parcels for this package, which
had, therefore, submitted that the capitalization of expenditure on the scheme could
not be achieved within the cut-off date and, accordingly, sought for extension of the
cut-off date of the project till 31.3.2019 in view of the constraints faced in the
execution of few project packages including Railways. Vide order dated 26.12.2017
incurred for these assets. The Petitioner, in this petition for truing up of tariff for the
2014-19 tariff period, claimed additional capitalization of these packages (Land &
Site and GCW) after the cut-off date (for 2015-19) on the ground that these
packages could not be completed within the cut-off date, due to ‘force majeure’
conditions, which were beyond the control of the Petitioner. It was also submitted by
the Petitioner that most of the project packages were completed in 2015-16, except
for the Railway System, GCW and Land & Site, which were expected to be
packages were put to use and part-capitalized during the 2014-19 tariff period and
184. It is noticed that the Petitioner had claimed actual additional capitalization of
Infrastructure Package, forming part of the original scope of work of the project and
had submitted that the said package was yet to be completed and operationalized by
the Petitioner, owing to severe land acquisition disputes as narrated therein including
evident that the ‘Railway Infrastructure Package’ had not been completed and put to
use by the Petitioner. Only certain civil assets like roads, over-bridges and under-
capitalized. Since the construction of these civil assets do not have any nexus with
the generation of power, the Commission, in this order, had not permitted the
additional capitalization of these assets, until the Railway Infrastructure Package was
Infrastructure Package’ after the cut-off date was never considered as the same had
not been completed and put to use by the Petitioner. As regards the delay in Railway
from these submissions that the delay was mainly on account of ‘land acquisition’
issues, which also involved litigation before the Courts and payment of
Package could not be commissioned until all land parcels in the route were available
with the Petitioner free of any encumbrance. It is noticed that Regulation 22(2) of the
except where the delay is attributable to the generating company or the transmission
licensee, as the case may be. The relevant portion of the said regulation is extracted
hereunder:
“The ‘uncontrollable factors’ shall include but shall not be limited to the following:
a. Force Majeure events;
b. Change in law; and
c. Land acquisition except where the delay is attributable to the generating company
or the transmission licensee.”
185. From the submissions of the Petitioner with regard to time overrun for Railway
Infrastructure Package read with the submissions in Annexures P/5 & P/12 of this
petition, it is noticed that a series of events had affected the progress of resolution of
communication with the local administration for expediting the land acquisition
Jharkhand seeking directions upon the local administration. Also, the identification of
the rightful owners, the correction of earlier awards in terms of the directions of the
Hon’ble High Court, the submission of claims and payment of compensation and
obstacles created by encroachment have all led to the delay in possession of land
and the construction and final commissioning of the said package got delayed. The
Petitioner has taken efforts to expedite the possession of land parcels and to
complete the construction in those patches of land parcels in phases as and when
paragraph 46 of this order, examined the submissions of the Petitioner with regard to
the delay in the availability of land & site and the delay in execution of the General
Civil Works, consequent upon the non-availability of land, attributed to the change in
policy of State Government and Order of the Hon’ble High Court, and allowed the
additional capitalisation of the expenditure claimed by the Petitioner for the period
2015-19 under Regulation 14(3)(i) of the 2014 Tariff Regulations, for compliance with
the orders of the Hon’ble Court. Considering the fact that these are balance works
which have spilled over from 2018-19 and keeping in view that the Railway
clearance of land acquisition issues, we hold, that the delay is on account of events
which are not attributable to the Petitioner. In our considered view, the delay due to
non-availability of land & site, which has caused the delay in the execution of the
General Civil Works for the period 2015-19, holds good for the delay in the
completion of Railway Infrastructure Package for the period 2019-21 also. For these
Rs.4041.64 lakh (Rs.3881.64 lakh for cost of Land and Site and Rs.160.00 lakh for
Tariff Regulations. However, the total cost including cost disallowed for the year
“25(2) In case of replacement of assets deployed under the original scope of the
existing project after cut-off date, the additional capitalization may be admitted by the
Commission, after making necessary adjustments in the gross fixed assets and the
cumulative depreciation, subject to prudence check on the following grounds:
(a) xxxxxx;
(b) The replacement of the asset or equipment is necessary on account of change in
law or Force Majeure conditions;
xxxx”
187. The following additional capital expenditure has been claimed by the
(Rs. in lakh)
Sl. Head of work/ Equipment 2019-20 2020-21 2021-22 2022-23 2023-24
No.
1 Coal Mill Internals 0.00 100.00 200.00 200.00 0.00
2 Coal Mill Journal Assembly 0.00 200.00 300.00 300.00 0.00
3 Economiser Coil 0.00 1200.00 0.00 0.00 0.00
(both Upper & Lower Bank)
4 LTSH Coil 0.00 0.00 800.00 0.00 0.00
(both Upper & Lower Bank)
5 Refurbishment of Economiser 50.00 0.00 0.00 0.00 0.00
Coil Unit 2
6 Refurbishment of Economiser 50.00 0.00 0.00 0.00 0.00
Coil Unit1
7 Refurbishment of Pulverizer 100.00 0.00 0.00 0.00 0.00
Internals
8 Re-Heater Straight Tubes & 0.00 350.00 400.00 450.00 450.00
Bends
9 C.T.Fan Gearbox 0.00 200.00 0.00 0.00 0.00
10 Centrifugal compressor and 0.00 350.00 400.00 0.00 0.00
motor for BTG
11 Centrifugal Compressors for 0.00 300.00 300.00 300.00 300.00
Ash Plant
12 Replacement of Slew Hydraulic 0.00 0.00 159.87 0.00 0.00
Motor of Stacker cum Re-
claimer
13 Vacuum Pump 0.00 200.00 200.00 0.00 0.00
188. As regards the claim for additional capitalization on items/ assets like Coal Mill
Internals, Coal Mill Journal Assembly, Economiser Coil (both Upper & Lower Bank),
LTSH Coil (both Upper & Lower Bank), Refurbishment of Economiser Coil Unit 2,
Heater Straight Tubes & Bends, the Petitioner has submitted that due to poor quality
of coal, higher quantity of ash is generated and coarse type of ash is produced in the
generating station. It has also stated that due to the abrasive nature and more
quantity of ash, the life of these equipment has reduced and are, therefore, required
has submitted that the amount claimed under this head mainly involves expenditure
189. The matter has been considered. The 2019 Tariff Regulations do not contain
any provision for correlating the life of the asset/ equipment corresponding to the
quality of coal. Different generating stations use different quality of coal as per the
Fuel Supply Agreements (FSA) executed by them with coal companies, depending
replacement of assets to poor quality of coal that has led to higher generation of ash
apart from ash being coarse in nature. The Petitioner has submitted that due to
abrasive nature and higher quantity of ash, the life of equipment have reduced and,
therefore, are required to be replaced. The Petitioner has submitted that these
events (higher quantity and coarse nature of ash which being abrasive, have lowered
life of equipment/ asset) are Force majeure conditions. However, we note that the
Petitioner has not furnished whether the coal received at the generating station is as
per the provisions of FSA and as per the design coal considered at the time of
selection of the equipment/ technology. The Petitioner has also not mentioned if the
quality of coal being supplied is different from the one agreed in FSA with coal
companies and whether the matter has been taken up with coal companies.
Moreover, reduction in the life of equipment and replacement of the same due to
poor quality of coal, cannot qualify as a force majeure condition to be eligible for
grant of relief under Regulation 25(2)(b) of the 2019 Tariff Regulations. In view of
this, the projected additional capital expenditure claimed in this respect is not
allowed.
190. As regards the claim of the Petitioner under Regulation 25(2)(b) of the 2019
C.T. fan gearbox, Centrifugal compressor & motor for BTG, Centrifugal compressors
191. The submissions have been considered. The Petitioner, in justification of the
claim for the aforesaid items/ assets, has mainly submitted that these equipment are
required to be procured as ‘spares’ or on account of the fact that these items have
‘worn out’ or likely to be ‘unserviceable’ in due course of time. The Petitioner has
also submitted that OEM has recommended their replacement in place of repair or
change of the defective part. It is observed that in some of the cases, the Petitioner’s
claim is premised on poor quality of coal and in some cases, the claim is based on
the recommendations of OEM. These factors do not, in our view, constitute change
in law or a force majeure event, warranting any relief to the Petitioner. However, after
Centrifugal Compressor & motor for Boiler Turbine Generator and Centrifugal
Compressors for Ash Plant, the OEM has suggested the replacement owing to the
Rs.400.00 lakh in 2021-22) for Centrifugal Compressor & motor for Boiler Turbine
Generator and Rs.1200.00 lakh (Rs.300 lakh during each year from 2020-24) is
allowed under Regulation 25(2)(c) of the 2019 Tariff Regulations. The Petitioner is
tariff.
192. However, for other items such as coal mill internals, cooling tower internals,
economizer coil DM plant equipment, C.T fan gearbox etc. required to be replaced
before the life of plant due to wear/ tear, we hold that the failure/ replacement of
items does not fall under force majeure. However, replacement of such consumables
may be met from the capital spares and may be claimed under capital spare
consumption during truing up. In view of this, the additional capital expenditure
claimed by the Petitioner is not allowed. Further, the prayer of the Petitioner for
servo system’ at the time of truing-up shall be considered as per the merit and
193. The Petitioner has also claimed additional capitalization for some minor
assets/ items like Flat top freezers (2 numbers), Godrej storewell (12 numbers for
guest house), office chairs, LG 230 litres fridge (5 numbers) and for replacement of
township ACs. As regards flat top freezers, the Petitioner has submitted that their
replacement is required as the existing units are not functioning properly due to
deteriorated condition. As regards Godrej storewell, it has been submitted that the
office chairs, the Petitioner has stated that the replacement of chairs (including those
in conference rooms) for officers and guests to ensure proper ergonomics and safety
of individuals. In respect of LG 230 litres fridge, it has been submitted that as part of
providing basic amenities at project office, gate house, CHP, switchyard and
technical building pantry, the fridge, being used has completed its useful life and is
ACs, the Petitioner has stated that all ACs are more than 7 years old and, therefore,
their replacement will be required by 2023-24 and will be done in a phased manner,
depending on the condition of the units at various blocks in township. The Petitioner
has contended that these minor items have life cycle of 7-8 years and need recurrent
replacement. It has stated that the provision for Compensation Allowance that
existed in the 2014 Tariff Regulations to compensate for addition of minor assets, is
not there in the 2019 Tariff Regulations. Hence, the Petitioner has stated that there is
no specific provision to claim the expenses for minor asset additions, which are
important for the power plant and significant cost of Rs.0.81 crore is expected to be
incurred during the 2019-24 tariff period. Accordingly, the Petitioner has submitted
that the additional capitalization of these assets may be allowed in exercise of power
vested under Regulation 76 read with Regulation 25(2)(b) of the 2019 Tariff
Regulations. The submissions of the Petitioner have been considered. Since the
additional capital expenditure claimed by the Petitioner do not relate to the operation
of the generating station and are minor in nature, the claim for additional
capitalization under Regulation 25(2)(b) of the 2014 Tariff Regulations is not allowed.
