Module 4
Module 4
Presents
Via
PMA
1
Module # 4
6. Determine value earned (what are you getting for money and time
allocated).
7. To provide feedback to all shareholders.
2. BCWP The budgeted cost for the work that was performed.
3. ACWP The actual cost for the work that was performed.
2
4. BAC The total budget at the completion of the project.
Now that we understand the all of the necessary terms, let’s see exactly
how the earned value system works.
A task is scheduled to take 5 days to complete and each of the 5 days are
equal.
Each day of the 5-day task is scheduled to cost $100, so the scheduled
cost for the whole task is $500.
Therefore:
The budget cost for the work scheduled (BCWS) is what?_ _ _ _ _ It
is $500.
Now, at the end of 5 days, you determine that only 3 days of the task are
complete (you do not receive credit for any partial days). See the center
section of the chart on page 61.
3
Now, accounting hands you a report that tells you that the actual cost for 5
days of effort but only 3 completed days of work was $400. See the right
hand section of the chart on page 61.
Now let’s graph the data. See the chart on page 62.
4
EARNED VALUE TECHNIQUE
5
EARNED VALUE TECHNIQUE
900
800
700
667
600
ACWP
500
COST
BCWS
400 BCWP
300
200
100
1 2 3 4 5 6 7 8 9
TIME
6
Now lets draw a simple graph with cost as the vertical (Y) axis and time (days) as the
horizontal (X) axis.
Plot BCWS at $500 and 5 days. This was the plan (schedule). Draw a line between
zero, zero and $500, 5 days.
Now plot BCWP at 5 days (it took you 5 days to complete only 3 days worth of work).
You earned $300 (this is what you actually accomplished). Draw a line between zero,
zero and $300, 5 days. Extend the BCWP line until it intersects the $500 line
(BCWS). Draw a vertical line through this point. This tells you that at the current rate
of progress, the task will complete at about 8.5 days.
Now plot ACWP at the $400 you actually spent and the 5 days it took you. Draw a line
between zero, zero and $400, 5 days. Extend the ACWP line until it intersects the 8.5
day vertical line. Draw a horizontal line back to the vertical (cost) axis. This tells you
that your estimate at completion (EAC) is $667.
Now you know the task will take 8.5 days and cost $667 at completion.
If you have a ten-task project, you calculate BCWS, BCWP and ACWP for each task,
the same as we have done above. You then sum all of the task and you plot the
totals. This will tell you where you are, when you will finish and how much the project
will cost at finish.
The same process works for a hundred or thousand task project. However, manually
handling the data gets very labor intensive for larger projects. There are many
software programs available to handle large volumes of data. Microsoft project is one
of them.
7
5. The team should report on previous action assignments.
1. Is this project on schedule? If no, has the end date been extended? If
yes, has the customer been notified?
7. What is the EAC (Estimated Cost at Completion)? How did you arrive at your
EAC?
Summary Lessons
8
4. Key steps to implementation are:
- Ensure that cost accounts, reports and work packages are properly
sized:
Must be manageable, have organizational accountability and be
realistic in terms of effort, time and costs.
- Be willing to re-plan:
The best-laid plans go astray, change is inevitable.