MOS Genset
MOS Genset
LTD
METHOD OF STATEMENT
SUPPLY OF DIESEL GENERATORS WITH INSTALLATION AND COMMISSIONING
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
SCOPE
This Method Statement applies to all installations of emergency and Diesel Generator Sets at site.
Manpower and equipment shall be organized to meet the schedule as per the approved program. This
method Statement shall cover the Transport, Loading/Offloading, Installation and Commissioning of
PURPOSE
The purpose of this Method Statement is to describe the details used and controls to be carried out for
the installation of Diesel Generator Set to ensure that it complies with Project requirements,
specifications.
Strictly followed as per the manufacturer’s Health and Safety recommendations for handling and
use of the materials.
Ensure all involved personnel shall be aware of the same.
Specific safety measures have to follow as applicable, and all the safety measures are covered
separately in the project safety plan.
PERMIT TO WORK
Permit to Work (PTW) requirements, both internal and external, in this section. This should cover all
hazardous activities such as Hot Works, Lifting Operations, working at Height, LOTO (Lock-Out Tag-Out),
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
OPERATION
MATERIALS:
This means all items covering the materials or equipment delivered to the site must be incorporated
Equipment:
Generators
Transformers
VCB breakers
RMU’S
Mobile Crane
Insulation Test Meter, Earth Resistance Tester
Multi meter Tester
Mechanical Test Tools: Torque Wrench.
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
TOOLS:
MANPOWER:
Site Manager
Safety officer (Tamimi)
Electrical Engineer (Tamimi)
Site Supervisor
Electrical Technician
Mechanical Technician
Driver
Crane Operator
Rigger
Permit receiver (Tamimi)
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
RESPONSIBILITIES
Project Manager:
Ensure all required submittals area made and required plant / tools/ material and manpower is
available.
Ensure all unloading of material area is according to approvals, contract specifications, approved
drawings, and safety measures are all implemented.
Ensure necessary coordination with all involved for timely completion of job.
To ensure that all the equipment and material required executing the work are available
according to the planned construction program.
To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper
execution of the works.
Site Supervisor:
Ensure implementation of all safety measures and procedures specific to the nature
To ensure that all project personnel / site execution team is fully aware of their responsibilities
and have full understanding of related safety rules, procedures.
To maintain a continuous inspection / surveillance of site activities, implementation of policies,
advise.
Specification, approved method statement and the shop drawings.
To provide all necessary information and distribute responsibilities to his construction.
To monitor the progress of work in relation with the work program and to report to the Project
Manager.
To co-ordinate with the safety officer and to ensure that the works are carried out in safe
practicing method
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
DRIVING PERSONNEL AND EQUIPMENT TO SITE:
LIFTING EQUIPMENT:
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
INSTALLATION AND FIXATION:
Off-Loading:
Arrangement of all necessary crane, rigger & operator documentation for review and approval
including lifting plan.
Use Mobile Crane to off-load the Generator Sets. Capacity of crane shall be capable to carry the
weight of the generator set.
All safety precaution shall be adhered during offloading.
Ensure the safety of equipment’s and workers.
Off load the Generator sets on the designated offloading area.
If the Generator Room is not ready for generator set installation, proper protection of Generator
set shall be provided and cover it.
Pre-Installation:
All materials and documentation relevant to this particular section of works shall be checked
prior to the installation.
Make sure that the generator room is clear and free of debris and foreign materials.
Ensure that the access for generator set installation is free from obstructions.
Installation:
It has been presumed that all related civil works have been completed before installation.
Move the generator from the Altaaqa facility using the crane and/or trailer and set them in site.
Make sure that the generator with regards to the position of cable entries, exhaust system and
ventilation system is correct.
Check mechanical operation of off-loading. Verify that the movement is positive.
Set the generator on its final position on the concrete base.
Install packaged engine generator to provide access, without removing connections or
accessories, for periodic maintenance.
Dress and terminate the incoming and outgoing cables on the generator. Ensure that the cables
are supported properly as per the approved details. Cable glands and lugs shall be from an
approved manufacturer (M.V & L.V cables route will be on cables tray).
After termination works have been completed, clean the generator cable box and ensure that it
is free from foreign materials. Ensure that all the connections are properly tight through the use
of a torque wrench.
Cover the cable boxes. Bolts and nuts must be tightened properly. Make sure that the generator
room is clean and free from foreign materials.
The generator will be connected to the designated earthling point using the earthling cable.
Ensure that workmanship is neat and clean and complying with good construction practices.
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
We’ll custom for each Generator M.V C. B and it will not have connected internally with each
other toavoid circulation current (the connection will be only from BB for customer SWG).