1
194. The following additional capital expenditure has been claimed by the
Petitioner in respect of assets/ works, which are within the original scope of work of
the project, but after the cut-off date, under Regulation 25(2)(c) of the 2019 Tariff
Regulations:
(Rs. in lakh)
Sl. Head of work / Equipment 2019-20 2020-21 2021-22 2022-23 2023-24
No.
1 Induced Draft fan motor with 0.00 450.00 450.00 450.00 450.00
Variable Frequency Drive
replacement
“25. Additional capitalization within the original scope and after the cut-off date:
(2) In case of replacement of assets deployed under the original scope of the existing
project after cut-off date, the additional capitalization may be admitted by the
Commission, after making necessary adjustments in the gross fixed assets and the
cumulative depreciation, subject to prudence check on the following grounds:
(c) The replacement of such asset or equipment is necessary on account of
obsolescence of technology; and...”
and Rs.450.00 lakh in 2023-24) for Induced Draft fan motor with Variable Frequency
Drive replacement under Regulation 25(2)(c) of the 2019 Tariff Regulations. The
Petitioner has submitted that the said item/ asset was supplied by M/s BHEL and is
in service for more than 7 years. It has submitted that there have been multiple
instances of channel tripping in the past, leading to loss of generation and reliability
and from past records and minutes recorded in MoM dated 3.8.2019 with M/s BHEL,
a tripping of particular LCI channel continued for more than 15 days in presence of
BHEL supervisory engineer and the tripping count reached to more than 40 days. In
gradation and to address issue of present unreliability of the system, the Petitioner
has proposed to retrofit the existing system with the latest technology, having
fan.
been multiple instances of channel tripping in the past and has referred to the MoM
Petitioner with OEM, we find that the replacement of the asset was based on the
expert opinion of the OEM as recorded in the said MoM. In view of this, the claim of
lakh in 2021-22, Rs.450.00 lakh in 2022-23 and Rs.450.00 lakh in 2023-24 for the
said asset is allowed along with the corresponding decapitalization of Rs.284.43 lakh
lakh in 2023-24. The Petitioner is, however, directed to furnish the obsolescence
Laboratory Instruments
lakh (Rs.21.94 lakh in 2020-21, Rs.57.08 lakh in 2021-22, Rs.52.90 lakh in 2022-23
and Rs.22.11 lakh for 2023-24) for Laboratory Instruments under Regulation 25(2)(c)
of the 2019 tariff Regulations. The Petitioner has submitted that ‘laboratory
instruments’ are getting old i.e. more than 8 to 10 years and new instruments need to
site, are quite old and have outlived their service life. The Petitioner has also
submitted that some of these machines are slow in response and hang quite
frequently and spares and service support for old machines are restricted due to
component obsolescence. The Petitioner has further stated that OEM has declared
the obsolescence of most spares and that most of the instruments cannot be
technology development (as the same have become obsolete in market). The
laboratory equipment and criticality of the system for plant operations, the Petitioner
has no choice but to go for complete up-gradation of the entire system to higher
has stated that an estimated additional expenditure of Rs 154 lakh, as per initial
offer, spread over the years 2020-21 to 2023-24 is required for up-gradation of
Laboratory Instruments.
199. The matter has been examined. The Petitioner has stated that the OEM has
declared obsolescence of most spares and that most of the instruments cannot be
under:
“This is to confirm that some of the instruments mentioned below from the order
cannot be serviced or repaired due to non-availability of spares, change in software
and technology development because they became obsolete in market, thus it makes
highly impossible to keep them in working condition…………………..
So we recommend you to upgrade the laboratory with new instruments in order to
maintain a better performance to minimize downtime”
200. The Petitioner has also referred to the correspondence made with M/s Orbit
the items like PH meter, turbidity meter, conductivity meter, LPG gas cylinder
®ulator, hot air oven, bomb calorimeter etc., and that the laboratory spares could
technology development. We, therefore, find merit in the claim of the Petitioner and
lakh for 2020-21, Rs.57.08 lakh for 2021-22, Rs.52.90 lakh for 2022-23, Rs.22.11
lakh for 2023-24) for Laboratory Instruments under Regulation 25(2)(c) of the 2019
Tariff Regulations.
lakh (Rs.80.00 lakh for 2020-21, Rs.80.00 lakh for 2021-22 and Rs.90.00 lakh for
Regulation 25(2)(c) of the 2019 Tariff Regulations along with the corresponding
unrecovered depreciation value of the assets. The Petitioner has submitted that in
case of system blackout, batteries feed the Direct Current (DC) equipment of the
plant and switchyard equipment such as Emergency Oil Pump (EOP), Lube Oil
Pump (LOP), Jacking Oil Pump (JOP) and Emergency lighting, thereby ensuring the
safe shutdown of the plant and safe operation of the switchyard equipment. The
Petitioner has submitted that as per OEM, the serviceable life of these battery sets is
8 to 10 years under normal application. It has also stated that the existing 220 V and
48 V battery banks have been supplied by M/s Exide/ M/s HBL and in view of the
obsolescence, as confirmed by OEMs and to avoid criticality of the system for plant
operation, it is necessary to replace the existing battery sets with new ones for
proposed to replace these battery sets as they will complete their useful life by 2020-
2021 and has accordingly proposed the aforesaid additional expenditure for
202. The matter has been examined. It is observed that the claim of the Petitioner
regarding obsolescence of these batteries has not been duly supported by OEM
certificate. It is, however, noticed that OEM in its letters has confirmed the life of
these batteries to be around 10-12 years and that the batteries form part of the
essential safety system against tripping of the plant. As the useful life of these assets
(batteries), which gets completed during the 2019-24 tariff period, are not
Up-gradation of Coal Handling Plant Main PLC, Up-gradation of DMP PLC, and
Up-gradation of Raw Water PLC
lakh (Rs.60.00 lakh for PLC of CHP, Rs.50.00 lakh for PLC of DMP and Rs.50.00
lakh for PLC of Raw water) in 2020-21 for Up-gradation of PLC in terms of
Regulation 25(2)(c) of the 2019 Tariff Regulations and has submitted the following:
(a) Up-gradation of Coal Handling Plant main PLC: The Programmable Logic
Control (“PLC”) system consists of Measurement and Closed Loop/ Open Loop
Control system (‘CLCS’ and ‘OLCS’), Data bus system, Operator workstations,
Engineer workstation, Software including data diagnostics and data bus system
with Control and Communication with the process. The workstations Human
Machine Interface (HMI) supplied with PLC system is based on Microsoft
Windows XP Operating platform. Microsoft has declared Windows XP as
obsolete and has withdrawn the support for all XP based systems including
automatic security updates. In the absence of such support from Microsoft one
cannot update the critical virus definition files and, thus, makes the system
vulnerable for the system security. Hence, the system needs up-gradation to
higher version of Windows platform to ensure improved reliability and availability.
The OEM in its life cycle report on installed PLC -HMI System at CHP has
strongly recommended immediate attention on migration from Windows XP to
Windows 10 Professional Operating System, owing to technological
obsolescence. Accordingly, it is proposed to incur amount of Rs.0.60 crore in
2020-21.
(b) Up-gradation of DMP PLC: The availability of this PLC system is very
important for the smooth and normal operation of the generating unit. This
system is based on Windows XP operating system and at that time (when the
agreement was inked in with M/s BGR Energy) Windows XP operating system
was the most popular and reliable Windows platform provided by all leading
industrial automation companies for their control system. As Microsoft has
withdrawn the support for Windows XP operating system, the Petitioner needs to
upgrade the PLC to higher version of Windows. Since spares and services
support for the old XP machines are restricted due to component obsolescence,
(c) Up-gradation of Raw Water PLC: The workstations (HMI) supplied with
PLC system is based on Microsoft Windows XP Operating platform. Microsoft
has declared Windows XP as obsolete and has withdrawn the support for all XP
based systems including automatic security updates. In the absence of such
support from Microsoft, one cannot update the critical virus definition files and,
thus, makes the system vulnerable for the system security. Hence, the system
needs up-gradation to higher version of Windows platform to ensure improved
reliability and availability. HMI systems presently in service at site are quite old
and have outlived their service life. Some of these machines are slow in
response and hang quite frequently. Spares and services support for the old
machines are restricted due to component obsolescence. Workstations
presently available in the market are with latest Windows OS and these current
machines are not one to one interchangeable with the existing old machines
presently in use. The OEM in its life cycle report strongly recommended to up-
grade the obsolete portion of the system, retaining majority of existing hardware
along with panels, etc. It is, therefore, proposed to incur an amount of Rs.0.50
crore in 2020-21 on account of technology obsolescence/non-support by OEM.
204. The submissions have been considered. It is evident from the submissions of
the Petitioner that PLC installed in the Coal Handling Plant, DMP PLC, Raw Water
PLC have become obsolete as Microsoft has declared Windows XP as obsolete and
had withdrawn its support for all Windows XP based systems. The Petitioner has
205. In addition, the Petitioner has also claimed additional capitalization for new
schemes like Augmentation of ash handing system, Max DCS version up-gradation
20 and 2020-21. In justification of the same, the Petitioner has submitted that these
new schemes, could not be completed within the 2014-19 tariff period due to various
maintenance plan of units, (ii) limited days of the annual outage and (iii) technical
constraints etc. The Petitioner has submitted that such small deviations in capital
investment are inevitable and there is nil or insignificant impact on the overall project
cost. The Petitioner has further submitted detailed submissions in justification for the
additional capitalization claimed for these new schemes during the 2014-19 tariff
period. Accordingly, the Petitioner has stated that the capitalization of these
schemes has been phased during 2019-20 and 2020-21 and that the same may be
allowed under Regulations 25(2)(b) and 25(2)(c) read with Regulation 76 of the 2019
Tariff Regulations.
206. The Respondent, KSEBL has submitted that carry forward of schemes
approved for 2014-19 period may not be allowed as there is no provision in the 2019
Tariff Regulations to claim such expenditure for the 2019-24 tariff period.
