Method Statement For Testing and Commissioning of MDB, SMDB, DB, MCC & CB
Method Statement For Testing and Commissioning of MDB, SMDB, DB, MCC & CB
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All
previous cover pages are hereby superseded and are to be destroyed.
Rev.
Approv
Date By Chkd. Description and Page Numbers of Revisions
No. als
PROJECT NAME
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Testing and Commissioning of MDB, SMDB, DB,
MCC & CB Page 3 of 12
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.0 PROCEDURE
8.0 ATTACHMENTS
PROJECT NAME
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Testing and Commissioning of MDB, SMDB, DB,
MCC & CB Page 4 of 12
1.0 PURPOSE
The purpose of generating this method statement is to define the procedure step by
step to implement the correct practices for Testing and commissioning of MDB,
SMDB, DB, MCC & CB through the guidelines contained herein so as to ensure that
the job execution complies with specification and serves the intended function to
satisfactory level where applicable in the building of the project.
2.0 SCOPE
This method statement covers all processes related to Testing of MDB, SMDB, DB,
MCC & CB as the following:
This procedure is to be read in conjunction with the relevant ITP, outlining the
responsibility and the quality verification to be performed by various parties.
3.0 REFERENCE
4.0 DEFINITIONS:
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are
specified at relevant steps in the procedure:
- Project Manager
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK
- Project Manager is the overall responsible for the project in terms of work execution, safety, planning &
quality. The Project Manager will maintain the planning progress and coordination of works with the
main contractor.
- The work progress shall be carried out as per planned program and all the
equipment’s required to execute the works shall be available and in good
condition as per project planned.
- Specific attention is paid to all safety measures and quality control in
coordination with Safety Engineer and QA/QC Engineer and in line with PSP and
PQP.
Construction team.
- The work progress shall be monitored in accordance with the planned work
program and he will provide reports to his superiors.
- The constant coordination with the Safety Engineer to ensure that the works are
carried out in safe working atmosphere.
- The constant coordination with the QA/QC Engineer for any works to be carried
out and initiate for the Inspection for the finished works.
- He will ensure the implementation of any request that might be raised by the
Consultant.
- Efficient daily progress shall be obtained for all the equipment and manpower.
- He will engage in the work and check the same against the daily report received
from the Foremen.
- The passage of all the revised information to the Foremen and ensure that it’s
being carried out properly.
- The monitoring of executions of works at site and should be as per the approved
shop drawings and project specifications.
- Ensure WIRs and MIRs are being raised for activities in timely manner and
inspected by the Consultant.
- Check and insure that all activities / work done / completed prior to offer for
consultant inspection.
- He will follow and carried out all the relevant tests as per project specifications.
- Obtain the required clearance prior to Consultant’s inspections.
- Should acquire any necessary civil works clearances and coordination.
- Coordinate with site construction team.
- One who will assist the Consultant Engineer / Inspector during inspection.
- The carrying-out of work and the proper distribution of all the available
resources in coordination with the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning
with the Site Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the
concerned Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the
same to the Site Engineer immediately.
- Inspection of all the site activities and training personnel in accident prevention
and its proper reporting to the Construction Manager and the Project Manager.
- The site is maintained in a clean and tidy manner.
- Ensure only trained persons shall operate the power tools.
- Ensure all concerned personals shall use PPE and all other items as required.
- Ensure adequate lighting is provided in the working area at night time.
- Ensure high risk elevated areas are provided are barricade, tape, safety nets
and provided with ladders.
- Ensure service area/inspection area openings are provided with barricade, tape,
and safety nets.
- Ensure safe access to site work at all times.
- Responsible for overall Store operations in making sure to store the material
delivery to the site and keep it in suitable area that will keep the material in safe
from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with
QA/QC and concerned Engineer.
6.0 EQUIPMENTS
7.0 PROCEDURE
7.1 Safety
- Ensure only trained / certified persons only shall operate the power tools.
- Ensure that Temporary live cable management plan shall develop and
implemented.
- Necessary PPE to be worn while working in energized to be worn while working
in energized circuits.
- Ensure adequate lighting is provided in the working area at night time and if
inside the building area to be well illuminated.
- Safe lifting and shifting of LV switch gear panels and its related hazards and
PROJECT NAME
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Testing and Commissioning of MDB, SMDB, DB,
MCC & CB Page 8 of 12
recommendation.
B. ELECTRICAL TEST
- Perform electrical test on ACB, MCCB.
- Perform electrical test on various motor starters.
- Ensure that the switchgear for which the testing is completed is clean
thoroughly.
- Open the busbar covers and check if the busbars chambers are free from any
foreign objects such as tools etc. Close the covers.
- Ensure that the settings on the ACB & MCCB Trip units are set as per the
approved protection setting recommendations.
- Keep the Switchgear in such a state that the power can be directly switched on.
8.0 ATTACHMENTS
- Quality Control Procedure
- Inspection and Testing Plan
- Check List
PROJECT NAME
TITLE Ref. No. :
Method Statement For REV. No. 0
Date :
Testing and Commissioning of MDB, SMDB, DB,
MCC & CB Page 11 of 12
- Check List
- Risk Assessment