COMMISSIONING:
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
PERSONNEL PROTECTIVE EQUIPMENT:
Safety Helmet
Safety Goggles (during drilling and use of grinders)
Face shield (during grinding)
Safety Footwear (steel toes)
Safety Gloves (for material handling)
Coverall (as protective clothing)
Full Body Harness
Respiratory Mask (if require)
Road Barriers & Signage
HOUSEKEEPING:
Risk Assessment.
ALTAAQA Insurance
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE SPECIFIED.
DIMENSIONS WITH OUT TOLERANCES ARE BASIC.
SIGN
DATE
DRAWING
STATUS
T ITLE:
SINGLE LINE DIAGRAM DRAWN BY: L.B.
Aramco-JAZAN, SS3 , 1-LINE DIAGRAM
APPROVED BY:
PROJECT:
DATE: 05/05/2024
Aramco, JAZAN SCALE: NTS
REF.: Dwg No Sht. No. REV No
HO-PP-16-24 R3 1- 1 0
X
X X X X X
17 m X
X
CB
MV CABLE TO SUB STATION
X
X
29 m
CB
MV CABLE TO SUB STATION
X
X
X
X
CB
MV CABLE TO SUB STATION
5m
X
X
28 m
FEEDER CABLE ROUTE
X X X X X
X
10000 L 10000 L 10000 L
FENCE
6.000
X
X
G3
3.000
3.000
29 m
12.192
2.438
X
G2
X
2.500
RMU
G1
X
STEP-UP TR ANSFOR MERS
2500kVA, 60HZ
X
0.48/13.8kV
X X X
Subject: Work Plan Site Name: Aramco – Jazan
Installation Stage
Installation team will complete site installation, according to the site layout plan as following:
Pre-commissioning stage
1. General visual inspection for all power module component (Engine, Alternator, Radiator and
SWG).
2. Check engine oil level
3. Check the engine water level
4. Check the controller parameter setting
5. Adjust base load application setting for the controller
Commissioning Stage
1. Run the engine from EMCP controller and SWG for warm up
2. Check all engine and engine running parameters
3. Confirm that all parameters within range and trouble shoot any problem if required
4. Install the load share control cable
5. Adjust the controller at load sharing mode
6. Check the communication between all generators
7. Check the transformer TAP setting @13,8 KV
8. Keep the MV CB in open position
9. Run the generator 1
10. Check the voltage and phase sequence of the generator 1/LV side
11. Check the voltage and phase sequence of the remaining generator/LV side
12. Synch the generator together
13. Close the remining generators to busbar
14. After successful synchronization, Closing the MV CB to connect the power plant to load
: ﻓﺎﻛﺲ+966 12 6876080 : ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﻫﺎﺗﻒ21441 ﺟـــــﺪﺓ1588 ﺏ. ﺍﳌﻤﻠﻜﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﺴﻌﻮﺩﻳﺔ | ﺹ، ﺟــــــﺪﺓ23826 ﺣﻲ ﺍﻟﺼﻮﺍﺭﻱ،9397 ، ﻃﺮﻳﻖ ﺍﳌﻠﻚ ﺳﻌﻮﺩ،4299
ﺭﻳﺎﻝ ﺳﻌﻮﺩﻱ100,000,000 | ﺭﺃﺱ ﺍﳌﺎﻝ106542 | ﻋﻀﻮﻳﺔ ﻏﺮﻓﺔ ﲡﺎﺭﻳﺔ4030157553 ﺕ. ﺱ+966 12 6871180
4299 King Saud Street, 9397 As Swaryee Dist. Jeddah 23826, Kingdom of Saudi Arabia | P.O. Box 1588 Jeddah 21441 Saudi Arabia | Tel.: +966 12 6876080 | Fax:
+966 12 6871180 C.R.: 4030157553 | C.O.C.: 106542 | Capital (SR) 100,000,000 | [email protected] | www.altaqaa.com
1.0 Introduction
Earthing of the outgoing cable, from the tee-off circuit breaker, is achieved by the use
of the circuit breaker and in series with an off-load isolator/selector switch. This
ensures that the tee-off earthing facility has a full short circuit-making capability
comparable with the ring main unit on the VCE6 and transformer earthing levels for
VCE2 units.
2.3.5 Operation
All operating positions and instructions are indicated on the main panel at the front of
the unit. Operation is by means of manually independent spring assisted mechanisms,
which are mounted externally to the gas enclosure.
The tee-off vacuum circuit breaker has two operating positions, 'ON', 'OFF', with an
off-load, interlocked selector allowing earthing of the tee-off circuit.
A single, bar type operating handle is stored at the front of the unit, inside the door.
2.3.7 Interlocks
Positive safety interlocks are incorporated on all switch positions to prevent mal-
operation.
2.3.8 Padlocks
All switch and selector positions can be padlocked.