207. We have examined the matter. The Petitioner has claimed additional
capitalization of the aforesaid schemes which are beyond the original scope of work
of the project (apparently on the ground of force majeure condition), stating that
these schemes have been carried forward from the 2014-19 tariff period on various
factors. It has also relied upon the submissions made in respect of these schemes
during the 2014-19 tariff period. It is noticed that the claim of the Petitioner for
Rs.700.13 lakh in 2017-18 and Rs.848.07 lakh in 2018-19 was allowed under
Regulation 14(3)(ii) of the 2014 Tariff Regulations as the same was for safety of
expenditure is for compliance with existing law, we allow the same under Regulation
claimed for new scheme viz. Max DCS version up-gradation (XP) Unit-2for
Rs.450.00 lakh in 2019-20, it is noticed that the Petitioner had claimed the additional
capitalization of Rs.67.52 lakh in 2015-16 and Rs.438.86 lakh 2017-18 mainly on the
ground that M/s BHEL had stopped extending its support after mid-2016 and had
strongly recommended to upgrade to higher versions. Considering the fact that the
Petitioner had incurred the said expenditure under unavoidable circumstances, the
additional capital expenditure claimed has been allowed during the years 2015-16
and 2017-18 in this order. Accordingly, we allow the additional capitalization of the
said expenditure for Rs.450.00 lakh in 2019-20 under Regulations 25(2)(c) and
schemes carried out and claimed during the 2014-19 tariff period.
and Tanks, IT Equipment, Re-heater Modification & MTM installation and Fabrication
of expansion bellows during 2019-20 and 2020-21, it is noticed that the claim of the
Petitioner had been disallowed during the 2014-19 tariff period. Also, justification
furnished by the Petitioner in support of the claim that it is due to change in law or
force majeure are not justifiable. In view of this, the claim of the Petitioner for
209. The Petitioner has also claimed projected additional capital expenditure for
various assets/ works which are beyond the original scope of work of the project
Petitioner for the assets/ works under Regulation 26(1)(a) of the 2019 Tariff
Regulations for the years 2019-20 and 2020-21 are examined below:
(Rs. in lakh)
Asset/Work 2019-20 2020-21
Implementation of Automatic Generation Control 80.00 -
system
Soak-pit for Station Transformer in switchyard. 40.00 -
Up-gradation of ABT for RRAS & SCED - 75.00
Implementation of Automatic Generation Control system
211. The Petitioner has claimed projected additional capitalization of Rs.80.00 lakh
under Regulation 26(1)(a) of 2019 Tariff Regulations. In justification for the same, the
Petitioner has pointed out that the Commission vide its order dated 28.8.2019 in
“34 (i)All thermal ISGS stations with installed capacity of 200 MW and above and all
hydro stations having capacity exceeding 25 MW excluding the Run-of-River Hydro
Projects irrespective of size of the generating station and whose tariff is determined or
adopted by CERC are directed to install equipment at the unit control rooms for
transferring the required data for AGC as per the requirement to be notified by the
212. The Petitioner has submitted that pursuant to the aforesaid order dated
letter dated 17.9.2019 has notified to the generating stations, the requirements for
AGC connecting equipment along with the list of plants identified for monitoring by
NLDC, which includes the generating station of the Petitioner. The Petitioner has
further submitted that NLDC in its letter, has sought details from the Petitioner
regarding the infrastructure for meeting the specified requirements and the
AGC system is put in place before 28.2.2020, in terms of the Commission’s order
sought the approval of the additional capital expenditure for Rs.80 lakh in 2019-20 as
per initial offer (and based on pilot projects implemented in NTPC generating
stations) for implementation of AGC in the generating station of the Petitioner, under
Regulation 26(1)(a) of the 2019 Tariff Regulations. Since the projected additional
capital expenditure claimed by the Petitioner for Rs.80 lakh in 2019-20 is in terms of
Petition No.319/RC/2019, we allow the same under Regulation 26(1)(a) of the 2019
Tariff Regulations.
213. The Petitioner has claimed projected additional capitalization of Rs.40.00 lakh
in 2019-20 towards ‘Soak Pit for Station Transformer in switchyard’ under Regulation
26(1)(a) of the 2019 Tariff Regulations. The Petitioner has submitted that ‘soak pit’
proposed for the station transformer in switchyard is for compliance with Regulation
44 of the CEA (Measures relating to Safety and Electric Supply) Regulations, 2010.
that since there is presently no such arrangement for Station Transformers in the
CEA, had noticed the deficiency (in sl. no. 5 of the report dated 5.6.2018) and has
directed the Petitioner for compliance with the same. Therefore, in order to comply
with the existing regulations of CEA, the Petitioner has projected additional capital
expenditure of Rs.40 lakh in 2019-20 for Soak Pit for station transformer in
switchyard under Regulations 26(1)(a) and 26(1)(b) of the 2019 Tariff Regulations.
214. The matter has been examined. Regulation 44 of the CEA (Measures relating
215. The Regulations of CEA mandating suitable soak oil pit for station transformer
was notified during the year 2010, which is much before COD of the generating
station (in 2012) and the deficiency has been pointed out by CEA in its report dated
5.6.2018. Therefore, the Petitioner should have complied with requirements of CEA
Regulations at the time of COD of the generating station. However, since the claim
of the Petitioner is towards compliance with existing law, we allow the projected
additional capitalization for Rs.40 lakh in 2019-20 for the said asset/ work. At the
time of truing-up, the Petitioner shall submit reasons for the delay/ deferment of the
work.
216. The Petitioner has claimed projected additional capitalization of Rs.75 lakh in
2020-21 for up-gradation of ABT system for RRAS & SCED under Regulation
submitted that it has an online system for monitoring and controlling schedules, as
Availability Based Tariff (ABT) system. It has stated that the core of ABT System is
energy meters, which are of L&T make and the software was developed by M/s CMS
computer Ltd. about 8 years ago. The Petitioner has pointed out that with the
time-block as compared to the earlier revision after 4 time-blocks. It has stated that
all revision of schedule has to be updated in the server manually and the same is
then reflected in the display screen for necessary action by the operation engineers.
The Petitioner has stated that with the implementation of RRAS and SCED, it has
ABT system to re-align with ERLDC schedule, as the cushion time for manual entry
is no more available. The Petitioner has submitted that the Commission in its order
metering, accounting and settlements and has also implemented the same on a pilot
basis and has also recommended that all future procurements of energy meter
should have recording at 5-minute interval. In this regard, the Petitioner has stated
that at present L&T meters in the generating station of the Petitioner do not have
registers to capture the 5-minute data and, accordingly, it has to be replaced with
new meters, in which block duration is programmable and can be adjusted from 15
minutes to 5 minutes, to be future ready and compliant with the 5-minute data
Petition No. 7/SM/2018 under Regulation 26(1)(a) of the 2019 Tariff Regulations.
217. The matter has been considered. Up-gradation of the existing ABT system for
RRAS & SCED is required to comply with the changing scenario, to update the
revised schedules from ERLDC. As the requirement for up-gradation of the existing
ABT system for RRAS and SCED is pursuant to the Commission’s order dated
Facility creation for workmen (Rest Room, Toilet & Drinking water point),
Drivers rest room, Drinking water facility and workers pathway
218. The Petitioner has claimed projected additional capitalization of Rs.19.77 lakh
in 2019-20 for Drinking water facility, Rs.5.00 lakh in 2020-21 for Drivers rest room,
Rs.150.00 lakh in 2020-21 for Workers pathway and Rs.150.00 lakh (Rs.37.50 lakh
each from 2020-21 to 2023-24) for Facility creation for Workmen (Rest Room, Toilet
& Drinking water point) under Regulation 26(1)(b) of the 2019 Tariff Regulations. In
a) Facility creation for workmen (Rest room, Toilet & Drinking water point):
As FGD and Railway system is envisaged, commensurate increase in work force
is expected and the existing facilities might fall short or might be far from the
construction place as per Factories Act. So, in order to ensure hygienic and safe
environment for workers, more Rest rooms, Toilets and drinking water points are
needed. An estimated expenditure of Rs.150 lakh as per initial offer, (Rs.37.50
lakh each spread over the years 2020-21 to 2023-24) is proposed to be incurred
for development of such facilities.
b) Workers Pathway: For protection from heat in summer and rain during
monsoon season for workers commuting from Gate house to workplace with
distance ranging from 2-5 kms, two sitting sheds between Raahi bridge and
Aahar-3 (CHP) are needed. Also, long sheds between Gate house-2 to BTG
area and between material gate to technical building parking area are required.
This would ensure proper working environment for workers. An estimated
219. The Petitioner has referred to Section 18, Section 19 and Section 47 of the
Factories Act, 1948, which mandate to provide drinking water facilities, toilets,
shelters, rest rooms and lunchrooms in a factory and has claimed the projected
additional capitalization of these assets/ works under Regulation 26(1)(b) of the 2019
Tariff Regulations. In our view, the additional expenditure claimed by the Petitioner is
in the nature of revenue expenditure and the same can be met from the O&M
expenses allowed to the generating station under the 2019 Tariff Regulations.
for Drinking water facility, Rs.5.00 lakh in 2020-21 for Drivers rest room, Rs.150.00
lakh during 2020-21 for Workers pathway and Rs.150.00 lakh (Rs.37.50 lakh each
for the years 2020-21 to 2023-24) for Facility creation for workmen (Rest room, Toilet
220. The Petitioner has also claimed projected additional capitalization for various
to 6B & 4B to 6A (Rs.5 lakh in 2021-22), Common C.W. Pump for Units-1&2 (Rs.300
lakh in 2021-22), Economiser Coil Repairing Bay with Shed (Rs.600 lakh in 2020-
Electrical Maintenance Department (EMD) (Rs.5 lakh in 2020-21) and certain Minor
assets, under Regulation 26(1)(c) (Force Majeure events) of the 2019 Tariff
c) Common C.W. Pump for Units-1&2: Each unit of the generating station is
having three numbers of Cooling Water (CW) pumps with all of them in
running configuration without any standby. So, the non-availability of CW
Pump has direct consequence on the reliability of the generation unit. This
standby pump will also ensure regular preventive maintenance of CW Pumps
and, hence, unit reliability will increase. Accordingly, the additional
capitalization projected for the standby pump is Rs.300 lakh for 2021-22.
221. It is observed that the projected additional capital expenditure claimed by the
Petitioner in respect of these assets/ works [(a) to (g) above], mainly pertain to
capitalization of these works/ assets based on ‘force majeure’ conditions, it has not
established the presence of any such force majeure events to consider the claims
made as above. Since no case for force majeure events have been made out by the
Petitioner, the claim for assets/ works like BCN 7 (Yard conveyor) modification,
Workshop for Electrical Maintenance Department (EMD) and certain Minor assets,
claimed under Regulation 26(1)(c) of the 2019 Tariff Regulations is not allowed.
Also, the prayer of the Petitioner to grant liberty to approach the Commission in case
the additional capital expenditure for BCN 7 (Yard conveyor) modification becomes
unavoidable is rejected.
lakh for Augmentation of store and Rs.399.53 lakh for ‘Coal Pit Run-off mechanized
store:
“These are the ‘carry forward schemes beyond the original scope of work’. Few
schemes that were envisaged for the control period 2014-19 could not be completed
within the control period due to various reasons beyond the control of the Petitioner.
The capitalization towards these schemes got carried forward to control period 2019-
24. The relevant regulations under which the capitalization for such schemes are
Regulation 26(1)(c) read with Regulation 3(25) and Regulation 76 of the 2019 Tariff
Regulations. The above mentioned items are claimed under specific provisions of the
2019 Tariff Regulations and justifications are provided in the truing-up section. In view
of above, it is prayed that the Commission may approve the proposed additional
capitalization for control period 2019-24 as proposed.”
223. The Petitioner has not demonstrated the existence of any force majeure
augmentation of store, which has been carried forward from the 2014-19 tariff period.
It is pertinent to mention that the claim of the Petitioner for additional capitalization of
this asset/ work has not been allowed under ‘force majeure’ in the 2014-19 tariff
period. In view of this, the projected additional capital expenditure of Rs.329.26 lakh
2014-19 tariff period, the same has been allowed in paragraph 94 of this order.
225. In view of this decision, the claim of the Petitioner for projected additional
lakh in 2020-21 towards “Boundary wall under pass area’ under Regulation 26(1)(d)
227. The Petitioner has enclosed the recommendations of IB in support of its claim
for additional capital expenditure towards ‘Boundary wall under pass area’ in 2020-
21. Since the recommendations of IB for higher security and safety of the plant, is
the Petitioner for Rs.100.00 lakh for Boundary wall for pass area in 2020-21, under
228. The Petitioner has claimed projected additional capitalization of Rs.20.00 lakh
229. Regulation 26(1)(d) of the 2019 Tariff Regulations provides for capitalization
The Petitioner, in this case, has not established through documentary evidence that
absence of any justification, the claim of the Petitioner for additional capitalization of
CCTV Installation
lakh (Rs.200.00 lakh in 2020-21 Rs.200.00 lakh in 2021-22 Rs.150.00 lakh in 2022-
23) for installation of CCTV all around the generating station, under Regulation
“The surrounding areas of MPL plant have strongholds of CPI (maoist) cadre. Also,
there is always possibility of damage to the MPL from disgruntled subverted
outsourced workers/employees during strikes/agitation. There are several incidents of
such disturbances in the past. So, in order to ensure safety of plant a proper
monitoring of plant premises is needed. CCTV installation all over the plant may help
averting any unwanted incidents and also activities of people in and around plant can
easily be monitored. Accordingly, additional capitalization has been proposed for an
estimated cost of Rs.550 lakh during the period 2020-23 in a phased manner and the
Commission may kindly approve the same.”
231. The Petitioner has not established through documentary evidence that the
Rs.550.00 lakh during the period 2020-23 for this asset/ work is not allowed.
lakh in 2020-21 towards ‘Economiser platform for both boilers’ under Regulation
“During annual outage most of the maintenance works are undertaken in the
economizer and LTSH region due to maximum erosion of coils. Due to space and
design constraints through inspection, lifting of multiple coils and carrying out repair
activity becomes difficult. Moreover, due to multiple activities being carried out
simultaneously, it becomes unsafe for the workers and employees. In view of above
constraint and safety of the workmen, it is proposed to fabricate permanent structure to
create additional space for the coil removal, inspection, immediate repair and re-
placement of coil in the boiler. Additional space shall enhance safety to the workplace
and thereby avoiding any unwanted eventuality. In addition, it will reduce downtime for
peak, off-peak availability. This expenditure is admissible in terms of Regulations
26(1)(d) of the 2019 Tariff Regulations and the cost of the work for Rs.350 lakh is
proposed to be incurred in 2020-21 and the Commission may kindly approve the
same.”
233. The Petitioner has submitted that the additional capital expenditure is required
for better safety/ security of plant based on the advice or direction of any Indian
projected additional capitalization claimed for Rs.350.00 lakh in 2020-21 for the
asset/ work is allowed. The Petitioner is however directed to furnish at the time of
234. The Petitioner has claimed projected additional capitalization of Rs.25.00 lakh
in 2020-21 for Mini Fire Tender under Regulation 26(1)(d) of the 2019 Tariff
“The fire fighting system was installed as per IS 3034 and Tariff Advisory Committee
TAC guidelines at MPL. During the forest fire (Both sides of boundary wall of plant) i.e.
235. The Petitioner has not established through documentary evidence that the
considering the fact that the asset is required for the safe operation of the plant, we
allow the projected additional capital expenditure claimed. The Petitioner is directed
to furnish, at the time of truing up of tariff, the relevant advice or direction of any
claim.
lakh (Rs.150.00 lakh in 2020-21, Rs.150.00 lakh in 2021-22, Rs.100.00 lakh in 2022-
23 and Rs.50.00 lakh in 2023-24) for ‘Road along Boundary wall’ under Regulation
“The Petitioner has submitted that Intelligence Bureau (IB) conducted security
inspection at plant premises in November 2018. IB submitted its security inspection
report to MPL giving some instructions for ensuring safety and security of the plant. IB
perceived threat from the surrounding areas since it is having stronghold of CPI
(Maoist) cadre. Further, Gate blocking/agitations by the Plant Affected People are very
common features. IB in its report observed that the patrolling track along the perimeter
wall is not metaled. It is away from the perimeter at several points and it is not
continuous. The continuity of motorable patrolling track is essential for reaching of
security personnel and fire tenders at the remotest areas. It recommended laying of
metaled patrolling track all along the perimeter for seamless movement of security
personnel and fire tenders. It is needed for higher security and safety of the plant as
directed by Intelligence Bureau responsible for national or internal security. The copy
of inspection report by IB is already enclosed. The estimated cost of Rs.450 lakh and
is proposed to be incurred during the period 2021-24 covering the periphery road of 18
237. The Petitioner has enclosed the recommendations of IB in support of its claim
for capitalization of the expenditure towards Road along Boundary wall during the
period 2020-24. Since the recommendations of IB for higher security and safety of
the plant, is statutory in nature, we allow the projected additional capital expenditure
claimed by the Petitioner for Rs.450.00 lakh during 2020-24 for Road along
lakh in 2019-20 for Gate house near JNT, Rs.248.99 lakh (Rs.148.99 lakh in 2019-
20 and Rs.100.00 lakh in 2020-21) for E-security system and Rs.300.00 lakh in
2019-20 for Construction of high-rise safety platform and walkways under Regulation
26(1)(d) of the 2019 Tariff Regulations and has submitted the following:
“These are the ‘carry forward schemes beyond the original scope of work’. It is
submitted that few schemes that were envisaged for the control period 2014-19 could
not be completed within the control period due to various reasons beyond the control
of the Petitioner. The capitalization towards these schemes got carried forward to
control period 2019-24. The relevant regulations under which the capitalization for
such schemes are Regulation 26(1)(c) read with Regulation 3(25) and Regulation 76
of the 2019 Tariff Regulations. The above mentioned items are claimed under specific
provisions of the 2019 Tariff Regulations and justifications are provided in the truing-up
section. In view of above, it is prayed that the Commission may approve the proposed
additional capitalization for control period 2019-24 as proposed.”
239. The Petitioner has not established through documentary evidence that the
absence of any justification, the claim of the Petitioner for additional capitalization of
Rs.120.70 lakh in 2019-20 for Gate house near JNT, Rs.248.99 lakh (Rs.148.99 lakh
in 2019-20 for Construction of high-rise safety platform and walkways is not allowed.
De-capitalization
under:
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
1138.34 2927.46 2110.64 1119.45 727.30
241. Based on the above discussion, the projected additional capitalization and de-
(Rs. in lakh)
Sl. Head of work / 2019-20 2020-21 2021-22 2022-23 2023-24
No. Equipment
1 Cost of Land & Site 3881.64 0.00 0.00 0.00 0.00
2 GCW- Boundary wall 160.00 0.00 0.00 0.00 0.00
3 Railway Package 0.00 68506.24 0.00 0.00 0.00
inclusive of IDC
4 Laboratory Instruments 0.00 21.94 57.08 52.90 22.11
5 MAX DCS Version up- 450.00 0.00 0.00 0.00 0.00
gradation (XP) Unit 2
6 Replacement of Battery 0.00 80.00 80.00 90.00 0.00
7 Up-gradation of CHP Main 0.00 60.00 0.00 0.00 0.00
PLC
8 Up-gradation of DMP PLC 0.00 50.00 0.00 0.00 0.00
9 Up-gradation of Raw 0.00 50.00 0.00 0.00 0.00
Water PLC
10 Up-gradation of ABT for 0.00 75.00 0.00 0.00 0.00
RRAS & SCED
11 Implementation of AGC 80.00 0.00 0.00 0.00 0.00
12 Augmentation of Ash 1416.80 500.00 0.00 0.00 0.00
handling
13 Boundary wall under pass 0.00 100.00 0.00 0.00 0.00
area
14 Road along Boundary wall 0.00 150.00 150.00 100.00 50.00
(Periphery road 18 kms)
15 Coal Pit Run-off 399.53 0.00 0.00 0.00 0.00
mechanised Drainage
system
16 ID fan Motor with VFD 0.00 450.00 450.00 450.00 450.00
17 Economiser Platform 0.00 350.00 0.00 0.00 0.00
18 Centrifugal compressor & 0.00 350.00 400.00 0.00 0.00
motor for BTG
Discharge of liabilities
242. The Petitioner has not claimed any discharge of liabilities during the 2019-24
tariff period.
Normative IDC
243. The Petitioner has claimed following amounts of normative IDC on excessive
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Normative IDC on Excess equity 735.90 446.12 337.89 185.90 158.15
Normative IDC on actual loan 79.84 39.84 31.94 0.32 0.10
244. In terms of the discussions and decision in paragraph 105 to paragraph 112
above, the normative IDC allowed for the 2019-24 tariff period are as under:
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
245. Based on the opening capital cost and the projected additional capital
expenditure allowed in the preceding paragraphs, the capital cost allowed for the
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Opening Capital Cost 478969.24 484317.13 553551.06 552899.60 552788.32
Net additional capital 3353.30 66290.72 -1523.46 -526.55 -255.19
expenditure allowed within
original scope of work of the
project
“18. Debt-Equity Ratio: (1) For new projects, the debt-equity ratio of 70:30 as on date
of commercial operation shall be considered. If the equity actually deployed is more
than 30% of the capital cost, equity in excess of 30% shall be treated as normative
loan: Provided that:
i. where equity actually deployed is less than 30% of the capital cost, actual
equity shall be considered for determination of tariff:
ii. the equity invested in foreign currency shall be designated in Indian rupees
on the date of each investment:
iii. any grant obtained for the execution of the project shall not be considered as
a part of capital structure for the purpose of debt: equity ratio.”
247. Gross loan and equity amounting to ₹335278.47 lakh and ₹143690.77 lakh
respectively as on 31.3.2019 as determined vide para 122 and 125 above, has been
considered as the gross loan and equity as on 1.4.2019. Based on the above quoted
Regulation, the debt-equity ratio of 70:30 has been applied on year wise allowed
additional capital expenditure for arriving at the additions to loan and equity during
each year of the tariff period 2019-24. The debt-equity ratio considered for the
(Rs in lakh)
Capital (in %) Additional (%) Capital (%)
cost as on Capitalization cost as
1.4.2019 during 2019-24 on
31.3.2024
Debt 335278.47 70.00 51748.58 70.00 387027.05 70.00
Equity 143690.77 30.00 22177.96 30.00 165868.73 30.00
Total 478969.24 100.00 73926.54 100.00 552895.78 100.00
Return on Equity
(2) Rate of return on equity shall be rounded off to three decimal places and shall be
computed as per the formula given below: Rate of pre-tax return on equity = Base
rate / (1-t) Where “t” is the effective tax rate in accordance with clause (1) of this
Regulation and shall be calculated at the beginning of every financial year based on
the estimated profit and tax to be paid estimated in line with the provisions of the
relevant Finance Act applicable for that financial year to the company on pro-rata
basis by excluding the income of non-generation or non-transmission business, as
the case may be, and the corresponding tax thereon. In case of generating
company or transmission licensee paying Minimum Alternate Tax (MAT), “t” shall be
considered as MAT rate including surcharge and cess. Illustration- (i) In case of a
generating company or a transmission licensee paying Minimum Alternate Tax
(MAT) @ 21.55% including surcharge and cess:
Rate of return on equity = 15.50/(1-0.2155) = 19.758% (ii) In case of a generating
company or a transmission licensee paying normal corporate tax including
surcharge and cess:
(a) Estimated Gross Income from generation or transmission business for FY 2019-
20 is Rs 1,000 crore;
(b) Estimated Advance Tax for the year on above is Rs 240 crore;
(c) Effective Tax Rate for the year 2019-20 = Rs 240 crore/Rs 1000 crore = 24%; (d)
Rate of return on equity = 15.50/ (1-0.24) = 20.395%. (3) The generating company
or the transmission licensee, as the case may be, shall true up the grossed up rate
of return on equity at the end of every financial year based on actual tax paid
together with any additional tax demand including interest thereon, duly adjusted for
any refund of tax including interest received from the income tax authorities
pertaining to the tariff period 2019-24 on actual gross income of any financial year.
However, penalty, if any, arising on account of delay in deposit or short deposit of
tax amount shall not be claimed by the generating company or the transmission
licensee, as the case may be. Any under-recovery or over-recovery of grossed up
rate on return on equity after truing up, shall be recovered or refunded to
beneficiaries or the long term customers, as the case may be, on year to year basis.
250. For calculation of ROE in respect of works within the original scope of work
but beyond cut-off date, the Petitioner has grossed up the base rate with MAT rate of
2019-20 (17.472%) for the entire 2019-24 tariff period. The Petitioner has also
grossed up the weighted average rate of interest with the same MAT rate (17.472%)
for calculation of ROE in respect of the additional capitalization beyond the original
scope of work.
as quoted above, specifically provides for grossing up of the base rate allowed under
for works within the original scope of the project) for the generating station is 15.50%
as per Regulation 30 of the 2019 Tariff Regulations. The same has been allowed for
grossing up with the MAT rate of 17.472% for all the years of the 2019-24 tariff
252. Regulation 31 of the 2019 Tariff Regulations provides for grossing up of the
base rate and does not provide for grossing up of weighted average rate of interest
to be used for ROE for additions beyond the original scope of the project.
Accordingly, in line with Regulation 31 of the 2019 Tariff Regulations, ROE has been
allowed as under:
A. Return on Equity allowed at base rate for works within the original scope of
project:
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Gross Notional Equity 143690.77 144715.59 164921.86 164479.80 164340.90
Addition due to additional 1024.82 20206.27 -442.07 -138.90 -86.77
capitalisation
Closing Equity 144715.59 164921.86 164479.80 164340.90 164254.13
Average Equity 144203.18 154818.73 164700.83 164410.35 164297.51
Return on Equity 15.500% 15.500% 15.500% 15.500% 15.500%
(Base Rate)
Tax rate for the year (MAT 17.472% 17.472% 17.472% 17.472% 17.472%
of 2019-20 applied for the
period)
Rate of Return on Equity 18.782% 18.782% 18.782% 18.782% 18.782%
A: Return on Equity 27083.53 29077.29 30933.29 30878.74 30857.54
allowed at base rate
Interest on Loan
(3) The repayment for each of the year of the tariff period 2019-24 shall be deemed to
be equal to the depreciation allowed for the corresponding year/period. In case of de-
capitalization of assets, the repayment shall be adjusted by taking into account
cumulative repayment on a pro rata basis and the adjustment should not exceed
cumulative depreciation recovered upto the date of de-capitalisation of such asset.
(4) Notwithstanding any moratorium period availed by the generating company or the
transmission licensee, as the case may be, the repayment of loan shall be considered
from the first year of commercial operation of the project and shall be equal to the
depreciation allowed for the year or part of the year.
(5) The rate of interest shall be the weighted average rate of interest calculated on the
basis of the actual loan portfolio after providing appropriate accounting adjustment for
interest capitalized: Provided that if there is no actual loan for a particular year but
normative loan is still outstanding, the last available weighted average rate of interest
shall be considered: Provided further that if the generating station or the transmission
system, as the case may be, does not have actual loan, then the weighted average
rate of interest of the generating company or the transmission licensee as a whole
shall be considered.
(6) The interest on loan shall be calculated on the normative average loan of the year
by applying the weighted average rate of interest.
(7) The changes to the terms and conditions of the loans shall be reflected from the
date of such re-financing.”
255. The salient features for computation of interest on loan are summarized
below:
c) The repayment for the year has been considered equal to the depreciation
allowed for that year;
d) Interest on loan has been calculated on the normative average loan of the
year by applying the weighted average rate of interest for 2018-19, which is
subject to truing-up.
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Gross Normative Loan 335278.47 339021.99 387485.74 387029.72 386951.83
Cumulative Repayment up 164733.83 188876.16 214160.52 241482.36 269161.00
to Previous Year
Net Loan-Opening 170544.64 150145.83 173325.22 145547.36 117790.83
Addition due to additional 3743.53 48463.75 -456.02 -77.89 75.22
capitalisation
Repayment during the year 24588.73 26492.50 28243.13 28223.66 28223.56
Less: Repayment 446.40 1208.14 921.29 545.02 390.71
adjustment on account of
de-capitalization
Net Repayment 24142.34 25284.36 27321.84 27678.64 27832.85
Net Loan-Closing 150145.83 173325.22 145547.36 117790.83 90033.20
Average Loan 160345.23 161735.52 159436.29 131669.10 103912.02
Weighted Average Rate of 8.790% 8.790% 8.790% 8.790% 8.790%
Interest on Loan
Interest on loan 14094.35 14216.55 14014.45 11573.71 9133.87
Depreciation
257. Regulation 33 of the 2019 Tariff Regulations provides as under:
“33. Depreciation
(1) Depreciation shall be computed from the date of commercial operation of a
generating station or unit thereof or a transmission system or element thereof including
communication system. In case of the tariff of all the units of a generating station or all
elements of a transmission system including communication system for which a single
tariff needs to be determined, the depreciation shall be computed from the effective
date of commercial operation of the generating station or the transmission system
taking into consideration the depreciation of individual units: Provided that effective
date of commercial operation shall be worked out by considering the actual date of
commercial operation and installed capacity of all the units of the generating station or
capital cost of all elements of the transmission system, for which single tariff needs to
be determined.
(2) The value base for the purpose of depreciation shall be the capital cost of the asset
admitted by the Commission. In case of multiple units of a generating station or
multiple elements of a transmission system, weighted average life for the generating
station of the transmission system shall be applied. Depreciation shall be chargeable
from the first year of commercial operation. In case of commercial operation of the
asset for part of the year, depreciation shall be charged on pro rata basis.
(4) Land other than the land held under lease and the land for reservoir in case of
hydro generating station shall not be a depreciable asset and its cost shall be excluded
from the capital cost while computing depreciable value of the asset.
(5) Depreciation shall be calculated annually based on Straight Line Method and at
rates specified in Appendix-I to these regulations for the assets of the generating
station and transmission system: Provided that the remaining depreciable value as on
31st March of the year closing after a period of 12 years from the effective date of
commercial operation of the station shall be spread over the balance useful life of the
assets.
(6) In case of the existing projects, the balance depreciable value as on 1.4.2019 shall
be worked out by deducting the cumulative depreciation as admitted by the
Commission upto 31.3.2019 from the gross depreciable value of the assets.
(7) The generating company or the transmission licensee, as the case may be, shall
submit the details of proposed capital expenditure five years before the completion of
useful life of the project along with justification and proposed life extension. The
Commission based on prudence check of such submissions shall approve the
depreciation on capital expenditure.
(8) In case of de-capitalization of assets in respect of generating station or unit thereof
or transmission system or element thereof, the cumulative depreciation shall be
adjusted by taking into account the depreciation recovered in tariff by the de-
capitalized asset during its useful services.
258. In line with Regulation 33 of the 2019 Tariff Regulations, the cumulative
for the purpose of tariff. Further, the value of freehold land included in the average
capital cost has been adjusted while calculating depreciable value for the purpose of
259. The depreciation allowed as above is subject to revision at the time of truing
260. The Petitioner has claimed following amounts of unrecovered depreciation for
(Rs. in lakh)
2020 2021 2022 2023 2024 Total
538.14 1297.37 813.33 378.54 207.54 3234.92
261. In line with our discussion and decision on this issue, in paragraph 133 and
paragraph 134 of this order, the prayer of the Petitioner to allow the recovery of
is not allowed, as the same is not in conformity with the provisions of the 2019 Tariff
Regulations.
O&M expenses
262. The O&M expenses claimed by the Petitioner for the 2019-24 tariff period are
as below:
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Normative O&M Expenses as per 23635.50 24465.00 25326.00 26218.50 27132.00
Regulation 35(1)(i) of the 2019
Tariff Regulations
Water Charges as per Regulation 1930.35 2117.58 2329.34 2562.28 2826.22
35(1)(6) of the 2019 Tariff
Regulations
Security expenses as per 808.07 882.05 956.60 1037.45 1125.15
Regulation 35(1)(6) of the 2019
Tariff Regulations
Capital spares as per Regulation 170.02 55.00 850.00 0.00 0.00
35(1)(6) of the 2019 Tariff
Regulations
Rental and Conveyance 75.65 79.43 83.40 87.57 91.95
Expenses in lieu of 2nd township
O&M expenses for RO Plant 593.40 623.07 880.57 924.60 970.83
Total O&M Expenses 27212.99 28222.13 30425.91 30830.40 32146.15
263. The Respondent KSEBL has contended that claim for additional O&M
expenses in lieu of 2nd township and Ash disposal expenses is not in line with the
2019 Tariff Regulations and, therefore, may be rejected. It has further contended that
there is no provision under the 2019 Tariff Regulations to claim additional O&M
expenses to run the Reverse Osmosis plant and the same may also be disallowed.
264. Regulation 35(1)(i) of the 2019 Tariff Regulations provide the following
Normative O&M expense norms for 500 MW series for coal based generating
stations:
(Rs. lakh/MW)
2019-20 2020-21 2021-22 2022-23 2023-24
22.51 23.30 24.12 24.97 25.84
has claimed the following Normative O&M expenses for the 2019-24 tariff period:
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
23635.50 24465.00 25326.00 26218.50 27132.00
266. The Normative O&M expenses claimed by the Petitioner is in accordance with
Water Charges
“(6) The Water Charges, Security Expenses and Capital Spares for thermal
generating stations shall be allowed separately after prudence check:
Provided that water charges shall be allowed based on water consumption
depending upon type of plant and type of cooling water system, subject to prudence
check. The details regarding the same shall be furnished along with the petition;
xxxxx
268. The Petitioner has claimed Water charges (on projected basis) in terms of
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
1930.35 2117.58 2329.34 2562.28 2826.22
269. In support of the projected water charges claimed, the Petitioner has
generation during the year and the estimated Specific Raw water consumption per
unit. It has submitted that Specific Raw water consumption in 2018-19 is 2.31 m3 per
Megawatt hour (MWh) which is below the Ministry of Environment & Forest
guidelines and the same has been projected during the 2019-24 tariff period. The
Petitioner has submitted that DVC vide its Office Memorandum dated 23.7.2019 had
revised the Water tariff for Industrial consumers (drawing water from reservoir/ river)
10% effective from 1.4.2019. Considering the revised tariff including the annual
m3/MWh, the Petitioner has prayed that the Commission may approve the projected
Raw Water charges for the 2019-24 tariff period as claimed. The Petitioner has also
furnished the copy of the DVC OM dated 23.7.2019 along with the communication
271. Considering the fact that Water charges projected by the Petitioner for the
2019-24 tariff period is based on actual consumption of water during the year 2018-
19 and the tariff rates specified by DVC for water, we allow the projected water
charges claimed by the Petitioner for the 2019-24 tariff period. However, the
projected water charges allowed are subject to truing-up, based on prudence check
Security Expenses
272. The first proviso to Regulation 35(6) of the 2019 Tariff Regulations provide as
under:
“Provided further that the generating station shall submit the assessment of the security
requirement and estimated expenses;
period is as under:
(Rs. in crore)
2014-15 2015-16 2016-17 2017-18 2018-19
Plant Security 5.51 6.44 6.46 6.44 6.96
Other Security related - AMC 0.00 0.02 0.12 0.15 0.35
Total Security Expenses 5.51 6.46 6.59 6.59 7.32
274. The Security Expenses projected by the Petitioner for the 2019-24 tariff period
is as under:
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Plant Security 754.88 818.39 887.23 961.86 1042.78
Other Security related AMC 38.40 41.64 45.14 48.93 53.05
Total Security Expenses 793.29 860.02 932.37 1010.80 1095.83
275. In addition to the above, the Petitioner has claimed projected additional
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Issuance of smart card 5.00 5.50 6.05 6.66 7.32
Purchase of Security gadgets 8.00 8.80 9.68 10.65 11.71
AMC for Turnstile 1.58 6.93 7.62 8.39 9.22
AMC for Boom Barrier 0.20 0.80 0.88 0.97 1.06
Total 14.78 22.03 24.23 26.66 29.32
276. Accordingly, the total Security Expenses (on projection basis) claimed by the
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Security Expenses 793.29 860.02 932.37 1010.80 1095.83
Additional Security Expenses 14.78 22.03 24.23 26.66 29.32
Total Security expenses 808.07 882.05 956.60 1037.45 1125.15
277. Considering the fact that the additional capitalization towards the Construction
of Boom Barrier has not been allowed in this order, the expenditure for AMC of the
said asset is not allowed as part of the security expenses. Accordingly, the projected
Security expenses allowed for the 2019-24 tariff period are as under.
Capital spares
278. The last proviso to Regulation 35(6) of the 2019 Tariff Regulations provide as
under:
“Provided also that the generating station shall submit the details of year-wise actual
capital spares consumed at the time of truing up with appropriate justification for
incurring the same and substantiating that the same is not funded through
compensatory allowance as per Regulation 17 of Central Electricity Regulatory
Commission (Terms and Conditions of Tariff) Regulations, 2014 or Special Allowance
or claimed as a part of additional capitalisation or consumption of stores and spares
and renovation and modernization.”
279. The Capital spares claimed by the Petitioner in terms of Regulation 35(6) of
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
170.00 55.00 850.00 0.00 0.00
280. The Petitioner has submitted that it requires several capital spares for critical
equipment during the 2019-24 tariff period in order to ensure the reliability and
availability of the main equipment. It has further submitted that these capital spares
have not been included in the additional capitalization claims projected by the
Petitioner above. Accordingly, the Petitioner has submitted that the Commission may
(Rs. in lakh)
Item/Activity 2019-20 2020-21 2021-22 2022-23 2023-24
Coal Mill Gearbox 0.00 0.00 400.00 0.00 0.00
Crusher Rotor Assembly 0.00 0.00 150.00 0.00 0.00
(Capital Spare -Imported)
Procurement of 400 kV Breaker 0.00 55.00 0.00 0.00 0.00
TDBFP Recirculation valve 170.00 0.00 0.00 0.00 0.00
TG Bearing Set 0.00 0.00 300.00 0.00 0.00
Total Capital Spares 170.00 55.00 850.00 0.00 0.00
Regulations that the Petitioner is required to furnish proper details and justification,
the actually consumed capital spares, at the time of truing up of tariff. Therefore, the
spares consumed, at the time of truing-up of tariff in terms of the last proviso to the
said regulation and the same will be considered in accordance with law.
282. In addition to the normative O&M expenses, the Petitioner has claimed Rental
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
75.65 79.43 83.40 87.57 91.95
283. The Petitioner has considered the incremental rate of 5% per annum on the
average of the total expenditure incurred during the 2014-19 tariff period, to claim the
284. The reasons furnished by the Petitioner in support of the claim are the same
as those furnished by the Petitioner for the 2014-19 tariff period as extracted in
paragraph 145 and paragraph 146 of this order. The Commission, after considering
the submissions of the Petitioner had rejected the claim of the Petitioner under this
head in paragraph 149 of this order. In line with the said decision, the additional
O&M expenses for Rental and Conveyance Expenses in lieu of 2nd township for the
285. The Petitioner has also claimed additional O&M Expenses towards Reverse
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
593.40 623.07 880.57 924.60 970.83
286. The Petitioner has submitted that in order to comply with the statutory
directions, it has to run the Reverse Osmosis (RO) Plant. It has also submitted that
with the commissioning of the RO Plant, the Petitioner is required to incur substantial
expenditure towards O&M expenses of the RO Plant on a daily basis. While pointing
out that O&M expenses mainly consist of cost towards consumables and service
cost, the Petitioner has submitted that the consumable cost mainly consists of cost
Petitioner, as per preliminary estimates and considering the chemical cost, the rate
an annual escalation of 5%, has projected the cost of consumables during the 2019-
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Chemical consumables 442.44 464.56 487.79 512.18 537.79
Replacement of Cartridge &
90.36 94.88 99.62 104.60 109.83
Membrane
Resin and Media top up 9.6 10.08 10.58 11.11 11.67
Maintenance Spares 51.00 53.55 56.23 59.04 61.99
Total Consumables 593.40 623.07 654.22 686.93 721.28
O&M Services 0.00 0.00 226.34 237.66 249.54
Total O&M Expenses 593.40 623.07 880.57 924.60 970.83
287. The O&M expense norms for the thermal generating station covers the O&M
of power plants in general, including equipment’s such as ETP, STP etc., which also
uses the consumables/chemicals and for other plants not having RO system, which
2019 Tariff Regulations provide for the grant of O&M expenses towards Water
2019 Tariff Regulations do not provide for the grant of additional O&M expenses
288. Based on the above discussion, the O&M expenses allowed for the 2019-24
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Normative O&M expenses as 23635.50 24465.00 25326.00 26218.50 27132.00
per Regulation 35(1)(i) of the
2019 Tariff Regulations
Water Charges as per 1930.35 2117.58 2329.34 2562.28 2826.22
Regulation 35(1)(6) of the 2019
Tariff Regulations
Security expenses as per first 807.87 881.25 955.72 1036.48 1124.09
proviso to Regulation 35(1)(6)
of the 2019 Tariff Regulations
Capital spares as per last 0.00 0.00 0.00 0.00 0.00
proviso to Regulation 35(1)(6)
of the 2019 Tariff Regulations
Total O&M Expenses allowed 26373.72 27463.83 28611.06 29817.26 31082.31
Total O&M Expenses claimed 27212.99 28222.13 30425.91 30830.40 32146.15
16/RP/2018 (in Petition No. 152/GT/2015) had allowed the projected ‘Ash disposal’
expenses for the 2014-19 tariff period based on the following observations:
“42. In the present case, the Petitioner is only claiming the cost incurred by it pertaining
to the activity of ash disposal during the period 2014-18 periods on the same basis as
was approved during 2011-14. The Additional O&M expenses for Ash Disposal claimed
by the Petitioner in the impugned Order is basically due to limited ash pond capacity,
which require mandatory disposal of ash from the pond, as per the statute prescribed
by MoEF and not of the nature of expenses claimed by NTPC, in Petition No.
172/MP/2016. Hence, there is an error apparent on the face of the record and the
expenditure of ₹260.90 lakh claimed by the Petitioner for Ash disposal during 2014-18
is allowed. However, the same will be trued up at the end of tariff period with prudence
check and the Petitioner is directed to submit the relevant documents in support of the
said expenditure.”
actual ‘Ash disposal’ expenses for the 2014-19 tariff period as under:
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19 Total
6098.44 3791.36 3647.73 3320.87 3340.46 20198.86
291. The Petitioner has claimed Ash disposal expenses (on projection basis) for
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
3425.52 3416.16 3416.16 3416.16 3425.52
292. The Petitioner has submitted that on account of dropping of Ash conveying
pipeline, due to uncertainty in the allocation of the abandoned mines for ash disposal
by ECL management, the ash disposal expenses may be allowed. It is observed that
the coal received at Maithon site is of sub-optimal quality as compared to the design
coal and ash content is to the tune of 43% to 46% (approx.). However, due to limited
capacity of the Ash ponds, the Petitioner has considered the option of disposing
unutilized ash through bulkers to sites for back filling of mines and to other approved
locations for land filling, thereby incurring the cost towards excavation and
transportation of pond ash. The projected ash disposal expenses claimed by the
Period Consumption Ash Fly Ash Fly Ash Bottom Pond Ash
Plan Generation (gainful (stowing Ash Ash Disposal
(As Per 85% PLF) (MT) utilisation) of (MT) (MT) cost
(MT) (MT) mines) (Rs. in lakh)
(MT)
2019-20 4598744 1868010 373602 1338016 311335 159404 3425.6
2020-21 4586180 1862906 372581 1334361 310484 158968 3416.2
2021-22 4586180 1862906 372581 1334361 310484 158968 3416.2
2022-23 4586180 1862906 372581 1334361 310484 158968 3416.2
2023-24 4598744 1868010 373602 1338016 311335 159404 3425.6
expenses for Ash disposal expenses is not in line with the 2019 Tariff Regulations
294. The matter has been considered. We observe that the Ash disposal expenses
claimed by the Petitioner and allowed to this generating station since COD, is in view
of limited capacity of the Ash ponds and the mandatory ash disposal in terms of the
capacity of ash ponds and the fact that the Petitioner is under an obligation of
meeting 100% ash utilization as per MOEF & CC notification, we, in line with our
quoted in paragraph 289 above), allow the expenses claimed towards Ash disposal,
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
3425.52 3416.16 3416.16 3416.16 3425.52
295. This is however subject to prudence check at the time of truing-up of tariff of
the generating station. The Petitioner is directed to award Ash disposal contracts
based on the transparent bidding process and shall submit the details of bidding
while claiming the actual ash disposal expenses during truing up of tariff for the
2019-24 tariff period. Considering the fact that the reimbursement of ash disposal
expenses is allowed based on the special circumstances (limited ash pond storage)
for this generating station, these expenses are not made part of the O&M expenses
allowed and the consequent annual fixed charges determined in this order.
296. Accordingly, the total O&M expenses allowed to the generating station for the
Operational Norms
297. The operational norms considered by the Petitioner in Form-3 of the petition,
is as under:
298. In terms of Regulation 49(A)(a) of the 2019 Tariff Regulations, the NAPAF of
the thermal generating station is 85%. Hence, the NAPAF of 85% as considered by
the Petitioner is in order and the same has been considered for the purpose of tariff.
299. Regulation 49(C)(b)(i) of the 2019 Tariff Regulations provides for Station Heat
Rate as under:
Provided further that in case pressure and temperature parameters of a unit are
different from above ratings, the maximum design unit heat rate of the nearest class
shall be taken:
Provided also that where unit heat rate has not been guaranteed but turbine cycle
heat rate and boiler efficiency are guaranteed separately by the same supplier or
different suppliers, the unit design heat rate shall be arrived at by using guaranteed
turbine cycle heat rate and boiler efficiency:
Provided also that where the boiler efficiency is below 86% for Sub-bituminous Indian
coal and 89% for bituminous imported coal, the same shall be considered as 86%
and 89% respectively for Sub-bituminous Indian coal and bituminous imported coal
for computation of station heat rate:
Provided also that maximum turbine cycle heat rate shall be adjusted for type of dry
cooling system:
Provided also that if one or more generating units were declared under commercial
operation prior to 1.4.2019, the heat rate norms for those generating units as well as
generating units declared under commercial operation on or after 1.4.2019 shall be
lowest of the heat rate norms considered by the Commission during tariff period
2014-19 or those arrived at by above methodology or the norms as per the sub-
clause (C)(a)(i) of this Regulation:):”
300. The Petitioner in Form-2 of the petition has furnished the Boiler Efficiency as
87.80% and the Turbine Heat Rate as 1945 kCal/kWh. Considering the operating
this, the Petitioner in Form-3 of the petition has considered the SHR of 2388
kCal/kWh for the 2019-24 tariff period, seeking relaxation in the Station Heat Rate on
“152. We have examined the matter. The issue of deviation in the design boiler efficiency
and the actual boiler efficiency was raised by the Petitioner in Petition No. 274/2010 and the
Commission after considering the submissions of Petitioner and the actual values of the PG
test vide had relaxed the norms of the station heat rate vide order dated 19.11.2014……
Xxxxx
153. The Commission in 2009-14 tariff allowed the GSHR of 2425 kCal/kWh with a rider that
up to 2360.47 kCal/kWh should be passed on to the beneficiaries in full and the benefit of
heat rate achieved below 2360.47 kCal/ kWh, may be retained by the Petitioner. The
Petitioner has submitted that Boiler Efficiency is 85.5% by using actual coal received by the
Petitioner as the quality of coal received remains the same. By considering the boiler
efficiency of 85.5% and Turbine cycle heat rate of 1945 Kcal/kWh, the Gross Station Heat
Rate of the generating station works out as 2377 kCal/kWh (1.045x1945/0.855) for the
period 2014-19. However, the Petitioner has considered the Gross Station Heat Rate of
2375 kCal/kWh. The GSHR claimed by the Petitioner during 2014-19 is less than the GSHR
allowed during 2009-14 period. In view of this, the Gross Station Heat Rate of 2375 Kcal/
kWh for the period 2014-19 has been allowed.” (emphasis supplied)
301. The Petitioner has submitted that due to availability of sub-optimal quality of
coal in the region, the quality of the actual coal received at the plant has not
improved and, therefore, the condition remains the same till date. Accordingly, the
Petitioner has prayed that the Commission may approve the boiler efficiency at
85.5% as obtained during the PG test with the actual coal for the 2019-24 tariff
period, in exercise of the power vested under Regulation 3(25) read with Regulation
Boiler Efficiency of 85.5% as the quality of coal received remain suboptimal and with
the Turbine Heat Rate of 1945 kCal/kWh, the Gross Station Heat Rate works out as
302. The Commission vide ROP of the hearing dated 2.6.2020 had directed the
Petitioner to furnish the actual coal quality (GCV, proximate and ultimate analysis)
coal, design coal and best coal envisaged by the OEM for guaranteed parameter of
boiler efficiency. In response, the Petitioner vide affidavit dated 20.6.2020 has
a) Since the current coal quality has not improved vis-à-vis the coal quality that
was there at the time of PG test, the Petitioner has proposed to consider the
Boiler efficiency as 85.5% in the 2019-24 tariff period as well.
b) The proximate and ultimate analysis data submitted by the Petitioner for the
entire period of 2019-20 is not a correct representative of the coal that will be
fired in the balance period of the control period. The same is on account of the
fact that imported coal of high quality (which was initiated during H2 of 2018-
19 due to coal scarcity at that time) was used along with domestic coal for first
5 months. Approximately 1.98 lakh MT of Imported coal was received in H2 of
2018-19 with opening stock of ~32000 MT in April 2020 and ~28000 MT
received in Q1 of 2019-20.
c) Since coal supplies from domestic sources have improved after the said
period, albeit the quality has not improved. It is most likely that only domestic
coal shall be fired in the balance control period as well. Further, the coal
quality is likely to be the same as in the latest 9 months when only domestic
coal was fired. Accordingly, for the purposes of comparing the coal quality
during PG test and the present/future coal quality of domestic coal, the
Petitioner proposes to discard the data for first two months of 2019-20 and
consider the coal characteristics for the last 9 months i.e. September 2019 to
May 2020.
d) With respect to coal quality during the PG test, the ash content has reduced
slightly by 2.11% from 42.98% to 40.87% (against design of 36.19%), which
has resulted in small increase in GCV by 109 kCal/kg, which should
theoretically improve the boiler efficiency. Simultaneously, the moisture
content in the coal has also increased by 0.59%, which causes some more
heat loss due to evaporation and hence causes decrease in efficiency. The
correction to be applied for variation in GCV and moisture may be done by
linear approximation of the correction curves for GCV and moisture variation
supplied by the OEM. A copy of the correction curves for GCV and Moisture is
annexed herewith.
e) The GCV correction curve shows that for an improvement of GCV of 240
kCal/kg (from 4431 to 4671), the efficiency improves by 0.28%. Similarly, for
an increase in moisture by 0.4% (from 7.11 to 7.61), the efficiency drops by
0.05%. Applying these corrections to the PG test result of 85.5%, the
theoretical net improvement in efficiency comes to only 0.049%
(109x0.28/240 – 0.59x0.05/0.5) i.e. 85.5% improves to 85.55% only. Thus, the
current coal quality should theoretically yield approximately the same
efficiency as was measured during PG test i.e. 85.5%.
304. The matter has been considered. The Commission in its orders relating to the
2009-14 and 2014-19 tariff periods had considered the Boiler Efficiency as 85.5%
against the Design Efficiency of 87.8% for the generating station, in relaxation of the
Tariff Regulations, based on the lower boiler efficiency achieved during PG test due
to poor quality of coal having more ash content and more moisture. The details of the
coal quality (domestic coal) furnished by the Petitioner, in response to the ROP
dated 2.6.2020, indicate that there is slight improvement in the GCV of coal and also
some increase in moisture is observed, as compared to the coal burnt at the time of
PG test. It is also observed that the variation in quality of coal from PG test quality to
the quality of coal received during the year 2019-20 has improved the efficiency by
0.05% only. The COD of the generating station is 24.7.2012. The Petitioner was
granted relaxation in Boiler Efficiency due to poor quality of coal received during the
previous tariff periods, as stated above. The question for consideration is ‘whether
the relaxation granted to the Petitioner during the previous tariff periods is required to
305. The Petitioner has considered PG Test performance based on the quality of
coal permissible to the Boiler and Plant characteristics. Also, the PPA was executed
had undergone changes due to receipt of poor quality of coal in comparison to the
temporary and cannot alter the plant characteristics on a perpetual basis. Coal is
being procured by the Petitioner after execution of the Fuel Supply Agreement with
the coal supplier. It was the obligation of the Petitioner, while entering into FSA, to
any other alternate sources of coal. The Petitioner, having not been prevented from
on the burden on the beneficiaries on this count, more so when the Petitioner has
not fulfilled the said obligations. It is further noticed that the Petitioner has not
the good quality of coal. In our view, the relaxation of SHR of the generating station,
in perpetuity, based on coal quality, will render the operational parameters specified
under the 2019-24 Tariff Regulations for all generators redundant, as more often
than not, the coal quality may no match with design coal. In view of this, there is no
merit in the prayer of the Petitioner for relaxation of SHR on grounds of deterioration
in quality of coal. The Petitioner is directed to ensure the required quality of coal as
as specified in Regulation 49(C)(b)(i) of the 2019 Tariff Regulations, the GSHR of the
generating station works out as 2326.03 kcal/kWh [1945*1.05)/0.878] and the same
306. Regulation 49(E)(a)(ii) of the 2019 Tariff Regulations provides for Auxiliary
MW and above have Steam-driven Boiler Feed Pumps & Induced Draft Cooling
Tower. Therefore, both the units qualify for a normative APC of 6.25% (5.75% for
Units having Steam-driven BFP and additional 0.50% for having Induced Draft
Cooling Tower). In view of the above, the normative APC of 6.25% as considered by
fuel oil consumption of 0.50 ml/kWh for Coal based generating stations. Hence, the
Secondary fuel oil consumption considered by the Petitioner in terms of the said
regulation is allowed.
provides as under:
(v) Operation and maintenance expenses, including water charges and security
expenses for one month.”
310. The Petitioner has claimed the cost for fuel component in working capital
based on price and on ‘as received’ GCV of coal procured and burnt for the months
of October 2018, November 2018, and December 2018 and Secondary fuel oil for
(Rs. in lakh)
Year 2019-20 2020-21 2021-22 2022-23 2023-24
Cost of coal for 50 days 28573.30 28573.30 28573.30 28573.30 28573.30
Cost of Secondary fuel oil 2 279.86 279.09 279.09 279.09 279.86
months
311. The computation of Energy Charges and Fuel component (coal cost) in
working capital during the 2019-24 tariff period is based on “as received GCV” of
coal. The Petitioner has claimed Energy Charge Rate (ECR) of 281.01 paise/kWh,
based on the Weighted Average Price, GCV of coal (on ‘as received’ basis) and Oil
procured and burnt for the three months (October, 2018 to December, 2018). The
cost for fuel components in working capital has been computed deducting the 85
kCal per Kg from the Weighted Average Gross Calorific Value of coal ‘as received’
on account of the variation during storage, as specified under Regulation 43(2) (b) of
the 2019 Tariff Regulations and considering the GCV and cost of coal procured and
GCV and cost of Secondary fuel oil procured for the three months (October, 2018 to
(Rs. in lakh)
Year 2019-20 & 2023-24 2020-21 to 2022-23
Working Capital towards Cost of Coal for stock 11266.15 11266.15
(20 days of generation at NAPAF)
Working Capital towards Cost of Coal for 16899.22 16899.22
Generation (30 days of generation at NAPAF)
Coal cost for 50 days of generation at NAPAF 28165.37 28165.37
Cost of Secondary fuel oil 315.50 314.64
(2 months of generation at NAPAF)
Maintenance Spares
312. The Petitioner has claimed maintenance spares in working capital as under:
313. Regulation 34(1)(a)(iv) of the 2019 Tariff Regulations provide for maintenance
spares @ 20% of the O&M expenses, including water charges and security
as under:
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
5274.74 5492.77 5722.21 5963.45 6216.46
Receivables
314. Regulation 34(1)(a)(iv) of the 2019 Tariff Regulations provide for Working
charges for sale of electricity calculated on the normative annual plant availability
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Receivables equivalent to 45 12427.67 13037.68 13544.78 13387.75 13244.30
days of capacity charges
Receivables equivalent to 45 25582.51 25582.51 25582.51 25582.51 25582.51
days of energy charge
315. O&M expenses for 1 month as claimed by the Petitioner for the purpose of
(Rs. in lakh)
2019-20 2020-2021 2021-22 2022-23 2023-24
2267.70 2351.80 2535.50 2569.20 2678.80
316. Regulation 34(a)(vi) of the 2019 Tariff Regulations provides for Working
Capital towards O&M expenses including water charges and security expenses for
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
2197.81 2288.65 2384.26 2484.77 2590.19
“(3) Rate of interest on working capital shall be on normative basis and shall be
considered as the bank rate as on 1.4.2019 or as on 1st April of the year during the
tariff period 2019-24 in which the generating station or a unit thereof or the
transmission system including communication system or element thereof, as the case
may be, is declared under commercial operation, whichever is later:
Provided that in case of truing-up, the rate of interest on working capital shall be
considered at bank rate as on 1st April of each of the financial year during the tariff
period 2019-24.”
318. In line with the Regulation 34(3) of the 2019 Tariff Regulations, the rate of
interest on working capital for 2019-20 is 12.05% (i.e. 1 year SBI MCLR of 8.55% as
on 1.4.2019 + 350 bps) and for 2020-21 is 11.25% (i.e. 1 year SBI MCLR of 7.75%
as on 1.4.2020 + 350 bps). However, since tariff of the generating station is being
determined by this order during the year 2021-22, the SBI MCLR as on 1.4.2021
(7.75%). Since, the rate of interest on working capital is subject to truing-up, based
on the bank rate as on 1st April of each financial year, we consider it prudent to allow
the rate of interest as on 1.4.2021 for the subsequent financial years. Accordingly,
the rate of interest considered is 12.05% for 2019-20, 11.25% for 2020-21 and for the
subsequent years of the tariff period, the rate of interest of 10.50% (i.e. 1 year SBI
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Working Capital for Cost of 11266.15 11266.15 11266.15 11266.15 11266.15
coal towards stock (20 days
of generation at NAPAF)
319. In addition to the components of the annual fixed charges allowed under the
on working capital and O&M expenses, the petitioner has also claimed additional tax
separately over and above the annual fixed charges as per the change in law
provisions. The additional tax amount claimed by the Petitioner is Rs.38.28 lakh
320. The matter has been examined. As regards the recovery of additional tax
liability due to implementation of Ind AS, it is observed that the 2019 Tariff
(ROE) with effective tax rate; or the Minimum Alternate Tax (MAT) in case of a
generating company or transmission licensee, as the case may be, paying MAT, of
activities, is considered for the purpose of tax recovery. In the present case, ROE is
allowed for grossing up with MAT rate, as envisaged under the 2019 Tariff
accounting treatment implication and does not result in income from generation
business activity. Similar claim of the Petitioner for the 2014-19 tariff period has been
disallowed in this order. Accordingly, the prayer of the Petitioner for the 2019-24 tariff
period, to allow the recovery of additional tax liability on increased income due to
321. Accordingly, the annual fixed charges approved for the generating station for
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24
Return on Equity 27109.00 29153.01 31044.64 31005.56 30994.24
Interest on Loan 14094.35 14216.55 14014.45 11573.71 9133.87
Depreciation 24588.73 26492.50 28243.13 28223.66 28223.56
O & M Expenses 26373.72 27463.83 28611.06 29817.26 31082.31
Interest on Working 8912.61 8424.18 7949.95 7969.34 7992.01
Capital
Annual Fixed Charges 101078.41 105750.08 109863.23 108589.54 107425.98
Note: (1) All figures are on annualised basis. (2) All figures under each head have been rounded. The figure in total column in
each year is also rounded. As such the sum of individual items may not be equal to the arithmetic total of the column.
322. As stated in paragraph 294 above, the Ash disposal expenses allowed are as
below:
(Rs. in lakh)
2019-20 2020-21 2021-22 2022-23 2023-24 Total
3425.52 3416.16 3416.16 3416.16 3425.52 17099.52
323. The annual fixed charges determined as above are subject to truing-up in
281.01 paise/kWh based on the weighted average price, GCV of coal & Oil procured
and burnt for the preceding three months i.e. October 2018 to December 2018. The
Petitioner did not subtract 85 kCal/kg from Weighted Average Gross calorific value
provided in Regulation 43(2)(b) of the 2019 Tariff Regulations, while computing the
IWC and the energy charge rate. The Commission has adjusted the same in
accordance with the Regulation 43(2)(b) of 2019 tariff regulations. ECR worked out,
based on the operational norms specified under the 2019 Tariff Regulations and on
‘as received’ GCV of coal for the preceding 3 months i.e. October 2018 to December
325. The Fuel component and Energy charges allowed in working capital are as
under:
(Rs. in lakh)
Year 2019-20 and 2023-24 2020-21 to 2022-23
Cost of Coal for stock (20 days) 11266.15 11266.15
Cost of Coal for Generation (30 days) 16899.22 16899.22
Cost of Secondary fuel oil 2 months 315.50 314.64
Energy charges for 45 days 25582.51 25582.51
326. There is variation between the Coal cost, Secondary fuel oil cost and Energy
against those claimed by the Petitioner. This is attributable to the variation between
the values of SHR, GCV and the Cost of coal and Secondary fuel claimed by the
in the Secondary fuel oil, the price and GCV of HFO only (as per consistent
methodology adopted) has been considered after excluding the quantity in stock,
while the Petitioner had considered the combined cost and GCV of LDO and HFO,
including the stock. Similarly, the GCV and landed price of coal, has been arrived at
after excluding the stock of coal, whereas, the Petitioner had included the stock of
coal. The fuel quantity in stock has been excluded to arrive at the exact value of
landed price and GCV of fuel procured during the three months from October 2018
327. The Petitioner, on a month to month basis, shall compute and claim Energy
Charges from the beneficiaries based on the formulae given under Regulation 43 of
328. The Petitioner has also sought reimbursement of fees paid by it for the 2019-
24 tariff period for filing the tariff petition and the publication expenses incurred for
the same. The Petitioner shall be entitled for reimbursement of the filing fees and
publication expenses in connection with the present petition, directly from the
beneficiaries on pro-rata basis in accordance with Regulation 70(1) of the 2019 Tariff
Regulations.
Summary
329. The annual fixed charges allowed for the 2014-19 tariff period (after truing-up)
is as under:
(Rs. in lakh)
2014-15 2015-16 2016-17 2017-18 2018-19
103521.74 104906.37 103399.96 100487.66 99726.57
330. The annual fixed charges approved for the 2019-24 tariff period is as under:
Name of Dep.
Depreciation Gross Depreciation Gross Depreciation Gross Depreciation Gross Depreciation Gross
Sr. Amount
the Assets rates as per Block amount for Block amount for Block amount for Block amount for Block
No. for 2018-
Regulations 2014-15 2014-15 2015-16 2015-16 2016-17 2016-17 2017-18 2017-18 2018-19
19
Land under
A full 0.00% 8635.47 0 17305.94 0 17340.93 0 17341.33 0 17427.03 0
ownership
Land under
B
lease
for
(a) investment in 3.34% 6068.48 202.69 8004.12 267.34 7936.78 265.09 7936.78 265.09 8907.31 297.5
the land
Assets
C purchased
new
Pl &
Machinery in
a.
generating
stations
Steam
electric
NHRB &
(i) 5.28% 372736.3 19680.48 376462.2 19877.21 380837 20108.19 382079.1 20173.77 389131.9 20546.17
waste heat
recovery
boilers
Building &
Civil
d.
Engineering
works
Offices and
(i) 3.34% 2711.34 90.56 2811.1 93.89 2812.63 93.94 2909.02 97.16 10399.72 347.35
showrooms
Containing
thermo-
(ii) electric 3.34% 20269.2 676.99 23623.96 789.04 24300.49 811.64 24311.59 812.01 24333.73 812.75
generating
plant
Containing
hydro-
(iii) electric 3.34% 0.00 0 263.44 8.8 526.88 17.6 526.88 17.6 263.44 8.8
generating
plant
Roads other
(v) than Kutcha 3.34% 2920.61 97.55 5064.62 169.16 5366.43 179.24 5436.96 181.59 2738 91.45
roads
(vi) Others 3.34% 15021.06 501.7 17794.86 594.35 20042.28 669.41 20230.55 675.7 10558.2 352.64
KVA and
over
Switchgear
including
f. 5.28% 13204.1 697.18 13220.88 698.06 13270.68 700.69 13270.68 700.69 13407.67 707.93
cable
connections
Lines on
steel on
(iii) reinforced 5.28% 0.00 0 1.73 0.09 3.47 0.18 1.73 0.09 0 0
concrete
support
Self-
k. propelled 9.50% 287.41 27.3 274.95 26.12 268.7 25.53 298.91 28.4 304.54 28.93
vehicles
(ii) Portable 9.50% 10.18 0.97 10.18 0.97 10.18 0.97 10.18 0.97 8.01 0.76
m. Office
furniture and 6.33% 679.29 43 770.74 48.79 793.91 50.25 770.89 48.8 764.54 48.4
furnishing
(i)
Office
(ii) 6.33% 584.44 37 652.13 41.28 685.24 43.38 684.06 43.3 683.58 43.27
equipment
Internal
wiring
(iii) including 6.33% 588.41 37.25 578.59 36.62 579.64 36.69 579.64 36.69 579.64 36.69
fittings and
apparatus
Telephone
(ii) lines and 6.33% 8.03 0.51 13.51 0.86 15.93 1.01 16.2 1.03 13.19 0.84
telephones
I. T
Equipment
p. 15.00% 246.44 36.97 265.7 39.86 252.74 37.91 255.11 38.27 291.12 43.67
including
software
Any other
assets not
q. 5.28% 387.17 20.44 388.38 20.51 388.59 20.52 382 20.17 386.19 20.39
covered
above
TOTAL 451342 22975.28 465835 23538.4 473739.8 23888.46 475316.5 23965.86 478452.8 24215.54
Weighted
Average
5.09% 5.05% 5.04% 5.04% 5.06%
rate of
depreciation